TABLE OF CONTENT

 

7             land contamination. 7-1

7.1           Introduction. 7-1

7.2           Environmental Legislation, Standards and Criteria. 7-1

7.3           Assessment Methodology. 7-1

7.4           Description of the Environment 7-2

7.5           Identification of Potential Land Contamination Concern. 7-2

7.6           Prediction and Evaluation of Environmental Impacts. 7-7

7.7           Evaluation of Residual Impacts. 7-7

7.8           Environmental Monitoring and Audit Requirements. 7-7

7.9           Conclusion. 7-7

 

List of Tables

 

Table 7.1              Aerial Photographs Reviewed

Table 7.2              Summary of Dangerous Goods License Information

 

List of Figures

 

Figure 7.1

Revised Trunk Road T4 Location Plan and Land Contamination Assessment Area under Previous EIA Study

Figure 7.2

Photographic Records of Site Reconnaissance (Sheet 1 of 4)

Figure 7.3

Photographic Records of Site Reconnaissance (Sheet 2 of 4)

Figure 7.4

Photographic Records of Site Reconnaissance (Sheet 3 of 4)

Figure 7.5

Photographic Records of Site Reconnaissance (Sheet 4 of 4)

Figure 7.6

Photographic Records of Site Reconnaissance (Site depots adjacent to Che Kung Miu Station)

 

List of Appendices

 

Appendix 7.1

Summary of Laboratory Testing Results from Approved EIA Report

Appendix 7.2

Relevant Historical Aerial Photographs

Appendix 7.3

Acquisition of Information from Government Departments

Appendix 7.4

Site Walkover Checklists

 

 

                       


7                      land contamination

7.1                  Introduction

7.1.1.1           This section presents the potential land contamination implications associated with the Project.

7.2                  Environmental Legislation, Standards and Criteria

7.2.1.1           The relevant environmental legislation guidelines and standards on land contamination aspect include the following:

·         Section 3 (Potential Contaminated Land Issues) of Annex 19 “Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

 

·         Guidance Note for Contaminated Land Assessment and Remediation (Guidance Note)

 

The Guidance Note sets out the requirements for proper assessment and management of potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling stations), gas works, power plants, shipyards / boatyards, chemical manufacturing / processing plants, steel mills / metal workshops, car repairing / dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be conducted and analysed and suggests practical remedial measures that can be adopted for the clean-up of contaminated sites.

 

·         Practice Guide for Investigation and Remediation of Contaminated Land (Practice Guide)

 

This guide outlines typical investigation methods and remediation strategies for the range of potential contaminants typically encountered in Hong Kong.

 

·         Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (Guidance Manual)

 

The Guidance Manual introduces the risk-based approach in land contamination assessment and present instructions for comparison of soil and groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern commonly found in Hong Kong.  The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary.

 

7.3                  Assessment Methodology

7.3.1.1           Land contamination assessment was carried out according to the abovementioned EIAO-TM, Guidance Note, Practice Guide and Guidance Manual.

7.3.1.2           A site appraisal, including site walkover and desktop review, was conducted to identify the potentially contaminating activities that may pose adverse impact to the Project.  Site walkover was conducted within the Project Area to review the general site conditions and to identify any sources of land contamination (or ‘hotspots’).  For the desktop review, the following information was reviewed:

·         Aerial photographs and topographic maps held by the Lands Department;

·         Hong Kong Geological Survey Map (Series HGM20) – Sheet No. 7 (1:20,000);

·         Records on dangerous goods, chemical wastes, chemical spillage/leakage and fire incidents from the identified potentially contaminated sites from Environmental Protection Department (EPD) and Fire Services Department (FSD); and

·         Relevant ground investigation (GI) reports from the Civil Engineering and Development Department (CEDD) civil engineering library.

7.3.1.3           If potentially contaminated land use(s) were identified within the Project Area, the potential land contamination impacts arising from the Project would be evaluated and appropriate mitigation measures would be recommended.  If necessary, Contamination Assessment Plan (CAP), Contamination Assessment Report (CAR) and Remediation Action Plan (RAP) would be submitted to EPD for endorsement.  Any contaminated soil and/or groundwater should be treated according to EPD’s approved RAP.  A Remediation Report (RR), demonstrating adequate clean-up, should be submitted to EPD for endorsement prior to the commencement of any development or redevelopment works within the Project Area.

7.4                  Description of the Environment

7.4.1.1           The Project includes the construction of a dual 2-lane trunk road of about 2.6km connecting Shing Mun Tunnel Road and Tsing Sha Highway in the northwest with Sha Tin Road in the southeast.  The location of the Project is shown in Figure 1.1.

7.4.1.2           As shown in the site location plan provided in Figure 1.1, the Project Area is located on a generally flat terrain and is mainly bounded by residential buildings and undeveloped vegetated land to the north, residential / industrial buildings and the Hong Kong Heritage Museum to the south, residential buildings, roads and the Shing Mun River Channel to the east and west.

7.4.1.3           Based on the latest engineering design and as shown in Figure 2.3.1, Figure 2.3.2, Figure 2.3.3 & Figure 2.3.4, the Project would include construction of at-grade roads, depressed roads, underpasses as well as piers of elevated roads where soil excavation would be anticipated. In addition, a section of the proposed elevated road (approximately 30m in length) in the central part of the Project and along Man Lam Road to the north of the Shing Mun River Channel, would be above the Caltex-Tai Wai Petrol Filling Station (refer to Figure 2.3.2).  Based on the latest design, the proposed road works, including the piers, will not encroach into the petrol filling station and the petrol station will be retained under the Project.

7.5                  Identification of Potential Land Contamination Concern

7.5.1              General

7.5.1.1           Site appraisal was carried out in the period from June 2019 to June 2020 with site walkovers conducted in February 2020.  Findings of the site appraisal are summarized below.

7.5.2              Review of Previous EIA Study

7.5.2.1           A comprehensive land contamination assessment was conducted under the approved EIA Report for Trunk Road T4 in Sha Tin (Register No.: AEIAR-084/2005).  The assessment was conducted in accordance with the EIAO-TM as well as EPD’s guidelines[1].  The Dutch Ministry of Housing, Planning and Environmental Soil and Groundwater Standards (1994) (the Dutch Guidelines) were used as the reference criteria for the classification of contaminated materials, with Dutch B level as the cleanup target for soil.

7.5.2.2           The assessment area of the approved EIA Report largely covered the current Project Area (refer to Figure 7.1).  The assessment included desktop study (e.g. review of aerial photographs, survey maps and relevant information from Lands Department, EPD and FSD), site reconnaissance and preliminary site investigation (SI).  The site reconnaissance and preliminary SI works were conducted in September 2003.

7.5.2.3           Based on the approved EIA report, apart from an open car park adjacent to Che Kung Miu Station (Site A) (refer to Figure 7.1), no other potentially contaminated sites were identified in the original alignment.  The preliminary SI works was conducted at Site A in September 2003.  Three boreholes were constructed for the preliminary SI works with a total of 9 soil samples collected.  The collected soil samples were tested by an HOKLAS accredited laboratory for heavy metals (chromium, copper, lead and zinc), total petroleum hydrocarbons, polycyclic aromatic hydrocarbons (PAHs), benzene, toluene, ethylbenzene, xylene (BTEX) and solvents (halogenated and non-halogenated).  Based on the laboratory analytical results, no exceedances in the Dutch B levels for all the tested parameters were found in the collected samples.  The laboratory analytical results are summarised in Appendix 7.1.  For the purpose of this assessment, the relevant RBRGs under the current EPD’s Guidance Manual are also presented in Appendix 7.1. As the future land uses of the Project are roads, cycling tracks, pedestrian walkways and footbridges, the RBRGs of Lower of Industrial or Public Park land use scenario is adopted for this assessment. According to the laboratory analytical results, there is no exceedance of relevant RBRGs in the collected samples.

7.5.2.4           According to the approved EIA report and the laboratory analytical results, no contaminated sites (including Site A) were identified within the assessment area for the original alignment as of Year 2003.

7.5.3              Review of Historical Land Uses

7.5.3.1           A review of aerial photographs in the period after the approval of EIA Report has been undertaken to evaluate the likelihood of potential contamination associated with past land uses within the Project Area.  Findings of the review are summarized in Table 7.1 and the reviewed aerial photographs are provided in Appendix 7.2.               

Table 7.1          Aerial Photographs Reviewed

Year

Reference of Aerial Photos in Appendix 7.2 (Photo Reference Number)

Site Description

1963

AP1, AP2 (#1963_0480)

The Project Area was largely occupied by agricultural land, village houses and vegetation. The Shing Mun River and Tai Po Road were also observed.

1973

AP3 (#03251), AP4 (#03249)

Reclamation was in progress and the Shing Mun River Channel was under modification to the present configuration. The existing Lion Rock Tunnel Road was observed. No significant land use changes were observed in the remaining areas of the Project Area.

1983

AP5 (#51133, #51152);

AP6 (#51152, #51171)

Tai Chung Kiu Temporary Housing Area and Sha Tin Tau Temporary Housing Area (Site A) were observed on both sides of Shing Mun River Channel near Lion Rock Tunnel Road. The existing Tai Po Road was widened and the existing Che Kung Miu Road and Shing Wan Road were observed. The construction site for the existing Sha Tin Road was also observed in the south of the Project Area.

 1993

AP7 (#A34663, #A34684);

AP8 (#A34684, #A34707)

The Tai Chung Kiu Temporary Housing Area was demolished and an open car park was observed. The Shing Mun Tunnel Road and Chung Ling Road were also observed in the northern portion of the Project Area. No significant land use changes were observed in the remaining areas of the Project Area.

2003

AP9 (#CW47503);

AP10 (#CW47592; #CW47611)

The Project Area remained largely occupied by roads, farmland and vegetation. The Temporary Housing Area in Site A was demolished and an open was observed. The existing Caltex-Tai Wai Petrol Filling Station was noted within the central portion of the Project Area.

2013

AP11 (#CS45680; #CS45683);

AP12 (#CS45206; #CS45680)

The existing Tsing Sha Highway was observed in the northern portion of the Project Area.  Site depots were observed adjacent to Che Kung Miu Station (previously open car park in Site A).

No significant land use changes were observed in the remaining areas of the Project Area.

2018

AP13 (#E039205C; #E039208C; #E039211C; #E049616C; #E049619C; #E049623C);

AP14 (#E049623C; #E049627C; #E049631C; #E039205C; #E039199C; #E039196C)

No significant land use changes were observed in the Project Area.

Source of aerial photographs: Survey and Mapping Office, Lands Department

7.5.3.2           Based on the review of aerial photographs, similar to the approved EIA report, the Project Area had been mainly occupied by roads, agricultural land, residential uses, open car park and vegetation. No potential land contamination issues were identified in these areas. A potentially contaminating land use (the Caltex-Tai Wai Petrol Filling Station) was identified within the Project Area.  However, as discussed in Section 7.4.1.3, the proposed road alignment and piers will not encroach into the Caltex-Tai Wai Petrol Filling Station and the petrol filling station will be retained under the Project. Two site depots were observed adjacent to Che Kung Miu station since 2013. Based on findings of the site walkover (refer to Section 7.5.6.4), the site depots had been used as site offices / car park only.

7.5.3.3           Based on the above, no historical potential land contamination issues were identified within the Project Area.

7.5.4              Site Geology

7.5.4.1           The superficial geology of the Project Area generally comprises Quaternary deposits and fill materials. Fill material is likely to be encountered within the urban areas in Shatin. Reclamation fills of various ages will be encountered near the river bank of Shing Mun River.  According to the archival GI records, local marine deposits which mainly comprising thin layer sand materials, are likely to be encountered near Heritage Museum and Shatin Park Area. A large extent of Alluvium is encountered in Shatin valleys and natural drainage lines on the hillsides, extending towards the Tolo Harbour. The deposit generally composes of interbedded clay, silt, sand, gravel, cobbles.  Colluvium, which consists of silt, sand, gravel or cobbles, occurs widely in the valleys or incised streams of the uphill of Shing Mun River and Shek Mun Area.

7.5.4.2           According to the published 1:20,000 Geological Map (Sheet No.7), the dominant rock types likely to be encountered within the Project Area are Jurassic Shatin Granite (Jkt_gc), with some minor Late Jurassic East Lantau Rhyodacite (Jkd_rf) and Needle Hill Granite (Jkn_gf) intrusions on the west of the Tolo Channel fault and generally underlain along Shing Mun Tunnel Road;  and Cretaceous Shui Cheun O Granite (Kcs_gm & Kcs_gc) with dykes of Cretaceous Tei Tong Tsui Quartz Monzonite (Klt_mq) are dominant on the east of the Tolo Channel fault, where situated at the central part of Shing Mun River area and near the hillside of Shatin Road.

7.5.4.3           The Sha Tin Granite (Jkt_gc) comprises a coarse-grained central core surrounded by medium- to fine-grained lithologies. The coarse-grained granite is texturally uniform comprising large crystals of quartz, alkali feldspar and plagioclase forming a subhedral granular texture. Interstitial aggregates of brown biotite are a distinctive feature of the granite and are especially conspicuous in the coarse-grained rocks. Porphyritic fine-grained lithologies are commonly observed close to the boundaries of the pluton. 

7.5.4.4           The Shui Chuen O Granite (Kcs_gm & Kcs_gc) is dominantly porphyritic and fine to medium grained and is commonly weakly deformed. Phenocrysts of perthitic orthoclase and strained quartz are set in a subhedral-granular matrix of strained quartz, weakly zoned plagioclase, and chloritized biotite. 

7.5.5              Information from Government Departments

7.5.5.1           The EPD and FSD were contacted for (i) records of any spillage / leakage of chemicals, (ii) records of Dangerous Goods (DG) and (iii) records of Chemical Waste Producer(s) (CWPs) and (iv) records of reported fire incidents within the Project Area.

7.5.5.2           EPD and FSD’s replies on the request have been received and attached in Appendix 7.3. The information is summarized below. 

                   Environmental Protection Department

7.5.5.3           Based on the reply given by EPD on 28 June 2019, there is no record of spillage / leakage of chemical wastes or chemicals within the Project Area.

7.5.5.4           Further to the EPD’s reply, visit to EPD’s Southorn Centre Office was undertaken on 3 April 2020 to review the available CWP records.  No CWP records were found within the Project Area.

                   Fire Services Department

7.5.5.5           Based on the reply from FSD on 22 July 2019, there are 2 DG license records identified within the Project Area. The records are likely to be associated with the Caltex-Tai Wai Petrol Filling Station situated in the central part of the Project Area (refer to Figure 2.3.2).  Details of the DG licenses are summarized in Table 7.2.  As discussed in Section 7.4.1.3, the Caltex-Tai Wai Petrol Filling Station will be retained under the Project.  Potential land contamination issues associated with the storage of DG in the petrol filling station are therefore not anticipated.

7.5.5.6           Furthermore, based on the reply from FSD, there was a ‘No.1 Alarm Fire’ incident reported at the Transport City Building on 10 March 2017.  As the concerned building is situated 30 m to the southwest of the Project Area (refer to Figure 2.3.2), the incident was not expected to pose any potential land contamination issues to the Project Area.              

Table 7.2          Summary of Dangerous Goods License Information

Location

Type of DG

Quantity

Storage Method

Caltex-Tai Wai Petrol Filling Station

Petrol

45,000 Litres

Underground Tank in Petrol Filling Station

Diesel Oil

45,000 Litres

7.5.6              Site Reconnaissance

7.5.6.1           Site walkover was conducted on 20 and 25 February 2020 to investigate any contaminative issues associated with current land uses and activities within the Project Area.  Findings of the site walkover, including the photographic records and site layout plan, are shown in Figure 7.2, Figure 7.3, Figure 7.4, Figure 7.5 & Figure 7.6.  Site walkover checklists are provided in Appendix 7.4.

7.5.6.2           Based on the site walkover, the Project Area was mainly occupied by non-contaminating land uses including roads, footpaths / cycling tracks, subways, car parks, refuse collection point, playground / sitting-out area, MTR East Rail, the Shing Mun River Channel, open area, agricultural land and vegetation (refer to Figure 7.2, Figure 7.3, Figure 7.4, Figure 7.5 & Appendix 7.4).  No potentially contaminating land uses / activities were observed in these areas.

7.5.6.3           The Caltex-Tai Wai Petrol Filling Station was observed in the central portion of the Project Area (refer to Photo No. 2806 in Figure 7.3) and was inaccessible for detailed site walkover. However, based on peripheral observations, the site was paved with intact concrete in good condition and as discussed in Section 7.4.1.3, the petrol filling station will be retained under the Project.  Potential land contamination issues associated with the operation of the Petrol Filling Station to the Project are therefore not anticipated.

7.5.6.4           There are two site depots located adjacent to Che Kung Miu Station in the central portion of the Project Area. The northern site depot is currently operated by CEDD under Contract No. NE/2017/05 Road Widening and Retrofitting Noise Barriers on Tai Po Road (Sha Tin Section) and the southern site depot is currently operated by the Highways Department (HyD) and China Road & Bridge Corporation (contractors). Based on information provided by the site representatives and site observations, the site depots are used for site offices and car parking only with no vehicle maintenance activities carried out on site. No potentially contaminating activities were identified, and no chemical / oil storage or stressed vegetation were observed within the sites. The concrete paved ground was noted to be in good condition with no oil stains observed.  As reported by the site representatives, there had been no major change in site operations at the two site depots for the last 5 years. Based on the above, potential land contamination issues associated with the operation of the site depots to the Project are not anticipated. Findings of the site walkover, including the photographic records are shown in Figure 7.6. Questionnaires were conducted with available site representatives and the site walkover checklists with site layout plans are provided in Appendix 7.4.

7.6                  Prediction and Evaluation of Environmental Impacts

7.6.1.1           Based on the site appraisal, a potentially contaminated site (i.e. Caltex-Tai Wai Petrol Filling Station) was identified within the Project Area.  No other potentially contaminating land uses / activities were identified within the Project Area. However, as discussed in Section 7.4 above, the proposed road works, including the piers, will not encroach into the petrol filling station and it will be retained under the Project.  Therefore, no land contamination impact associated with the petrol filling station to the Project is anticipated.

7.6.1.2           From the above, no land contamination impact arising from the Project is anticipated and mitigation measures are considered not necessary. No further site investigation (SI) works at the Project Area is required.

7.7                  Evaluation of Residual Impacts

7.7.1.1           As land contamination impacts are not anticipated for the Project, no residual impacts are expected.

7.8                  Environmental Monitoring and Audit Requirements

7.8.1.1           Based on the site appraisal, no land contamination impacts are anticipated for the Project.  No environmental monitoring and audit programme would be required.

7.9                  Conclusion

7.9.1.1           A site appraisal, in the form of desktop review and site walkover, was conducted from June 2019 to June 2020 to identify any current/historical potentially contaminating and uses within the Project Area. 

7.9.1.2           Based on the findings of the site appraisal, no adverse land contamination impact arising from Project is anticipated. No further SI works at the Project Area is required.



[1] Professional Persons Environmental Consultative Committee Practice Note 3/94 – Contaminated Land Assessment and Remediation (ProPECC PN 3/94) and Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repair/Dismantling Workshops.