TABLE
OF CONTENTS
Page
1.2 Project Scope and Implementation Programme
2............. Key
Findings of the environmental impact Assessment
2.4 Waste Management Implication
2.7 Landscape and Visual Impact
2.8 Impact on Cultural Heritage
3............. ENVIRONMENTAL
MONITORING AND AUDIT (EM&A)
LIST OF Tables
Table
1.1 Summary of Possible
Construction Methods for the Revised Trunk Road T4
Table 2.1 Summary of
Environmental Impacts.
LIST OF FIGURES
Figure 1.1 Revised Trunk Road T4 General Layut
Plan (Sheet 1 of 4)
Figure 1.2 Revised Trunk Road T4 General Layut
Plan (Sheet 2 of 4)
Figure 1.3 Revised Trunk Road T4 General Layut
Plan (Sheet 3 of 4)
Figure 1.4 Revised Trunk Road T4 General Layut Plan
(Sheet 4 of 4)
·
Item A.8 - A road or railway
bridge more than 100 m in length between abutments; and
·
Item Q.1 - All projects
including new access roads, railways, sewers, sewage treatment facilities,
earthworks, dredging works and other building works partly or wholly in an
existing country park.
i. Construction of dual two-lane elevated carriageways of approximately
1.4km long connecting Shing Mun Tunnel Road and Tsing Sha Highway to the
proposed at-grade carriageways fronting the Riverpark;
ii. Construction of dual two-lane at-grade carriageways and underpasses of approximately
600m long between the Riverpark and Tsang Tai Uk;
iii. Construction of a slip road of approximately 80m long near the Riverpark
connecting at-grade carriageway northbound and Lion Rock Tunnel Road northbound
across Shing Mun River Channel;
iv. Construction of a slip road of approximately 300m long near Tsang Tai Uk connecting Lion Rock Tunnel Road southbound and Sha Tin
Road eastbound;
v. Widening of a section of Sha Tin Road of approximately 150m long from a dual
two-lane carriageway to a dual four-lane carriageway;
vi. Modification of a section of the elevated carriageway of Shing Mun Tunnel
Road eastbound near Chung Ling Lane of approximately 200m long to provide extra
space for improved merging of traffic;
vii. Modification and realignment of a section of Tung Lo Wan Hill Road, Chung
Ling Road, Chung Ling Lane, Tai Po Road (Tai Wai Section), Shing Chuen Road,
Shing Wan Road, Man Lam Road and Man Lai Road;
viii. Construction of an at-grade and an elevated footpath of approximately 50m
long across the proposed underpass near Sha Tin Tau Village;
ix. Construction of an elevated cycle track and an elevated footpath of
approximately 100m long across Shing Mun River Channel;
x. Demolition of the existing subways across Lion Rock Tunnel Road fronting
the Riverpark and construction of an elevated cycle track and an elevated
footpath with lifts and staircases across Lion Rock Tunnel Road fronting the Riverpark;
xi. Demolition of the existing pedestrian subway across Che Kung Miu Road and Lion Rock Tunnel near MTR Che Kung Temple
Station and construction of an elevated footpath with lifts and staircases across
Che Kung Miu Road;
xii. Ancillary works including geotechnical, drainage, sewerage, water, utilities,
lighting, landscaping, electrical and
mechanical works, construction/reconstruction of noise barriers, retaining
walls, slope improvement, mitigation works for natural terrain hazard near
Shing Mun Tunnel Road and within Lion Rock Country Park and installation of
street furniture and traffic aids; and
xiii. Modification of Existing Noise Barrier/Enclosure at Tsing Sha Highway
(Trunk Road T3).
Widening
of Tai Po Road (Sha Tin)
Improvement
of Lion Rock Tunnel
Revitalisation
of Tai Wai Nullah
Table
1.1 Summary of Possible Construction Methods for
the Revised Trunk Road T4
Section |
Possible
Construction Method |
Selection
Reason |
Viaduct |
Precast Segmental Bridge by Launching Gantry |
|
Depressed
Road / Underpass |
Cut-and-Cover |
|
Table 2.1 Summary of Environmental Impacts.
Sensitive Receivers /
Assessment Points |
Impact Prediction Results
(Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without Mitigation) |
Impact Avoidance Measures /
Mitigation Measures |
Residual Impacts (After
Implementation of Mitigation Measures) |
|
Air Quality Impact |
||||||
Construction Impact |
||||||
Representative existing
residential, commercial developments and government uses within 500m from the
boundary of the Project Site |
RSP ·
10th highest 24-hr average conc: 69 – 99 μg/m3 ·
Annual average: 31 – 50 μg/m3 FSP ·
10th highest 24-hr average conc: 52 – 57 μg/m3 ·
Annual average: 22 – 26 μg/m3 TSP ·
1st highest hourly average conc: 186 – 376 μg/m3 |
RSP ·
24-hr average conc.: 100 μg/m3 (Number of exceedances
allowed: 9) ·
Annual average conc.: 50 μg/m3 FSP ·
24-hr average conc.: 75 μg/m3 (Number of exceedances
allowed: 9) ·
Annual average conc.: 35 μg/m3 TSP ·
1st highest hourly average conc : 500 μg/m3 |
N/A |
The approved non-road mobile machinery (NRMMs) under NRMM Regulation
(excluding exempted NRMMs) would be used on site and NRMMs supplied with
mains electricity instead of diesel-powered should be adopted as far as
possible to minimize the potential emission from NRMMs. Dust suppression measures and good site practices ·
Skip hoist for material transport should be totally enclosed by
impervious sheeting. ·
All dusty materials should be sprayed with water prior to any loading,
unloading or transfer operation so as to maintain the dusty materials wet. ·
All stockpiles of aggregate or spoil should be covered and/or water
applied. ·
The height from which excavated materials are dropped should be
controlled to a minimum practical height to limit fugitive dust generation
from unloading. ·
Every vehicle should be washed to remove any dusty materials from its
body and wheels before leaving the construction sites. ·
The load of dusty materials carried by a vehicle leaving a
construction site should be covered entirely by clean impervious sheeting to
ensure dust materials do not leak from the vehicle. ·
Erection of hoarding of not less than 2.4m high from ground level
along the site boundary which adjoins a road, street, service lane or other
area accessible to the public. |
No adverse residual
impacts anticipated |
|
Operation Impact |
||||||
Existing and planned
residential, commercial developments and government uses within 500m from the
boundary of the Project Site |
NO2 ·
19th highest 1-hr average conc.: 92 – 145 μg/m3 ·
Annual average conc.: 13 – 37 μg/m3 RSP ·
10th highest 24-hr average conc: 69 – 72 μg/m3 ·
Annual average: 31 – 33 μg/m3 FSP ·
10th highest 24-hr average conc: 52 – 54 μg/m3 ·
Annual average: 22 – 24 μg/m3 |
NO2 ·
1-hr average conc.: 200 μg/m3 (Number of exceedances
allowed: 18) ·
Annual average conc.: 40 μg/m3 RSP ·
24-hr average conc.: 100 μg/m3 (Number of exceedances
allowed: 9) ·
Annual average conc.: 50 μg/m3 FSP ·
24-hr average conc.: 75 μg/m3 (Number of exceedances
allowed: 9) ·
Annual average conc.: 35 μg/m3 |
N/A |
No adverse air quality
impact is anticipated during the operation phase of the Project, thus
mitigation measure is deemed not necessary. |
No adverse residual
impacts anticipated |
|
Noise Impact |
||||||
Construction Impact |
||||||
Representative existing
noise sensitive developments (e.g. residential) within 300m from the boundary
of the Project Site |
·
58 – 99 dB(A) |
·
Annexes 5 and 13 of the EIAO-TM ·
Leq(30 min) 75dB(A) at 1m from the façade of residential
dwellings ·
Leq(30 min) 70dB(A) at 1m from the façade of educational
institutions which rely on openable window for ventilation (Leq(30 min)
65dB(A) during examinations). |
·
0 – 24 dB(A) |
- Quality PME prescribed in EPD’s
Quality Powered Mechanical Equipment (QPME) database. - Temporary movable noise barriers,
full enclosure for PME. - Good site practices ·
Only well-maintained plant should be operated on site and plant should
be serviced regularly. ·
Silencers or mufflers on construction plant should be utilized and
should be properly maintained. ·
Mobile plant should be sited as far away from sensitive uses as
possible. ·
Machines and plant that may be in intermittent use should be shut down
between works periods or should be throttled down to a minimum. ·
Plant known to emit noise strongly in one direction should, where
possible, be orientated so that noise is directed away from the nearby
sensitive uses. ·
Material stockpiles and other structures should be effectively utilized
to screen noise from on-site construction activities. |
·
No adverse residual impacts anticipated |
|
Operation Impact |
||||||
Representative existing and planned residential
developments, educational institutions, clinic, etc. within 300m from the boundary
of the Project Site |
·
Predicted overall noise levels: 45 – 82 dB(A) ·
Predicted noise levels of the Project roads: 0 – 80 dB(A) ·
Contribution from Project roads: 0 – 34 dB(A) |
·
Annexes 5 and 13 of the EIAO-TM ·
L10(1 hour) 70dB(A) at 1m from the façade of residential
dwellings · 65 dB(A) at 1 m from the external façades of schools, places of public worship, courts of law, places where unaided voice communication is required ·
55 dB(A) at 1 m from the external
façades of hospital and clinics. |
·
Exceedance of the noise criteria by up to 17 dB(A) ·
The exceedances are dominantly contributed by the existing roads at
some Representative NSRs, while at some other Representative NSRs, the
exceedances are dominantly contributed by Project Roads |
·
Low Noise Road Surfacing -
Approx 180m at proposed slip road SR1-1
(LNRS1). -
Approx 210m at proposed T4 (westbound) slip road (LNRS2). ·
Proposed Noise Barriers and
Enclosures -
Approx 60m of 2m High Vertical Noise
Barrier (N1). -
Approx 130m of 5m High Vertical Noise
Barrier (N2). -
Approx 100m of 5.5m High with 1.5m
Cantilever (at 45 degrees) Barrier (N3). -
Approx 50m of 2.7m High with 3.7m
Cantilever (at 20 degrees) Barrier (N4). -
Approx 170m Semi-enclosure (SE1). -
Approx 390m Full-enclosure (FE1). |
·
No adverse residual impacts anticipated |
|
Water Quality Impact |
||||||
Construction Impact |
||||||
Representative WSRs
within 500m from the boundary of the Project Site, including Shing Mun Main
River Channel, Lion Rock Country Park, natural streams running from Hillside
to Shing Mun River catchment and concrete channel near Sha Tin Tau Village
and Shui Chuen O Estate. |
The potential sources
of water quality impact associated with the construction works include: ·
Construction works at Shing Mun Main River Channel; ·
Wastewater from general construction activities; ·
Construction site run-off; ·
Construction works in close proximity to inland water; ·
Sewage from construction workforce; ·
Accidental spillage of chemicals; and ·
Diversion of Sha Tin Tau Nullah. |
·
Annexes 6 and 14 of the EIAO-TM ·
Water Quality Objectives for the Tolo Harbour and Channel Water
Control Zone (WCZ) ·
Technical Memorandum on Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) ·
Practical Note for Professional Persons (ProPECC) PN 1/94 ·
Environmental, Transport and Works Bureau (ETWB) Technical Circular
(Works) No. 5/2005 ·
Hong Kong Planning Standards and Guidelines (HKPSG) Chapter 9
(Environment) |
·
N/A |
·
Mitigation measures and good site practices in ProPECCPN 1/94 “Construction
Site Drainage” ·
Guidelines in DSD Technical Circular No. 14/200 “Temporary Flow
Diversions and Temporary Works Affecting Capacity in Stormwater System” ·
Practices in ETWB TC (Works) No. 5/2005 “Protection of natural
streams / rivers from adverse impacts arising from construction works” ·
Waste Disposal
Regulation ·
Provision of interim treatment facilities, such as chemical toilets,
for construction workforce |
·
No adverse residual impacts anticipated |
|
Operation Impact |
||||||
Representative WSRs
within 500m from the boundary of the Project Site, including Shing Mun Main
River Channel, Lion Rock Country Park, natural streams running from Hillside
to Shing Mun River catchment and concrete channel near Sha Tin Tau Village
and Shui Chuen O Estate. |
Potential water quality
impacts associated with the operation phase include: ·
Non-point source surface run-off from new impervious areas; and ·
Hydrodynamic and water quality impact on Shing Mun River |
·
Annexes 6 and 14 of the EIAO-TM ·
Water Quality Objectives for the Victoria Harbour (Phase Two) WCZ ·
Technical Memorandum on Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) ·
ProPECC PN 5/93 |
·
N/A |
·
Adequate design in silt trap for the new road drainage which take into
account the guidelines in ProPECC PN 5/93. ·
Best Storm Water Management Practices and Storm Water Pollution
Control Plan to reduce non-point source pollution. |
·
No adverse residual impacts anticipated |
|
Waste Management Implication |
||||||
Construction Impact |
||||||
C&D materials, excavated
sediments, chemical wastes and general refuse |
·
Around 23,850 m3 of non-inert C&D materials and 299,614
m3 of inert C&D materials will be generated from demolition of
the existing carriageways, site clearance/set-up/plant mobilization,
underground utilities protection and diversion works, piling works, pile
cap/pier/abutment construction, falsework/deck construction, and drainage and
pavement construction. ·
Around 800 m3 of excavated marine-based sediment will be
generated from construction of piled foundation for the viaduct section
across the Shing Mun River Channel. ·
Small quantity of chemical wastes in the order of a few cubic meters
per month. ·
Around 163 kg per day of general refuse will be generated from
construction works and on-site staff and workers. |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Charges for Disposal of Construction Waste) Regulation
(Cap. 354N) ·
Land (Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public Health and Municipal Services Ordinance – Public Cleansing and
Prevention of Nuisances Regulation (Cap. 132BK) ·
Dumping at Sea Ordinance (Cap. 466) |
·
N/A |
·
Implementation of good site practices, waste reduction measures and
proper storage, collection and transport of waste. ·
The excavated sediment will be treated and reused on site. |
·
No adverse residual impact anticipated |
|
Operation Impact |
||||||
N/A |
·
It is expected that no waste will be generated during the operation
phase of the Project. |
·
N/A |
·
N/A |
·
No mitigation measures to be provided as the Project would not cause
adverse impacts. |
·
No adverse residual impact anticipated |
|
Land Contamination |
||||||
Onsite construction
workers and future occupants |
·
Adverse land contamination impact arising from the Project is not
anticipated |
·
Annex 19 of the EIAO-TM ·
Guidance Note for Contaminated Land Assessment and Remediation (EPD,
2007) ·
Practice Guide for Investigation and Remediation of Contaminated Land
(EPD, 2011) ·
Guidance Manual for Use of Risk-based Remediation Goals for
Contaminated Land Management (EPD, 2007) |
·
N/A |
·
As adverse land contamination impact arising from the Project is not
anticipated, no mitigation measures were considered necessary. |
·
No adverse residual impact anticipated |
|
Ecology (Terrestrial) |
||||||
Natural/Semi-natural
habitats including woodland, mixed woodland, plantation and the associated
wildlife (including species of conservation importance) Ardeid night roost site
between HKHM and Man Lai Court |
·
Permanent loss of approximately 2.8 ha
natural/semi-natural habitat ·
Very small area of woodland (13 m2)
and mixed woodland (153 m2) within LRCP would be permanently
affected ·
Potential direct injury/mortality to
wildlife and bird collision ·
Disturbance impact on bird flight path
(including ardeids) ·
Indirect disturbance impact (e.g. dust,
noise, glare, site runoff, groundwater infiltration) on ardeid night roost,
natural/semi-natural habitats and associated wildlife in the vicinity |
·
Annexes 8 and 16 of
the EIAO-TM ·
EIAO Guidance Notes No. 7/2010 and No. 10/2010 |
·
N/A |
·
Avoidance of direct
impact to ardeid night roost site between HKHM
and Man Lai Court ·
Avoidance of direct
impact to recognized sites of conservation importance as far as possible ·
Minimization of
direct impact to LRCP by proposing the flexible barrier at the fringe of LRCP
closest to Sha Tin Road as far as possible ·
Carefully design the
construction works to preserve the directly impacted flora species of
conservation importance in-situ as far as possible. If direct impact is
unavoidable, transplant the flora species of conservation importance, where
possible, according to Plant Preservation and Transplantation Proposal ·
Implementation of good site practices (e.g. provision of screening,
direct lighting away from the night roosting site and LRCP, etc.) ·
Restriction hours of construction works approximately 100 m from the
nearest ardeid night roost site |
·
No adverse residual impact anticipated |
|
Operation Phase |
||||||
Natural/Semi-natural
habitats including mixed woodland, plantation and the associated wildlife
(including species of conservation importance) Ardeid night roost site
between HKHM and Man Lai Court |
·
Potential direct mortality to wildlife
(e.g. road kill) and bird collision ·
Disturbance impact on bird flight path (including ardeids) ·
Disturbance impacts
(e.g. dust, noise, glare) on ardeid night roost, natural/semi-natural habitats and the associated wildlife (including species of
conservation importance) in the vicinity of Project site |
·
Same
as construction phase |
·
N/A |
·
Implementation of
good site practices and mitigation measures (e.g. planting of peripheral
screening plants/vertical green, control of glare / lighting) measures ·
Carefully
design the noise barrier (e.g. location, use of tinted materials and
superimposing dark patterns or strips on the noise barrier) |
·
No adverse residual impact anticipated |
|
Landscape and Visual Impacts |
||||||
Construction Impact |
||||||
Landscape Resources (LRs) |
·
Substantial landscape impact on Tree and Shrub Planting in Village
Areas Near Tsang Tai Uk, Sha Tin Tau Village Sitting-Out Area, Landscape
Areas in Urban Development Area near Lion Rock Tunnel Road, Agricultural Land
Near Sha Tin Tau Village, Plantation on Engineered Slopes and Tree and Shrub
Planting in Roadside Areas. ·
Moderate landscape impact on Woodland and Mixed Woodland near Needle Hill and Sha Tin Road, Tree
and Shrub Planting in Village Areas near Lai Chi Yuen and Shing Mun River
Promenade. ·
Slight landscape impact on Waterbodies in Shing Mun River Channel and
Modified Watercourse in Sha Tin Tau. ·
No discernible change in other LRs identified within the study
boundary of the Project |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 |
·
N/A |
·
Preservation of
Existing Vegetation ·
Preservation of Old
and Valuable Trees (OVTs) ·
Transplanting of
Affected Trees ·
Control of Night-time
Lighting Glare ·
Erection of
Decorative Screen Hoarding ·
Management of
Construction Activities and Facilities ·
Reinstatement of Temporarily
Disturbed Landscape Areas ·
Reinstatement of
Affected Watercourses |
·
Moderate
landscape impact on Tree and Shrub Planting in Village Areas Near Tsang Tai Uk, Sha Tin Tau Village Sitting-Out Area, Landscape Areas
in Urban Development Area near Lion Rock Tunnel Road, Agricultural Land Near
Sha Tin Tau Village, Plantation on Engineered Slopes , Tree and Shrub
Planting in Roadside Areas, Woodland
and Mixed Woodland near Needle Hill and Sha Tin Road, Tree and Shrub Planting
in Village Areas near Lai Chi Yuen and Shing Mun River Promenade. ·
Slight landscape impact on Waterbodies in Shing Mun River Channel and
Modified Watercourse in Sha Tin Tau. |
|
Landscape Character
Areas (LCAs) |
·
Substantial landscape impact on Sha Tin Tau Residential Urban LCA. ·
Moderate landscape impact on Sha Tin Upland and Hillside LCA, Tai Wai Miscellaneous Urban Fringe
LCA and Tai Wai Residential Urban Fringe LCA. ·
Slight landscape impact on Sha Tin Miscellaneous Urban Fringe LCA, Tai
Wai Residential Urban LCA, Tai Wai Urban Peripheral Village LCA, Tai Wai
Transportation Corridor LCA and Sha Tin Road Transportation Corridor LCA. ·
No discernible change in other LCAs identified within the study
boundary of the Project |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 |
·
N/A |
·
Preservation of
Existing Vegetation ·
Preservation of Old
and Valuable Trees (OVTs) ·
Transplanting of
Affected Trees ·
Control of Night-time
Lighting Glare ·
Erection of
Decorative Screen Hoarding ·
Management of
Construction Activities and Facilities ·
Reinstatement of
Temporarily Disturbed Landscape Areas ·
Reinstatement of
Affected Watercourses |
·
Moderate landscape impact on Sha Tin Tau Residential Urban LCA, Sha Tin Upland and Hillside LCA, Tai Wai Miscellaneous Urban Fringe
LCA and Tai Wai Residential Urban Fringe LCA. ·
Slight landscape impact on Sha Tin Miscellaneous Urban Fringe LCA, Tai
Wai Residential Urban LCA, Tai Wai Urban Peripheral Village LCA, Tai Wai Transportation
Corridor LCA and Sha Tin Road Transportation Corridor LCA. |
|
Visually Sensitive
Receivers (VSRs) |
·
Substantial visual impact on where the proposal would cause significant deterioration or
improvement in existing visual quality (R-05, R-06, I-07). ·
Moderate visual impact on immediately adjacent VSRs who have full
overview of the project that cause a noticeable deterioration or improvement
in existing visual quality (R-03, R-04, I-03, I-04, I-06, O-01, O-3, O-04,
O-05, T-01, T-02, T-03, T-04, T-05, T-06). ·
Slight visual impact on VSRs further away that cause a barely
perceptible deterioration or improvement in existing visual quality (R-01,
I-01, I-05, W-01). ·
Insubstantial visual impact on long distant VSRs with no discernible
change in the existing visual quality (R-02, I-02, I-08, O-02). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 ·
|
·
N/A |
·
Preservation of
Existing Vegetation ·
Transplanting of
Affected Trees ·
Control
of Night-time Lighting Glare ·
Erection
of Decorative Screen Hoarding ·
Management
of Construction Activities and Facilities ·
Reinstatement
of Temporarily Disturbed Landscape Areas ·
Reinstatement
of Affected Watercourses |
·
Moderate residual impact on where the proposal would cause significant
deterioration or improvement in existing visual quality and immediately
adjacent VSRs who have full overview of the project that cause a noticeable
deterioration or improvement in existing visual quality (R-05, R-06, I-07,
R-03, R-04, I-03, I-04, I-06, O-01, O-3, O-04, O-05). ·
Slight visual impact on VSRs further away that cause a barely
perceptible deterioration or improvement in existing visual quality (R-01,
I-01, I-05, T-01, T-02, T-03, T-04, T-05, T-06, W-01). ·
Insubstantial visual visual impact on long distant VSRs with no
discernible change in the existing visual quality (R-02, I-02, I-08, O-02). |
|
Operation Impact |
||||||
Landscape Resources (LRs) |
·
Substantial landscape impact on Tree and Shrub Planting in Village
Areas Near Tsang Tai Uk, Landscape Areas in Urban Development Area near Lion
Rock Tunnel Road, Agricultural Land Near Sha Tin Tau Village, Plantation on
Engineered Slopes and Tree and Shrub Planting in Roadside Areas. ·
Moderate landscape impact on Woodland and Mixed Woodland near Needle Hill and Sha Tin Road, Tree
and Shrub Planting in Village Areas near Lai Chi Yuen, Sha Tin Tau Village
Sitting-Out Area and Shing Mun River Promenade. ·
Slight landscape impact on Waterbodies in Shing Mun River Channel and
Modified Watercourse in Sha Tin Tau. ·
No discernible change in other LRs identified within the study
boundary of the Project |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory
Planting for Loss of Existing Trees ·
Landscape
Treatment on Slopes ·
Provision of Screen
Planting ·
Maximization of
Roadside Planting ·
Re-provision of
Affected Open Space ·
Visually pleasing
aesthetic treatment on noise barriers and noise enclosures ·
Aesthetically pleasing
design for footbridges, pedestrian subways, cycle paths, carriageways
and other highways structures |
·
Slight residual impact during day 1 of operation and insubstantial
residual impact during year 10 of operation on all affected landscape resources. |
|
Landscape Character
Areas (LCAs) |
·
Substantial landscape impact on Sha Tin Tau Residential Urban LCA. ·
Moderate landscape impact on Sha Tin Upland and Hillside LCA, Tai Wai Miscellaneous Urban Fringe
LCA and Tai Wai Residential Urban Fringe LCA. ·
Slight landscape impact on Sha Tin Miscellaneous Urban Fringe LCA, Tai
Wai Residential Urban LCA, Tai Wai Urban Peripheral Village LCA, Tai Wai
Transportation Corridor LCA and Sha Tin Road Transportation Corridor LCA. ·
No discernible change in other LCAs identified within the study
boundary of the Project |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory
Planting for Loss of Existing Trees ·
Landscape
Treatment on Slopes ·
Provision of Screen
Planting ·
Maximization of
Roadside Planting ·
Re-provision of
Affected Open Space ·
Visually pleasing
aesthetic treatment on noise barriers and noise enclosures ·
Aesthetically
pleasing design for footbridges, pedestrian subways, cycle paths, carriageways and other highways structures |
·
Slight residual impact during day 1 of operation and insubstantial
residual impact during year 10 of operation on all affected landscape
character areas. |
|
Visually Sensitive
Receivers (VSRs) |
·
Substantial visual impact on where the proposal would cause significant deterioration or
improvement in existing visual quality (R-05, I-07). ·
Moderate visual impact on immediately adjacent VSRs who have full
overview of the project that cause a noticeable deterioration or improvement in
existing visual quality (R-03, R-04, R-06, I-03, I-04, I-06, O-01, O-3, O-04,
O-05). ·
Slight visual impact on VSRs further away that cause a barely
perceptible deterioration or improvement in existing visual quality (R-01,
I-01, I-05, T-01, T-03, T-06, W-01). ·
Insubstantial visual visual impact on long distant VSRs with no
discernible change in the existing visual quality (R-02, I-02, I-08, O-02,
T-02, T-04, T-05). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Assessment Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory
Planting for Loss of Existing Trees ·
Landscape
Treatment on Slopes ·
Provision
of Screen Planting ·
Maximization
of Roadside Planting ·
Re-provision
of Affected Open Space ·
Visually
pleasing aesthetic treatment on noise barriers and noise enclosures ·
Aesthetically
pleasing design for footbridges, pedestrian subways, cycle paths, carriageways and other highways structures |
·
Slight residual impact during day 1 of operation and insubstantial
residual impact during year 10 of operation on most of the affected visually
sensitive receivers (R-01, R-04, R-06, I-01, I-05, I-06, I-07, O-03, O-04,
O-05, T-01, T-03, W-01). ·
Slight residual impact during day 1 of operation and remain slight
residual impact during year 10 of operation on serval affected visually
sensitive receivers (R-03, R-05, I-03, I-04, O-01, T-06) |
|
Impact on Cultural Heritage |
||||||
Construction Impact |
||||||
Cultural heritage resources |
·
Potential direct impacts on Gatehouse of Pok Ngar Villa, Tsang Tai Uk,
Li Cottage, Ng Yuen, OLD26, due to damages through contacting with heavy
construction machineries and site negligence ·
Indirect impacts of ground-borne vibration, tilting and settlement on
Gatehouse of Pok Ngar Villa, Tsang Tai Uk, Li Cottage, Ng Yuen, Lau Ancestral
Hall, High Rock Christian Camp, No. 1, 2 and 3 First Street, Tai Wai, OLD1,
OLD9, OLD11-21, OLD26-28 |
·
Annexes 10 and 19 of the EIAO-TM ·
Guidelines for Cultural Heritage Impact Assessment |
·
N/A |
·
Conduct pre and post condition survey for Tsang Tai Uk, Gatehouse of
Pok Ngar Villa, Li Cottage and Ng Yuen ·
Implement monitoring of vibration, settlement and tilting incorporated
with a set of Alert, Alarm and Action system for Tsang Tai Uk, Gatehouse of
Pok Ngar Villa, Li Cottage, Lau Ancestral Hall, Ng Yuen, High Rock Christian
Camp, No. 1, 2 and 3 First Street, OLD1, OLD9, OLD11-21, OLD26-28 ·
Verify foundation information of the historic buildings and provide
sufficient lateral support and de-watering if necessary ·
Set up physical barriers for Li Cottage, Ng Yuen, OLD26, and buffer zones
with physical barriers for Tsang Tai Uk, Gatehouse of Pok Ngar Villa, OLD26 ·
Provide protective covering of plastic sheets for Tsang Tai Uk,
Gatehouse of Pok Ngar Villa, Li Cottage and Ng Yuen ·
As a precautionary measure, AMO should be informed immediately in case
of discovery of antiquities or supposed antiquities in the course of works,
so that appropriate mitigation measures, if needed, can be timely formulated
and implemented in agreement with AMO. |
·
N/A |
|
Operation Impact |
||||||
Cultural heritage resources |
·
No impact would be anticipated during the operation phase. |
·
Annexes 10 and 19 of the EIAO-TM ·
Guidelines for Cultural Heritage Impact Assessment |
·
N/A |
·
No mitigation measure would be required. |
·
N/A |
|