SMEC INTERNAL REF. 7076457 D01
EIA Report Volume IV: EM&A Manual
Mai Po Nature Reserve Infrastructure
Upgrade Project
Revision 7.3 Final
Prepared for World Wide Fund For Nature Hong Kong
20 October 2021
Contents
i
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Contents
1 INTRODUCTION 1-1
1.1 Project Background ................................................................................................................... 1-1
1.2 Project Description .................................................................................................................... 1-1
1.3 Purpose of the Manual .............................................................................................................. 1-2
1.4 Project Organisation .................................................................................................................. 1-2
1.5 Project Programme .................................................................................................................... 1-5
2 AIR QUALITY 2-1
2.1 Introduction ............................................................................................................................... 2-1
2.2 Mitigation Measures.................................................................................................................. 2-1
2.3 Audit Requirements ................................................................................................................... 2-1
3 NOISE 3-1
3.1 Introduction ............................................................................................................................... 3-1
3.2 Mitigation Measures.................................................................................................................. 3-1
3.3 Audit Requirements ................................................................................................................... 3-1
4 WATER QUALITY 4-1
4.1 Introduction ............................................................................................................................... 4-1
4.2 Monitoring ................................................................................................................................. 4-1
4.3 Mitigation Measures.................................................................................................................. 4-3
4.4 Audit Requirements ................................................................................................................... 4-4
5 WASTE MANAGEMENT 5-1
5.1 Introduction ............................................................................................................................... 5-1
5.2 Mitigation Measures.................................................................................................................. 5-1
5.3 Audit Requirements ................................................................................................................... 5-1
6 ECOLOGY 6-1
6.1 Introduction ............................................................................................................................... 6-1
6.2 Mitigation Measures.................................................................................................................. 6-1
6.3 Monitoring and Audit Requirements ......................................................................................... 6-1
7 FISHERIES 7-1
7.1 Introduction ............................................................................................................................... 7-1
7.2 Mitigation Measures.................................................................................................................. 7-1
7.3 Monitoring and Audit Requirements ......................................................................................... 7-1
8 LANDSCAPE AND VISUAL 8-1
8.1 Introduction ............................................................................................................................... 8-1
8.2 Mitigation Measures.................................................................................................................. 8-1
8.3 Monitoring and Audit Requirements ......................................................................................... 8-1
9 INSPECTION/AUDIT 9-1
9.1 Site Inspection/Audit Requirements ......................................................................................... 9-1
9.2 Compliance with Legal and Contractual Requirements ............................................................ 9-1
9.3 Environmental Complaints ........................................................................................................ 9-2
10 REPORTING 10-1
10.1 Baseline Monitoring Report .................................................................................................... 10-1
10.2 Monthly EM&A Reports ........................................................................................................... 10-1
10.3 Final Summary EM&A Report .................................................................................................. 10-3
10.4 Letters Documenting Post-planting Landscape Inspections.................................................... 10-4
10.5 Data Keeping ............................................................................................................................ 10-4
10.6 Interim Notifications of Environmental Quality Limit Exceedances ........................................ 10-4
Contents
ii
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Appendices
Appendix A Implementation Schedule for the Project
Appendix B Sample Template for Interim Notification
Figures
Figure 1-1 Statutory Plan Showing Location of Project and its Environs
Figure 1-2 Project Elements (Indicative Plan Only)
Figure 1-3 EM&A Organisation
Figure 1-4 Project Programme
Figure 4-1 Locations for Water Quality Monitoring
Introduction
1-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
1 INTRODUCTION
1.1 Project Background
1.1.1 Since 1983, the World Wide Fund for Nature Hong Kong (WWF) has been managing 211.7ha of
the 372.1ha Mai Po Nature Reserve (MPNR). Classified as a Biodiversity Management Zone
under the Mai Po Inner Deep Bay Ramsar Site Management Plan, MPNR offers benefits to
wildlife and the local community through education, recreation and conservation initiatives.
1.1.2 Development of MPNR commenced in the 1980s with the setting-up of nature reserve and
associated infrastructure, including the Mai Po Education Centre and the launch of schools
programmes. From 1990 to 2000, MPNR further developed its management, education and
training programmes at the adjacent Peter Scott Field Studies Centre (PSFSC).
1.1.3 Public visits to MPNR began in 1985. By the early 1990s, visitor numbers were in excess of
35,000 per year, hitting a peak of over 45,000 in 2002, and stabilizing at around 40,000 per year
for the remainder of that decade. Due to the commencement of operations at Hong Kong
Wetland Park, the number of visitors to MPNR dropped to 24,000 per year. The Project
Proponent targets a return to visitor numbers, anticipated at 32,000 per year by 2023.
1.1.4 The aim of the Project is to provide a unique experience in educational recreation, groom local
scientists and contribute to a greater understanding of the unique Mai Po environment through
cutting-edge research in ecology. It is crucial to transform MPNR into a 21st Century Nature
Classroom in order to facilitate this unique learning experience and effectively manage this
important, world-class living ecosystem.
1.1.5 The Project Site and its environs are shown on Figure 1-1.
1.2 Project Description
1.2.1 Within the Project Site, the Mai Po Nature Reserve Infrastructure Upgrade Project will comprise
the following components, which are shown on Figure 1-2:
1. Construction of New Tower Hide 2 (TH2). This is a new three-storey tower hide on the bund
between Gei Wai No. 19/20, with a footprint of 60m
2
and a Gross Floor Area (GFA) of 145m
2
.
TH2 will be used primarily by more serious bird watchers. Components for TH2 will be
prefabricated off-site and assembled on-site without the need for on-site concrete mixing.
The work will also involve constructing a path leading towards the hide from bund #18/19. A
new boardwalk will be constructed on existing bunds and will be around 156m long and
1.65m wide, connecting to an existing concrete footpath between gei wai nos. 18 and 19.
2. Construction of New Tower Hide 3 (TH3). This is a new three-storey tower hide on the bund
between Gei Wai No. 7/8, east of the Existing Tower Hide 1 (TH1), with a footprint of 60m
2
and
a GFA of 145m
2
(same design as TH2). TH3 will cater for groups of casual visitors and school
groups on short trips. Components for TH3 will be pre-fabricated off-site and assembled on-site
without the need for on-site concrete mixing. The work will also involve constructing an access
path leading towards the hide from bund #9. A new boardwalk will be constructed on the bund
between gei wai nos. 7 and 9 and will be around 85m long and 1.65m wide, connecting to the
main boardwalk.
3. Construction of New Boardwalks. There are two existing narrow concrete footpaths that
due to age are in a poor state of repair cracked and in some places subsiding, which make
access challenging for some visitors. To allow universal access for all visitors, these footpaths
will be widened.
a. Construction of New Boardwalks Above Existing Paths:
i. The main concrete footpath, running between the MPNR entrance and the Mai
Po Education Centre (MPEC) is around 1.5m wide and about 921m long. The new
boardwalk will be up to 1.65m wide and, space permitting, there will also be a
number of passing bays.
Introduction
1-2
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
ii. The footpath to TH1 is around 1.5m wide and about 66m long. The new
boardwalk will be will be 1.65m wide.
b. Construction of New Boardwalks for Education Areas (EAs):
i. The boardwalk replacing the main footpath will be further widened at six locations
into EAs that provide seating and informative signboards to provide opportunities
for interactive public education. The boardwalks forming these EAs range from
1.4m to 10m in length and range from 1.0m to 3.5m in width (in addition to the
1.65m boardwalk replacing the main footpath).
1.3 Purpose of the Manual
1.3.1 The purpose of this EM&A Manual (hereinafter refer to as the “Manual”) is to guide the setup of
an EM&A programme to ensure compliance with the recommendations in the EIA study to assess
the effectiveness of the recommended mitigation measures and to identify any further need for
additional mitigation measures or remedial action. This Manual outlines the monitoring and audit
programme for the construction phase of the Project (monitoring and audit programme for the
operation phase of the Project is not required).
1.3.2 The Manual provides specific information, guidance and instruction to personnel in charged with
environmental responsibilities and undertaking environmental monitoring and auditing works
for the Project. It also provides systematic procedures for monitoring, auditing and minimizing
environmental impacts associated with the construction activities.
1.3.3 This Manual contains the following information:
EM&A organisation.
Responsibilities of the Employer’s Representative (ER), the Contractor, the Environmental
Team (ET) and the Independent Environmental Checker (IEC) with respect to the
environmental monitoring and audit requirements.
The basis for, and description of the broad approach underlying the EM&A programme.
Requirements with respect to the construction programme schedule and the necessary
environmental monitoring and audit programme to track the varying environmental impacts.
Details of the methodologies to be adopted, including all field laboratories and analytical
procedures, and details on quality assurance and quality control programme.
Definition of Action and Limit levels.
Establishment of Event and Action plans.
Requirements for reviewing pollution sources and working procedures required in the event of
non-compliance with the environmental criteria and complaints.
Requirements for presentation of environmental monitoring and audit data and appropriate
reporting procedures.
Requirements for review of EIA predictions and the effectiveness of the mitigation
measures/environmental management systems and the EM&A programme.
1.3.4 This Manual is a living document which shall be reviewed periodically and updated if necessary
during the course of implementing the Project.
1.4 Project Organisation
1.4.1 Involvement of relevant parties in a collaborative and interactive manner is essential for the
implementation of the recommended EM&A programme. The following sections outline the
primary responsibilities and duties of the key EM&A programme participants.
1.4.2 The proposed project organisation and lines of communication with respect to EM&A works are
shown in Figure 1-3.
Introduction
1-3
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Employer’s Representative (ER)
1.4.3 The ER shall appoint an appropriate individual, who shall:
Monitor the Contractor’s compliance with the contract specifications, including the EM&A
programme, and the effective implementation and operation of environmental mitigation
measures in a timely manner.
Ensure that impact monitoring is conducted at the correct locations at the correct frequency
as identified in the Manual.
Instruct the Contractor to follow the agreed protocols or those in the Contract in the event of
exceedances or complaints.
Review the programme of works with a view to identifying any potential environmental
impacts before they arise.
Check that mitigation measures that have been recommended in the EIA Report, this Manual
and contract documents, or as required, are correctly implemented in a timely manner, when
necessary.
Verify the environmental acceptability of permanent and temporary works, relevant design
plans and submissions.
Comply with the agreed Event Contingency Plan in the event of any exceedance.
The Contractor
1.4.4 The Contractor shall report to the ER. The duties and responsibilities of the Contractor are:
Work within the scope of the construction contract and other tender conditions with respect
to environmental requirements.
Operate and strictly adhere to the guidelines and requirements in this EM&A programme and
contract specifications.
Provide assistance to ET and IEC in carrying out monitoring and auditing.
Participate in the site inspections undertaken by ET and IEC as required, and undertake
correction actions.
Provide information to the ET and IEC regarding works activities which may contribute, or be
contributing to, the generation of adverse environmental conditions.
Submit proposals on mitigation measures in case of exceedance of Action and Limit levels in
accordance with the Event/Action Plans.
Implement measures to reduce impact where Action and Limit levels are exceeded.
Adhere to the procedures for carrying out complaint investigation.
1.4.5 The Contractor shall also participate in the environmental performance review undertaken by
the ER and undertaken any corrective actions as instructed by the ER.
Environmental Team (ET)
1.4.6 The ET shall be employed to conduct the EM&A programme and ensure the Contractor’s
compliance with the Project’s environmental performance requirements during construction. The
ET shall not be in any way an associated body of the ER, the Contractor or the IEC for the Project.
The ET shall be an independent party from the IEC and have relevant professional qualifications, or
have sufficient relevant EM&A experience subject to approval of the ER and the environmental
Authority (the Environmental Protection Department, EPD). The ET shall be led and managed by
the ET leader.
1.4.7 The ET leader shall possess at least 7 years’ experience in EM&A and/or environmental
management and shall be an Accredited Monitoring Professional (AMP) under the Hong Kong
Institute of Environmental Impact Assessment (HKIEIA) and a Qualified Environmental
Professional under the Hong Kong Institute of Qualified Environmental Professionals (HKIQEP).
Introduction
1-4
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
1.4.8 The duties and responsibilities of the ET are:
Monitor various environmental parameters as required in this Manual.
Analyse the environmental monitoring and audit data and review the success of EM&A
programme to cost-effectively confirm the adequacy of mitigation measures implemented and
the validity of the EIA predictions and to identify any adverse environmental impacts arising.
Carry out regular site inspection to investigate and audit the Contractors' site practice,
equipment and work methodologies with respect to pollution control and environmental
mitigation, and effect proactive action to pre-empt problems; carry out ad hoc site
inspections if significant environmental problems are identified.
Audit and prepare monitoring and audit reports on the environmental monitoring data and
site environmental conditions.
Report on the environmental monitoring and audit results to the IEC, Contractor, the ER and
EPD or its delegated representative.
Recommend suitable mitigation measures to the Contractor in the case of exceedance of
Action and Limit levels in accordance with the Event and Action Plans.
Advise to the Contractor on environmental improvement, awareness, enhancement
matters, etc. on site.
Adhere to the procedures for carrying out complaint investigation in accordance with
Section 9 of this Manual.
Independent Environmental Checker (IEC)
1.4.9 The IEC shall advise the ER on environmental issues related to the Project. The IEC shall not be in
any way an associated body of the ER, the Contractor or the ET for the Project. The IEC shall be
empowered to audit from an independent viewpoint the environmental performance during the
construction of the Project.
1.4.10 The IEC shall possess at least 7 years’ experience in EM&A and/or environmental management
and shall be an AMP under the HKIEIA and a Qualified Environmental Professional under the
HKIQEP.
1.4.11 The IEC shall be responsible for the duties defined in this Manual, and shall audit the overall
EM&A programme, including the implementation of all environmental mitigation measures,
submissions required in this Manual, as well as any other relevant submissions required under
the Environmental Permit (EP). The IEC shall be responsible for verifying the environmental
acceptability of permanent and temporary works, relevant design plans and submissions under
the EP. The IEC shall verify the logbook prepared and kept by the ET Leader. The IEC shall notify
EPD by fax, within 24 hours of receipt of notification from the ET Leader, of any such instance or
circumstance or change of circumstances or non-compliance with the EIA Report or the EP,
which might affect the monitoring or control of adverse environmental impact.
1.4.12 The duties and responsibilities of the IEC are:
Review and audit in an independent, objective and professional manner in all aspects of the
EM&A programme.
Validate and confirm the accuracy of monitoring results, appropriateness of monitoring
equipment, monitoring locations with reference to the locations of the nearby sensitive
receivers, and monitoring procedures.
Carry out random sample check and audit on monitoring data and sampling procedures, etc.
Conduct random site inspection (at least once a month).
Audit the EIA recommendations and EP requirements against the status of implementation of
environmental protection measures on site.
Review the effectiveness of environmental mitigation measures and Project environmental
performance.
Introduction
1-5
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
On an as needed basis, verify and certify the environmental acceptability of the construction
methodology (both temporary and permanent works), relevant design plants and submissions
under the EP. When necessary, the IEC agree in consultation with the ET Leader and the
Contractor the least impact alternative.
Verify investigation results of complaint cases and the effectiveness of corrective measures.
Verify EM&A reports submitted and verified by the ET Leader.
Feedback audit results to ER/ET by signing accordingly to the Event/Action Plans specified in
this Manual.
1.5 Project Programme
1.5.1 The construction programme must accommodate planned draining of gei wai for desilting, as
per the MPNR Management Plan 2019-2024. Specifically, the planned draining of Gei Wai No.
20e and Gei Wai Nos. 7 and 8a for the construction of footings/substructure for TH2 and TH3,
respectively.
1.5.2 Based on best available information, the Project programme shown in Figure 1-4 assumes that
the Project will be constructed from mid-April 2022 to mid-May 2022 and early-September 2022
to mid-October 2022, a total period of about three months.
Introduction
1-6
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Figure 1-1 Statutory Plan Showing Location of Project and its Environs
Source: Extract from the approved Mai Po and Fairview Park OZP No. S/YL-MP/6, from PlanD Statutory Planning Portal 2.
Mangroves
0 250 500
Metres
Mai Po Marshes SSSI
Mangroves
Mai Po Nature Reserve
Project Site Boundary
Commercial
Fish Ponds
Gei Wai
Gei Wai
PSFSC
Introduction
1-7
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Figure 1-2 Project Elements (Indicative Plan Only)
Source: Google Earth Pro
TH2
Indicative Routes for Construction Traffic:
Existing Paved Roads
Temporary Access Along Bunds (Unpaved)
Haul Road ID
Project Components:
New Tower Hides
New Boardwalk / With EAs
Project Site Boundary
Existing Facilities
(not DPs in EIA)
Gei Wai Number
TH3
0 100 200 300 400 500
Metres
Footpath to TH3
Footpath to TH2
Boardwalk Above
Main Footpath
Boardwalk Above
Access to TH1
MPEC
TH1
MPNR Entrance
10
17
3
24
14
13
12
11
8
4
6
7
23
20
21
22
16
15
18
19
5
9
2
1
HR1
HR
HR2
HR3
HR4
HR5
HR1
HR1-2
HR1-3
HR1-3
HR1-4
Introduction
1-8
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Figure 1-3 EM&A Organisation
EIAO
Authority
_____________
EPD
Employment
Communication / Reporting
Employer
_____________
Employer’s
Representative
Environmental
Team
Independent
Environmental
Checker
Contractor
Introduction
1-9
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Figure 1-4 Project Programme
New TH2 (including Boardwalk Access)
Foundation Works (Phase 1)
Superstructure Works (Phase 2)
Roof, Cladding and Interior Works upto Handover
New TH3 (including Boardwalk Access)
Foundation Works (Phase 1)
Superstructure Works (Phase 2)
Roof, Cladding and Interior Works upto Handover
New Boardwalk (including EAs)
Construction (Part 1 - North)
Construction (Part 2 - Centre)
Construction (Part 3 - South)
Vehicular Movement (Site-wide)
Construction Vehicles
Planned MPNR Management Plan Maintenance Activities in 2022 - NOT Concurrent
Drain Down of gei wai
Habitat management
Gei Wai Refill
Key: Dry season during which there will be no outdoor Works for the Project within MPNR
Outdoor Works for the Project within MPNR
Works for Other Projects (including
the planned drain-down and re-fill of gei wai i #7, 8a, 19, 20e)
Jan
Other Projects
2022
Jul
Aug
Sep
Oct
Nov
Jun
Jan
Feb
Mar
Apr
May
Dec
Project Activity
Dec
2022
Jul
Aug
Sep
Oct
Nov
Jun
Feb
Mar
Apr
May
Air Quality
2-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
2 AIR QUALITY
2.1 Introduction
2.1.1 Potential air quality impacts arising from the construction phase of the Project were assessed in
Chapter 3 of the EIA Report. With the implementation of dust suppression measures, no adverse
air quality impact from the Project is anticipated at off-site Air Sensitive Receivers (ASRs) during
construction. No air quality monitoring is therefore deemed necessary. Nevertheless, regular site
environmental audit is recommended to ensure the implementation of the recommended
mitigation measures.
2.2 Mitigation Measures
2.2.1 Mitigation measures to prevent dust impacts have been recommended in the Section 3.7 of the
EIA Report. All the recommended mitigation measures are detailed in the implementation
schedule in Appendix A. Appropriate parties have been identified to be responsible for the
design and implementation of these mitigation measures.
2.3 Audit Requirements
2.3.1 Regular inspection and audit of each works area shall be conducted during the construction
phase of the Project to ensure that the recommended air quality mitigation measures are
properly implemented. When there are ongoing construction works within the Project Site, the
ET shall carry out inspections once per week and the IEC shall carry out audits jointly with the ET
once every two weeks.
2.3.2 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted.
Noise
3-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
3 NOISE
3.1 Introduction
3.1.1 Potential noise impacts arising from the construction phase of the Project were assessed in
Chapter 4 of the EIA Report. Based on the assessment results, and with the implementation of
recommended noise control measures, no adverse noise impact from the Project is anticipated
at off-site Noise Sensitive Receivers (NSRs) during construction. No noise monitoring is therefore
deemed necessary for NSRs. Nevertheless, regular site environmental audit is recommended to
ensure the implementation of the recommended mitigation measures.
3.2 Mitigation Measures
3.2.1 Mitigation measures to prevent construction phase noise impacts have been recommended in
the EIA Report. All the recommended mitigation measures are detailed in the implementation
schedule in Appendix A. Appropriate parties have been identified to be responsible for the
design and implementation of these mitigation measures.
3.3 Audit Requirements
3.3.1 Regular inspection and audit of each works area shall be conducted during the construction
phase of the Project to ensure the recommended noise mitigation measures are properly
implemented. When there are ongoing construction works within the Project Site, the ET shall
carry out inspections once per week and the IEC shall carry out audits jointly with the ET once
every two weeks.
3.3.2 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted.
Water Quality
4-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
4 WATER QUALITY
4.1 Introduction
4.1.1 Potential water impacts arising from the construction of the Project were assessed in Chapter 5
of the EIA Report. It was identified that Deep Bay, the gei wai, Shan Pui River, commercial
fishponds and SSSIs adjacent to and within the Site and the natural watercourses running
through the Study Area as Water Sensitive Receivers (WSRs).
4.1.2 The EIA Report therefore recommended a series of stringent mitigation measures to be
implemented at each works site to ensure that no contaminated run-off enters the fishponds or
gei wai, and from there potentially into Deep Bay.
4.1.3 With the implementation of water pollution control measures no adverse water quality impact
from the Project is anticipated during construction. Nevertheless, as a precautionary measure and
to demonstrate that the “Zero Water Pollution” approach is working, it is proposed to carry out
water quality EM&A before, during and (if required) after the foundation works at TH2 and TH3.
4.2 Monitoring
Parameters, Equipment and Analysis
4.2.1 The following parameters are related to construction activity:
Water depth to be measured in-situ
pH to be measured in-situ
Temperature in
o
C to be measured in-situ
Salinity in mg/L to be measured in-situ
Turbidity in NTU to be measured in-situ
Dissolved Oxygen (DO) in % saturation and mg/L to be measured in-situ
Suspended Solids (SS) in mg/L to be determined in a laboratory
Oil and Grease (O&G) in mg/L to be determined in a laboratory
4.2.2 Equipment provided by the ET to measure the above parameters shall include:
Portable, battery-operated echo sounder shall be used for the determination of water depth
at each designated monitoring station.
Portable pH Meter, which shall be checked, calibrated and certified before use by a HOKLAS
laboratory.
DO and Temperature Measuring Equipment capable of measuring DO in the range of 0 to 20
mg/L and 0 to 200% saturation; and temperate of 0 to45
o
C, which shall be checked, calibrated.
Portable salinometer capable of measuring salinity in the range of 0-40 mg/l shall be
provided for measuring salinity of the water and certified before use by a HOKLAS laboratory.
Turbidity Measurement Equipment capable of measuring turbidity between 0-1000 NTU and
certified before use by a HOKLAS laboratory.
A high density 1L capacity polythene bottle shall be used to collect a water sample from just
below the water surface for SS measurements while water sample for O&G measurement
shall be collected in glass bottles and preserved by addition of H
2
SO
4
. At least two replicate
samples should be collected from each location. After fully filling the bottles, they shall be
cooled to 4
O
C without being frozen.
4.2.3 All in-situ monitoring equipment shall be checked, calibrated and certified by a laboratory
accredited under HOKLAS or any other international accreditation scheme before use, and
subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes shall be checked with certified standard
solutions before each use. Wet bulb calibration for a DO meter shall be carried out before
measurement at each monitoring location.
Water Quality
4-2
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
4.2.4 The water samples shall be delivered to a HOKLAS laboratory as soon as possible for analysis,
which shall start the next working day after collection of samples. Analyses shall follow standard
methods as described in APHA Standard Methods for the Examination of Water and Wastewater,
19th Edition, unless otherwise specified (APHA 2540D for SS and APHA 5520C for O&G). The
submitted information should include pre-treatment procedures, instrument use, Quality
Assurance/Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate
samples per-batch, etc.), detection limits and accuracy. The QA/QC details shall be in accordance
with requirements of HOKLAS.
4.2.5 In addition to the water quality parameters, other relevant data should also be measured and
recorded in field logs, including coordinates of the sampling stations, the location of construction
works at the time of sampling, sampling depth, weather conditions, special phenomena and work
activities undertaken around the monitoring and works area that may influence the monitoring
results, etc.
Monitoring Locations
4.2.6 Monitoring shall be carried out adjacent to the sluice gates connecting MPNR to Deep Bay that
are closest to the tower hides works areas, i.e. Sluice Gate 7 (closest to TH3) and Sluice Gate 19
(closest to TH2). Sluice Gate 7 and Sluice Gate 19 are the only connection of Gei Wai 7 and Gei
Wai 19 to Deep Bay. These locations are show Figure 4-1 and indicative co-ordinates of these
monitoring locations are listed in Table 4-1. Samples to be taken at the sluice gate shall be at the
depth of 1m below water surface. For stations with a water depth of less than 1m, monitoring
shall be carried out at the mid-depth. Water sampling shall not be taken if water depth is less
than 0.25m.
Table 4-1 Co-ordinates of the Water Quality Monitoring Locations (HK Grid)
LOCATION
EASTING
NORTHING
Sluice Gate 7
822107
839868
Sluice Gate 19
821344
838681
Baseline Monitoring
4.2.7 Baseline water quality monitoring at Sluice Gate 7 and Sluice Gate 19 shall be carried out three
times per week, with a minimum interval of 36 hours, for a period of four weeks prior to the
commencement of foundation works at TH2 and TH3. EPD shall be advised two weeks prior to
the start of baseline monitoring. A Baseline Monitoring Report shall be prepared by the ET,
verified by the IEC and then submitted to EPD within two weeks after completion of monitoring.
Baseline conditions for water quality shall be established and agreed with DEP prior to the
commencement of works.
Precautionary Monitoring
4.2.8 Precautionary water quality monitoring at Sluice Gate 7 and Sluice Gate 19 shall be carried out
three times per week, with a minimum interval of 36 hours, when foundation works are carried
out at TH2 and TH3. Each month that foundation works are carried out at TH2 and TH3, a
Monthly EM&A Report shall be prepared by the ET, verified by the IEC and then submitted to
EPD within two weeks after the end of the month.
Post-construction Monitoring (if Needed)
4.2.9 If, at the completion of foundation works, the final week of precautionary monitoring shows
more than two consecutive exceedances of Action and/or Limit Levels attributable to the Project,
then post-construction monitoring at Sluice Gate 7 and/or Sluice Gate 19 (as needed) shall be
carried out three times per week until readings return to baseline levels. Upon completion of
post-construction monitoring, a Final Summary EM&A Report will be prepared by ET, verified by
the IEC and then submitted to EPD within two weeks after completion of monitoring.
Water Quality
4-3
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Action and Limit Levels and Event/Action Plan for Precautionary Monitoring
4.2.10 Precautionary monitoring results shall be evaluated against Action and Limit levels shown in
Table 4-2, with action being taken as per the Event/Action Plan shown in Table 4-3. Please note
that the Event/Action Plan relates only to exceedances that are directly attributable to the
construction works of this Project, over which the installation contractor has control. The advice
of the IEC shall be sought in case of any concern.
Table 4-2 Action and Limit Levels for Water Quality
PARAMETER
ACTION LEVEL
LIMIT LEVEL
DO in mg/L
5
th
percentile of baseline data
1
st
percentile of baseline data
SS in mg/L
95
th
percentile of baseline data
99
th
percentile of baseline data
Turbidity in NTU
95
th
percentile of baseline data
99
th
percentile of baseline data
Table 4-3 Event / Action Plan for Water Quality
EVENT
CONTRACTOR / ET
IEC
ER
Action
Level
Exceedance
1. Repeat sampling event.
2. Inform EPD and AFCD and
confirm notification of the
non-compliance in
writing.
3. Discuss with contractor
and the IEC the most
appropriate method of
reducing water quality
pollution during
construction and agree
with EPD.
4. Repeat measurements
after implementation of
mitigation for
confirmation of
compliance.
5. If non-compliance
continues, increase
measures in Step 3 and
repeat measurement in
Step 4. If non-compliance
occurs a third time,
suspend construction
works and continue
sampling until normal
water quality resumes.
1. Discuss with
Contractor/ET on the
mitigation measures
2. Review proposals on
mitigation measures
submitted by Contractor
and advise the ER
accordingly
3. Assess the effectiveness
of the implemented
mitigation measures.
1. Discuss with IEC on
the proposed
mitigation measures;
2. Make agreement on
the mitigation
measures to be
implemented;
3. Assess the
effectiveness of the
implemented
mitigation measures.
Limit Level
Exceedance
Suspend construction works
and undertake Steps 1-4
immediately. Construction
works should only continue
when the water quality shows
compliance again.
Undertake Steps 1-3
immediately
Undertake Steps 1-3
immediately and consider
and instruct, if necessary,
the Contractor to slow
down or to stop all or
part of the construction
works until no
exceedance of Limit level.
4.3 Mitigation Measures
4.3.1 Mitigation measures to prevent construction phase water quality impacts have been
recommended in the EIA Report. All the recommended mitigation measures are detailed in the
implementation schedule in Appendix A. Appropriate parties have been identified to be
responsible for the design and implementation of these mitigation measures.
Water Quality
4-4
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
4.4 Audit Requirements
4.4.1 Regular inspection and audit of each works area shall be conducted during the construction
phase of the Project to ensure the recommended water quality mitigation measures are
properly implemented. When there are ongoing construction works within the Project Site, the
ET shall carry out inspections once per week and the IEC shall carry out audits jointly with the ET
once every two weeks.
4.4.2 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted. The audits
should examine all aspects of on-site water pollution prevention, including the following:
Perimeter Bund. A perimeter bund shall be constructed around the work sites for TH2 and
TH3 to ensure that any runoff generated from these sites is discharged only into the adjacent
drained gei wai and not into any other water-filled gei wai that are hydraulically connected to
each other and to Deep Bay. Runoff is therefore prevented from entering other water-filled
gei wai and Deep Bay and so potential pollution of these water bodies is avoided.
Off-site Pre-fabrication. The majority of construction components shall be pre-fabricated
off-site to avoid any impacts associated with construction on-site. With this approach, the
construction activities will mainly involve assembly of pre-fabricated components.
Off-site Concrete Mixing. One of the main sources of contaminated runoff from
construction sites is concrete washings from concrete mixing on site. To avoid this problem,
all concrete will be mixed off-site and brought into each works area only when needed and
only in the quantities required, so that there is no need to store (or dispose of) any surplus
concrete. Any concrete spilled within the works area will be immediately cleaned up and
removed from the works area.
Off-site Maintenance/Repair of Plant. Plant, equipment and vehicles shall not be
maintained or repaired within any works area in the Project Site. Instead, all such servicing
shall be undertaken off-site, such that any resulting oil, chemical waste or other polluting
substances can be handled and treated off-site in an appropriate manner.
Extreme Care When Re-fuelling Plant. In the event that non-mobile plant and equipment
require re-fuelling, and it is not practicable to move off-site for re-fuelling, then re-fuelling
shall be carried out with extreme care. Drip trays shall be provided at any fuel connection
point, e.g. between the delivery pipe and the fuel tank. Any spilled fuel shall be collected
and taken off-site for proper treatment/disposal.
Covering Materials, Plant and Equipment. Materials, plant or equipment that could give rise
to contaminated runoff during extreme rainfall will be protected by storing above ground
level and also by being covered, either by tarpaulin or by small gazebos that can be erected
and folded up within a few minutes.
Provision of Chemical Toilets. Each works area will be provided with at least one chemical
toilet for use by workers. Sewage collected in these chemical toilets will be treated off-site
by the toilet provider.
Bunded, Covered Construction C&D Material Storage Areas. Each works area will be
provided one bunded and covered area for the temporary storage of C&D material one
section for inert C&D material and one area for C&D waste. These areas will be emptied
frequently, using construction material delivery vehicles that are empty on their return
journey. All inert C&D material and C&D waste will be transported off-site for recycling or
treatment as appropriate.
Waterproof General Waste Receptacles. Each works area will be provided with at least one
set of waterproof waste receptacles one for recyclable waste and one for non-recyclable
waste. These areas will be emptied frequently.
4.4.3 In addition to the above, the Construction Contractor shall be audited on his implementation of
good site practice on the design construction, operation and maintenance of relevant mitigation
measures specified in ProPECC PN 1/94 for construction site drainage.
Water Quality
4-5
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Figure 4-1 Locations for Water Quality Monitoring
Source: Google Earth Pro
Project Elements:
New Tower Hides
New Boardwalk / With EAs
Project Site Boundary
Gei Wai to be Drained
Sluice Gate Connecting
MPNR to Deep Bay
Water Quality
Monitoring Locations
(Gei Wai with Sluice Gate)
X
X
Deep Bay
TH2
TH3
0 100 200 300 400 500
Metres
Boardwalk Above
Main Footpath
8a
7
19
20e
19
7
Waste Management
5-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
5 WASTE MANAGEMENT
5.1 Introduction
5.1.1 Potential waste management implications arising from the construction phase of the Project
were assessed in Chapter 6 of the EIA Report.
5.1.2 Waste management during the construction phase will mainly be the responsibility of the
Contractor, who shall implement the mitigation measures recommended in the EIA Report in
order to minimise waste or resolve the issues associated with the management of waste. The
Contractor should also ensure that all wastes produced during the construction phase are
handled, stored and disposed of in accordance with good waste management practices, relevant
legislation and waste management guidelines.
5.2 Mitigation Measures
5.2.1 With the proper handling, storage and disposal of wastes arising from the construction of the
Project, it is anticipated that the potential adverse environmental impacts would be avoided or
minimised. During site inspections, the ER, ET and IEC should pay special attention to the issues
relating to the waste management and check whether the Contractor has implemented the
recommended good site practices and other mitigation measures listed in Appendix A.
Appropriate parties have been identified to be responsible for the design and implementation of
these mitigation measures.
5.2.2 The Contractor should submit a Waste Management Plan (WMP) prior to the commencement of
construction work, in accordance with ETWB TC(W) No 19/2005 to provide an overall framework
of waste management and reduction.
5.3 Audit Requirements
5.3.1 Regular inspection and audit of each works area shall be conducted during the construction
phase of the Project to ensure the recommended waste mitigation measures are properly
implemented. When there are ongoing construction works within the Project Site, the ET shall
carry out inspections once per week and the IEC shall carry out audits jointly with the ET once
every two weeks.
5.3.2 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted. The audits
should examine all aspects of on-site waste management practices, including the following:
The Construction Contractor’s documents, including licenses, permits, disposal and recycling
records, shall be regularly inspected to ensure they comply with legislation and contract
requirements.
Review of the Construction Contractor’s Waste Management Plan (WMP) prepared in
accordance with ETWB TC(W) No. 19/2005 to be submitted to the Engineer for approval
before the commencement of any construction work.
Implementation of mitigation measures listed in Practice Note for Registered Contractors No.
17 Control of Environmental Nuisance from Construction Sites and compliance with the
particular specification listed in Part B of Annex 2 to Appendix C of ETWB TC(W) No. 19/2005
in relation to the use of dump trucks.
Implementation of a trip-ticket system in accordance with DevB TC(W) No. 6/2010 and the
Waste Disposal (Charges for Disposal of Construction Waste) Regulation and the Demolition
Contractor’s regular submission of chits.
Provision of suitable enclosed bins or compaction units (separate from C&D Material) in an
enclosed and covered area to be used for the temporary storage of general refuse prior to
its removal from Site by a reputable waste contractor.
Ecology
6-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
6 ECOLOGY
6.1 Introduction
6.1.1 Potential ecological impacts arising from the construction phase of the Project were assessed in
Chapter 7 of the EIA Report. Mitigation measures have been recommended to minimise
potential direct and indirect impacts to ecology and biodiversity. With the implementation of
appropriate mitigation measures, no unacceptable ecological impact is anticipated.
6.2 Mitigation Measures
6.2.1 Mitigation measures to prevent potential construction phase direct and indirect ecological
impacts have been recommended in the EIA Report and are detailed in the implementation
schedule in Appendix A. Appropriate parties have been identified to be responsible for the
design and implementation of these mitigation measures.
6.2.2 The three project elements will be assembled/constructed over a two-month period between
mid-April and mid-October, thus avoiding impacts on the high number of waterbirds and
wetland-dependent species present in the dry season.
6.2.3 Adequate site checks in the works area and in the vicinity of the footprint of all project elements
will be conducted by a suitably qualified ecologist prior to commencement of works to search for
substantive usage of the habitat by flora and/or fauna of conservation concern, e.g. the
presence of an otter holt. If roosting or breeding species are found appropriate measures should
be taken to avoid adverse impact, including adjustments to the timing of the works.
6.2.4 It is proposed to reduce the potential for disturbance impacts during the construction phase on
species using adjacent habitats by installing a 2m-high solid, opaque screen around works areas.
In addition, planting bamboo using the native species Bambusa tuldoides (青稈竹, 花眉竹) a
minimum of 2m-high and of sufficient depth to provide an effective screen will be provided
along the access path to the new Tower Hides to reduce disturbance during the operational
phase. It may be necessary to install artificial screens in the early phase while the natural screen
planting reaches acceptable height/depth. Monitoring and Audit requirements regarding these
measures are detailed in Chapter 8 of this Manual.
6.2.5 All construction activity for TH2 and its associated access path, including the passage of
construction vehicles, will cease two hours before sunset, this means 4pm in the wet season
construction period, to avoid impacts on nocturnal roost sites and associated pre-roost
gatherings of Collared Crow in the vicinity of Pond 20.
6.2.6 All construction activity for TH3 and the footpath will cease one hour before sunset to avoid
impacts on ardeid roost or pre-roost sites in the vicinity.
6.2.7 Ahead of construction, ET checks will be conducted during the breeding season to check for the
presence of breeding ardeids within 500m of the footprint of project elements. These checks
should be carried out two weeks prior to construction commencing and the day before. Should
any egretry be discovered in the vicinity of works areas, the need for mitigation measures shall
be assessed in consultation with AFCD.
6.2.8 Adequate site checks along haul roads and in the works area and in the immediate vicinity
should be conducted prior to the commencement of works at TH2 and TH3 to detect substantive
use of adjacent habitat by species of conservation concern. If roosts or breeding species are
found, appropriate measures should be taken to avoid adverse impact, including adjustments to
the timing of works.
6.3 Monitoring and Audit Requirements
Ecology
6-2
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
6.3.1 Regular inspection and audit of each works area shall be conducted both prior to and during the
construction phase of the Project to ensure the recommended ecological mitigation measures
are properly implemented.
6.3.2 To detect substantive use of adjacent habitat by species of conservation concern, adequate site
checks in the works area and in the immediate vicinity should be conducted prior to
commencement of works at TH2 and TH3.
6.3.3 Throughout the construction period, ET checks will be conducted during the early part of the
breeding season (March to May) at works areas.
6.3.4 When there are ongoing construction works within the Project Site, the ET shall carry out
inspections once per week and the IEC shall carry out audits jointly with the ET once every two
weeks.
6.3.5 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted.
Fisheries
7-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
7 FISHERIES
7.1 Introduction
7.1.1 Potential fisheries impacts arising from the construction phase of the Project were assessed in
Chapter 8 of the EIA Report. No unacceptable fisheries impact is anticipated.
7.2 Mitigation Measures
7.2.1 No mitigation measures are needed.
7.3 Monitoring and Audit Requirements
7.3.1 Regular inspection and audit of each works area adjacent to fishponds shall be conducted during
the construction phase of the Project. When there are ongoing construction works within the
Project Site, the ET shall carry out inspections once per week and the IEC shall carry out audits
jointly with the ET once every two weeks.
7.3.2 Inspection findings shall be logged in a site monitoring report.
Landscape and Visual
8-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
8 LANDSCAPE AND VISUAL
8.1 Introduction
8.1.1 Potential landscape and visual impacts arising from the construction phase of the Project were
assessed in Chapter 9 of the EIA Report. Mitigation measures have been recommended to
minimise potential landscape and visual impacts. With the implementation of appropriate
mitigation measures, no unacceptable landscape and visual impact is anticipated.
8.2 Mitigation Measures
8.2.1 Mitigation measures to prevent construction phase landscape and visual impacts have been
recommended in the EIA Report. All the recommended mitigation measures are detailed in the
implementation schedule in Appendix A. Appropriate parties have been identified to be
responsible for the design and implementation of these mitigation measures.
8.3 Monitoring and Audit Requirements
Baseline Monitoring
8.3.1 Prior to the commencement of construction works, a Baseline Landscape and Visual Report shall
be prepared to check, record and report the status of the Landscape Resources (LRs) and
Landscape Character Areas (LCAs) within the works areas and the Visually Sensitive Receivers
(VSRs) within the visual envelope. The Landscape and Visual Impact Assessment (LVIA) in the EIA
Report may be used to formulate the Baseline Monitoring Report provided that there have been
no significant changes to the status of LRs, LCAs and VSRs since the approval of the EIA Report.
8.3.2 If there have been significant changes to the status of LRs, LCAs and VSRs since the approval of
the EIA Report, the recommended landscape and visual mitigation measures should be reviewed
to determine if such changes warrant a change in the design of the landscape and visual
mitigation measures.
Audit
8.3.3 Regular inspection and audit of each works area shall be conducted during the construction
phase of the Project to ensure that proposed landscape and visual mitigation measures are
properly implemented and maintained as per their intended objectives. When there are ongoing
construction works within the Project Site, the ET shall carry out inspections once per week and
the IEC shall carry out audits jointly with the ET once every two weeks.
8.3.4 The screen planting of bamboo at the access to TH2 and TH3 shall be inspected and audited on a
monthly basis by a qualified plant specialist for the first twelve months after planting; on a two-
monthly basis during the second twelve months (months 13 to 24 inclusive); and on a quarterly
basis for the third twelve months (months 25 to 36 inclusive).
8.3.5 Inspection findings shall be logged in a site monitoring report with any discrepancies or concerns
regarding the implementation and effectiveness of mitigation measures highlighted.
Inspection/Audit
9-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
9 INSPECTION/AUDIT
9.1 Site Inspection/Audit Requirements
9.1.1 Site inspection/audit provides a direct means to trigger and enforce the specified environmental
protection and pollution control measures. In conjunction with the Project’s contractual
environmental requirements, the implementation of pollution control and mitigation measures,
and a site deficiency and action reporting system (in accordance with the event contingency
plan), site inspection/audit is one of the most effective tools available to enforce environmental
protection requirements on site.
9.1.2 In order to ensure that appropriate environmental protection and pollution control mitigation
measures are properly implemented, when there are ongoing construction works within the
Project Site the ET shall carry out inspections once per week and the IEC shall carry out audits
jointly with the ET once every two weeks.
9.1.3 All observations and results of site inspection/audit will be recorded by the ET on a Site
Inspection/Audit Checklist that will be passed to the Contractor. If non-compliance is found, the
relevant Event/Action Plan shall be implemented.
9.1.4 The Site Inspection/Audit Checklist shall be prepared by the ET and verified by the IEC then
submitted to the ER for approval. The ET is also responsible for formulation of the
environmental site inspection/audit, deficiency and action reporting system.
9.1.5 The areas of inspection/audit shall not be limited to the environmental situation, pollution
control and mitigation measures within the site; it will also review the environmental situation
outside the site area which is likely to be affected, directly or indirectly, by the site activities. The
ET shall make reference to the following information in conducting the inspection/audit:
Recommendations on pollution control mitigation measures in the EIA Report.
Works progress, programme and activities currently being carried out within the Site.
Individual works methodology proposals (which shall include proposals on associated
pollution control measures).
Contract specifications on environmental protection.
Relevant environmental protection and pollution control laws
Previous site inspection/audit results.
9.1.6 The Contractor shall regularly update the ET Leader and IEC with relevant information regarding
construction works to enable site inspections/audits to be carried out effectively. The inspection
/audit results and any associated recommendations on improvements to the environmental
protection and pollution control works shall be submitted to the ER and the Contractor within 24
hours, for taking action as appropriate. The Contractor shall follow the procedures and time-
frame as stipulated in the environmental site inspection/audit, deficiency and action reporting
system to report on any remedial measures subsequent to the site inspections/audits.
9.1.7 The inspections/audits carried out by the ET and IEC shall also check the implementation and
effectiveness of previously recommended remedial measures.
9.1.8 Ad hoc site inspections/audits shall also be carried out if significant environmental problems are
identified. Inspections/audits may also be required subsequent to receipt of an environmental
complaint, or as part of the investigation/audit work, as specified in the Event/Action Plan.
9.2 Compliance with Legal and Contractual Requirements
9.2.1 There are contractual environmental protection and pollution control requirements as well as
environmental protection and pollution control laws in Hong Kong, which the Contractor shall
ensure his construction activities comply with.
Inspection/Audit
9-2
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
9.2.2 In order that the works are in compliance with the contractual requirements, all the works
method statements submitted by the Contractor to the ER for approval shall be sent to ET
Leader for vetting to see whether sufficient environmental protection and pollution control
measures have been included.
9.2.3 The ET Leader shall also review the progress and programme of the works to check that relevant
environmental laws have not been violated and that the any foreseeable potential for violating
the laws can be prevented.
9.2.4 The Contractor shall regularly copy relevant documents to the ET Leader so that the checking
work can be carried out. These document shall at least include an updated Work Progress
Report, updated Works Programme, application letters for various licences/permits and copies
of valid licences/permits when issued. The Site Diary shall also be made available for the ET
Leader‘s inspection upon request.
9.2.5 The ET Leader shall advise the ER and the Contractor of any non-compliance with the contractual
and legislative requirements on environmental protection and pollution control for them to take
follow-up actions. If the ET Leader’s review concludes that the current status on licence/permit
application and any environmental protection and pollution control preparation works may not
be compatible with the works programme or may result in violation of environmental protection
and pollution control requirements in due course, he/she shall advise the Contractor and the ER
accordingly.
9.2.6 Upon receipt of the ET Leader’s advice, the Contractor shall undertake immediate action to
remedy the situation. The ER shall follow up to ensure that appropriate action has been taken by
the Contractor in order that the environmental protection and pollution control requirements
are fulfilled.
9.3 Environmental Complaints
9.3.1 Complaints shall be referred to the ET Leader for carrying out an investigation. The ET Leader
shall undertake the following procedures upon receipt of a complaint:
Log complaint and date of receipt and inform the ER immediately.
Investigate the complaint to determine its validity, and to assess whether the source of the
problem is due to works activities.
If a complaint is valid and due to works, identify mitigation measures.
If mitigation measures are required, advise the Contractor accordingly.
Review the Contractor’s response on the identified mitigation measures and the updated
situation.
If the complaint is a referral from EPD, submit an Interim Complaint Report to EPD (after
endorsement by ER) on status of the complaint investigation and follow-up action within the
time frame assigned by EPD.
Undertake additional monitoring and audit, if necessary, to verify the situation and ensure
that reasons for the original complaint do not recur.
Report the investigation results and the subsequent actions to remedy the source of complaint
and respond to complainant directly or, if the complaint was a referral from EPD, submit a
Complaint Report to EPD (after endorsement by ER) on status of the complaint investigation
and follow-up action within the time frame assigned by EPD.
Record the complaint, investigation, the subsequent actions and the results in the monthly
EM&A report.
9.3.2 During the complaint investigation, the Contractor and ER shall co-operate with the ET Leader in
providing all necessary information and assistance to complete the investigation. If additional
mitigation measures are identified in the investigation, the Contractor shall promptly implement
these. The ER shall ensure that the measures have been carried out by the Contractor.
Reporting
10-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
10 REPORTING
10.1 Baseline Monitoring Report
10.1.1 The baseline monitoring results, their interpretation and any proposals for the Action/ Limit level
parameters shall be presented in the Baseline Monitoring Report that will be submitted to the
ER for agreement. The Baseline Monitoring Report should be supported by baseline monitoring
data in electronic format prepared in HTML or PDF format, along with information from the
covering monitoring locations, equipment and protocols. The agreed Baseline Monitoring Report
will then be reissued as a standalone report. The report shall be prepared by the ET and shall be
verified by the IEC.
10.1.2 The Baseline Monitoring Report shall include at least the following:
Up to half a page of Executive Summary
Project background information
Drawings showing the locations of the baseline monitoring stations
Monitoring results including graphical plots, together with the following information, as
needed:
Monitoring methodology
Name of the laboratory and types equipment used and calibration details
Parameters monitored
Monitoring locations
Monitoring date, time, frequency and duration
QA/QC results and detection limits
Interpretation of the significance of monitoring results and explanation of any influencing
factors, including:
Major activities, if any, being carried out in the Project Site
Weather conditions
Other factors which might affect the monitoring results
Determination of Action and Limit levels for monitoring parameters, as needed.
Baseline Landscape and Visual Report
Any revisions for inclusion in the EM&A programme
Comments and conclusions
10.2 Monthly EM&A Reports
10.2.1 The results and finding of all EM&A work required in the EM&A programme shall be recorded in
the Monthly EM&A Reports prepared by the ET Leader. Monthly EM&A Reports shall be
submitted to the ER within 10 working days of the end of each reporting month after being
verified by the IEC. The first report will be submitted in the month after construction works
commence. Each Monthly EM&A Report shall be submitted to the following parties: the
Contractor, the IEC, the ER and EPD.
10.2.2 Before submission of the first Monthly EM&A Report, the ET Leader shall liaise with the parties
on format of the monthly reports to be submitted as .pdf files via email.
10.2.3 The monthly EM&A Report shall include the following:
1-2 pages Executive Summary:
Any exceedances of Action and Limit levels
Compliant log
Notifications of any summons and successful prosecutions
Reporting changes
Future key issues
Reporting
10-2
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Basic project information:
Project organisation, including key personnel contact details
Programme
Management structure
Works undertaken during the month
Any updates as needed to the scope of works and construction methodologies
Brief Summary of EM&A Requirements:
All monitoring parameters
Environmental quality performance limits (Action and Limit Levels)
Event/Action Plan
Environmental mitigation measures as recommended in the EIA Report
Environmental requirements in contract documents
Environmental Status:
Advice on the status of statutory environmental compliance such as the status of
compliance with the EP conditions under the EIAO, submission status under the EP and
implementation status of mitigation measures
Works undertaken during the month with illustrations (such as location of works, daily
excavation rate, etc.)
Drawings showing the Project Site, any environmental sensitive receivers and the
locations of the monitoring and control stations (with co-ordinates of the monitoring
locations)
Implementation Status: Advice on the implementation status of environmental
protection/pollution control/mitigation measures, recommended in the EIA Report
Monitoring results together the following information:
Monitoring methodology
Name of laboratory and types of equipment used and calibration details
Monitoring parameters
Monitoring locations
Monitoring date, time, frequency, and duration
Weather conditions during the period
Any other factors which might affect the monitoring results
QA/QC results and detection limits
Report on any non-compliance, complaints, and any notifications of summons and
successful prosecutions:
Record of all non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit levels)
Record of all complaints received (written or verbal) for each media, including locations
and nature of complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary
Record of all notification of summons and successful prosecutions for breaches of
current environmental protection/pollution control legislation, including locations and
nature of the breaches, investigation, follow-up actions taken, results and summary
Review of the reasons for and the implications of non-compliances, complaints,
summons and prosecutions including review of pollution sources and working
procedures
Description of the actions taken in the event of non-compliance and deficiency reporting
Others:
An account of the future key issues as reviewed from the works programme and work
method statements
Advice on the solid waste management status
Reporting
10-3
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Record of any project changes from that originally proposed in the EIA Report (e.g.
construction methods, programme, mitigation, design changes, etc.)
Comments (for example, effectiveness and efficiency of the mitigation measures),
recommendations (for examples, any improvement in the EM&A programme) and
conclusions
Appendices:
Action and Limit levels
Graphical plots of trends of the monitoring parameters at key stations over the past four
reporting periods (where available) annotated against the following:
Major activities being carried out on site during the period
Weather conditions during the period
Any other factors that might affect the monitoring results
Monitoring schedule for the present and next reporting period
Cumulative statistics on complaints, notifications of summons and successful
prosecutions
Outstanding issues and deficiencies
10.3 Final Summary EM&A Report
10.3.1 The EM&A programme for construction stage shall be terminated upon the completion of the
construction activities. The proposed termination should only be implemented after the
proposal has been endorsed by the IEC and the ER followed by approval from the Director of
Environmental Protection.
10.3.2 The Final EM&A Review Report for construction stage (to be submitted after completion of
construction activities) shall be prepared by the ET and shall be verified by the IEC and should
contain at least the following information:
Executive Summary (1-2 pages)
Drawings showing the project area, any environmental sensitive receivers and the locations
of the monitoring and control stations, if any
Basic project information including a synopsis of the project organisation, contacts of key
management, and a synopsis of work undertaken during the course of the EM&A
programme
A brief summary of EM&A requirements including:
Environmental mitigation measures for construction stage, as recommended in the
project EIA Report
Environmental impact hypotheses tested
Environmental quality performance limits (Action and Limit levels)
All monitoring parameters
Event and Action Plans
A summary of the implementation status of environmental protection and pollution
control/mitigation measures for construction stage, as recommended in the project EIA
Report and summarised in the updated implementation schedule
A summary of the monitoring results over the period of the EM&A programme together
with the following information:
Monitoring methodology
Name of laboratory and types of equipment used and calibration details
Monitoring parameters
Monitoring locations
Monitoring date, time, frequency, and duration
Graphical plots of monitored trends over the period of the EM&A programme
Any other factors which might affect the monitoring results
QA/QC results and detection limits
Reporting
10-4
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
A summary of non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit levels)
A review of the reasons for and the implications of non-compliance including review of
pollution sources and working procedures as appropriate
A description of the actions taken in the event of non-compliance
A summary record of all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up actions taken and results
A review of the validity of EIA predictions for construction stage and identification of
shortcomings in EIA recommendations
Comments (for example, a review of the effectiveness and efficiency of the mitigation
measures, the performance of the environmental management system, and the overall
EM&A programme for construction stage)
Recommendations and conclusions (for example, a review of success of the overall
EM&A programme for construction stage to cost-effectively identify deterioration and to
initiate prompt effective mitigatory action when necessary)
10.4 Letters Documenting Post-planting Landscape Inspections
10.4.1 Commencing after completion of the planting of the bamboo screen at TH2 and TH3, letter
reports shall be prepared by the ET and submitted to the Director of Environmental Protection
at the frequency indicated in paragraph 8.3.5.
10.5 Data Keeping
10.5.1 Documents such as the monitoring field records, site inspection forms etc. are not required to be
included in the monthly EM&A reports for submission. However, all documents and records shall
be kept by the ET and be ready for inspection upon request. All documents and data shall be
kept by the ET for at least one year after termination of the EM&A programme.
10.6 Interim Notifications of Environmental Quality Limit Exceedances
10.6.1 With reference to the Event and Action Plans, when the environmental quality performance
limits are exceeded, and if they are proven to be valid, the ET shall immediately notify the IEC
and EPD, as appropriate. The notification should be followed up with advice to the IEC and EPD
on the results of the investigation, proposed actions and success of the actions taken, with any
necessary follow-up proposals.
10.6.2 A sample template for the interim notification is provided in Appendix B.
Appendix A
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Appendix A Implementation Schedule for the Project
Appendix A
A-1
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
AIR QUALITY
3.2.6
A.1
Use of approved Non-road Mobile Machinery
(NRMM) for all site works areas
To minimise pollutants from
exhaust emissions of mobile plant
and equipment
All works
areas
Construction
Contractor
Air Pollution Control
(Non-road Mobile
Machinery)
(Emission) Regulation
3.6.2
A.2
Off-site Pre-fabrication of key elements for TH2 and
TH3
To reduce air quality impacts
associated with construction of
new buildings
TH2 and
TH3
Engineer +
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
3.7.2
A.3
1. Regular watering to reduce dust emissions from
exposed site surfaces and unpaved roads,
particularly during dry weather
2. Open stockpiles shall be avoided or covered.
Where possible, prevent placing dusty materials
storage piles near ASRs.
3. Side enclosure of any aggregate or dusty
material storage piles to reduce emissions.
Where this is not practicable owing to frequent
usage, spraying with water shall be carried out
4. Tarpaulin covering of all dusty vehicle loads
transported to and from the Site
5. Use of water sprinklers at the loading area
where dust generation is likely during the
loading process of loose material, particularly in
dry weather
6. Imposition of speed controls for vehicles on Site
7. Establishment and use of vehicle wheel and
body washing facilities at the exit of the Site to
minimise the fugitive dust emissions generated
8. Site layout should be carefully planned such
that machinery and dust causing activities (e.g.
To reduce fugitive dust emissions
from works areas
All works
areas
Construction
Contractor
Air Pollution Control
(Construction Dust)
Regulation
Appendix A
A-2
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
haul roads and stockpiling areas) could be
located away from the ASR as far as possible
9. Where possible, routing of vehicles and
positioning of construction plant should be at
the maximum possible distance from ASRs
10. Solid screens are recommended to be erected
around any dusty construction activities
NOISE
4.6.3
N.1
Prohibition of works during Restricted Hours
To restrict and reduce noise
nuisance during restricted hours.
All works
areas
Construction
Contractor
NCO
4.6.3
N.2
Prohibition of percussive piling
To restrict and reduce noise
nuisance from the use of noisy and
heavy piling equipment.
All works
areas
Construction
Contractor
TM on Noise from
Percussive Piling
4.9.1
N.3
1. Adopt Code of Practice on Good Management
Practice to Prevent Violation of the NCO
2. Before commencing work, the Contractor shall
submit to the Project Engineer the method of
working, equipment and noise mitigation
measures intended to be used at the Site
3. Devise and execute working methods to
minimise the noise impact on the surrounding
sensitive uses, and provide experienced
personnel with suitable training to ensure that
those methods are implemented
4. PME should be kept to a minimum and the
parallel use of noisy equipment/ machinery
should be avoided
5. Turn off unused equipment
6. Regular maintenance (off-site) of all plant and
equipment
To restrict and reduce noise
nuisance from works areas.
All works
areas
Construction
Contractor
Mai Po Inner Deep
Bay Ramsar Site
Management Plan
Code of Practice on
Good Management
Practice to Prevent
Violation of the NCO
(for Construction
Industry)
Appendix A
A-3
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
WATER QUALITY
5.4.17
WQ.1
Foundation works at TH2 and TH3 shall be aligned
with the schedule of draining the adjacent gei wai
set out in the MPNR Management Plan 2019-2024.
Making use of hydraulic isolation of
adjacent gei wai to avoid pollution
of other gei wai and Deep Bay
TH2 and
TH3 for
foundation
works
Engineer +
Construction
Contractor
MPNR Management
Plan 2019-2024
5.4.27
WQ.2
A perimeter bund will be constructed around the
work sites for TH2 and TH3 to ensure that any
runoff generated from within these sites is
discharged only into the adjacent drained gei wai
To ensure pollutants cannot
discharge into other water-filled gei
wai and so provide a pathway for
pollutants to enter Deep Bay
TH2 and
TH3 for
foundation
works
Engineer +
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
5.4.27
WQ.3
The majority of construction components shall be
pre-fabricated off-site to avoid any impacts
associated with construction on-site
To achieve zero polluted runoff
from works areas by minimising on-
site construction of building
components
Off-site
Engineer +
Construction
Contractor
5.4.27
WQ.4
All concrete will be mixed off-site and brought into
each works area only when needed and only in the
quantities required, so that there is no need to store
(or dispose of) any surplus concrete
To achieve zero polluted runoff
from works areas by avoiding
concrete mixing, storage and/or
disposal on site
Off-site
Construction
Contractor
5.4.27
WQ.5
Any concrete spilled within the works area will be
immediately cleaned up and removed from the area
To achieve zero polluted runoff
from works areas by immediate
cleaning up and removal of spilled
concrete
All works
areas
Construction
Contractor
5.4.27
WQ.6
Plant, equipment and vehicles shall not be
maintained or repaired within any works area in the
Project Site
To achieve zero polluted runoff
from works areas by handling and
treating any resulting oil, chemical
waste or other polluting substances
off-site in an appropriate manner
Off-site
Construction
Contractor
5.4.27
WQ.7
During re-fuelling, drip trays shall be provided at any
fuel connection point. Any spilled fuel shall be
collected and taken off-site for proper treatment/
disposal
To achieve zero polluted runoff
from works areas by carrying out
the refuelling with extreme care
All works
areas
Construction
Contractor
Good Site Practice
5.4.27
WQ.8
Materials, plant or equipment that could give rise to
contaminated runoff during extreme rainfall will be
To minimise the quantity of
contaminated runoff during
All works
areas
Construction
Contractor
Appendix A
A-4
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
protected by being covered, either by tarpaulin or
by small gazebos that can be erected within minutes
extreme rainfall
5.4.27
WQ.9
Each works area will be provided with at least one
chemical toilet for use by workers. Sewage collected
in these chemical toilets will be treated off-site
To ensure sewage is collected and
treated off-site properly
All works
areas
Construction
Contractor
5.4.27
WQ.10
Each works area will be provided one bunded and
covered area for the temporary storage of C&D
material one section for inert C&D material and one
area for C&D waste. These areas will be emptied
frequently, using construction material delivery
vehicles that are empty on their return journey
To ensure proper storage of C&D
material to avoid polluting adjacent
gei wai or fishponds
All works
areas
Construction
Contractor
5.4.27
WQ.11
Each works area will be provided with at least one
set of waterproof waste receptacles one for
recyclable waste and one for non-recyclable waste.
These areas will be emptied frequently
To ensure proper storage of wastes
to avoid polluting adjacent gei wai
or fishponds
All works
areas
Construction
Contractor
5.6.2
WQ.12
1. Perimeter channels at site boundaries shall be
provided to intercept storm runoff from outside
the works areas so that it will not wash across
the works areas and to direct all site runoff only
into adjacent drained gei wai
2. For the purpose of preventing soil erosion,
exposed slope surfaces shall be covered e.g. by
tarpaulin, and temporary access roads shall be
protected by crushed stone or gravel
3. Intercepting channels shall be provided (e.g.
along the crest/edge of excavation) to prevent
storm runoff from washing across exposed soil
surfaces. Arrangements shall always be in place
to ensure that adequate surface protection
measures can be safely carried out well before
the arrival of a rainstorm
4. Earthworks final surfaces shall be well
compacted and subsequent permanent works
To minimise the quantity of
contaminated runoff and muddy
water from works areas by
following the good site practice
All works
areas
Construction
Contractor
ProPECC PN 1/94
Construction Site
Drainage
Appendix A
A-5
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
or surface protection shall be carried out
immediately after the final surfaces are formed
to prevent erosion. Appropriate drainage like
intercepting channels shall be provided where
necessary
5. Measures shall be taken to minimise the ingress
of rainwater into trenches they shall be dug
and backfilled in short sections
5.5.1
WQ.13
The two new tower hides will not be provided with
toilets or washrooms. Runoff from the roof of the
tower hides and from the boardwalks will not be
contaminated
No wastewater will be generated
during operation.
TH2 and
TH3
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
WASTE MANAGEMENT
6.6.2
WM.1
Preparation of a WMP to manage waste on site
To identify potential environmental
impacts from the generation of
waste; to recommend appropriate
waste handling, collection, sorting,
disposal and recycling measures;
and to categorise and permit
segregation of C&D material (i.e.
inert C&D materials, C&D waste,
etc.) for off-site reuse, recycling,
treatment and/or disposal
All works
areas
Construction
Contractor
ETWB TC(W) No.
19/2005, Env Mgmt
on Construction Sites
6.6.3
WM.2
Waste storage areas should be well maintained and
cleaned regularly
To adopt good housekeeping
practices and prevent waste
materials being blown around by
wind, flushed or leached into nearby
waters, or creating odour nuisance
or pest and vermin problems
All works
areas
Construction
Contractor
Good Site Practice
6.6.4
WM.3
Store refuse pending removal in receptacles
provided with close fitting covers and remove and
properly dispose of refuse daily
To avoid waste materials be flushed
or leached during inclement weather
conditions such as heavy rainfall
All works
areas
Construction
Contractor
PNRC No. 17 Control
of Env Nuisance from
Construction Sites
Appendix A
A-6
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
6.6.4
WM.4
Dump trucks shall be fitted with covered box type
dump bed and such dump trucks shall comply with
the particular specification listed in Part B of Annex
2 to Appendix C of ETWB TC(W) No. 19/2005
To ensure C&D Material will be
delivered to the appropriate
designated outlets and dump trucks
to minimise potential nuisance
during transportation of waste
All works
areas
Construction
Contractor
Part B of Annex 2 to
Appendix C of ETWB
TC(W) No. 19/2005
6.6.5
WM.5
Establishment of a Trip Ticket System to monitor the
disposal of public fill and solid wastes at public filling
facilities and landfills, and to control fly-tipping
To monitor the disposal of public
fill and solid wastes at public filling
facilities and landfills, and to
control fly-tipping
Off-site
Construction
Contractor
DevB TC(W) No.
6/2010 and Waste
Disposal (Charges for
Disposal of Constr.
Waste) Reg
6.6.6
WM.6
General refuse should be stored in enclosed bins or
compaction units separate from C&D material. A
reputable waste collector should be employed by
the construction contractor to remove general
refuse from the Site, separately from C&D materials
To separate general refuses from
C&D material and ensure proper
disposal
All works
areas
Construction
Contractor
Good Site Practice
6.6.7
WM.7
1. The Contractor shall observe and comply with
the WDO and its subsidiary regulations
2. The Contractor shall submit to the Engineer a
WMP with appropriate mitigation measures
including allocation of an area for waste
segregation and shall ensure that day-to-day
site operations comply with the approved WMP
3. The Contractor shall minimise the generation of
waste from his work. Avoidance and
minimisation of waste can be achieved through
changing or improving design and practices,
careful planning and good site management
4. The Contractor shall ensure that different types
of wastes are segregated on-site and stored in
different containers, skips or stockpiles to
facilitate reuse/recycling of waste and, as the
last resort, disposal at different outlets
To further minimise the
environmental impacts related to
waste arising from the Project
All works
areas
Construction
Contractor
Good Site Practice
Waste Disposal
(Chemical Waste)
(General) Regulation
Appendix A
A-7
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
5. The reuse and recycling of waste shall be
practised as far as possible. The recycled
materials shall include paper/cardboard, timber
and metal, etc.
6. The Contractor shall ensure that C&D materials
are sorted into public fill (inert portion) and C&D
waste (non-inert portion). Public fill, which
comprises soil, rock, concrete, brick, cement
plaster/mortar, inert building debris, aggregates
and asphalt, shall be reused in earth filling,
reclamation or site formation works. C&D waste,
which comprises metal, timber, paper, glass, junk
and general refuse, shall be reused, recycled or,
as the last resort, disposed of at landfill
7. The Contractor shall record the amount of
waste generated, recycled and disposed of
8. The Contractor shall use a trip ticket system for
the disposal of C&D materials to any designated
PFRFs and/or landfill
9. Training shall be provided for workers about the
concepts of site cleanliness and appropriate
waste management procedures, including waste
reduction, reuse and recycling
10. The Contractor shall not permit any sewage,
wastewater or effluent containing sand,
cement, silt or any other suspended or
dissolved material to flow from the Site onto
any adjoining land or allow any waste matter
that is not part of the final product from waste
processing plants to be deposited anywhere
within the Site or onto any adjoining land. He
shall arrange removal of such matter from the
site in a proper manner to the satisfaction of
the Engineer
Appendix A
A-8
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
11. The Contractor shall observe and comply with
the Waste Disposal (Chemical Waste) (General)
Regulation
6.6.8
WM.8
1. Construction material, stockpiles, chemical and
waste storage/recycling facilities should be
immediately moved to secured area
2. Construction material, stockpiles and waste
storage/recycling facilities should be covered by
an impermeable sheeting, if necessary
3. Intercepting channels will be provided at the
edge of the excavated area to prevent storm
runoff from washing across the exposed surface
To adopt additional control
measures when inclement weather
(e.g. heavy rain, typhoon, etc.) is
forecast
All works
areas
Construction
Contractor
Good Site Practice
6.6.9
WM.9
Visitors will be encouraged to bring their own
reusable water bottles and food containers, rather
than single-use containers, and free drinking water
for visitors will be provided at the MPEC. No waste
receptacles are provided within MPNR and visitors
will be encouraged to take their waste home with
them
To minimise the amount of waste
generated by visitors to MPNR
Throughout
MPNR
WWF
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
Table
6-3
WM.10
Inert C&D Material: PFRF at Tuen Mun Area 38
To ensure proper management and
treatment of inert C&D material
Off-site
Construction
Contractor
Table
6-3
WM.11
C&D Waste (non-inert): Segregation + recycling by
local recyclers / residual waste to NENT Landfill
To ensure proper management and
treatment of C&D waste (non-inert)
Off-site
Construction
Contractor
Table
6-3
WM.12
C&D Waste (vegetation): Vegetation shall be
composted on-site
To ensure proper management and
treatment of C&D waste (veg)
On-site
WWF
Table
6-3
WM.13
General Refuse: Segregation + off-site recycling by
local recyclers/residual waste to NWNT RTS
To ensure proper management and
treatment of general refuse
Off-site
Construction
Contractor
ECOLOGY
7.9.3
E.1
The three project elements will be
assembled/constructed over a two-month period
between mid-April and mid-October
To avoid impacts on the high
number of waterbirds and wetland-
dependent species present in the
dry season
All works
areas
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
Appendix A
A-9
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
7.9.4
E.2
Adequate site checks in the works area and in the
vicinity of the footprint of all project elements will
be conducted by a suitably qualified ecologist prior
to commencement of works to search for
substantive usage of the habitat by flora and/or
fauna of conservation concern, e.g. the presence of
an otter holt
To avoid impacts on mammals, in
particular Eurasian Otter
All works
areas
ET
local community
7.9.6
E.3
Install a 2m-high solid, opaque screen around works
areas
To mitigate disturbance to species
using adjacent habitats
All works
areas
Construction
Contractor
7.9.6
E.4
Provide screen planting using native bamboo
species Bambusa tuldoides (青稈竹, 花眉) to the
access path to the new Tower Hides to reduce
disturbance during the construction and operational
phase (see also LV.6, below)
To mitigate disturbance to species
using adjacent habitats
Access to
THs
Construction
Contractor
+WWF
7.9.7
E.5
All construction activity for TH2 and its associated
access path, including the passage of construction
vehicles, will cease two hours before sunset, this
means 4pm in the wet season construction period
To avoid impacts on nocturnal
roost sites and associated pre-roost
gatherings of Collared Crow in the
vicinity of Pond 20
TH2
Construction
Contractor
7.9.8
E.6
Ahead of construction, ET checks will be conducted
during the breeding season. These checks should be
carried out two weeks prior to construction
commencing and the day before. Should any egretry
be discovered in the vicinity of works areas, the
need for mitigation measures shall be assessed in
consultation with AFCD
To check for the presence of
breeding ardeids within 500m of
the footprint of project elements
All works
areas
ET
7.9.9
E.7
All construction activity for footpath and TH3 will
cease one hour before sunset
To prevent disturbance to nearby
ardeid pre-roost and roost activities
TH3 and
footpath
Construction
Contractor
7.9.11
E.8
Adequate site checks along haul roads and in the
works area and in the immediate vicinity should be
conducted prior to the commencement of works at
TH2 and TH3
To detect substantive use of
adjacent habitat by species of
conservation concern. If roosts or
breeding species are found,
TH2 and
TH3
ET
Appendix A
A-10
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
appropriate measures should be
taken to avoid adverse impact,
including adjustments to the timing
of works
7.9.12
E.9
Prior to any tree pruning or felling works, a careful
check should be conducted by an experienced
ecologist to ensure that bats or active bird nests are
not present
To avoid disturbance to bat and
bird species nesting in trees
All works
areas
ET
7.9.14
E.10
Desilting channels at gei wai 19, reconnecting
gei wai 19a with gei wai 19b, and merging the
six sub-ponds (20a to 20f) of gei wai 20 (for
TH2); and enhancement of gei wai 8a through
reprofiling and connection of gei wai 8a with
gei wai 7 (forTH3).
To provide habitat
enhancement to offset the loss
of very small areas of gei wai
bund and pond bund due to
construction of the new TH2,
TH3 and boardwalk path
TH2 and
TH3
Construction
Contractor
+WWF
FISHERIES
8.3.19
F.1
Contingency plan when construction works are in
the vicinity of commercial fish ponds:
1. Identification of potential emergency situations
consult with WWF and owners of the ponds.
2. Emergency response team
3. Emergency response procedures
4. List of emergency telephone hotlines
5. Location and type of emergency equipment
6. Training plan and testing for effectiveness
To prevent perforated liner and
damaged/destabilized pond bunds
In the
vicinity of
commercial
fish ponds
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
LANDSCAPE AND VISUAL
9.7.4
LV.1
CM1: Construction lighting control: to ensure no
night time lighting at all works areas.
To restrict and reduce light
pollution during night time.
All works
areas
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
9.7.4
LV.2
CM2: All existing trees and vegetation outside the
works footprints shall be properly preserved and
To protect the landscape quality of
the existing trees and vegetation.
All works
areas
Construction
Contractor
DevB TCW No.
7/2015
Appendix A
A-11
Note: * D = Deign Stage | C = Construction Stage | O = Operation Stage
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
EIA
REPORT
REF.
EM&A
ACTION
REF.
RECOMMENDED MITIGATION MEASURES
OBJECTIVES OF THE MEASURE AND
MAIN CONCERNS TO ADDRESS
LOCATION
OF
MEASURE
WHO TO
IMPLEMENT
MEASURE?
WHEN TO
IMPLEMENT
MEASURE?*
STANDARD OR
REQUIREMENTS FOR
MEASURE TO
ACHIEVE?
D
C
O
protected.
9.7.4
LV.3
CM3: All the construction materials shall be
properly stored at the designated locations within
the works areas.
To ensure proper storage of
construction materials and enhance
tidiness on site.
All works
areas
Construction
Contractor
Good Site Practice
9.7.4
LV.4
CM4: Erection of screen hoarding for TH2 and TH3
(where appropriate, hoardings with surface
treatment/ colour suitable to the rural context shall
be used).
To minimise potential impact on
landscape / visual quality during
construction of TH2 and TH3.
All works
areas
Construction
Contractor
Additional measure
for minimisation of
detrimental impacts
to wildlife and the
local community
9.7.5
LV.5
OM1: Suitable/responsive design of the proposed
Boardwalks and Bird-watching Hides
To enhance overall landscape /
visual quality by fitting in with the
surrounding natural landscapes.
TH2 and
TH3, New
Boardwalks
Design
Consultant/
WWF
9.7.5
LV.6
OM2: Provide screen planting using native bamboo
species Bambusa tuldoides (青稈竹, 花眉) to the
access to the new Tower Hides to soften the
appearance of the hard elements of the Project.
To enhance overall landscape /
visual quality by fitting in with the
surrounding natural landscapes.
Access to
THs
Construction
Contractor
Appendix B
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Appendix B Sample Template for Interim Notification
Appendix B
B-1
EIA REPORT VOLUME IV: EM&A MANUAL
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D01
20 October 2021
Incident Report on Action Level or Limit Level Non-compliance
To ______________________________
Attention ______________________________
Fax No. ______________________________
Project
Mai Po Nature Reserve Infrastructure Upgrade Project
EP No.
Date and Time
Monitoring
Location
Parameter
Action & Limit
Levels
Measured Level
Reason for Non-
compliance
Action to be
Taken
Remarks
Prepared by _______________________ Signature _______________________
Designation _______________________ Date _______________________
SMEC is recognised for providing technical excellence
and consultancy expertise in urban, infrastructure and
management advisory. From concept to completion, our
core service offering covers the life-cycle of a project
and maximises value to our clients and communities.
We align global expertise with local knowledge and
state-of-the-art processes and systems to deliver
innovative solutions to a range of industry sectors.