Executive Summary
EIA REPORT VOLUME V: EXECUTIVE SUMMARY
Mai Po Nature Reserve Infrastructure Upgrade Project
Prepared for World Wide Fund For Nature Hong Kong
SMEC Internal Ref. 7076457 D05
20 October 2021
4.1.4 During construction, it is estimated that a total of 280.3 tonnes of waste will be generated, of
which up to 261.3 tonnes could potentially be treated /recycled/recovered, which is a 93% waste
diversion rate from landfill. This waste comprises inert C&D material, C&D waste and general
refuse. Chemical waste will not be generated as WWF will mandate in all contract documents that
there shall be no maintenance or repair of vehicles, plant or equipment on site. Provided that the
recommended mitigation measures are followed, there should be no adverse waste impact from
the handling, transportation or disposal of inert C&D material, C&D waste or general waste during
construction. During the operation, there will be no waste of any type generated within the
Project Site. No waste receptacles are provided within MPNR and visitors will be encouraged to
take their waste home with them. Overall, therefore, no adverse waste management implications
are anticipated during the construction or operational stages of the Project.
4.1.5 The current ecological conditions and potential ecological impacts of the Project have been
assessed. Based on this review, measures to avoid and minimise ecological impacts have been
recommended. With these measures in place and having considered the relevant assessment
criteria listed in the EIAO-TM (i.e. effects on health of biota, the magnitude, geographic extent,
duration and frequency of adverse impacts, the likely community size affected, the degree to
which the adverse impacts are irreversible, the ecological context, the international or regional
importance of the species or habitats and both the likelihood and degree of uncertainty of
adverse environmental impacts), it is considered that all significant ecological impacts from the
Project will be addressed and there will be no unacceptable residual impacts.
4.1.6 There are no commercial fishponds in the Project Area and so there will be no direct impact on
fisheries within the Project Area during construction. Adjacent to the Project Site are commercial
fisheries. However, with the mitigation measures proposed in this report to control dust, water
pollution and waste generation, indirect impacts on fisheries due to construction activities will be
insignificant. The two new tower hides will not be provided with toilets or washrooms and so no
wastewater will be generated during the operation stage. Runoff from the roof of the tower hides
and from the footpaths will not be contaminated. As such, there will be no point or non-point
pollution sources due to the operation of the Project and therefore no impact to the water
systems – fish ponds, gei wai or Deep Bay – or associated sensitive receivers within the Project
Site or within the Assessment Area for fisheries impact. Overall, therefore, no adverse fisheries
impacts are anticipated during the construction or operational stages of the Project.
4.1.7 With full implementation of the recommended mitigation measures, the overall landscape and
visual impacts resulting from the construction and operation of Project are all considered to be
acceptable. Some of the receivers may experience potentially beneficial impacts from the
upgrading of the existing paved footpath to the new wooden boardwalks, which are more
aesthetically compatible with the surrounding natural landscapes.
4.1.8 Overall, the EIA Study has concluded that with the implementation of recommended mitigation
measures, no adverse environmental (air quality, noise, water quality, waste), ecological,
fisheries or landscape and visual impacts are anticipated during the construction or operation
stages of the Project.
4.1.9 The demolition and rebuild of Peter Scott Field Study Centre (PSFSC) near MPNR will have been
completed by March 2022 whereas the construction of this Project will commence at end-April
2022. As such, the demolition and rebuild of PSFSC will not be carried out concurrently with this
Project. There are also no other concurrent projects near MPNR. Thus, cumulative
environmental impacts for this Project is not anticipated. As shown in the Project Programme in
Figure 3, there are also no concurrent works related to the MPNR Management Plan 2019-2024
and so no cumulative environmental impacts.
4.1.10 A comprehensive EM&A programme has been recommended, covering baseline, impact and
post-construction monitoring of various parameters, to ensure that there are no unacceptable
impacts and to demonstrate compliance with the findings of the EIA Study.