The
existing OCGTs (i.e. GT2, GT3, GT4 and GT6) and CCGT (i.e. GT57) within the GT
Compound have been in operation for more than 30 years since 1989. The aging units, which are approaching the
end of their service life, are becoming less efficient in their operation and
requiring more frequent inspections and maintenance. The control system of the existing units is
also obsolete and the equipment suppliers do not have the necessary spare parts
or provide technical support that enable the continuous operation of these
existing units. Hence, there is a need
to decommission and demolish these existing units, and to construct and
commission new units progressively in the effort to replace the function of the
existing units in maintaining the peak-lopping and emergency operation
requirements, so as to ensure the continuous operation of the LPS and its
provision of stable and reliable electricity supply in Hong Kong.
The
Project aims to decommission and demolish the existing GT2, GT3, GT4, GT57 and
GT6 which are approaching the end of their service life, and subsequently
construct and operate up to four new OCGTs (i.e. GT8, GT9, GT10 and GT11) as a
replacement to the abovementioned existing units. Upon the progressive retirement of the
existing units, the new OCGTs serve to take over the function of these existing
units in providing additional power generation during peak-lopping and
maintaining back-up power supply in case of emergency situations for the
continuous operation of the LPS. The
four new OCGTs would have a capacity of up to 130MW each, with a total power
generation capacity of up to 520MW.
The
Project is classified as a Designated Project under the EIAO (Cap. 499) as a
result of the following elements:
§ Demolition of
four existing OCGTs and one existing CCGT at LPS (Schedule 2, Part II, Item 4 A
public utility --- electricity power plant); and
§ Installation
of up to four new OCGTs at LPS (Schedule 2, Part I, Item D.1 Public utility
electricity power plant).
The
operation of the aging units is increasingly less efficient and could
potentially lead to higher air emissions.
New OCGTs are much more efficient and capable of attaining a more
stringent emission standards and thus producing lower air emissions during
operation, in particular nitrogen oxides (NOx), when generating the
same amount of power as the existing OCGTs.
Therefore, the Project is beneficial from an environmental perspective
and can be considered as part of the ongoing effort of HK Electric to further
reduce the overall air emissions from the operation of LPS and contribute to
the long-term air quality improvement in Hong Kong.
If
the Project does not proceed, HK Electric will slowly lose the capacity of
additional power generation to cope with the electricity demand during
peak-lopping and maintaining power supply in case of emergencies upon the
progressive retirement of the existing units from 2022 onwards. Such capacity will be completely lost upon
complete retirement and decommissioning of these existing units. This would hamper the normal operation of LPS
significantly and put HK Electric’s stable and reliable supply of electricity
at risk.
With
the Project in place, HK Electric would enable the decommissioning of the
existing units and construction of the new OCGTs progressively (i.e.
decommissioning of at least one existing unit before commissioning of one new
OCGT), allowing a smooth transition of the OCGT reprovision programme and at
the same time maintaining the necessary capacity for coping with the additional
power demand during peak-lopping and emergency operation. Upon putting into operation, the new OCGTs
can be in service for years to come and are integral to the future LPS
operation in supplying stable and reliable electricity in Hong Kong.
The
existing GT2, GT3, GT4, GT57 and GT6 have been in operation since 1989 and are
situated in the GT Compound of the LPS at the western edge of Lamma Island (see
Figure 2.1a). The GT Compound has been occupied by these
existing units and their associated buildings and facilities ever since the
commencement of LPS operation. GT57 was
originally two separate OCGTs (i.e. GT5 and GT7) that were converted into a
CCGT with power generation capacity of 345MW in 2002. GT57 was subsequently converted to a gas-fired
unit in 2008. Having a power generation
capacity of 125MW each, GT2, GT3, GT4 and GT6, together with GT57, have a total
power generation capacity of 845MW. The
new OCGTs will be constructed within the GT Compound where the existing GT2,
GT3, GT4, GT57 and GT6 are located. This
has been identified as the preferred development option which is further
discussed in Section 2.4 below.
A
number of different development options have been considered having regard to
the upcoming retirement and decommissioning of the existing OCGTs and CCGT
within the GT Compound. Options of power
generation for peak-lopping and emergency operations, and site selection for
the new OCGTs have been considered.
A
number of options have been explored to cope with the electricity demand during
peak-lopping and emergency operations upon progressive retirement and
decommissioning of the aforementioned existing units. The options considered include:
§ Construction
of new CCGTs;
§ Construction
of new OCGTs;
§ Extending
services of existing OCGTs;
§ Importing
power supply from Mainland China; and
§ Use
of renewable energy.
The
considerations of the above options are discussed in the following
sub-sections.
CCGT
is equipped with a steam generator to recover heat from exhaust gas of the gas
turbine and is thus more efficient than an OCGT in power generation. Due to CCGT’s higher efficiency, fuel
consumption and associated air emissions arising from the operation of a CCGT
would be lower than that from the operation of an OCGT. However, CCGT does not have fast start-up
capability which is the key to providing swift electricity supply during
peak-lopping and emergency situations.
Therefore, construction and operation of new CCGTs is considered not
suitable and thus is not preferred.
OCGT
consists of a single compressor/ gas turbine assembly that is connected to an
electricity generator via a shaft. OCGT
has the major advantage of fast start-up capability and can generate
electricity within a relatively short time.
It is less efficient than a CCGT in power generation as it does not have
a steam generator to recover heat from the exhaust gas of the gas turbine. Due to OCGT’s relatively low efficiency, fuel
consumption and associated air emissions during the operation of an OCGT would
be higher as compared with that of a CCGT.
However,
given their fast start-up capability, OCGTs are capable of serving the
objective of providing swift electricity supply during peak-lopping and
emergency situations. As the OCGTs will
only be needed during peak-lopping and emergency situations and not used as
base load for electricity generation, the operation of the OCGTs is only
intermittent and the associated emissions are only short-term. New OCGTs can also achieve more stringent
emission standards as compared with the existing OCGTs. Hence, construction and operation of new
OCGTs is considered more favourable from an operational and fit-for-purpose
perspective.
The
existing units have been in operation since 1989. Most of the critical components of the power
block facilities including the gas turbine casings, hot gas path components and
generators would require replacement in order to extend the services of these
existing units. Besides the need of
replacement of different components of the existing units, substantial
refurbishment works will also be required for the steel structures, gas turbine
inlet air and exhaust gas ductworks. The
control system of the existing units is also obsolete and the equipment
suppliers do not have the necessary spare parts or provide technical support
that enable the continuous operation of the existing units. Therefore, replacement of components and
refurbishment works to extend services of the existing units are considered not
technically viable or cost-effective and hence not the long-term solution for
the operation of LPS. Hence, such option
is considered less favourable.
In
addition to generating power locally, importing power from the Mainland China
for the purpose of peak-lopping and emergency operations has also been explored
with the following considerations:
§ Infrastructure
– there is currently lack of infrastructure for connecting to the power grid in
Mainland China. There is a long lead
time to build the necessary infrastructure and will not meet the retirement
schedule of the existing units (to be retired and decommissioned tentatively
starting from 2022);
§ Reliability and control issue
– the HKSAR government do not have direct control and regulation of the
electricity imported from Mainland China.
Reliable electricity supply during peak-lopping or emergency operations
cannot be guaranteed if HK Electric rely on power supply import from Mainland
China;
§ Displacement of pollutants
– local pollutants from power generation will be displaced to Mainland China,
where the HKSAR government or HK Electric have no control over the emission
performance.
In
view of the above, it is considered that local generation would provide more
certainty in terms of maintaining electricity supply reliability, especially
during peak-lopping and emergency operations, as well as improving
environmental performance. Hence,
importing power from Mainland China is not preferred.
HK
Electric has made continual effort to explore the use of renewable energy for
electricity generation. For example, HK
Electric is planning to build an offshore wind farm in Hong Kong waters to be
located around 4km southwest of Lamma Island.
However, renewable energy cannot supply electricity on demand in order
to serve the purpose of peak-lopping or emergency operations due to its
intermittent nature and is thus not a viable option.
Based
on the above discussion, the construction and operation of new OCGTs is
considered the most practicable and preferred option to pursue as this involves
essentially like-to-like replacement, is fit for purpose, environmentally
beneficial and technically the most practicable. Other options would present impracticality
and uncertainties, or may not tie in with the retirement schedule of the
existing units.
The
existing GT Compound, L13 area and L3 Main Station Building within the LPS and
Lamma Extension (LMX) have been identified as potential sites for accommodating
the new OCGTs. The locations of the
existing GT Compound, L13 area and L3 Main Station Building are shown in Figure 2.2. These three potential sites have been
carefully compared based on a number of factors. Consideration of these factors for site
selection are detailed in Table 2.1.
Table 2.1 Comparison of the Identified Potential Sites for New OCGTs
Considering Factors |
GT Compound |
L13 Area |
L3 Main Station Building (a) |
Site Condition |
The GT
Compound area can be made available after demolition of the existing OCGTs
and CCGT. The existing foundation
piles and reinforced concrete structures could be reused for the construction
of the new OCGTs. |
The L13
Area is currently vacated for the future development of the proposed
L13. The layout of the proposed L13
will be affected and needs to be redesigned to accommodate the new OCGTs
within the L13 Area. The construction
of the new OCGTs could interface with that of the proposed L13 and
potentially pose constraints on the design and construction of the proposed L13. Foundations
and concrete structures for the new OCGTs need to be constructed. |
Part of
the L3 Main Station Building structures could be reused for the installation
of the new OCGTs. The
entire coal-fired boiler and power train and associated auxiliary equipment
inside the L3 Main Station Building need to be demolished to create space for
installation of the new OCGTs, which is a costly construction option and
requires much longer construction period.
The
proximity of the L3 Main Station Building to the existing coal conveyor and
electrostatic precipitators would restrict the layout of the new OCGTs. |
Space Adequacy |
With the removal of the existing OCGTs
and CCGT, there would be sufficient space for constructing the new OCGTs,
cable trenches and associated facilities. |
L13 Area is currently vacated and have
sufficient space for the Project.
However, the installation of the new OCGTs and associated facilities
would take up part of the L13 Area that would otherwise be available for the
proposed L13 and thus will hinder the development of the proposed L13 in the
future. |
The L3 Main Station Building is
congested with a number of existing equipment, some of which may need to be
demolished and removed to make space for the installation of the new OCGTs
and associated facilities. This would
pose challenges from a technical and engineering perspective and would also
prolong the construction period of the Project. |
Chimneys |
With minor repair and refurbishment
works, existing chimneys serving the existing OCGTs and CCGT can be reused
for the new OCGTs. |
The
chimney to be constructed for the proposed L13 could be used to serve the new
OCGTs. However, the chimney will need
to be re-designed to accommodate the new flues within the chimney. With the
use of the same chimney, there could be interfacing issue between the
development of the proposed L13 and the new OCGTs. |
Existing
chimney used to serve L3 cannot be reused for the new OCGTs and needs to be
removed which involve significant demolition works. Construction of a new chimney is required
for the new OCGTs. |
Foundation and Civil Works |
The
construction of the Project only involves minor civil works as the existing
foundation piles and reinforced concrete structures could be reused. Foundation works for the new OCGTs are not required. |
No
existing foundation piles or reinforced concrete structures are present. The construction of the Project requires
foundation works which involve considerable excavation and piling works. Major aboveground civil works are also
required. |
Existing
foundation piles and reinforced concrete structures cannot be reused. Significant demolition works followed by
excavation, piling and civil works are required for the construction of the
Project. |
Environmental Consideration |
No
foundation works and only minor civil works are required, resulting in low
generation of waste materials. Other
potential environmental impacts (e.g. air quality and noise) can also be
minimised. |
Significant
foundation works and civil works are required, resulting in high generation
of waste materials. The associated
excavation and piling works may also pose implications on other environmental
aspects (e.g. air quality and noise) |
Significant
demolition, foundation and civil works are required, resulting in higher
generation of waste materials. The
associated demolition, excavation and piling works may also pose implications
on other environmental aspects (e.g. air quality and noise). Detailed land contamination assessment
within the area may also be required. |
Notes: (a) Unit L3
was decommissioned in 2018. |
The
site comparison assessment as shown in Table 2.1 revealed that it is more
desirable to develop the new OCGTs within the GT Compound where the existing
OCGTs and CCGT to be removed are located, having considered various factors
including site condition, space adequacy, construction feasibility and
complexity, and environmental impacts.
The development and construction of the new OCGTs in L13 Area and L3
Main Station Building would increase the scale and scope of the Project, are
technically more challenging and complex in construction, require a longer
programme and incur higher costs. In
terms of environmental impact, development of the new OCGTs in L13 Area and L3
Main Station Building would require considerable excavation and piling works
which have the potential to generate significant amount of construction waste
and also cause other environmental impacts such as impacts on air quality and
noise. Development of the new OCGTs in
L3 Main Station Building may even require extensive demolition works to create
space, resulting in additional environmental impacts. On the other hand, development of the new
OCGTs within the existing GT Compound can minimise waste generation and other
environmental impacts as the foundation and reinforced concrete structures
after the removal of the existing units can be reused for the installation of
the new OCGTs. Therefore, it is
considered preferable to develop the new OCGTs within the GT Compound.
The
Project involves the decommissioning and demolition of the existing GT2, GT3,
GT4, GT57 and GT6 within the GT Compound of LPS, and the construction and
operation of four new OCGTs (i.e. GT8, GT9, GT10 and GT11) within the GT
Compound, in order to maintain the peak-lopping and emergency operation
requirements essential for the continuous operation of LPS in the future. The Project site includes the GT Compound as
shown in Figure 2.1a / Figure 2.1b. The existing units will be decommissioned and
demolished sequentially, with one new OCGT to be constructed upon the removal
of at least one existing unit. The locations
of the existing units and the proposed new units within the Project site are
shown in Figure 2.1a and Figure 2.1b,
respectively. As part of the Project,
some modifications to the existing buildings and facilities and construction of
new cable trenches within the GT Compound will be carried out to support the
future operation of the new OCGTs.
Each
of the four new OCGTs essentially consists of a gas turbine and a generator,
and will be operated by firing ultra-low sulphur diesel (ULSD) to produce
electricity under peak loads and emergency situations. Fresh air is drawn into the compressor where
it is compressed for mixing with the fuel (i.e. ULSD) and burning in the
combustion chamber. The high temperature
gas generated in the combustion chamber is then passed through the turbine
blades, which in turn rotate the generator rotor to generate electricity. The generation capacity of each new OCGT is
up to 130MW, with a total generation capacity of up to 520MW from four new
OCGTs. The exhaust gas from GT8, GT9,
GT10 and GT11 will be discharged via the existing chimneys currently serving
GT2, GT5, GT6 and GT7. The existing
chimneys for GT3 and GT4 will be retained but not utilised under this
Project. The new OCGTs will be
air-cooled with no requirement for cooling water intake or discharge during
operation.
A
BSGT with capacity of 2.2MW is currently installed near the west boundary of
the GT Compound and serves to provide start up power for the OCGTs in case of
rare black out situations. The existing
BSGT is also nearing the end of its service life and will be replaced by a new
BSGT of similar capacity as the existing BSGT as part of this Project.
A
new BESS with an estimated output of around 3MW will be erected to the south of
the BSGT. The BESS is of modular type
and will be accommodated in a container in which all equipment including
inverter, transformer, air conditioner, fire services, lighting etc. are
equipped. Similar to the BSGT, the BESS
also serves to provide start up power for the OCGTs in case of rare black out
situations. During black out situations,
the BESS will be put into operation first, while BSGT acts as the back up to
the BESS.
The
existing GT57 Auxiliary Building (GTAB) will be converted to a new 132kV
Switching Station for the operation of the new OCGTs. All existing equipment inside the GTAB,
including the GT57 steam turbine, generator, condenser and other auxiliary
equipment as well as the existing Turbo Block structure will be removed and
demolished to make space for converting the GTAB into a new 132kV Switching
Station. The new 132kV Switching Station
will accommodate the gas insulated switchgear, associated electrical,
instrumentation and control equipment, as well as a battery charger system. A new staircase and lift for the new 132kV
Switching Station and new cable trenches for 132kV cables connecting the new
OCGTs, BSGT and BESS to the new 132kV Switching Station will also be
constructed.
The
existing GT2, GT3, GT4, GT57 and GT6 as well as their auxiliaries (e.g.
generator coolers, transformers) will be decommissioned and demolished to make
space for the construction of the new OCGTs.
The existing BSGT will also be demolished and replaced with a new
BSGT. The new BESS will also be
installed south of the BSGT. Typical
construction equipment such as electric breakers, flame cutting and powered
mechanical hand tools will be used during demolition works. All major equipment and piping associated
with the new OCGTs and BSGT will be fully assembled off-site as far as
practicable and then installed on site such that construction works on site can
be minimised. Mobile cranes will be
deployed for the removal and installation of heavy equipment such as
generators, gas turbines and tube bundles.
The new OCGTs and BSGT will have similar footprint as the existing ones
and as such, the existing foundation piles and reinforced concrete structure
will be reused to support the new OCGTs and BSGT as far as practicable. It is expected that foundation works for the
new OCGTs and BSGT are not required and the civil works associated with the
construction of the new OCGTs and BSGT are minimal. The existing chimneys to be retained for use
by the new OCGTs will undergo necessary refurbishment works.
The
existing GTAB will be converted to a new 132kV Switching Station. All equipment inside the existing GTAB, including
the lube oil tank, chemical dosing pit, steam turbine, generator, condenser,
cooling water pump, etc., will be removed and demolished using typical
equipment such as grinder, flame cutting and powered mechanical hand tools. The demolition and removal of the existing
Turbo Block Structure inside the GTAB will require minor excavation down to
about 2.6m below ground over an area of about 200m2, and such
demolition and removal works will use typical equipment such as excavators,
mobile cranes, electric breakers and other powered mechanical hand tools. The installation of gas insulated switchgear,
electrical and control panels and other associated equipment inside the new
132kV Switching Station will involve general lifting operation and manual installation,
which will be carried out by typical equipment such as overhead crane and
powered mechanical hand tools.
A
new staircase and lift will be constructed at the immediate east of the GTAB,
which is currently occupied by the circulating water pipe room to be demolished
under this Project. The construction of
the new lift pit will require excavation down to 5m below ground. In addition, new cable trenches will be
constructed to house the new 132kV cables connecting the new OCGTs, BSGT and
BESS to the new 132kV Switching Station.
Minor excavation down to about 1.8m below ground will be required for
the construction of new cable trenches, where the excavated materials will be
used for backfilling as far as practicable after cable laying. Typical equipment such as excavators, mobile
cranes, welding machines and other powered mechanical hand tools will be used
during excavation and backfilling works, cable laying and construction of the
new staircase and lift.
As
part of the Project, the existing lube oil storage tank near GT5 and the
miscellaneous storage shed south of the existing BSGT will be demolished. Typical equipment used for removal of these
other structures include grinder, flame cutting and other powered mechanical
hand tools.
The
new OCGTs will commence operation in phases upon completion of construction and
testing and commissioning. The OCGTs
will be operated under peak-lopping and emergency situations. The new BESS and BSGT will also be put into
service upon completion of construction and testing and commissioning, but they
will only be operated to supply the required power to start up the new OCGTs in
case of rare black-out situation. Under
such rare black-out situation, the new BESS, which does not involve air
emissions during its operation, will be used first instead of the BSGT. Therefore, the operation of the new BSGT is
considered extremely rare.
Both
the new OCGTs and BSGT will be fuelled by ULSD and stack emissions during their
operation will comply with the requirements recommended in the Guidance Note on the Best Practicable Means
for Electricity Works (BPM7/1(2018)), and those to be stipulated in the SP
licence issued under the Air Pollution
Control Ordinance (APCO). The power
generated by the new OCGTs, BSGT and BESS will be transmitted via the new 132kV
cables to the 132kV Switching Station, and eventually to HK Electric’s power
grid.
HK
Electric proposes to decommission and demolish the existing GT2, GT3, GT4, GT57
and GT6, and to construct and commission the new GT8, GT9, GT10 and GT11 within
the GT Compound successively between 2022 and 2028. The tentative implementation programme is
provided in Table 2.2.
Table 2.2 Tentative Implementation Programme of the Project
The
Project is located within the existing LPS site. The following existing, committed or planned
projects in the vicinity of the Project site may potentially interface with the
demolition, construction and operation of this Project:
§ 1,800MW Gas-fired Power Station at
Lamma Extension (AEIAR-010/1999): This project includes the
construction and operation of six new gas-fired CCGT units at the Lamma
Extension. L9 and L10 have been
constructed and are currently under operation.
L11 and L12 are currently under construction and are scheduled for
commercial operation in 2022 and 2023 respectively. L13 is scheduled for commercial operation
after 2023.
§ Hong Kong Offshore LNG Terminal
(AEIAR-218/2018):
This project involves the construction and operation of an offshore
liquefied natural gas (LNG) terminal that is to be located in the southern
waters of Hong Kong, to the east of the Soko Islands. The offshore LNG terminal will supply natural
gas to the gas receiving stations at the Black Point Power Station (BPPS) and
the LPS via two subsea pipelines. The
construction of the project commenced in the third quarter of 2020 and is
expected to last for about 2 years.
§ Improvement Dredging for Lamma
Power Station Navigation Channel (AEIAR-212/2017): This project involves
improvement dredging of the Channel to the west of LPS during construction
phase, and subsequent recurrent improvement dredging every 4 to 10 years during
operation phase. The construction of the
Project commenced in February 2020 for completion tentatively by end of 2021.
§ Development of a 100MW Offshore
Wind Farm in Hong Kong (AEIAR-152/2010): The project involves the development of an
offshore wind farm located in the waters between Lamma Island and Cheung
Chau. The offshore wind farm will
produce around 100MW of electricity, which will be supplied directly to the HK
Electric grid network. The
implementation programme of this project is under review and not yet available
at this stage.
§ Lamma Power Station – Unit L2 Flue Gas Desulphurization Plant Retrofit Project (DIR-153/2007): The project involves retrofit of Flue Gas Desulphuization (FGD) plant to the existing unit L2 for reducing sulphur dioxide emissions. The project is anticipated to retire along the tentative retirement of unit L2 in late 2022.
§ Lamma Power Station Units
L4 & L5 Flue Gas Desulphurization Plant Retrofit Project (AEIAR-098/2006): The project involves retrofit of FGD plant to
the existing units L4 and L5 for reducing sulphur dioxide emissions and is
currently under operation phase. The
project is anticipated to retire along the tentative retirement of units L4 and
L5 in 2022-2023.
§ Renewable Energy by a Wind Turbine
System on Lamma Island (AEIAR-080/2004): The project
involves the construction and operation of a 800kW wind turbine at Tai Ling
Tsuen on Lamma Island. The construction
of the project commenced in February 2005 and lasted for 12 months. The project has been put into operation since
February 2006
The
above concurrent projects may pose cumulative impact with the demolition,
construction and/or operation of the Project.
The cumulative impacts from the above concurrent projects are addressed
in the relevant technical assessments in this EIA as appropriate.
In
addition, Conversion of Two Existing Gas
Turbines (GT5 & GT7) into a Combined Cycle Unit (DIR-037/2000) is
currently active and in operation phase.
With GT57 to be decommissioned and demolished as part of this Project,
DIR-037/2000 will not interface with the demolition, construction or operation
of this Project and thus would not pose any cumulative impact.
As
part of the EIA study, ERM, on behalf of HK Electric has reached out to the
local communities in Lamma Island via three community leaders in Lamma, namely
Mr Chan Lin-wai, MH, Chairman of the Lamma Island (North) Rural Committee, Mr
Chow Yuk-tong, SBS, MH, Chairman of the Lamma Island (South) Rural Committee,
and Ms Lau Shun-ting, Islands District Council Member, by providing
them briefing notes of the Project by registered mail on 21 July 2021 in order
to seek their views and opinions on the Project and the associated
environmental impact. Face-to-face
meetings were avoided due to the current COVID-19 pandemic. No feedback or opinions have been obtained
from the stakeholders concerned during the course of the EIA study.