3.             Air Quality

3.1         Introduction

This Section presents the potential air quality impacts associated with the demolition/ construction and operation phases of the Project.

3.2         Legislative Requirements and Evaluation Criteria

The principal legislation for the management of air quality in Hong Kong is the Air Pollution Control Ordinance (APCO) (Cap. 311).  As the new set of AQOs will be implemented on 1 January 2022, the new AQOs have been adopted as the assessment criteria as shown in Table 3.1.

Table 3.1 Hong Kong Air Quality Objectives

Air Pollutant

Averaging Time

New AQOs

Concentration (µg m-3) (a)

No. of Exceedances Allowed per Year

Nitrogen Dioxide (NO2)

1-hour

200

18

 

Annual

40

-

Sulphur Dioxide (SO2)

10-minute

500

3

 

24-hour

50

3

Carbon Monoxide (CO)

1-hour

30,000

0

 

8-hour

10,000

0

Respirable Suspended Particulates (RSP) (b)

24-hour

100

9

Annual

50

-

Fine Suspended Particulates (FSP) (c)

24-hour

50

35

Annual

25

-

Ozone

8-hour

160

9

Lead

Annual

0.5

-

Notes:

(a)   Concentrations of gaseous air pollutants (i.e .NO2, SO2, CO and O3) are measured at 293K and 101.325kPa.

(b)   Suspended particles in air with a nominal aerodynamic diameter of 10 μm or less.

(c)   Suspended particles in air with a nominal aerodynamic diameter of 2.5 μm or less.

In addition to the APCO, a maximum hourly average Total Suspended Particulates (TSP) concentration of 500µg m-3 at Air Sensitive Receivers (ASRs) is stipulated in Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) to address potential construction dust impacts.  The measures stipulated in the Air Pollution Control (Construction Dust) Regulation will be followed to ensure that potential dust impacts are properly controlled.  Requirements stipulated in the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation and Air Pollution Control (Fuel Restriction) Regulation will also be followed to control potential emissions from non-road mobile machinery during decommissioning /demolition and construction phases.  Furthermore, Air Pollution Control (Marine Light Diesel) Regulation and Air Pollution Control (Fuel for Vessels) Regulation will be followed to control potential emissions from marine vessels arising from the Project.

3.3         Assessment Area and Air Sensitive Receivers

The Assessment Area is defined as an area within 15km from the boundary of the Project site.  The Project site and the Assessment Area are shown in Figure 3.1.

The representative ASRs have been identified in various districts within the Assessment Area, including:

n  The Islands (Lamma Island, Cheung Chau, Peng Chau, Hei Ling Chau, Northern and Eastern part of Lantau Island);

n  Southern District of Hong Kong Island;

n  Central and Western District of Hong Kong Island;

n  Eastern District of Hong Kong Island;

n  Kowloon; and

n  Tsing Yi.

The identification of representative ASRs within each of the abovementioned 6 districts have considered a number of factors, including:

n  Proximity of ASRs from the Project site:

Distance between the ASRs and the Project site has been considered as ASRs closer to the Project site would potentially experience higher impact from the stack emissions of the Project.  As far as distance is concerned, ASRs may be considered more representative if they are located closer to the Project site within a specific district.

n  Base elevation and building height of ASRs:

Base elevation and building height of the ASRs have been considered as ASRs with higher building height or situated at a higher base elevation has the potential to be more impacted by the stack emissions of the Project than those with lower building height or situated at a lower base elevation.  As far as base elevation and building height of ASRs are concerned, ASRs may be considered more representative if they are high-rise buildings or situated at a higher base elevation within a specific district.

n  Nature of ASRs:

Type of use of the ASRs (e.g. residential, commercial, industrial, GIC ([1])) has been considered in the identification of representative ASRs within each district.  ASRs that are of higher sensitivity to air quality impact (e.g. residential buildings, hospitals, schools) may be considered more representative relative to those of lower sensitivity to air quality impact (e.g. commercial and industrial buildings) within a specific district.

n  Representativeness of ASRs within a specific district:

ASRs that are prominent, large-scale, and/or landmark developments (e.g. large residential complexes) which can reasonably represent a specific district may be considered more representative. 

n  Geography of the district:

The locations and number of representative ASRs within a specific district have been considered such that they can reasonably cover different areas within that specific district.  For example, Islands District consists of a number of islands including Lamma Island, Cheung Chau, Hei Ling Chau and Peng Chau. 

n  Presence of natural terrain and physical barriers:

Presence of natural terrain and physical barriers has been considered in the identification of representative ASRs within each district.  ASRs that have direct line of sight to the stacks of the Project may be considered more representative than those ASRs with natural terrain or physical barriers blocking their views to the stacks of the Project.

In general, more representative ASRs have been identified within a district that is relatively close to the Project site (e.g. Islands District, Southern District of Hong Kong Island) compared with a district that is at a greater distance from the Project site (e.g. Tsing Yi, Eastern District of Hong Kong Island).  More representative ASRs have also been identified within a district with scattered areas (e.g. Islands District, Southern District of Hong Kong Island) to provide a comprehensive coverage of the district.

Apart from the review of relevant Outline Zoning Plans (OZPs), Development Permission Area Plans, Outline Development Plans and Layout Plans and other relevant published land use plans from the Lands Department and development applications approved by the Town Planning Board, the identification of these representative ASRs has also made reference to the approved EIA report for the 1,800MW Gas-Fired Power Station at Lamma Extension (LMX) Project (AEIAR-010/1999), the Air Quality Impact Assessment (AQIA) study for Variation of Environmental Permit (VEP) for the LMX project in 2020, and the Air Pollution Control Plan (APCP) for the operation of unit L10 at Lamma Power Station (LPS) in 2019.  

Locations of the identified representative ASRs are shown in Figure 3.1.  Details of these representative ASRs, including the ASR descriptions, uses, base elevation, approximate building height and approximate distance from the Project site are presented in Table 3.2.


Table 3.2         Identified Representative ASRs

ASR

District

Description

Type of Use

PATH Grid

Approx. Base Elevation (mPD)

Approx. Maximum Height (m above ground)

Approx. Separation Distance from the Project Site Boundary (km)

A1

Islands (Lamma Island)

Village House at Po Wah Yuen

Residential

3423

33.7

10

1.32

A2

Islands (Lamma Island)

Pak Kok San Tsuen House 40

Residential

3424

21.3

10

2.32

A3

Islands (Lamma Island)

Village house at Tai Shan Central

Residential

3423

30.5

10

0.81

A4

Central & Western HK Island

Cape Mansions Block B

Residential

3528

76.0

70

6.37

A5

Southern HK Island

Pine Court Block 2

Residential

3527

35.6

50

5.75

A6

Central & Western HK Island

Queen Mary Hospital Block S

Hospital

3628

146.2

55

6.43

A7

Central & Western HK Island

Smithfield Court Block 1

Residential

3529

7.0

70

7.54

A8

Southern HK Island

Residence Bel-Air Phase 1 Tower 8

Residential

3626

8.7

170

5.23

A9

Southern HK Island

Baguio Villa Block 22

Residential

3627

92.6

95

5.78

A10

Central & Western HK Island

The University of Hong Kong Main Building

GIC

3629

60.8

15

8.09

A11

Southern HK Island

Pokfulam Gardens Block 1

Residential

3627

131.5

105

5.56

A12

Central & Western HK Island

Overthorpe Block A

Residential

3728

478.7

10

7.70

A13

Southern HK Island

Wah Fu (II) Estate Wah Tai House

Residential

3626

61.0

80

5.00

A14

Southern HK Island

Sherwood's Bluff Block A2

Residential

3827

429.7

10

7.49

A15

Central & Western HK Island

Regent On The Park Tower 1

Residential

3928

59.8

115

8.84

A16

Southern HK Island

Wah Kwai Estate Wah Hau House

Residential

3726

10.6

120

5.11

A17

Southern HK Island

Matilda International Hospital

Hospital

3827

410.9

15

6.44

A18

Southern HK Island

Aberdeen Centre Kwun Chiu Court

Residential

3825

4.0

90

6.05

A19

Southern HK Island

San Wui Commercial Society Chan Pak Sha School

School

3925

23.1

20

7.04

A20

Southern HK Island

Ocean Park Maritime Point

Theme Park

4024

120.0

10

6.85

A21

Southern HK Island

Hong Kong Ocean Park Marriott Hotel

Hotel

4025

14.0

20

8.02

A22

Southern HK Island

South Horizons Block 13 Yee Lok Court

Residential

3725

6.0

115

5.07

A23

Southern HK Island

Lei Tung Estate Tung Mau House

Residential

3825

59.8

115

5.84

A24

Islands (Cheung Chau)

Seaview Garden

Residential

2621

60.0

10

6.84

A25

Islands (Lamma Island)

Concerto Inn

Hotel

3522

7.1

15

1.42

A26

Islands (Lamma Island)

South Lamma Public Library

GIC

3621

4.8

10

2.94

A27

Southern HK Island

Ma Hang Estate Block 4 Leung Ma House

Residential

4323

42.5

40

10.35

A28

Southern HK Island

34-38 Chung Hom Kok Road House B

Residential

4322

79.3

15

10.06

A29

Southern HK Island

The Repulse Bay Tower III Harston

Residential

4224

45.5

90

9.62

A30

Eastern HK Island

Taikoo Shing Yiu Sing Mansion

Residential

4530

5.0

90

13.93

A31

Eastern HK Island

Wah Shun Gardens

Residential

4430

30.8

120

13.25

A32

Eastern HK Island

Chan's Creative School (H.K. Island)

School

4330

7.5

20

12.97

A33

Eastern HK Island

Braemar Hill Mansions Block 7

Residential

4329

140.2

85

12.45

A34

Eastern HK Island

City Garden Hotel

Hotel

4230

3.8

85

12.19

A35

Central & Western HK Island

Hay Wah Building Block B

Residential

4029

3.8

75

9.54

A36

Kowloon

Harbour Pinnacle

Residential

4031

4.8

120

11.28

A37

Kowloon

Sorrento Tower 1

Residential

3932

10.9

260

11.45

A38

Kowloon

On Lee Building

Residential

4033

4.9

50

12.60

A39

Kowloon

The Open University of Hong Kong

School

4133

35.5

50

13.39

A40

Kowloon

King's Court

Residential

4134

12.4

60

14.18

A41

Kowloon

Cheung Sha Wan Government Offices

GIC

3935

4.9

100

13.86

A42

Kowloon

Caritas Medical Centre

Medical Centre

3836

36.4

45

14.59

A43

Tsing Yi

Cheung Hong Estate Hong On House

Residential

3337

40.0

100

14.68

A44

Tsing Yi

Hong Kong Institute of Vocational Education (Tsing Yi Campus)

School

3336

39.4

45

13.74

A45

Islands (Lantau Island)

Hong Kong Disneyland Hotel

Hotel

2732

3.0

25

11.72

A46

Islands (Lantau Island)

Hong Kong Disneyland

Theme Park

2733

7.4

10

12.17

A47

Islands (Lantau Island)

Inspiration Lake Recreation Centre

Water Recreation Centre

2633

8.8

10

13.18

A48

Islands (Lantau Island)

Graceful Mansion

Residential

2432

32.0

90

13.81

A49

Islands (Lantau Island)

Cherish Court

Residential

2531

10.5

60

11.83

A50

Islands (Peng Chau)

Tung Wan Villa House 8

Residential

2630

6.6

10

10.11

A51

Islands (Peng Chau)

Holy Family School

School

2629

24.0

25

9.69

A52

Islands (Lantau Island)

Silvermine Beach Resort

Hotel

2228

2.0

20

12.21

A53

Islands (Lantau Island)

Bui O Public School

School

2025

7.4

15

13.40

A54

Islands (Hei Ling Chau)

Hei Ling Chau Correctional Institution

GIC

2726

89.0

25

7.48

A55

Islands (Hei Ling Chau)

Hei Ling Chau Addiction Treatment Centre

GIC

2626

44.5

25

8.47

A56

Islands (Cheung Chau)

Buddish Wai Yan Memorial College

School

2521

1.5

15

8.06

A57

Islands (Cheung Chau)

Cheung Chau Kwok Man School

School

2521

2.8

15

7.67

A58

Islands (Cheung Chau)

Scenic Garden Block 29

Residential

2522

17.5

10

7.81

A59

Southern HK Island

Eredine

Residential

3827

455.5

30

6.54

A60

Tsing Yi

Ching Wah Court Wah Yan House

Residential

3336

76.4

100

14.55

A61

Islands (Lantau Island)

Bijou Drive 32

Residential

2330

221.1

10

12.81


3.4         Baseline Conditions

The Project is located at the GT Compound within the existing LPS.  The local air quality is primarily influenced by the emissions from the existing operation of LPS.

3.4.1    Measured Background Air Quality from Air Quality Monitoring Stations

Eight EPD’s air quality monitoring stations (AQMSs) in Kwai Chung, Sham Shui Po, Mongkok, Central/Western, Central, Causeway Bay, Eastern and Southern are located within the Assessment Area.

Table 3.3 presents the relevant time averaging concentrations of air pollutants measured at the above AQMS in the most recent five years (i.e. 2016 to 2020) for comparison with the prevailing AQOs.

Table 3.3 Concentrations of Air pollutants Measured at EPD’s AQMS within the Assessment Area in the Recent Five Years (2016 to 2020)

Station

Year

Concentration of Pollutants (µg m-3) (a)

19th highest 1-hour NO2

Annual NO2

4th highest 24-hour SO2

4th highest   10-min SO2

10th highest 24-hour RSP

Annual RSP

10th highest 24-hour FSP

Annual FSP

10th highest daily max. 8-hour O3

Daily max. 1-hour CO (d)

Daily max. 8-hour CO (d)

Kwai Chung

 

2016

185

59

36

147

71

33

50

22

107

-

-

2017

204

57

24

93

74

35

49

23

129

-

-

2018

196

55

27

134

62

32

38

20

133

-

-

2019

184

54

18

53

59

29

39

18

143

-

-

2020

184

48

12

43

46

23

29

14

124

-

-

Sham Shui Po

2016

161

58

26

126

77

35

48

23

106

-

-

2017

194

54

25

76

72

33

46

21

130

-

-

2018

152

49

21

98

59

33

41

21

147

-

-

2019

176

48

14

41

65

33

36

18

164

-

-

2020

151

45

12

40

59

28

30

14

134

-

-

Mongkok (b)

2016

218

78

21

83

80

37

57

26

71

2,570

1,911

2017

257

81

20

83

84

38

57

27

91

2,390

2,156

2018

240

79

19

88

73

36

51

24

97

2,340

2,041

2019

248

78

10

39

74

35

55

24

125

2,280

2,103

2020

214

74

10

45

63

29

42

18

96

1,810

1,580

Central / Western

2016

152

43

27

103

80

32

50

22

138

-

-

2017

164

40

29

125

84

35

59

23

159

-

-

2018

159

39

22

135

70

34

46

21

164

-

-

2019

153

37

12

62

69

30

49

20

191

-

-

2020

128

32

9

31

60

25

37

16

140

-

-

Central (b)

2016

258

78

24

75

82

31

50

20

96

2,000

1,739

2017

267

80

24

91

84

33

56

21

103

2,050

1,879

2018

257

80

20

101

74

34

50

21

96

2,330

1,685

2019

252

80

15

42

74

37

53

24

133

2,440

2,205

2020

223

68

10

26

63

29

39

17

107

1,980

1,620

Causeway Bay (b)

2016

274

89

15

89

89

45

59

32

69

3,130

2,215

2017

325

97

25

95

90

46

65

31

78

2,420

2,090

2018

277

87

19

82

82

46

55

30

78

2,610

2,047

2019

287

81

11

51

80

43

54

27

108

2,620

2,309

2020

216

68

11

35

70

36

44

22

91

2,850

1,685

Eastern

2016

134

46

16

82

71

30

45

20

132

-

-

2017

139

42

14

54

74

33

49

20

160

-

-

2018

128

39

12

123

68

33

39

19

161

-

-

2019

136

38

7

41

66

31

40

18

169

-

-

2020

113

34

6

16

60

27

31

14

140

-

-

Southern (c)

2020

101

-

6

27

51

-

27

-

151

1,250

1,150

Prevailing AQOs

200

40

125

500

100

50

75

35

160

30,000

10,000

Notes:

(a)   Data underlined indicate exceedance of the AQO.

(b)   Roadside AQMS.

(c)   As southern AQMS commissioned since 10 July 2020, monitoring results are only available in 2020.  Concentration of pollutants in annual average are also not available as annual averages calculated from less than eight representative months will not be published in any form of air quality reports.

(d)   CO concentrations were not monitored for AQMSs in Kwai Chung, Sham Shui Po, Central/ Western and Eastern.

HK Electric operates a number of AQMSs in accordance with the requirements of its Lamma Power Station Specified Process (SP) licence, and the air quality monitoring data (i.e. NO2 and SO2) from these AQMSs are available for the most recent three years on HK Electric’s website ([2]).  All AQMSs fall within the assessment area of the Project.  The relevant time-averaging concentrations of the measured NO2 and SO2 data from these AQMSs in the most recent three years (i.e. 2018 to 2020) are presented in Table 3.4 for comparison with the prevailing AQOs.

Table 3.4 Concentrations of Air pollutants Measured at HK Electric’s AQMS within the Assessment Area in the Recent Three Years (2018 to 2020)

Station

Year

Concentration of Pollutants (µg m-3) (a)

 

19th highest 1-hour NO2

Annual NO2

4th highest 24-hour SO2

4th highest 10-min SO2

Chung Hum Kok

2018

97

12

17

107

2019

115

10

8

23

2020

80

12

9

24

Victoria Road

2018

63

11

16

69

2019

76

14

12

17

2020

60

12

4

16

Ap Lei Chau

2018

127

18

35

183

2019

123

13

12

32

2020

92

14

6

28

Cheung Chau

2018

160

27

20

67

2019

154

27

12

47

2020

123

22

14

34

Victoria Peak (a)

2018

113

14

14

177

2019

89

13

11

42

2020

79

12

7

29

Pok Fu Lam

2018

126

26

37

152

2019

141

25

14

79

2020

114

23

15

33

Prevailing AQOs

200

40

125

500

Note:

(a)   Ambient air monitoring at Victoria Peak Station was temporarily suspended from 1 Sep 2018 to 14 Jul 2019 due to renovation works.

n  NO2

No exceedance of 19th highest 1-hour NO2 was recorded at all EPD’s general AQMSs for the past five years except in Kwai Chung in 2017.  Exceedances of 19th highest 1-hour NO2 were recorded at EPD’s roadside AQMSs in Mongkok, Central and Causeway Bay in all recent five years.  No exceedances of 19th highest 1-hour NO2 were recorded at all HK Electric’s AQMSs from 2018 to 2020.

Exceedances of annual NO2 were recorded in all recent five years at the EPD’s general AQMSs in Kwai Chung and Sham Shui Po, as well as roadside AQMSs in Mongkok, Central and Causeway Bay.  EPD’s AQMSs in Central/Western had exceedances of annual NO2 from 2016 to 2017 but no exceedance from 2018 to 2020.  No exceedances were recorded at all HK Electric’s AQMSs for the past three years.

n  SO2

No exceedances of 4th highest 24-hour SO2 and 4th highest 10-min SO2 were recorded at all EPD’s AQMSs for the past five years (2016-2020) and all HK Electric’s AQMSs for the past three years (2018-2020).

n  RSP

No exceedances of 10th highest 24-hour RSP and annual RSP were recorded at all EPD’s AQMSs for the past five years (2016-2020).

n  FSP

No exceedances of 10th highest 24-hour FSP and annual FSP were recorded at all EPD’s AQMSs for the past five years (2016-2020).

n  CO

No exceedances of maximum 1-hour CO and 8-hour CO were recorded at all EPD’s AQMSs for the past five years (2016-2020).

n  O3

Exceedances of 10th highest 8-hour O3 were recorded at EPD’s AQMSs in Sham Shui Po in 2019, in Central/Western in 2018 and 2019, and in Eastern from 2017 to 2019 over the past five years (2016-2020).  O3 exceedances were not recorded at the other EPD’s AQMSs in the past five years.

3.4.2    Predicted Future Background Air Quality

The background air pollutant concentrations predicted by the PATH v2.1 model (i.e. Pollutants in the Atmosphere and their Transport over Hong Kong) in different PATH grids where the identified ASRs are located in within the Assessment Area in Year 2025 (i.e. the year of tentative commencement of operation of Project) are presented in Table 3.5.

 

 

Table 3.5 Background Air Pollutant Concentrations Predicted by the PATH v2.1 Model in 2025

PATH Grid

Concentration of Pollutants (µg m-3)

 

 

 

19th highest 1-hour NO2

Annual NO2

4th highest 24-hour SO2

4th highest   10-min SO2 (a)

10th highest 24-hour RSP

Annual RSP

36th highest 24-hour FSP

Annual FSP

10th highest   Daily Max. 8-hour O3

Daily Max. 1-hour CO

Daily Max. 8-hour CO

 

2025

91.6

17.3

11.6

81.4

66.4

27.9

25.2

15.2

227.9

882

773

 

2228

107.8

19.8

11.5

78.1

65.4

27.4

23.2

14.7

229.4

917

838

 

2330

113.0

19.7

11.9

89.5

66.0

27.5

24.1

14.8

234.6

911

825

 

2432

113.4

22.5

11.6

90.5

64.4

26.5

22.6

14.4

227.3

897

810

 

2521

121.4

24.0

11.5

83.6

60.7

26.7

21.3

13.6

222.8

905

799

 

2522

120.7

26.2

11.1

82.0

62.5

27.4

21.7

13.9

219.8

909

810

 

2531

112.8

29.9

11.4

69.9

63.9

27.5

22.1

14.5

216.7

890

801

 

2621

119.2

24.8

11.4

78.2

62.6

27.6

21.9

13.9

222.7

902

799

 

2626

121.0

27.4

11.3

67.3

62.1

27.2

22.0

14.0

217.5

891

794

 

2629

114.8

29.4

11.3

62.1

63.9

27.9

22.1

14.4

215.9

881

791

 

2630

112.4

28.7

11.2

61.7

63.8

27.9

22.1

14.4

215.9

870

781

 

2633

115.0

23.9

11.5

86.6

62.0

26.1

22.0

14.2

228.1

870

776

 

2726

117.9

27.3

10.8

66.7

62.9

27.6

21.8

14.1

215.0

874

782

 

2732

119.6

32.2

11.3

67.3

63.6

27.6

22.7

14.6

211.2

852

761

 

2733

118.0

28.7

11.5

67.5

61.7

26.7

22.4

14.4

219.5

863

768

 

3336

137.7

34.8

11.2

66.6

62.5

27.1

23.0

15.0

210.0

790

716

 

3337

143.3

30.4

10.9

61.8

62.1

27.1

22.9

14.9

203.5

799

718

 

3423

125.4

21.4

11.3

70.3

63.6

27.4

21.8

14.0

213.2

834

743

 

3424

130.5

23.6

11.9

74.1

64.5

28.3

23.4

14.8

211.3

839

749

 

3522

114.9

17.4

11.6

59.1

61.7

26.5

20.6

13.3

218.9

817

733

 

3527

126.1

24.9

11.6

73.8

60.5

26.7

21.9

13.9

198.6

839

744

 

3528

125.2

20.7

10.9

61.5

59.8

26.0

22.1

13.8

204.5

840

730

 

3529

134.7

21.8

11.2

65.6

61.5

26.2

22.6

14.1

214.6

835

731

 

3621

108.3

17.6

10.8

53.4

63.1

26.6

21.0

13.4

212.6

794

732

 

3626

114.4

19.7

10.5

57.1

60.8

26.3

21.8

13.7

205.9

845

739

 

3627

112.5

17.3

10.0

55.5

60.8

26.3

22.5

13.8

209.7

845

741

 

3628

112.9

16.8

9.9

57.7

62.7

26.7

23.6

14.2

215.0

861

740

 

3629

123.6

20.2

10.1

57.9

64.1

27.3

24.3

14.8

218.9

870

748

 

3725

111.0

22.5

10.9

55.9

62.4

27.2

21.7

14.0

200.1

842

753

 

3726

99.8

17.1

10.0

51.2

62.1

26.4

22.4

13.9

208.6

861

739

 

3728

103.6

15.5

9.8

49.4

64.6

27.4

25.2

14.8

209.7

864

743

 

3825

104.4

17.9

10.3

57.3

62.2

26.8

22.0

13.9

208.4

856

753

 

3827

97.9

14.1

9.8

44.7

64.4

27.2

23.9

14.5

206.3

871

744

 

3836

108.9

19.9

9.8

49.5

62.5

26.6

23.5

14.7

187.7

828

733

 

3925

94.4

14.7

10.2

48.7

61.2

26.1

20.8

13.4

209.5

856

739

 

3928

97.1

15.2

9.8

45.4

64.9

27.3

23.3

14.7

211.0

870

737

 

3932

132.1

26.8

9.9

58.5

64.0

27.7

24.1

15.2

205.9

950

770

 

3935

119.5

20.0

9.8

49.9

62.2

27.0

23.7

14.7

187.2

843

740

 

4024

98.8

15.1

9.9

44.1

63.0

26.9

20.3

13.4

200.6

839

745

 

4025

87.3

13.4

10.0

42.3

62.0

26.0

20.7

13.3

210.1

846

736

 

4029

128.9

20.9

9.9

48.1

66.2

28.8

24.8

15.5

208.1

899

770

 

4031

139.8

26.5

10.1

51.5

64.4

28.5

24.0

15.3

202.8

938

760

 

4033

130.6

23.9

9.8

59.4

63.8

28.4

24.7

15.5

191.5

1,016

777

 

4133

123.3

22.1

9.7

55.1

62.7

27.5

23.9

14.9

189.3

1,008

759

 

4134

121.0

21.3

9.7

54.6

62.9

27.6

24.2

15.0

190.6

972

771

 

4224

84.9

12.9

9.5

40.4

64.3

27.3

21.2

13.6

207.3

821

739

 

4230

124.6

19.3

9.9

48.2

63.7

27.7

24.0

14.9

195.9

964

757

 

4322

87.4

13.2

9.6

41.2

63.4

26.6

20.9

13.3

206.8

827

735

 

4323

83.7

12.6

9.5

40.3

65.3

27.3

21.8

13.7

204.6

830

734

 

4329

105.2

12.4

9.7

52.8

64.7

26.9

22.4

14.2

202.4

854

741

 

4330

116.4

17.7

9.9

53.7

64.4

27.7

24.0

14.9

196.4

862

758

 

4430

109.2

17.8

9.9

52.7

64.5

27.7

23.6

14.7

195.9

870

770

 

4530

111.8

18.9

9.9

50.2

63.7

27.4

22.4

14.4

195.4

892

786

 

AQOs (e)

200

40

50

500

100

50

50

25

160

30,000

10,000

 

Notes:

(a)   The multiplicative factor for the stability class calculated for each hour was applied to the 1-hour SO2 concentrations to estimate the 10-minute SO2 concentrations.

(b)   Underlined values mean AQO exceedance.

(c)   An adjustment of 11.0ug/m3 and 10.3ug/m3 were added to the RSP background for calculation of 24-hour RSP and annual RSP, respectively.

(d)   An adjustment of 3.5ug/m3 was added to the FSP background for calculation of annual FSP.

(e)   New AQOs to be implemented on 1 January 2022.

 

As shown in Table 3.5, predicted background concentrations of NO2, SO2, RSP, FSP and CO in all PATH grids in 2025 are below the relevant new AQO criteria.  The predicted background concentrations of O3 in 2025 show exceedances of the relevant AQO criterion in all PATH grids.

3.5         Potential Sources of Impact

3.5.1    Decommissioning/ Demolition and Construction Phases

All activities associated with decommissioning/ demolition and construction of the Project will be located within the GT Compound of the LPS.  No major earthworks or site formation works will be required.

The decommissioning/ demolition and construction of the Project will include the following key activities (see Section 2 for details):

n  Decommissioning and demolition of existing units GT2, GT3, GT4, GT57 ([3]), GT6 and their auxiliaries (e.g. generator coolers, transformers), existing lube oil tank near GT5, existing BSGT and the miscellaneous shed, as well as equipment inside the existing GTAB;

n  Construction of new OCGTs (i.e. GT8, GT9, GT10 and GT11), new BSGT and BESS;

n  Construction of new cable trenches and new staircase and lift at the immediate east of GTAB; and

n  Installation of new equipment inside the GTAB for conversion to a new 132kV switching station.

Demolition of existing units and equipment associated with the Project have the potential generate dust emissions.  Soil excavation, material handling and wind erosion from open stockpiling of dusty materials during the construction of the new cable trenches and new staircase and lift are also considered potential dust generating activities.  The key air pollutants of concern from these dust generating activities are TSP, RSP and FSP.  In addition, the demolition and construction works will involve the use of powered mechanical equipment (PME) and marine vessels for equipment delivery, which will produce emissions from fuel combustion.  The key air pollutants of concern from fuel combustion emissions include RSP, FSP, NO2 and SO2. 

3.5.2    Operation Phase

3.5.2.1             Emissions from New OCGTs

The stack emissions from the operation of the new OCGTs (i.e. GT8, GT9, GT10 and GT11) are the major air emission sources of the Project during the operation phase.  The stack locations of these new OCGTs are shown in Figure 3.2.

The new OCGTs will only be operated intermittently during peak-lopping and emergency operation.  ULSD will be used for the new OCGTs.  The key air pollutants of concern arising from the operation of the new OCGTs include NO2, SO2, RSP and FSP.

3.5.2.2             Emissions from Other Air Emission Sources within LPS

There are a number of key existing and planned stack emission sources associated with the LPS operation that will be operated concurrently during the operation phase of the Project.  These emission sources include:

n  Planned L11, L12 and L13 (gas-fired) and their gas heaters;

n  Existing L10 (gas-fired) and its gas heater;

n  Existing L9 (gas-fired) and its gas heater;

n  Existing coal-fired units (i.e. L6 to L8) and

n  Existing GT1.

The abovementioned stack emission sources associated with the LPS operation are considered major emission point sources that have the potential to contribute to the cumulative air quality impacts at the identified ASRs, in particular those in Lamma Island, Cheung Chau, Hei Ling Chau and Southern District of HK Island that are of relatively close distance from LPS.    

The key air pollutant of concern associated with these stack emission sources are NO2, SO2, RSP and FSP.

3.5.2.3             Vehicular Emissions from Open Roads

Vehicular emissions from open roads in the vicinity of the identified ASRs (i.e. a distance of 500m from the ASRs) may contribute to the cumulative air quality impact to the identified ASRs, except for those on Lamma Island, Cheung Chau, Hei Ling Chau and Peng Chau (i.e. A1, A2, A3, A24, A25, A26, A50, A51, A54, A55, A56, A57 and A58) where there are no open roads and thus no vehicular emissions.  The key air pollutants from vehicular emissions include NO2, RSP and FSP.  It should be noted that additional road traffic will not be generated as a result of the operation of the Project.

3.5.2.4             Emissions from Marine Vessels

Emissions from marine vessels in the vicinity of the identified ASRs (i.e. a distance of 500m from the ASRs) have the potential to give rise to cumulative air quality impact to the identified ASRs.  The key air pollutants from marine emissions include NO2, SO2, RSP and FSP.  A number of marine vessel travel routes and typhoon shelters are located within 500m from the identified ASRs (e.g. A2, A18, A22, A26, A37, A45, A50, A51).  It should be noted that additional marine traffic will not be generated as a result of the operation of the Project.

3.5.2.5             Emissions from Industrial Premises

Emissions from industrial premises (e.g. chimneys) in the vicinity of the identified ASRs (i.e. a distance of 500m from the ASRs) may contribute to the cumulative air quality impact to the identified ASRs.  In addition, major emission point sources, such as crematorium, power plant and asphalt plant, may pose air quality impact if they are located within 4km from the identified ASRs.  The key air pollutants from industrial emissions are NO2, SO2, RSP and FSP. 

3.6         Assessment Methodology for Decommissioning/ Demolition and Construction Phases

As discussed in Section 3.5.1, fugitive dust emissions may arise from the decommissioning/ demolition and construction activities of the Project.

The demolition works will mainly involve typical construction equipment such as electric breakers, flame cutting and other hand-held power mechanical equipment.  Blasting or excavation works will not be required for the demolition.  During the construction phase, foundation works will not be required as the existing foundation piles and reinforced concrete structure will be reused to support the new units as far as practicable.  Only minor excavation works will be required for the construction of the new cable trenches and the new staircase and lift.  In addition, all major equipment and piping associated with the new units will also be fully assembled off-site as far as practicable for subsequent installation on site, and thus associated civil works are minimised.  Generation of fugitive dust emissions during the decommissioning/ demolition and construction phases is expected to be limited and localised within the LPS.  There are also no ASRs within 500m from the Project site (except for the Administration and Control Building within LPS), with the nearest ASR (i.e. A3) about 800m away. 

In view of the nature of the decommissioning/ demolition and construction works associated with the Project and sufficient separation distance between the Project site and the ASRs, no adverse fugitive dust impact during the decommissioning/ demolition and construction phases of the Project is anticipated.  A quantitative assessment of the decommissioning/ demolition and construction air quality impacts arising from the Project is considered not necessary and hence these impacts are addressed qualitatively in Section 3.8.1.

3.7         Assessment Methodology for Operation Phase

3.7.1    Overview

As per Clause 3.4.3 of the EIA Study Brief, a comparative assessment has been carried out to evaluate the air quality impacts arising from the concerned units before and after the Project.  The purpose of the comparative assessment is to demonstrate that the air quality impacts from the operation of new OCGTs (i.e. the proposed GT8, GT9, GT10 and GT11) are lower than those from the operation of existing OCGTs/CCGT (i.e. GT2, GT3, GT4, GT57 and GT6) at the identified representative ASRs within the Assessment Area.

If the result of the comparative assessment shows increased air quality impacts at ASRs due to operation of the new OCGTs, cumulative assessment would be carried out to evaluate the cumulative impacts at these ASRs against the new AQOs as shown in Table 3.1.  Based on the results of the comparative assessment presented in Section 3.8.2 below, reduction of air quality impacts has been predicted at all relevant assessment heights of all identified ASRs within the Assessment Area.  As such, cumulative assessment for the operation of the Project is not required. 

The following sub-sections in Section 3.7 detail the assessment methodology for the comparative assessment.

3.7.2    Modelling Scenarios

The stack locations of the proposed GT8, GT9, GT10 and GT11 are shown in Figure 3.2, while the stack locations of the existing GT2, GT3, GT4, GT57 and GT6 are shown in Figure 3.3.   The existing stacks serving the existing GT2, GT57 and GT6 will be retained for the proposed new GT8, GT9, GT10 and GT11 in the following arrangement:

n  GT8 to replace GT5 and use the existing stack of GT5;

n  GT9 to replace GT6 and use the existing stack of GT6;

n  GT10 to replace GT7 and use the existing stack of GT7; and

n  GT11 to replace GT2 and use the existing stack of GT2.

GT3 and GT4 will be decommissioned and demolished with no replacement units under this Project.  The stacks of GT3 and GT4 will be retained but there will be no emissions during the operation of the Project.

One modelling scenario assuming the operation of the existing OCGTs and CCGT was assessed and represents the “Without Project” scenario.  As the new OCGTs will be commissioned and put into operation in four phases (i.e. Phase 1 to Phase 4), a modelling scenario for each phase of the Project operation was assessed to consider the air quality impacts throughout all phases of the operation of the Project.

For the comparative assessment, the air quality impacts (i.e. NO2, SO2, RSP and FSP) at the representative ASRs under each of the four phases of “With Project” scenario (i.e. Phase 1 to Phase 4) were compared with those under the “Without Project” scenario. 

Details of the modelling scenarios and the assessment parameters modelled are presented in Table 3.6.  The stack parameters and emission information adopted in the modelling assessment under the “Without Project” and “With Project” scenarios are presented in Table 3.7 and Table 3.8, respectively.  The stack locations of the existing and/or new units considered under the four phases of “With Project” scenario are shown in Figures 3.4a to 3.4d.

Table 3.6   Modelling Scenarios and Assessment Parameters

Modelling Scenario

Emission Sources Considered

Assessment Parameters in the Modelling Assessment (a)(b)

“Without Project”

      Existing GT2, GT3, GT4, GT57, GT6

      Maximum 1-hour NO2 and annual NO2

      Maximum 10-minute SO2 and maximum 24-hour SO2

      Maximum 24-hour RSP and annual RSP

      Maximum 24-hour FSP and annual FSP

“With Project” – Phase 1

      Existing GT2, GT3, GT4

      New GT10

“With Project” – Phase 2

      Existing GT3, GT4

      New GT8, GT10

“With Project” – Phase 3

      Existing GT4

      New GT8, GT9, GT10

“With Project” – Phase 4

      New GT8, GT9, GT10, GT11

Notes:

(a)   The new OCGTs will only be operated during peak-lopping and emergency situation, and thus the operation is expected to be short-term and infrequent.  However, considering that the operation of the new OCGTs may last for more than 24 hours, annual assessment for both “Without Project” and “With Project” scenarios has been conducted as a conservative and consistent approach.

(b)   For the purpose of this comparative assessment, all units under the “Without Project” scenario and “With Project” scenario (Phase 1 to Phase 4) were assumed to be operating continuously under normal operating condition as a consistent modelling assumption.

(c)   The black start gas turbine within the Project site will also be replaced under this Project.  However, as the operation of the black start gas turbine within the Project site is highly unlikely (during black out situations) and short-term (i.e. duration of a few hours), potential emissions from its operation have not been considered under all modelling scenarios.  Also, as confirmed by HK Electric, the emission and stack parameter information for the operation of the black start gas turbine remain unchanged after replacement, and thus consideration of the emissions from the black start gas turbine is deemed not necessary in this comparative assessment.

 

Table 3.7   Stack Parameters and Emission Information under “Without Project” Scenario

Parameters

GT2

GT3

GT4

GT6

GT5 (f)

GT7 (f)

Stack Locations (X, Y)

828711,

808699

828718,

808703

828711,

808707

828892,

808705

828899,

808702

828899,

808709

Stack Diameter (m)

5.6

5.6

5.6

5.6

5.6

5.6

Stack Height (mPD)

86

86

86

86

86

86

Exit Velocity (m/s)

32

32

32

32

20

20

Exit Temperature (°K)

663

663

663

663

423

423

Emission Rate of NOx (g/s) (b)

74.31

74.31

74.31

74.31

34.72

34.72

Emission Rate of SO2 (g/s) (c)

0.83

0.83

0.83

0.83

2.78

2.78

Emission Rate of PM (g/s) (d)(e)

4.86

4.86

4.86

4.86

2.78

2.78

Notes:

a)    The stack parameters and emission information were made reference to the current LPS SP licence.  The stack input parameters presented represent the normal operating condition with reference to the LPS SP licence (i.e. at “74% base load condition” as specified in the LPS SP licence).  Emission rates of GT2 to GT7 were calculated with reference to Schedule A2 of the LPS SP licence.  According to Clause A.2.1 of the LPS SP licence, the total NOx, SO2 and PM emissions from GT2 to GT7 are limited to 1,320 kg/hour, 32 kg/hour and 90 kg/hour, respectively.

b)    NOx of GT5 / GT7 = 125kg/hr x 1000 / 3600 = 34.72g/s

NOx of GT2 / GT3 / GT4 / GT6 = (1320kg/hr – 125kg/hr x 2) / 4 x 1000 / 3600 = 74.31g/s

c)     SO2 of GT5 / GT7 = 10kg/hr x 1000 / 3600 = 2.78g/s

SO2 of GT2 / GT3 / GT4 / GT6 = (32kg/hr – 10kg/hr x 2) / 4 x 1000 / 3600 = 0.83g/s

d)    PM of GT5 / GT7 = 10kg/hr x 1000 / 3600 = 2.78g/s

PM of GT2 / GT3 / GT4 / GT6 = (90kg/hr – 10kg/hr x 2) / 4 x 1000 / 3600 = 4.86g/s

e)    PM refers to particulate matter.  The emission rate for PM applies to both RSP and FSP.

f)      GT57 is a CCGT unit converted from 2 OCGTs (i.e. GT5 and GT7) with two separate stacks.  GT57 will be modelled as 2 separate emission sources GT5 and GT7 under “Without Project” scenario.

g)    Existing GT2, GT3, GT4, GT6 are oil-fired with generation capacity of 125MW each, while the existing GT57 is gas-fired with generation capacity of 345MW.  The total power generation capacity from these existing units is 845MW.

Table 3.8   Stack Parameters and Emission Information under “With Project” Scenario

Parameters

GT8

GT9

GT10

GT11

Stack Locations (X, Y)

828899,

808702

828892,

808705

828899,

808709

828711,

808699

Stack Diameter (m)

5.6

5.6

5.6

5.6

Stack Height (mPD)

86

86

86

86

Exit Velocity (m/s)

32

32

32

32

Exit Temperature (°K)

663

663

663

663

Emission Rate of NOx (g/s) (b)

51.67

51.67

51.67

51.67

Emission Rate of SO2 (g/s) (b)

1.03

1.03

1.03

1.03

Emission Rate of PM (g/s) (b)(c)

3.44

3.44

3.44

3.44

Notes:

a)    The stack parameters and emission information of the proposed new OCGTs are based on design specifications provided by HK Electric.  The stack input parameters presented represent the normal operating condition of the proposed new OCGTs.

b)    Emission rates of each new unit were calculated based on the NOx, SO2 and PM emission concentrations of 150mg/Nm3, 3mg/Nm3 and 10mg/Nm3, respectively, and the stack volumetric flow rate of 1,240,000Nm3/hour (at 15% O2, 0 degree C, 1 atm) for each unit.  The NOx and PM emission concentrations adopted were made reference to those stipulated in Guidance Note on the Best Practicable Means for Electricity Works (BPM7/1(2018)).  SO2 emission concentration was provided by HK Electric and is based on fuel oil with sulphur content of not more than 0.005% by weight as required in BPM7/1(2018).

c)     PM refers to particulate matter.  The emission rate for PM applies to both RSP and FSP.

d)    The new GT8, GT9, GT10 and GT11 are oil-fired and have generation capacity of up to 130MW each, with a total power generation capacity of up to 520MW.

3.7.3    Air Dispersion Model and Meteorological Data

An EPD recommended air dispersion model, AERMOD, was used to assess the potential air quality impact at the representative ASRs under the “Without Project” and “With Project” scenarios.  The quantitative assessment was conducted following the latest EPD’s Guidelines for Local-scale Air Quality Assessment Using Model.

The relevant PATH grids in which the representative ASRs are located have been identified.  The predicted meteorological data for the relevant PATH grids from the PATH v2.1 model obtained from EPD’s website ([4]) were used for model input.  The relevant PATH grids for the representative ASRs are shown in Table 3.2.

AERMET has been run to generate AERMOD-ready meteorological data for AERMOD model input.  The land use parameters, including albedo, bowen ratio and surface roughness are required inputs for AERMET.  The land use of 1km from the identified ASRs within each PATH grid has been evaluated to determine the PATH-grid specific surface roughness values.  Eleven 10km x 10km regions have been evaluated to determine the values of albedo and bowen ratio in the respective regions.  The bowen ratio and albedo values of the region were applied to the representative ASRs that have been identified to correspond to that specific region.  Detailed calculations of albedo, bowen ratio and surface roughness are presented in Appendix 3A.  Land use maps illustrating the determination of the land use parameters are also shown in Appendix 3A.

The AERMET/ AERMOD model input parameters and assumptions for the assessment are summarised in Table 3.9.

Table 3.9   AERMET/ AERMOD Model Input Parameters and Assumptions

Input Parameters & Assumptions

Descriptions

Air dispersion model

      AERMOD

Type of source

      Point sources

Assessment parameter

      Maximum 1-hour NO2 and annual NO2

      Maximum 10-minute SO2 and maximum 24-hour SO2

      Maximum 24-hour RSP and annual RSP

      Maximum 24-hour FSP and annual FSP

Assessment Heights

      1.5m, 5m, 10m, 15m, 20m, 25m, 30m above ground level

      40m to 260m (at interval of 10m) above ground level

Meteorological data

      Weather Research and Forecasting Model (WRF) data in 2015 from the PATH v2.1 model to be used to input into AERMET to produce AERMOD-ready meteorological data

      52 PATH Grids (See Appendix 3A)

      Actual mixing heights recorded by the HKO in 2015 were in the range of 131m to 1,941m.  Mixing heights from WRF data which are lower than 131m or higher than 1,941m were adjusted to 131m and 1,941m, respectively

      Wind direction of 0ş was adjusted to 360ş

      Wind speed smaller than 1m s-1 was adjusted to 1m s-1

      Anemometer height of WRF data = 9m

3.7.4    Post-processing of Modelling Results

The hourly concentrations of NOx were predicted at the relevant assessment heights of the representative ASRs.  Ozone Limiting Method (OLM) was adopted for the conversion of NOx to NO2.  The initial NO2/NOx ratio for stack emissions of the Project was assumed to be 0.1([5]), with NO and NO2 comprising 90% and 10% of NOx, respectively.  The conversion of NOx to NO2 for stack emissions was calculated as follows:

 

[NO2]pred = 0.1x[NOX] pred + MIN {0.9x[NOX] pred, or (46/48)x[O3] bkgd}

where

[NO2] pred    =     the predicted NO2 concentration

[NOX] pred   =     is the predicted NOX concentration

MIN                  means the minimum of the two values within the brackets

[O3]bkgd      =     the representative O3 background concentration; (46/48) is the molecular weight of NO2 divided by the molecular weight of O3

As the proposed new OCGTs will tentatively commence operation starting 2025, the predicted ozone concentrations in 2025 in the relevant PATH grids obtained from the PATH v2.1 model were used for the conversion of NOx to NO2 in OLM.

The predicted hourly SO2 concentrations at the representative ASRs were converted into 10-minute SO2 concentrations as per the relevant AQO criterion.  According to the EPD’s “Guidelines on the Estimation of 10-minute Average SO2 Concentration for Air Quality Assessment in Hong Kong”, it is recommended that the stability-dependent multiplicative factors from Duffee et al., 1991([6]) be used.  The conversion factors adopted in this assessment for the different stability classes are shown in Table 3.10.

Table 3.10 Conversion Factors from 1-hour to 10-minutes Mean Concentrations

Pasquill Stability Class

Conversion Factor (1-hour to 10-minute)

A

2.45

B

2.45

C

1.82

D

1.43

E

1.35

F

1.35

Notes:

(a)   Reference to the EPD’s “Guidelines on the Estimation of 10-minute Average SO2 Concentration for Air Quality Assessment in Hong Kong”.

3.7.5    Assessment of Impacts

Hourly NO2, SO2, RSP and FSP concentrations at the relevant assessment heights of the representative ASRs under the “Without Project” and “With Project” scenarios were predicted.  Based on the predicted hourly results, the relevant time period averages of each air pollutant assessed were calculated at the relevant assessment heights of the ASRs.  The relevant time period averages assessed under the “Without Project” and “With Project” scenarios are as follows:

n  Maximum 1-hour NO2 and annual NO2;

n  Maximum 10-minute SO2 and maximum 24-hour SO2;

n  Maximum 24-hour RSP and annual RSP; and

n  Maximum 24-hour FSP and annual FSP

The predicted concentrations of the relevant time period averages at the relevant assessment heights of the representative ASRs under each of the four phases of “With Project” scenario were presented and compared against those under the “Without Project” scenario to evaluate the difference in air quality impacts (see Section 3.8.2 below).

3.8         Evaluation of Impacts

3.8.1    Decommissioning/ Demolition and Construction Phases

During decommissioning and demolition works, typical construction equipment such as electric breaker, flame cutting and other hand-held power mechanical equipment will be used.  No blasting or excavation works will be required.  Potential fugitive dust emissions arising from the decommissioning and demolition works are expected to be minor and localised. 

Major equipment and piping associated with the new units will be fully assembled off-site as far as practicable for subsequent installation on site, and thus associated civil works are expected to be minimal.  Also, foundation work is expected not required as the existing foundation piles and reinforced concrete structure will be reused to support the new units as far as practicable.  Therefore, potential fugitive dust emissions due to the construction of the new units and installation of equipment (e.g. inside GTAB) are expected to be minimal, if any.

Excavation works for the construction of new cable trenches of about 1.5m in width and 1,240m in length down to about 1.8m below ground and for the construction of the new staircase and lift down to about 5m below ground (footprint of about 10m x 5m) are required during the construction phase.  In addition, reconstruction works inside GTAB also requires minor excavation down to about 2.6m below ground over an area of about 200m2.  As the scale of excavation is relatively small and the quantity of excavated materials will be low, fugitive dust emissions arising from excavation works are expected to be minor.  The excavated materials will be temporarily stockpiled on site and covered with tarpaulin sheets to reduce potential fugitive dust emissions. 

Considering that potential dust emissions are limited and that the nearest ASR (outside of LPS) is at least 800m away from the Project site, adverse fugitive dust impact on ASRs outside of LPS due to the decommissioning/ demolition and construction works is not anticipated.  The Administration and Control Building within LPS is located about 110m to the east of the Project site.  With about 110m apart, there is sufficient separation distance between the Administration and Control Building and the Project site given that potential dust impacts would be limited and highly localised.  Adverse fugitive dust impact on HK Electric staff in the Administration and Control Building due to decommissioning/ demolition and construction works of the Project is not anticipated with the implementation of good construction site practices and relevant mitigation measures recommended in the Air Pollution Control (Construction Dust) Regulation. 

Mobile cranes and other typical construction equipment such as excavator, welding machine, electric breaker, grinder, flame cutting and other hand-held power mechanical equipment would be used during the decommissioning/ demolition and construction of the Project.  Given the demolition and construction works are relatively small scale and that the units are to be demolished and installed in phases, the number of construction plants deployed on site will be limited and the associated emissions from the operation of these construction plants are expected to be minor.  Requirements in the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation and Air Pollution Control (Fuel Restriction) Regulation will be followed to control the emissions from the construction plants.  Adverse air quality impact associated with the operation of the construction plants is not anticipated.

Construction plants and major equipment of the new units will be delivered via marine vessels to the LPS jetty, and then by construction vehicles to the Project site via existing roads within LPS.  Demolished equipment will also be transported off-site via marine vessels.  As the demolition and construction works associated with the Project are small scale, additional marine traffic for equipment transport during the decommissioning/ demolition and construction phases of the Project is expected to be limited (no more than 1 to 2 vessel trips within every 2 days).  With such limited number of vessel trips and requirements in Air Pollution Control (Marine Light Diesel) Regulation and Air Pollution Control (Fuel for Vessels) Regulation properly followed, adverse air quality impact with respect to marine vessel emissions associated with the Project is not anticipated.

3.8.2    Operation Phase

The predicted concentrations of maximum 1-hour NO2 and annual NO2, maximum 10-minute SO2 and maximum 24-hour SO2, maximum 24-hour RSP and annual RSP, as well as maximum 24-hour FSP and annual FSP under the “Without Project” scenario and “With Project” scenario under each of the four phases (i.e. Phase 1 to Phase 4) at the relevant assessment heights of each identified ASR are provided in Appendix 3B.  The difference in predicted impacts between the “Without Project” scenario and “With Project” scenario under each of the four phases (i.e. Phase 1 to Phase 4) at the relevant assessment heights of each identified ASR are also detailed in Appendix 3B.   The difference in predicted impacts between the “Without Project” scenario and “With Project scenario (Phase 1 to Phase 4) at all identified ASRs are summarised in Tables 3.11 to 3.14. 


 Table 3.11 Difference in Predicted Impacts between “Without Project” Scenario and “With Project” Scenario (Phase 1) at the Identified ASRs

ASR

Difference in Predicted Concentration (mg m-3)

Max. 1-hour NO2

Annual NO2

Max. 10-min SO2

Max. 24-hour SO2

Max. 24-hour RSP

Annual RSP

Max. 24-hour FSP

Annual FSP

A1

-22.71 to -22.67

-1.41 to -1.40

-3.64 to -3.63

-1.17 to -1.14

-1.32 to -1.29

-0.11

-1.32 to -1.29

-0.11

A2

-17.17 to -17.09

-0.81

-2.00 to -1.99

-0.59

-0.67

-0.06

-0.67

-0.06

A3

-20.20 to -19.71

-0.83 to -0.81

-4.59 to -4.47

-0.62 to -0.57

-0.68 to -0.63

-0.07 to -0.06

-0.68 to -0.63

-0.07 to -0.06

A4

-80.78 to -17.48

-1.00 to -0.59

-16.21 to -2.40

-1.33 to -0.19

-1.45 to -0.23

-0.11 to -0.05

-1.45 to -0.23

-0.11 to -0.05

A5

-17.26 to -17.24

-0.71

-2.64

-0.29

-0.35 to -0.34

-0.06

-0.35 to -0.34

-0.06

A6

-95.08 to -7.74

-0.66 to -0.61

-12.44 to -7.34

-1.39 to -0.73

-1.55 to -0.78

-0.07 to -0.05

-1.55 to -0.78

-0.07 to -0.05

A7

-12.76 to -12.45

-0.49 to -0.47

-1.48 to -1.44

-0.26

-0.30

-0.04

-0.30

-0.04

A8

-65.97 to -11.71

-0.72 to -0.42

-39.21 to -2.62

-2.17 to -0.20

-2.40 to -0.25

-0.14 to -0.03

-2.40 to -0.25

-0.14 to -0.03

A9

-107.26 to -11.03

-0.60 to -0.42

-16.47 to -1.94

-0.93 to -0.15

-1.05 to -0.18

-0.08 to -0.03

-1.05 to -0.18

-0.08 to -0.03

A10

-6.72 to -6.47

-0.40 to -0.39

-1.10

-0.27

-0.30

-0.03

-0.30

-0.03

A11

-138.55 to -10.37

-0.62 to -0.49

-16.79 to -7.91

-0.87 to -0.37

-0.90 to -0.40

-0.08 to -0.04

-0.90 to -0.40

-0.08 to -0.04

A12

-14.03 to -13.00

-0.21

-1.27 to -1.25

-0.12

-0.12 to -0.11

-0.02

-0.12 to -0.11

-0.02

A13

-51.82 to -13.99

-0.57 to -0.40

-10.68 to -2.62

-0.71 to -0.21

-0.77 to -0.25

-0.05 to -0.03

-0.77 to -0.25

-0.05 to -0.03

A14

-8.67 to -5.83

-0.20

-1.51 to -1.47

-0.07

-0.10 to -0.09

-0.02

-0.10 to -0.09

-0.02

A15

-73.87 to -9.84

-0.30 to -0.16

-9.77 to -1.36

-0.36 to -0.16

-0.30 to -0.18

-0.03 to -0.01

-0.30 to -0.18

-0.03 to -0.01

A16

-33.50 to -16.22

-0.71 to -0.45

-16.23 to -2.85

-1.50 to -0.25

-1.60 to -0.30

-0.07 to -0.04

-1.60 to -0.30

-0.07 to -0.04

A17

-7.19 to -6.08

-0.24 to -0.23

-1.56 to -1.47

-0.08 to -0.07

-0.10 to -0.09

-0.02

-0.10 to -0.09

-0.02

A18

-16.81 to -16.74

-0.33 to -0.31

-2.00 to -1.99

-0.17 to -0.16

-0.20

-0.03 to -0.02

-0.20

-0.03 to -0.02

A19

-19.37 to -19.22

-0.27

-3.13 to -3.12

-0.15

-0.18

-0.02

-0.18

-0.02

A20

-67.83 to -37.95

-0.34 to -0.28

-7.52 to -4.05

-0.45 to -0.24

-0.44 to -0.18

-0.03 to -0.02

-0.44 to -0.18

-0.03 to -0.02

A21

-13.37 to -13.23

-0.14

-1.51 to -1.50

-0.11

-0.13

-0.01

-0.13

-0.01

A22

-51.47 to -22.88

-0.89 to -0.55

-15.89 to -3.00

-0.99 to -0.28

-1.05 to -0.34

-0.09 to -0.04

-1.05 to -0.34

-0.09 to -0.04

A23

-66.44 to -19.69

-0.58 to -0.29

-17.46 to -2.35

-1.01 to -0.15

-1.06 to -0.17

-0.08 to -0.02

-1.06 to -0.17

-0.08 to -0.02

A24

-21.13 to -21.11

-0.25 to -0.24

-2.66

-0.13

-0.16

-0.02

-0.16

-0.02

A25

-15.80 to -15.67

-0.14

-2.09 to -2.03

-0.16

-0.18 to -0.17

-0.01

-0.18 to -0.17

-0.01

A26

-23.53 to -23.44

-0.12

-3.34 to -3.33

-0.18

-0.21

-0.01

-0.21

-0.01

A27

-13.41 to -13.39

-0.09 to -0.08

-1.60

-0.08 to -0.07

-0.09 to -0.08

-0.01

-0.09 to -0.08

-0.01

A28

-18.82 to -18.80

-0.10 to -0.09

-1.86

-0.10 to -0.09

-0.12

-0.01

-0.12

-0.01

A29

-25.25 to -12.29

-0.13 to -0.09

-2.35 to -1.47

-0.12 to -0.05

-0.10 to -0.06

-0.01

-0.10 to -0.06

-0.01

A30

-7.24 to -7.11

-0.13 to -0.11

-0.83 to -0.81

-0.08 to -0.07

-0.10 to -0.07

-0.01

-0.10 to -0.07

-0.01

A31

-36.76 to -9.05

-0.34 to -0.12

-4.82 to -1.05

-0.32 to -0.06

-0.36 to -0.07

-0.03 to -0.01

-0.36 to -0.07

-0.03 to -0.01

A32

-5.67 to -5.63

-0.14

-0.73 to -0.72

-0.06

-0.07

-0.01

-0.07

-0.01

A33

-42.30 to -14.10

-0.21 to -0.16

-6.23 to -2.07

-0.28 to -0.14

-0.33 to -0.12

-0.02 to -0.01

-0.33 to -0.12

-0.02 to -0.01

A34

-14.58 to -13.03

-0.22 to -0.18

-1.43 to -1.28

-0.11 to -0.10

-0.13 to -0.12

-0.02 to -0.01

-0.13 to -0.12

-0.02 to -0.01

A35

-9.44 to -9.31

-0.15 to -0.14

-1.14 to -1.12

-0.07

-0.08

-0.01

-0.08

-0.01

A36

-36.56 to -12.85

-0.36 to -0.17

-7.56 to -1.33

-0.87 to -0.11

-0.93 to -0.13

-0.03 to -0.01

-0.93 to -0.13

-0.03 to -0.01

A37

-70.63 to -2.58

-0.30 to -0.12

-11.56 to -1.17

-0.92 to -0.09

-1.05 to -0.11

-0.04 to -0.01

-1.05 to -0.11

-0.04 to -0.01

A38

-8.72 to -8.37

-0.10

-1.05

-0.07

-0.09 to -0.08

-0.01

-0.09 to -0.08

-0.01

A39

-7.80 to -7.71

-0.10

-0.91 to -0.90

-0.07 to -0.06

-0.08

-0.01

-0.08

-0.01

A40

-8.44 to -8.13

-0.09

-0.78 to -0.76

-0.06

-0.08

-0.01

-0.08

-0.01

A41

-8.43 to -8.01

-0.13 to -0.10

-0.81 to -0.80

-0.09 to -0.06

-0.09 to -0.07

-0.01

-0.09 to -0.07

-0.01

A42

-6.59 to -6.56

-0.12

-0.75

-0.09

-0.09

-0.01

-0.09

-0.01

A43

-23.72 to -10.46

-0.47 to -0.29

-2.60 to -0.90

-0.22 to -0.09

-0.24 to -0.11

-0.04 to -0.02

-0.24 to -0.11

-0.04 to -0.02

A44

-10.59 to -10.47

-0.27 to -0.26

-1.24 to -1.23

-0.11 to -0.09

-0.13 to -0.11

-0.02

-0.13 to -0.11

-0.02

A45

-13.23 to -13.22

-0.30 to -0.29

-2.18

-0.16 to -0.15

-0.19

-0.02

-0.19

-0.02

A46

-9.09 to -9.04

-0.22 to -0.21

-1.26

-0.11

-0.14 to -0.13

-0.02

-0.14 to -0.13

-0.02

A47

-8.97 to -8.91

-0.20

-1.04 to -1.03

-0.13

-0.15

-0.02

-0.15

-0.02

A48

-10.16 to -8.74

-0.26 to -0.22

-1.20 to -1.12

-0.10 to -0.08

-0.11 to -0.09

-0.02

-0.11 to -0.09

-0.02

A49

-13.57 to -13.17

-0.35 to -0.34

-2.16 to -2.02

-0.20

-0.25 to -0.24

-0.03

-0.25 to -0.24

-0.03

A50

-14.42

-0.23

-1.71

-0.11

-0.13

-0.02

-0.13

-0.02

A51

-16.65 to -16.58

-0.31

-2.25 to -2.19

-0.16

-0.18

-0.02

-0.18

-0.02

A52

-12.52 to -12.49

-0.22

-1.97

-0.13

-0.16

-0.02

-0.16

-0.02

A53

-9.78 to -9.66

-0.11

-1.16 to -1.15

-0.07

-0.08

-0.01

-0.08

-0.01

A54

-23.13 to -23.10

-0.36 to -0.29

-2.66

-0.20 to -0.14

-0.21 to -0.17

-0.03 to -0.02

-0.21 to -0.17

-0.03 to -0.02

A55

-13.67 to -13.57

-0.22

-1.58 to -1.56

-0.11

-0.12

-0.02

-0.12

-0.02

A56

-20.76

-0.22

-2.43

-0.12

-0.15

-0.02

-0.15

-0.02

A57

-20.04

-0.29 to -0.28

-2.35

-0.16

-0.19

-0.02

-0.19

-0.02

A58

-14.28 to -14.27

-0.31

-2.11

-0.15

-0.18

-0.02

-0.18

-0.02

A59

-11.61 to -10.52

-0.22

-1.84 to -1.78

-0.12 to -0.10

-0.11 to -0.08

-0.02

-0.11 to -0.08

-0.02

A60

-39.05 to -10.74

-0.41 to -0.24

-5.49 to -1.26

-0.41 to -0.08

-0.46 to -0.10

-0.04 to -0.02

-0.46 to -0.10

-0.04 to -0.02

A61

-5.23 to -5.00

-0.26 to -0.25

-5.60 to -5.05

-0.23 to -0.19

-0.31 to -0.27

-0.02

-0.31 to -0.27

-0.02

Notes:

(a)   Figures shown are the range of difference in predicted pollutant concentrations among all relevant assessment heights of each ASR between “With Project” scenario and “Without Project” scenario.

(b)   Negative values represent a reduction of predicted pollutant concentrations due to the new OCGTs (i.e. “With Project” scenario) compared with the existing units (i.e. “Without Project” scenario).

 

Table 3.12 Difference in Predicted Impacts between “Without Project” Scenario and “With Project” Scenario (Phase 2) at the Identified ASRs

ASR

Difference in Predicted Concentration (mg m-3)

Max. 1-hour NO2

Annual NO2

Max. 10-min SO2

Max. 24-hour SO2

Max. 24-hour RSP

Annual RSP

Max. 24-hour FSP

Annual FSP

A1

-26.67 to -26.63

-1.51 to -1.50

-3.55 to -3.54

-1.13 to -1.11

-1.34 to -1.32

-0.12

-1.34 to -1.32

-0.12

A2

-19.84 to -19.67

-0.88

-1.97

-0.58

-0.74

-0.07

-0.74

-0.07

A3

-26.87 to -26.31

-0.80 to -0.78

-4.56 to -4.44

-0.61 to -0.56

-0.72 to -0.67

-0.06

-0.72 to -0.67

-0.06

A4

-82.54 to -20.58

-1.14 to -0.70

-16.15 to -2.33

-1.33 to -0.18

-1.61 to -0.27

-0.12 to -0.05

-1.61 to -0.27

-0.12 to -0.05

A5

-20.87 to -20.84

-0.83 to -0.82

-2.57

-0.28

-0.40 to -0.39

-0.06

-0.40 to -0.39

-0.06

A6

-106.35 to -10.39

-0.74 to -0.69

-12.30 to -7.30

-1.36 to -0.72

-1.68 to -0.82

-0.08 to -0.05

-1.68 to -0.82

-0.08 to -0.05

A7

-14.66 to -14.33

-0.57 to -0.54

-1.44 to -1.39

-0.25

-0.34 to -0.33

-0.04

-0.34 to -0.33

-0.04

A8

-70.98 to -18.12

-0.82 to -0.49

-38.67 to -2.57

-2.11 to -0.20

-2.54 to -0.29

-0.15 to -0.04

-2.54 to -0.29

-0.15 to -0.04

A9

-127.25 to -15.66

-0.69 to -0.50

-16.26 to -1.90

-0.91 to -0.14

-1.12 to -0.21

-0.09 to -0.04

-1.12 to -0.21

-0.09 to -0.04

A10

-8.13 to -7.94

-0.45 to -0.44

-1.07

-0.26

-0.33

-0.03

-0.33

-0.03

A11

-138.09 to -12.87

-0.70 to -0.58

-16.50 to -7.69

-0.84 to -0.35

-1.01 to -0.44

-0.09 to -0.05

-1.01 to -0.44

-0.09 to -0.05

A12

-18.82 to -17.90

-0.25

-1.26 to -1.24

-0.12

-0.14 to -0.13

-0.02

-0.14 to -0.13

-0.02

A13

-62.22 to -17.14

-0.65 to -0.46

-10.70 to -2.55

-0.71 to -0.20

-0.84 to -0.28

-0.06 to -0.03

-0.84 to -0.28

-0.06 to -0.03

A14

-13.57 to -10.47

-0.25

-1.46 to -1.42

-0.06

-0.13 to -0.12

-0.02

-0.13 to -0.12

-0.02

A15

-81.08 to -11.74

-0.34 to -0.18

-9.70 to -1.32

-0.35 to -0.15

-0.33 to -0.20

-0.03 to -0.01

-0.33 to -0.20

-0.03 to -0.01

A16

-40.78 to -17.76

-0.80 to -0.53

-16.17 to -2.78

-1.48 to -0.24

-1.67 to -0.34

-0.08 to -0.04

-1.67 to -0.34

-0.08 to -0.04

A17

-13.20 to -11.75

-0.29

-1.46 to -1.41

-0.08 to -0.07

-0.16 to -0.15

-0.02

-0.16 to -0.15

-0.02

A18

-19.74 to -19.69

-0.39 to -0.37

-1.96 to -1.95

-0.16

-0.23

-0.03

-0.23

-0.03

A19

-23.94 to -23.80

-0.32

-3.07 to -3.06

-0.14

-0.21

-0.02

-0.21

-0.02

A20

-73.75 to -41.70

-0.38 to -0.32

-7.47 to -4.00

-0.44 to -0.24

-0.47 to -0.21

-0.03

-0.47 to -0.21

-0.03

A21

-15.95 to -15.81

-0.17

-1.48 to -1.46

-0.10

-0.15

-0.01

-0.15

-0.01

A22

-56.98 to -27.62

-1.01 to -0.63

-15.83 to -2.92

-0.98 to -0.28

-1.11 to -0.39

-0.10 to -0.05

-1.11 to -0.39

-0.10 to -0.05

A23

-75.18 to -22.82

-0.66 to -0.34

-17.03 to -2.29

-0.99 to -0.14

-1.11 to -0.19

-0.09 to -0.03

-1.11 to -0.19

-0.09 to -0.03

A24

-25.04 to -25.03

-0.29 to -0.28

-2.59

-0.13

-0.19

-0.02

-0.19

-0.02

A25

-18.69 to -18.55

-0.16

-2.07 to -2.01

-0.16

-0.19

-0.01

-0.19

-0.01

A26

-27.59 to -27.49

-0.14

-3.28 to -3.27

-0.18 to -0.17

-0.24

-0.01

-0.24

-0.01

A27

-15.77 to -15.75

-0.10

-1.56 to -1.55

-0.08 to -0.07

-0.10 to -0.09

-0.01

-0.10 to -0.09

-0.01

A28

-21.84 to -21.82

-0.12 to -0.11

-1.82

-0.10 to -0.09

-0.14 to -0.13

-0.01

-0.14 to -0.13

-0.01

A29

-27.21 to -14.25

-0.15 to -0.10

-2.31 to -1.43

-0.12 to -0.05

-0.11 to -0.07

-0.01

-0.11 to -0.07

-0.01

A30

-8.68 to -8.55

-0.15 to -0.13

-0.80 to -0.79

-0.08 to -0.07

-0.12 to -0.09

-0.01

-0.12 to -0.09

-0.01

A31

-41.39 to -10.59

-0.38 to -0.15

-4.78 to -1.02

-0.32 to -0.06

-0.39 to -0.09

-0.03 to -0.01

-0.39 to -0.09

-0.03 to -0.01

A32

-6.87 to -6.80

-0.17

-0.70

-0.06

-0.09 to -0.08

-0.01

-0.09 to -0.08

-0.01

A33

-49.80 to -15.63

-0.24 to -0.18

-6.07 to -2.04

-0.28 to -0.14

-0.35 to -0.13

-0.02 to -0.01

-0.35 to -0.13

-0.02 to -0.01

A34

-16.89 to -15.74

-0.26 to -0.22

-1.38 to -1.23

-0.10 to -0.09

-0.15 to -0.14

-0.02

-0.15 to -0.14

-0.02

A35

-11.00 to -10.88

-0.18 to -0.17

-1.12 to -1.10

-0.07 to -0.06

-0.09

-0.01

-0.09

-0.01

A36

-38.88 to -16.36

-0.41 to -0.20

-7.49 to -1.30

-0.86 to -0.10

-0.98 to -0.15

-0.04 to -0.02

-0.98 to -0.15

-0.04 to -0.02

A37

-71.34 to -3.37

-0.35 to -0.15

-11.29 to -1.14

-0.91 to -0.09

-1.21 to -0.12

-0.05 to -0.01

-1.21 to -0.12

-0.05 to -0.01

A38

-10.11 to -9.71

-0.12

-1.03

-0.07

-0.10

-0.01

-0.10

-0.01

A39

-9.20 to -9.10

-0.12

-0.88 to -0.87

-0.07 to -0.06

-0.10 to -0.09

-0.01

-0.10 to -0.09

-0.01

A40

-10.05 to -9.70

-0.11

-0.76 to -0.74

-0.06

-0.09

-0.01

-0.09

-0.01

A41

-10.04 to -9.56

-0.15 to -0.12

-0.79 to -0.78

-0.08 to -0.05

-0.10 to -0.08

-0.01

-0.10 to -0.08

-0.01

A42

-7.96 to -7.94

-0.14

-0.73

-0.08

-0.10

-0.01

-0.10

-0.01

A43

-24.71 to -12.33

-0.54 to -0.35

-2.58 to -0.87

-0.22 to -0.09

-0.26 to -0.13

-0.04 to -0.03

-0.26 to -0.13

-0.04 to -0.03

A44

-12.28 to -12.13

-0.33 to -0.31

-1.20 to -1.19

-0.11 to -0.08

-0.15 to -0.12

-0.02

-0.15 to -0.12

-0.02

A45

-16.23 to -16.22

-0.36

-2.13

-0.15

-0.22 to -0.21

-0.03

-0.22 to -0.21

-0.03

A46

-11.54 to -11.50

-0.26

-1.24 to -1.23

-0.11

-0.16

-0.02

-0.16

-0.02

A47

-10.76 to -10.69

-0.24 to -0.23

-1.01 to -1.00

-0.13

-0.17

-0.02

-0.17

-0.02

A48

-11.94 to -10.40

-0.30 to -0.26

-1.18 to -1.09

-0.10 to -0.08

-0.13 to -0.10

-0.02

-0.13 to -0.10

-0.02

A49

-16.28 to -15.87

-0.42

-2.11 to -1.98

-0.20

-0.29

-0.03

-0.29

-0.03

A50

-17.12 to -17.11

-0.27

-1.67

-0.11

-0.16

-0.02

-0.16

-0.02

A51

-19.41 to -19.31

-0.37

-2.20 to -2.15

-0.16 to -0.15

-0.22 to -0.21

-0.03

-0.22 to -0.21

-0.03

A52

-15.71 to -15.69

-0.27

-1.93

-0.13

-0.19

-0.02

-0.19

-0.02

A53

-11.40 to -11.25

-0.13

-1.14 to -1.13

-0.06

-0.09

-0.01

-0.09

-0.01

A54

-27.80 to -27.79

-0.42 to -0.34

-2.60 to -2.59

-0.20 to -0.14

-0.23 to -0.19

-0.03

-0.23 to -0.19

-0.03

A55

-16.28 to -16.18

-0.26

-1.54 to -1.53

-0.11

-0.14

-0.02

-0.14

-0.02

A56

-24.61

-0.26

-2.38

-0.12

-0.17

-0.02

-0.17

-0.02

A57

-23.72

-0.34 to -0.33

-2.29

-0.15

-0.22

-0.03

-0.22

-0.03

A58

-17.29 to -17.28

-0.37

-2.05

-0.15

-0.21

-0.03

-0.21

-0.03

A59

-16.64 to -15.79

-0.27 to -0.26

-1.75 to -1.69

-0.11 to -0.09

-0.14 to -0.11

-0.02

-0.14 to -0.11

-0.02

A60

-44.00 to -12.53

-0.48 to -0.29

-5.39 to -1.23

-0.40 to -0.08

-0.51 to -0.11

-0.05 to -0.02

-0.51 to -0.11

-0.05 to -0.02

A61

-7.10 to -6.82

-0.31

-5.53 to -4.98

-0.21 to -0.18

-0.36 to -0.33

-0.03

-0.36 to -0.33

-0.03

Notes:

(a)   Figures shown are the range of difference in predicted pollutant concentrations among all relevant assessment heights of each ASR between “With Project” scenario and “Without Project” scenario.

(b)   Negative values represent a reduction of predicted pollutant concentrations due to the new OCGTs (i.e. “With Project” scenario) compared with the existing units (i.e. “Without Project” scenario).

 

Table 3.13 Difference in Predicted Impacts between “Without Project” Scenario and “With Project” Scenario (Phase 3) at the Identified ASRs

ASR

Difference in Predicted Concentration (mg m-3)

Max. 1-hour NO2

Annual NO2

Max. 10-min SO2

Max. 24-hour SO2

Max. 24-hour RSP

Annual RSP

Max. 24-hour FSP

Annual FSP

A1

-30.62 to -30.58

-1.62 to -1.61

-3.46 to -3.45

-1.09 to -1.07

-1.37 to -1.34

-0.12

-1.37 to -1.34

-0.12

A2

-22.05 to -21.89

-0.96

-1.94

-0.57

-0.81

-0.07

-0.81

-0.07

A3

-31.51 to -30.72

-0.78 to -0.76

-4.43 to -4.33

-0.59 to -0.55

-0.75 to -0.70

-0.06

-0.75 to -0.70

-0.06

A4

-84.28 to -23.71

-1.27 to -0.81

-16.07 to -2.26

-1.32 to -0.18

-1.77 to -0.31

-0.13 to -0.06

-1.77 to -0.31

-0.13 to -0.06

A5

-24.48 to -24.44

-0.94

-2.51 to -2.50

-0.27

-0.45

-0.07

-0.45

-0.07

A6

-115.74 to -19.80

-0.83 to -0.77

-11.79 to -7.26

-1.34 to -0.71

-1.82 to -0.85

-0.09 to -0.06

-1.82 to -0.85

-0.09 to -0.06

A7

-16.60 to -16.24

-0.64 to -0.62

-1.39 to -1.35

-0.25

-0.37

-0.05

-0.37

-0.05

A8

-90.16 to -22.61

-0.92 to -0.56

-37.77 to -2.51

-2.06 to -0.19

-2.63 to -0.33

-0.16 to -0.04

-2.63 to -0.33

-0.16 to -0.04

A9

-146.61 to -24.09

-0.80 to -0.58

-16.03 to -1.87

-0.89 to -0.14

-1.19 to -0.24

-0.10 to -0.04

-1.19 to -0.24

-0.10 to -0.04

A10

-10.74 to -10.54

-0.51 to -0.50

-1.04

-0.26

-0.37 to -0.36

-0.04

-0.37 to -0.36

-0.04

A11

-136.06 to -15.40

-0.79 to -0.66

-16.26 to -7.03

-0.82 to -0.32

-1.16 to -0.48

-0.10 to -0.05

-1.16 to -0.48

-0.10 to -0.05

A12

-23.49 to -22.71

-0.30 to -0.29

-1.21

-0.12 to -0.11

-0.16 to -0.15

-0.02

-0.16 to -0.15

-0.02

A13

-72.33 to -20.32

-0.73 to -0.53

-10.57 to -2.49

-0.70 to -0.20

-0.91 to -0.32

-0.06 to -0.04

-0.91 to -0.32

-0.06 to -0.04

A14

-18.42 to -15.06

-0.30

-1.42 to -1.37

-0.06 to -0.05

-0.16 to -0.15

-0.02

-0.16 to -0.15

-0.02

A15

-88.10 to -13.65

-0.38 to -0.20

-9.58 to -1.28

-0.34 to -0.15

-0.36 to -0.21

-0.03 to -0.01

-0.36 to -0.21

-0.03 to -0.01

A16

-47.90 to -19.26

-0.90 to -0.61

-16.10 to -2.71

-1.47 to -0.24

-1.74 to -0.38

-0.09 to -0.04

-1.74 to -0.38

-0.09 to -0.04

A17

-17.90 to -15.85

-0.35 to -0.34

-1.36 to -1.31

-0.07 to -0.06

-0.23 to -0.21

-0.03

-0.23 to -0.21

-0.03

A18

-22.66 to -22.63

-0.45 to -0.42

-1.92 to -1.91

-0.16

-0.26 to -0.25

-0.03

-0.26 to -0.25

-0.03

A19

-28.50 to -28.37

-0.37

-3.01 to -3.00

-0.14

-0.24

-0.03

-0.24

-0.03

A20

-79.66 to -45.44

-0.43 to -0.36

-7.41 to -3.94

-0.44 to -0.23

-0.49 to -0.23

-0.04 to -0.03

-0.49 to -0.23

-0.04 to -0.03

A21

-18.52 to -18.39

-0.20 to -0.19

-1.44 to -1.43

-0.10

-0.18 to -0.17

-0.01

-0.18 to -0.17

-0.01

A22

-60.14 to -32.32

-1.12 to -0.72

-15.76 to -2.84

-0.96 to -0.27

-1.18 to -0.44

-0.11 to -0.05

-1.18 to -0.44

-0.11 to -0.05

A23

-83.90 to -25.96

-0.73 to -0.39

-16.61 to -2.24

-0.97 to -0.14

-1.17 to -0.21

-0.09 to -0.03

-1.17 to -0.21

-0.09 to -0.03

A24

-28.95 to -28.94

-0.33 to -0.32

-2.52

-0.13

-0.22

-0.02

-0.22

-0.02

A25

-21.52 to -21.37

-0.17

-2.05 to -1.99

-0.16

-0.20

-0.01

-0.20

-0.01

A26

-31.64 to -31.54

-0.16

-3.21

-0.17

-0.27

-0.01

-0.27

-0.01

A27

-18.15 to -18.12

-0.12

-1.51

-0.07 to -0.06

-0.11 to -0.10

-0.01

-0.11 to -0.10

-0.01

A28

-24.86 to -24.84

-0.13

-1.78 to -1.77

-0.09

-0.16 to -0.15

-0.01

-0.16 to -0.15

-0.01

A29

-29.17 to -16.21

-0.17 to -0.12

-2.27 to -1.39

-0.12 to -0.05

-0.12 to -0.08

-0.01

-0.12 to -0.08

-0.01

A30

-10.13 to -9.99

-0.18 to -0.15

-0.78 to -0.77

-0.08 to -0.07

-0.13 to -0.10

-0.01

-0.13 to -0.10

-0.01

A31

-45.99 to -12.13

-0.43 to -0.17

-4.73 to -0.99

-0.32 to -0.06

-0.42 to -0.10

-0.04 to -0.01

-0.42 to -0.10

-0.04 to -0.01

A32

-8.06 to -7.98

-0.20

-0.68 to -0.67

-0.06

-0.10

-0.01

-0.10

-0.01

A33

-51.87 to -17.17

-0.28 to -0.20

-5.94 to -2.01

-0.27 to -0.14

-0.36 to -0.15

-0.02

-0.36 to -0.15

-0.02

A34

-19.21 to -18.45

-0.30 to -0.26

-1.34 to -1.19

-0.10 to -0.09

-0.17 to -0.16

-0.02

-0.17 to -0.16

-0.02

A35

-12.55 to -12.45

-0.21 to -0.20

-1.10 to -1.08

-0.07 to -0.06

-0.11 to -0.10

-0.02 to -0.01

-0.11 to -0.10

-0.02 to -0.01

A36

-41.21 to -18.65

-0.46 to -0.24

-7.43 to -1.26

-0.85 to -0.10

-1.04 to -0.17

-0.04 to -0.02

-1.04 to -0.17

-0.04 to -0.02

A37

-72.07 to -4.21

-0.41 to -0.17

-11.02 to -1.11

-0.90 to -0.08

-1.39 to -0.13

-0.06 to -0.01

-1.39 to -0.13

-0.06 to -0.01

A38

-11.52 to -11.06

-0.14

-1.01

-0.07 to -0.06

-0.12 to -0.11

-0.01

-0.12 to -0.11

-0.01

A39

-10.61 to -10.49

-0.14

-0.86 to -0.85

-0.06

-0.11

-0.01

-0.11

-0.01

A40

-11.67 to -11.27

-0.13 to -0.12

-0.74 to -0.72

-0.06

-0.11 to -0.10

-0.01

-0.11 to -0.10

-0.01

A41

-11.65 to -11.10

-0.18 to -0.14

-0.76 to -0.75

-0.08 to -0.05

-0.11 to -0.09

-0.01

-0.11 to -0.09

-0.01

A42

-9.33 to -9.31

-0.16

-0.71

-0.08

-0.11

-0.01

-0.11

-0.01

A43

-27.17 to -14.21

-0.62 to -0.42

-2.56 to -0.85

-0.21 to -0.08

-0.28 to -0.15

-0.05 to -0.03

-0.28 to -0.15

-0.05 to -0.03

A44

-13.98 to -13.79

-0.39 to -0.37

-1.17 to -1.16

-0.10 to -0.08

-0.17 to -0.14

-0.03

-0.17 to -0.14

-0.03

A45

-19.21 to -19.20

-0.42

-2.08

-0.15

-0.24

-0.03

-0.24

-0.03

A46

-13.98 to -13.94

-0.31

-1.21

-0.10

-0.19

-0.02

-0.19

-0.02

A47

-12.54 to -12.46

-0.27

-0.98 to -0.97

-0.13

-0.19

-0.02

-0.19

-0.02

A48

-13.71 to -12.05

-0.34 to -0.30

-1.15 to -1.07

-0.09 to -0.08

-0.14 to -0.12

-0.03 to -0.02

-0.14 to -0.12

-0.03 to -0.02

A49

-18.98 to -18.57

-0.49

-2.06 to -1.94

-0.19

-0.33

-0.04

-0.33

-0.04

A50

-19.81

-0.31

-1.63

-0.11

-0.18

-0.02

-0.18

-0.02

A51

-22.18 to -22.06

-0.43

-2.16 to -2.10

-0.15

-0.25 to -0.24

-0.03

-0.25 to -0.24

-0.03

A52

-18.90 to -18.88

-0.32

-1.89 to -1.88

-0.12

-0.21

-0.02

-0.21

-0.02

A53

-13.02 to -12.83

-0.16 to -0.15

-1.11 to -1.10

-0.06

-0.10

-0.01

-0.10

-0.01

A54

-32.47 to -32.44

-0.48 to -0.40

-2.53

-0.19 to -0.14

-0.25 to -0.22

-0.04 to -0.03

-0.25 to -0.22

-0.04 to -0.03

A55

-18.89 to -18.80

-0.30

-1.50 to -1.49

-0.11

-0.16

-0.02

-0.16

-0.02

A56

-28.46 to -28.45

-0.30

-2.32

-0.12

-0.20

-0.02

-0.20

-0.02

A57

-27.39

-0.39 to -0.38

-2.24

-0.15

-0.25

-0.03

-0.25

-0.03

A58

-20.29

-0.43

-2.00

-0.15

-0.24

-0.03

-0.24

-0.03

A59

-21.62 to -20.99

-0.33 to -0.31

-1.67 to -1.61

-0.10 to -0.08

-0.16 to -0.13

-0.02

-0.16 to -0.13

-0.02

A60

-51.30 to -14.34

-0.55 to -0.34

-5.30 to -1.20

-0.40 to -0.08

-0.56 to -0.13

-0.05 to -0.02

-0.56 to -0.13

-0.05 to -0.02

A61

-8.92 to -8.60

-0.37 to -0.36

-5.45 to -4.90

-0.20 to -0.17

-0.41 to -0.38

-0.03

-0.41 to -0.38

-0.03

Notes:

(a)   Figures shown are the range of difference in predicted pollutant concentrations among all relevant assessment heights of each ASR between “With Project” scenario and “Without Project” scenario.

(b)   Negative values represent a reduction of predicted pollutant concentrations due to the new OCGTs (i.e. “With Project” scenario) compared with the existing units (i.e. “Without Project” scenario).

 

Table 3.14         Difference in Predicted Impacts between “Without Project” Scenario and “With Project” Scenario (Phase 4) at the Identified ASRs

ASR

Difference in Predicted Concentration (mg m-3)

Max. 1-hour NO2

Annual NO2

Max. 10-min SO2

Max. 24-hour SO2

Max. 24-hour RSP

Annual RSP

Max. 24-hour FSP

Annual FSP

A1

-34.55 to -34.48

-1.76 to -1.75

-3.40 to -3.39

-1.08 to -1.06

-1.47 to -1.44

-0.13

-1.47 to -1.44

-0.13

A2

-24.41 to -24.25

-1.05

-1.90 to -1.89

-0.56

-0.88

-0.08

-0.88

-0.08

A3

-35.62 to -34.84

-0.82 to -0.80

-4.37 to -4.26

-0.59 to -0.54

-0.80 to -0.74

-0.06

-0.80 to -0.74

-0.06

A4

-85.67 to -27.22

-1.42 to -0.93

-15.90 to -2.20

-1.31 to -0.17

-1.89 to -0.34

-0.14 to -0.07

-1.89 to -0.34

-0.14 to -0.07

A5

-27.96 to -27.91

-1.06

-2.44

-0.27 to -0.26

-0.50

-0.08

-0.50

-0.08

A6

-121.71 to -41.45

-0.93 to -0.85

-11.57 to -7.19

-1.32 to -0.71

-1.99 to -0.89

-0.10 to -0.06

-1.99 to -0.89

-0.10 to -0.06

A7

-18.79 to -18.43

-0.72 to -0.69

-1.36 to -1.31

-0.24

-0.41 to -0.40

-0.05

-0.41 to -0.40

-0.05

A8

-103.04 to -25.94

-1.03 to -0.64

-37.26 to -2.46

-2.03 to -0.19

-2.82 to -0.36

-0.18 to -0.05

-2.82 to -0.36

-0.18 to -0.05

A9

-155.65 to -27.29

-0.90 to -0.66

-15.76 to -1.81

-0.87 to -0.14

-1.29 to -0.27

-0.11 to -0.05

-1.29 to -0.27

-0.11 to -0.05

A10

-13.25 to -13.04

-0.56 to -0.55

-1.01

-0.25

-0.40

-0.04

-0.40

-0.04

A11

-142.24 to -18.35

-0.88 to -0.76

-16.03 to -6.62

-0.80 to -0.30

-1.31 to -0.52

-0.11 to -0.06

-1.31 to -0.52

-0.11 to -0.06

A12

-26.63 to -26.48

-0.35 to -0.34

-1.17

-0.11

-0.19 to -0.18

-0.02

-0.19 to -0.18

-0.02

A13

-74.81 to -23.69

-0.82 to -0.60

-10.48 to -2.43

-0.69 to -0.19

-0.96 to -0.35

-0.07 to -0.04

-0.96 to -0.35

-0.07 to -0.04

A14

-22.95 to -19.35

-0.36 to -0.35

-1.36 to -1.31

-0.05 to -0.04

-0.20 to -0.18

-0.03

-0.20 to -0.18

-0.03

A15

-93.40 to -15.69

-0.42 to -0.23

-9.49 to -1.25

-0.33 to -0.15

-0.40 to -0.23

-0.04 to -0.02

-0.40 to -0.23

-0.04 to -0.02

A16

-53.66 to -20.48

-1.01 to -0.69

-15.96 to -2.65

-1.46 to -0.23

-1.82 to -0.42

-0.10 to -0.05

-1.82 to -0.42

-0.10 to -0.05

A17

-23.11 to -20.74

-0.42 to -0.41

-1.29 to -1.24

-0.06 to -0.05

-0.28 to -0.25

-0.03

-0.28 to -0.25

-0.03

A18

-25.49 to -25.46

-0.51 to -0.48

-1.88 to -1.86

-0.16 to -0.15

-0.29 to -0.28

-0.04 to -0.03

-0.29 to -0.28

-0.04 to -0.03

A19

-32.96 to -32.85

-0.42

-2.94 to -2.93

-0.14 to -0.13

-0.27

-0.03

-0.27

-0.03

A20

-85.33 to -49.10

-0.48 to -0.41

-7.34 to -3.89

-0.43 to -0.23

-0.52 to -0.26

-0.04 to -0.03

-0.52 to -0.26

-0.04 to -0.03

A21

-21.01 to -20.88

-0.22

-1.41 to -1.39

-0.10

-0.20

-0.02

-0.20

-0.02

A22

-61.15 to -36.44

-1.25 to -0.82

-15.64 to -2.77

-0.95 to -0.26

-1.26 to -0.49

-0.12 to -0.06

-1.26 to -0.49

-0.12 to -0.06

A23

-92.34 to -29.14

-0.82 to -0.45

-16.40 to -2.19

-0.96 to -0.14

-1.24 to -0.24

-0.10 to -0.03

-1.24 to -0.24

-0.10 to -0.03

A24

-32.75 to -32.74

-0.37 to -0.36

-2.45

-0.12

-0.24

-0.03

-0.24

-0.03

A25

-23.82 to -23.66

-0.19 to -0.18

-2.01 to -1.95

-0.16 to -0.15

-0.21

-0.01

-0.21

-0.01

A26

-35.68 to -35.57

-0.18 to -0.17

-3.15 to -3.14

-0.17

-0.30

-0.01

-0.30

-0.01

A27

-19.37 to -19.14

-0.13

-1.48 to -1.47

-0.07 to -0.06

-0.12 to -0.11

-0.01

-0.12 to -0.11

-0.01

A28

-27.90 to -27.89

-0.15

-1.73

-0.09

-0.18 to -0.17

-0.01

-0.18 to -0.17

-0.01

A29

-31.18 to -18.23

-0.19 to -0.13

-2.23 to -1.35

-0.12 to -0.05

-0.13 to -0.09

-0.01

-0.13 to -0.09

-0.01

A30

-11.56 to -11.40

-0.20 to -0.18

-0.76 to -0.74

-0.08 to -0.07

-0.14 to -0.11

-0.01

-0.14 to -0.11

-0.01

A31

-50.30 to -13.76

-0.48 to -0.20

-4.68 to -0.96

-0.31 to -0.06

-0.45 to -0.11

-0.04 to -0.01

-0.45 to -0.11

-0.04 to -0.01

A32

-9.28 to -9.17

-0.23 to -0.22

-0.66 to -0.65

-0.05

-0.11

-0.02

-0.11

-0.02

A33

-55.70 to -18.94

-0.32 to -0.23

-5.84 to -1.99

-0.26 to -0.13

-0.40 to -0.17

-0.03 to -0.02

-0.40 to -0.17

-0.03 to -0.02

A34

-21.69 to -21.09

-0.34 to -0.30

-1.30 to -1.15

-0.10 to -0.09

-0.19 to -0.18

-0.02

-0.19 to -0.18

-0.02

A35

-14.02 to -13.94

-0.24 to -0.23

-1.08 to -1.06

-0.07 to -0.06

-0.12

-0.02

-0.12

-0.02

A36

-43.62 to -21.03

-0.52 to -0.28

-7.37 to -1.23

-0.84 to -0.10

-1.09 to -0.20

-0.05 to -0.02

-1.09 to -0.20

-0.05 to -0.02

A37

-76.22 to -6.84

-0.46 to -0.20

-10.82 to -1.08

-0.89 to -0.05

-1.54 to -0.15

-0.06 to -0.01

-1.54 to -0.15

-0.06 to -0.01

A38

-13.05 to -12.54

-0.16

-0.99 to -0.98

-0.07 to -0.06

-0.13

-0.01

-0.13

-0.01

A39

-12.08 to -11.95

-0.16

-0.84 to -0.83

-0.06

-0.13 to -0.12

-0.01

-0.13 to -0.12

-0.01

A40

-13.29 to -12.84

-0.15 to -0.14

-0.72 to -0.70

-0.06

-0.12

-0.01

-0.12

-0.01

A41

-13.20 to -12.59

-0.20 to -0.16

-0.74 to -0.73

-0.08 to -0.05

-0.12 to -0.10

-0.01

-0.12 to -0.10

-0.01

A42

-10.66 to -10.63

-0.18

-0.69

-0.08

-0.12

-0.01

-0.12

-0.01

A43

-29.47 to -16.08

-0.69 to -0.48

-2.53 to -0.82

-0.21 to -0.08

-0.31 to -0.17

-0.05 to -0.03

-0.31 to -0.17

-0.05 to -0.03

A44

-15.81 to -15.60

-0.44 to -0.42

-1.14 to -1.13

-0.10 to -0.08

-0.19 to -0.16

-0.03

-0.19 to -0.16

-0.03

A45

-21.97 to -21.96

-0.48

-2.02

-0.14

-0.27

-0.04

-0.27

-0.04

A46

-16.28 to -16.23

-0.35

-1.18 to -1.17

-0.10

-0.21

-0.03

-0.21

-0.03

A47

-14.15 to -14.06

-0.31

-0.95 to -0.94

-0.13

-0.21

-0.02

-0.21

-0.02

A48

-15.44 to -13.70

-0.38 to -0.34

-1.12 to -1.04

-0.09 to -0.08

-0.16 to -0.13

-0.03 to -0.02

-0.16 to -0.13

-0.03 to -0.02

A49

-21.64 to -21.23

-0.56

-2.01 to -1.89

-0.19

-0.37 to -0.36

-0.04

-0.37 to -0.36

-0.04

A50

-22.51

-0.35

-1.59 to -1.58

-0.10

-0.20

-0.03

-0.20

-0.03

A51

-25.12 to -24.97

-0.48

-2.10 to -2.05

-0.15

-0.27

-0.04

-0.27

-0.04

A52

-21.95 to -21.93

-0.36

-1.84 to -1.83

-0.12

-0.24

-0.03

-0.24

-0.03

A53

-14.65 to -14.42

-0.18

-1.09 to -1.08

-0.06

-0.11

-0.01

-0.11

-0.01

A54

-36.94 to -36.89

-0.54 to -0.45

-2.46

-0.19 to -0.13

-0.28 to -0.24

-0.04 to -0.03

-0.28 to -0.24

-0.04 to -0.03

A55

-21.45 to -21.36

-0.34

-1.46 to -1.44

-0.11 to -0.10

-0.18

-0.02

-0.18

-0.02

A56

-32.19

-0.34

-2.26

-0.11

-0.22

-0.02

-0.22

-0.02

A57

-30.97

-0.44 to -0.43

-2.18

-0.15

-0.28

-0.03

-0.28

-0.03

A58

-23.26 to -23.25

-0.48

-1.95 to -1.94

-0.14

-0.26

-0.04

-0.26

-0.04

A59

-25.99 to -25.43

-0.38 to -0.36

-1.61 to -1.55

-0.10 to -0.07

-0.19 to -0.16

-0.03

-0.19 to -0.16

-0.03

A60

-55.93 to -16.20

-0.62 to -0.39

-5.23 to -1.17

-0.39 to -0.08

-0.60 to -0.15

-0.06 to -0.03

-0.60 to -0.15

-0.06 to -0.03

A61

-10.37 to -10.01

-0.42

-5.28 to -4.72

-0.19 to -0.16

-0.48 to -0.45

-0.04

-0.48 to -0.45

-0.04

Notes:

(a)   Figures shown are the range of difference in predicted pollutant concentrations among all relevant assessment heights of each ASR between “With Project” scenario and “Without Project” scenario.

(b)   Negative values represent a reduction of predicted pollutant concentrations due to the new OCGTs (i.e. “With Project” scenario) compared with the existing units (i.e. “Without Project” scenario).


It can be seen from the assessment results that the predicted NO2, SO2, RSP and FSP concentrations at all relevant assessment heights for all identified ASRs under all four phases of the “With Project” scenario are lower than those under the “Without Project” scenario.  Therefore, it can be concluded that the air quality impact during the operation of the Project would be lower than that during the existing operation. 

As the air quality impacts at all identified ASRs are expected to improve as a result of the operation of the Project, cumulative assessment is not required to be carried out.  Adverse air quality impact associated with the operation of the Project is not anticipated.

3.9         Mitigation Measures

3.9.1    Decommissioning/ Demolition and Construction Phases

The following dust control measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices will be incorporated into the Contract Specifications and implemented throughout the decommissioning/ demolition and construction phases:

n  Impervious sheet shall be provided for skip hoist for material transport;

n  The area where demolition work or any dusty work take place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after such work as far as practicable;

n  All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation;

n  Dropping heights for excavated materials should be controlled to a practical height to minimise the fugitive dust arising from unloading;

n  During transportation by truck, materials should not be loaded to a level higher than the side and tail boards, and should be dampened or covered before transport;

n  Temporary stockpiles of dusty materials shall be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time;

n  Stockpiles of more than 20 bags of cement, dry pulverised fuel ash and dusty construction materials shall be covered entirely by impervious sheeting sheltered on top and 3-sides;

n  All exposed areas shall be kept wet to minimise dust emission;

n  ULSD will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites;

n  The engine of the construction equipment during idling shall be switched off;

n  Regular maintenance of construction equipment deployed on-site shall be conducted to prevent black smoke emission;

n  All marine vessels fuelled in Hong Kong are required to operate using marine light diesel with sulphur content lower than 0.05% in accordance with the Air Pollution Control (Marine Light Diesel) Regulation;

n  NRMMs, e.g. mobile generator and air compressor, shall comply with the prescribed emission standards with a proper label approved by EPD in accordance with the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation; and

n  Electric power supply for on-site machinery shall be provided as far as practicable for construction activities.

3.9.2    Operation Phase

Air quality impacts are expected to improve during the operation of the Project.  With proper maintenance of the new OCGTs on a regular basis, specific mitigation measures during the operation phase of the Project are considered not necessary.

3.10      Cumulative Impact

3.10.1  Decommissioning/ Demolition and Construction Phases

The construction of the Hong Kong Offshore LNG Terminal is currently in progress and the associated land-based works at the Lamma Power Station Extension (LMX) may coincide with the decommissioning/ demolition and construction works of the Project.  In addition, the proposed L12 and L13 at LMX are scheduled for commercial operation in 2023 and post-2023, respectively, and their construction may also take place during the decommissioning/ demolition and construction phases of the Project.  As these land-based construction works, which are located entirely within the existing LPS and LMX, are relatively minor with limited excavation required, adverse cumulative air quality impact on ASRs outside of LPS (more than 800m away) during the decommissioning/ demolition and construction phases of the Project is not expected.  Given that these land-based construction works would only generated limited and localised dust impacts and are of sufficient separation distance from the Administration and Control Building of LPS (more than 100m apart), adverse cumulative air quality impact on HK Electric staff in the Administration and Control Building is also not expected provided that good construction site practices and proper dust control measures are in place.

3.10.2  Operation Phase

Air quality impacts are expected to improve during the operation of the Project.  Adverse cumulative air quality impact during the operation phase is not anticipated. 

3.11      Residual Impact

3.11.1  Decommissioning/ Demolition and Construction Phases

Adverse air quality impact arising from the decommissioning/ demolition and construction works of the Project is not expected.  There would be no adverse residual air quality impact during the decommissioning/ demolition and construction phases of the Project.

3.11.2  Operation Phase

Adverse air quality impact arising from the operation of the new units is not expected.  There would be no adverse residual air quality impact during the operation phase of the Project. 

3.12      Environmental Monitoring and Audit

3.12.1  Decommissioning/ Demolition and Construction Phases

With no adverse air quality impact anticipated to arise from the decommissioning/ demolition and construction works of the Project, air quality monitoring is considered not necessary.  However, it is recommended to carry out regular environmental site inspections to ensure the implementation of the air quality mitigation measures and good site practices as recommended in Section 3.9.1 throughout the decommissioning/ demolition and construction phases.

3.12.2  Operation Phase

Adverse air quality impact is not anticipated during the operation of the Project.  Environmental monitoring and audit during the operation phase is considered not necessary.

3.13      Conclusion

3.13.1  Decommissioning/ Demolition and Construction Phases

Fugitive dust emissions or emissions from construction plants and marine vessels as a result of the decommissioning/ demolition and construction works of the Project are expected to be limited.  Due to sufficient separation distance between the Project site and the identified ASRs as well as the nature of the construction works, unacceptable dust impact is not anticipated to arise during the decommissioning/ demolition and construction phases of the Project.  Dust control measures, proper site management and good housekeeping shall be implemented to further minimise any potential fugitive dust emissions.

3.13.2  Operation Phase

A comparative assessment has been carried out to evaluate the potential impacts of NO2, SO2, RSP and FSP from the operation of the Project (“With Project” scenario) under each of the four phases (i.e. Phase 1 to Phase 4) against those from the operation of existing GT2, GT3, GT4, GT6, GT57 (“Without Project” scenario).  The assessment results show that the “With Project” scenario under all four phases leads to reduced impacts at the identified ASRs.  Hence, adverse air quality impact during the operation phase of the Project is not anticipated.


 


 

 



([1])        GIC – Government, institution or community

([2])        Air Quality Monitoring Statistics, HK Electric

([3])        GT57 is a CCGT consisting of two separate gas turbines GT5 and GT7 with two separate stacks.

([4])        PATH v2.1 Data Dissemination System (Data last updated in July 2021). 

([5])        Air Quality Studies for Heathrow: Base Case, Segregated Mode, Mixed Mode and Third Runway Scenarios modelled using ADMS-Airport, 2007.

([6])        Richard A. Duffee, Martha A. O'Brien and Ned Ostojic (1991) Odor Modeling - Why and How. Page 295, Recent Developments and Current Practices in Odor Regulations, Controls and Technology. Air & Waste Management Association, 1991.