The
Hongkong Electric Co., Ltd (HK Electric) operates the Lamma Power Station (LPS)
with a number of power generating units currently in active operation,
including six coal-fired units (i.e. L2, L4 to L8), three gas-fired combined
cycle gas turbine units (CCGTs) (i.e. L9, L10 and GT57) and five oil-fired open
cycle gas turbine units (OCGTs) (i.e. GT1 to GT4, GT6).
At LPS,
there were originally seven OCGTs, GT1 to GT7, which were commissioned in the
late 80s prior to the enactment of the Environmental Impact Assessment
Ordinance (EIAO). Two of the OCGTs, namely GT5 and GT7, were later converted
into a CCGT unit (GT57) in 2002 with a total power generation capacity of 345
MW. GT57 was subsequently converted to a
gas-fired unit in 2008. The other five
OCGTs, namely GT1 (55 MW) as well as GT2, GT3, GT4 and GT6 (125 MW each), are
used for peak-lopping and provide back-up power supply in case of emergencies.
GT2, GT3,
GT4, GT57 and GT6, which are located within the Gas Turbine Compound (GT
Compound) of LPS and have a total power generation capacity of 845 MW, are
approaching the end of their service life. Therefore, HK Electric
proposes to decommission and demolish these units sequentially from 2022
onwards, and to construct and commission up to four new OCGTs with a capacity
of up to 130 MW each (i.e. the proposed GT8, GT9, GT10 and GT11, with a total
power generation capacity of 520 MW) within the GT Compound (hereafter referred
to as “the Project”) in order to maintain the peak-lopping and emergency
operational requirements of the LPS. GT1 located outside of the GT
Compound is not included in the Project. GT1 will continue to operate
within the LPS.
The
operation of the aging units is increasingly less efficient and could
potentially lead to higher air emissions. New OCGTs are much more
efficient and capable of attaining more stringent emission standards and thus
producing lower air emissions, in particular nitrogen oxides (NOx),
for generating the same amount of power comparing with the existing
OCGTs. Therefore, the Project is beneficial from an environmental
perspective and can be considered as part of the ongoing effort of HK Electric
to further reduce the overall air emissions from the operation of LPS and contribute
to the long-term air quality improvement in Hong Kong.
The
submission of and content described in this Environmental Impact Assessment
(EIA) Report does not amount to a commitment by or on behalf of HK Electric to
proceed with the Project.
The scope of the Project is to decommission and
demolish the existing OCGTs (i.e. GT2, GT3, GT4 and GT6) and CCGT (i.e. GT57)
which are approaching the end of their service life, and subsequently construct
and operate up to four new OCGTs (i.e. GT8, GT9, GT10 and GT11) as a
replacement of the existing units. Upon the progressive retirement of the
existing units, the new OCGTs serve to take over the function of these existing
units in providing additional power generation during peak-lopping and
maintaining back-up power supply in case of emergency situations for the
continuous operation of the LPS. The four new OCGTs would have a capacity
of up to 130 MW each, with a total power generation capacity of up to 520 MW.
Key activities associated with Project include the following:
§
Decommissioning and demolition of
existing GT2, GT3, GT4, GT57 and GT6, and auxiliary equipment including the
black start gas turbine (BSGT), the miscellaneous storage shed, and the lube
oil storage tank near GT5;
§
Construction of the new GT8, GT9,
GT10 and GT11, and installation of the new BSGT and Battery Energy Storage
System (BESS);
§
Construction of new cable trenches
and the new staircase and lift, and reconstruction of the GT57 Auxiliary
Building (GTAB) to a new 132kV Switching Station; and
§
Operation of the new GT8, GT9, GT10
and GT11.
The Project
is classified as a Designated Project under the EIAO (Cap. 499) as a
result of the following elements:
§
Decommissioning and demolition of four existing OCGTs
and one existing CCGT at LPS (Schedule 2, Part II, Item 4 A public utility ---
electricity power plant); and
§
Installation of up to four new OCGTs at LPS (Schedule
2, Part I, Item D.1 Public utility electricity power plant).
This EIA
Report is prepared by ERM-Hong Kong, Ltd (ERM) for HK Electric in accordance
with the EIA Study Brief No. ESB-331/2020 (“the EIA Study Brief”), issued in
July 2020, and the Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM).
The purpose
of this EIA study is to provide information on the nature and extent of
potential environmental impacts arising from the decommissioning/ demolition,
construction and operation of the Project in accordance with the requirements
described in the EIA Study Brief. This information will contribute to
decisions by the Director of Environmental Protection on:
§
The overall acceptability of any adverse environmental
consequences (if any) that are likely to arise as a result of the Project;
§
The conditions and requirements for the detailed
design, decommissioning/ demolition, construction and operation of the Project to
mitigate against adverse environmental consequences wherever practicable; and
§
The acceptability of residual impacts (if any) after
the proposed mitigation measures are implemented.
The detailed requirements of the EIA study are set out
in Clause 3 of the EIA Study Brief. As specified in the EIA Study Brief,
the EIA study has addressed the key environmental issues associated with the
decommissioning/ demolition, construction and operation of the Project.
The objectives and needs of the Project are considered
in detail in the EIA study. Given the existing OCGTs/ CCGT (i.e.
GT2, GT3, GT4, GT6 and GT57) are approaching the end of their service life,
these units need to be progressively retired and replaced by new OCGTs which
serve to take over the function of these existing units in providing additional
power generation during peak-lopping and maintaining back-up power supply in
case of emergency situations for the continuous operation of the LPS.
Without the Project, HK Electric will slowly lose the capacity to cope with the
additional electricity demand during peak-lopping and maintain power supply in
case of emergencies, putting HK Electric’s stable and reliable supply of
electricity at risk.
The existing GT2, GT3, GT4, GT6 and GT57 have been in
service since 1989 and are increasingly less efficient and potentially
producing higher air emissions. New OCGTs which serve to replace these
existing units are much more efficient and capable of attaining more stringent
emission standards and thus producing lower air emissions during operation, in
particular NOx. Therefore, the Project is beneficial from an
environmental perspective, contributing to the continuous reduction of overall
air emissions from the operation of LPS and the long-term air quality
improvement in Hong Kong.
A number of options have been explored in Section
2.4.1 of the EIA Report to cope with the electricity demand during
peak-lopping and emergency operations upon progressive retirement and decommissioning
of the aforementioned existing units. The options considered include:
§ Construction of new CCGTs;
§ Construction of new OCGTs;
§ Extending services of existing OCGTs;
§ Importing power supply from Mainland China; and
§ Use of renewable energy.
The benefits and dis-benefits of the abovementioned
options for power generation during peak-lopping and emergency operations are
summarised in Table 2.1.
Table 2.1 Benefits and Dis-benefits
of Power Generation Options during Peak-lopping and Emergency Operations
Options |
Benefits |
Dis-benefits |
Conclusion |
Construction
of new CCGTs |
CCGT has high efficiency with relatively lower
consumption and associated air emissions during its operation. |
CCGT does not have fast start-up capability which is the
key to providing swift electricity supply during peak-lopping and emergency
situations. |
Not a preferred option – not fit-for-purpose due to its
lack of fast start-up capability. |
Construction
of new OCGTs |
OCGT has fast start-up capability with the ability to
generate electricity within a relatively short time. New OCGTs produces lower emissions than the existing ones
during operation. |
- |
A preferred option – fit-for-purpose with its fast start-up
capability, and is beneficial from an environmental perspective with its
lower emissions compared with existing units. |
Extending
services of existing OCGTs |
- |
Substantial replacement of components and refurbishment works
for the existing OCGTs are required. The control system of the existing OCGTs is obsolete and
the equipment suppliers do not have the necessary spare parts or technical
support to enable continuous operation of the existing units. |
Not a preferred option – technically not viable, not
cost-effective and not the long-term solution in securing power generation
during peak-lopping and emergency operations. |
Importing
power supply from mainland China |
- |
Lack of infrastructure for connecting to the power grid
in Mainland China. Reliable electricity supply cannot be guaranteed as HKSAR
government does not have direct control and regulation of the electricity
imported from Mainland China. Displacement of local pollutants from power generation to
Mainland China where the HKSAR government or HK Electric has no control over
the emission performance. |
Not a preferred option – lack of infrastructure,
uncertainty in maintaining electricity supply reliability and lack of control
over emission performance. |
Use
of renewable energy |
No emissions would be generated. |
Renewable energy cannot supply electricity on demand to
serve the purpose of peak-lopping and emergency operations due to its
intermittent nature. |
Not a preferred option – not fit-for-purpose due to its
inability to supply electricity on demand. |
The construction and operation of new OCGTs is
considered the most practicable and preferred option to pursue as this involves
essentially like-to-like replacement, is fit for purpose, technically the most
practicable, environmentally beneficial and can tie in with the retirement
schedule of the existing units. Other options would present
impracticality and uncertainties, or may not tie in with the retirement
schedule of the existing units.
The benefits and dis-benefits of potential sites for
accommodating the new OCGTs within the LPS and Lamma Extension (LMX) are
discussed in Section 2.4.2 of the EIA Report and summarised in Table
2.2 below, with due consideration of various factors including site
condition, space adequacy, construction feasibility and complexity, and
environmental impacts. The preferred location to develop the new OCGTs is
at the GT Compound where the existing units to be demolished are located.
Table 2.2 Benefits and
Dis-benefits of Potential Sites for the New OCGTs
Potential Sites |
Benefits |
Dis-benefits |
Conclusion |
GT
Compound |
There would be sufficient space for constructing the new OCGTs,
cable trenches and associated facilities after the removal of the existing
units. Foundation works are not required as the existing
foundation piles and reinforced concrete structures could be reused for the
construction of the new OCGTs. Existing chimneys can also be reused for
the new OCGTs. |
- |
A preferred option – small project scope with no
foundation works and limited civil works involved and low environmental
impacts. |
L13
Area |
L13 Area is currently vacated and have sufficient space for
the Project. |
L13 Area is planned for the future development of the
proposed L13. The construction of the new OCGTs in L13 Area may pose
constraints on the design and construction of the proposed L13. Foundations and concrete structures for the new OCGTs
need to be constructed. New chimneys for the new OCGTs need to be
constructed as well. |
Not a preferred option – design complexity and
constraints due to interfacing with the proposed L13. Increased project
scope, construction time and cost, and environmental impacts due to new
foundations and extensive civil works required. |
L3
Main Station Building |
- |
Extensive demolition of existing structures and equipment
associated with the L3 Main Station Building is required to create space for the
construction of new OCGTs. Foundations and concrete structures for the new OCGTs
need to be constructed. New chimneys for the new OCGTs need to be
constructed as well. |
Not a preferred option – extensive demolition works
required to create space. Increased project scope, construction time
and cost, and environmental impacts due to extensive demolition, foundation
and civil works required. |
If the Project does not proceed, HK Electric will
slowly lose the capacity of additional power generation to cope with the
electricity demand during peak-lopping and maintaining power supply in case of
emergencies upon the progressive retirement of the existing units from 2022
onwards. Such capacity will be completely lost upon complete retirement
and decommissioning of these existing units. This would hamper the normal
operation of LPS significantly and put HK Electric’s stable and reliable supply
of electricity at risk.
With the Project in place, HK Electric would enable
the decommissioning of the existing units and construction of the new OCGTs
progressively (i.e. decommissioning of at least one existing unit before
commissioning of one new OCGT), allowing a smooth transition of the OCGT
reprovisioning programme and at the same time maintaining the necessary
capacity for coping with the additional power demand during peak-lopping and
emergency operation. Upon putting into operation, the new OCGTs can be in
service for years to come and are integral to the future LPS operation in
supplying stable and reliable electricity in Hong Kong.
The Project site covers the existing GT Compound
within the LPS as illustrated in Figure
3.1a / Figure 3.1b. The
reclamation for LPS was completed between late 1970s and early 1980s. The
Project site has been vacant until the existing GT2 to GT7 were constructed and
put into operation in 1989. GT5 and GT7 were later converted into a CCGT
(i.e. GT57) in 2002. The operation of GT Compound remains unchanged since
2002.
The Project is comprised of the following key
components which are discussed in detail in Section 2.5 of the
EIA Report.
§ New OCGTs – each of the four new OCGTs essentially consists of a gas
turbine and a generator, and will be operated by firing ultra-low sulphur
diesel (ULSD) to produce electricity under peak loads and emergency
situations. The generation capacity of each new OCGT is up to 130 MW,
with a total generation capacity of up to 520 MW. The exhaust gas from
GT8, GT9, GT10 and GT11 will be discharged via the existing chimneys currently
serving GT5, GT6, GT7 and GT2, respectively. The existing chimneys for
GT3 and GT4 will be retained but not utilised under this Project. The new
OCGTs will be air-cooled with no requirement for cooling water intake or
discharge during operation.
§ BSGT – A new BSGT will replace the existing BSGT installed near the west
boundary of the GT Compound. The new BSGT with capacity similar to the
existing one (i.e. about 2.2 MW) will serve to provide start up power for the
OCGTs in case of rare black out situations.
§ BESS – A new BESS with an estimated output of around 3 MW will be
installed to the south of the BSGT. Similar to the BSGT, the BESS also
serves to provide start up power for the OCGTs in case of rare black out
situations. During black out situations, the BESS will be put into
operation first, while BSGT acts as the back up to the BESS.
§ 132 kV Switching Station – The existing GTAB will be converted to a new
132 kV Switching Station to support the operation of the new OCGTs. The
new 132 kV Switching Station will be equipped with a new staircase and lift, as
well as new cable trenches for 132 kV cables connecting to the new OCGTs, BSGT
and BESS.
The EIA study has identified a number of existing and
committed projects in the vicinity of the Project site which may potentially
interface with the decommissioning/ demolition, construction and operation of
the Project. The cumulative impacts from these projects, if any, have
been addressed in the technical assessments of this EIA study where appropriate
as required in the EIA Study Brief.
The Project essentially involves the replacement of existing,
aging units (i.e. GT2, GT3, GT4, GT57 and GT6) with new, more efficient units
(i.e. GT8, GT9, GT10 and GT11) within the GT Compound in order to maintain the
peak-lopping and emergency operational requirements for the continuous
operation of LPS. The operation of the Project brings environmental
benefits from an air quality perspective as the new units are more efficient
with lower emissions relative to the existing units.
This EIA study has examined the decommissioning/
demolition, construction and operation phase impacts to air quality. The
impacts have been identified and analysed for compliance with the new set of
Air Quality Objectives (AQOs) to be implemented on 1 January 2022 under the Air
Pollution Control Ordinance (APCO), and the criteria and guidelines stated
in the EIAO-TM Annexes 4 and 12 respectively.
The Assessment Area is defined as an area within 15 km
from the Project site boundary and includes six districts, namely the Islands
(Lamma Island, Cheung Chau, Peng Chau, Hei Ling Chau, Northern and Eastern part
of Lantau Island), Southern District of Hong Kong Island, Central and Western
District of Hong Kong Island, Eastern District of Hong Kong Island, Kowloon,
and Tsing Yi. A total of 61 representative air sensitive receivers
(ASRs) among these six districts within the Assessment Area have been
identified, and the potential impacts arising from the decommissioning/
demolition, construction and operation phases of the Project on these
representative ASRs have been evaluated.
The potential impacts of noise caused by the
decommissioning/ demolition, construction and operation activities of this
Project have been assessed in this EIA Report. The impacts have been
identified and analysed for compliance with the criteria and guidelines stated
in the EIAO-TM Annexes 5 and 13 respectively and the applicable
criteria stipulated under the Noise Control Ordinance (NCO).
The Project site is located within the LPS on the
Lamma Island which is rural in nature and surrounded by natural terrain with
open sea to the south. Background noise at the Project site and the
surrounding environment is dominated by the prevailing general background
including sea waves and operation of the existing LPS. No existing or
planned Noise Sensitive Receiver (NSR) was identified within the Assessment
Area which covers a distance of 300m from the Project site boundary. Two
representative NSRs beyond the Assessment Area, namely the village houses at
Tai Shan Central and at Hung Shing Yeh about 810 m and 1,450 m away from the
Project site respectively, have been identified and the potential impacts
arising from the decommissioning/ demolition, construction and operation phases
of the Project on these representative NSRs have been evaluated where
appropriate.
The EIA study has described the potential impacts
associated with the decommissioning/ demolition, construction and operation of
the Project on water quality. The impacts have been identified and
analysed for compliance with the prevailing Water Quality Objectives (WQOs)
stipulated under the Water Pollution Control Ordinance (WPCO) and the
criteria and guidelines stated in the EIAO-TM Annexes 6 and 14
respectively.
The Assessment Area for the water quality assessment
includes areas within 500 m from the Project site boundary and covers the
Southern Water Control Zone (WCZ). Baseline condition within the
Assessment Area and the vicinity is heavily influenced by discharges from the
Pearl River. A total of five Water Quality Sensitive Receivers (WSRs)
have been identified and the potential impacts arising from the
decommissioning/ demolition, construction and operation phases of the Project
on these WSRs have been evaluated.
The potential waste management implications arising
from the decommissioning/ demolition, construction and operational activities
of the Project have been assessed in this EIA Report. The impacts have
been identified and analysed for compliance with the criteria and guidelines
stated in the EIAO-TM Annexes 7 and 15, respectively.
This EIA study has examined the potential of land
contamination at the Project site. A land contamination assessment was undertaken
in accordance with the guidelines stated in the EIAO-TM Annex 19 and
other relevant guidance notes and practice guides.
Based on the findings of the site appraisal and a
review of potential land contamination sources in the Project area, site investigation
(SI) and sampling are recommended at five hotspot locations (including 4
boreholes and 1 trial pit) to assess the potential land contamination impacts
associated with the Project. SI and sampling will be undertaken in
accordance with the Contamination Assessment Plan (CAP) endorsed by the
Environmental Protection Department (EPD) when the proposed sampling locations
are made available after the demolition of the existing units and
structures.
The potential land contamination impacts arising from
the decommissioning/ demolition, construction and operation phases of this
Project have been evaluated.
The scope of the Project involves the decommissioning
and demolition of the existing units (i.e. GT2, GT3, GT4, GT57 and GT6) and
auxiliary equipment within the GT Compound of LPS, and the construction and
operation of four new OCGTs (i.e. GT8, GT9, GT10 and GT11) within the GT
Compound. The Project site includes the GT Compound as shown in Figure 3.1a. The locations of
the existing units and the proposed new units within the Project site are shown
in Figure 3.1a and Figure 3.1b, respectively.
No major earthworks, site formation works or dredging
works will be required during the decommissioning/ demolition or construction
of the Project. Key activities associated with the Project are summarised
in Table 5.1.
Table 5.1 Summary of Key Project Activities
Item |
Detail |
Decommissioning/
Demolition Activities |
§
The existing GT2, GT3, GT4, GT57 and GT6
and their auxiliaries will be decommissioned and demolished. §
The existing BSGT, the miscellaneous
storage shed adjacent to the existing BSGT, and the existing lube oil storage
tank near GT5 will be demolished. §
The existing Turbo Block structure and
equipment inside the GTAB will be removed and demolished which requires minor
excavation down to about 2.6m below ground over an area of about 200m2. §
Typical equipment such as excavators, mobile
cranes, electric breakers, grinder, flame cutting and powered mechanical hand
tools will be used for the demolition works. |
Construction
Activities |
Construction
of new units: § Major equipment of the
new OCGTs assembled off-site will be installed on the existing foundation
piles and reinforced concrete structure for the demolished units in the GT
Compound. § New BSGT and BESS will
be installed in the northwest corner of the GT Compound. § Typical equipment such
as mobile cranes and powered mechanical hand tools will be used for the
construction and installation of the new units. |
|
Conversion
of existing GTAB to the new 132kV Switching Station: § Gas insulated
switchgear, electrical and control panels and other associated equipment will
be installed inside the new 132kV Switching Station. § Typical equipment such
as overhead crane and powered mechanical hand tools will be used for the
equipment installation. |
|
Construction
of new staircase and lift and cable trenches: § A new staircase and
lift with footprint of about 10m x 5m will be constructed at the immediate
east of the GTAB which requires minor excavation down to 5m below ground. § New cable trenches of
about 1.5m in width and 1,240m in length will be constructed to house the new
132kV cables connecting the new OCGTs, BSGT and BESS to the new 132kV
Switching Station. Minor excavation down to 1.8m below ground will be
required. § Typical equipment such
as excavators, mobile cranes, welding machines and other power mechanical
hand tools will be used during the construction of new staircase and lift and
cable trenches and the subsequent cable laying. |
Operational
Activities |
§ The new OCGTs and
auxiliary equipment will be operated during peak-lopping and emergency
situations. § The new BESS and BSGT
will be operated to supply the required power to start up the new OCGTs in
case of rare black-out situation. |
HK Electric proposes to decommission and demolish the existing
GT2, GT3, GT4, GT57 and GT6, and to construct and commission the new GT8, GT9,
GT10 and GT11 within the GT Compound successively between 2022 and 2028.
The tentative implementation programme is provided in Figure
5.1.
Figure 5.1 Tentative
Implementation Programme of the Project
The decommissioning/ demolition and construction works
of the Project are not considered potential dust generating activities except
for minor excavation works for the construction of new cable trenches, new
staircase and lift, and reconstruction works inside the existing GTAB.
Limited excavated materials will be generated and the potential fugitive dust
emissions are expected to be small. Considering the large separation
distance between the worksite and the nearest ASR outside of LPS (at least 800m
away), no adverse fugitive dust impact on ASRs outside of LPS arising from the
decommissioning/ demolition and construction activities of the Project is
anticipated. Considering the potential dust impact would be limited and
highly localised, there is also sufficient separation distance between the
Administration and Control Building and the Project site (more than 100m
apart). Adverse fugitive dust impact on HK Electric staff in the
Administration and Control Building due to decommissioning/ demolition and
construction works of the Project is also not anticipated with the
implementation of good construction site practices and relevant mitigation
measures recommended in the Air Pollution Control (Construction Dust)
Regulation.
As the decommissioning/ demolition and construction
works of the Project are relatively small scale and that the units are to be
demolished and installed in phases, the number of construction plants deployed
on site will be limited and the associated emissions from the operation of
these construction plants are expected to be minor. No adverse air
quality impact associated with the operation of the construction plants is
anticipated provided that the requirements in the Air Pollution Control
(Non-road Mobile Machinery) (Emission) Regulation and Air Pollution
Control (Fuel Restriction) Regulation are followed.
Demolished equipment will be transported off-site via
marine vessels. As the demolition and construction works associated with
the Project are small scale, additional marine traffic for equipment transport
during the decommissioning/ demolition and construction phases of the Project
is expected to be limited (no more than 1 to 2 vessel trips within every 2
days). The requirements in Air Pollution Control (Marine Light Diesel)
Regulation and Air Pollution Control (Fuel for Vessels) Regulation
will be followed for the operation of the marine vessels. No adverse air
quality impact with respect to marine vessel emissions associated with the
Project is anticipated.
Stack
emissions from the proposed new OCGTs would be the major air emission source of
operation phase air quality impact. Comparative assessments have been
carried out to evaluate the air quality impacts arising from the concerned
units before and after the Project. The comparative assessments have
considered the “Without Project” scenario and the “With Project” scenario under
different phases as presented in Table 5.2.
Table 5.2
Modelling Scenarios and Emission Sources Considered
Modelling
Scenario |
Emission
Sources Considered |
“Without Project” |
§ Existing GT2, GT3, GT4, GT57,
GT6 |
“With Project” – Phase 1 |
§ Existing GT2, GT3, GT4 § New GT10 |
“With Project” – Phase 2 |
§ Existing GT3, GT4 § New GT8, GT10 |
“With Project” – Phase 3 |
§ Existing GT4 § New GT8, GT9, GT10 |
“With Project” – Phase 4 |
§ New GT8, GT9, GT10, GT11 |
The air quality impacts at the identified
representative ASRs under each of the “With Project” scenario (Phase 1 to Phase
4) have been compared with those under the “Without Project” scenario. Results of
the comparative assessments show that contribution from the Project (i.e. NO2,
SO2, RSP and FSP) under all phases of “With Project” scenario are
lower than that under “Without Project” scenario at all relevant assessment
heights for all identified ASRs. The reduction of predicted pollutant
concentrations under the “With Project” scenario compared with the “Without
Project” scenario is summarised in Table 5.3. With a
reduction of air quality impacts at the identified representative ASRs under
all phases of the Project operation, no adverse air quality impact arising from
the operation of the Project is anticipated.
Table 5.3 Reduction of Predicted Pollutant
Concentrations under “With Project” Scenario Compared with “Without Project”
Scenario
Modelling
Scenario |
Reduction of Predicted Concentration (mg m-3) |
|||||
Max. 1-hour NO2 |
Annual NO2 |
Max. 10-min SO2 |
Max. 24-hour
SO2 |
Max. 24-hour
RSP/ FSP |
Annual RSP/
FSP |
|
“With Project” – Phase 1 |
-138.55 to -2.58 |
-1.41 to -0.08 |
-39.21 to -0.72 |
-2.17 to -0.05 |
-2.40 to -0.06 |
-0.14 to -0.01 |
“With Project” – Phase 2 |
-138.09 to -3.37 |
-1.51 to -0.10 |
-38.67 to -0.70 |
-2.11 to -0.05 |
-2.54 to -0.07 |
-0.15 to -0.01 |
“With Project” – Phase 3 |
-146.61 to -4.21 |
-1.62 to -0.12 |
-37.77 to -0.67 |
-2.06 to -0.05 |
-2.63 to -0.08 |
-0.16 to -0.01 |
“With Project” – Phase 4 |
-155.65 to -6.84 |
-1.76 to -0.13 |
-37.26 to -0.65 |
-2.03 to -0.04 |
-2.82 to -0.09 |
-0.18 to -0.01 |
Potential sources of noise impacts during the
decommissioning/ demolition and construction phases of the Project will mainly
arise from powered mechanical equipment (PME) operating at the construction
work sites. No NSR was identified within the 300m Assessment Area, and
the nearest NSR is at least 810m from the Project site boundary. Due to
large separation distance and screening by terrain and existing building structures,
the potential noise impacts arising from the demolition and construction works
are expected to be minimal.
All NSRs are located far away from the LPS jetty (at
least 1.6 km) and further away from the marine vessel route. With no more
than 1 to 2 vessel trips within every 2 days, no adverse noise impact due to
marine traffic during decommissioning/ demolition, and construction phases are
anticipated.
No mitigation measures or noise monitoring during decommissioning/
demolition and construction phases of the Project are required.
Fixed plant noise associated with the operation of the
new OCGTs, i.e. GT8, GT9, GT10 and GT11, is the major potential noise source
during the operation phase of the Project. The new OCGTs would only be
operated intermittently during peak-lopping and emergency situations. No
NSR was identified within the 300m Assessment Area, and two NSRs (i.e. village
house at Tai Shan Central and village house at Hung Shing Yeh) were identified
at 810m and 1,450m from the Project site boundary, respectively. A
quantitative fixed plant noise assessment has been carried out for the
operation of the new OCGTs at the village house of Hung Shing Yeh (NSR N2), which
is the nearest NSR with possible direct line of sight towards the OCGTs.
The predicted noise levels at 1m from the façade of NSR N2 due to operation of
the new OCGTs is 37dB(A) and comply with the respective noise criteria during
both daytime and night-time periods. Therefore, no adverse noise impacts
during the operation of the Project are anticipated. No mitigation
measures or noise monitoring during operation of the Project are required.
The decommissioning/ demolition and construction works
of the Project will not involve marine or major site formation works.
Unacceptable water quality impacts from land-based runoff and sewage discharge
from construction workforce during the decommissioning/ demolition and
construction phases of the Project are not expected with proper implementation
of good site practices and water quality mitigation measures.
There will be no cooling water discharge associated
with the operation of the Project and thus water quality impacts during
operation phase are not expected. No mitigation measures or water quality
monitoring during operation of the Project are required.
Waste that is expected to be generated during the
decommissioning/ demolition and construction phases of the Project include
construction and demolition (C&D) materials from demolition and removal of
existing units and associated equipment/ parts as well as from minor civil
works, excavated materials from the construction of new cables trenches and new
staircase and lift as well as reconstruction works within GTAB, chemical waste
from decommissioning of existing units, maintenance of construction plant and
commissioning of new units, and general refuse from construction
workforce. The estimated waste arisings during decommissioning/
demolition and construction phases are summarised in Table 5.4.
With the implementation of the mitigation measures recommended, no unacceptable
environmental impacts arising from storage, handling, collection, transport and
disposal of wastes are expected.
Table 5.4 Summary of Estimated
Waste Arisings during Decommissioning/ Demolition and Construction Phases
Types of Waste |
Approximate Quantity |
C&D materials (demolition works) |
§ Scrap
metals: 4,500 tonnes |
§ Other
non-inert C&D materials (e.g. plastics, timber, cardboard): 100m3 |
|
§ Inert
C&D materials (e.g. broken concrete): 720m3 |
|
C&D materials (civil works) |
§ Inert
C&D materials: 84m3 |
§ Non-inert
C&D materials: 21m3 |
|
Excavated materials |
§ 5,000m3 |
Chemical
waste |
§ Few hundred litres per
month |
General
refuse |
§ 162.5kg per day |
Chemical waste (few hundred litres per month) and
general refuse (insignificant quantity) will be generated during the operation
phase of the Project. General refuse will be collected, handled,
transported and disposed of following the existing waste management practices
for LPS operation. Chemical waste will be collected by licenced chemical
waste collectors and delivered to the Chemical Waste Treatment Facilities
(CWTC) for disposal. Unacceptable environmental impacts related to waste
management during the operation of the Project are not expected.
Based on the findings of the site appraisal and review
of potential land contamination sources in the Project site area, potential
land contamination risks could not be ruled out at the Lube Oil Tank area,
BSGT, Chemical Dosing Pit and Miscellaneous Storage Shed, and a total of five
hotspot locations have been identified at these areas. SI and sampling
are recommended at these five hotspot locations to assess the potential land
contamination impacts associated with the Project. SI and sampling will
be undertaken in accordance with the Contamination Assessment Plan (CAP)
endorsed by EPD when the proposed sampling locations are made available after
the demolition of the existing units and structures. The potential land
contamination within the Project site, if any, is considered localised and the
chemical of concerns identified are treatable with existing remediation
techniques. Provided that the soil and groundwater contamination
identified during the SI, if any, is properly treated using the appropriate
remediation techniques, no adverse land contamination impacts during the
decommissioning/ demolition and construction phases of the Project are
anticipated. Good house-keeping practices shall be maintained by the
contractor(s) to minimise the risk of land contamination arising from the
decommissioning/ demolition and construction works within the Project site.
No land contamination impacts during the operation
phase of the Project are anticipated. No mitigation measures are
required.
The EIA study of the Project has evaluated impacts
related to air quality, noise, water quality, waste management and land
contamination arising from the Project, and has demonstrated to comply with the
EIAO-TM requirements with the implementation of recommended mitigation
measures and good site practices. Actual impacts during the
decommissioning/ demolition and construction works will be monitored through a
detailed EM&A programme involving regular environmental site inspections
and audits to ensure that the recommended mitigation measures and good site
practices related to air quality, noise, water quality, waste management and
land contamination are properly implemented and are effective. Full
details of the programme are presented in the EM&A Manual associated with
the EIA Report. This programme will provide management actions and
supplemental mitigation measures to be employed should any impacts arise,
thereby ensuring the environmental acceptability of the decommissioning/
demolition, construction and operation of the Project.
During the decommissioning/ demolition and
construction phases, regular site inspections and audits will be conducted to
confirm the effective and timely implementation of the recommended mitigation
measures.
Regular waste audits will also be conducted to
determine if wastes are being managed in accordance with the recommended good
site practices and the Waste Management Plan (WMP).
No regular monitoring or site inspections/ audits
during the operation phase of the Project are required.
The EIA study has critically assessed the overall
acceptability of the environmental impacts likely to arise as a result of the decommissioning/
demolition, construction and operation of the Project. It has
demonstrated the acceptability of any residual impacts from the Project and the
protection of the population and environmentally sensitive resources. The
EIA study concluded that, with the implementation of the recommended mitigation
measures, the Project would be environmentally acceptable and in compliance
with the relevant assessment standards/criteria of the EIAO-TM.
Where appropriate, EM&A mechanisms have been recommended to verify the
accuracy of the EIA predictions to ensure the effectiveness of the recommended
mitigation measures.
The implementation of the Project is critical to the
continuous operation of LPS in providing additional power generation during
peak-lopping and maintaining back-up power supply in case of emergency
situations, having regard to the progressive retirement of the existing
OCGTs/CCGT in the GT Compound from 2022 onwards. The operation of the new
OCGTs under the Project will produce lower air emissions compared with that of
the existing, aging units when generating the same amount of power. The
Project is therefore also beneficial from an environmental perspective and
contributes to the reduction of overall air emissions from the operation of LPS
and improvement of air quality in Hong Kong in the long run.
This EIA Report has been
prepared to comply with the requirements of the EIA Study Brief and the
EIAO-TM, as a basis for the Director of Environmental Protection to consider granting
the Environmental Permit to allow the decommissioning/ demolition, construction
and operation of the Project.
The English version of this
Executive Summary shall prevail wherever there is a discrepancy between the
English version and the Chinese version.
The submission of this
Environmental Impact Assessment (EIA) Report and the said Environmental Permit
application(s) does not amount to a commitment by or on behalf of HK Electric
to proceed with the Project.