1.1.1.1
The Government plans to develop
Yuen Long South Development Area (YLS DA) which is a mega-scale and complex
development aiming to provide land to transform the degraded brownfield land to
developable land contributing to meet the territory’s medium to long-term need
for housing development. The YLS DA is proposed to accommodate a population of
approximately 101,200 persons and generate about 13,630 employment
opportunities on full development.
1.1.1.2
The purpose of the Project is
to provide sewage treatment to the sewage collected from the YLS DA and other
developments in the North West New Territories (NWNT).
1.1.1.3
The Civil Engineering and
Development Department (CEDD) commenced Agreement, namely the Agreement No. CE
35/2012 (CE) “Planning and Engineering Study for Housing Sites in Yuen Long
South – Investigation” in 2012, to formulate the detailed development proposals
for the YLS DA. This Study recommends that the sewage generated from the YLS DA
will be discharged to separate new sewage treatment work, namely the Yuen Long
South Effluent Polishing Plant (YLSEPP) which is located to the southern end of
the YLS DA.
1.1.1.4
The above study recommended
preliminary treatment capacity, treatment level and discharge arrangement of
YLSEPP taking into account the constraints for discharge to North Western
Waters and Deep Bay. Further reviews of flow projection, treatment level,
treated effluent discharge and sludge treatment scheme shall be carried out to
formulate the preliminary design of YLSEPP to cater for the sewage collected from
the new developments within the YLS DA and other developments in the NWNT to
support the medium and long-term housing and economic needs of the NWNT.
1.1.1.5
AECOM Asia Co Ltd. was
commissioned by Drainage Services Department (DSD) on 27 March 2020 to carry out
this Assignment for the investigation for YLSEPP. Site
location plan of the YLSEPP is shown in Figure 1.1.
1.2.1.1
A Project Profile (No. PP-576/2019)
was submitted to the Environmental Protection Department (EPD) on 1 February 2019 for application for
an Environmental Impact Assessment (EIA) Study Brief under section 5(1)(a) of
the Environmental Impact Assessment Ordinance (EIAO) and the EIA Study Brief No.
ESB-313/2019 for the Project was issued on 15 March 2019 under the EIAO.
1.2.1.2
The Project comprise the following
elements which are classified as Designated Projects (DPs) under per Schedule
2, Part I of the EIAO. The DPs elements
of this Project is summarized in Table 1.1.
Table 1.1 Schedule 2 Designated Projects in this Project
Schedule 2 Designated Project
|
Designated
Project Element under the Project
|
Item
F.1, Part I
|
Sewage
treatment works with an installed capacity of more than 15,000 m3/day.
|
The
proposed treatment capacity of YLSEPP would be 65,000 m3/day.
|
Item
F.4, Part I
|
An
activity for reuse of treated sewage effluent from a treatment plant
|
Reuse
of some portion of treated effluent inside the YLSEPP for chemical
preparation, water supplement to deodorisation units and cleaning of
treatment equipment
|
1.3.1.1
This Executive Summary (ES)
summarizes the findings, recommendations and conclusions of the EIA Report for
the Project.
2.1.1.1
The purposes and objectives of
the Project is to provide sewage treatment to the sewage collected from the YLS
DA and other developments in the North West New Territories (NWNT).
2.1.1.2
YLS DA has reserved about 4.6
hectares of land for the proposed YLSEPP, the location of which is shown in Figure 1.1. According to the YLS
DA’s Revised Recommended Outline Development Plan (RODP), YLSEPP is located at
the southern tip of YLS DA. It is bound by Ma Shan (Kung Um Shan) and Tai Lam
Country Park at its south west. There will be a planned reedbed and green belt
to its north, and planned government and institutional land use to its east
side.
2.1.1.3
The Scope of this Project would
only cover the construction of YLSEPP of which the associated supporting
structures, including the upstream sewage pumping station, rising main for raw
sewage, water reclamation facilities, its associated pumping
facilities and rising main for reclaimed water (as shown in Figure 1.1), are out of the study
brief of this EIA study. For avoidance of doubt, the site formation works of
the YLSEPP site (including land OU3.3 and G3.1) are also not covered in the
scope of this Project and the environmental impact of such works should be duly
reviewed in the separate EIA Report: AEIAR-215/2017- Housing Sites in Yuen Long
South.
2.1.1.4
The pre-treated food waste
collected in YLSEPP would be transported by EPD for subsequent co-digestion
with sewage sludge. As such, no food waste pre-treatment would be carried out
in YLSEPP. YLSEPP’s treated tertiary
effluent will be discharge to Yuen Long Nullah in the interim. In the ultimate
scenario, it is planned that there will be Water Reclamation Facilities and
reedbed (to be constructed by others) adjacent to YLSEPP. YLSEPP’s treated
tertiary effluent would be supplied to the Water Reclamation Facilities
(planned to be co-located with YLSEPP at land OU3.3) to produce reclaimed water
and discharged to the reedbed for river revitalization. Part of the effluent would also be reused
within YLSEPP for plant operation. An
emergency discharge pipe will be constructed within the proposed YLSEPP boundary
and connected to the underground section of the Yuen Long Nullah (as shown in Figure 1.1) for emergency
effluent discharge to Yuen Long Nullah.
2.1.1.5
The proposed works of the
Project comprise:
1)
Construction of a sewage treatment plant with a maximum capacity of
Average Dry Weather Flow (ADWF) up to 65,000 m3/day;
2)
Construction of sludge treatment facilities for treating sludge
generated from YLS EPP and other nearby sewage treatment works;
3)
Construction of facilities for receiving and co-digesting pre-treated
food or organic wastes;
4)
Construction of effluent discharge pipe for the purpose of emergency
discharge; and
5)
Associated ancillary works.
2.2.1.3
Upon the completion of YLSEPP,
YLSEPP will provide enough treatment capacity for the sewage generated from YLS
DA and its surrounding areas including HSK/HT NDA and Yuen Long Area 13
&14. With sufficient treatment capacity and high effluent quality, there
are opportunities to handle sewage from future developments within YLSEPP
catchment.
2.2.1.4
YLSEPP will give higher
treatment efficiency and cost effectiveness as well as improve the living
environment of its surrounding areas. With the enhancement of odour management
of the YLSEPP (covering all odorous facilities and installation of
deodorization units), odour nuisance to the surrounding area would be
effectively controlled and minimized.
2.2.1.5
It is planned that there will
be a Water Reclamation Facility adjacent to YLSEPP where YLSEPP’s tertiary
effluent will be further treated as Reclaimed Water to meet flushing demand in
YLS DA, HSK/HT NDA and the surrounding new development areas. In addition, there
is future opportunity that YLSEPP’s tertiary effluent, would provide a clean
water source to revitalize the Yuen Long Nullah. Such high quality flow would
improve the scenic appearance of Yuen Long Nullah and would enhance the
ecological value to the nearby community. In addition, the surplus treated
effluent to Yuen Long Nullah could also serve as a back-up water for periodic
flushing of the Yuen Long Nullah Barrage under the Yuen long Nullah Barrage Scheme.
2.2.1.6
As a sustainability
consideration, co-digestion of organic wastes with sewage sludge within YLSEPP
will be adopted to enhance energy recovery from the anaerobic digestion
process. Additional facilities for organic wastes co-digestion, including reception
facilities, digesters and dewatering facilities, will be located within the
YLSEPP’s footprint.
2.3.1.1
The treatment option evaluation
section mainly focuses on the biological treatment processes as this is the
critical part in YLSEPP layouts.
2.3.1.2
A preliminary review of
potential biological treatment processes, including proven treatment processes,
market availability, overseas and local experiences and the emerging treatment
process, have been conducted. Two major options of biological treatment process
for the YLSEPP were considered, including:
·
Conventional Activated Sludge (CAS)
·
Compacted-type technologies
2.3.1.3
In considering the footprint
for various biological treatment options, CAS will involve a considerably
larger volume of excavation works and higher construction period. Thus,
compacted-type technologies were recommended.
2.3.2.1
Sludge cake generated from
YLSEPP’s treatment of sewage sludge and organic waste will be delivered to the
Sludge Treatment Facility (STF) in Tuen Mun for incineration. Prior to
conveyance to the STF, the following handling options are considered:
·
Dewatering with prior anaerobic digestion including
organic waste co-digestion
·
Direct dewatering without digestion
2.3.2.2
Anaerobic digestion is
recommended with the environmental benefits of reducing the volume of sludge
and food waste to be disposed of at STF, and allow energy recovery from biogas
generation for utilization within YLSEPP. Also, the organic contents in
digested sludge would be much lower so as to minimize the odour level in the
downstream dewatering and offsite disposal process.
2.3.2.3
As a sustainability
consideration, co-digestion of organic wastes with sewage sludge within YLSEPP
is recommended to enhance biogas generation and, hence, increase the generation
of renewable energy for plant internal usage. Additional facilities for organic
wastes co-digestion, including reception facilities, digesters and dewatering
process, will be located within the YLSEPP’s footprint.
2.3.3
Consideration of Layout Options
2.3.3.1
For developing of YLSEPP’s
internal layout, considerations of numerous engineering constraints and
environmental factors have been made as below:
·
The locations, size and arrangement on new treatment facility is bounded by
recommended treatment options. Thus, compacted size treatment facility is
provided in the layout.
·
In green building consideration, energy recovery from biogas is
recommended. Thus, chimneys from CHP is required in YLSEPP.
·
The required treatment capacity of 65,000 m3/day would determine
the size of treatment units and likewise would determine the amount of odour
emission and the requirement on deodorization units to cater the odour nuisance
due to sewage treatment process.
·
Odour emission rates to be treated by deodourization units are
determined by the surface area of the treatment facilities, the air exchange
flow rate and the odour emission strength according to odour generation sources
such as sewage and sludge tanks. Compacted treatment facilities would assist in
reducing the odour emissions with smaller tank sizes.
·
Odour extraction rates will be appropriately provided for man-access
areas with higher air exchange rates and for non-man-access odour enclosures
with lower air exchange rates to reduce the size of the deodourization units
necessary to treat the extracted foul air.
·
Foul air is treated as close to the emission source as possible with
decentralized deodourization units to reduce the footprint required for odour
extraction ductwork and to provide optimal deodourization treatment technology
for the various types of odour sources.
·
The layout of different treatment units is determined with due
considerations of not only the process requirements, but also environmental
factors, e.g. most of the air emission sources as well as deodourization units
are located with as much setback from the site boundary as possible to provide
maximum distance between the air emission sources and the sensitive receivers.
·
The scale and size of above-ground structures are determined by striking
a balance between the plant’s hydraulics and visual impacts to the
surroundings.
Consideration
of Locations for the New Treatment Facilities
2.3.3.2
The locations of new treatment
facilities are bounded by the inlet sewage pipes and effluent outfall at the
northern and south-eastern sides, respectively.
In order to minimize the scale of construction, sewage inlet works would
be located at the north side of YLSEPP to minimise the distance of the incoming
sewage rising mains and the effluent outfall would be located close to the
existing Yuen Long Nullah. As such, the locations of new facilities are
designed with inlet works at the north, primary and biological unit in the
middle and tertiary treatment units at the south of YLSEPP. In addition, all
the construction works and new facilities would be within the site boundary.
The new treatment facilities arrangement is then designed under these boundary
conditions.
Avoidance and
Reducing Environmental Impacts from Design and Layout
2.3.3.3
In order to avoid and minimize
environmental impacts in terms of air quality, noise, water quality,
ecological, landscape and visual aspect, the following major design and layout
will be adopted in YLSEPP:
·
All
the treatment units will be covered and ventilated via deodorization units.
Thus, odour impact would be minimized.
·
All
the treatment facilities and building will be ventilated with silencers at
lourvers. Thus, fixed noise impact would then be minimized.
·
A
set of design measures will be installed to avoid and minimize the chance on
emergency discharge
·
All
the treatment units and buildings are designed with due considerations on
minimizing the building heights by such means as adopting equipment that
requires low headroom. This is to ensure
all the aboveground structures would not be excessively bulky so as to minimize
the visual impacts
2.4.1
Consideration of Site Formation
Works
2.4.1.1
The environmental implication
of site formation work for both land OU3.3 and G3.1 are covered in the EIA
report no. AEIAR-215/2017 – Housing Sites in Yuen Long South. As such, the
consideration of alternative site formation method is not included in this EIA
report.
2.4.1.2
However, it is noted that the
site formation level for the land G3.1 as shown in the EIA report no.
AEIAR-215/2017 (i.e. 31.0 mPD) will be changed to suit the latest proposed site
formation level of YLSEPP. Thus, an environmental review should be conducted by
others (e.g. CEDD) to assess the environmental impact resulted from this
change.
2.4.2
Consideration of Foundation
Methods
2.4.2.1
The foundation options are
highly dependent on the ground conditions. According to the available ground
information, the site is generally overlaid by fill, alluvium clay, completely
decomposed granite (CDG) and slightly/moderately decomposed granite (S/MDG). In
considering the geotechnical feasibility, the following foundation methods have
been considered:-
·
Pre-bored
socketed steel H piles (for heavy-duty structures only)
·
Percussive
piles
·
Shallow
foundation (for light-duty structures)
2.4.2.2
Since the proposed boundary of
YLSEPP is currently located within private land lots with numerous existing
private structures, the area assessable for ground investigation works is
limited. As such, the technical feasibility of different foundation options
should be further reviewed at a later project stage when more ground
information can be gathered.
Light-duty Structures
2.4.2.3
Piling foundation and shallow
foundation are both the feasible foundation options for light-duty structures
in YLSEPP. In order to minimize the disturbance to adjacent environment in
terms of noise and vibration, shallow foundation is adopted for light-duty
structure to reduce the environmental implication of the project during
construction stage.
Heavy-duty Structures
2.4.2.4
Based on the existing drilling
record of ground investigation work, it is considered that both percussive pile
and bored pile are the feasible foundation options for heavy-duty structures
within YLSEPP. However, since the stiffness of underground soil is undesirable
for percussive pile, it is not the preferable option due to anticipated long
pile length leading to low economic efficiency. Meanwhile, the tentative bed
rock level is at about 20m below ground level which allows the adoption of
pre-bored socketed steel H piles for heavy-duty buildings. Therefore, subject
to the detailed design of YLSEPP, bored pile would be the likely foundation
options for those heavy structures in YLSEPP.
2.4.2.5
In addition, it is recognised
that there are existing graves located at the south-western side of YLSEPP.
With this consideration, application of percussive piling will be avoided as
far as practicable to minimize the disturbance to existing structures and
prevent potential public complaint during Project’s construction stage. Bored
pile remains the preferrable foundation option for heavy-duty structures in
YLSEPP since it would generate less vibration and disturbance to the adjacent
area. However, it should also be noted that bored pile has its demerits of
requiring a comparatively longer construction period as well as generating much
higher volume of excavated materials to be disposed which would generate other
environmental impacts.
2.5.1.1
The Project construction works
are anticipated to commence in early 2028 with completion of the Project by
2032.
2.5.1.2
3.1.1.1
The potential air quality
impacts from the construction works of the YLSEPP would mainly be related to
the construction dust from the excavation works for substructure (substructures
defined as the underground structures), pilling works, road paving works,
construction for substructures and superstructures works.. With the implementation of mitigation
measures specified in the Air Pollution Control (Construction Dust) Regulation,
good site practices, regular watering and EM&A programme, no adverse dust
impact at ASRs is anticipated due to the construction activities of the
Project.
3.1.1.2
Flue gas emission would be
emitted from the stacks of CHP and boiler in the YLSEPP. Cumulative air quality impact arising from
YLSEPP operation, the vehicular emissions from the open roads within the 500m
assessment area has been assessed for operation of YLSEPP. The assessment results conclude that the
predicted cumulative 19th highest 1-hour average and annual average
NO2, the 10th highest daily and annual average RSP, the
19th highest daily and annual average FSP, 10-min average and daily
average SO2, and the maximum 1-hour and the maximum 8-hour average
CO at representative ASRs would comply with the corresponding new AQOs. The predicted maximum 1-hour average and
annual average HCl, maximum 1-hour average and annual average HF, maximum
1-hour average methane, maximum 30-minute average and annual average formaldehyde
would comply with the corresponding international standards. No adverse air quality impact is anticipated
arising from the flue gas emission associated with the operation of YLSEPP.
3.1.1.3
All odour sources in YLSEPP are
fully enclosed. The potential odour
emission from the sewage treatment facilities, sludge treatment facilities and
organic waste co-digestion facilities would all be treated in the deodourizers
before discharge into atmosphere. With
implementation of the best-available deodourizers in the market with 95% odour
removal efficiency, locating deodourizer exhaust away from ASRs as far as
practicable, the assessment results show that the predicted Project-alone
5-second average odour concentration at the representative ASRs within the
Study Area would be below 1 OU.
3.1.1.4
Considering the cumulative
odour impact due to the Project and the retained chicken farm, the predicted
cumulative odour concentrations at all planned ASRs would comply with the
EIAO-TM criterion of 5 OU. No adverse
residual odour impact would be expected at the planned ASRs.
3.1.1.5
Cumulative odour exceedances to
the EIAO-TM criterion of 5 OU are predicted at two existing representative
ASRs, YAE01 and YAE02, and nearby village houses for a short duration of time
during operation phase of the Project.
The frequency of exceedance in odour concentrations at ASRs within the
exceedance zone is up to 0.51% of the time in a year. During the time of exceedance, the proposed
YLSEEP would contribute less than 0.45 OU/m3, while the major odour
contribution would be from the retained existing chicken farm. Nonetheless, the Project will support the YLS
DA and bring about a net improvement in cumulative odour impact at the YLS DA
area. Despite the predicted odour
exceedance at some existing ASRs, the cumulative odour impacts during the
exceedance period will be substantially improved compared to that of existing
condition without removal of the five livestock farms. With the removal of the
five livestock farms in YLS DA, an overall reduction in odour impacts at all
the ASRs within YLS DA would be anticipated.
3.1.1.6
It is therefore concluded that
there is no adverse residual odour impact arising from the Project.
3.2.1.1
The assessment for the
potential construction noise impact from construction of the proposed YLSEPP
and its cumulative impact with concurrent projects have been conducted. The predicted construction noise levels at the
representative NSRs would comply with the noise criteria stipulated in EIAO-TM
with the adoption of temporary movable noise barrier, noise insulating fabric,
ventilated acoustic enclosure and quiet powered mechanical equipment. No adverse construction noise impact arising
from the Project, as well as cumulative construction noise impact from the
concurrent projects, would be anticipated.
Good site practices are also recommended to further minimize the
potential construction noise impacts.
3.2.1.2
The fixed noise impact
associated with the operation of the YLSEPP has been assessed based on the
plant design information provided by the Project Engineer at the time of the
assessment. Based on the current design
in which fixed plants will be located inside reinforced concrete buildings, and
installing acoustic louvres for ventilation fans, the predicted fixed plant
noise levels at the representative NSRs would comply with noise criteria stipulated
in EIAO-TM. No adverse fixed noise
impact due to the operation of the YLSEPP would be anticipated.
3.3.1.2
During
the operation phase, the proposed YLSEPP will be designed to achieve treatment
capacity of 65,000 m3/day in ADWF and up to tertiary level treatment
standard to enable further treatment as reclaimed water in the Reclaimed Water
Facility for non-potable uses within HSK/HT NDA, YLS DA
and the surrounding areas.
Part of the treated effluent would be used within YLSEPP for plant
operation and part of treated effluent would be discharged to adjacent reedbed
for river revitalization. However, the proposed water reclamation facility and
reedbed are included under CEDD's D&C consultancy for YLS DA Stage 2 Works and
Stage 3 Works respectively,, all the treated effluent would be discharged to
Yuen Long Nullah in the interim.
3.3.1.3
Contingency
measures such as standby unit for all major equipment and back-up power for
dual power supply would be provided for the proposed YLSEPP to prevent
emergency situation as far as practicable.
An Emergency Response Plan will be formulated prior to commissioning of
YLSEPP to minimize the impact of emergency discharges and facilitate subsequent
management of the emergency.
3.3.1.4
Other
water quality impacts associated with the operation phase are identified as
surface runoff from paved areas and accidental spillage. It is expected that these potential impacts
can be prevented by adopting recommended mitigation measures.
3.4
Waste Management Implication
3.4.1.1
Waste management implications
associated with the construction and operation of the Project were identified
and assessed. Waste types generated by the construction activities of the
Project would include C&D materials (from excavation and
construction works for the proposed YLSEPP), general
refuse (from construction workforce) and chemical waste (from maintenance of
construction plant and equipment).
Provided that these wastes are handled, transported and reuse/disposed
of using approved methods and that the recommended good site practices are
strictly followed, adverse environmental impacts during construction phase
would not be anticipated.
3.4.1.2
Reduction measures have been
recommended to minimise the amount of materials generated in the Project. Approximately 268,100 m3 of inert
materials and 20,900 m3 of non-inert materials would be generated
during the construction phase of the Project.
52,900 m3 of inert material would be reused on site while the
remaining 215,200 m3 of surplus C&D inert material would be
recycled or transported to Public Fill Reception Facilities (PFRFs) for
beneficial reuse in other projects.
Non-inert waste would be recycled as far as possible before disposed of
to landfill. Opportunities in
minimisation of generation and maximisation of reuse would be continually
investigated during the detailed design and construction phases. The other materials that cannot be reused or
recycled would be disposed of to designated outlets.
3.4.1.3
During operation, the main
waste types to be generated would be grit and screenings, dewatered sludge,
chemical waste and general refuse. The
grit and screenings would be compacted and properly stored in a covered
container prior being disposed of at landfill on a daily basis. The transportation and disposal of the grit
and screenings would be managed and controlled by a reputable waste
collector. The dewatered sludge would be
disposed of to the Sludge Treatment Facility (STF). Provided proper handling procedures and
disposal method are adopted, adverse environmental impacts would not be
anticipated during the operation phase.
3.5.1.1
A site appraisal, including the review of the YLS EIA Study,
further desktop review and site walkover, was conducted from August 2020 to
September 2021 to identify any potentially contaminating land uses within the
proposed YLSEPP site. Based on the site
appraisal findings, 23 potentially contaminated sites are located within the
proposed YLSEPP site.
3.5.1.3
With
the implementation of the recommended further works for the Project, any soil /
groundwater contamination would be identified and properly treated prior to the
construction works. No insurmountable
land contamination impacts to the Project are therefore anticipated.
3.6.1.1
The Ecological Impact
Assessment was conducted in accordance with the criteria and guidelines as
stated in the requirements given in Clause 3.4.9 and Appendix G of the EIA
Study Brief, as well as Annexes 8 and 16 of the EIAO-TM.
3.6.1.2
A literature review and 6-month
ecological field surveys have been conducted. A total of eleven habitat types,
including developed area/wasteland, plantation, grassland, shrubland, mixed
woodland, village/orchard, agricultural land, marsh, pond, modified watercourse
and natural watercourse were recorded within the 500 m assessment area from
recent surveys, with developed area/wasteland, and small areas of shrubland and
modified watercourse recorded within the Project site. The ecological values of habitats within the
Project site are low.
3.6.1.3
The Project site of YLS EPP is
restricted within developed land which would be formed under a separate
agreement of YLS DA prior to the commencement of construction works for this
Project, and no encroachment into any sites of conservation importance is
anticipated. As such, no direct impact
on natural habitats and sites of conservation importance is anticipated. Similarly, no species of conservation
importance or fauna of particular concern (i.e. ardeids, waterbirds,
wetland-dependent birds and reedbed-associated birds) and their dependent habitats
was recorded within the Project site, thus no direct impact is expected. Species of conservation importance that
recorded in close proximity of the Project site, such as Luofushan Joint-fir,
Japanese Pipistrelle and Greater Coucal, are species that are more tolerant of
human disturbance and are well-adapted and commonly found in or close to disturbed
urban areas. Thus, indirect impact on these species is anticipated to be minor.
3.6.1.4
Though indirect impacts, in the
form of construction disturbance and water quality reduction, are anticipated,
the ecological impact from these indirect impacts is expected to be minor and
low and no mitigation measures are required.
Precautionary measures and enhancement opportunities to further minimise
any potential environmental impacts and to promote the ecological value of the
Project are recommended.
3.6.1.5
Ecological monitoring is not
required as no significant construction and operational phase ecological
impacts impact are anticipated.
3.7.1.1
Landscape and visual impacts
assessment has been assessed in accordance with the criteria and guidelines as
stated in Annexes 10 and 18 of the EIAO-TM and the Environmental Impact
Assessment Ordinance (EIAO) Guidance Note No. 8/2010 on “Preparation of
Landscape and Visual Impact Assessment under the Environmental Impact
Assessment Ordinance”, as well as Section 3.4.9 and Appendix Q1 of the EIA
study brief.
3.7.1.2
The Project will inevitably
result in some landscape and visual impacts during construction and operation
phases. These impacts have been
minimized through minimization of works areas, and incorporation of sensitive
and aesthetically pleasing design of aboveground structures and appropriate
landscape and visual treatments for the project.
Landscape
Impacts
3.7.1.3
Within the assessment area, 10
Landscape Resources (LRs) and 5 Landscape Character Areas (LCAs) are
identified.
3.7.1.4
Based on the broad-brush tree
estimate with approximately 402 nos. of trees surveyed, total 402 trees in
9 tree groups (no trees of particular interests and potential tree of
particular interest) that within the project boundary and would be potentially
affected. There is no OVT in accordance with DEVB TC(W) No. 5/2020 identified
within the project boundary. The dominant tree species include Macaranga
tanarius, Ficus microcarpa, Ficus hispida, Sterculia lanceolata, Schefflera
heptaphylla, Ficus benjamina, Celtis sinensis, Microcos nervosa, Sapium
discolor, Melia azedarach and Leucaena leucocephala. They are
generally of heavy-standard to mature size.
All tree species in tree groups surveyed are common in Hong Kong and
without specific conservation interest, in which 10 nos. of the surveyed trees
are undesirable tree species Leucaena leucocephala.
3.7.1.5
Under the proposed scheme for
the Project, opportunities for tree compensation within the Project boundary
has been fully explored and incorporated in the proposed mitigation measures as
much as practicable. Compensatory tree planting in heavy standard size is
proposed On-Site and along roadside flat areas. Within the project boundary, a
minimum of 405 heavy standard trees will be proposed On-Site. Mix of native
tree species will be proposed in reference to Guiding Principles on Use of
Native Plant Species in Public Works Projects promulgated by DEVB to improve
the vegetation diversity, enhance ecological value and re-creation of
vegetation habitat particular for areas adjoining the hillside area.
Visual Impacts
3.7.1.6
There are 7 types of Key
Visually Sensitive Receiver (VSR) Types identified in the Visual Envelopes of
the Project, which are Residential VSRs, Planned Residential VSRs, Occupational
VSR, Planned Occupational VSR, Recreational VSR, Planned Recreational VSR and
Travelling VSR.
3.7.1.7
Appropriate landscape and
visual mitigation measures are proposed during construction phase, including
Preservation of Existing Vegetation, Minimize Disturbance on Watercourses,
Management of Construction Activities and Facilities, Reinstatement of Temporarily
Disturbed Landscape Areas, Control of Night-time Lighting Glare and Erection of
Decorative Screen Hoarding, and during operation phase, including Compensatory
Tree Planting for Loss of Existing Trees, Roadside and Amenity Planting,
Sensitive and Aesthetically Pleasing Design of Aboveground Structures,
Enhancement of Landscape Buffer, Provision of Green Roof and Control of
Night-time Lighting Glare, to alleviate the potential impacts. Regarding
mitigated visual impact, it is predicted that there would be slight to moderate
residual impact on most of the VSRs during construction, and would be
insubstantial to slight on day 1 of operation and be further reduced to
insubstantial when the proposed tree planting becomes mature in year 10 of
operation.
3.7.1.8
As a whole, the residual
landscape and visual impacts of the proposed Project is considered acceptable
with the proposed mitigation measures implemented during construction and
operation phases.
3.8.1.1
A quantitative hazard
assessment was conducted to evaluate the biogas risk to existing, committed and
planned off-site population due to operation of the organic wastes co-digestion
facility at the proposed YLSEPP.
3.8.1.2
The assessment findings
revealed that both the individual and societal risk levels would meet relevant
requirements stipulated in the Hong Kong Risk Guidelines (HKRG), i.e. the
off-site individual risk level is far below 1×10-5 per year and
the societal risk falls into the “Acceptable” region. Therefore, the
biogas risk associated with the operation of the proposed YLSEPP is considered
acceptable.
4.1.1.1
Environmental Monitoring and
Audit (EM&A) requirements for air quality, noise, water quality, waste
management, land contamination, ecological (terrestrial and aquatic), and
landscape and visual impacts as well as hazard to life have been recommended,
with regular site inspection and audits during construction phase to ensure
that the recommended mitigation measures are properly implemented. The EM&A requirements are specified and
detailed in the EM&A Manual.
5.1.1.1
The
findings of the EIA provided information on the nature and extent of the
environmental impacts likely to arise from the construction and operation of
the Project. The EIA has, where appropriate,
identified mitigation measures to ensure compliance with environmental
legislation and standards.
5.1.1.2
Overall,
the EIA concluded that the Project would comply with the requirements of the
EIA Study Brief and EIAO-TM with the implementation of the proposed mitigation
measures during construction and operational phases of the Project. The schedule of implementation of the
proposed mitigation measures has been provided in the EIA Report. An EM&A programme has also been
recommended to check the effectiveness of the proposed mitigation measures.