TABLE OF CONTENTS
12........... Implementation schedule of Recommended Mitigation Measures
12.1........ Implementation Schedule of
Recommended Mitigation Measures
List of Tables |
|
Table 12.1 Implementation
Schedule of Recommended Mitigation Measures
|
|
EIA Ref. |
EM&A Ref. |
Recommended Mitigation Measures |
Objectives of the Measures & Main
Concerns to Address |
Location / Duration of Measures /
Timing of Completion of Measures |
Implementation Agent |
Implementation Stage* |
Relevant Legislation & Guidelines |
|
||
Des |
C |
O |
|
|||||||
Air Quality
Impact |
||||||||||
Construction Phase |
||||||||||
3.8.1 |
2.4.1 |
Regular
watering on works area every two hours. |
To reduce dust emission. |
Construction Sites |
Contractor |
|
√ |
|
Air Pollution Control Ordinance (APCO); Air
Pollution Control (Construction Dust) Regulation; HKAQO; Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM) |
|
3.8.1 |
2.4.1 |
Dust
suppression measures stipulated in the Air Pollution Control (Construction
Dust) Regulation and good site practices listed below shall be carried out to
further minimize construction dust impact: •
Use of regular watering to reduce dust emissions
from exposed site surfaces and unpaved roads, particularly during dry
weather. •
Use of frequent watering for particularly dusty
construction areas and areas close to ASRs. •
Side enclosure and covering of any aggregate or
dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering shall be applied to aggregate fines. •
Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs. •
Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations. •
Establishment and use of vehicle wheel and body
washing facilities at the exit points of the site. •
Provision of wind shield and dust extraction units
or similar dust mitigation measures at the loading area of barging point, and use of water sprinklers at the loading area
where dust generation is likely during the loading process of loose material,
particularly in dry seasons/ periods. •
Provision of not less than 2.4m high hoarding from
ground level along site boundary where adjoins a road, streets or other
accessible to the public except for a site entrance or exit. •
Imposition of speed controls for vehicles on site
haul roads. •
Where possible, routing of vehicles and positioning
of construction plant should be at the maximum possible distance from ASRs. •
Instigation of an environmental monitoring and
auditing program to monitor the construction process in
order to enforce controls and modify method of work if dusty
conditions arise. |
To minimize construction dust
impacts. |
Construction Sites |
Contractor |
|
√ |
|
Air Pollution Control Ordinance (APCO); Air
Pollution Control (Construction Dust) Regulation; HKAQO; Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM) |
|
Operation Phase |
||||||||||
3.5.2 |
2.4.1 |
Biogas
generated will be stored in the biogas holders. The stored biogas will go through the
sulphur absorption vessels to remove the hydrogen sulphide (H2S)
before passing to the combined heat and power (CHP) generator. |
To minimize air quality impact
during plant operation. |
YLSEPP / Operation Phase |
Operator |
√ |
|
√ |
EIAO-TM |
|
3.6.3 & 3.7.3 |
2.4.1 |
All the odour sources in YLSEPP
should be covered and all odourous
gas should be treated at the deodourizers (DOs)
with 95% odour removal efficiency before venting to the atmosphere. |
To minimize odour impacts
during plant operation. |
YLSEPP / Operation Phase |
Operator |
√ |
|
√ |
EIAO-TM |
|
Noise
Impact |
||||||||||
Construction Phase |
||||||||||
4.8.1 |
3.8.1 |
Temporary movable noise barriers are recommended for
excavators, mobile cranes, dump trucks, grout mixers and grout pumps. Noise insulating fabric are recommended for
drilling rig and piling machines.
Ventilated acoustic enclosure are recommended for generators. Quiet excavator and mobile cranes are also
recommended. Good site practices listed below
and the noise control requirements stated in EPD’s “Recommended Pollution Control Clauses for Construction Contracts”
should be included in the Contract Specification for the Contractors to
follow and should be implemented to further minimize the potential noise impacts
during the construction phase of the Project. •
Quiet PME, such that those listed in EPD’s Quality
Powered Mechanical Equipment, should be considered for construction works to
further minimize the potential construction noise impact. •
Only well-maintained plant should be operated on-site and plant should be serviced regularly during the
construction programme. •
Silencers or mufflers on construction equipment
should be utilised and should be properly maintained during the construction
programme. •
Mobile plant, if any, should be sited as far away
from noise sensitive receivers (NSRs) as possible. •
Machines and plant (such as trucks) that may be in
intermittent use should be shut down between work periods or should be
throttled down to a minimum. •
Plant known to emit noise strongly in one direction
should, wherever possible, be orientated so that the noise is directed away
from the nearby NSRs •
Material stockpiles and other structures should be
effectively utilised, wherever practicable, in screening noise from on-site
construction activities. |
To minimize construction noise
impact arising from the Project at the affected NSRs. |
Construction sites |
Contractor |
√ |
√ |
|
EIAO-TM |
|
Operation Phase |
||||||||||
4.8.2 |
3.10.1.1 |
Commissioning
test should be conducted to ensure fixed plant noise impact would comply with
the relevant noise standards |
To ensure compliance with
relevant noise standards. |
YLSEPP / Operational Phase |
Project Proponent |
√ |
|
√ |
EIAO-TM;
Noise
Control Ordinance (NCO) |
|
Water
Quality Impact |
||||||||||
Construction Phase |
||||||||||
5.7.1.2 & 5.7.1.3 |
S4 |
The
site practices outlined in ProPECC PN 1/94 “Construction
Site Drainage” should be followed as far as practicable to minimise
surface run-off and the chance of erosion.
Surface run-off from construction sites should be discharged into
storm drains via adequately designed sand / silt removal facilities such as
sand traps, silt traps and sedimentation basins. Channels, earth bunds or sand
bag barriers should be provided on site to properly direct stormwater
to such silt removal facilities.
Perimeter channels at site boundaries should be provided as necessary
to intercept storm run-off from outside the site so that it will not wash
across the site. Catchpits and
perimeter channels should be constructed in advance of site formation works
and earthworks. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
Water Pollution Control
Ordinance (WPCO); EIAO-TM, Professional Persons Environmental Consultative
Committee (ProPECC) Practice Note (PN) 1/94 |
|
5.7.1.4 |
S4 |
Silt removal facilities, channels and manholes should be maintained and the deposited silt and grit should be
removed regularly (as well as at the onset of and after each rainstorm) to
prevent overflows and localised flooding.
Before disposal at the public fill reception facilities, the deposited
silt and grit should be solicited in such a way that it can be contained and
delivered by dump truck instead of tanker truck. Any practical options for the diversion and
realignment of drainage should comply with both engineering and environmental
requirements in order to provide adequate hydraulic
capacity of all drains. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, ProPECC PN 1/94 |
|
5.7.1.5 |
S4 |
Construction
works should be programmed to minimise soil excavation in the wet season (i.e. April to September).
If soil excavation cannot be avoided in these months or at any time of
year when rainstorms are likely, temporarily exposed slope surfaces should be
covered e.g. by tarpaulin, and temporary access
roads should be protected by crushed stone or gravel, as excavation
proceeds. Intercepting channels should
be provided (e.g. along the crest / edge of
excavation) to prevent storm run-off from washing across exposed soil
surfaces. Arrangements should always
be in place in such a way that adequate surface protection measures can be
safely carried out well before the arrival of rainstorm. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, ProPECC PN 1/94 |
|
5.7.1.6 |
S4 |
Earthworks
final surfaces should be well compacted and the
subsequent permanent work or surface protection should be carried out
immediately after the final surfaces are formed to prevent erosion caused by
rainstorms. Appropriate drainage like
intercepting channels should be provided where necessary. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.7 |
S4 |
Measures should be taken to minimise the ingress
of rainwater into trenches. If
excavation of trenches in the wet season is necessary, they should be dug and
backfilled in short sections. Rainwater
pumped out from trenches or foundation excavations should be discharged into
storm drains via silt removal facilities |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.8 |
S4 |
Construction materials (e.g.
aggregates, sand and fill material) on sites should be covered with tarpaulin
or similar fabric during rainstorms. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.9 |
S4 |
Manholes (including newly constructed ones)
should always be adequately covered and temporarily sealed so
as to prevent silt, construction materials or debris from getting into
the drainage system, and to prevent storm run-off from getting into foul
sewers. Discharge of surface run-off
into foul sewers must always be prevented in order not to unduly overload the
foul sewerage system. |
To minimize water quality impact
from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.10 |
S4 |
Water used in ground boring and drilling for site
investigation or rock / soil anchoring should as far as practicable be
re-circulated after sedimentation.
When there is a need for final disposal, the wastewater should be
discharged into storm drains via silt removal facilities |
To minimize water quality
impact from boring and drilling activities |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.11 |
S4 |
All vehicles and plants should be cleaned before
they leave a construction site to minimise the deposition of earth, mud and debris on roads.
A wheel washing bay should be provided at every site exit if
practicable and washwater should have sand and silt
settled out or removed before discharging into storm drains. The section of construction road between
the wheel washing bay and the public road should be paved with backfill to
reduce vehicle tracking of soil and to prevent site run-off from entering
public road drains. |
To minimize water quality
impact from wheel washing. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; ProPECC PN 1/94 |
|
5.7.1.12 |
S4 |
Good site practices should be adopted to remove
rubbish and litter from construction sites so as to
prevent the rubbish and litter from spreading from the site area. It is recommended to clean the construction
sites on a regular basis. |
To minimize water quality
impact from rubbish and litter in construction site. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, Waste Disposal Ordinance (WDO) |
|
5.7.1.13 |
S4 |
There is a need to apply to EPD for a discharge
licence for discharge of effluent from the construction site under the
WPCO. The discharge quality must meet
the requirements specified in the discharge licence. All the runoff and wastewater generated
from the works areas should be treated so that it satisfies all the standards
listed in the TM-DSS. The beneficial
uses of the treated effluent for other on-site activities such as dust
suppression, wheel washing and general cleaning etc., can minimise water
consumption and reduce the effluent discharge volume. If monitoring of the treated effluent
quality from the works areas is required during the construction phase of the
Project, the monitoring should be carried out in accordance with the relevant
WPCO licence. |
To minimize water quality
impact from effluent discharge. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM; Technical
Memorandum for Effluents Discharged into Drainage and Sewerage Systems,
Inland and Coastal Waters (TM-DSS) |
|
5.7.1.14 |
S4 |
The practices outlined in ETWB TC (Works) No.
5/2005 “Protection of natural streams / rivers from adverse impacts
arising from construction works” should also be adopted where applicable
to minimise the water quality impacts on natural streams or surface water
systems. Relevant mitigation measures
from the ETWB TC (Works) No. 5/2005 are listed below: •
Construction works close to the inland waters
should be carried out in the dry season as far as practicable where the flow
in the surface channel or stream is low. •
The use of less or smaller construction plants
may be specified in areas close to the water courses to reduce the
disturbance to the surface water. •
Temporary storage of materials (e.g. equipment, chemicals and fuel) and temporary
stockpile of construction materials should be located well away from any
water courses when carrying out of the construction works. •
Stockpiling of construction materials and dusty
materials should be covered and located away from any water courses. •
Construction debris and spoil should be covered
up and / or disposed of as soon as possible to avoid being washed into the
nearby water receivers. •
Proper shoring may need to be erected in order to prevent soil or mud from slipping into the
watercourses |
To minimize water quality
impact from construction works in close proximity to
inland water. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, ETWB TC (Works)
No. 5/2005 |
|
5.7.1.15 |
S4 |
Contractor
must register as a chemical waste producer if chemical wastes would be
produced from the construction activities.
The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations
in particular the Waste Disposal (Chemical Waste) (General) Regulation should
be observed and complied with for control of chemical wastes. |
To minimize water quality
impact from accidental spillage of chemicals. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, WDO |
|
5.7.1.16 |
S4 |
Any
service shop and maintenance facilities should be located on hard standings
within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential leakage and spillage should only be
undertaken within the areas appropriately equipped to control these
discharges. |
To minimize water quality
impact from accidental spillage of chemicals. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM |
|
5.7.1.17 |
S4 |
Disposal
of chemical wastes should be carried out in compliance with the WDO. The “Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes” published under the Waste
Disposal Ordinance should be followed to avoid leakage or spillage of chemicals. General requirements are given as follows: • Suitable containers
should be used to hold the chemical wastes to avoid leakage or spillage
during storage, handling and transport • Chemical waste
containers should be suitably labelled, to notify and warn the personnel who
are handling the wastes to avoid accidents • Storage area should
be selected at a safe location on site and adequate space should be allocated
to the storage area. |
To minimize water quality
impact from accidental spillage of chemicals. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM, WDO |
|
5.7.1.18 |
S4 |
Sufficient
chemical toilets should be provided in the works area, with a licensed waste
collector employed to clean the chemical toilets on a regular basis. |
To minimize water quality
impact from sewage effluent from construction workforce. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM |
|
5.7.1.19 |
S4 |
Notices
should be posted at conspicuous locations to remind the workers not to discharge
any sewage or wastewater into the surrounding environment. Regular environmental audit of the
construction site will provide an effective control of any malpractices and
can encourage continual improvement of environmental performance on site. |
To minimize water quality
impact from construction site run-off. |
Construction Sites /
Construction Phase |
Contractor |
|
√ |
|
WPCO; EIAO-TM |
|
Design and
Operation Phases |
||||||||||
5.7.2.1 |
S4 |
Given
the sensitivity of inner Deep Bay in term of water quality and ecology,
extensive effort will be expedited to avoid the occurrence for emergency
discharge. In order
to achieve this, the design of YLSEPP will be cautiously reviewed to
include additional provisions including as follows: ·
Applied peaking factors
for all major treatment units and electrical and mechanical equipment to
avoid equipment failure; ·
By-pass mechanism would
be provided for both coarse screens and fine screens in the inlet to
avoid/minimize failure in coarse/fine screens; Interim by-pass would be provided
after the PST to avoid raw sewage by-pass as much as possible; ·
Standby unit for all
major equipment would be provided in case of unexpected breakdown of pumping
and treatment facilities such that the standby pumps and treatment facilities
could take over and function to replace the broken pumps; and ·
Back-up power for dual
power supply would be provided in case of power failure to sustain the
function of pumping and treatment facilities. |
To protect the inner Deep Bay’s
water quality and ecology. |
Project site / Design and
Operation Phase |
Project Proponent |
√ |
|
√ |
WPCO |
|
5.7.2.2 |
S4 |
To
provide a mechanism to minimise the impact of emergency discharges and
facilitate subsequent management of any emergency, an Emergency Response Plan
will be formulated prior to commissioning of YLSEPP to set out the emergency
response procedures and actions to be followed in case of equipment or sewage
treatment failure. The plant operators
of YLSEPP should carry out necessary follow-up actions according to the
procedures of the contingency plan to minimise any impacts on the identified
WSRs due to emergency bypass. Regular
maintenances and inspections to all treatment units, penstocks and plant
facilities are necessary to maintain a good operation condition. A follow-up water quality monitoring
exercise shall be conducted after each emergency discharge event to monitor
the recovery of water quality in the vicinity. |
To protect inner Deep Bay’s water
quality and ecology. |
Project site / Design and
Operation Phase |
Project Proponent |
√ |
|
√ |
WPCO |
|
5.7.2.3 to 5.7.2.10 |
S4 |
Best
Management Practices (BMPs) to reduce storm water and non-point source
pollution are also proposed as follows: Design Measures
·
Exposed surface shall be
avoided within the the proposed development to
minimise soil erosion. The site shall
be either hard paved or covered by landscaping area and plantation where
appropriate. ·
Green areas /
tree / shrub planting etc. should be introduced within the site as far as
possible including open space and along roadside amenity strips, which can
help to reduce soil erosion. ·
The existing
watercourses in adjacent to the Project site will be retained to maintain the
original flow path. The drainage
system will be designed to avoid any case of flooding based on the 1 in 50 year return period. Devices/ Facilities to Control
Pollution
·
Screening
facilities such as standard gully grating and trash grille, with spacing
which is capable of screening off large substances such as fallen leaves and
rubbish should be provided at the inlet of drainage system. ·
Road gullies
with standard design and silt traps and oil interceptors should be
incorporated during the detailed design to remove particles present in storm
water runoff. Administrative Measures ·
Good
management measures such as regular cleaning and sweeping of road surface /
open areas is suggested. The road
surface / open area cleaning should also be carried out prior to occurrence
of rainstorm. ·
Manholes, as
well as storm water gullies, ditches provided at the Project site should be
regularly inspected and cleaned (e.g. monthly). Additional inspection and cleansing should
be carried out before forecast heavy rainfall. |
To minimize water quality impact
from surface run-off. |
Project site / Design and
Operation Phase |
Project Proponent |
√ |
|
√ |
WPCO; ProPECC
PN 5/93 |
|
5.7.2.11 |
S4 |
Chemical should be stored on site at bunded area and separate drainage
system as appropriate should be provided to avoid any spilled chemicals from
entering the storm drain in case of accidental spillage. Also, adequate tools for cleanup of spilled
chemicals should be stored on site and appropriate training shall be provided
to staffs to further prevent potential adverse water quality impacts from
happening. |
To minimize water quality
impact from accidental spillage of chemicals. |
Project site / Design and
Operation Phase |
Project Proponent |
√ |
|
√ |
WPCO |
|
Waste
Management Implication |
||||||||||
Construction Phase |
||||||||||
6.6.1 |
5.2 |
Good
Site Practices Recommendations
for good site practices during the construction phase include: •
Nomination of an approved personnel, such as a site
manager, to be responsible for good site practices, and making arrangements
for collection of all wastes generated at the site and effective disposal to
an appropriate facility; •
Training of site personnel in proper waste
management and chemical waste handling procedures; •
Provision of sufficient waste reception/ disposal
points, of a suitable vermin-proof design that minimises windblown litter; •
Arrangement for regular collection of waste for
transport off-site and final disposal; •
Appropriate measures to minimise windblown litter
and dust during transportation of waste by either covering trucks or by
transporting wastes in enclosed containers; •
Regular cleaning and maintenance programme for
drainage systems, sumps and oil interceptors; •
A recording system for the amount
of wastes generated, recycled and disposed (including the disposal sites)
should be proposed; and • Preparation of a WMP in accordance with ETWB TCW No. 19/2005 and
submit to the Engineer for approval. |
|
Construction Sites |
Contractor |
|
√ |
|
Waste Disposal Ordinance (WDO) |
|
6.6.1 |
5.2 |
Waste Reduction Measures Recommendations
to achieve waste reduction include: •
Segregate and store different types of construction
related waste in different containers, skips or stockpiles to enhance reuse
or recycling of materials and their proper disposal; •
Provide separate labelled bins to segregate
recyclable waste such as aluminium cans from other general refuse generated
by the work force, and to encourage collection by individual collectors; •
Any unused chemicals or those with remaining
functional capacity shall be recycled; •
Maximising the use of reusable steel formwork to
reduce the amount of C&D materials; •
Prior to disposal of C&D waste, it is
recommended that wood, steel and other metals shall be separated for re-use
and/or recycling to minimise the quantity of waste to be disposed of at landfill; •
Adopt proper storage and site practices to minimise
the potential for damage to, or contamination of, construction materials; •
Plan the delivery and stock of construction
materials carefully to minimize the amount of surplus waste generated; •
Adopt pre-cast construction method instead of
cast-in-situ method for construction of concrete structures as much as possible; •
Minimise over ordering of concrete, mortars and cement grout by doing careful check before
ordering; and • Provide training to workers on the importance of appropriate waste
management procedures, including waste reduction, reuse
and recycling. |
|
Construction Sites |
Contractor |
|
√ |
|
WDO |
|
6.6.1 |
5.2 |
Storage of Waste Recommendations
to minimise the impacts include: •
Waste, such as soil, should be handled and stored
well to ensure secure containment, thus minimizing the potential of pollution; •
Maintain and clean storage areas routinely; •
Stockpiling area should be provided with covers and
water spraying system to prevent materials from wind-blown or being washed
away; and • Different locations should be designated to stockpile each material to
enhance reuse. |
|
Construction Sites |
Contractor |
|
√ |
|
- |
|
6.6.1 |
5.2 |
Collection
of Waste Licensed
waste haulers should be employed for the collection and transportation of
waste generated. The following measures should be enforced to minimise the
potential adverse impacts: •
Remove waste in a timely manner; •
Waste collectors should only collect wastes
prescribed by their permits; •
Impacts during transportation, such as dust and
odour, should be mitigated by the use of covered trucks or in enclosed containers; •
Obtain relevant waste disposal permits from the
appropriate authorities; •
Dispose of waste at licensed waste disposal
facilities; and •
Maintain records of quantities of waste generated, recycled and disposed. |
|
Construction Sites |
Contractor |
|
√ |
|
WDO;
Waste Disposal (Charges for Disposal of Construction Waste) Regulation; Land
(Miscellaneous Provisions) Ordinance |
|
6.6.1 |
5.2 |
Transportation
of Waste In order to monitor the disposal
of C&D materials at PFRFs and landfills and to control fly-tipping, a
trip-ticket system should be established in accordance with DEVB TCW No.
6/2010. A recording system for the amount of waste
generated, recycled and disposed, including the disposal sites, should also
be set up. Warning signs should be put up to remind the designated disposal
sites. CCTV should be installed at the vehicular entrance and exit of the
site as additional measures to prevent fly-tipping. |
|
Transportation Route of Waste /
Construction Phase |
Contractor |
|
√ |
|
DEVB TC(W) No. 6/2010 |
|
6.6.1 |
5.2 |
Construction
and Demolition Material Careful
design, planning together with good site management can reduce over-ordering
and generation of C&D materials such as concrete, mortar and cement
grouts. Formwork should be designed to maximize the use of standard wooden
panels, so that high reuse levels can be achieved. Alternatives such as steel
formwork or plastic facing should be considered to increase the potential for
reuse. |
|
Construction Sites |
Contractor |
√ |
√ |
|
- |
|
6.6.1 |
5.2 |
The
excavated material arising from site formation and foundation works should be
reused on-site as backfilling material and for landscaping works as far as
practicable. Other mitigation requirements are listed below: •
A WMP, which becomes part of the EMP, should be
prepared in accordance with ETWB TCW
No.19/2005; •
A recording system for the amount
of wastes generated, recycled and disposed (including the disposal sites)
should be adopted for easy tracking; and •
In order
to monitor the disposal of C&D materials at public
filling facilities and landfills and to control fly-tipping, a trip-ticket
system should be adopted (refer to DEVB
TCW 06/2010). |
|
Construction Sites |
Contractor |
|
√ |
|
WDO; ETWB TCW No.19/2005; ETWB
TCW No. 6/2010 |
|
6.6.1 |
5.2 |
It
is recommended that specific areas should be provided by the Contractors for
sorting and to provide temporary storage areas (if required) for the sorted
materials. Control measures for temporary stockpiles on-site should be taken in order to minimize the noise, generation of dust and
pollution of water. These measures include: •
Surface of stockpiled soil should be regularly
wetted with water especially during dry season; •
Disturbance of stockpile soil should be minimised; •
Stockpiled soil should be properly covered with
tarpaulin especially when heavy storms are predicted; and • Stockpiling areas should be enclosed where space is available. |
|
Construction Sites |
Contractor |
|
√ |
|
ETWB TCW No.19/2005 |
|
6.6.1 |
5.2 |
The
Contactor should prepare and implement an EMP in accordance with ETWB TCW No.
19/2005, which describes the arrangements for avoidance, reuse, recovery,
recycling, storage, collection, treatment and
disposal of different categories of waste to be generated from construction
activities. Such a management plan should incorporate site-specific factors,
such as the designation of areas for segregation and temporary storage of
reusable and recyclable materials. The EMP should be submitted to the
Engineer for approval. The Contractor should implement waste management
practices in the EMP throughout the construction stage of the Project. The
EMP should be reviewed regularly and updated by the Contractor, preferably on a monthly basis. |
|
Construction Sites |
Contractor |
|
√ |
|
ETWB TCW No.19/2005 |
|
6.6.1 |
5.2 |
The
Contractor would be responsible for devising a system to work for on-site
sorting of C&D materials and promptly removing all sorted and process
materials arising from the construction activities to minimise temporary
stockpiling on-site. The system should be included in the EMP identifying the
source of generation, estimated quantity, arrangement for on-site sorting,
collection, temporary storage areas and frequency of collection by recycling
Contractors or frequency of removal off-site. |
|
Construction Sites |
Contractor |
|
√ |
|
- |
|
6.6.1 |
5.2 |
Suitable
containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. Appropriate labels should
be securely attached on each chemical waste container indicating the
corresponding chemical characteristics of the chemical waste, such as
explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc.
The Contractor shall employ a licensed collector to transport and dispose of
the chemical wastes, to the licensed CWTC, or other licensed facilities, in
accordance with the Waste Disposal (Chemical Waste) (General) Regulation |
|
Construction and Operation
Phases |
Contractor / Operator |
|
√ |
√ |
ETWB
TC(W) 19/2005; TC(W) 6/2010; WDO; Waste Disposal (Chemical Waste) (General)
Regulation; Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes |
|
6.6.1 |
5.2 |
It
is recommended to place clearly labelled recycling bins at designated
locations with convenient access. Other general refuse should be separated
from chemical and industrial waste by providing separated bins or skips for
storage to maximise the recyclable volume. A
reputable licensed waste collector should be employed to remove general
refuse on a daily basis to minimise odour, pest and
litter impacts. |
|
Construction and Operation
Phases |
Contractor / Operator |
|
√ |
√ |
Public
Health and Municipal Services
Ordinance
(Cap.132) |
|
Operation
Phase |
||||||||||
6.6.2 |
5.2 |
The
below good housekeeping practices for the proposed YLSEPP should be followed
to further ameliorate any odour impact from handling, collection,
transportation and disposal of screenings, grits and
sludge: •
Screens should be cleaned regularly to remove any
accumulated organic debris; •
Screening and grit transfer systems should be
flushed regularly with water to remove organic debris and grit; •
Grit and screened materials should be transferred to
closed containers; •
Scum and grease collection wells and troughs should
be emptied and flushed regularly to prevent putrefaction of accumulated organics; •
Skim and remove floating solids and grease from
primary clarifiers regularly; •
Frequent sludge withdrawal from tanks is necessary
to prevent the production of gases; •
Organic waste should be transported to YLSEPP by
fully enclosed trucks to avoid odour nuisance; •
Organic waste should be stored in closed containers
at the reception area; •
During the unavailability of digesters (e.g. maintenance or co-digestion period), the diluted
organic waste should remain inside the Diluted Food Waste Preparation Tank
under continuously mixed condition; •
Sludge should be transported to the STF by
water-tight containers to avoid H2S/odour emission and ingress of
water into the containers which would lower the sludge dryness during transportation; •
Sludge cake should be transferred to closed containers; •
Sludge containers should be flushed with water
regularly; and •
Sludge trucks and containers should be washed
thoroughly before leaving the YLSEPP to avoid any odour nuisance during
transportation. |
|
Operation Phase |
Operator |
|
|
√ |
WDO |
|
6.6.2 |
5.2 |
The
screenings and grits would be collected and disposed of at landfill regularly
by a reputable waste collector while the dewatered sludge would be disposed
of at STF in Tuen Mun to reduce the potential pest, odour
and litter impacts. In addition, all wastewater generated from the sludge
dewatering process and all contaminated water from the cleaning operations
recommended for odour control will be diverted to the proposed YLSEPP for
proper treatment. |
|
Operation Phase |
Operator |
|
|
√ |
WDO |
|
Land
Contamination |
||||||||||
7.8.1 |
S6 |
Site
re-appraisal should be conducted for the potentially contaminated sites once
site access is available (e.g. after land resumption)
in order to identify the need for SI for any additional hotspots as a result
of the on-going land contaminating activities. In addition, re-appraisal would be required
for the other remaining areas of the proposed YLSEPP site to assess the latest
site situation in order to address any change in
land use that may give rise to potential land contamination issues. Findings
of the re-appraisal and strategy of the recommended SI, if required, will be
presented in a supplementary CAP. Upon
approval of the supplementary CAP and completion of the SI works, a
Contamination Assessment Report (CAR) would be prepared to present findings
of the SI works. If contamination has
been identified, a RAP would be prepared to recommend specific remediation
measures. Upon completion of the
remediation works, if any, a Remediation Report (RR) would also be prepared
to demonstrate that the clean-up works
are adequate. The CAR, RAP and RR
would be submitted to EPD for approval prior to commencement of any
construction / development works at the identified contaminated sites.
|
To
identify the need for SI for any additional hotspots as a
result of the on-going land contaminating activities and to assess the
latest site situation in order to address any change in land use that may
give rise to potential land contamination issues. |
Proposed
YLSEPP site / When site access is available (e.g. after land resumption) and prior to construction /
development works at the identified contaminated sites. |
Project
Proponent / Consultant / Contractor under the Yuen Long South Development
Area (YLS DA) project |
√ |
√ |
|
Guidance Note for Contaminated
Land Assessment and Remediation; Practice Guide for Investigation and
Remediation of Contaminated Land; Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management |
|
7.8.3 |
S6 |
The
mitigation measures will be recommended in the RAP and would typically
include the following: • Excavation profiles must be properly designed and executed with
attention to the relevant requirements for environment, health and safety; • Excavation shall be carried out during dry season as far as possible
to minimise contaminated runoff from contaminated soils; • Supply of suitable clean backfill material (or treated soil) after excavation; • Stockpiling site(s) shall be lined with impermeable sheeting and
bunded. Stockpiles shall be fully covered by impermeable sheeting to reduce
dust emission. If this is not practicable due to frequent usage, regular
watering shall be applied. However, watering shall be avoided on stockpiles
of contaminated soil to minimise contaminated runoff. • Vehicles containing any excavated materials shall be suitably covered
to limit potential dust emissions or contaminated wastewater run-off, and
truck bodies and tailgates shall be sealed to prevent any discharge during
transport or during wet conditions; • Speed control for the trucks carrying contaminated materials shall be enforced; • Vehicle wheel and body washing facilities at the site’s exist points
shall be established and used; and Pollution control measures for air emissions (e.g. from biopile blower and
handling of cement), noise emissions (e.g. from blower or earthmoving
equipment), and water discharges (e.g. runoff control from treatment
facility) shall be implemented and complied with relevant regulations and
guidelines.
|
To
minimise potential adverse environmental impacts arising from the handling of
potentially contaminated materials. |
Proposed
YLSEPP site / During remediation works and prior to
construction / development works at the identified contaminated sites. |
Contractor
under the YLS DA project |
|
√ |
|
Guidance Note for Contaminated
Land Assessment and Remediation; Practice Guide for Investigation and
Remediation of Contaminated Land; Guidance Manual for Use of Risk-based
Remediation Goals for Contaminated Land Management |
|
Ecological
Impact (Terrestrial and Aquatic) |
||||||||||
Nil |
||||||||||
Landscape
and Visual Impact |
||||||||||
Table 9.11 |
8.1.2 |
Preservation
of Existing Vegetation All
the existing vegetation and trees to be retained and not to be affected by
the Project shall be carefully protected during construction accordance with
DEVB TC(W) No. 4/2020 - Tree Preservation and the latest Guidelines on Tree
Preservation during Development issued by GLTMS of DEVB. Any existing vegetation in landscaped areas
and natural terrain not to be affected by the Project shall be carefully
preserved. |
To preserve existing
vegetation. |
Construction sites / Design and
Construction phase |
Project Proponent /
Contractor |
√ |
√ |
|
DEVB TC(W) No. 4/2020 - Tree
Preservation and the latest Guidelines on Tree Preservation during
Development issued by GLTMS of DEVB, Guidelines for Tree Risk Assessment and Management
Arrangement issued by DEVB |
|
Table 9.11 |
8.1.2 |
Minimize
Disturbance on Watercourses The
design shall minimize disturbance on watercourses, particularly for natural
watercourse. Good site practices as described in ETWB TCW No. 5/2005
“Protection of natural streams/rivers from adverse impacts arising from
construction works” shall also be adopted to avoid any pollution entering the
watercourses nearby where applicable. Should temporarily or indirect
disturbance on watercourse is unavoidable, it shall be reinstated to the
satisfaction of relevant Government Departments. |
To minimize disturbance to
watercourses. |
Construction sites / Design and
Construction phase |
Project Proponent /
Contractor |
√ |
√ |
|
ETWB TCW No. 5/2005 “Protection
of natural streams/rivers from adverse impacts arising from construction
works” |
|
Table 9.11 |
8.1.2 |
Management
of Construction Activities and Facilities The
facilities and activities at works sites and areas, which include site
office, temporary storage areas, temporary works etc., shall be carefully
managed and controlled on the height, deposition and
arrangement to minimise any potential adverse landscape and visual
impacts. |
To reinstate to equal or better
quality of temporarily disturbed landscape areas. |
Construction sites /
Construction phase |
Contractor |
|
√ |
|
- |
|
Table 9.11 |
8.1.2 |
Reinstatement
of Temporarily Disturbed Landscape Areas All
hard and soft landscape areas disturbed temporarily during construction due
to temporary excavations, temporary works sites and works areas shall be
reinstated to equal or better quality, to the satisfaction of the relevant
Government Departments. |
To reinstate to equal or better
quality of temporarily disturbed landscape areas. |
Construction sites /
Construction phase |
Contractor |
|
√ |
|
- |
|
Table 9.11 |
8.1.2 |
Control
of Night-time Lighting Glare Any
lighting provision of the construction works at night shall be carefully control to prevent light overspill to the nearby VSRs and
into the sky. Relevant best practices
as suggested in the “Guidelines on Industry Best Practices for External
Lighting Installations” promulgated by ENB shall be adopted. |
To prevent light overspill to
the nearby VSRs and into the sky. |
Construction sites /
Construction and Operational phase |
Project Proponent /
Contractor |
|
√ |
√ |
“Guidelines on Industry Best
Practices for External Lighting Installations” promulgated by ENB |
|
Table 9.11 |
8.1.2 |
Erection
of Decorative Screen Hoarding Decorative
Hoarding, which is compatible with the surrounding natural settings, shall be
erected during construction to minimise the potential landscape and visual
impacts due to the construction works and activities. |
To minimise the potential
landscape and visual impacts due to the construction works and
activities. |
Construction sites /
Construction phase |
Project Proponent /
Contractor |
|
√ |
|
- |
|
Table 9.12 |
8.1.2 |
Compensatory
Tree Planting for Loss of Existing Trees Any trees to be removed under
the Project shall be compensated in accordance with DEVB TC(W) No. 4/2020 -
Tree Preservation. The compensatory plantings shall be realistic, practicable
and sustainable with a holistic consideration to balance the quantity and
quality of tree planting and follow the “right tree for the right place”
principles. The proposed planting species shall be made
reference to the Greening Master Plan issued by CEDD and the Street
Tree Selection Guide issued by DEVB. Approximately
417 heavy standard trees are proposed within site under OM1, the exact number
and location subject to the detailed design at design and construction stage
of this Project. |
To compensate for loss of
existing trees. |
Construction sites / Design,
Construction and Operational phase |
Project Proponent /
Contractor/ Operator |
√ |
√ |
√ |
DEVB TC(W) No. 4/2020 - Tree
Preservation, GEO Publication No. 1/2011, the Greening Master Plan issued by
CEDD, the Street Tree Selection Guide issued by DEVB and DEVB TC(W) No.
6/2015 - Maintenance of Vegetation and Hard Landscape Features |
|
Table 9.12 |
8.1.2 |
Roadside
and Amenity Planting Roadside
amenity trees and understory planting to be planted along EVA and access road
within YLSEPP, as green buffers for the new proposed structures. The proposed
planting species shall be made reference to the
Greening Master Plan issued by CEDD and the Street Tree Selection Guide
issued by DEVB. |
To enhance ecological value and
improve overall value of landscape setting. |
Construction sites / Design,
Construction and Operational phase |
Project Proponent /
Contractor/ Operator |
√ |
√ |
√ |
DEVB TC(W) No. 4/2020 - Tree
Preservation, GEO Publication No. 1/2011, the Greening Master Plan issued by
CEDD, the Street Tree Selection Guide issued by DEVB and DEVB TC(W) No. 6/2015
- Maintenance of Vegetation and Hard Landscape Features |
|
Table 9.12 |
8.1.2 |
Sensitive
and Aesthetically Pleasing Design of Aboveground Structures Sensitive
and aesthetically pleasing design as regard to the form, material and
finishes shall be incorporated to the proposed above-ground structures e.g. effluent polishing plant, etc. Vertical greening
shall also be maximised as far as appropriate to provide a source of green
visual relief, minimise any potential adverse landscape and visual impacts,
and to blend in the structures to the adjacent landscape and visual
context. |
To minimise any potential
adverse landscape and visual impact. |
Construction sites / Design,
Construction and Operational phase |
Project Proponent /
Contractor/ Operator |
√ |
√ |
√ |
- |
|
Table 9.12 |
8.1.2 |
Enhancement
of Landscape Buffer With
the retained existing trees surrounding the YLSEPP perimeter, thickening of
understory plantings and/ or mounding in YLSEPP will be created as much as
possible. For planting to be proposed on slopes, the guidelines for planting
stipulated in GEO Publication No. 1/2011 will be followed. |
To enhance landscape quality. |
Construction sites / Design,
Construction and Operational phase |
Project Proponent /
Contractor/ Operator |
√ |
√ |
√ |
GEO Publication No. 1/2011, the
Greening Master Plan issued by CEDD, the Street Tree Selection Guide issued
by DEVB and DEVB TC(W) No. 6/2015 - Maintenance of Vegetation and Hard
Landscape Features |
|
Table 9.12 |
8.1.2 |
Provision
of Green Roof Green
Roof shall be proposed to enhance the landscape quality of the Aboveground
Structures including Primary Sedimentation Tanks and mitigate any potential
adverse visual impact on adjacent VSRs. The extent of roof greening shall be
in accordance with DEVB TC(W) No. 3/2012 – Site Coverage of Greenery for
Government Building Projects. |
To enhance landscape quality of
aboveground structures. |
Construction sites / Design,
Construction and Operational phase |
Project Proponent /
Contractor/ Operator |
√ |
√ |
√ |
DEVB TC(W) No. 3/2012 – Site
Coverage of Greenery for Government Building Projects |
|
Hazard
to Life |
||||||||||
Operation Phase |
||||||||||
10.9.1 |
9.2 |
·
Process
plant building should be provided with adequate number of gas detectors
distributed over various areas of potential leak sources to provide adequate
coverage. ·
All
electrical equipment inside the building should be classified in accordance
with the electrical area classification requirements. No unclassified
electrical equipment should be used during operations or maintenance. ·
All
safety valves should be designed to discharge the released fluid to a safe
location and stop misdirection of fluid flows in order to
avoid hazardous outcome. ·
Safety
markings and crash barriers should be provided to the aboveground piping, digesters and gas holders near the entrance. ·
Fixed
crash barriers should be provided in areas where process equipment is
adjacent to the internal roadway to protect against vehicle collision.
Adequate warning signage and lighting should also be provided
and maximum speed limit should also be in place. ·
Lightning
protection installations should be installed following IEC 62305, BS EN
62305, AS/NZS 1768, NFPA 780 or equivalent standards. ·
Suitable
fire extinguishers should be provided within the site. An External Water
Spray System (EWSS) should be installed in appropriate areas, such as around
the gasholders, digester and sulphur removal
vessels. The facilities should also be equipped with fire and gas detection
system and fire suppression system. ·
Stringent
procedures should be implemented to prohibit smoking or naked flames to be
used on-site. |
To minimize hazard to life. |
YLSEPP / Operational Phase |
Project Proponent, Operators |
√ |
|
√ |
- |
|