TABLE OF CONTENTS

 

13........... Conclusions. 13-1

13.1........ Introduction. 13-1

13.2........ Summary of Key Environmental Outcomes. 13-1

13.3........ Overall Conclusion. 13-7

 

List of Figures

 

 

 

 

 

 

List of Appendices

 

Appendix 13.1

Key Assessment Assumptions, Limitations of Assessment Methodologies and Prior Agreements with the Director

Appendix 13.2

Summary of Environmental Impacts

 

 

 


13                   Conclusions

13.1               Introduction

13.1.1.1       The Project covers the following designated project (DP) elements of Schedule 2, Part I under the Environmental Impact Ordinance (EIAO) (Cap.499):

·              Item F.1, Part I of Schedule 2 of the EIAO - Sewage treatment works with an installed capacity of more than 15,000 m3/day.

·              Item F.4, Part I of Schedule 2 of the EIAO - an activity for reuse of treated sewage effluent from a treatment plant

13.1.1.2       This EIA report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project based on the preliminary engineering design information available at this stage.  The assessment has been conducted, in accordance with the Study Brief No. ESB-313/2019 under the EIAO for the Project and the EIAO-TM, covering the following environmental issues.

        Air Quality Impact

        Noise Impact

        Water Quality Impact

        Waste Management Implication

        Land Contamination

        Ecological Impact (Terrestrial and Aquatic)

        Landscape and Visual Impact

        Hazard to Life

13.1.1.3       The findings of this EIA Study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, specific environmental control and mitigation measures have been identified and incorporated into the planning and design of the Project in order to achieve compliance with environmental legislation and standards during both the construction and operation phases.  An environmental monitoring and audit (EM&A) programme has also been developed.  The Implementation Schedules listing the recommended mitigation measures are presented in the Section 13.

13.1.1.4       A summary of the environmental outcomes/benefits that have accrued from the environmental considerations and analysis during the EIA study and the implementation of environmental control measures of the Project are presented in the sections below.  The key assessment assumptions and limitations of methodologies and summary of environmental impacts with proposed mitigation measures are presented in Appendices 13.1 and 13.2, respectively.

13.2               Summary of Key Environmental Outcomes

13.2.1           Environmental Benefits of the Project

13.2.1.1       The Government plans to develop Yuen Long South Development Area (YLS DA) which is a mega-scale and complex development aiming to provide land to transform the degraded brownfield land to developable land contributing to meet the territory’s medium to long-term need for housing development.  YLSEPP will provide sewage treatment to the sewage collected from the YLS DA and other developments in the North West New Territories (NWNT), and to subsequently provide treated effluent for further production of reclaimed water for reuse.

13.2.1.2       This Project will treat the collected sewage to a tertiary treatment level. The high effluent standard is suitable for further production of reclaimed water.  Most tertiary treated effluent will be reused to supply YLS DA and other surrounding areas’ flushing water demand, which saves freshwater resources.  Any surplus tertiary effluent will be discharged to Yuen Long Nullah for river vitalization.  Given the high effluent standard of tertiary treatment, it is anticipated that no negative impact to Deep Bay will be resulted.

13.2.1.3       The Project will also provide the opportunity to incorporate sustainable design and green features in the proposed treatment facilities such as co-digestion of organic wastes with sewage sludge to enhance energy recovery, renewable energy, green roof, effluent reuse, etc.

13.2.2           Environmental Friendly Design

13.2.2.1       Environmental considerations were taken into account in the selection of preferred option, design and construction method of the Project as detailed in Section 2.  The following environmental friendly designs have been considered:

·         Tertiary treatment will be adopted in YLSEPP, so that the treated effluent can be reused.

·         All the treatment units will be covered and ventilated via deodorization units to control and minimize odour impact.

·         All the treatment facilities will be enclosed within reinforced concrete buildings and ventilated with silencers at louvers such that fixed noise impact can be kept within the acceptable level.

·         A set of design measures will be installed to avoid and minimize the chance on emergency discharge

·         All the treatment units and buildings are designed with due considerations on minimizing the building heights by such means as adopting equipment that requires low headroom.  This is to ensure all the aboveground structures would not be excessively bulky so as to minimize the visual impacts.

·         Green building design will be incorporated to encourage low carbon and green STW, such as provision of photovoltaics (PV) system at building rooftops, biogas recovery and biodiesel as alternative power source for plant operation, reuse of treated effluent, etc.

13.2.3           Key Environmental Problem Avoided and Compensation Area Included

Avoidance of Encroachment into Recognized Site of Conservation Importance

13.2.3.1       While a number of sites of conservation importance are located within the assessment area for the Project and that the Project site is located adjacent to “CA”.  The Project site and construction works for the Project are designed to be confined within areas of existing development and/or within the boundary for planned development under the approved YLS DA, such that no sites of conservation importance would be directly affected.

Avoidance of Works within Adjacent Nullah

13.2.3.2       The effluent discharge pipe for the purpose of emergency discharge will be constructed within the site boundary.  As such, any works within the adjacent nullah that would induce direct impact to nearby waterbody has been avoided.

Avoidance and Minimization of Emergency Discharges

13.2.3.3       The design layout would adopt measures to ensure the reliability and to avoid and minimize the risk of emergency discharges of YLSEPP. The following design measures would be adopted at YLSEPP:

·         Provision of adequate standby units and peaking factors

·         Provision of by-pass mechanism at coarse and fine screens

·         Provision of reliable power supply

·         Provision on interim emergency by-pass after PST

·         Regular maintenances and inspections

·         Application of Emergency Response Plan

 

13.2.3.4       In addition, in case of emergency discharge, the upstream pumping station could be temporarily suspended, preventing sewage from entering to YLSEPP, so to lower the risk of any emergency discharge.

13.2.4           Population and Environmental Sensitive Areas Protected

13.2.4.1       The YLSEPP is located at the southern tip of YLS DA.  Population and environmental sensitive areas in the vicinity of the Project site have been protected through the avoidance and/or minimization of environmental impacts from the construction and operation the Project.

13.2.4.2       Provided that the site formation works of YLSEPP, which will be undertaken by CEDD under Agreement No. CE 35/2012 (CE) “Planning and Engineering Study for Housing Sites in Yuen Long South – Investigation”, will be completed before the construction of YLSEPP and all construction works of the Project being confined within the site boundary, no ecological sensitive areas would be directly impacted.  Population protected from air quality and noise impacts due to the construction and operation of the Project comprise the nearby village houses at Pak Sha Tsuen, Wong Nai Tun Tsuen and Pui Hong Kui.  Environmental sensitive areas protected from adverse water quality impacts include nearby modified watercourses, and the future reedbed planned under RODP for YLS DA.

13.2.5           Summary of Environmental Findings

Air Quality Impact

13.2.5.1       The potential air quality impacts from the construction works of the YLSEPP would mainly be related to the construction dust from the excavation, piling works, road paving works, construction of substructures and superstructure works.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation, good site practices, regular watering and EM&A programme, no adverse dust impact at ASRs is anticipated due to the construction activities of the Project.

13.2.5.2       Flue gas emission would be emitted from the stacks of CHP and boiler in the YLSEPP.  Cumulative air quality impact arising from YLSEPP operation, the vehicular emissions from the open roads within the 500m assessment area has been assessed for operation of YLSEPP.  The assessment results conclude that the predicted cumulative the 19th highest 1-hour average and annual average NO2, the 10th highest daily and annual average RSP, the 19th highest daily and annual average FSP, 10-min average and daily average SO2, and the maximum 1-hour and the maximum 8-hour average CO at representative ASRs would comply with the corresponding new AQOs.  The predicted maximum 1-hour average and annual average HCL, maximum 1-hour average and annual average HF, maximum 1-hour average methane, maximum 30-minute average and annual average formaldehyde would comply with the corresponding international standards.  No adverse air quality impact is anticipated arising from the flue gas emission associated with the operation of YLSEPP.

13.2.5.3       All odour sources in YLSEPP are fully enclosed.  The potential odour emission from the sewage treatment facilities, sludge treatment facilities and organic waste co-digestion facilities would all be treated in the deodourizers before discharge into atmosphere.  With implementation of the best-available deodourizers in the market with 95% odour removal efficiency, locating deodourizer exhaust away from ASRs as far as practicable, the assessment results show that the predicted Project-alone 5-second average odour concentration at the representative ASRs within the Study Area would be below 1 OU.

13.2.5.4       Considering the cumulative odour impact due to the Project and the retained chicken farm, the predicted cumulative odour concentrations at all planned ASRs would comply with the EIAO-TM criterion of 5 OU.  No adverse residual odour impact would be expected at the planned ASRs.

13.2.5.5       Cumulative odour exceedances to the EIAO-TM criterion of 5 OU are predicted at two existing representative ASRs, YAE01 and YAE02, and nearby village houses for a short duration of time during operation phase of the Project.  The frequency of exceedance in odour concentrations at ASRs within the exceedance zone is up to 0.51% of the time in a year.  During the time of exceedance, the proposed YLSEEP would contribute less than 0.45 OU/m3, while the major odour contribution would be from the retained existing chicken farm. Nonetheless, the Project will support the YLS DA and bring about a net improvement in cumulative odour impact for the YLS DA area.  Despite the predicted odour exceedance at some existing ASRs, the cumulative odour impacts at these ASRs will be substantially improved compared to that of existing condition without removal of the five livestock farms.  With the removal of the five livestock farms, an overall reduction in odour impacts at all the ASRs would be anticipated.

13.2.5.6       It is therefore concluded that there is no adverse residual odour impact arising from the Project.

Noise Impact

13.2.5.7       The assessment for the potential construction noise impact from construction of the proposed YLSEPP and its cumulative impact with concurrent projects have been conducted.  The assessment results indicate that the predicted construction noise levels of the Project at the NAPs would exceed the noise criteria without mitigation measures.  With mitigation measures in place, the predicted construction noise levels at all NAPs due to Project would comply with the noise criteria.  Thus, no adverse construction noise impact arising from the Project would be anticipated.  Based on best available information the cumulative construction noise levels at the NAPs would also comply with the noise criteria.  No adverse cumulative construction noise impact would be anticipated due to the Project and concurrent projects.

13.2.5.8       The fixed noise sources impact associated with the operation of the YLSEPP has been assessed based on the plant design information provided by the Project Engineer at the time of the assessment.  The assessment results indicate that the predicted fixed noise levels at the NAPs would comply with the noise criteria under unmitigated scenario.  No adverse fixed noise sources impact due to the operation of the YLSEPP would be anticipated.  Commissioning test should be conducted prior to operation of the Project to ensure that the fixed noise sources impact would comply with the relevant noise standards.

Water Quality Impact

13.2.5.9       Minor water quality impact would be associated with land-based construction works.  Water quality impact may result from wastewater generated from the general construction activities, construction site runoff, construction works near inland watercourses, sewage effluent from workforce and accidental chemical spillage.  The potential impact could be mitigated and controlled by implementing the recommended mitigation measures.  No adverse water quality impact from construction works for the YLSEPP is anticipated.  No adverse residual water quality impacts is expected.

13.2.5.10    Mathematical modelling was conducted under this EIA to study the water quality impacts caused by the effluent discharge from the proposed YLSEPP.  The model results indicated that the proposed YLSEPP would reduce the UIA, TP and E. coli levels in Deep Bay.  There would be an increase in BOD, TIN, TN and SS levels in Deep Bay due to the effluent discharge from the proposed YLSEPP.  The high levels of these parameters were mainly contributed from other background pollution sources which non-compliance for BOD, TIN and UIA were predicted even under the "without Project" scenario.  The water quality impact will be alleviated once the Water Reclamation Facilities is implemented.  The overall DO levels were predicted to be improved in inner Deep Bay.  The predicted change in salinity levels would comply well within the WQO of no more than 10% change from the background levels.

13.2.5.11       It should be noted that the proposed YLSEPP has already adopted tertiary treatment which is the highest treatment standard and the best effluent quality that could be achieved in HK’s sewage treatment.  Although the nutrient level in Deep Bay WCZ was very high and the water was static, it is anticipated that red tide occurrence in Deep Bay WCZ was limited by the presence of high SS level in the water column which could reduce the light penetration and limit the energy source for excessive algal growth.  Hence, nutrient (TIN, TN and TP) was not a critical factor for algal bloom in the Deep Bay waters.  Further effect on the red tide occurrence due to the slightly increase in TN (and TIN) level from the Project is not expected given that the existing Deep Bay waters has already contained abundant TN which is considered high enough to trigger red tide but the red tide occurrence in Deep Bay waters was limited by other environmental factors.  Furthermore, there will be a future water reclamation facility to further polish part of the treated effluent from YLSEPP into reclaimed water which will cut down the freshwater demand in the region, save the precious freshwater resources in the region and reduce the pollution loading discharge to the Deep Bay waters.  The residual impact on the water quality would be decrease as comparing with normal operation of YLSEPP (i.e. 65,000m3 discharge to Deep Bay).

13.2.5.12    For emergency discharge, the model results indicated that elevated levels of key water quality parameters would be recovered within 1 day after termination of the emergency discharge for WSRs within Inner Deep Bay.  The more distant WSR i.e. Oyster Culture Area was found not to be affected by emergency discharge event.  The occurrence of emergency discharge from the proposed YLSEPP can be minimised by the implementation of appropriate contingency measures, such as standby unit for all major equipment and back-up power for dual power supply would be provided for the proposed YLSEPP to prevent emergency situation as far as practicable.  An Emergency Response Plan will be formulated prior to commissioning of YLSEPP to minimize the impact of emergency discharges and facilitate subsequent management of the emergency. 

13.2.5.13    Other water quality impacts associated with the operation phase are identified as surface runoff from paved areas and accidental spillage.  It is expected that these potential impacts can be prevented by adopting recommended mitigation measures. 

Waste Management Implication

13.2.5.14    Waste management implications associated with the construction and operation of the Project were identified and assessed. Waste types generated by the construction activities of the Project would include C&D materials (from excavation and construction works for the proposed YLSEPP), general refuse (from construction workforce) and chemical waste (from maintenance of construction plant and equipment).  Provided that these wastes are handled, transported and reused/disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts during construction phase would not be anticipated.

13.2.5.15    Reduction measures have been recommended to minimise the amount of materials generated in the Project.  Approximately 268,100 m3 of inert materials and 20,900 m3 of non-inert materials would be generated during the construction phase of the Project.  52,900 m3 of inert material would be reused on site while the remaining 215,200 m3 of surplus C&D inert material would be recycled or transported to PFRFs for beneficial reuse in other projects.  Non-inert waste would be recycled as far as possible before disposed to landfill.  Opportunities in minimisation of generation and maximisation of reuse would be continually investigated during the detailed design and construction phases.  The other materials that cannot be reused or recycled would be disposed to designated outlets.

13.2.5.16    During operation, the main waste types to be generated would be grit and screenings, dewatered sludge, chemical waste and general refuse.  The grit and screenings would be compacted and properly stored in a covered container prior being disposed of at landfill on a daily basis.  The transportation and disposal of the grit and screenings would be managed and controlled by a reputable waste collector.  The dewatered sludge would be disposed of to the STF.  Provided proper handling procedures and disposal method are adopted, adverse environmental impacts would not be anticipated during the operation phase.

Land Contamination

13.2.5.17    A site appraisal, including the review of the YLS EIA Study, further desktop review and site walkover, was conducted from August 2020 to September 2021 to identify any potentially contaminating land uses within the proposed YLSEPP site.  Based on the site appraisal findings, 23 potentially contaminated sites are located within the proposed YLSEPP site.

13.2.5.18    Similar to the recommendation in the YLS EIA Study, as the potentially contaminated sites were inaccessible and still in operation, and there could be changes in site operation or changes in land use within the proposed YLSEPP site prior to development which may cause potential land contamination issues, site re-appraisal for the potentially contaminated sites within the proposed YLSEPP site should be conducted once site access is available (e.g. after land resumption) in order to identify the need for SI for any additional hotspots as a result of on-going land contaminating activities. In addition, re-appraisal would be required for the other remaining areas of the proposed YLSEPP site to assess the latest site situation in order to address any change in land use that may give rise to potential land contamination issues.  The further works including site re-appraisal for the whole proposed YLSEPP site, associated SI works, any necessary remediation works and submission of supplementary CAP / CAR / RAP / RR are recommended to be carried out when site access is available (e.g. after land resumption) but prior to commencement of any construction or development works at the identified contaminated sites, and would follow the relevant Guidance Manual, Guidance Note and Practice Guide.

13.2.5.19    With the implementation of the recommended further works for the Project, any soil / groundwater contamination would be identified and properly treated prior to the construction works.  No insurmountable land contamination impacts to the Project are therefore anticipated.

13.2.5.20    Ecological Impact (Terrestrial and Aquatic)

13.2.5.21    The Project site of YLS EPP is restricted within developed land which would be formed under a separate agreement of YLS DA prior to the commencement of construction works for this Project, and no encroachment into any sites of conservation importance is anticipated.  As such, no direct impact on natural habitats and sites of conservation importance is anticipated.  Similarly, no species of conservation importance or fauna of particular concern (i.e. ardeids, waterbirds, wetland-dependent birds and reedbed-associated birds) and their dependent habitats was recorded within the Project site, thus no direct impact is expected.  Species of conservation importance that recorded in close proximity of the Project site, such as Luofushan Joint-fir, Japanese Pipistrelle and Greater Coucal, are species that are more tolerant of human disturbance and are well-adapted and commonly found in or close to disturbed urban areas. Thus, indirect impact on these species is anticipated to be minor.

13.2.5.22    Though indirect impacts, in the form of construction disturbance and water quality reduction, are anticipated, the ecological impact from these indirect impacts is expected to be minor and low and no mitigation measures are required.  Precautionary measures and enhancement opportunities to further minimise any potential environmental impacts and to promote the ecological value of the Project are recommended.

13.2.5.23    Ecological monitoring is not required as no significant construction and operational phase ecological impacts impact are anticipated.

Landscape and Visual Impact

13.2.5.24    The Project will inevitably result in some landscape and visual impacts during construction and operation phases. These impacts have been minimized through incorporation of sensitive and aesthetic external designs of aboveground Structures and appropriate landscape and visual treatments within site.

13.2.5.25    With the implementation of the proposed preliminary mitigation measures, it is considered that the residual landscape and visual impact will be reduced to an acceptable level.

Hazard to Life

13.2.5.26    A quantitative hazard assessment was conducted to evaluate the biogas risk to existing, committed and planned off-site population due to operation of the organic wastes co-digestion facility at the proposed YLSEPP.  Both the individual and societal risk levels were found to meet relevant requirements stipulated in the HKRG, i.e. the off-site individual risk level is far below 1×10-5 per year and the societal risk falls into the “Acceptable” region.  No adverse impact is anticipated.  Nonetheless, implementation of good safety practices and recommended design measures are recommended.

13.3               Overall Conclusion

13.3.1.1       The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the construction and operation of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

13.3.1.2       Overall, the EIA Report has predicted that the Project would be environmentally acceptable with the implementation of the proposed mitigation measures for construction and operation phases.  An environmental monitoring and audit programme has been recommended to ensure the effectiveness of recommended mitigation measures.