TABLE OF CONTENTS
1.1.......... Project Background
1.2.......... Designated Projects under EIAO
1.3.......... Purpose of the EIA Study
1.4.......... Objectives of this EIA Study
1.5.......... Structure of the EIA Report
List of Figures |
|
Location
of Proposed Yuen Long South Effluent Polishing Plant (YLSEPP) |
List of Appendices |
|
·
Item F.1, Part I of Schedule 2
of the EIAO - Sewage treatment works with an installed capacity of more than
15,000 m3/day.
·
Item F.4, Part I of Schedule 2
of the EIAO - an activity for reuse of treated sewage effluent from a treatment
plant
·
the acceptability of potential
environmental consequences that are likely to arise as a result of the Project;
·
the conditions and requirements
for the design, construction and operation of the Project and related
activities to mitigate against potential environmental consequences; and
·
the acceptability of residual
impacts after the proposed mitigation measures are implemented.
(i)
to describe the Project and
associated works together with the requirements and environmental benefits for
carrying out the Project;
(ii)
to identify and describe
elements of community and environment likely to be affected by the Project
and/or likely to cause adverse impacts to the Project, including both the natural
and man-made environment and the associated environmental constraints;
(iii)
to identify and quantify
emission sources and determine the significance of impacts on sensitive
receivers and potential affected uses;
(iv)
to identify and quantify
contaminated land within any project area for development works, and to propose
measures to avoid disposal in the first instance;
(v)
to identify and quantify any
potential losses or damages to ecology, flora, fauna and natural habitats;
(vi)
to identify and evaluate any
potential landscape and visual impacts and to propose measures to mitigate these
impacts;
(vii) to identify any potential hazard to life due to generation, storage,
utilization, processing and transmission (if applicable) of biogas and other
dangerous goods (DGs) during the operation phase of the Project and to propose
measures to mitigate these impacts if required;
(viii) to propose the provision of infrastructure or mitigation measures so
as to minimize pollution, environmental disturbance and nuisance during
construction and operation of the Project;
(ix)
to investigate the feasibility,
effectiveness and implications of the proposed mitigation measures;
(x)
to identify, predict and
evaluate the residual (i.e. after practicable
mitigation) environmental impacts and the cumulative effects expected to arise
during the construction and operation phases of the Project in relation to the
sensitive receivers and potentially affected uses;
(xi)
to identify, assess and specify
methods, measures and standards, to be included in the detailed design,
construction and operation of the Project which are necessary to mitigate these
residual environmental impacts and cumulative effects and reduce them to
acceptable levels;
(xii) to design and specify environmental monitoring and audit
requirements and
(xiii) to identify any additional studies necessary to implement the mitigation
measures or monitoring and proposals recommended in the EIA report.
·
Section 3: Air Quality Impact
·
Section 4: Noise Impact
·
Section 5: Water Quality Impact
·
Section 6: Waste Management Implication
·
Section 7: Land Contamination
·
Section 8: Ecological Impact (Terrestrial
and Aquatic)
·
Section 9: Landscape and Visual
Impact
·
Section 10: Hazard to Life
·
Volume 1 of 3 – Main Text (This
booklet)
·
Volume 2 of 3 – Figures
·
Volume 3 of 3 – Appendices