TABLE OF CONTENTS

 

4............. Noise Impact. 4-1

4.1.......... Introduction. 4-1

4.2.......... Environmental Legislation, Standards and Criteria. 4-1

4.3.......... Description of Environment 4-5

4.4.......... Noise Sensitive Receivers. 4-5

4.5.......... Identification of Environmental Impacts. 4-7

4.6.......... Assessment Methodology. 4-8

4.7.......... Prediction and Evaluation of Environmental Impacts. 4-10

4.8.......... Mitigation of Adverse Environmental Impacts. 4-11

4.9.......... Evaluation of Residual Impacts. 4-13

4.10........ Environmental Monitoring and Audit 4-13

4.11........ Conclusion. 4-13

 

List of Tables

 

Table 4.1                   Area Sensitivity Ratings (ASRs)

Table 4.2                   Noise Criteria for Construction Noise during Non-Restricted Hours

Table 4.3                   Acceptable Noise Levels under GW-TM

Table 4.4                   Acceptable Noise Levels for Fixed Noise

Table 4.5                   Summary of Prevailing Background Noise Measurement Results

Table 4.6                   Identified Noise Sensitive Receivers in the Vicinity of Proposed YLSEPP

Table 4.7                   Identified Noise Assessment Points in the Vicinity of Proposed YLSEPP for Construction Noise Impact Assessment

Table 4.8                   Identified Noise Assessment Points in the Vicinity of Proposed YLSEPP for Operational Noise Impact Assessment

Table 4.9                   Noise Criteria for Fixed Noise Sources Impact Assessment

Table 4.10                 Potential Concurrent Projects

Table 4.11                 Predicted Construction Noise Levels at Representative Noise Assessment Points under Unmitigated Scenario

Table 4.12                 Predicted Fixed Noise Levels under Unmitigated Scenario

Table 4.13                 Recommended Construction Noise Mitigation Measures

Table 4.14                 Predicted Construction Noise Levels at Representative Noise Sensitive Receivers under Mitigated Scenario

 

 

List of Figures

Figure 4.1

Locations of Noise Sensitive Receivers and Noise Assessment Points (YLSEPP)

 

List of Appendices

Appendix 4.1

Background Noise Survey

Appendix 4.2

Photographs of Existing Representative Noise Sensitive Receivers

Appendix 4.3

Construction Programme

Appendix 4.4

Construction Plant Inventory (Unmitigated)

Appendix 4.5

Construction Noise Calculation (Unmitigated)

Appendix 4.6

Operation Phase Fixed Noise Calculation (Unmitigated)

Appendix 4.7

Construction Plant Inventory (Mitigated)

Appendix 4.8

Construction Noise Calculation (Mitigated)

 

 


4                    Noise Impact

4.1                Introduction

4.1.1.1         This section presents an assessment of potential noise impacts associated with the construction and operation of the Project.  The noise impact assessment has been conducted in accordance with the requirements of Annex 5 and Annex 13 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the requirements set out under Clause 3.4.5 of the Environmental Impact Assessment (EIA) Study Brief (No. ESB-313/2019) (hereinafter “the Study Brief”).

4.2                Environmental Legislation, Standards and Criteria

4.2.1            General

4.2.1.1         Noise impact has been assessed in accordance with the criteria and methodology given in the EIAO-TM and the Technical Memoranda (TM) under the Noise Control Ordinance (NCO).

4.2.1.2         The NCO provides the statutory framework for noise control.  This defines statutory limits applicable to equipment used during the construction and operation phases of the Project.  The NCO invokes four Technical Memoranda, which define the technical means for noise assessment:

(i)         Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM);

(ii)        Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM);

(iii)       Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and

(iv)       Technical Memorandum on Noise from Percussive Piling (PP-TM).

4.2.1.3         With regard to the assessments of the construction noise impact during restricted hours (on all days during 1900 and 0700 hours and at any time on Sundays and public holidays) and operational fixed noise sources impact, the NCO designates acceptable noise levels for Noise Sensitive Receivers (NSRs) on the basis of an Area Sensitivity Rating (ASR), based on the type of area containing the NSR (see Table 4.1).  Within these areas, the presence of "influencing factors" (such as the presence of industrial area or major roads) can further affect the ASR and hence the acceptable noise levels.

Table 4.1     Area Sensitivity Ratings (ASRs)

Type of Area Containing NSR

Degree to which NSR is affected by Influencing Factor

Not Affected

Indirectly Affected

Directly Affected

Rural area, including country parks or village type developments

A

B

B

Low density residential area consisting of low-rise or isolated high-rise developments

A

B

C

Urban area

B

C

C

Area other than those above

B

B

C

Notes:

·         “country park” means an area that is designated as a country park pursuant to section 14 of the Country Parks Ordinance;

·         “directly affected" means that the NSR is at such a location that noise generated by the IF is readily noticeable at the NSR and is a dominant feature of the noise climate of the NSR;

·         "indirectly affected" means that the NSR is at such a location that noise generated by the IF, whilst noticeable at the NSR, is not a dominant feature of the noise climate of the NSR;

·         "not affected" means that the NSR is at such a location that noise generated by the IF is not noticeable at the NSR; and

·         "urban area" means an area of high density, diverse development including a mixture of such elements as industrial activities, major trade or commercial activities and residential premises.

4.2.2            Construction Noise

Construction Works during Non-restricted Hours

4.2.2.1         The NCO provides the statutory framework for control of noise from construction works, other than percussive piling, using powered mechanical equipment (PME) between the hours of 1900 and 0700 hours or at any time on Sundays and general holiday (i.e. restricted hours).  Noise from construction activities taking place at 0700 – 1900 hours on any day not being a Sunday or general holiday is subject to the Noise Standards for Daytime Construction Activities in Table 1B of Annex 5 in the EIAO-TM.  The criteria are summarised in Table 4.2.

Table 4.2       Noise Criteria for Construction Noise during Non-Restricted Hours

Uses

Noise Criteria for Construction Noise during
Non-Restricted Hours, Leq (30mins), dB(A)

Domestic premises

75

Educational Institution

70

Educational Institution (during examination)

65

Notes:

·         Non-restricted hours are 0700 to1900 hours on any day not being a Sunday or general holiday.

·         The above standards apply to uses which rely on opened windows for ventilation.

·         The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external façade.

 

Construction Works during Restricted Hours

4.2.2.2         During restricted hours (i.e. on all days during 1900 and 0700 hours and at any time on Sundays and general holidays), the use of PME for the purpose of carrying out construction works is prohibited unless a Construction Noise Permit (CNP) has been obtained.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) for the NSRs.   ANLs are assigned depending upon the ASRs.  The corresponding ANLs for construction work other than percussive piling during restricted hours are given in Table 4.3.

Table 4.3     Acceptable Noise Levels under GW-TM

Time Period

Acceptable Noise Levels (ANLs), dB(A)

ASR A

ASR B

ASR C

All days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the daytime and evening (0700 to 2300 hours)

60

65

70

All days during the night-time (2300 to 0700 hours)

45

50

55

 

4.2.2.3         The Noise Control Authority will consider a well-justified CNP application, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance.  The Noise Control Authority will take into account of contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in this EIA shall bind the Noise Control Authority in making his decision.  If a CNP is to be issued, the Noise Control Authority shall include in it any condition he thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

4.2.2.4         Under the DA-TM, the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours would require a valid CNP.  The SPME includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker.  The PCW are:

·         Erecting or dismantling of formwork or scaffolding.

·         Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material.

·         Hammering.

4.2.2.5         In general, it should not be presumed that a CNP would be granted for carrying out PCW within a designated area during restricted hours.  The CNP may be granted for the execution of construction works during restricted hours involving the use of PME and/ or SPME if the relevant Acceptable Noise Levels and criteria stipulated in the GW-TM and DA-TM can be met.  These noise level requirements are more stringent (i.e. 15 dB(A) less than those listed in the GW-TM) to offer additional protection to the population.

4.2.2.6         Percussive piling is prohibited between 1900 and 0700 hours on any weekday not being a general holiday and at any time on Sunday or general holiday.  A CNP is required for the carrying out of percussive piling between 0700 and 1900 hours on any day not being a general holiday.  PP-TM sets out the requirements for working and determination of the permitted hours of operations for the CNP applications.  The permitted hours of operations would be 3, 6 or 12 hours per day depending on the types of percussive piling and the predicted noise impact at NSRs.

4.2.3            Operational Phase Fixed Noise

4.2.3.1         Fixed noise sources impact are controlled by the NCO and IND-TM.  The ANLs for the NSRs are determined based on the ASR as stated in Table 4.1.  The ANLs for different ASRs during different periods are summarised in Table 4.4 below.

Table 4.4     Acceptable Noise Levels for Fixed Noise

Time Period

ANL, dB(A)

ASR A

ASR B

ASR C

Day (0700 to 1900 hours)

60

65

70

Evening (1900 to 2300 hours)

60

65

70

Night (2300 to 0700 hours)

50

55

60

 

4.2.3.2         According to the Revised Recommended Outline Development Plan (RODP) of Planning and Engineering Study for Housing Sites in Yuen Long South (YLS DA), YLSEPP is located at the southern tip of YLS DA.  It is bound by Ma Shan (Kung Um Shan) and Tai Lam Country Park at its south west. There will be a planned reedbed and green belt to its north, and planned government and institutional land use to its east side.  YLS DA will be developed as a new town with a mixture of land uses, which comprised of medium to high-rise residential developments, schools and governmental reserve, etc.  The ASR of the type of area within the NSR located has been determined for assessment purpose.  When determining the ASR for an NSR, the following are considered:

·         The type of area containing the NSR;

·         The Influencing Factor (IF) identified;

·         The Degree to which the NSR is affected by IF; and

·         If applicable, nearby OZP “Industrial” or “Industrial Estates” zone.

4.2.3.3         There are two existing residential NSRs identified within the 300m assessment area.  The identified NSRs are located to the east of the proposed YLSEPP.  These NSRs are 1-storey to 3-storey high village houses.  They are located in rural area and are not affected by any influence factor, an ASR of “A” has been assigned.  The planned NSRs are medium-rise residential developments and schools located within the YLS DA.  Thus, they are considered to be located in an area other than rural, urban or low density residential area and they are not affected by any influence factor, an ASR of “B” has been assigned.

4.2.3.4         As stipulated in Annex 5 of the EIAO-TM, the noise standard for planning purpose for fixed noise source are (a) 5dB(A) below the appropriate ANL shown in Table 2 of the IND-TM or (b) the prevailing background noise levels (for quiet area with level 5dB(A) below the ANL).  In this regard, noise measurement was undertaken in the vicinity of the representative NSRs, which having similar typical background noise environment of the identified, to study the prevailing background noise level.  The noise measurement results are presented in Appendix 4.1.  The lesser of the lowest background noise levels has been compared with the 5dB(A) below the appropriate ANL to obtain the fixed noise criteria, which listed in below Table 4.5.

Table 4.5     Summary of Prevailing Background Noise Measurement Results

Noise Assessment Point

Measurement Location ID

Lowest

Measured Noise Level,

 LA90 30-min, dB(A)(1)

ID

Description

Day (2)

Evening (3)

Night (4)

YE03

121 Wong Nai Tun Tsuen

PSSR

49

49

47

YE04

125 Wong Nai Tun Tsuen

YP01

Planned Residential Development (R3.1e)

YP02

Planned Residential Development (R3.4b)

YP03

Planned Education Development (E3.3)

YP04

Planned Education Development (E3.1)

YP05

Planned Low-rise Residential Development (VR3.1)

Note:

(1)        Façade corrections of 3 dB(A) have been added for free-field measurements of the NSRs

(2)        Daytime means 07:00 – 19:00.

(3)        Evening time means 19:00 – 23:00.

(4)        Night-time means 23:00 – 07:00 of the next day.

 

4.2.3.5         In any event, the ASR assumed in the EIA Report is for indicative assessment only.  It should be noted that the fixed noise sources are controlled under Section 13 of the NCO.  At the time of investigation, the Noise Control Authority shall determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force and taking account of contemporary conditions/situations of adjoining land uses.  Nothing in the EIA Report shall bind the Noise Control Authority in the context of law enforcement against all the fixed noise sources being assessed.

4.3                Description of Environment

4.3.1.1         The YLSEPP is located at the southern tip of YLS DA.  It is bound by Ma Shan (Kung Um Shan) and Tai Lam Country Park at its south west. There will be a planned reedbed and green belt to its north, and planned government and institutional land use to its east side.

4.3.1.2         The YLS DA is generally rural in character with a mixture of land uses. The predominant uses are brownfield operations including open storage yards, warehouses, industrial workshops, etc. These brownfield operations are intermingled with rural settlements and residential settlements, agricultural land, livestock farms and vacant land.  The prevailing noise climate of the assessment area is dominated by the brownfield operations.

4.4                Noise Sensitive Receivers

4.4.1.1         In accordance with Annex 13 of the EIAO-TM, domestic premises including temporary housing, educational institutions (including kindergartens and nurseries), hospitals, medical clinics, homes for the aged, convalescent homes, places of public worship, libraries, courts of law, performing arts centres, auditoria and amphitheatres, and Country Park are noise sensitive receivers (NSRs).

4.4.1.2         The assessment area for noise impact assessment is defined by a distance of 300m from the Project boundary as specified in the Study Brief.  The NSRs within the assessment area for the construction and operation noise impact assessments have been identified based on the finding of the site visits and review of latest information from Planning Department, and Lands Department as well as the statutory Outline Zoning Plan (OZP) gazetted under Town Planning Ordinance including OZP Plan No. S/YL-TT/18 – Tai Tong and Plan No. S/YL-TYST/14 – Tong Yan San Tsuen, Revised Recommended Outline Development Plan (RODP) for YLS DA and other published plans in the vicinity of the Project site.  The identified NSRs in the vicinity of the Proposed YLSEPP are listed in Table 4.6. Locations of these NSRs are presented in Figure 4.1.

Table 4.6     Identified Noise Sensitive Receivers in the Vicinity of Proposed YLSEPP

NSR ID

Description

Land Use

Existing / Planned

PST

Pak Sha Tsuen

Residential

Existing

WNTT

Wong Nai Tun Tsuen

Residential

Existing

YLSDA

Yuen Long South Development Area

Residential

Planned

TLCP

Tai Lam Country Park

Country Park

Existing

 

4.4.1.3         The first layer of NSRs located close to the subject noise sources are considered as the most affected location and would provide acoustic shielding to those receivers at further distance behind.  The first layer of NSRs represent the worst-case scenario and are selected as representative noise assessment points (NAPs) for the noise assessment.  In accordance with Annex 13 of the EIAO-TM, country park is also classified as NSRs.  However, there would be no noise sensitive uses in Tai Lam Country Park that rely on opened windows for ventilation.  Therefore, noise criteria listed in Annex 5 of EIAO-TM is not applicable to Tai Lam Country Park.  The EIAO-TM however does not stipulate specific noise limits for this type of NSRs.  Given that visitors using hiking trails in the Tai Lam Country Park are of transient nature, no adverse construction noise impact is anticipated. The identified existing and planned representative NAPs within 300m assessment area for construction phase and operation phase are presented in Table 4.7 and Table 4.8 respectively.  Locations of the representative NAPs are shown in Figure 4.1.  Photographs of the existing NSRs are provided in Appendix 4.2.

Table 4.7     Identified Noise Assessment Points in the Vicinity of Proposed YLSEPP for Construction Noise Impact Assessment

NAP ID

Description

Land Use

No. of Storeys

Shortest Distance from Project Site Boundary (m)

Existing / Planned

YE01*

291 Pak Sha Tsuen

Residential

3

50

Existing

YE02*

Pui Hong Kui

Residential

3

120

Existing

YE03

121 Wong Nai Tun Tsuen

Residential

3

250

Existing

YE04

125 Wong Nai Tun Tsuen

Residential

3

250

Existing

Note:

*  This NAP would be demolished no later than 2029 under YLSDA Stage 3 in accordance with its latest programme.

 

Table 4.8     Identified Noise Assessment Points in the Vicinity of Proposed YLSEPP for Operational Noise Impact Assessment

NAP ID

Description

Land Use

No. of Storeys

Shortest Distance from Project Site Boundary (m)

Existing / Planned

YE03

121 Wong Nai Tun Tsuen

Residential

3

250

Existing

YE04

125 Wong Nai Tun Tsuen

Residential

3

250

Existing

YP01

YLS DA - Planned Residential Development (R3.1e)

Residential

11

270

Planned

YP02

YLS DA - Planned Residential Development (R3.4b)

Residential

14

270

Planned

YP03

YLS DA - Planned Education Development (E3.3)

Educational

8

270

Planned

YP04

YLS DA - Planned Education Development (E3.1)

Educational

8

260

Planned

YP05

YLS DA - Planned Low-rise Residential Development (VR3.1)

Residential

3

190

Planned

 

4.4.1.4         Based on the ANLs presented in Table 4.4 and the background noise measurement results as summarized in Table 4.5, the fixed plant noise criteria of the representative NSRs have been determined and are presented in Table 4.9.

Table 4.9     Noise Criteria for Fixed Noise Sources Impact Assessment

NAP ID

ANL – 5,

 dB(A)

Measured Lowest Prevailing Background Noise Level (1),

LA90 30-min, dB(A)

Noise Criteria, dB(A)

Day (2)

Evening (3)

Night (4)

Day (2)

Evening (3)

Night (4)

Day (2)

Evening (3)

Night (4)

YE03

55

55

45

49

49

47

49

49

45

YE04

55

55

45

49

49

47

49

49

45

YP01

60

60

50

49

49

47

49

49

47

YP02

60

60

50

49

49

47

49

49

47

YP03

60

60

50

49

49

47

49

49

47

YP04

60

60

50

49

49

47

49

49

47

YP05

60

60

50

49

49

47

49

49

47

Notes:

(1)        Façade correction of +3 dB(A) has been added to the measurement results for free-field measurement.

(2)        Daytime means 07:00 – 19:00.

(3)        Evening time means 19:00 – 23:00.

(4)        Night-time means 23:00 – 07:00 of the next day.

 

4.5                Identification of Environmental Impacts

4.5.1            Construction Phase

4.5.1.1         The Project is to construct a sewage treatment works and effluent discharge pipe for the purpose of emergency discharge.  The construction of the Project would commence in early 2028 with completion of the Project by 2032, the construction period would be around 5 years.  Potential source of noise impact during construction phase of the Project would be expected from the use of power mechanical equipment (PME) during the following construction activities of the Project such as foundation works, superstructure works and E&M equipment installation, etc.  The site formation for the proposed YLSEPP will be undertaken by CEDD under Agreement No. CE 35/2012 (CE) “Planning and Engineering Study for Housing Sites in Yuen Long South – Investigation”.  The major construction works of the Project would only include superstructure works for the YLSEPP and a short section of effluent discharge pipe connecting to the Yuen Long Nullah.  Details of the proposed construction methods and sequence of works are described in Section 2 of this EIA Report.

4.5.1.2         As described in Section 2 of this EIA Report, the foundation options are highly dependent on the ground conditions.  Since the proposed boundary of YLSEPP is currently located within private land lots with numerous existing private structures, the area assessable for ground investigation works is limited. As such, the technical feasibility of different foundation options should be further reviewed at a later project stage when more ground information can be gathered.  Should the percussive pilling construction method to be used for the Project, a CNP, as mentioned in Section 4.2.3.5, will be applied during construction phase of the Project.

4.5.1.3         The construction programme at the time of assessment does not require any construction activities using PME undertaken during restricted hours (i.e. on all days during 1900 and 0700 hours and at any time on Sundays and public holidays).  Therefore, only noise impact from general construction activities during the non-restricted hours have been assessed in this EIA Report.

4.5.1.4         Based on the current construction programme, the Project would likely interactions with some other projects, which may have cumulative environmental impacts.  Table 4.10 summarise the concurrent projects located within 300m from the Project boundary that would contribute to the cumulative environmental impacts during construction phase.

Table 4.10   Potential Concurrent Projects

Potential Concurrent Projects

Tentative Construction Commencement Year

Tentative Commissioning Year

Water Reclamation Facilities

Under YLS DA Stage 2 Works.

The construction programme is yet to be confirmed

YLS DA Stage 2 works

2022

2033

(Full population intake)

YLS DA Stage 3 works

2031

2038

(Target intake year)

Remarks:

-       YLS DA Stage 1 works are located more than 1km from the YLSEPP.  No construction phase cumulative impact would be anticipated.

-       With reference to Appendices 5.4 and 5.12 of YLS DA EIA, only land resumption and minor construction works such as site clearance would be conducted in Year 2022 – Jun 2023 and Year 2031 – Jun 2033 for YLS DA Stage 2 works and YLS DA Stage 3 works, respectively.  Site formation construction works for YLS DA phases 3 will begin no earlier than Jul 2033.  No adverse construction phase cumulative impact would be anticipated.

4.5.1.5         According to the approved EIA Study “Agreement No. CE 35/2012 (CE) Planning and Engineering Study for Housing Sites in Yuen Long South – Investigation”, which is the best available information for the YLS DA project.  YLS DA Stage 2 works will tentatively be commenced in 2022 and completed in 2033. YLS DA Stage 3 works will tentatively be commenced in 2031, while the intake year will be targeted to be 2038. However, according to YLS DA EIA, only land resumption and minor construction works would be anticipated during 2031 – Jun 2033 for YLS DA Stage 3, while site formation construction activity will begin no earlier than Jul 2033.  Hence, no adverse cumulative construction phase noise impact would be anticipated from YLS DA Stage 3 works during construction of the YLSEPP.  The potential construction noise impact arising from the YLS DA, cumulative impact associated with the construction of YLSEPP and Water Reclamation Facilities were identified and assessed in the EIA Study for YLS DA.  In view of the latest RODP for YLS DA, the planned NSRs at YLS DA Stage 2 located within the defined noise assessment area will be occupied in 2033. The construction noise impacts from the planned rising mains and planned reclaimed water pipe within the 300m assessment area will not be addressed under this study as no detailed information can be provided to carry out cumulative construction noise impact.

4.5.2            Operation Phase

4.5.2.1         Potential fixed noise sources impact during operation of the proposed YLSEPP would be generated from the operation of the fixed plants, such as pumps, air blowers, motors, ventilation fans and extraction fans of deodourisation units, etc. at the proposed treatment facilities.  The details of fixed plant inventory for proposed YLSEPP are provided by project engineer and agreed by DSD and presented in Appendix 4.6.  The pumps, air blowers and motors would be located within reinforced concrete buildings, while ventilation fans would be provided at the ventilation vents of these buildings.  No fixed noise source is associated with the effluent discharge pipe as effluent is discharged into Yuen Long Nullah by gravity. There is no information regarding proposed planned water reclamation facilities nearby, thus cumulative noise will not be assessed.  The Project proponent advised the proposed YLEPP will be operated 24 hours per day, 7 days per week throughout the year.  Thus, the daytime, evening time and night-time operational fixed noise sources impact have been assessed.

4.6                Assessment Methodology

4.6.1            Construction Phase

4.6.1.1         The construction noise impact assessment was undertaken based on standard acoustic principles and followed the procedures given in the GW-TM.  The sound pressure level of each construction task has been calculated, depending on the number of plant items and the distance from NSR.  The general approach is summarized below:

·                Locate the NSRs which would most likely be affected by noise from the construction work;

·                Determine the items of PME for each discrete construction activity, based on available information or agreed plant inventories;

·                Assign sound power levels (SWLs) to the proposed PME according to the GW-TMs;

·                Calculate distance attenuation due to the notional separation distance between the noise source and the NSR;

·                Apply correction due to screening effects to NSRs from the noise source; and

·                Predict construction noise levels at NSRs in the absence of any mitigation measures. 

4.6.1.2         The construction programme and the plant inventory (including type and quantity of the PME used as well as percentage on time utilization) respectively presented in Appendices 4.3 and 4.4 are confirmed by Project Engineer to be practical and suitable for completing the proposed works within the proposed construction programme.  Based on the construction programme, the plant inventory and the sound power level (SWL) of equipment in Table 3 of GW-TM, the SWL of each construction activities has been calculated, based on the type and quantity of the PME used as well as percentage on time utilization.

4.6.1.3         To calculate the sound pressure level of each construction activities, distance attenuation correction has been applied.  The distance attenuation was determined by using the following formula:

Distance Attenuation in dB(A) = 20 log D + 8

where D is distance between PME and NSR in metres

4.6.1.4         The following assumptions have been applied as well:

(i)         A +3 dB(A) façade correction was added to the predicted noise levels to account for the facade effect at each identified representative NSR;

(ii)        All PME items required for a particular construction activity was assumed to be located at the notional source position of the workfront where such activity is to be performed in accordance with the GW-TM;

(iii)       As a worst-case assumption, noise impact at the nearest sensitive facades of the residential buildings to the source positions was assessed; and

(iv)       As a worst-case assumption, noise assessment points of all NSRs were assumed at the same height as the Project Site, i.e. G/F of all NSRs.

4.6.1.5         In accordance with the construction programme (Appendix 4.3) at the time of the assessment, no construction activities with PME operation would be undertaken in the restricted hours.  The predicted construction noise impact would be compared with the noise standards mentioned in Section 4.2.2.1.

4.6.1.6         If exceedance of relevant noise standards is predicted, practicable direct noise mitigation measures including the use of quieter equipment, movable noise barriers, noise barriers, enclosures and quieter alternative methods would be considered.  Appropriate correction factors for barrier effect would be adopted in accordance with Section 2.10 of the GW-TM.  In cases where the mitigated noise levels still exceed the relevant criteria, the duration of noise exceedance would be estimated.

4.6.2            Operation Phase

4.6.2.1         The fixed plant noise impact assessment was undertaken based on standard acoustic principles and followed the procedures given in the IND-TM.  The following standard acoustic formula was used for calculating the sound pressure levels at the representative NAP.

SPL = SWL – DC + FC – BC

 

Where:

SPL      Sound Pressure Level at NAP, in dB(A)

SWL     Sound Power Level of the PME, in dB(A)

DC       Distance Attenuation, in dB(A) (i.e. 20logD + 8 [where D is the distance in metres])

FC        Façade Correction, in dB(A) (i.e. 3 dB(A))

BC       Barrier Correction, in dB(A)

 

4.6.2.2         The SWL of the fixed plants were referenced to EPD’s Good Practices on Ventilation System Noise Control, approved EIA reports, namely EIA report of Expansion of Sha Tau Kok Sewage Treatment Works (EIA-245/2016), EIA report of Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008), EIA report of Upgrading and expansion of San Wai Sewage Treatment Works, EIA report of Yuen Long Effluent Polishing Plant (EIA-259/2018), product catalogue and engineering design information. The SWL of CHP gas engine will be specified in contract to be followed by future contractor.

4.6.2.3         The fixed noise plant inventory (Appendix 4.6) for the assessment have been confirmed by Project proponent.

4.6.2.4         It was assumed that all the fixed plant within the same location would be operated simultaneously at any time of the day for the worst-case scenario.  With reference to EPD’s Good Practices on Pumping System Noise Control, a noise reduction of more than 20 dB(A) could be provided by complete enclosures constructed by compressed strawboard (56mm thick) or plastered brick wall (125mm thick).  As a conservative assumption in the assessment, noise reduction of 20 dB(A) was applied for fixed plants fully enclosed by plastered brick wall (125mm thick and surface density of 240 kg/m2).  A 10 dB(A) noise reduction acoustic louvre would be provided for ventilation fans.  A positive 3 dB(A) was added to the predicted noise levels at the NAP due to the façade effect. 

4.6.2.5         With reference to EPD’s Good Practices on Pumping System Noise Control and Good Practices on Ventilation System Noise Control, a positive 3 dB(A) for correction of tonality has been considered in the assessment.

4.6.2.6         The predicted noise levels at the representative NAPs were compared with criteria set out in Table 4.9 above. Mitigation measures have been recommended in cases where an exceedance is predicted. 

4.7                Prediction and Evaluation of Environmental Impacts

4.7.1            Construction Phase

4.7.1.1         Potential noise impacts from construction of the proposed YLSEPP during non-restricted hours have been assessed at the representative NAPs based on the construction programme as shown in Appendix 4.3 and the construction plant inventory presented in Appendix 4.4.  The unmitigated noise assessment results are summarised in Table 4.7.  Details of the construction unmitigated noise assessment are presented in Appendix 4.5.

Table 4.11   Predicted Construction Noise Levels at Representative Noise Assessment Points under Unmitigated Scenario

NAP ID

Noise Criteria,

Leq 30-min, dB(A)

Predicted Construction Noise Level due to Construction of YLSEPP, Leq 30-min, dB(A)

Predicted Cumulative Construction Noise Level,

Leq 30-min, dB(A)

YE01

75

78 - 81

79 - 82

YE02

75

72 - 77

76 - 79

YE03

75

61 - 73

67 - 74

YE04

75

61 - 73

65 - 73

Note:

·         Boldfaced values indicate exceedance of noise criteria.

 

4.7.1.2         Referring to Table 4.11, in the absence of noise mitigation measures, non-compliance of the construction noise criterion would be predicted at the representative NAPs YE01 and YE02.  Hence, direct mitigation measures would be required to alleviate the potential construction noise impact on the affected NSRs during construction.

4.7.2            Operation Phase

4.7.2.1         Referring to the latest design, the sound power levels of the fixed plants under the worst-case scenario in the fixed noise sources impact assessment are presented in Appendix 4.6.  Details of the fixed noise calculation are also presented in Appendix 4.6.  A summary of the fixed noise sources impact assessment results at the representative NAPs during the operation phase of the Project is shown in Table 4.12.  The predicted fixed noise levels at the NAPs would comply with the respective noise criteria.  No adverse fixed noise impact would be anticipated. Therefore, there is no dwelling, classroom or other NSR that will be exposed to fixed noise impact exceeding criteria set out in Annex 5 of EIAO-TM.

Table 4.12      Predicted Fixed Noise Levels under Unmitigated Scenario

NAP ID

Noise Criteria,

Leq 30-min, dB(A)

Predicted Fixed Noise Level,

Leq 30-min, dB(A)

Day (1)

Evening (2)

Night (3)

YE03

49

49

45

43

YE04

49

49

45

43

YP01

49

49

47

41

YP02

49

49

47

42

YP03

49

49

47

42

YP04

49

49

47

42

YP05

49

49

47

44

Notes:

(1)        Daytime means 07:00 – 19:00.

(2)        Evening time means 19:00 – 23:00.

(3)        Night-time means 23:00 – 07:00 of the next day.

(4)        Boldfaced indicates exceedance to night-time criterion.

 

4.8                Mitigation of Adverse Environmental Impacts

4.8.1            Construction Phase

4.8.1.1         Due to the predicted exceedance of the construction noise criteria under unmitigated scenario, noise mitigation measures are recommended as follow.  Construction noise mitigation measures are recommended as in Table 4.13.  These recommended construction noise mitigation measures should be included in the Contract Specification for the Contractors to follow and implement the relevant measures to further minimize the potential noise impacts during the construction phase of the Project.

Table 4.13   Recommended Construction Noise Mitigation Measures

Recommended Mitigation Measures

Construction Plant

Noise Reduction,

Leq 30 min dB(A)

Temporary movable noise barrier

Excavator, Mobile crane, Dump truck, Grout mixer and Grout pump

5

Noise insulating fabric

Drilling rig and Piling machine

10

Ventilated acoustic enclosure

Generator

15

Quiet PME

Excavator (1) and Mobile crane (2)

Refer to Appendix 4.7

Notes:

(1)         KOBELCO SK125SR (EPD-11011) referenced from the QPME system published by EPD is recommended as a quiet PME for excavator.

(2)         Kobelco CKS900 (EPD- 09602) referenced from the QPME system published by EPD is recommended as a quiet PME for mobile crane.

 

4.8.1.2         Temporary movable noise barriers should be made of materials with density of at least 10 kg/m2 to provide sufficient noise reduction.  No sound leaks should be allowed through the barriers due to holes, slits, cracks, openings or gaps.  Noise barriers will become more effective when located immediately adjacent to the work area and can reduce the noise level by up to 5dB(A) and 10dB(A) for mobile and stationary plant respectively. With reference to GW-TM, noise attenuation of 5 dB(A) is applied when this type of PME would be screened from NSR’s view. 

4.8.1.3         Noise insulating fabric of at least 10 dB(A) reduction should be used to alleviate noise emission from the respective plant.  The fabric should be lapped such that there would be no opening or gaps on the joints. Hence, the noise reduction effect from the fabric could be maximised.

4.8.1.4         Enclosing generator by a ventilated acoustic enclosure can provide a noise reduction of up to 20 dB(A) with reference to Table B.1 of BS 5228-1:2009+A1:2014 Code of Practice for Noise and Vibration Control on Construction and Open Sites – Part 1: Noise.  As a conservative assumption, 15 dB(A) reduction is assumed for this assessment.

4.8.1.5         Quiet PME labelled under EPD’s Quality Powered Mechanical Equipment (QPME) System should be considered as far as practicable to reduce the potential noise emission from PME.  In particular, quiet PME for excavator and mobile crane should be used as referenced in Appendix 4.7 to ensure the noise performance of the PME.

4.8.1.6         The construction plant inventory for the assessment of mitigated scenario is presented in Appendix 4.7.  The details of construction noise impact assessment under mitigated scenario are presented in Appendix 4.8 and the mitigated noise levels at NAPs are summarized in below Table 4.13.  With the implementation of the above proposed mitigation measure, the predicted mitigated construction noise levels at the NAPs would comply with relevant noise criteria.  No adverse construction noise impact would be anticipated.  No further noise mitigation measures would be required.

Table 4.14   Predicted Construction Noise Levels at Representative Noise Sensitive Receivers under Mitigated Scenario

NAP ID

Noise Criteria,

Leq 30-min, dB(A)

Predicted Construction Noise Level due to Construction of YLSEPP, Leq 30-min, dB(A)

Predicted Cumulative Construction Noise Level,

Leq 30-min, dB(A)

YE01

75

64 - 71

74 - 75

YE02

75

58 - 67

74 - 75

YE03

75

53 - 68

66 - 70

YE04

75

53 - 68

63 - 69

 

4.8.1.7         In addition to the above construction noise mitigation measures, good site practices listed below and the noise control requirements stated in EPD’s “Recommended Pollution Control Clauses for Construction Contracts” should be included in the Contract Specification for the Contractors to follow and implement the relevant measures to further minimize the potential noise impacts during the construction phase of the Project.

·         Quiet PME, such that those listed in EPD’s Quality Powered Mechanical Equipment, should be considered for construction works to further minimize the potential construction noise impact.

·         Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme.

·         Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction programme.

·         Mobile plant, if any, should be sited as far away from NSRs as possible.

·         Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

·         Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs

·         Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

4.8.1.8         A construction noise management plan, which to verify the inventory of noise sources, and to assess the effectiveness and practicality of all identified measures for mitigating the construction noise impact of the project, would be prepared and submitted to EPD 3 months prior to the commencement of the construction works.

4.8.2            Operation Phase

4.8.2.1         No adverse fixed noise sources impact would be anticipated during operation of the Project.

4.9                Evaluation of Residual Impacts

4.9.1            Construction Noise

4.9.1.1         No residual noise impact due to the construction of the Project is anticipated.

4.9.2            Operational Fixed Plant Noise

4.9.2.1         No residual fixed plant noise impact due to the operation of the Project is anticipated.

4.10              Environmental Monitoring and Audit

4.10.1          Construction Noise

4.10.1.1      With the implementation of the above proposed mitigation measures, residual construction noise impact would not be anticipated.  An Environmental Monitoring and Audit (EM&A) programme is recommended to ensure the proper implementation of the proposed mitigation measures and good site practices, and take remedial measures when non-compliance is recorded.

4.10.2          Operational Fixed Noise

4.10.2.1      No adverse fixed noise sources impact is anticipated during the operation of the YLSEPP.  Commissioning test should be conducted prior to operation of the Project to ensure fixed noise sources impact would comply with the relevant noise standards.  No operation noise monitoring is therefore deemed necessary.

4.11              Conclusion

4.11.1          Construction Phase

4.11.1.1      The assessment for the potential construction noise impact from construction of the proposed YLSEPP and its cumulative impact with concurrent projects have been conducted.  The assessment results indicate that the predicted construction noise levels of the Project at the NAPs would exceed the noise criteria without mitigation measures.  With mitigation measures in place, the predicted construction noise levels at all NAPs due to Project would comply with the noise criteria.  Thus, no adverse construction noise impact arising from the Project would be anticipated.  Based on best available information the cumulative construction noise levels at the NAPs would also comply with the noise criteria.  No adverse cumulative construction noise impact would be anticipated due to the Project and concurrent projects.

4.11.2          Operation Phase

4.11.2.1      The fixed noise sources impact associated with the operation of the YLSEPP has been assessed based on the plant design information provided by the Project Engineer at the time of the assessment.  The assessment results indicate that the predicted fixed noise levels at the NAPs would comply with the noise criteria under unmitigated scenario.  No adverse fixed noise sources impact due to the operation of the YLSEPP would be anticipated.  Commissioning test should be conducted prior to operation of the Project to ensure that the fixed noise sources impact would comply with the relevant noise standards.