TABLE
OF CONTENTS
11.4 Description of Assessment Area
11.7 Consequence and Impact Analysis
11.10 Environmental Monitoring and Audit
Requirement
List of tables
Table 11.1 Population within Consultation Zone of the LPG Store
Table 11.2 Road Population in Construction Phase Scenario (Year
2026)
Table 11.3 Road Population in Operational Phase Scenario (Year
2031)
Table 11.4 Train Population in Operational Phase Scenario (Year
2031)
Table 11.5 Pedestrian Population
Table 11.6 Definitions of Time Modes
Table 11.7 Stability Category-Wind Speed Frequencies at HKO Tuen
Mun Weather Station
Table 11.8 Weather Class-Wind Direction Frequencies at HKO Tuen
Mun Weather Station
Table 11.9 Identified Failure Cases for the LPG Store
Table 11.10 Summary of Identified Failure Cases and Their
Associated Failure Rates
Table 11.11 Summary of Identified Failure Cases and Their
Associated Failure Rates
Table 11.12 Summary of Road Ignition Sources for Construction Phase
(Year 2026)
Table 11.13 Summary of Road Ignition Sources for Operational Phase
(Year 2031)
Table 11.14 Societal Risk Data for the LPG Store covering all
Assessed Scenarios
Table 11.15 Breakdown of PLL for the LPG Store by Major Events (All
Assessed Scenarios)
LIST OF FIGURES
Figure No. |
Title |
Location
of the LPG Store |
LIST OF DIAGRAMS
Diagram 11-1 |
Societal
Risk Guidelines |
Diagram 11-2 |
Location
of Population Groups in relation to LPG Store (Construction Phase) |
Diagram 11-3 |
Location
of Population Groups in relation to LPG Store (Operational Phase) |
Diagram 11-4 |
Individual
Risk Contours |
Diagram 11-5 |
FN Curves
for the LPG Store (Construction Phase) |
Diagram 11-6 |
FN Curves
for the LPG Store (Operational Phase) |
|
|
LIST OF Appendices
Population Data |
|
Calculation of Aircraft Crash Frequency |
|
Fault Tree Analysis |
|
Event Tree Analysis Consequence Analysis Results |
|
Photos showing Surrounding Environment of the LPG
Store |
|
|
|
|
|
Diagram 11‑1 Societal Risk Guidelines
¡¤ Year 2026 without Project
(2026 Base Case) ¨C The risk posed by the LPG Store to the planned population in
2026, in the absence of the Project;
¡¤ Year 2026 with Project
(Construction Phase) ¨C The risk posed by the LPG Store to the planned
population in 2026. This also accounted for the presence of the construction
workers in close vicinity of the LPG Store and the potential impacts associated
with the construction activities. Year 2026 was selected as the assessment year
for construction phase of the Project since it was expected to be the peak
construction year with maximum number of construction workers and construction
vehicles within the CZ of the LPG Store;
¡¤ Year 2031 without Project
(2031 Base Case) ¨C The risk posed by the LPG Store to the planned population in
2031, in the absence of the Project; and
¡¤ Year 2031 with Project
(Operational Phase) ¨C The risk posed by the LPG Store to the planned population
in 2031 upon the commissioning of the Project.
The LPG Store
Population Data
Diagram 11‑2 Location of
Population Groups in relation to LPG Store
(Construction Phase)
Diagram 11‑3 Location
of Population Groups in relation to LPG Store (Operational Phase)
Diagram 11‑4 Location
of Population Groups in relation to LPG Store (Base Cases for Year 2026 and
Year 2031)
Construction
Workers for the Project
Land and Building
Population
Table 11.1 Population
within Consultation Zone of the LPG Store
ID |
Description |
Maximum
Population |
||
Construction
Phase |
Operational
Phase |
2026
Base Case and 2031 Base Case |
||
1 |
Wu Shan Recreation Playground |
0 |
108 |
108 |
2 |
Open Car Park |
0 |
20 |
20 |
3 |
Promenade |
0 |
10 |
10 |
4 |
Tuen Mun Area 44 Joint User Complex and Wholesale
Fish Market |
147 |
147 |
147 |
5 |
Wu Shan Tennis Court |
12 |
12 |
12 |
6 |
Tuen Mun Wu Hong Clinic |
193 |
193 |
193 |
9a |
Land WA 5.4 |
20 |
0(1) |
0 |
9b |
Land WA 5.5 |
30 |
0(1) |
0 |
10a |
Lands WS 5.2, 5.3 & 5.6 |
88 |
0(1) |
0 |
10b |
Land WS 5.8 |
12 |
0(1) |
0 |
Note:
(1) The works areas and works
sites (i.e. population ID#9a, #9b, #10a and #10b) will
be reinstated to their present uses (i.e. population ID#1, #2 and #3) after the
completion of the construction of the Project.
Road Population
Table 11.2 Road
Population in Construction Phase Scenario (Year 2026)
Population ID |
Description |
Maximum Population [Note 1] |
|
Daytime |
Night-time |
||
8a |
Hoi Wong Road |
25 |
12 |
8b |
Wu Shan Road |
13 |
7 |
8c |
Wu Hong Street |
2 |
1 |
Note 1: Road population was estimated based on Traffic Impact Assessment
forecasted for Year 2026.
Table 11.3 Road
Population in Operational Phase Scenario (Year 2031)
Population ID |
Description |
Maximum Population [Note 1] |
|
Daytime |
Night-time |
||
8a |
Hoi Wong Road |
25 |
12 |
8b |
Wu Shan Road |
10 |
5 |
8c |
Wu Hong Street |
2 |
1 |
Note 1: Road population was estimated based on Traffic Impact Assessment
forecasted for Year 2031.
Railway Population
Table 11.4 Train Population in Operational
Phase Scenario (Year 2031)
Population ID |
Description |
Maximum Population |
|
0700 ¨C 2300 hours |
2300 - 0700 hours |
||
7 |
LRT [Note 1] |
296 |
148 |
11 |
TME Railway Population |
932 |
666 |
Note 1: The population of LRT was estimated based on the design capacity of a LRT Vehicle and the existing
train frequency, and the population for both the construction phase scenario
and the operational phase scenario were assumed to be the same.
Pedestrian Population
Table 11.5 Pedestrian
Population
Population ID |
Description |
Maximum Population [Note 1][Note
2] |
8a |
Hoi Wong Road |
3 |
8b |
Wu Shan Road |
4 |
8c |
Wu Hong Street |
2 |
12 |
Cycling Track - Near
LPG Store |
2 |
13 |
Cycling Track - Near Wu
Shan Recreation Playground |
1 |
Note 1: The pedestrian population was estimated based on site survey carried
out during daytime of 17-18 September 2021. Night-time population was assumed
to be same as the daytime population as a conservative approach.
Note 2: The pedestrian
population along Hoi Wong Road, Wu Shan Road and Wu Hong Street was combined
with the road population in the model.
Time Modes
Table 11.6 Definitions of Time Modes
Time Period |
Definition |
Proportion of Time |
Weekday
Day |
Mon
¨C Fri, 7am ¨C 7pm |
35.71% |
Weekend Day |
Sat ¨C Sun, 7pm ¨C 7am |
14.29% |
Night (1900-2300) |
All days, 7pm ¨C 11pm |
16.67% |
Night (2300-0700) |
All days, 11pm ¨C 7am |
33.33% |
Meteorological Data
Table 11.7 Stability Category-Wind Speed
Frequencies at HKO Tuen Mun Weather Station
Daytime |
|||||||
Wind
Speed (m/s) |
A |
B |
C |
D |
E |
F |
Total
(%) |
0.0-1.9 |
12.39 |
5.55 |
0.00 |
7.65 |
0.00 |
9.26 |
34.85 |
2.0-3.9 |
7.35 |
18.77 |
8.15 |
11.12 |
4.26 |
0.51 |
50.16 |
4.0-5.9 |
0.00 |
5.80 |
3.55 |
4.38 |
0.30 |
0.00 |
14.03 |
6.0-7.9 |
0.00 |
0.00 |
0.16 |
0.78 |
0.00 |
0.00 |
0.94 |
Over 8.0 |
0.00 |
0.00 |
0.00 |
0.02 |
0.00 |
0.00 |
0.02 |
All (%) |
19.74 |
30.12 |
11.86 |
23.95 |
4.56 |
9.77 |
100.00 |
Night-time |
|||||||
Wind
Speed (m/s) |
A |
B |
C |
D |
E |
F |
Total
(%) |
0.0-1.9 |
0.00 |
0.00 |
0.00 |
1.45 |
0.00 |
51.11 |
52.56 |
2.0-3.9 |
0.00 |
0.00 |
0.00 |
13.01 |
22.05 |
3.16 |
38.22 |
4.0-5.9 |
0.00 |
0.00 |
0.00 |
7.70 |
0.99 |
0.00 |
8.69 |
6.0-7.9 |
0.00 |
0.00 |
0.00 |
0.44 |
0.00 |
0.00 |
0.44 |
Over 8.0 |
0.00 |
0.00 |
0.00 |
0.09 |
0.00 |
0.00 |
0.09 |
All (%) |
0.00 |
0.00 |
0.00 |
22.69 |
23.04 |
54.27 |
100.00 |
Table 11.8 Weather Class-Wind Direction
Frequencies at HKO Tuen Mun Weather Station
Daytime |
|||||||||||||
Direction |
3B |
1D |
3D |
6D |
2E |
1F |
Total
(%) |
||||||
0 ¨C 30 |
6.90 |
1.12 |
2.84 |
0.05 |
1.24 |
1.78 |
13.93 |
||||||
30 ¨C 60 |
4.59 |
0.84 |
7.16 |
0.36 |
2.08 |
0.84 |
15.87 |
||||||
60 ¨C 90 |
0.05 |
0.10 |
0.13 |
0.00 |
0.08 |
0.25 |
0.61 |
||||||
90 ¨C 120 |
0.51 |
0.05 |
0.43 |
0.03 |
0.15 |
0.18 |
1.35 |
||||||
120 ¨C 150 |
2.82 |
0.20 |
3.07 |
0.53 |
0.38 |
0.36 |
7.36 |
||||||
150 ¨C 180 |
16.01 |
0.46 |
11.24 |
1.40 |
1.80 |
0.66 |
31.57 |
||||||
180 ¨C 210 |
6.78 |
0.30 |
3.07 |
0.03 |
0.71 |
0.28 |
11.17 |
||||||
210 ¨C 240 |
5.94 |
0.30 |
1.47 |
0.00 |
0.56 |
0.18 |
8.45 |
||||||
240 ¨C 270 |
2.49 |
0.43 |
0.41 |
0.00 |
0.23 |
0.20 |
3.76 |
||||||
270 ¨C 300 |
0.56 |
0.18 |
0.13 |
0.00 |
0.18 |
0.43 |
1.48 |
||||||
300 ¨C 330 |
1.42 |
0.15 |
0.25 |
0.00 |
0.05 |
0.20 |
2.07 |
||||||
330 ¨C 360 |
1.52 |
0.23 |
0.25 |
0.00 |
0.15 |
0.23 |
2.38 |
||||||
All (%) |
49.59 |
4.36 |
30.45 |
2.40 |
7.61 |
5.59 |
100.00 |
||||||
Night-time |
|||||||||||||
Direction |
1D |
4D |
6D |
2E |
1F |
Total
(%) |
|||||||
0 ¨C 30 |
0.42 |
0.95 |
0.03 |
3.65 |
7.88 |
12.93 |
|||||||
30 ¨C 60 |
0.19 |
8.33 |
0.40 |
10.09 |
6.29 |
25.30 |
|||||||
60 ¨C 90 |
0.00 |
0.03 |
0.00 |
0.19 |
0.61 |
0.83 |
|||||||
90 ¨C 120 |
0.00 |
0.26 |
0.16 |
1.40 |
1.56 |
3.38 |
|||||||
120 ¨C 150 |
0.11 |
2.51 |
0.37 |
4.50 |
2.27 |
9.76 |
|||||||
150 ¨C 180 |
0.05 |
9.87 |
0.19 |
14.75 |
3.17 |
28.03 |
|||||||
180 ¨C 210 |
0.08 |
0.71 |
0.00 |
4.39 |
1.96 |
7.14 |
|||||||
210 ¨C 240 |
0.00 |
0.29 |
0.00 |
2.46 |
1.30 |
4.05 |
|||||||
240 ¨C 270 |
0.00 |
0.08 |
0.00 |
0.79 |
1.24 |
2.11 |
|||||||
270 ¨C 300 |
0.00 |
0.03 |
0.00 |
0.48 |
2.17 |
2.68 |
|||||||
300 ¨C 330 |
0.00 |
0.11 |
0.00 |
0.19 |
1.51 |
1.81 |
|||||||
330 ¨C 360 |
0.05 |
0.29 |
0.00 |
0.42 |
1.22 |
1.98 |
|||||||
All (%) |
0.90 |
23.46 |
1.15 |
43.31 |
31.18 |
100.00 |
|||||||
Hazard Analysis
Spontaneous Failures
Failure of Storage Vessel
Failure of Road Tanker
Guillotine Failure of Liquid Filling Line to
Storage Vessel
Guillotine Failure of Liquid Supply Line to
Vaporisers
Failure of Vaporisers
Guillotine Failure of Liquid Line from
Tanker Pipe to Loading Hose
Failure of Flexible Hose
Loading / Unloading Failures
Hose Misconnection and Disconnection Error
Tanker Drive-away Error
Road Tanker Collision
Vehicle Impact with Road Tanker during
Unloading
Storage Vessel Overfilling
Over-pressurisation of Pipework
External Events
Safety Features
Non-return Valve
Excess Flow Valve
Emergency Shutdown System
Breakaway Coupling
Manual Isolation System
Double-check Filler Valve
Relief Valve
Human Error
Fire Protection / Fighting System
Chartek Coating
Water Spray System
Fire Services
Escalation
Summary
Table 11.9 Identified
Failure Cases for the LPG Store
Failure Types |
Failure Cases |
Spontaneous Failure of Pressurised LPG Equipment |
¡¤
Storage Vessel Failure ¡¤
Road Tanker Failure ¡¤
Pipework Failure ¡¤
Hose Failure ¡¤
Vaporiser Failure |
External Event |
¡¤
Earthquake MMI VIII ¡¤
Aircraft Crash |
Delivery Failure |
¡¤
Hose Misconnection Error ¡¤
Hose Disconnection Error ¡¤
Tanker Drive-away Error ¡¤
Road Tanker Collision during Unloading ¡¤
Storage Vessel Overfilling ¡¤
Over-pressurisation of pipework |
Safety System Failure |
¡¤
Pressure Relief Valve Failure ¡¤
Non-return Valve Failure ¡¤
Excess Flow Valve Failure ¡¤
Emergency Shutdown System Failure ¡¤
Double-check Filler Valve Failure ¡¤
Breakaway Coupling Failure ¡¤
Human Error ¡¤
Manual Isolation Valve Failure |
Fire Fighting System Failure |
¡¤
Fire Services Failure ¡¤
Chartek Coating Failure ¡¤
Water Spray System Failure |
Introduction
Frequency
Estimation
Spontaneous
Failures
Storage
Vessel Failure
Road
Tanker Failure
Pipework
Failure
Vaporiser
Failure
Hose
Failure
Loading
/ Unloading Failures
Hose
Misconnection Error
Hose
Disconnection Error
Tanker
Drive-away Error
Tanker
Collision during Unloading
Overfilling
of Storage Vessel
Over-pressurization
of Pipework
External
Events
Earthquake
MMI VIII
Aircraft
Crash
Safety
System Failure
Pressure
Relief Valve Failure
Pump
Overpressure Protection System
Non-return
Valve Failure
Excess
Flow Valve Failure
Emergency
Shutdown System Failure
Breakaway
Coupling Failure
Double-check
Filler Valve Failure
Manual
Isolation Valve
Human
error
Fire
Fighting System Failure
Water
Spray System Failure
Failure
of Fire Services
Chartek
Coating Failure
Table 11.10 Summary of Identified Failure Cases and Their
Associated Failure Rates
Failure Cases |
Failure Rates |
Reference Source |
Spontaneous
Failure of Pressurised LPG Equipment |
||
Catastrophic Failure of Storage Vessel |
1.8¡Á10¨C7 per vessel year |
Reference [5] |
Partial Failure of Storage Vessel |
5.0¡Á10-6 per vessel year |
Reference [5] |
Catastrophic Failure of Road Tanker |
2.0¡Á10-6 per tanker year |
Reference [5] |
Partial Failure of Road Tanker |
5.0¡Á10-6 per tanker year |
Reference [5] |
Guillotine Failure of Pipework |
1.0¡Á10-6 per meter per year |
Reference [5] |
Vaporiser Failure |
1.0¡Á10-6 per meter per year |
Reference [5] |
Hose Failure |
1.8¡Á10-7 per transfer or 9.0¡Á10-8 per hour |
Reference [5] |
External Event |
||
Earthquake MMI VIII |
1.0¡Á10-5 per year |
Reference [5] |
Aircraft Crash |
1.61¡Á10-9 per year |
|
LPG Loading
Failure |
||
Hose Misconnection Failure |
3.0¡Á10-5 per operation |
Reference [5] |
Hose Disconnection Failure |
2.0¡Á10-6 per operation |
Reference [5] |
Tanker Drive-away Error |
4.0¡Á10-6 per operation |
Reference [5] |
Road Tanker Collision |
1.5¡Á10-4 per operation |
Reference [5] |
Storage Vessel Overfilling |
2.0¡Á10-2 per operation |
Reference [5] |
Safety
Features Failure |
||
Pressure Relief Valve Failure |
1.0¡Á10-4 per demand |
Reference [5] based on ESD system |
Failure of Pump Over-pressurization
Protection |
1.0¡Á10-4 per demand |
Based that for failure of pressure relief valve |
Non-return Valve Failure |
0.013 per demand |
Reference [5] |
Excess Flow Valve Failure |
1.00 per demand for liquid filling line
and flexible hose 0.13 per demand for line to vaporiser |
Reference [5] |
Manual Isolation Valve Failure |
0.5 per demand |
Reference [5] |
Emergency Shutdown System Failure |
1.0¡Á10-4 per demand |
Reference [5] |
Breakaway Coupling Failure |
0.013 per demand for tanker |
Reference [5] Conservative estimate, based on breakaway
coupling for road tanker |
Double-check Filler Valve Failure |
2.6¡Á10-3 per demand |
Reference [5] |
Operator fails to Rectify Problem |
1.5¡Á10-3 per demand |
Reference [11] |
Fire
Protection / Fighting System Failure |
||
Water Spray System Failure |
1.5¡Á10-2
per demand |
Reference [5] |
Failure of Fire Services |
0.5 per demand |
Reference [5] |
Chartek Coating Failure |
0.1 |
Reference [5] |
Failure
Probability |
||
Catastrophic failure of vessel provided
over-pressurization |
0.01 |
Reference [11] |
Partial failure of vessel provided over-pressurization |
0.1 |
Reference [11]; 10 times of catastrophic
failure |
Probability of catastrophic / guillotine
failure due to aircraft crash [Note 1] |
1 |
Assume 100% failure leading to rupture /
guillotine failure |
Probability of partial failure due to
aircraft crash [Note 1] |
0 |
Assume 100% failure leading to rupture /
guillotine failure |
Probability of equipment failure due to
earthquake |
0.01 |
Reference [6] |
Probability of catastrophic / partial
failure in earthquake |
0.5 / 0.5 |
It is more likely for an earthquake to
lead to the failure of the pipeline connection rather than the failure of the
storage vessel, for which damages would be prevented by the buffering effect
of the washed sand. Pipeline failure has already been accounted for in other
hazardous events, and therefore a 50:50 split was conservatively adopted for
vessel failure events. |
Note 1: The probability of road tanker rupture
and road tanker partial failure due to aircraft crash are considered as 1 and 0
respectively, which assumes only catastrophic failure of road tanker will be
resulted in the event of aircraft crash.
The probability for storage vessel failure due to aircraft crash will be
significantly less as compared to other equipment since storage vessels are
located underground. Hence, 0.01
and 0.09 were adopted for catastrophic and partial failure of storage vessels
respectively.
Escalation
Frequency
of Occurrence
Fault
Tree Analysis
Event
Tree Analysis
Table 11.11 Summary of Identified Failure Cases
and Their Associated Failure Rates
Ref. |
Event Description |
Outcome Event |
Event Frequency per year |
Outcome Probability |
Probability of Failure to isolate |
Total Outcome Frequency /year |
F1 |
Cold Catastrophic
Failure of Storage Vessels |
FBL |
5.90E-07 |
9.00E-01 |
1.00E+00 |
5.31E-07 |
F1 |
Cold Catastrophic
Failure of Storage Vessels |
VCE |
5.90E-07 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F1 |
Cold Catastrophic
Failure of Storage Vessels |
FFR |
5.90E-07 |
1.00E-01 |
1.00E+00 |
5.90E-08 |
F2 |
Cold Partial
Failure of Storage Vessels |
JFI |
1.505E-05 |
5.00E-02 |
1.00E+00 |
7.53E-07 |
F2 |
Cold Partial
Failure of Storage Vessels |
BLEVE |
1.51E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2 |
Cold Partial
Failure of Storage Vessels |
VCE |
1.505E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2 |
Cold Partial
Failure of Storage Vessels |
FFR |
1.51E-05 |
9.50E-01 |
1.00E+00 |
1.43E-05 |
F3 |
Cold Catastrophic
Failure of Road Tanker |
FBL |
5.56E-08 |
9.00E-01 |
1.00E+00 |
5.00E-08 |
F3 |
Cold Catastrophic
Failure of Road Tanker |
VCE |
5.56E-08 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F3 |
Cold Catastrophic
Failure of Road Tanker |
FFR |
5.56E-08 |
1.00E-01 |
1.00E+00 |
5.56E-09 |
F4 |
Cold Partial
Failure of Road Tanker |
JFI |
1.39E-07 |
5.00E-02 |
1.00E+00 |
6.94E-09 |
F4 |
Cold Partial
Failure of Road Tanker |
BLEVE |
1.39E-07 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F4 |
Cold Partial
Failure of Road Tanker |
VCE |
1.39E-07 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F4 |
Cold Partial
Failure of Road Tanker |
FFR |
1.39E-07 |
1.90E-01 |
1.00E+00 |
2.64E-08 |
F5.1 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Tanker) |
JFI |
1.85E-07 |
5.00E-02 |
4.53E-03 |
4.19E-11 |
F5.1 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Tanker) |
BLEVE |
1.85E-07 |
6.18E-05 |
4.53E-03 |
5.18E-14 |
F5.1 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Tanker) |
VCE |
1.85E-07 |
0.00E+00 |
4.53E-03 |
0.00E+00 |
F5.1 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Tanker) |
FFR |
1.85E-07 |
1.90E-01 |
4.53E-03 |
1.59E-10 |
F5.2 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Vessel) |
JFI |
1.85E-07 |
5.00E-02 |
1.27E-02 |
1.18E-10 |
F5.2 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Vessel) |
BLEVE |
1.85E-07 |
6.18E-05 |
1.27E-02 |
1.45E-13 |
F5.2 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Vessel) |
VCE |
1.85E-07 |
0.00E+00 |
1.27E-02 |
0.00E+00 |
F5.2 |
Guillotine Failure
of Liquid filling Line to Vessel (fed from Vessel) |
FFR |
1.85E-07 |
1.90E-01 |
1.27E-02 |
4.47E-10 |
F6 |
Guillotine Failure
of Liquid Supply Line to Vaporiser |
JFI |
2.01E-05 |
5.00E-02 |
1.30E-01 |
1.31E-07 |
F6 |
Guillotine Failure
of Liquid Supply Line to Vaporiser |
BLEVE |
2.01E-05 |
6.18E-05 |
1.30E-01 |
1.62E-10 |
F6 |
Guillotine Failure
of Liquid Supply Line to Vaporiser |
VCE |
2.01E-05 |
0.00E+00 |
1.30E-01 |
0.00E+00 |
F6 |
Guillotine Failure
of Liquid Supply Line to Vaporiser |
FFR |
2.01E-05 |
1.90E-01 |
1.30E-01 |
4.97E-07 |
F7 |
Guillotine Failure
of Liquid Filling Line to Flexible Hose |
JFI |
2.55E-07 |
5.00E-02 |
7.55E-03 |
9.64E-11 |
F7 |
Guillotine Failure
of Liquid Filling Line to Flexible Hose |
BLEVE |
2.55E-07 |
6.18E-05 |
7.55E-03 |
1.19E-13 |
F7 |
Guillotine Failure
of Liquid Filling Line to Flexible Hose |
VCE |
2.55E-07 |
0.00E+00 |
7.55E-03 |
0.00E+00 |
F7 |
Guillotine Failure
of Liquid Filling Line to Flexible Hose |
FFR |
2.55E-07 |
1.90E-01 |
7.55E-03 |
3.66E-10 |
F8 |
Vaporiser Failure |
JFI |
3.51E-05 |
5.00E-02 |
1.30E-01 |
2.28E-07 |
F8 |
Vaporiser Failure |
BLEVE |
3.51E-05 |
6.18E-07 |
1.30E-01 |
2.82E-12 |
F8 |
Vaporiser Failure |
VCE |
3.51E-05 |
0.00E+00 |
1.30E-01 |
0.00E+00 |
F8 |
Vaporiser Failure |
FFR |
3.51E-05 |
1.90E-01 |
1.30E-01 |
8.67E-07 |
F9.1 |
Guillotine Failure
of Flexible Hose (fed from Tanker) |
JFI |
1.02E-04 |
5.00E-02 |
7.55E-03 |
3.86E-08 |
F9.1 |
Guillotine Failure
of Flexible Hose (fed from Tanker) |
BLEVE |
1.02E-04 |
1.240E-04 |
7.55E-03 |
9.54E-11 |
F9.1 |
Guillotine Failure
of Flexible Hose (fed from Tanker) |
VCE |
1.02E-04 |
0.00E+00 |
7.55E-03 |
0.00E+00 |
F9.1 |
Guillotine Failure
of Flexible Hose (fed from Tanker) |
FFR |
1.02E-04 |
1.90E-01 |
7.55E-03 |
1.47E-07 |
F9.2 |
Guillotine Failure
of Flexible Hose (fed from Vessel) |
JFI |
1.02E-04 |
5.00E-02 |
1.30E-03 |
6.64E-09 |
F9.2 |
Guillotine Failure
of Flexible Hose (fed from Vessel) |
BLEVE |
1.02E-04 |
1.24E-04 |
1.30E-03 |
1.64E-11 |
F9.2 |
Guillotine Failure
of Flexible Hose (fed from Vessel) |
VCE |
1.02E-04 |
0.00E+00 |
1.30E-03 |
0.00E+00 |
F9.2 |
Guillotine Failure
of Flexible Hose (fed from Vessel) |
FFR |
1.02E-04 |
1.90E-01 |
1.30E-03 |
2.52E-08 |
Note 1: FBL
¨C Fireball; BLEVE ¨C Boiling Liquid Expanding Vapour Explosion; VCE ¨C Vapour
Cloud Explosion; JFI ¨C Jet fire; FFR ¨C Flash Fire
Introduction
Physical
Effects Modelling
Fireball
/ BLEVE
Jet
fire
Dense
gas dispersion / flash fire and Vapour Cloud Explosion (VCE)
Ignition
Source
Point
Sources
Line Sources
Table 11.12 Summary
of Road Ignition Sources for Construction Phase (Year 2026)
Line Source |
Peak
Hour Traffic Density |
Daytime
Traffic Density (veh
/ hr) |
Night-time
Traffic Density (veh
/ hr) |
Average
Traffic Speed (km
/ hr) |
Hoi Wong Road |
1,223 |
1,223 |
573 |
50 |
Wu Shan Road |
618 |
618 |
298 |
|
Wu Hong Street |
309 |
309 |
149 |
Table 11.13 Summary of Road Ignition Sources for
Operational Phase (Year 2031)
Line Source |
Peak
Hour Traffic Density |
Daytime
Traffic Density (veh
/ hr) |
Night-time
Traffic Density (veh
/ hr) |
Average
Traffic Speed (km
/ hr) |
Hoi Wong Road |
1,275 |
1,275 |
600 |
50 |
Wu Shan Road |
591 |
591 |
286 |
|
Wu Hong Street |
296 |
296 |
143 |
Area
Source
Ignition
Probability
Protection
Factors
Protection
afforded to persons indoors in a building
Protection
afforded to persons by being on the upper floors of building
Individual
Risk
Risk
Level
Diagram 11‑5 Individual
Risk Contours
Acceptability
Societal
Risk
Risk
Level
Diagram 11‑6 FN
Curves for the LPG Store (Construction Phase)
Diagram 11‑7 FN
Curves for the LPG Store (Operational Phase)
Acceptability
Table 11.14 Societal Risk Data for the LPG Store covering all
Assessed Scenarios
No. Fatalities |
Frequency (/year) |
|||
Year 2026 ¨C Base Case |
Year 2026 ¨C Construction Phase |
Year 2031 ¨C Base Case |
Year 2031 ¨C Operational Phase |
|
1 |
9.62E-06 |
9.83E-06 |
9.62E-06 |
9.62E-06 |
2 |
8.26E-06 |
8.89E-06 |
8.26E-06 |
8.26E-06 |
3 |
7.61E-06 |
7.92E-06 |
7.61E-06 |
7.61E-06 |
4 |
6.28E-06 |
6.41E-06 |
6.28E-06 |
6.28E-06 |
5 |
5.26E-06 |
5.36E-06 |
5.26E-06 |
5.26E-06 |
6 |
2.73E-06 |
3.58E-06 |
2.73E-06 |
2.73E-06 |
8 |
8.17E-07 |
8.59E-07 |
8.16E-07 |
8.16E-07 |
10 |
6.48E-07 |
6.48E-07 |
6.48E-07 |
6.48E-07 |
12 |
6.44E-07 |
6.46E-07 |
6.44E-07 |
6.44E-07 |
15 |
6.40E-07 |
6.39E-07 |
6.40E-07 |
6.40E-07 |
20 |
6.39E-07 |
6.39E-07 |
6.39E-07 |
6.39E-07 |
25 |
6.39E-07 |
6.39E-07 |
6.39E-07 |
6.39E-07 |
30 |
6.38E-07 |
6.38E-07 |
6.38E-07 |
6.38E-07 |
40 |
6.37E-07 |
6.37E-07 |
6.37E-07 |
6.37E-07 |
50 |
6.35E-07 |
4.58E-07 |
6.35E-07 |
6.35E-07 |
60 |
4.56E-07 |
4.55E-07 |
4.56E-07 |
4.56E-07 |
80 |
4.51E-07 |
4.47E-07 |
4.51E-07 |
4.51E-07 |
100 |
3.97E-08 |
3.00E-07 |
3.97E-08 |
3.97E-08 |
120 |
3.17E-08 |
2.95E-08 |
3.14E-08 |
3.17E-08 |
150 |
2.30E-08 |
2.22E-08 |
2.28E-08 |
2.30E-08 |
200 |
7.01E-09 |
5.12E-09 |
6.82E-09 |
6.96E-09 |
Potential
Loss of Life (PLL)
Table 11.15 Breakdown
of PLL for the LPG Store by Major Events (All Assessed Scenarios)
Event Description |
Outcome [Note
1] |
Year 2026 ¨C Base Case |
Year 2026 ¨C Construction Phase |
Year 2031 ¨C Base Case |
Year 2031 ¨C Operation Phase |
||||
Potential Loss of Life (PLL) per year |
% of Total PLL |
Potential Loss of Life (PLL) per year |
% of Total PLL |
Potential Loss of Life (PLL) per year |
% of Total PLL |
Potential Loss of Life (PLL) per year |
% of Total PLL |
||
Cold
Catastrophic Failure of Storage Vessels |
FBL |
4.40E-05 |
47.4% |
4.43E-05 |
46.3% |
4.40E-05 |
47.5% |
4.40E-05 |
47.4% |
Cold Partial
Failure of Storage Vessels |
FFR |
3.30E-05 |
35.6% |
3.46E-05 |
36.1% |
3.30E-05 |
35.6% |
3.30E-05 |
35.6% |
Cold
Catastrophic Failure of Storage Vessels |
FFR |
6.97E-06 |
7.5% |
6.56E-06 |
6.9% |
6.94E-06 |
7.5% |
6.97E-06 |
7.5% |
Cold
Catastrophic Failure of Road Tanker |
FBL |
4.31E-06 |
4.6% |
4.92E-06 |
5.1% |
4.31E-06 |
4.6% |
4.31E-06 |
4.6% |
Vaporiser
Failure |
FFR |
1.47E-06 |
1.6% |
1.56E-06 |
1.6% |
1.47E-06 |
1.6% |
1.47E-06 |
1.6% |
Guillotine
Failure of Liquid Supply Line to Vaporiser |
FFR |
1.02E-06 |
1.1% |
1.44E-06 |
1.5% |
1.02E-06 |
1.1% |
1.02E-06 |
1.1% |
Cold Partial
Failure of Storage Vessels |
JFI |
8.53E-07 |
0.9% |
9.03E-07 |
0.9% |
8.53E-07 |
0.9% |
8.53E-07 |
0.9% |
Cold Catastrophic
Failure of Road Tanker |
FFR |
6.98E-07 |
0.8% |
7.15E-07 |
0.7% |
6.95E-07 |
0.7% |
6.98E-07 |
0.8% |
Vaporiser
Failure |
JFI |
2.53E-07 |
0.3% |
4.13E-07 |
0.4% |
2.53E-07 |
0.3% |
2.53E-07 |
0.3% |
Guillotine
Failure of Liquid Supply Line to Vaporiser |
JFI |
9.13E-08 |
0.1% |
1.79E-07 |
0.2% |
9.13E-08 |
0.1% |
9.13E-08 |
0.1% |
Others |
- |
1.14E-07 |
0.1% |
1.52E-07 |
0.2% |
1.14E-07 |
0.1% |
1.15E-07 |
0.1% |
Total |
9.28E-05 |
- |
9.57E-05 |
- |
9.28E-05 |
- |
9.28E-05 |
- |
|
Note 1: FBL ¨C Fireball;
JFI ¨C Jet fire; FFR ¨C Flash Fire |
|
|
|
|
|
|
|
|
Risk
Mitigation Measure Identification
Construction
Phase
Operational
Phase
Approach
Evaluation
of Risk Mitigation Measures
Construction
Phase
Operational
Phase
Recommendations