TABLE OF CONTENTS
13 Summary of Environmental
Outcomes
13.2..... Environmental
Benefits of the Project
13.3..... Incorporation
of Environmentally Friendly Options
13.4..... Environmental
Designs Recommended
13.5..... Key
Environmental Problems Avoided and Environmentally Sensitive Areas Protected
13.6..... Environmental
Protection Measures Recommended
13.7..... Estimation
of Population Protected
List of Tables
Table 13.1 Summary
of Key Environmental Problems Avoided and Sensitive Areas Protected
· Enhance the local transport connectivity and mobility across the territory by extending the railway network to Tuen Mun South;
· Help relieve road traffic congestion, reduce air pollution, noise nuisance and carbon emissions in the region; and
· Enhance the sustainability in the local community by providing a sustainable and convenient railway service with energy efficiency.
· Avoidance of encroachment into the recognized sites of conservation importance;
· Avoidance of traversing Tuen Mun River Channel through selection of elevated option, which in turns minimising substantial reduction in hydraulic capacity and unacceptable environmental impacts; and
· Minimisation of number of piers and foundations works in the river and the associated environmental impacts.
· Adoption of environmentally friendly construction methods;
· Adoption of bird-friendly design on noise enclosures/ barriers and TRB;
· Adoption of ecological enhancement measures;
· Provision of noise mitigation measures;
· Incorporation of sustainable building considerations in the station design;
· Adoption of proactive measures to avoid illegal dumping; and
· Implementation of environmental monitoring and auditing system.
Adoption of Environmentally Friendly Construction Methods
Adoption of Bird-friendly Design
Adoption of Ecological Enhancement Measures
Provision of Direct Noise Mitigation Measures
Incorporation of Sustainable Building Considerations in the Station Design
Adoption of Proactive Measures to Avoid Illegal Dumping
Implementation of Environmental Monitoring and Auditing System
Table 13.1 Summary
of Key Environmental Problems Avoided and Sensitive Areas Protected
Design Approach
|
Environmental
Problems Avoided and Sensitive Areas Protected
|
Avoidance of encroachment into recognized
sites of conservation importance
(Section 13.3.1)
|
· During the planning and conceptual design stage, recognised site of conservation importance (i.e. Tuen Mun egretry) in the vicinity of the Project was identified and avoided in the selection of temporary works areas /work sites and the design of permanent works areas. |
Avoidance of direct impact and minimization of
indirect impact on ardeids night roost in Tuen Mun Park
|
· During the planning and conceptual design stage, ardeids night roost in Tuen Mun Park was identified and avoided in the selection of temporary works areas /work sites and the design of permanent works areas. Only limited maintenance works including diversion of cycle track and pedestrian walkway (e.g. erection of hoarding/signage, painting of road sign) and minor pruning works at the overgrown trees branches that may pose safety issue to the public would be conducted at Tuen Mun Park. · Minimisation of indirect impact and the potential disturbance through establishment of buffer zone and control of working hour throughout the construction stage to control the timing of the noisy construction activities (ceased 30 minutes before sunset and until the ardeids leave the roosting location of the following day (i.e. around 30 min after sunrise)) within 100 m from the night roosting site. · Minimization of noise and glare / visual disturbance from railway operation by provision of vertical panel on top of the parapet of viaduct along the eastern side of the viaduct. |
Adoption of environmentally friendly construction
method
(Section
13.4.2- 13.4.3) |
· Minimisation of construction dust and water quality impact at Tuen Mun River Channel through adoption of temporary steel platform. · Adoption of environmental friendly construction method (e.g. DfMA) and quiet piling method. |
Adoption of bird-friendly design
(Section 13.4.4)
|
· Adoption of non-transparent / non-reflective panels at noise enclosures / barriers as far as practicable. · Adoption of non-glaring tinted materials, or superimposing dark patterns or strips on the transparent enclosures / barriers and station structures. · Installation of highway lighting at Tuen Mun Bridge during night-time to minimise bird collision. |
Adoption of ecological enhancement measures
(Section 13.4.5) |
· Consideration of the enlarged pile cap of piers, perching and foraging structures such as ledges at the pier structure as additional standing areas to enhance perching opportunities of ardeids at Tuen Mun River Channel. · Vegetation / promoting landscape tree planting along the promenade of Tuen Mun River Channel would be explored to enhance the overall ecological opportunities. |
Provision of direct noise mitigation measures
(Section 13.4.6)
|
· Protection of NSRs through provision of adequate noise mitigation measures during the operation of the Project. |
Incorporation of Sustainable Building Considerations
in the Station Design
(Section 13.4.7) |
· Maximisation of natural ventilation to reduce demand for air-conditioning. · Appropriate glazing and/or shading in the façade design to reduce solar heat gain. · Allowance for natural daylight penetration to minimise artificial lighting dependency. · Onsite renewable energy generation in the form of photovoltaic panels or micro wind turbines. · Rainwater harvesting for landscape planting irrigation. · High efficiency potable water fixtures and dual flush systems to reduce water consumption. |
Avoidance of illegal dumping (Section 13.4.8)
|
· Adoption
of preventive measures to avoid/minimise the chance of illegal dumping. |
Implementation of Environmental Monitoring and
Auditing System
|
· Ensure all
the recommended measures are properly in place and their effectiveness during
the construction and operation of the Project. |
Table 13.2 Key
Recommended Mitigation Measures / Good Site Practices / Enhancement Measures
and their Associated Benefits
Environmental
Aspect |
Key
Recommended Mitigation Measures / Good Site Practices / Enhancement Measures |
Associated
Benefits |
Air Quality
|
· Implement
relevant control measures as required in the Air Pollution Control
(Construction Dust) Regulation to minimise dust generation. ·
Watering once every two hours on heavy construction works
sites, exposed site surfaces and unpaved haul roads to reduce dust emission
by 91.7%, subject to actual site condition. ·
Avoid the use of exempted Non-road Mobile Machineries (NRMMs) and
deploy electrified NRMMs as far as practicable to minimise exhaust emission
from NRMMs during construction phase. |
· Protect air sensitive receivers by reducing fugitive dust emissions |
Noise
|
· Adopt quiet
construction method, Quality Powered Mechanical Equipment (QPME), movable
noise barriers, noise insulating fabric, noise enclosures, acoustic measures
(e.g. soundproof hammer bracket for hydraulic
breaker), carefully scheduled construction programme and good site practices
to mitigate the construction noise impact. · Provide
noise mitigation measures including noise barriers and noise enclosures to
alleviate the railway noise impact during the operation of the Project. · Provide
acoustic measures where necessary for the planned fixed plants to ensure
noise compliance. |
· Protect noise sensitive receivers by reducing construction and operational noise |
Water Quality
|
· Implement
the proposed mitigation measures including installation of casing/concrete
cofferdam and watertight precast pile cap shells to isolate the construction
activities from the river water, use of water pumps to collect any
construction site runoff and ingress/seepage water within the concrete
cofferdam and watertight precast pile cap shells to the on-site wastewater
treatment facilities for treatment to satisfactory levels before discharge,
and deployment of silt curtains to completely enclose the concrete
cofferdam/watertight precast pile cap shells prior to setting up piling works
and installation of concrete cofferdam/watertight precast pile cap shells. · Implement
the mitigation measures as detailed in the ProPECCPN
1/94 “Construction Site Drainage” and |
· Protect the neighbouring Water Sensitive Receivers (WSRs) during construction phase |
Waste Management Implications
|
· Implement
good site practices and waste reduction measures (e.g.
reuse of construction and demolition (C&D) materials as far as
practicable before off-site disposal or develop a materials recovery and
recycling programme during construction and operation). · Submit an
Environmental Management Plan (EMP), which includes the Waste Management Plan
(WMP) to the Engineer for approval. · Implement
a trip-ticket system for each works contract in accordance with DEVB TC(W)
No. 6/2010 to ensure that the disposal of C&D materials are properly documented and verified. · Adopt GPS
or equivalent system for tracking and monitoring of all dump trucks engaged
for the Project in recording their travel routings and parking locations to
prohibit illegal dumping and landfilling of C&D materials. · Handle
chemical waste in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes, and disposal of chemical waste at
licensed chemical waste recycling / treatment facilities. |
· Minimise waste generation · Ensure proper handling of chemical waste · Ensure the C&D materials are disposed to the designated outlets |
Land Contamination
|
· Prior to the commencement of the site investigation (SI) works, review the Contamination Assessment Plan (CAP) provided in Appendix 7.1 and conduct site re-appraisal to confirm whether the proposed SI works (e.g. sampling locations, testing parameters etc.) are still valid, and to confirm the appropriate RBRGs land use scenario for the development. · Should any changes in operation which lead to any new or the relocation of contamination hotspots or occurrence of spillage or accident be found in the review, supplementary CAP(s), presenting the findings of the review, the latest site conditions and updated sampling strategy and testing protocol, should be submitted to EPD for approval. · The SI works should be carried out according to EPD’s approved CAP(s). · Contamination Assessment Report(s) (CAR(s)) should be prepared to present the findings of the SI works and to discuss the presence, nature and extent of contamination. If contamination is identified in the CAR(s), Remediation Action Plan(s) (RAP(s)) which provides details of the remedial actions for the identified contaminated soil and/or groundwater should be developed prior to construction works at the concerned areas. Submission to EPD for approval of the supplementary CAP(s), CAR(s) and, if required, RAP would be carried out in stages according to the programme of TME. · If required, carry out soil/groundwater remediation works according to EPD approved RAP(s) and submit Remediation Report(s) (RR(s)) afterwards for EPD approval. The remediation works should be completed and RR(s) demonstrating the completion of remediation works at the area(s) (if any) confirmed with contamination will be prepared and submitted to EPD for approval prior to the commencement of construction works at the contaminated areas. |
· Land contamination issues could be resolved before commencement of construction works |
Ecology
|
· Control of working hours for noisy construction activities to be conducted within the 100m buffer zone from the ardeid night roost in Tuen Mun Park during construction phase to minimise adverse impacts on the ardeid night roost. · Conduct pre-construction bat survey prior to the felling of Chinese Fan-palm, if any, to verify no existence of bat roosting within the concerned trees to be affected. · Adopt bird-friendly design as mentioned in Section 13.4.4 to avoid bird collision. · Reinstate areas of temporary loss such as reinstatement of landscape areas and compensatory tree planting where applicable. · Adopt noise mitigation measures, glare reduction measures, and dust suppression measures to minimise disturbance impacts to the surrounding habitats and associated wildlife nearby during construction phase. · Reduce glare or excessive lighting with balancing the need to safety during construction and operational phases to minimise unnecessary indirect impacts to the ardeid night roost as far as practicable. · Provide vertical panel on top parapet of viaduct along the eastern side of the viaduct to minimize noise and glare / visual disturbance from railway operation. |
· Avoid direct impact to ardeid night roost in Tuen Mun Park · Minimise the indirect impacts to ecological sensitive receivers during construction and operational phases |
Landscape and Visual
|
· CM1 - Trees unavoidably affected by the works should be transplanted as far as possible in accordance with DEVB TC(W) No. 4/2020 – Tree Preservation. · CM2 - Control of night-time lighting glare to prevent light overspill to the nearby VSRs and into the sky. Relevant best practices as suggested in the "Charter on External Lighting" and “Guidelines on Industry Best Practices for External Lighting Installations” promulgated by ENB shall be adopted. · CM3 - Erection of decorative screen hoarding, or hoarding compatible with the surrounding setting. · CM4 - Management of facilities on work sites which give control on the height and disposition/arrangement of all facilities on the works site to minimise visual impact to adjacent VSRs. · CM5 - All hard and soft landscape areas disturbed temporarily during construction should be reinstated on like-to-like basis, to the satisfaction of the relevant Government Departments. · CM6 - Tree without impact from proposed works should be retained as far as possible in accordance with DEVB TC(W) 4/2020 – Tree Preservation. · OM1 - Aesthetically pleasing design as regard to the form, material and finishes should be incorporated to Entrance, Plant Buildings, Ventilation Shafts and associated engineering facilities so as to blend in the structures to the adjacent landscape and visual context. · OM2 - Tree Planting and shrub planting should be incorporated to provide screening to the Station building, viaduct and associated engineering facilities and serves as roadside amenity planting to provide ornamental value and enhance the landscape character of the streets. · OM3 - Roof greening should be proposed to the roof area of the propose structures as far as practical to enhance the landscape quality of the structures and mitigate any potential visual impact on adjacent VSRs. · OM4 - Roadside soft landscape should be incorporated to the station buildings and associated engineering facilities. Shade tolerant plants with tall to medium height should be planted to under the viaduct to soften the hard building edges and provide screening. · OM5a - Provision of New Open Space for recreational use. · OM5b - Provision of New hard and soft landscape area – provision of street furniture and tree pit planting along the pedestrian as streetscape improvement. · OM6 - Compensatory tree planting should be provided in accordance with DEVB TC(W) 4/2020 – Tree Preservation to compensate for felled trees and maintained until end of the establishment period. Compensatory shrub planting should be provided to compensate for the loss of shrub planting in amenity areas. |
· Minimise landscape and visual impact during construction and operational phases |
Cultural Heritage
|
· If there are any buildings / structures both at grade level and underground which were built on or before 1969 found within the works sites/ works areas during the excavation, the Project Proponent will alert AMO in an early stage or once identified. · The Contractor should inform the AMO in case of discovery of antiquities or supposed antiquities in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with AMO. |
· No impact to cultural heritage resources anticipated |
Hazard to Life
|
· Establishment of emergency response plans. · Provision of safety/ emergency response training and drills for all personnel. · Provision of fire protection equipment. · Maintain the number of construction workers onsite to a minimum. · Implement adequate safety measures and procedures that completely eliminate the possibility of dropping anything into the LPG compound due to hoisting and transportation of precast segments or any other activities. · Restriction of hot work to be conducted in the vicinity of the LPG Store, i.e. works areas ID#9a and #9b. · Construction activities at works areas ID#9a and #9b should be considered to be ceased when testing / examination / inspection of the underground storage tanks are conducted at the LPG Store. · Keep close coordination with the LPG Store’s owner and registered gas supply company on necessary precautionary measures to safeguard the LPG facilities during the construction phase of the Project. In particular, the delivery route and schedule of the LPG road tanker transportation should be fully understood, for preventing any interruption on the LPG delivery. |
· Protect nearby sensitive receivers due to construction works within consultation zone of LPG Store. |