TABLE
OF CONTENTS
2.2 Purpose and Objective of the
Project
2.3 Consideration of
Alternatives/Options
List of tables
Table 2.1 Considerations and Constraints for Alignment
Option Selection
Table 2.2 Comparison of Alignment Options
Table 2.3 Comparison of TRB Scheme Options
Table 2.4 Key Public Views and Corresponding Design
Considerations
Table 2.6 List of Concurrent Projects and Potential
Cumulative Impacts
LIST OF FIGURES
Figure No. |
Title |
Proposed TME Alignment |
|
Proposed Works Areas and Works Sites (Sheet 1 of
2) |
|
Proposed Works Areas and Works Sites (Sheet 2 of
2) |
|
Alignment Options |
|
Locations of Concurrent Projects |
LIST OF Appendices
Vertical Profile of the Alignment |
|
Construction Sequence of Viaduct Section between
TUM and A16 |
|
Construction Programme |
|
|
|
Benefit of the Project
Relieve Traffic
Congestion and Extend Railway Services to Existing and Future Communities
Support Further
Housing Development and Renewal
Develop Long Term
Railway Corridor
Scenario ¡°With¡± the Project
Scenario ¡°Without¡± the Project
Station Locations
Alignment Options
Option A ¨C Base
Scheme
Option B ¨C
Riverside Scheme
Option C ¨C Refined
Base Scheme
Consideration of
Alignment Options
Table 2.1 Considerations
and Constraints for Alignment Option Selection
Considerations
|
Description |
Engineering
Factors |
|
Interface with
Existing / Planned Facilities |
Different
options of the alignment would have different interface issues with the
existing / planned facilities, such as Tuen Mun
Swimming Pool, Tuen Mun River, Tuen
Mun River Promenade area and future Leisure and Cultural Services Department
(LCSD) sports ground. An option
with the least interfacing issues relating to these facilities should be
considered as far as practicable to avoid potential programme implication,
land acquisition and disturbances to the environment. |
Constructability |
¡¤ Practicality in constructing the viaduct and
station structures in the well-developed area; and ¡¤ Difficulty in undertaking
utilities diversion and Temporary Traffic Management Scheme (TTMS) |
Construction /
Operational Safety, Flexibility and Maintenance Requirements |
A number of safety,
flexibility and maintenance requirements in the design and construction of
railway lines constrain certain alignment options. Particular constraints identified included: ¡¤
horizontal curve radius
for a rail track and stations; ¡¤
overrun track allowance; ¡¤
achievement of a
maximum vertical gradient of 3%, with minimum gradients for long lengths of
track to improve energy efficiency; and ¡¤
provision of stabling
sidings. |
Construction
Programme |
Minimisation of construction period. Shorter
construction period is preferred to minimise the disturbance to the
community. |
Environmental
Factors |
|
Construction
Dust |
Minimisation
of construction dust impact. |
Noise |
Minimisation
of construction, railway and fixed plant noise
impacts. |
Terrestrial
Ecology |
Avoid
direct impact and minimise disturbance to sensitive ecological area. |
Water Quality |
Minimisation
of construction activities on Tuen Mun River
Channel. |
Other
Factors |
|
Community Disruption |
The construction works arising from the Project
should be
minimised as far as practicable to minimise the disturbance to the community. |
Table 2.2 Comparison
of Alignment Options
Considerations
|
Option A |
Option B |
Option C (Preferred
Option) |
Engineering Factors |
¡¤ Adverse programme implications as A16
Station and adjacent viaduct construction cannot commence until the
reprovisioned TMSP is completed. |
¡¤ Potential approval issues with Drainage
Services Department (DSD) due to the station to be constructed over the
river. ¡¤ Issue on provision of evacuation access, emergency
vehicular access (EVA) and normal access, as well as impact on the existing
promenade for the station over the water. |
¡¤ A balanced option for Options A and B,
which allows for construction of the southern end of A16 Station while maintaining the operation
of the existing TMSP, and minimising the impact on Tuen
Mun River Channel due to reduced no. of station piers. |
Environmental Factors |
¡¤ Relative lower water quality impact with a smaller number of
piers along Tuen Mun River Channel ¡¤ Relative smaller footprint in the river affected ¡¤ Similar
construction noise and dust issues |
¡¤
Relative higher water quality impact with a larger
number of piers along Tuen Mun River Channel ¡¤ Relative larger footprint in the river affected ¡¤
Similar construction noise and dust issues |
¡¤
Relative
lower water quality impact with relatively smallest
number of piers along Tuen Mun River Channel ¡¤ Relative smaller river area affected ¡¤
Similar construction noise and dust issues |
Other Factors |
¡¤
Relatively longer disruption to general public |
¡¤
Relatively shorter disruption to general public |
¡¤
Relatively shorter disruption to general public |
Bridge Design Option
¡¤
Refined Base Scheme (concrete box
girder similar to standard viaduct);
¡¤
Arch Scheme (steel-composite); and
¡¤
Extradosed Scheme (concrete box with
cables).
Refined Base Scheme
Arch Scheme
¡¤
Two steel arches (both sides of the
deck) that have a parabolic/circular elevation with a maximum rise over the
deck elevation of span length, resulting in a dynamic and relatively flat
rise-to-span ratio.
¡¤
A composite deck (steel and concrete)
consists of two steel edge box edges girders (approximately 3.5m deep) and
transverse floor beams that will support the concrete slab on top.
¡¤
The use of prefabricated steel
components permits significantly expedite the construction schedule and ease
the construction works.
¡¤
The diagonal inclination of the
network arch hangers improves the efficiency and redundancy of the structure
and reduces the dimension of the arch and tied girder, providing steel weight
savings.
¡¤
Network arches have a good resistance
to vibrations due to wind. Harmful effects of vibrations of the hangers due to
wind can be avoided by tying the passing hangers loosely to each other.
¡¤
The piers are proposed to be vertical
for the bowstring arrangement and in concrete to ensure durability and
maintenance.
Extradosed Scheme
¡¤
Provide economical means of crossing
spans of 130 to 150m with new aesthetic opportunities relative to cantilever
constructed girder and cable-stayed bridges.
¡¤
Allow a hybrid design combining the
concepts of a girder bridge (allow depth reduction) and a cable-stayed bridge,
with the girder directly supported by resting on part of towers while
cable-stays acted as prestressing cables for the deck girder.
¡¤
Minimise the pylon dimensions to enable the
stay cables to cross over the pylon, and to help improve structural efficiency
through adoption of an extradosed deviation saddle.
¡¤
Allow variable dimensions in both
longitudinal and transverse directions with minimum dimensions required to
allocate the cable saddles at the upper part.
¡¤
Minimisation of maintenance and fulfil the
durability requirements with use of cast-in situ pylons.
Consideration of
TRB Scheme Options
¡¤
the land-based pile caps to be
embedded below the ground level to minimise the
impact on the existing footpath and cycle path; and
¡¤
consideration of the future and current road alignments
and pedestrian walkways underneath the viaduct to minimise the impact.
Table 2.3 Comparison
of TRB Scheme Options
Considerations |
Refined Base Scheme |
Arch Scheme |
Extradosed Scheme |
Structural Type |
Prestressed concrete box girder |
Double Arch (Bowstring) |
2- Twin Pylon 3 Span |
River Crossing Impact - Intermediate Piers in the
river |
¡Á 4 intermediate piers in the Tuen
Mun River Channel |
¨¹ 2 intermediate piers in the River |
¨¹ 3 intermediate river piers |
Operation Management and Maintenance |
¨¹ Minimal maintenance required (bearings, concrete
repairs) ¨¹ Easy access through the box girder void or
maintenance platforms/ walkways |
¡Á Special equipment/ system required for arch and
cable maintenance ¡Á Re-painting operations required for steel arches
and steel deck elements |
¨¹ Similar maintenance requirements to Refined Base
Scheme ¨¹ Specific provision of access for pylons and saddles
inspection |
Alignment modifications between TMS and A16 |
¨¹ No modifications expected on the alignment due to
the structural form |
¡Á Modifications are expected on the alignment due to
the structural form (track system, overhead line (OHL) centred mast). |
¨¹ No modifications expected on the alignment due to
the structural form (trackside accommodation similar to
Refined Base Scheme) |
Stiffness and Dynamic Performance |
¨¹ Rigid structure |
¡Á More flexible structure compared with balanced
cantilever/extradosed scheme |
¡Á More rigid structure compared with arch scheme |
Constructability |
Balanced Cantilever (Precast) ¨¹
Expedite
schedule and ease of construction as the long-proven viaduct construction
method in Hong Kong ¡Á Off-site yard for segment casting and storage and
the potential logistically constraints to segment delivery ¡Á Special equipment e.g.
segment lifters required for segment erection |
Temporary Supporting Piers in the River ¨¹
Deck
completion in advance to provide working areas for arch erection and cable
installation ¡Á Hydraulic and marine traffic impact during
construction stages ¡Á High quality control on site welding required ¡Á Greater works areas required |
Balanced Cantilever (In-situ) ¨¹
Minimal
site areas required ¨¹
Adaptive to
the special segments at cable and anchorages
locations ¡Á Programme, quality and
safety concern due to the casting operation over the river ¡Á Special equipment required for segment casting |
Environmental Considerations |
¡Á Relatively higher water quality impact due to 4
intermediate piers in Tuen Mun River Channel |
¨¹
Relatively
lower water quality impact due to 2 intermediate piers in Tuen
Mun River Channel |
¨¹
Relatively
lower water quality impact due to 3 intermediate piers in Tuen
Mun River Channel |
Consideration of Construction Methodologies
¡¤
Modification of overrun section at TUM Station;
¡¤
Construction of the viaduct and finishing works;
¡¤
Construction of A16 Station; and
¡¤
Construction of TMS Station.
Modification of Overrun Section at TUM Station
Foundation of the Viaduct
Construction of Pier and Viaduct Structure
Construction of Station
Sequence of Construction Works
Viaduct at Tuen Mun River Channel
A16 Station
Tuen Mun River Bridge
Land-based
Construction of Viaduct
Tuen Mun South Station
Project Alignment
Works Area(s) / Site(s) and Their Locations
Construction Programme
Environmental Design Consideration
Public Views and Consultation
Table 2.4 Key
Public Views and Corresponding Design Considerations
Environmental
Aspect(s) |
Public
Views/Concerns |
Corresponding Design Considerations |
Air Quality and Noise |
¡¤
Potential construction
dust and noise impact during the construction phase of the Project ¡¤
Management approach in
reduction of construction dust and noise impact ¡¤
Potential rail and
fixed plant noise impact to the neighbourhood |
¡¤
Mitigation measures including
dust suppression measures, regular water spraying, quieter construction
methods, adoption of quality power mechanical equipment and temporary
barriers, etc would be adopted as far as practicable during construction
phase. ¡¤
An Environmental Monitoring
and Audit (EM&A) programme would be adopted to monitor the dust and noise
impact for evaluation of effectiveness of adopted mitigation measures, and to
ensure the proper implementation of measures by the contractor(s). ¡¤
Appropriate measures
such as installation of semi-enclosure and acoustic silencer would be adopted
to minimise potential rail and fixed plant noise impact. Commissioning test will be conducted
before operation stage to ensure the compliance of noise level at the noise
sensitive receivers. |
Terrestrial Ecology |
¡¤
Potential impact on Tuen Mun Egretry and its
foraging ground ¡¤
Suggest conducting
ecological survey and impact assessment ¡¤
Loss of foraging
grounds of breeding ardeids ¡¤
Potential impact on
ardeids night roost in Tuen Mun Park |
¡¤
Avoid direct impact on Tuen Mun Egretry and ardeids
night roost in Tuen Mun Park. ¡¤
Minimise the disturbance to ardeids night roost in Tuen
Mun Park through proper construction planning. ¡¤
Works sites/areas at the river bank of Tuen Mun River Channel were minimised as far as
practicable. ¡¤
Ecological survey was
conducted to obtain the baseline condition for evaluation of impact
significancy and recommendation of appropriate mitigation measures ¡¤
Working hours would be controlled to minimise impact on ardeids night roost in Tuen Mun Park. ¡¤
An EM&A programme
would be adopted to monitor the impact on ardeids night roost in Tuen Mun Park for evaluation of
effectiveness of adopted mitigation measures, and to audit the proper
implementation of measures by the contractor(s). ¡¤
Provision of panel at the viaduct section adjoining to the ardeid night
roost to minimise the potential disturbance from night-time railway operation
during night-time period. |
Water Quality |
¡¤
Potential impact to Tuen Mun River Channel |
¡¤
Mitigation measures
including the use of concrete cofferdam, silt curtain and precast pile cap
shell, etc would be implemented during the construction of temporary platform
and pile cap, and piling works. ¡¤
An EM&A programme
would be adopted to monitor the water quality impact for evaluation of
effectiveness of adopted mitigation measures, and to audit the proper
implementation of measures by the contractor(s). |
Landscape |
¡¤
Management approach in
reducing the no. of affected trees |
¡¤
Works sites and works
areas would be clearly demarcated to avoid impact to adjoining landscaping
area. ¡¤
Retained trees would be
properly fenced off and protected. ¡¤
An EM&A programme
would be adopted to audit the effectiveness of adopted mitigation measures as
well as the proper implementation of measures by the contractor(s). |
Visual |
¡¤
Potential visual impact
during construction and operation stages |
¡¤
Mitigation measures
including the control of lighting glare, erection of decorative screen
hoarding and proper tree management throughout the construction stage. ¡¤
During the detailed
design stage, aesthetically pleasing design elements as regard to the form,
material and finishes would be incorporated into the Station Entrances, Plant
Buildings, Ventilation Shafts and associated
engineering facilities so as to blend in the structures to the surrounding
environment. |
Reprovision of Open Space |
¡¤
Programme and location
of reprovisioned pet garden |
¡¤
The Hoi Wong Road Garden (including Pet Garden) will be re-provisioned
adjacent to the Tuen Mun River (Eastern Bank)
Garden, which is about 80m from its original location. ¡¤
MTRCL is exploring appropriate location for temporary re-provision of
the Garden during project construction and will further discuss with relevant
Government on the arrangements. |
Sustainability |
¡¤
Adoption of sustainable
measures at stations |
¡¤
Sustainable building
considerations, such as maximisation of natural ventilation to reduce demand
for air-conditioning, appropriate glazing and/or shading in the façade design
to reduce solar heat gain, allowance for natural daylight penetration to
minimise artificial lighting dependency, onsite renewable energy generation
in the form of photovoltaic panels or micro wind turbines, rainwater
harvesting for landscape planting irrigation, high efficiency potable water
fixtures and dual flush systems to reduce water consumption, would be adopted
in the station design where appropriate and practicable. |
Summary of Environmental Benefits and Environmental Achievements of the Project
Table 2.5 Key Recommended Mitigation Measures / Good Site Practices /
Enhancement Measures and their Associated Benefits
Environmental
Aspect
|
Key Recommended Mitigation Measures / Good Site Practices /
Enhancement Measures
|
Associated Benefits
|
Air Quality
|
¡¤
Implement relevant
control measures as required in the Air Pollution Control (Construction Dust)
Regulation to minimise dust generation. ¡¤
Watering once every
two hours on heavy construction works sites, exposed site surfaces and
unpaved haul roads to reduce dust emission by 91.7%, subject to actual site
condition. ¡¤
Avoid the use of
exempted Non-road Mobile Machineries (NRMMs) and
deploy electrified NRMMs as far as practicable to minimise exhaust emission
from NRMMs during construction phase. |
¡¤ Protect air sensitive receivers by reducing fugitive dust emissions |
Noise
|
¡¤
Adopt quiet
construction method, Quality Powered Mechanical Equipment (QPME), movable
noise barriers, noise insulating fabric, noise enclosures, acoustic measures
(e.g. soundproof hammer bracket for hydraulic
breaker), carefully scheduled construction programme and good site practices
to mitigate the construction noise impact. ¡¤
Provide noise
mitigation measures including noise barriers and noise enclosures to
alleviate the railway noise impact during the operation of the Project. ¡¤
Provide acoustic
measures where necessary for the planned fixed plants to ensure noise
compliance. |
¡¤
Protect noise sensitive
receivers by reducing construction and operational noise |
Water Quality
|
¡¤
Implement the proposed
mitigation measures including installation of casing/concrete cofferdam and
watertight precast pile cap shells to isolate the construction activities
from the river water, use of water pumps to collect any construction site
runoff and ingress/seepage water within the concrete cofferdam and watertight
precast pile cap shells to the on-site wastewater treatment facilities for
treatment to satisfactory levels before discharge, and deployment of silt
curtains to completely enclose the concrete cofferdam/watertight precast pile
cap shells prior to setting up piling works and installation of concrete
cofferdam/watertight precast pile cap shells. ¡¤
Implement the
mitigation measures as detailed in the ProPECCPN
1/94 ¡°Construction Site Drainage¡± and |
¡¤
Protect the neighbouring
Water Sensitive Receivers (WSRs) during construction phase |
Waste
Management Implications
|
¡¤
Implement good site
practices and waste reduction measures (e.g. reuse
of construction and demolition (C&D) materials as far as practicable
before off-site disposal or develop a materials recovery and recycling
programme during construction and operation). ¡¤
Submit an Environmental
Management Plan (EMP), which includes the Waste Management Plan (WMP) to the
Engineer for approval. ¡¤
Implement a trip-ticket
system for each works contract in accordance with DEVB TC(W) No. 6/2010 to
ensure that the disposal of C&D materials are
properly documented and verified. ¡¤
Adopt GPS or equivalent
system for tracking and monitoring of all dump trucks engaged for the Project
in recording their travel routings and parking locations to prohibit illegal
dumping and landfilling of C&D materials. ¡¤
Handle chemical waste
in accordance with the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes, and disposal of chemical waste at licensed
chemical waste recycling / treatment facilities. |
¡¤
Minimise waste
generation ¡¤
Ensure proper handling
of chemical waste ¡¤
Ensure the C&D
materials are disposed to the designated outlets |
Land
Contamination
|
¡¤
Prior
to the commencement of the site investigation (SI) works, review the
Contamination Assessment Plan (CAP) provided in Appendix
7.1 and conduct site re-appraisal to confirm
whether the proposed SI works (e.g. sampling locations, testing parameters
etc.) are still valid, and to confirm the appropriate RBRGs land use scenario
for the development. ¡¤
Should
any changes in operation which lead to any new or the relocation of
contamination hotspots or occurrence of spillage or accident be found in the
review, supplementary CAP(s), presenting the findings of the review, the
latest site conditions and updated sampling strategy and testing protocol,
should be submitted to EPD for approval. ¡¤
The
SI works should be carried out according to EPD¡¯s approved CAP(s). ¡¤
Contamination
Assessment Report(s) (CAR(s)) should be prepared to present the findings of
the SI works and to discuss the presence, nature and
extent of contamination. If
contamination is identified in the CAR(s), Remediation Action Plan(s)
(RAP(s)) which provides details of the remedial actions for the identified
contaminated soil and/or groundwater should be developed prior to
construction works at the concerned areas. Submission to EPD for approval of the
supplementary CAP(s), CAR(s) and, if required, RAP would be carried out in
stages according to the programme of TME. ¡¤
If
required, carry out soil/groundwater remediation works according to EPD
approved RAP(s) and submit Remediation Report(s) (RR(s)) afterwards for EPD
approval prior to the commencement of construction works at the contaminated
areas. |
¡¤
Land contamination
issues could be resolved before commencement of construction works |
Ecology
|
¡¤
Control
of working hours for noisy construction activities to be conducted within the
100m buffer zone from the ardeid night roost in Tuen
Mun Park during construction phase to minimise adverse impacts on the ardeid
night roost. ¡¤
Conduct
pre-construction bat survey prior to the felling of Chinese Fan-palm, if any,
to verify no existence of bat roosting within the concerned trees to be
affected. ¡¤
Adopt
bird-friendly design as mentioned in Section 13.4.4 to avoid bird
collision. ¡¤
Reinstate
areas of temporary loss such as reinstatement of landscape areas and
compensatory tree planting where applicable. ¡¤
Adopt
noise mitigation measures, glare reduction measures, and dust suppression
measures to minimise disturbance impacts to the surrounding habitats and associated
wildlife nearby during construction phase. ¡¤
Reduce
glare or excessive lighting with balancing the need to safety during
construction and operational phases to minimise unnecessary indirect impacts
to the ardeid night roost as far as practicable. ¡¤
Provision
of panel at the viaduct section adjoining to the ardeid night roost to
minimise the potential disturbance from night-time railway operation during
night-time period. |
¡¤
Avoid direct impact to
ardeid night roost in Tuen Mun Park ¡¤
Minimise the indirect
impacts to ecological sensitive receivers during construction and operational
phases |
Landscape and
Visual
|
¡¤
CM1
- Trees unavoidably affected by the works should be transplanted as far as
possible in accordance with DEVB TC(W) No. 4/2020 ¨C Tree
Preservation. ¡¤
CM2
- Control of night-time lighting glare to prevent light overspill to the
nearby VSRs and into the sky.
Relevant best practices as suggested in the "Charter on External
Lighting" and
¡°Guidelines on Industry Best Practices for External Lighting Installations¡±
promulgated by ENB shall be adopted. ¡¤
CM3
- Erection of decorative screen hoarding, or
hoarding compatible with the surrounding setting. ¡¤
CM4 - Management
of facilities on work sites which give control on the height and
disposition/arrangement of all facilities on the works site to minimise
visual impact to adjacent VSRs. ¡¤
CM5
- All hard and soft landscape areas disturbed temporarily during construction
should be reinstated on like-to-like basis, to the satisfaction of the
relevant Government Departments. ¡¤
CM6 - Tree without
impact from proposed works should be retained as far as possible in
accordance with DEVB TC(W) 4/2020 ¨C Tree Preservation. ¡¤
OM1
- Aesthetically pleasing design as regard to the form, material and finishes
should be incorporated to Entrance, Plant Buildings, Ventilation Shafts and associated engineering facilities so as to
blend in the structures to the adjacent landscape and visual context. ¡¤
OM2
- Tree Planting and shrub planting should be incorporated to provide
screening to the Station building, viaduct and associated engineering
facilities and serves as roadside amenity planting to provide ornamental
value and enhance the landscape character of the streets. ¡¤
OM3 - Roof
greening should be proposed to the roof area of the proposed structures as
far as practical to enhance the
landscape quality of the structures and mitigate any potential visual impact
on adjacent VSRs. ¡¤
OM4 - Roadside
soft landscape should be incorporated to the station buildings and associated
engineering facilities. Shade tolerant plants with tall to medium height
should be planted to under the viaduct to soften the hard building edges and
provide screening. ¡¤
OM5a
- Provision
of New Open Space for recreational use. ¡¤
OM5b
- Provision of New hard and soft landscape area ¨C provision of street
furniture and tree pit planting along the pedestrian as streetscape
improvement. ¡¤
OM6
- Compensatory tree planting should be provided in accordance with DEVB TC(W)
4/2020 ¨C Tree Preservation to compensate for felled trees and maintained
until end of the establishment period. Compensatory shrub planting should be
provided to compensate for the loss of shrub planting in amenity areas. |
¡¤ Minimise landscape and visual impact during construction and operational phases |
Cultural
Heritage
|
¡¤
If
there are any buildings / structures both at grade level and underground
which were built on or before 1969 found within the works sites/ works areas
during the excavation, the Project Proponent will alert AMO in an early stage
or once identified. ¡¤
The
Contractor should inform the AMO in case of discovery of antiquities or
supposed antiquities in the course of works, so that appropriate mitigation
measures, if needed, can be timely formulated and implemented in agreement
with AMO. |
¡¤ No impact to cultural heritage resources anticipated |
Hazard to Life
|
¡¤
Establishment
of emergency response plans. ¡¤
Provision
of safety/ emergency response training and drills for all personnel. ¡¤
Provision
of fire protection equipment. ¡¤
Maintain
the number of construction workers onsite to a minimum. ¡¤
Implement
adequate safety measures and procedures that completely
eliminate the possibility of dropping anything into the LPG compound
due to hoisting and transportation of precast segments or any other
activities. ¡¤
Restriction
of hot work to be conducted in the vicinity of the LPG Store, i.e. works areas ID#9a and #9b. ¡¤
Construction
activities at works areas ID#9a and #9b should be
considered to be ceased when testing / examination / inspection of the
underground storage tanks are conducted at the LPG Store. ¡¤
Keep close coordination with the LPG Store¡¯s owner
and registered gas supply company on necessary precautionary measures to
safeguard the LPG facilities during the construction phase of the Project. In
particular, the delivery route and schedule of the LPG road tanker
transportation should be fully understood, for preventing any interruption on
the LPG delivery. |
¡¤ Protect nearby sensitive receivers due to construction works within consultation zone of LPG Store. |
¡¤
Sports Ground and Open Space in Area 16, Tuen Mun;
Table 2.6 List
of Concurrent Projects and Potential Cumulative Impacts
Concurrent
Project |
Programme |
Potential
Cumulative Impact |
||
Start |
Complete |
Construction
Phase |
Operation
Phase |
|
Planned Public Housing Development at Yip Wong Road(1)
|
Foundation Works - May 2020 Building Works - Jun 2021 |
Foundation Works - Jul 2021 Building Works - Dec 2024 |
Construction dust is not anticipated due
to heavy construction works of concurrent project completed before
commencement of the Project. Cumulative construction noise impact
was evaluated in Section 4 of this EIA Report. |
Not anticipated in view of the nature
of the concurrent project. |
Planned Public Housing Development at Hang Fu Street
|
Foundation Works - Oct 2020 Building Works - Dec 2021 |
Foundation Works - Dec 2021 Building Works - Aug 2024 |
Construction dust is not anticipated due
to heavy construction works of concurrent project completed before
commencement of the Project. Cumulative construction noise impact
was evaluated in Section 4 of this EIA Report. |
Not anticipated in view of the nature
of the concurrent project. |
Planned Public Housing Development at Wu Shan Road
|
2022 (Tentative) |
2026 (Tentative) |
Cumulative
construction dust and noise impact was evaluated in Section 3 & Section
4 of this EIA Report respectively. |
Not anticipated in view of the nature
of the concurrent project. |
Planned Property Development
at Area 16, Tuen Mun(1)
|
Under Planning(3) |
Under Planning(3) |
Details of construction programme and
plant inventory is not available during the preparation of this EIA study for
detailed impact assessment. |
Not
anticipated in view of the nature of the concurrent project. |
Reprovision of Tuen Mun Swimming Pool and Tuen Mun Golf Centre Practice Green
|
2023 |
2026 |
Not anticipated due to considerable
separation distance between the Project and this concurrent project. |
Not anticipated in view of the nature
of the concurrent project. |
Reprovision of Pet Garden(1) |
2028 |
2029 |
Cumulative dust and noise impacts were
evaluated in Section 3 and 4 of this EIA Report respectively. |
Not anticipated in view of the nature
of the concurrent project. |
Reprovision of Community Green Station |
2023 |
2024 |
Not
Anticipated due to considerable separation
distance between the Project and this concurrent project. |
Not anticipated in view of the nature
of the concurrent project. |
Sports Ground and Open Space in Area 16, Tuen Mun(1) |
Under Planning |
Under Planning |
Subject to the construction programme of the concurrent project, there may be potential cumulative dust and noise impact. However, details of construction programme and plant inventory is not available during the preparation of this EIA study for detailed impact assessment. |
Not anticipated in view of the nature
of the concurrent project. |
Widening
of Castle Peak Road ¨C Castle Peak Bay |
2020 |
Q2 2024 |
Not
Anticipated due to considerable separation
distance between the Project and this concurrent project. |
Not anticipated in view of the nature
of the concurrent project. |
Tuen Mun Bypass(2) |
Under Planning |
Under Planning |
Subject
to the construction programme of the concurrent project, there may be
potential cumulative dust and noise impact. However, details of construction
programme and plant inventory is not available during the preparation of this
EIA study for detailed impact assessment. |
Not anticipated in view of the nature
of the concurrent project. |
Cycle
Track between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat Section) |
Under detailed design |
Under detailed design |
These current projects are located at
more than 500m from the TME, and thus cumulative impacts are not anticipated. |
Not anticipated in view of the nature
of the concurrent project. |
Traffic
Improvement Scheme in Tuen Mun ¨C Widening and
Addition of Slip Roads at Lung Fu Road/ Tuen Mun
Road/ Wong Chu Road/ Hoi Wing Road |
Under detailed design |
2031 (Tentative) |
Subject to the construction programme
of the concurrent project, there may be potential cumulative dust and noise
impact. However, details of
construction programme and plant inventory is not available during the
preparation of this EIA study for detailed impact assessment. |
Not anticipated in view of the nature
of the concurrent project. |
Remarks:
(1)
The development boundary of
the planned concurrent project falls within the works areas/sites of the
Project.
(2)
https://www.hyd.gov.hk/en/our_projects/road_projects/tmb/index.html.
(3)
The implementation programme of the planned development is still under planning and it is intended to conduct first phase works at
the southern portion of Tuen Mun Swimming Pool in
2028. However, details of
construction programme and plant inventory of advance
works is not available during the preparation of this EIA study for detailed
impact assessment.