TABLE OF CONTENTS

 

 

5         water quality Impact. 5-1

5.1         Introduction. 5-1

5.2         Environmental Legislation, Plans, Standards, and Guidelines. 5-1

5.3         Description of the Environment 5-5

5.4         Water Sensitive Receivers. 5-9

5.5         Assessment Methodologies. 5-10

5.6         Identification and Evaluation of Environmental Impacts. 5-10

5.7         Cumulative Impacts from Concurrent Project 5-14

5.8         Recommended Water Quality Mitigation Measures. 5-14

5.9         Evaluation of Residual Impacts. 5-19

5.10      EM&A Requirements. 5-19

5.11      Conclusions. 5-19

 

 

List of tables

Table 5.1      Summary of Water Quality Objectives for North Western WCZ  5-1

Table 5.2      WSD Standards at Flushing Water Intakes. 5-5

Table 5.3      Summary Statistics of Marine Water Quality of North Western WCZ Collected by EPD in 2020. 5-6

Table 5.4          Summary Statistics of River Water Quality of Tuen Mun River Collected by EPD in 2020. 5-8

 

 

LISTS OF FIGURES

C1502/C/TME/ACM/M53/101

Locations of Water Sensitive Receivers and Water Quality Monitoring Stations (Sheet 1 of 2)

C1502/C/TME/ACM/M53/102

Locations of Water Sensitive Receivers and Water Quality Monitoring Stations (Sheet 2 of 2)

 

 



5                    water quality Impact

5.1               Introduction

5.1.1           This section presents an assessment of the potential water quality impacts associated with construction and operation of the Project. Recommendations for mitigation measures were provided to minimize the identified water quality impacts.

5.2               Environmental Legislation, Plans, Standards, and Guidelines

Environmental Impact Assessment Ordinance (EIAO)

5.2.1           The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) was issued by Environmental Protection Department (EPD) under Section 16 of the EIAO.  It specifies the assessment method and criteria that are to be followed in an EIA Study. Reference sections in the EIAO-TM provide the details of assessment criteria and guidelines that are relevant to the water quality impact assessment, including:

¡¤       Annex 6 ¨C Criteria for Evaluating Water Pollution

¡¤       Annex 14 ¨C Guidelines for Assessment of Water Pollution

 

Water Quality Objective

5.2.2          The Water Pollution Control Ordinance (WPCO) provides the major statutory framework for the protection and control of water quality in Hong Kong.  According to the Ordinance and its subsidiary legislation, Hong Kong waters are divided into ten Water Control Zones (WCZs).  Water Quality Objectives (WQOs) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in the WCZs based on their beneficial uses. The Project site is located within the North Western WCZ. The WQOs for the North Western WCZ are listed in Table 5.1.  These WQOs were used as the water quality assessment criteria for the Project.

Table 5.1     Summary of Water Quality Objectives for North Western WCZ

Parameters

Objectives

Sub-Zone

Aesthetic appearance

(a)   Waste discharges shall cause no objectionable odours or discolouration of the water

Whole zone

(b)   Tarry residues, floating wood, articles made of glass, plastic, rubber or of any other substances should be absent

Whole zone

(c)    Mineral oil should not be visible on the surface. Surfactants should not give rise to a lasting foam

Whole zone

(d)   There should be no recognisable sewage-derived debris

Whole zone

(e)   Floating, submerged and semi-submerged objects or a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be absent

Whole zone

(f)     Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits

Whole zone

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2mg/L for 90% of the sampling occasions during the whole year

Marine waters

Depth-averaged DO

(a)   Waste discharges shall not cause the level of dissolved oxygen to fall below 4mg/L for 90% of the sampling occasions during the whole year

Marine waters

(b)   Waste discharges shall not cause the level of dissolved oxygen to be less than 4mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones and other inland waters

pH

(a)   Within the range of 6.5-8.5 units. Waste discharge shall not cause the natural pH range to be extended by more than 0.2 unit.

Marine waters excepting Bathing Beach Subzones

(b)   Waste discharges shall not cause the pH of the water to exceed the range of 6.5-8.5 units.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

(c)    Within the range of 6.0-9.0 units

Other inland waters

(d)   Within the range of 6.0-9.0 units for 95% of samples collected during the whole year. Waste discharges shall not cause the natural pH range to be extended by more than 0.5 unit.

Bathing Beach Subzones

Salinity

Waste discharges shall not cause the natural ambient salinity level to change by more than 10%

Whole zone

Temperature

Waste discharges shall not cause the natural daily temperature range to change by more than 2.0 degree Celsius.

Whole zone

Suspended solids (SS)

(a)   Waste discharges shall neither cause the natural ambient level to be raised by more than 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities

Marine waters

(b)   Waste discharges shall not cause the annual median of suspended solid to exceed 20mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

(c)    Waste discharges shall not cause the annual median of suspended solid to exceed 25mg/L

Other inland waters

Unionized Ammonia (UIA)

Arithmetic mean should not be more than 0.021 mg/L

Whole zone

Nutrients

(a)   Shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants

Marine waters

(b)   Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.3 mg/L, expressed as annual mean

Castle Peak Bay Subzone

(c)    Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 mg/L, expressed as annual mean

Marine waters excepting Castle Peak Bay Subzone

Bacteria

(a)   The level of E.coli should not exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in a calendar year.

Secondary Contact Recreation Subzones

(b)   The level of E.coli should be less than 1 per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

(c)    The level of E.coli should not exceed 1000 per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Tuen Mun (C) Subzone and other inland waters

(d)   The level of E.coli should not exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive.  Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.

Bathing Beach Subzones

Colour

(a)   Waste discharges shall not cause the colour of water to exceed 30 Hazen units

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

(b)   Waste discharges shall not cause the colour of water to exceed 50 Hazen units

Tuen Mun (C) Subzone and other inland waters

5-Day Biochemical Oxygen Demand (BOD5)

(a)   Waste discharges shall not cause to exceed 3 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

(b)   Waste discharges shall not cause to exceed 5 mg/L

Other inland waters

Chemical Oxygen Demand (COD)

(a)   Waste discharges shall not cause to exceed 15 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

(b)   Waste discharges shall not cause to exceed 30 mg/L

Other inland waters

Toxins

(a)   Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms

Whole zone

(b)   Waste discharges shall not cause a risk to any beneficial use of the aquatic environment

Whole zone

Phenol

Shall not be present in such quantities as to produce a specific odour, or in concentration greater than 0.05 mg/L as C6H5OH

Bathing Beach Subzones

Turbidity

Waste discharges shall not reduce light transmission substantially from the normal level

Bathing Beach Subzones

Source:                  Statement of Water Quality Objectives (North Western Water Control Zone)

 

Technical Memorandum on Effluents Discharge Standards

5.2.3           Discharges of effluents are subject to control under the WPCO.  The ¡°Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters¡± (TM-DSS), issued under Section 21 of the WPCO, gives guidance on permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluent.  Any sewage from the proposed construction and operational activities must comply with the standards for effluent discharged into the foul sewers, inshore waters and marine waters of the North Western WCZ provided in the TM-DSS.

Practice Note

5.2.4           The Professional Persons Environmental Consultative Committee Practice Note on ¡°Construction Site Drainage¡± (ProPECC PN 1/94) published by EPD provides good practice guidelines for dealing with ten types of discharge from a construction site.  These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities.  Guidelines given in ProPECC PN 1/94 should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.

5.2.5           The ¡°Drainage Plans Subject to Comment by the EPD¡± (ProPECC PN 5/93) provides guidelines and practices for handling, treatment and disposal of various effluent discharges to stormwater drains and foul sewers during the operational phase.  The design of site drainage and disposal of various site effluents generated within the new development area should follow the relevant guidelines and practices as given in the ProPECC PN 5/93.

Technical Circular

5.2.6           Environment, Transport and Works Bureau (ETWB) Technical Circular (Works) No. 5/2005 (ETWB TC (Works) No. 5/2005) provides an administrative framework to better protect all natural streams/rivers from the impacts of construction works.  The procedures promulgated under this Circular aim to clarify and strengthen existing measures for protection of natural streams/rivers from government projects and private developments.  The guidelines and precautionary mitigation measures given in the ETWB TC (Works) No. 5/2005 should be followed as far as possible to protect the inland watercourse at or near the Project area during the construction phase.

Hong Kong Planning Standards and Guidelines

5.2.7           The Hong Kong Planning Standards and Guidelines (HKPSG), Chapter 9 (Environment), provides additional guidelines against water pollution for sensitive use such as aquaculture and fisheries zones, bathing waters and other contact recreational waters.

WSD Water Quality Criteria for Flushing Water Intakes

5.2.8          Water Supplies Department (WSD) has established a set of criteria for seawater uptake at flushing water intake points. These requirements are listed in Table 5.2.  These water quality criteria were used as the water quality assessment criteria for the Project.

Table 5.2     WSD Standards at Flushing Water Intakes

Parameters (in mg/L unless otherwise stated)

Water Quality Criteria

Colour (H.U.)

< 20

Turbidity (N.T.U.)

< 10

Threshold Odour No. (T.O.N.)

< 100

Ammoniacal Nitrogen

< 1

Suspended Solids

< 10

Dissolved Oxygen

> 2

Biochemical Oxygen Demand

< 10

Synthetic Detergents

< 5

E. coli (no./100mL)

< 20, 000

 

5.3               Description of the Environment

Assessment Area

5.3.1           The Assessment Area for this water quality impact assessment includes areas within 500 m from the Project boundary including works sites and works areas.  The Assessment Area fall within the North Western WCZ as designated under the WPCO (Cap. 358). The baseline condition of water bodies in the Study Area were established with reference to routine river and marine water quality monitoring data collected by EPD. Descriptions of the baseline conditions provided in the subsequent sections are extracted from the EPD¡¯s reports River Water Quality in Hong Kong in 2020 and Marine Water Quality in Hong Kong in 2020 which contain the latest information published by EPD on river and marine water quality.

Marine Water

5.3.2           The EPD monitoring data collected in 2020 are summarized in Table 5.3 for Pearl Island (NM2) and Tuen Mun Typhoon Shelter (NT1) and the respective locations of these monitoring stations are illustrated in Figure No. C1502/C/TME/ACM/M53/101.  Descriptions of the baseline water quality conditions provided in the subsequent section are based on the EPD¡¯s report Marine Water Quality in Hong Kong in 2020.

5.3.3           The North Western WCZ attained an overall WQO compliance rate of 67%, with the DO and NH3-N WQOs fully met.  The TIN level, however, could not meet the WQO under the influence of high background level in the Pearl River Estuary. Notwithstanding, the red tides occurrence in these waters remained very low even in the presence of rich nutrients, likely owing to strong tidal flushing hindering the proliferation of phytoplankton community in the area.

Table 5.3      Summary Statistics of Marine Water Quality of North Western WCZ Collected by EPD in 2020

Parameters

Pearl Island

Tuen Mun Typhoon Shelter

WPCO WQO

(in marine waters)

NM2

NT1

Temperature

(¡æ)

25.9

(20.5 - 29.4)

26.1

(20.9 - 29.8)

Not cause more than ¡À2¡æ in daily temperature range

Salinity

26.6

(19.8 - 31.6)

26.1

(16.8 - 31.7)

Not to cause more than ¡À10% change

Dissolved Oxygen

(mg/L)

Depth Average

5.8

(4.7 - 7.2)

6.4

(4.8 - 8.2)

Not less than 4 mg/L

Bottom

5.6

(4.0 - 7.5)

6.1

(4.8 - 9.1)

Not less than 2 mg/L

Dissolved Oxygen

(% Saturation)

Depth Average

82

(68 - 104)

91

(69 - 119)

-

Bottom

79

(58 - 108)

87

(69 - 131)

 

pH

7.9

(7.7 - 8.1)

8.0

(7.7 - 8.3)

Marine waters excepting Bathing Beach Subzones: 6.5 - 8.5 (¡À0.2 from natural range)

Bathing Beach Subzones:  6.0 - 9.0 (¡À0.5 from natural range)

Secchi Disc Depth (m)

2.1

(1.7 - 2.6)

1.8

(1.6 - 1.9)

 

Turbidity (NTU)

4.3

(1.9 - 7.8)

5.4

(3.3 - 7.5)

-

Suspended Solids

(mg/L)

7.1

(2.4 - 12.7)

12.1

(4.4 - 21.0)

Not more than 30% increase

5-day Biochemical Oxygen Demand (mg/L)

0.6

(0.3 - 1.0)

1.1

(0.5 - 3.0)

-

Ammonia-nitrogen

(mg/L)

0.076

(0.031 - 0.177)

0.110

(0.055 - 0.195)

-

Unionised Ammonia

(mg/L)

0.003

(0.001 - 0.007)

0.005

(0.002 - 0.007)

Not more than 0.021 mg/L

Nitrite-nitrogen

(mg/L)

0.077

(0.023 - 0.150)

0.062

(0.022 - 0.135)

-

Nitrate-nitrogen

(mg/L)

0.469

(0.157 - 0.757)

0.384

(0.150 - 0.580)

-

Total Inorganic Nitrogen

(mg/L)

0.62

(0.28 - 0.90)

0.56

(0.29 - 0.69)

Castle Peak Bay Subzone: Not more than 0.3 mg/L

Marine waters excepting Castle Peak Bay Subzone: Not more than 0.5 mg/L

Total Kjeldahl Nitrogen

(mg/L)

0.32

(0.07 - 0.62)

0.43

(0.28 - 0.68)

 

Total Nitrogen

(mg/L)

0.87

(0.57 - 1.08)

0.88

(0.59 - 1.03)

-

Ortho-phosphate

(mg/L)

0.022

(0.015 - 0.033)

0.014

(0.012 - 0.015)

-

Total phosphorus

(mg/L)

0.08

(0.03 - 0.24)

0.06

(0.05 - 0.07)

-

Silica (as SiO2) (mg/L)

2.59

(0.54 - 4.27)

2.28

(0.51 - 4.25)

 

Chlorophyll-a

(µg/L)

3.8

(0.5 - 22.3)

7.9

(1.1 - 33.0)

-

E. coli

(cfu/100mL)

36

(13 - 140)

110

(12 - 730)

Secondary Contact Recreation Subzones: Annual geometric mean not to exceed 610 cfu/100mL

Bathing Beach Subzones: Geometric mean of March to October samples not to exceed 180 cfu/100mL

Faecal Coliforms

(cfu/100mL)

87

(24 - 590)

850

(110 - 18000)

-

Notes:

1.    Data source: EPD Marine Water Quality in Hong Kong in 2020

2.    Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: surface, mid-depth and bottom.

3.    Data presented are annual arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.

4.    Data in brackets indicate the ranges.

Inland Water

5.3.4           The water quality monitoring results at EPD¡¯s river water quality monitoring stations at Tuen Mun River, TN3, TN5 and TN6, are shown in Table 5.4 and the locations of these stations are illustrated in Figure No. C1502/C/TME/ACM/M53/101. According to the EPD¡¯s publication River Water Quality in Hong Kong in 2020, the compliance rate of Tuen Mun River was 84% in 2020.

5.3.5           All industrial discharges are controlled under the WPCO. Discharges from domestic and commercial premises are connected to public sewers. Construction of a trunk sewer to the west of Tuen Mun River was completed in 2015. The Water Quality Index (WQI) gradings for the upper Tuen Mun River was rated ¡°Bad¡±, mainly due to discharges from unsewered rural areas. The WQI gradings for the middle and lower river sections maintained at ¡°Good¡± in 2020. Given that Tuen Mun River is still affected by effluents discharged from unsewered villages especially in the upstream areas and expedient connections, sewerage works for villages are being planned and progressively implemented.

Table 5.4     Summary Statistics of River Water Quality of Tuen Mun River Collected by EPD in 2020

Parameters

Tuen Mun River

WPCO WQO

(in inland waters)

TN3

TN5

TN6

Dissolved Oxygen

(mg/L)

4.4

(3.1 - 6.6)

4.9

(2.8 - 6.3)

4.9

(3.3 - 9.1)

Not less than 4 mg/L

pH

7.5

(7.3 - 7.8)

7.6

(7.4 - 7.9)

7.6

(6.2 - 8.4)

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones: Within the range of 6.5-8.5

Other inland waters: Within the range of 6.0-9.0

Suspended Solids

(mg/L)

8.3

(2.5 - 19.0)

8.0

(2.2 - 25.0)

6.7

(2.6 - 9.0)

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones: Annual median not to exceed 20 mg/L

Other inland waters: Annual median not to exceed 25 mg/L

5-Day Biochemical Oxygen Demand (mg/L)

4.5

(2.2 - 15.0)

3.3

(1.8 - 9.4)

3.1

(2.1 - 6.8)

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones: Not to exceed 3 mg/L

Other inland waters: Not to exceed 5 mg/L

Chemical Oxygen Demand (mg/L)

15

(12 - 32)

12

(8 - 23)

12

(4 - 35)

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones: Not to exceed 15 mg/L

Other inland waters: Not to exceed 30 mg/L

Oil & Grease (mg/L)

<0.5

(<0.5 - <0.5)

<0.5

(<0.5 - <0.5)

<0.5

(<0.5 - <0.5)

-

E.coli (counts/100mL)

9,300

(1,100 - 60,000)

7,000

(300 - 57,000)

3,400

(10 - 55,000)

Tuen Mun (A), Tuen Mun (B) Subzones and Water Gathering Ground Subzones: Not to exceed 1 cfu/100mL

Tuen Mun (C) Subzones and other inland waters: Not to exceed 1000 cfu/100mL

Faecal Coliforms (counts/100mL)

91,000

(6,400 - 3,000,000)

50 000

(2,000 - 550,000)

36,000

(490 - 630,000)

-

Ammonia-Nitrogen (mg/L)

0.495

(0.160 - 1.100)

0.585

(0.220 - 0.930)

0.470

(0.110 - 1.000)

-

Nitrate-nitrogen

(mg/L)

0.320

(0.160 - 0.650)

0.340

(0.180 - 0.680)

0.350

(0.120 - 0.700)

-

Total Kjeldahl Nitrogen (mg/L)

1.05

(0.43 - 1.50)

1.25

(0.45 - 2.20)

0.95

(0.27 - 1.70)

-

Ortho-Phosphate

(mg/L)

0.037

(0.007 - 0.057)

0.035

(0.007 - 0.063)

0.035

(0.017 - 0.054)

-

Total phosphorus

(mg/L)

0.11

(0.07 - 0.17)

0.12

(0.06 - 0.13)

0.11

(0.05 - 0.19)

-

Sulphide

(mg/L)

<0.02

(<0.02 - <0.02)

<0.02

(<0.02 - <0.02)

<0.02

(<0.02 - 0.02)

-

Aluminium

(µg/L)

<50

(<50 - 173)

<50

(<50 - 81)

<50

(<50 - 254)

-

Cadmium

(µg/L)

<0.1

(<0.1 - <0.1)

<0.1

(<0.1 - 0.1)

<0.1

(<0.1 - <0.1)

-

Chromium

(µg/L)

2

(<1 - 3)

2

(<1 - 3)

2

(<1 - 3)

-

Copper

(µg/L)

4

(1 - 8)

4

(1 - 7)

5

(2 - 7)

-

Lead

(µg/L)

<1

(<1 - <1)

<1

(<1 - <1)

<1

(<1 - <1)

-

Zinc

(µg/L)

11

(<10 - 25)

13

(<10 - 19)

11

(<10 - 27)

-

Flow

(m3/s)

NM-

NM

NM

-

Remarks:

1.      Data source: EPD River Water Quality in Hong Kong in 2020

2.      Data presented are in annual medians of monthly samples; except those for faecal coliforms and E. coli which are in annual geometric means

3.      Figures in brackets are annual ranges

4.      cfu ¨C colony forming unit

5.      Values at or below laboratory reporting limits are presented as laboratory reporting limits

6.      Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits.

7.      NM indicates no measurement taken

5.4               Water Sensitive Receivers

5.4.1           Water sensitive receivers (WSRs) within 500m from the Project site boundary are identified and listed below:

¡¤       Tuen Mun River Channel (WSR1);

¡¤       Tuen Mun Typhoon Shelter (WSR2);

¡¤       Secondary contact recreation subzone (WSR3); and

¡¤       Tuen Mun flushing water intake (WSR4).

5.4.2           The indicative locations of these WSRs are shown in Figure No. C1502/C/TME/ACM/M53/101. The WSRs of the offsite Mong Wing Street works area site boundary are shown in Figure No. C1502/C/TME/ACM/M53/102.  The offsite works area is currently used as site office for the project ¡°Tuen Mun - Chek Lap Kok Link (TM-CLKL)¡±, to support the construction of the Project.  This works area would be handed over by Highways Department in 2024 tentatively.   This offsite works area will only be used as site office, material storage for pre-cast unit (non-dusty material) and temporary tree nursery, and there would be no excavation works, earthworks and stockpiling of dusty materials to be conducted at this works area.

5.5               Assessment Methodologies

5.5.1           The assessment area includes all areas within 500 m from the Project boundary including works site and works area, and covers relevant WSRs that have a bearing on the environmental acceptability of the Project within the North Western WCZ.  The methodology employed to assess potential water quality impacts associated with the construction and operation of the Project followed the detailed technical requirements given in Appendix D of the Study Brief.  The WSRs that may be affected by the Project were identified.  Potential sources of water quality impact that may arise during the construction works and operation activities were described and quantified, where applicable, including point discharges and non-point sources to surface water runoff, sewage from workforce and polluted discharge generated from the Project.  All the identified sources of potential water quality impact were then evaluated and their impact significance determined.  The need for mitigation measures to reduce any identified adverse impacts on water quality to acceptable levels was also determined.

5.6               Identification and Evaluation of Environmental Impacts

Construction Phase

5.6.1           No open sea dredging would be involved for construction of the Project.  The potential sources of water quality impact associated with the construction of the Project include:

¡¤       Construction works at Tuen Mun River Channel;

¡¤       General construction activities;

¡¤       Construction site runoff;

¡¤       Construction works in close proximity to inland water;

¡¤       Accidental spillage of chemicals;

¡¤       Sewage effluent from construction workforce; and

¡¤       Groundwater from Contaminated Areas, Contaminated Site Runoff and Wastewater from Land Decontamination.

 

Construction Works at Tuen Mun River Channel

5.6.2           The construction of pier and viaduct structure across Tuen Mun River would require the installation of new piers in Tuen Mun River.  Pier installation would involve pilling and minor excavation activities in Tuen Mun River, which may lead to elevated suspended solids (SS) levels and dispersion of SS to the downstream section of the river if in contact with river water.  However, according to the proposed design as discussed in Section 2, concrete cofferdams will be erected at Tuen Mun River and thereafter dewatering will be conducted inside the cofferdam to create a dry working zone for the construction of temporary steel platform and/or watertight casing.  Piles will then be constructed within the watertight casing with piling rigs on barge or temporary steel platforms.  Upon the completion of pile cap construction, the cofferdams will be removed to maintain the water flow within Tuen Mun River.  Water pumps would be used to collect any construction site runoff and ingress/seepage water within the concrete cofferdam/watertight casing.  The collected construction site runoff and ingress/seepage water would be diverted to the on-site wastewater treatment facilities for treatment to satisfactory levels before discharge.  Adoption of the proposed construction method not only enables safe and secured working area on water, but also provides cleaner, dry and tidier working environment.

5.6.3           The pier construction would be conducted in phases at the embankment during dry seasons.  Since the cross-section area of the river channel to be blocked by the pier installation was anticipated localized and temporary, the change in flow regime would be localized and any local water quality impact would expect to be transient.  As a result, the potential impact on water quality and hydrology of Tuen Mun River would be insignificant, no unacceptable water quality would be expected if the mitigation measures detailed in Section 5.8 are implemented properly.

General Construction Activities

5.6.4           Wastewater generated from construction activities, including general cleaning and polishing, wheel washing, dust suppression, concreting works and utility installation may contain high SS concentrations.  It may also contain a certain amount of grease and oil.  Potential water quality impacts due to the wastewater discharge can be minimised if construction and site management practices are implemented to ensure that litter, fuels, and solvents do not enter public drainage systems.  It is expected that if the good site practice suggested in Section 5.8 are followed as far as practicable, the potential water quality impacts associated with construction activities would be minimal.

Construction Site Runoff

5.6.5           Surface runoff generated from the construction site may contained increased loads of SS and contaminants.  Potential pollution sources of site runoff may include:

¡¤       Runoff and erosion of exposed bare soil and earth, drainage channel, earth working area and stockpiles;

¡¤       Release of any bentonite slurries, concrete washings and other grouting materials with construction runoff or storm water;

¡¤       Wash water from dust suppression sprays and wheel washing facilities; and

¡¤       Fuel, oil and lubricants from maintenance of construction vehicles and equipment.

5.6.6           During rainstorms, site runoff would wash away the soil particles on unpaved lands and areas with the topsoil exposed.  The construction runoff is generally characterized by high concentrations of SS.  Release of uncontrolled site runoff would increase the SS levels and turbidity in the nearby water environment.  Site runoff may also wash away contaminants and therefore cause water pollution.

5.6.7           Windblown dust would be generated from exposed soil surfaces in the works sites.  It is possible that windblown dust would fall directly onto the nearby water bodies when a strong wind occurs.  Dispersion of dust within the works sites may increase the SS levels in surface runoff causing a potential impact to the nearby sensitive receivers.

5.6.8           However, it is anticipated that with the implementation of appropriate measures to control runoff and drainage from the construction site, disturbance of water bodies would be avoided and deterioration in water quality would be minimal.  Thus, unacceptable impacts on the water quality are not expected, provided that the relevant mitigation measures as specified in Section 5.8 are properly implemented.

Construction Works in Close Proximity to Inland Water

5.6.9           Pollution of inland waters may occur due to potential release of construction wastewater from the adjacent construction works area.  Construction wastewater are generally characterized by high concentration of SS and elevated pH.  Adoption of good housekeeping and mitigation measures would reduce the generation of construction wastes and potential water quality impact.  The implementation of measures to control site run-off and drainage water will be adopted for the construction works adjacent to the inland water in order to prevent run-off and drainage water with high levels of SS from entering the water environment.  With the implementation of adequate construction site drainage and Best Management Practices as described in Section 5.8 and provision of mitigation measures as specified in ETWB TC (Works) No. 5/2005 ¡°Protection of natural streams / rivers from adverse impacts arising from construction works¡± as detailed in Section 5.8, it is anticipated that water quality impacts would be minimised.

Accidental Spillage of Chemicals

5.6.10        The use of chemicals such as engine oil and lubricants, and their storage as waste materials has the potential to create impacts on the water quality if spillage occurs and enters adjacent water environment.  Waste oil may infiltrate into the surface soil layer, or runoff into the nearby water environment, increasing hydrocarbon levels.  The potential impacts could however be mitigated by practical mitigation measures and good site practices (as given in Section 5.8).

Sewage Effluent from Construction Workforce

5.6.11        During the construction of the Project, the workforce on site will generate sewage effluents, which are characterized by high levels of BOD, ammonia and E. coli counts. Based on the DSD Sewerage Manual, the sewage production rate for construction workers is estimated at 0.35 m3 per worker per day.  For every 100 construction workers working simultaneously at the construction site, about 35 m3 of sewage would be generated per day. Potential water quality impacts upon the local drainage and fresh water system may arise from these sewage effluents, if uncontrolled.

5.6.12        However, this temporary sewage can be adequately treated by interim sewage treatment facilities, such as portable chemical toilets. Provided that sewage is not discharged directly into storm drains or inland waters adjacent to the construction site, temporary sanitary facilities would be used and properly maintained, and mitigation measures as recommended in Section 5.8 are adopted as far as practicable, it is unlikely that sewage generated from the sites would have a significant water quality impact. 

Groundwater from Contaminated Areas, Contaminated Site Runoff and Wastewater from Land Decontamination

5.6.13        It is identified that some of the works sites might have land contamination issues.  Proper land contamination remediation and mitigation measures are proposed in Section 7.  Any contaminated material disturbed, or material which comes into contact with the contaminated material, has the potential to be washed with site runoff into watercourses and drainage system.  Any wastewater discharge from land decontamination processes could also adversely affect the nearby water environment.  Excavated contaminated materials would be properly stored, housed and covered to avoid generation of contaminated runoff. Open stockpiling of contaminated materials will not be allowed. Any contaminated site runoff and wastewater from land decontamination activities will be properly treated and disposed in compliance with the requirements of the TM-DSS.  Mitigation measures for contaminated site runoff and wastewater from land decontamination are recommended in Section 5.8.  With proper implementation of the recommended mitigation measures, the potential water quality impacts arising from the land decontamination works would be minimised. 

5.6.14        Groundwater pumped out or from dewatering process during excavation works in the contaminated areas would be potentially contaminated. Any contaminated groundwater will be either properly treated or properly recharged into the ground in compliance with the requirements of the TM-DSS. No direct discharge of contaminated groundwater will be adopted. Mitigation measures and monitoring requirements for contaminated groundwater discharge / recharge are recommended in Section 5.8. With proper implementation of the recommended mitigation measures, no unacceptable water quality would be expected from the groundwater generated from contamination areas.

Operational Phase

5.6.15        Potential sources of water quality impact associated with the operation of the Project include:

¡¤       Sewage and wastewater effluents from stations;

¡¤       Non-point source surface run-off from new impervious areas including viaduct; and

¡¤       Hydrodynamic and water quality impact on Tuen Mun River Channel.

Sewage and Wastewater Effluents from stations

5.6.16        Sewage effluent from the staff and passengers at A16 and TMS Stations would be connected to the existing foul sewerage system.  Runoff from cleaning activities at the stations which would enter floor drains would also be connected to the foul sewer. Hence, no adverse water quality impact is anticipated to arise from sewage and wastewater effluents generated during the operation of the stations.

Non-point source surface run-off from new impervious areas

5.6.17        Surface runoff to be generated from the Project is known as non-point source pollution.  A small amount of grease and grit may be deposited on the surfaces of the rail tracks on viaduct and these pollutants could be washed into the nearby drainage system during rainfall events. Surface runoff generated from the paved areas of stations may also contain debris, refuse, dust from the roof of buildings and cleaning agents used for washing station façade, which may also affect the quality of the nearby receiving water environment, if uncontrolled.

5.6.18        An additional paved area of about 2.71 ha is anticipated to generate surface runoff when in operation and the surface runoff collected from the paved areas of viaduct and stations would be conveyed to the existing public drainage system. 

5.6.19        According to the ¡°DSD Stormwater Drainage Manual (5th edition)¡±, annual rainfall in Hong Kong is around 2,400mm.  However, the EPD study namely "Update on Cumulative Water Quality and Hydrological Effect of Coastal Developments and Upgrading of Assessment Tool (Update Study)¡± suggested that only rainfall events of sufficient intensity and volume would give rise to runoff and that runoff percentage is about 44% and 82% for dry and wet season, respectively.  Therefore, only 1,512mm of 2,400mm annual rainfall would be considered as effective rainfall that would generate runoff (i.e. 1,512mm=2,400mm¡Á(82%+44%)/2). 

5.6.20        More surface runoff would be generated from the paved area than from the unpaved area.  Making reference to the ¡°DSD Stormwater Drainage Manual¡±, about 0.9 as the runoff coefficient for paved areas is assumed.  The average daily runoff generated from the additional paved area is estimated to be about 101.0m3/day (= 0.9 ¡Á 1,512mm/year ¡Á 2.71ha).  The hydrology and flow regime impacts, if any, would be limited and localized due to about 101.0 m3/day surface runoff will be generated, and hence no adverse impacts would be expected.

5.6.21        Storm water control measures including Best Management Practices (BMPs), would be implemented within the development site as described in Sections 5.8.28 to 5.8.33.  It is expected that with proper implementation of the recommended measures, the water quality impact due to the non-point source pollution from the Project would be minimized.

Hydrodynamic and water quality impact on Tuen Mun River Channel

5.6.22        The permanent pier structures of the Project in Tuen Mun River Channel has potential to obstruct the river flow.  Based on preliminary design, the total area of permanent structures including pile caps and piers would be about 340 m2 in Tuen Mun River Channel.  The percentage of the total area of permanent structures within the 500m assessment area of the Tuen Mun River Channel is estimated to be less than 0.2%.  It is therefore considered that the area of the river channel to be blocked by the piers was anticipated small, the change in flow regime would be insignificant and any local water quality impact would expect to be acceptable. 

5.7               Cumulative Impacts from Concurrent Project

5.7.1           The construction of the Project potentially overlap with the construction period of other nearby concurrent projects as identified in Section 2.5.  However, with incorporation of the recommended mitigation measures during the construction and operational phases of the Project, the water quality impact generated from the Project would be localized and no adverse cumulative water quality impacts would be expected.

5.8               Recommended Water Quality Mitigation Measures

Construction Phase

Construction of Piers in Tuen Mun River

5.8.1           The pilling works should be conducted by phases.  The method and sequence of the proposed pier works in Tuen Mun River should be carefully designed so that wastewater and sediment laden water generated from the pilling works would be confined and physically separated from the watercourse.

5.8.2           All pilling, the associated excavation works and construction of pile caps in river should be fully enclosed by casing/concrete cofferdam/watertight precast pile cap shells.  Concrete cofferdam and watertight precast pile cap shells should be constructed to isolate the construction activities from the river water.  The detail design of the concrete cofferdams and watertight precast pile cap shells will be conducted by the Contractor during the construction phase to fulfil the requirements in DSD Technical Circular No. 1/2017 "Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater System" for DSD approval in order to formulate feasible options of these temporary structure.

5.8.3           Water pumps should be used to collect any construction site runoff and ingress/seepage water within the concrete cofferdam and watertight precast pile cap shells.  The collected construction site surface runoff and ingress/seepage water should be diverted to the on-site wastewater treatment facilities for treatment to satisfactory levels before discharged.  Discharge licence issued by the EPD for discharging effluent from the construction site under the WPCO is needed.  The discharge quality and quantity must meet the requirements specified in the discharge licence and follow the TM-DSS.

5.8.4           To further minimize any adverse water quality impact during the pilling and excavation works, silt curtains should be deployed to completely enclose the concrete cofferdam/watertight precast pile cap shells prior to setting up piling works and installation of concrete cofferdam/watertight precast pile cap shells.  Silt curtains should only be removed after completion of pilling works and removal of concrete cofferdam/watertight precast pile cap shells.  The Contractor should be responsible for the design, installation and maintenance of the silt curtain to minimize the impacts on water quality.  The design and specification of the silt curtains should be submitted by the Contractor to the Project Engineer for approval.

Construction Site Runoff and General Construction Activities

5.8.5           Control of potential pollution of nearby water bodies during the construction phase of the Project should be achieved by measures to:

¡¤       prevent or minimise the likelihood of pollutants (generated from construction activities) being in contact with rainfall or runoff; and

¡¤       abate pollutants in the stormwater surface runoff prior to the discharge of surface runoff to the nearby water bodies.

5.8.6           It is important that Best Management Practices (BMPs) of mitigation measures in controlling water pollution and good site management, as specified in the ProPECC PN 1/94 ¡°Construction Site Drainage¡± are followed, where applicable, to prevent runoff with high level of SS from entering the surrounding waters.

5.8.7           All effluent discharged from the construction site should comply with the standards stipulated in the TM-DSS. The measures discussed below are recommended to protect water quality of the inland and coastal waters, and when properly implemented should be sufficient to adequately control site discharges so as to avoid water quality impacts.

5.8.8           Surface runoff from construction sites should be discharged into storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sedimentation basins.  Channels or earth bunds or sand bag barriers should be provided on site during construction works to properly direct stormwater to such silt removal facilities.  Perimeter channels should be provided on site boundaries where necessary to intercept storm runoff from outside the site so that it will not wash across the site. Catchpits and perimeter channels should be constructed in advance of site formation works and earthworks.

5.8.9           Silt removal facilities, channels and manholes should be maintained and the deposited silt and grit should be removed regularly, at the onset of and after each rainstorm to prevent local flooding.  Any practical options for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements in order to provide adequate hydraulic capacity of all drains. 

5.8.10        Construction works should be programmed to minimize soil excavation works in rainy seasons (April to September) as far as practicable.  If soil excavation cannot be avoided in these months or at any time of year when rainstorms are likely, for the purpose of preventing soil erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds.  Intercepting channels should be provided (e.g. along the crest / edge of excavation) to prevent storm runoff from washing across exposed soil surfaces.  Arrangements should always be in place in such that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.

5.8.11        Earthworks final surfaces should be well compacted and the subsequent permanent work or surface protection should be carried out immediately after the final surfaces are formed to prevent erosion caused by rainstorms.  Appropriate drainage like intercepting channels should be provided where necessary.

5.8.12        Measures should be taken to minimize the ingress of rainwater into trenches. If excavation of trenches in wet seasons is necessary, they should be dug and backfilled in short sections.  Rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.

5.8.13        If bentonite slurries are required for any construction works, they should be reconditioned and reused wherever practicable to minimise the disposal volume of used bentonite slurries.  Temporary enclosed storage locations should be provided on-site for any unused bentonite that needs to be transported away after the related construction activities are completed. Requirements as stipulated in ProPECC Note PN 1/94 should be closely followed when handling and disposing bentonite slurries.

5.8.14        Open stockpiles of construction materials (e.g. aggregates, sand and fill material) on sites should be covered with tarpaulin or similar fabric. 

5.8.15        Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris from getting into the drainage system, and to prevent storm runoff from getting into foul sewers.  Discharge of surface runoff into foul sewers must always be prevented in order not to unduly overload the foul sewerage system.

5.8.16        Good site practices should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from the site area.  It is recommended to clean the construction sites on a regular basis.  Also, as discussed in Section 6.4.21 and 6.4.22, the following mitigation measures related to the transportation of the sediment should be implemented to minimize the potential water quality impact:

¡¤       Loading of the excavated sediment to the barge should be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.

¡¤       The barge transporting the sediments to the designated disposal sites should be equipped with tight fitting seals to prevent leakage and should not be filled to a level that would cause overflow of materials or laden water during loading or transportation.  

¡¤       Monitoring of the barge loading should be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels should be equipped with automatic self-monitoring devices as specified by the Director of Environmental Protection (DEP). 

5.8.17        Discharge licence issued by the EPD for discharge of effluent from the construction site under the WPCO is needed.  The discharge quality and quantity must meet the requirements specified in the discharge licence.  All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS.  The beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., can minimise water consumption and reduce the effluent discharge volume.  If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the relevant WPCO licence.

Construction Works in Close Proximity to Inland Water

5.8.18        The practices outlined in ETWB TC (Works) No. 5/2005 ¡°Protection of natural streams / rivers from adverse impacts arising from construction works¡± should also be adopted where applicable to minimise the water quality impacts on any natural streams or surface water systems.  Relevant mitigation measures from the ETWB TC (Works) No. 5/2005 are listed below:

¡¤       The use of less or smaller construction plants may be specified in works area close to the inland water bodies.

¡¤       Temporary storage of material (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from watercourses when carrying out of the construction works.

¡¤       Stockpiling of construction materials and dusty materials should be covered and located away from any watercourses.

¡¤       Construction debris and spoil should be covered up and / or disposed of as soon as possible to avoid being washed into the nearby water receivers.

¡¤       Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the watercourses, where practicable.

¡¤       Construction effluent, site run-off and sewage should be properly collected and / or treated.

¡¤       Proper shoring may need to be erected in order to prevent soil / mud from slipping into the inland water bodies.

Accidental Spillage of Chemicals

5.8.19        Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities.  The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation, should be observed and complied with for control of chemical wastes.  The Contractor is also recommended to develop management procedures for chemicals used and prepare an emergency spillage handling procedure to deal with chemical spillage in case of accident occurs.

5.8.20        Any service shop and maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided.  Maintenance of vehicles and equipment involving activities with potential leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

5.8.21        Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance.  The ¡°Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes¡± published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes.  General requirements are given as follows:

¡¤       Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

¡¤       Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

¡¤       Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

Sewage Effluent from Construction Workforce

5.8.22        No discharge of sewage to the storm water system and marine water will be allowed.  Adequate and sufficient portable chemical toilets should be provided in the works areas to handle sewage from construction workforce.  A licensed waste collector should be employed to clean and maintain the chemical toilets on a regular basis.

5.8.23        Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the surrounding environment.  Regular environmental audit of the construction site should be conducted to provide an effective control of any malpractices and achieve continual improvement of environmental performance on site.  It is anticipated that sewage generation during the construction phase of the project would not cause water pollution problem after undertaking all required measures.

Groundwater from Contaminated Areas, Contaminated Site Runoff and Wastewater from Land Decontamination

5.8.24        Remediation of contaminated land, if any, should be properly conducted following the recommendations of Land Contamination Assessment to be conducted in future. Any excavated contaminated material and exposed contaminated surface should be properly housed and covered to avoid generation of contaminated runoff. Open stockpiling of contaminated materials should not be allowed.  Any contaminated runoff or wastewater generated from the land decontamination processes should be properly collected and diverted to wastewater treatment facilities (WTF).  The WTF should deploy suitable treatment processes (e.g. oil interceptor / activated carbon) to reduce the pollution level to an acceptable standard and remove any prohibited substances (such as total petroleum hydrocarbon) to an undetectable range.  All treated effluent from the wastewater treatment system should meet the requirements as stated in TM-DSS and should be either discharged into the foul sewers or tankered away for proper disposal.

5.8.25        No direct discharge of groundwater from contaminated areas should be adopted.  Prior to any excavation works within the potentially contaminated areas, the baseline groundwater quality in these areas should be reviewed based on the past relevant site investigation data and any additional groundwater quality measurements to be performed with reference to Guidance Note for Contaminated Land Assessment and Remediation and the review results should be submitted to EPD for examination. If the review results indicated that the groundwater to be generated from the excavation works would be contaminated, this contaminated groundwater should be either properly treated or properly recharged into the ground in compliance with the requirements of the TM-DSS.  If wastewater treatment is to be deployed for treating the contaminated groundwater, the wastewater treatment unit should deploy suitable treatment processes (e.g. oil interceptor / activated carbon) to reduce the pollution level to an acceptable standard and remove any prohibited substances (such as total petroleum hydrocarbon) to an undetectable range. All treated effluent from the wastewater treatment plant should meet the requirements as stated in the TM-DSS and should be either discharged into the foul sewers or tankered away for proper disposal.

5.8.26        If deployment of wastewater treatment is not feasible for handling the contaminated groundwater, groundwater recharging wells should be installed as appropriate for recharging the contaminated groundwater back into the ground. The recharging wells should be selected at places where the groundwater quality will not be affected by the recharge operation as indicated in section 2.3 of TM-DSS.  The baseline groundwater quality should be determined prior to the selection of the recharge wells.  Pollution levels of groundwater to be recharged should not be higher than pollutant levels of ambient groundwater at the recharge well. Groundwater monitoring wells should be installed near the recharge points to monitor the effectiveness of the recharge wells and to ensure that no likelihood of increase of groundwater level and transfer of pollutants beyond the site boundary. Prior to recharge, free products should be removed as necessary by installing the petrol interceptor.  The Contractor should apply for a discharge licence under the WPCO through the Regional Office of EPD for groundwater recharge operation or discharge of treated groundwater.

Operational Phase

Sewage and Wastewater Effluents discharge

5.8.27        All sewage and wastewater effluents generated from operation of the stations should be properly collected and diverted to public sewers for proper treatment and disposal.  No direct discharge of sewage and wastewater effluents into the storm drains or inland/marine waters will be allowed.

Stormwater Runoff

5.8.28        Best Management Practices (BMPs) for stormwater discharge are recommended to reduce stormwater pollution arising from the Project.  Details are as follows:

Design Measures

5.8.29        Exposed surface should be avoided to minimise soil erosion.  The Site should be either hard paved or covered by landscaping area and plantation where appropriate.

5.8.30        The drainage system should be designed to avoid flooding. The drainage system will be designed to avoid any case of flooding based on at least 1 in 50 year return period.

Devices and Facilities

5.8.31        Screening facilities such as standard gully grating and trash grille, with spacing which is capable of screening large substances such as fallen leaves and rubbish should be provided at the inlet of drainage system. 

5.8.32        Silt traps and oil interceptors should be incorporated as appropriate during the detailed design to remove particles and oil present in stormwater runoff, where appropriate. 

Administrative Measures

5.8.33        Good management measures such as regular cleaning and sweeping of road surface / open areas are suggested.  Manholes and stormwater gullies provided at the Project sites should be regularly inspected and cleaned (e.g. monthly).  Additional inspection and cleansing should be carried out before forecast heavy rainfall. 

Hydrodynamic and water quality impact on Tuen Mun River Channel

5.8.34        No significant change in flow regime and water quality associated with operation of the Tuen Mun South Extension is anticipated.  No adverse hydrodynamic and water quality impacts would therefore be expected during the operational phase and no mitigation measures are considered necessary.

5.9               Evaluation of Residual Impacts

5.9.1           With the full implementation of the recommended mitigation measures for the construction and operational phases of the proposed Project, no adverse residual impact on water quality are anticipated.

5.10            EM&A Requirements

5.10.1        It is recommended that regular water quality monitoring and site inspections during the construction phase should be undertaken to inspect the construction activities and works sites / areas in order to ensure the recommended mitigation measures are properly implemented.  Details of the audit requirements are provided in the stand-alone EM&A Manual for the Project.

5.11            Conclusions

Construction Phase

5.11.1        The potential water quality impacts from the construction works are associated with the construction works at Tuen Mun River and in close proximity to inland water, wastewater generated from general construction activities, construction site run-off, groundwater from contaminated areas and contaminated site runoff, accidental spillage of chemicals and sewage effluent from construction workforce.  Provided that proper site management practices and the mitigation measures including adequate construction site drainage, provision of sediment removal facilities, practical groundwater control measures and chemical toilets would be implemented, no adverse water quality impact during construction phase would be anticipated.

Operational Phase

5.11.2        The key potential source of water quality impact during operational phase would be related to non-point source stormwater runoff, sewage and wastewater effluents from stations, and potential hydrodynamic and water quality impact on Tuen Mun River due to the installation of pier structure.  Adequate drainage system should be provided to collect the stormwater runoff.  All sewage and wastewater generated from the Project should be properly collected and diverted to public sewers for proper treatment and disposal.  With proper design of drainage and sewerage systems and implementation of the recommended mitigation measures, the associated water quality impacts are expected to be minimal and acceptable.  No significant change in flow regime and water quality associated with the proposed piers is expected.  Therefore, no adverse water quality impact during operational phase would be anticipated.