TABLE OF CONTENTS

 

 

6         waste management implications. 6-1

6.1         Introduction. 6-1

6.2         Environmental Legislation, Standards and Guidelines. 6-1

6.3         Identification and Evaluation of Wastes Implications. 6-4

6.4         Mitigation of Adverse Environmental Impacts. 6-12

6.5         Evaluation of Residual Environmental Impacts. 6-18

6.6         Environmental Monitoring and Audit Requirement 6-18

6.7         Conclusion. 6-18

 

 

List of tables

Table 6.1      Summary of Inert and non-inert C&D Materials Quantities Generated  6-6

Table 6.2      Changes in Sampling Location ID.. 6-8

Table 6.3      Summary of Chemical Screening Results. 6-10

Table 6.4      Summary of Biological Screening Results. 6-10

Table 6.5      Estimated Quantities of Sediment under each Disposal Option  6-11

Table 6.6      Waste Arising, Waste Handling Procedures and Disposal Outlets  6-16

 

 

LIST OF FIGURES

Figure C1502/C/TME/ACM/M54/101

The Proposed Sediment Sampling Locations for Land-based Sediment and the Preferred Alignment

Figure C1502/C/TME/ACM/M54/102

Proposed Sediment Sampling Locations for River-based Sediment and the Preferred Alignment

Figure C1502/C/TME/ACM/M54/103

As-built Sediment Sampling Locations for Land-based Sediment

Figure C1502/C/TME/ACM/M54/104

As-built Sediment Sampling Locations for River-based Sediment

 

LIST OF appendiCES

Appendix 6.1         Sediment Sampling and Testing Plan (SSTP) January 2021

Appendix 6.2         Memo on Control Measures for Management of Dredged/Excavated Contaminated Sediment

Appendix 6.3         Summary of Chemical Screening Results and Disposal Options

Appendix 6.4         Summary of Biological Screening Results

Appendix 6.5         Laboratory Analytical Report (Chemical Screening)

Appendix 6.6         Laboratory Analytical Report (Biological Screening)

Appendix 6.7         Details of Sediment Quantity Estimation

Appendix 6.8         Tentative Transportation Routings

 



6                    waste management implications

6.1                Introduction

6.1.1           This section identifies the types of wastes that are likely to be generated during the construction and operation phases of the Project, and evaluates the potential environmental impacts that may result from handling, transport and disposal of the wastes.

6.1.2           Mitigation measures and good site practices, including waste handling, storage, collection and disposal, have been recommended with reference to the applicable waste legislation and guidelines.  Handling and disposal of sediments are also discussed in this section.

6.2                Environmental Legislation, Standards and Guidelines

6.2.1           The criteria and guidelines for assessing waste management implications are outlined in Annex 7 and 15, respectively, of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

6.2.2           The following legislation, which has been used in assessing potential impacts, relates to the handling, treatment and disposal of wastes in the Hong Kong SAR:

      Waste Disposal Ordinance (Cap. 354);

      Waste Disposal (Chemical Waste) (General) Regulation (Cap.354C);

      Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap.354N);

      Land (Miscellaneous Provisions) Ordinance (Cap.28);

      Public Health and Municipal Services Ordinance (Cap.132) (PHMSO) and  Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK);

      Dumping at Sea Ordinance (Cap. 466); and

      Buildings Ordinance (Cap 123).

 

Waste Disposal Ordinance (Cap. 354)

6.2.3           The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes. Construction waste, defined under Cap. 354N of the WDO means any substance, matter or thing that is generated from construction works and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works.  Under WDO, waste should be disposed of at designated waste disposal facilities licensed by the Environmental Protection Department (EPD).

Waste Disposal (Chemical Waste) (General) Regulation (Cap.354C)

6.2.4           Issued under the WDO, the Chemical Waste (General) Regulation administers the possession, storage, collection, transport and disposal of chemical wastes.  EPD has also issued three &guideline* documents, namely A Guide to the Chemical Waste Control Scheme (2016), A Guide to the Registration of Chemical Waste Producers (2016) and Code of Practice on the Packaging, Labelling and Storage of chemical Wastes (1992), which detail how the Contractor should comply with the regulations on chemical wastes.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap.354N)

6.2.5           Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material.  Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a Public Fill Reception Facility (PFRF) for disposal must consist entirely of inert material.

Land (Miscellaneous Provisions) Ordinance (Cap. 28)

6.2.6           The inert portion of Construction and Demolition (C&D) materials (including rocks, soil, broken concrete, building debris, etc.) may be taken to PFRFs.  PFRFs usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the PFRFs are required to obtain Dumping Licences. The licences are issued by CEDD under delegated authority from the Director of Lands.

6.2.7           Individual licences and windscreen stickers are issued for each vehicle involved.  Under the licence conditions, PFRFs will only accept soil, sand, rubble, brick, tile, rock, boulder, concrete, asphalt, masonry or used bentonite. In addition, in accordance with paragraph 12 of the Development Bureau (DevB) Technical Circular (Works) TC(W) No.6/2010, Public Fill Committee (PFC) will advise on the acceptance criteria.  The material will, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the public fill reception facility supervisor.

Public Health and Municipal Services Ordinance (Cap. 132) and Public Cleansing and Prevention of Nuisances Regulation (Cap.132BK)

6.2.8           The PHMSO and Public Cleansing and Prevention of Nuisances Regulation provides control on illegal dumping of wastes on unauthorised (unlicensed) sites. The illegal dumping of wastes can lead to a fine and/or imprisonment.

Dumping at Sea Ordinance (Cap.466)

6.2.9           The Dumping at Sea Ordinance (DASO) came into operation in April 1995 and empowers the Director of Environmental Protection (DEP) to control the disposal and incineration of substances and particles at sea for the protection of the marine environment.  Under the Ordinance, a dumping permit from the DEP is required for the disposal of regulated substances within and outside the waters of Hong Kong.  The permit contains terms and conditions which include the following specifications:

      Type and quantity of substances permitted to be dumped;

      Location of the disposal grounds;

      Requirement of equipment for monitoring the disposal operations; and

      Environmental monitoring requirements.

6.2.10        Marine disposal of any dredged/excavated sediment is subject to control under the DASO.  Dredged/excavated sediment destined for marine disposal is classified based on its contaminant levels with reference to the Practice Notes for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers No. 252 ADV-21 - Management Framework for Disposal of Dredged/Excavated Sediment (PNAP No. 252 (ADV-21)).  The PNAP No. 252 (ADV-21) stipulated a set of sediment quality criteria or Chemical Exceedance Levels (CEL) for contaminants including metals, metalloid and organic pollutants.  

Buildings Ordinance (Cap.123)

6.2.11        Private projects are regulated by the Buildings Ordinance and relevant Practice Notes for Authorised Persons, Registered Structural Engineers and Registered Geotechnical Engineers (PNAPs). The PNAP No. 243 (ADV-19) Construction and Demolition Waste has introduced waste prevention measures to enhance the management of C&D materials which include:

      Identifying opportunities to prevent waste during project planning and design stage and construction stage; and

      Requiring the contractor to prepare a Waste Management Plan (WMP) including areas described in PNAP No. 243 (ADV-19) and submit to the project proponent for agreement. 

Environmental Guidelines

6.2.12        Environmental guidelines that are related to waste management and disposal include:

      Works Branch Technical Circular (WBTC) No. 2/93, Public Dumps;

      Works Branch Technical Circular No. 2/93B, Public Filling Facilities;

      Section 4.1.3 of Chapter 4 of the Project Administration Handbook (PAH) for Civil Engineering Works, Management of Construction/Demolition Materials including Rocks;

      PNAP No. 252 (ADV-21) 每 Management Framework for Disposal of Dredged/Excavated Sediment;

      PNAP No. 243 (ADV-19) 每 Construction and Demolition Waste; and

      DevB TC(W) No. 6/2010, Trip-ticket System for Disposal of Construction and Demolition Materials.

6.2.13        The current policy related to the disposal of C&D materials is documented in the WBTC No. 2/93, &Public Dumps*. C&D materials that are wholly inert, namely public fill, should not be disposed of at landfill, but be taken to PFRFs, which usually form part of reclamation schemes. 

6.2.14        In accordance with the DevB TC(W) No. 6/2010 &Trip Ticket System for Disposal of Construction and Demolition Materials*, all contracts that are expected to generate inert C&D materials (e.g. soil, broken rock, broken concrete and building debris, etc.) requiring disposal from site, the project office shall write to the PFC through Secretary of the PFC to request a designated disposal ground for incorporation into the tender documents.  For contracts where the estimated amount of non-inert C&D materials requiring disposal at landfill facilities equal or exceed 50m3, the project office shall seek confirmation from the DEP in terms of the availability of landfill facilities for disposal of such materials.  The DEP will designate landfill facilities, if available, for the contract.  Where the estimated amount of non-inert C&D materials to be generated from the contract is less than 50m3, the project office is not required to apply to DEP for designated landfill facilities.  However, the project office should still specify in the tender documents of the appropriate landfill facilities for disposal.

6.2.15        Further measures have been introduced under Paragraph 4.1.3 of Chapter 4 of the PAH for Civil Engineering Works to enhance the management of C&D materials including rock, and to minimize its generation at source. The enhancement measures include:

      Drawing up a Construction and Demolition Materials Management Plan (C&DMMP) at an early design stage to minimize C&D materials generation and to encourage proper management of such materials; and

      Providing the contractor with information from the C&DMMP in order to facilitate the preparation of Waste Management Plan (WMP) and to minimize C&D materials generation during construction.

6.2.16        Measures have been introduced in PNAP No. 243 (ADV-19) to enhance the management of C&D materials and to minimize its generation at source.  The enhancement measures include the identification of opportunities to prevent waste during both the project planning and design stage as well as construction stage, and preparation of a Waste Management Plan (WMP) to ensure that measures are implemented during the construction stage for reduction of C&D materials.

6.2.17        The PNAP No. 252 (ADV-21) sets out the procedure for seeking approval to and the management framework for marine disposal of dredged/excavated sediment.  This Practice Note outlines the requirements to be followed in assessing and classifying the sediment and explains the marine disposal arrangement for the classified material. The sediment quality criteria for the classification of sediment were referred as the Lower Chemical Exceedance Level (LCEL) and Upper Chemical Exceedance Level (UCEL). The LCEL and UCEL are presented in Appendix A of PNAP No. 252 (ADV-21). Subject to the results of the chemical screening, biological screening may be required to determine the disposal requirement of the sediment.  There are three types of disposal options for dredged / excavated sediments stipulated in the PNAP No. 252 (ADV-21):

      Type 1 每 Open Sea Disposal or Open Sea Disposal in Dedicated Sites;

      Type 2 每 Confined Marine Disposal; and

      Type 3 每 Special Treatment / Disposal.  For Type 3 disposal, the Authorized Persons / Registered Structural Engineers shall be responsible for identifying and agreeing with the DEP the most appropriate treatment and/or disposal arrangement. 

6.3                Identification and Evaluation of Wastes Implications

Assessment Methodology

6.3.1           The criteria and methodology of assessing potential waste management implications during the construction and operation phases follows Annexes 7 and 15 of the EIAO-TM, respectively.  Appendix E of the EIA Study Brief (No. ESB-332/2020) also specifies the requirements for assessment of waste management implications.   Assessment approaches are discussed below:

      Identification and estimation of the types, quantities, qualities and timing of the wastes generated;

      Evaluation of opportunities for waste reduction, re-use and recycling;

      Identification of disposal options for each type of wastes;

      Assessment of potential environmental impacts arising from the waste management with respect of potential hazards, air and odour emissions, noise, wastewater discharges and public transport;

      Assessment of impacts on the capacity of waste collection, transfer and disposal facilities; and

      Identification of practicable means of avoiding illegal dumping and landfilling.

Construction Phase

6.3.2           The construction activities to be carried out for the Project would generate a variety of wastes that can be divided into distinct categories based on their composition and ultimate method of disposal. The following wastes types are anticipated to be generated:

      Construction and demolition (C&D) materials;

      General refuse;

      Chemical wastes; and

      Land-based and river-based sediments.

Construction and Demolition Materials

6.3.3           C&D materials would be generated from excavation, demolition works, site formation, piling works, and construction of facilities and stations. These C&D materials comprise both inert (e.g. rocks, soil, broken concrete, building debris) and non-inert components (e.g. vegetation and wood).

6.3.4           In view of site constraints, scale and nature of the Project, the available schemes for construction of the Project are limited, generation of C&D materials has been minimized as far as possible with the following measures taken in consideration:

      Minimal interference with existing structures as far as possible to reduce the quantity of demolition materials;

      Maximisation in the use of prefabricated materials where possible; and

      Reuse of excavated materials where possible.

6.3.5           Based on preliminary design information, it was estimated that the total volume of C&D materials to be approximately 97,202 m3 of inert materials and approximately 27,930 m3 of non-inert materials.  

6.3.6           A summary of inert and non-inert C&D materials generated during construction phase is shown in Table 6.1.  Due to limited space of Project site, it may not be practicable to provide a major stockpile area of inert C&D materials for subsequent backfilling or reuse on site.  As such, only small stockpile area(s) could be provided on-site for temporary storage before delivery to disposal outlets.  Inert C&D materials would be reused on-site as far as practicable subject to the review of detailed design stage before exported off-site for reuse at other concurrent projects.  Surplus inert C&D materials generated from the Project would be delivered to the Tuen Mun Area 38 Fill Bank which is being operated by CEDD.


 

Table 6.1    Summary of Inert and non-inert C&D Materials Quantities Generated

Works

Construc-tion Period

Approx. Quantities of Waste To be Generated (m3)

Soft Inert Materials(1)

Grade III Rock(2)

Artificial Hard Material(3)

Non-inert C&D Material(4)

A16, Viaduct & TRB

2023 每 2027

55,776

3,207

15,340

23,640

TMS

2024 每 2026

7,009

350

15,520

4,290

Total Generation

62,785

3,557

30,860

27,930

Disposal Outlet

Tuen Mun Area 38 Fill Bank or reclamation sites

Tuen Mun Area 38 Fill Bank or reclamation sites

Tuen Mun Area 38 Fill Bank or reclamation sites

Designated Landfill Site such as WENT landfill to be agreed with EPD/CEDD

Notes:

(1)    ※Soft Inert Materials§ include fill, alluvium, colluvium, Grade IV to Grade VI (Granite) and Grade IV to Grade VI (Volcanic).

(2)    ※Grade III Rock§ includes Grade III granite rock and Grade III volcanic rock.

(3)    ※Artificial hard material§ includes, but not limited to, asphalt, broken concrete, bitumen and granular materials, etc.

(4)    ※Non-inert C&D material§ includes, but not limited to, bamboo, timber, paper and plastic, etc.

 

6.3.7           Non-inert C&D materials generated would be reused and recycled as much as possible before disposal of at designated landfill site (e.g. WENT landfill) to be agreed with EPD/CEDD. 

6.3.8           The number of construction vehicle involved in transporting C&D materials/land-based sediment to the disposal outlets is estimated to be about 12 nos. per day, 8am to 6pm, throughout the construction phase, based on the current engineering design.  Upon leaving the construction site, construction vehicles will enter Wu King Road, Wu Chui Road, Wong Chu Road, Lung Fu Road / Lung Mun Road via local roads (Appendix 6.8 refers) and ultimately to the designated disposal outlets (Table 6.1 refers) as agreed with EPD/CEDD during construction phase. It is expected that the potential environmental impacts arising from the handling and disposal of the inert C&D materials, such as air and odour emissions, noise and potential hazard, could be minimized with the implementation of appropriate measures as detailed in Section 6.4.

General Refuse

6.3.9           During the construction period, the workforce would generate refuse comprising food scraps, waste paper, empty containers, etc.  Proper disposal, storage of general refuse on-site and regular cleaning of waste containers are crucial in preventing environmental impacts such as water pollution, odour nuisance, visual impacts, vermin and pests infestation.

6.3.10        The maximum number of construction workers to be employed on the Project is estimated to be about 350 workers in each stage.  Based on a generation rate of 0.65 kg per worker per day, approximately 228 kg of general refuse will be generated daily during the construction period.

6.3.11        The refuse should be stored in enclosed bin to avoid adverse impacts to the surroundings. Recycling bins should be provided to maximize reuse and recycle volume.  A reputable waste collector should be employed to collect the general refuse for later disposal of at designated landfills (e.g. WENT landfill) to be agreed with EPD/CEDD.

6.3.12        With proper implementation of waste management practices as detailed in Section 6.4, it is anticipated that the secondary environmental impacts from collection and handling of general refuse would be minimal.

Chemical Waste

6.3.13        The maintenance and servicing of construction plant and equipment may possibly generate a variety of chemical wastes, for instance, cleaning fluids, solvents, lubrication oil, waste fuel, etc. 

6.3.14        Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations.  The potential hazards include:

      Toxic effects on the workforce;

      Adverse impacts on water quality and aquatic biota from spills; and

      Fire hazards.

6.3.15        Chemical waste producers are required to apply for registration as specified in the Guide to the Registration of Chemical Waste Producers. Materials classified as chemical wastes will be handled and stored on-site according to the requirements specified in Code of Practice on Packaging, Labelling and Storage of Chemical Wastes before collection by licensed collectors and disposal of at the Chemical Waste Treatment Centre (CWTC) at Tsing Yi or other licensed facilities.  Wherever possible, opportunities will be taken to reuse and recycle materials.  It is difficult to quantify the amount of chemical waste that would arise from the construction activities since it would depend on the Contractor*s on-site maintenance requirements and the amount of plant utilised.  However, it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance, would be small to in the order of a few hundred litres per month.   Mitigation and control requirements for chemical wastes are detailed in Section 6.4 Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts are not expected.

Excavated Sediments

6.3.16        The Project is situated on reclaimed land and Tuen Mun River.  Based on previous ground investigation (GI) records, land-based and river-based sediment is expected within the Project area and maybe encountered during the piling and excavation works associated with the construction of the piers and columns for the viaducts and stations.

6.3.17        Pursuant to Appendix E, 3(i) of ESB-332/2020, a Sediment Sampling and Testing Plan (SSTP) was prepared with reference to PNAP No. 252 (ADV-21) and submitted to EPD for approval. This Plan details the ranges of parameters to be analysed; the number, type and methods of sampling; sample preservation; chemical and biological laboratory test methods to be used.

6.3.18        The nearest EPD*s sediment monitoring station is NS5 located within the Tuen Mun Typhoon Shelter. The latest available sediment quality data from 2016 to 2020 are summarised in the Annual Marine Water Quality Report 2020 published by EPD. Based on the EPD*s annual report, the measured concentrations of the parameters, except for silver, zinc, arsenic and lead, as listed in PNAP No. 252 (ADV-21) were below the corresponding Lower Chemical Exceedance Level (LCEL).  For zinc, arsenic and lead, the highest levels measured (zinc: 260 mg/kg, arsenic: 14 mg/kg and lead: 89 mg/kg) were above the corresponding LCEL but below the UCEL. For silver, the arithmetic mean value (1.4 mg/kg) had exceeded the LCEL but below the UCEL and the highest level measured (9.7 mg/kg) was above the UCEL.

6.3.19        As contaminants exceeding the LCEL / UCEL were identified in the EPD monitoring data, a 200m x 200m sampling grid arrangement with reference to the memo ※Control Measures for Management of Dredged/Excavated Contaminated Sediment§ issued by Development Bureau (ref: 0 in DEVB(W) 515/83/04) (Appendix 6.2 refers) would be suffice.  However, in order to refine the sediment profile and quantities estimation, a more stringent 100 x 100m sampling grid arrangement, as recommended in PNAP No. 252 (ADV-21) for expected high sediment contamination level, was proposed.

6.3.20        Based on the adopted sampling grid arrangement, a total of 32 sampling locations (16 land-based and 16 river-based) were proposed according to the proposed alignment options during the course of the study.  For the remaining areas within the Scheme Boundary, either no excavation works or only shallow excavation above the sediment layer and no excavation of sediment is anticipated.  The SSTP as agreed by the EPD on 29 January 2021 are enclosed in Appendix 6.1.  After the agreement on the SSTP sought, the preferred alignment had been selected for the EIA study.  A review of validity of SSTP has been conducted and it was confirmed that the proposed sediment sampling locations remain valid for the preferred alignment.  The proposed sampling locations and the preferred alignment are shown in Figure Nos. C1502/C/TME/ACM/M54/101 - 102.  

6.3.21        Site investigation (SI) was conducted between March and August 2021 according to the agreed SSTP. The sampling works were conducted by Tysan Foundation Limited and Lam Geotechnical Limited, while the laboratory testing was carried out by ALS Technichem (HK) Pty. Ltd., which is an HOKLAS accredited laboratory.

6.3.22        The sediment sampling locations were conducted taken into consideration the site constraints within the Scheme Boundary (e.g. presence of existing road traffic / structures / facilities / utilities).  It should be noted that minor changes were made to the sampling location IDs after EPD*s agreement on the SSTP. The changes are shown in Table 6.2 below and are adopted in the remaining part of this section. The as-built sampling locations are shown in Figure Nos. C1502/C/TME/ACM/M54/103 - 104. 

Table 6.2      Changes in Sampling Location ID 

Sampling Location ID Proposed in SSTP

As-built Sampling Location ID

Land-based

1530-TME-EDH203

1530-TME-EDH501

1530-TME-EDH204

1530-TME-EDH502

1530-TME-EDH205(P)

1530-TME-EDH503(P)

1530-TME-EDH306

1530-TME-EDH504

1530-TME-EDH206

1530-TME-EDH505

1530-TME-EDH207

1530-TME-EDH506

1530-TME-EDH315

1530-TME-EDH507

1530-TME-EDH116

1530-TME-EDH508

1530-TME-EDH210(P)

1530-TME-EDH509

1530-TME-EDH227(P)

1530-TME-EDH510(P)

1530-TME-EDH213

1530-TME-EDH511

1530-TME-EDH215

1530-TME-EDH512

1530-TME-EDH117

1530-TME-EDH513

River-based

1530-TME-MEDH203

1530-TME-MEDH601

1530-TME-MEDH117

1530-TME-MEDH602

1530-TME-MEDH105

1530-TME-MEDH603

1530-TME-MEDH106

1530-TME-MEDH604

1530-TME-MEDH107

1530-TME-MEDH605

1530-TME-MEDH108

1530-TME-MEDH606

1530-TME-MEDH109

1530-TME-MEDH607A

1530-TME-MEDH110

1530-TME-MEDH608

1530-TME-MEDH111

1530-TME-MEDH609

1530-TME-MEDH112

1530-TME-MEDH610

1530-TME-MEDH113

1530-TME-MEDH611A

1530-TME-MEDH114

1530-TME-MEDH612

1530-TME-MEDH115

1530-TME-MEDH613

1530-TME-MEDH116

1530-TME-MEDH614

 

6.3.23        The land-based sediment sampling was carried out using borehole drilling method. Sediment was collected using U100 sampler at depths where marine deposits are firstly encountered and samples were generally taken at that particular depth (i.e. top level of marine deposit), 0.9m down, 1.9m down, 2.9m down and then every 3m down to the borehole termination depth. The depth of sediment sampling was terminated at least 1m below the base of sediment.

6.3.24        The river-based sediment sampling was carried out by means of grab sampling using closed grab sampler at the riverbed level and borehole drilling method for the vertical sediment profiles below.  The sediment below the riverbed level was collected using U100 sampler at depths where marine deposits were firstly encountered and samples were generally taken at that particular depth (i.e. top level of marine deposit), 0.9m down, 1.9m down, 2.9m down and then every 3m down to the borehole termination depth. The depth of sediment sampling was terminated at least 1m below the base of sediment.

6.3.25        Upon completion of the SI works, a review on the sediment quality of the sediment sampling and testing works were conducted, making reference to PNAP No. 252 (ADV-21) and memo issued by Development Bureau ※Control Measures for Management of Dredged/Excavated Contaminated Sediment§ (ref: 0 in DEVB(W) 515/83/04) (Appendix 6.2 refers), to identify and characterize the excavated sediment, estimate the quantity of sediment to be encountered in the Project and propose transportation routings and handling/disposal arrangements/methods to fulfill the requirements of ESB-332/2020.

6.3.26        Grab sediment sample was collected from EPD*s routine sediment monitoring station PS6 at Port Shelter (850234E, 820057N) on 14 April 2021 as the reference sediment sample using closed grab sampler.

Sediment Sampling and Testing Results

6.3.27        Chemical and biological screening of sediment samples were carried out and each sample was tested for chemical screening according to PNAP No. 252 (ADV-21).

6.3.28        Of the 32 sampling locations, 10 sampling locations (viz. 1530-TME-EDH506, 1530-TME-EDH109(P), 1530-TME-EDH508, 1530-TME-EDH513, 1530-TME-MEDH101, 1530-TME-MEDH102, 1530-TME-MEDH601, 1530-TME-MEDH607A, 1530-TME-MEDH610 and 1530-TME-MEDH611A) did not encounter sediment and as such, no sediment samples were collected and tested from these locations.

6.3.29        A total of 56 samples were collected from the remaining 22 land-based and river-based sampling locations and tested for chemical screening. The chemical screening results are summarised in Table 6.3 with details provided in Appendix 6.3.  The laboratory analytical reports for chemical screening are provided in Appendix 6.5.

6.3.30        Based on the chemical screening results, Category H sediments were identified in 5 samples at sampling locations 1530-TME-EDH501, 1530-TME-EDH505, 1530-TME-EDH114, 1530-TME-MEDH613 and 1530-TME-MEDH614 with lead / zinc exceeded the UCEL but below 10 times the LCEL.  Category M sediments were also found in 6 samples at sampling locations 1530-TME-EDH504, 1530-TME-EDH505, 1530-TME-EDH507, 1530-TME-MEDH613 and 1530-TME-MEDH614 with arsenic / copper / lead / low molecular weight polycyclic aromatic hydrocarbons (LMW PAHs) exceeded the LCEL but equal to or below the UCEL. The remaining samples were identified as Category L sediment.

Table 6.3      Summary of Chemical Screening Results 

Category

Percentage

No. of Samples

Category L (equal to or below LCEL)

80.4%

45

Category M (above LCEL but equal to or below UCEL)

10.7%

6

Category H (above UCEL but equal to or below 10x LCEL)

8.9%

5

Category H (above 10x LCEL)

0%

0

Total:

100%

56

 

6.3.31        Based on the chemical screening results, Tier III biological screening was conducted on the 6 Category M sediment samples and all the samples passed the screening. The results of the biological screening are summarised in Table 6.4 with details provided in Appendix 6.4.  The laboratory analytical reports for biological screening are provided in Appendix 6.6.

Table 6.4     Summary of Biological Screening Results

Sampling ID

Sampling

Depth (m bgl)

Classification

Result of Biological Screening

1530-TME-EDH504

15.90 每 16.90

Category M

Pass

1530-TME-EDH505

11.00 每 12.00

Category M

Pass

1530-TME-EDH507

17.10 每 18.10

Category M

Pass

1530-TME-EDH507

19.10 每 20.10

Category M

Pass

1530-TME-MEDH613

1.00 每 1.95

Category M

Pass

1530-TME-MEDH614

0.50 每 0.95

Category M

Pass

Sediment Disposal Options and Quantities

6.3.32        Based on the screening results and the above findings, the disposal options for each of the sediment samples were determined in accordance with the PNAP No. 252 (ADV-21). The quantities of sediments to be generated under each disposal option is then estimated with consideration of (i) the proposed piling works for the viaduct and stations, (ii) the depths and thickness of the underlying sediment and (iii) the determined disposal options of the sediment samples as based on the chemical and biological screening results.  The total volume of sediment generated is estimated to be approximately 2,840 m3.  Beneficial reuse will be considered on site as far as practicable during the construction stage before the disposal of excavated sediment.  Based on current estimation, the quantities for each disposal type are presented in Table 6.5.  Detailed calculation of excavated sediment quantities and assumptions are presented in Appendix 6.7.

6.3.33        It should be noted that no sediment were encountered in sampling locations 1530-TME-EDH109(P), 1530-TME-EDH506, 1530-TME-EDH508, 1530-TME-EDH513, 1530-TME-MEDH101, 1530-TME-MEDH102, 1530-TME-MEDH601, 1530-TME-MEDH607A, 1530-TME-MEDH610 and 1530-TME-MEDH611A. It is assumed that no sediment would be encountered within the concerned sampling grid in the quantity estimation.

Table 6.5      Estimated Quantities of Sediment under each Disposal Option

Disposal Option

Corresponding Category

Estimated In-situ Quantity(1),(2) (m3)

Type 1 每 Open Sea Disposal

Category L Sediment

2,088

Type 1 每 Open Sea Disposal (Dedicated Sites) at disposal site(s) allocated by MFC

Category M Sediment (passed the biological screening)

433

Type 2 每 Confined Marine Disposal at disposal site(s) allocated by MFC

Category H Sediment (does not require biological screening)

319

Type 3 每 Special Treatment/ Disposal

Category H Sediment (failed biological screening)

0

Total

2,840

Notes:

(1)    The quantities shown in the table are estimates only based on the piling works for current scheme of TME and the possibility of reusing excavated sediment will be subject to further review during the detailed design and construction stages.

(2)    The estimated quantities included marine deposits only and excluded other materials such as fill and alluvium.

6.3.34        The SSTP, testing results and disposal option presented above are to fulfill the EIA Study under the EIAO. Separate submissions of SSTP and Sediment Quality Report (SQR) for the application of dumping permit under the DASO should be submitted to Marine Dumping Control Section of EPD in accordance with PNAP No. 252 (ADV-21).

6.3.35        The sediment would be disposed of at the designated marine disposal areas according to PNAP No. 252 (ADV-21).  The disposal options for the excavated sediment should follow the procedures in PNAP No. 252 (ADV-21). The transportation routing and frequency for marine disposal to designated disposal outlets shall be agreed with EPD/CEDD during the construction phase prior to marine disposal.  The recommended mitigation measures for marine disposal are discussed in Section 6.4.  No adverse waste management implications are anticipated if the recommended mitigation measures are implemented.

Operation Phase

6.3.36        During operation of the Project, the major types of wastes generated include:

      Chemical waste; and

      General refuse. 

Chemical Waste

6.3.37        Chemical wastes such as cleaning fluids, solvents, lubrication oil and waste fuel may be generated during maintenance activities in stations.  This waste may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner.  Measures as stipulated in the Waste Disposal (Chemical Waste) (general) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes would be strictly followed for the handling and disposal of chemical waste.

6.3.38        For the chemical waste generated from maintenance activities, it is difficult to quantify the amount of chemical waste as it would depend on the maintenance/housekeeping requirements.  Though, in view of the small project scale, it is anticipated that the quantity of chemical waste during operation period would be small to in the order of a few hundred litres per month.  Should any chemical waste be generated, the operator must register with EPD as a chemical waste producer.  The chemical waste would be readily accepted for disposal of at the CWTC at Tsing Yi or other licensed facilities.  This chemical waste should be collected periodically in drum-type containers by licensed chemical waste collectors.  With proper storage, handling and disposal of this waste, no adverse environmental impact is anticipated.

General Refuse

6.3.39        During the operation phase, general refuse such as food waste, paper, plastic and office waste would be generated by staff and commercial operators, and scrap materials from tracks and stations maintenance, used fluorescent tubes, used welding rods, cleansing materials and discarded electronic equipment from maintenance activities of the stations and tracks.  

6.3.40        The maximum number of persons including staff and commercial operators during the operation phase of the Project is estimated to be about 415, subject to operational need in the future. Based on a generation rate of 0.65 kg per person per day, approximately 270 kg of general refuse will be generated daily during the operation period. As the passengers are only transient population and will not stay in the stations, and thus the quantities of general refuse generated from passengers are negligible. 

6.3.41        Plastics, papers and other recyclable wastes should be separated from general refuse and recycled at respective recycling facilities as far as possible.  The remaining refuse would be collected by waste collectors and disposed of at refuse transfer stations .

6.4                Mitigation of Adverse Environmental Impacts

Construction Phase

6.4.1           The waste management hierarchy has been applied in the assessment and development of mitigation measures for waste which aims at evaluating the desirability of waste management methods and includes the followings in descending preference:

      Avoidance and reduction of waste generation;

      Reuse of materials as far as practicable;

      Recovery and recycling of residual materials where possible; and

      Treatment and disposal according to relevant laws, guidelines and good practices.

6.4.2           Based on the waste management hierarchy, waste reduction measures are recommended as follow to reduce impacts and costs arisen from the Project.  Recommendations of good site practices and waste reduction measures have been stated in order to achieve avoidance and minimization of waste generation in the hierarchy. 

Good Site Practices

6.4.3           Adverse impacts would not arise in the construction site, provided that good site practices are strictly followed.  Recommendations for good site practices during the construction phase include:

      Nomination of approved personnel, such as a site manager, to be responsible for implementation of good site practices, arrangements for waste collection and effective disposal to an appropriate facility;

      Training of site personnel in site cleanliness, concepts of waste reduction, reuse and recycling, proper waste management and chemical waste handling procedures;

      Provision of sufficient waste reception/ disposal points, and regular collection of waste;

      Adoption of appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

      Provision of regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;

      Adoption of a recording system for the amount of wastes generated, recycled and disposed (including the disposal sites); and

      Preparation of Waste Management Plan (WMP), as part of the Environmental Management Plan (EMP), and submission of WMP to the Engineer of the Project for approval.

Waste Reduction Measures

6.4.4           Good management and control of construction site activities / processes can minimise the generation of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction are discussed as follow:

      Segregate and store different types of construction related waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

      Provide separate labelled bins to segregate recyclable waste such as aluminium cans from other general refuse generated by the work force, and to encourage collection by individual collectors;

      Recycle any unused chemicals or those with remaining functional capacity;

      Maximise the use of reusable steel formwork to reduce the amount of C&D materials;

      Adopt proper storage and site practices to minimise the potential for damage to, or contamination of construction materials;

      Plan the delivery and stock of construction materials carefully to minimise the amount of waste generated; and

      Minimize over ordering and wastage through careful planning during purchasing of construction materials.

6.4.5           In addition to the above measures, other specific mitigation measures are recommended below to minimise environmental impacts during handling, transportation and disposal of wastes.

Construction and Demolition Materials

6.4.6           The C&D materials generated from demolition works, site clearance, excavation works, and construction of viaduct and stations should be sorted on-site into inert C&D materials (i.e. public fill) and C&D waste.  To minimise the impact resulting from collection and transportation of C&D materials as far as practicable, C&D waste, such as wood, plastic, steel and other metals should be reused or recycled and, as a last resort, disposed to landfill.  A suitable area should be designated within the site for temporary stockpiling of C&D materials and to facilitate the sorting process. Within the stockpile areas, the following measures should be taken to control potential environmental impacts or nuisance:

      Proper handling and storage of waste such as soil by means of covers and/or water spraying system to minimise the potential environmental impact and to prevent materials from wind-blown or being washed away;

      Covering materials during heavy rainfall;

      Locating stockpiles to minimise potential visual impacts;

      Minimising land intake of stockpile areas as far as possible;

      Adopting GPS or equivalent system for tracking and monitoring of all dump trucks engaged for the Project in recording their travel routings and parking locations to prohibit illegal dumping and landfilling of C&D materials; and

      keeping record and analysis of data collected by GPS or equivalent system related to travel routings and parking locations of dump trucks engaged on site.

General Refuse

6.4.7           General refuse should be stored in enclosed bins or compaction units separate from C&D materials and chemical waste.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D materials and chemical wastes.  An enclosed and covered area is preferred to reduce the occurrence of 'wind blown' light materials.

6.4.8           The recyclable component of general refuse, such as aluminium cans, paper and cleansed plastic containers should be separated from other waste.  Provision and collection of recycling bins for different types of recyclable waste shall be set up by the Contractor.  The Contractor shall also be responsible for arranging recycling companies to collect these materials.

6.4.9           The Contractor should carry out an education programme for workers in avoiding, reducing, reusing and recycling of materials generation.  Posters and leaflets advising on the use of the bins should also be provided in the sites as reminders.

Chemical Wastes

6.4.10        If chemical wastes were to be produced at the construction site, the Contractor would be required to register with the EPD as a Chemical Waste Producer, and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. 

6.4.11        Appropriate containers with proper labels should be used for storage of chemical wastes.  Chemical wastes should be collected and delivered to designated outlet by a licensed collector.  Chemical wastes (e.g. spent lubricant oil) should be recycled at an appropriate facility as far as possible, while the chemical waste that cannot be recycled should be disposed of at either the CWTC, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

6.4.12        Any unused chemicals or those with remaining functional capacity should be collected for reuse as far as practicable.

Sediments

6.4.13        The sediment should be excavated, handled, transported and disposed of in a manner that would minimise adverse environmental impacts.  For minimization of sediment disposal, beneficial reuse should be considered on site as far as practicable during the construction stage before the disposal of excavated sediment. 

6.4.14        Requirements of the Air Pollution Ordinance (Construction Dust) Regulation, where relevant, should be adhered to during excavation, transportation and disposal of the sediment.

6.4.15        In order to minimise the exposure to contaminated materials, workers should, if necessary, wear appropriate personal protective equipments (PPE) when handling contaminated sediments.  Adequate washing and cleaning facilities should also be provided on site.

6.4.16        For off-site disposal, the basic requirements and procedures specified under PNAP No. 252 (ADV-21) should be followed. Marine Fill Committee (MFC) of CEDD is managing the disposal facilities in Hong Kong for the excavated sediment, while EPD is the authority of issuing marine dumping permit under the DASO.

6.4.17        For the purpose of site allocation and application of marine dumping permit and if considered necessary by EPD (Marine Dumping Section), a separate SSTP should be submitted to EPD for agreement under DASO.  Additional SI works, based on the SSTP, should then be carried out in order to confirm the disposal arrangements of the excavated sediment.  A Sediment Quality Report (SQR), reporting the chemical and biological screening results and the estimated quantities of sediment under different disposal options, should then be submitted to EPD for agreement under DASO.

6.4.18        To ensure disposal space is allocated for the Project, the Project Proponent should be responsible for obtaining agreement from MFC on the allocation of the disposal site. The contractor(s), on the other hand, should be responsible for the application of the marine dumping permit under DASO from EPD for the sediment disposal.

6.4.19        The excavated sediments is expected to be loaded onto the barge at public barging point of which the exact location will be determined by the contractor(s) and agreed by EPD/CEDD and transported to the designated disposal sites allocated by MFC.  The excavated sediment would be disposed of according to its determined disposal options and PNAP No. 252 (ADV-21).

6.4.20        Stockpiling of contaminated sediments should be avoided as far as possible.  If temporary stockpiling of contaminated sediments is necessary, the excavated sediment should be covered by tarpaulin and the area should be placed within earth bunds or sand bags to prevent leachate from entering the ground, nearby drains and surrounding water bodies.  The stockpiles should be placed on surface completely paved or covered by linings in order to avoid contamination to underlying soil or groundwater.  Separate and clearly defined areas should be provided for stockpiling of contaminated and uncontaminated materials.  Leachate, if any, should be collected and discharged according to the Water Pollution Control Ordinance (WPCO).

6.4.21        In order to minimise the potential odour / dust emissions during excavation and transportation of the sediment, the excavated sediments should be wetted during excavation / material handling and should be properly covered when placed on trucks or barges.  Loading of the excavated sediment to the barge should be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.

6.4.22        The barge transporting the sediments to the designated disposal sites shall be equipped with tight fitting seals to prevent leakage and should not be filled to a level that would cause overflow of materials or laden water during loading or transportation.  In addition, monitoring of the barge loading should be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels should be equipped with automatic self-monitoring devices as specified by the DEP.

Operational Phase

Chemical Wastes

6.4.23        The requirements given in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes should be followed in handling of chemical waste as in construction phase.  A trip-ticket system would be adopted by the Project Proponent to monitor disposal of chemical waste.

6.4.24        Non-recyclable chemical waste should be disposed of at appropriate facility like CWTC by licensed collectors.  Recyclable chemical waste should be collected and transported off-site by licensed collectors.

General Refuse

6.4.25        Designated areas will be assigned for proper storage and collection of general refuse generated on site. A reputable waste collector should be employed to remove general refuse regularly to minimize potential impacts arising from storage and collection of general refuse. Recycling bins would be provided to staff and passengers to separate recyclable component of general refuse. Posters and leaflets advising on the use of the bins would also be provided as reminders.

6.4.26        Table 6.6 provides a summary of the various waste types likely to be generated during the construction and operation of the Project, together with the recommended handling and disposal methods.

Table 6.6         Waste Arising, Waste Handling Procedures and Disposal Outlets

Waste Material Type

Generated From

Materials Generated

Total Quantity Generated

Handling Methods/

Reuse

Disposal Outlet, Tentative Routing and Frequency(1)

C&D Materials

Construction Phase: Excavation, demolition works, site formation, piling works, and construction of viaduct and stations.

Inert C&D materials 每 rock, soil, broken concrete, building debris, etc.

97,202m3

   Segregation from inert C&D materials during stockpiling

   Stockpile area (if required) should be well managed with covers and water spraying system

Inert C&D materials would be delivered to Tuen Mun Area 38 Fill Bank or reclamation sites by approx. 9 dump trucks per day through Wu King Road, Wu Chui Road, Lung Fu Road / Lung Mun Road. 

Non-inert C&D materials 每 vegetation, wood, etc.

27,930 m3

   Segregation from non-inert C&D materials during stockpiling

   Reusable materials should be separated and recycled as far as practicable

Dispose to Designated Landfill Site such as WENT landfill to be agreed with EPD/CEDD by approx. 3 dump trucks per day through Wu King Road, Wu Chui Road, Lung Fu Road / Lung Mun Road.

General Refuse

Construction Phase: Workforce

 

 

Operation Phase:

Staff and commercial operators; maintenance and operation of equipment and machineries

Construction Phase:
Food scraps, waste paper, empty containers, etc.

 

Operation Phase:

Food waste, paper, plastic and office waste, used fluorescent tubes(2),  cleansing materials,  etc. 

Construction Phase:

228 kg/day

 

Operation Phase: 270 kg/day

 

   Provide on-site collection points together with recycling bins

   To be collected and recycled by reputable waste collectors

Construction Phase:  Dispose to Designated Landfill Site such as WENT landfill to be agreed with EPD/CEDD by approx. 1 dump trucks per day through Wu King Road, Wu Chui Road, Lung Fu Road / Lung Mun Road.

 

Operation Phase:

Refuse transfer station or recycling facilities, routing to be determined by the waste collectors.

Chemical Waste

Construction and Operation Phase:
Maintenance and servicing of construction plant and equipment

Cleaning fluids, solvents, lubrication oil, waste fuel, etc.

Construction and Operation Phase:

Small to a few hundred litres per month

   Store in compatible containers in designated area on site

   To be collected and recycled by licensed collectors

Dispose to Chemical Waste Treatment Centre (CWTC) or other licensed facilities on a need basis, routing to be determined by the licensed collectors

 

Land-based and River-based Sediment

Piling works and excavation works for the Project.

Category L Sediment

2,088 m3

 

   Beneficial reuse on site as far as practicable

   Type 1 每 Open sea disposal at marine disposal site(s) allocated by by MFC.

Final disposal site (typically South Cheung Chau / East of Ninepin) shall be determined by MFC; and disposal arrangement on a need basis

Category M Sediment (passed Tier III - biological screening)

433 m3

   Beneficial reuse on site as far as practicable

   Type 1 每 Open sea disposal (dedicated site) at marine disposal site(s) allocated by MFC.

Final disposal site (typically South Cheung Chau / East of Ninepin) shall be determined by MFC; and disposal arrangement on a need basis

Category H Sediment (does not require the Tier III biological screening))

319 m3

   Beneficial reuse on site as far as practicable

   Type 2 每 Confined marine disposal at marine disposal site(s) allocated by MFC.

Final disposal site (typically East Sha Chau) shall be determined by MFC; and disposal arrangement on a need basis

Notes:

(1)    Frequency of the trucks/vessels involved for each identified type of waste is tentative only and is subject to change at the time of actual construction activities.

(2)    If the number of used fluorescent tubes is more than 500, it would be handled as chemical waste in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

6.5                Evaluation of Residual Environmental Impacts

6.5.1           With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, adverse residual impact is not expected to occur during the construction and operation of the Project.

6.6                Environmental Monitoring and Audit Requirement

Construction Phase

6.6.1           During the construction period, it is the Contractor*s responsibility to ensure that all waste produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices, relevant legislation and waste management guidelines.

6.6.2           Waste materials generated during construction activities, such as C&D materials, are recommended to be audited at regular intervals to ensure that proper storage, transportation and disposal practices are being implemented.  This would ensure the waste generated would be properly disposed of.  The Contractor would be responsible for the implementation of any mitigation measures to minimise waste or mitigate problems arisen from waste materials.

6.6.3           A WMP should be prepared by the Contractor and submitted to the Engineer of the Project for approval.  The recommended mitigation measures should form the basis of the WMP. 

Operational Phase

6.6.4           With the implementation of good waste management practices, no adverse environmental impacts are expected to arise, and therefore waste monitoring and audit programme during the operation phase of the Project is not required.

6.7                Conclusion

6.7.1           Waste types generated by the construction of this Project are likely to include C&D materials (from excavation, demolition works, site formation, piling works, and construction of viaduct and stations), general refuse, chemical wastes from maintenance and servicing of construction plant and equipment, and land-based and river-based sediments.  Provided that these wastes are handled, transported and disposed of according to the recommended good site practices, adverse environmental impacts are not expected during the construction phase.

6.7.2           The total volume of excavated sediment generated from the Project is estimated to be approximately 2,840 m3. Based on the results of the chemical and biological screening, approximately 2,088 m3 of sediment is suitable for Type 1 每 Open Sea Disposal, 433 m3 of sediment is suitable for Type 1 每 Open Sea Disposal (Dedicated Sites) and 319 m3 of sediment requires Type 2 每 Confined Marine Disposal in accordance with PNAP No. 252 (ADV-21).  With the implementation of the recommended mitigation measures detailed in Section 6.4 and in accordance with the requirements of PNAP No. 252 (ADV-21), no adverse environment impacts would be expected from excavation, transportation and disposal of marine sediment.

6.7.3           The main waste types generated during the operation of the Project would be chemical waste and general refuse from maintenance activities, staff, and commercial operators.  The handling, collection, transportation and disposal practices of the identified waste generated should follow the current practices at other operating railway lines.  It is anticipated that no adverse impacts would arise if the mitigation measures are strictly followed.