TABLE OF
CONTENTS
7.2 Environmental Legislation, Plans, Standards, and Guidelines
7.4 Description
of the Environment
7.5 Identification of Potential Land Contamination Concern
7.7 Evaluation of Environmental Impacts
7.8 Mitigation of Adverse Environmental Impacts
7.9 Evaluation of Residual Environmental Impacts
List of tables
Table 7.1 Summary of Historical Land
Uses of the Project Area
Table
7.2 Summary
of Potential Land Contamination Issues within the Project Area
Table 7.3 Sampling and Testing Plan
LIST OF Appendices
Appendix
7.1 Contamination
Assessment Plan
﹞ Section 3 (Potential Contaminated Land Issues) of Annex 19 ※Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other Impacts§ of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).
﹞
※Guidance Note for
Contaminated Land Assessment and Remediation§ (Guidance Note)
Guidance
Note sets out the requirements for proper assessment and management of
potentially contaminated sites such as oil installations (e.g.
oil depots, petrol filling stations), gas works, power plants,
shipyards/boatyards, chemical manufacturing/processing plants, steel
mills/metal workshops, car repairing/dismantling workshops and scrap yards. In
addition, this Guidance Note provides guidelines on how site assessments should
be conducted and analyzed and suggests practical remedial measures that can be
adopted for the cleanup of contaminated sites.
﹞ ※The Practice Guide for
Investigation and Remediation of Contaminated Land§
(Practice Guide)
This guide outlines typical
investigation methods and remediation strategies for the range of potential
contaminants typically encountered in Hong Kong.
﹞
※Guidance Manual for Use of Risk-based Remediation Goals for
Guidance
Manual introduces a risk based approach to land
contamination assessment and presents instructions for comparison of soil and
groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals
of concern commonly found in
﹞
Selected
aerial photographs and topographic maps held by the
Lands Department (LandsD); and
﹞
Records on dangerous goods
(DGs), chemical wastes and chemical spillage/leakage incidents from Fire Services Department (FSD)
and Environmental Protection Department (EPD).
Table 7.1 Summary
of Historical Land Uses of the Project Area
Year |
Description |
1963 |
The
Project Area was occupied by open waters. |
1973 |
Reclamation
works and reclaimed land were observed in the north and the east of the
Project Area. The nullah was modified to the existing configuration in the
north of the Project Area. |
1983 |
Reclaimed
land was observed in the centre and south of the Project Area. Tuen Mun Park and Tuen Mun 3rd Village Temporary
Housing Area were
observed. The
nullah was largely modified to the existing configuration except for the
southwest of the Project Area. |
1993 |
A
suspected industrial facility with electrical substation (Site TME-S1) was
observed in the centre of the Project Area. The area appeared to be concrete
paved. An
open storage (Site TME-S2) was observed in the south of the Project Area. A
cargo working area was also observed in the south of the Project Area. The
area appeared to be concrete paved with containers, construction materials
and barging point for cargo handling. The
existing Tuen Mun Swimming Pool, garden, playground
and existing Wong Chu Road were observed. The Tuen Mun River Channel was
modified to the existing configuration. Tuen Mun 3rd Village Temporary
Housing Area was replaced by the existing Tuen Mun Park. |
2003 |
The
suspected industrial facility (Site TME-S1) was replaced by an open storage. The
open storage (Site TME-S2) was replaced by an existing open car park,
vegetated land and vacant land. The
cargo working area was replaced by an existing open car park. A construction
site was observed in the northern portion of the Project Area. The existing Construction Industry Training Authority (CITA) /
Construction Industry Council (CIC) Tuen Mun Training Ground was observed in
the central portion of the Project Area. The existing open car park, a construction
site and a temporary structure were also observed in the central portion of the Project Area. The
existing Wu King Road Garden, Wu Shan Recreation Playground, Tuen Mun Promenade and public toilet were observed in the south of
the Project Area. |
2013 |
The
existing Pui To Road (South) Rest Garden and Hoi
Wong Road Garden were observed in the north of the Project Area. A site
office was observed in the central portion of the Project Area. |
2020 |
The
open storage (Site TME-S1) was turned into the existing Tuen Mun Community
Green Station. The site office was vacated. Tuen Mun River (Eastern Bank)
Garden was observed. An existing works site was observed
within Tuen Mun Park. |
﹞ Tuen Mun Community Green Station (former open storage, former
suspected industrial land use and former electrical substation) (Site TME-S1);
﹞ Wu Shan Road Car Park (STT No. MX16007) and land in the vicinity
(former open storage) (Site TME-S2);
﹞ Electrical substation (No. 08271-1) at Tuen Mun Swimming Pool (Site
TME-S3); and
﹞ Diesel generator in Works site of Contract No. DC/2018/09 (Site TME-S4).
Table 7.2 Summary of Potential Land Contamination
Issues within the Project Area
Site ID / Concerned Site |
Current
Land Use |
Site
Observation / Current Potentially Contaminating Activities |
Corresponding
Photographic Record Reference in the CAP in Appendix 7.1 |
Other
Past Potential Contaminating Land Use / Activities |
Approx.
Site Area (m2) |
Any
Potential Land Contamination Issues? |
Potential
COCs |
Future
Land Uses |
RBRGs
Land Use Scenario3 |
TME-S1
|
Recycling station |
The Tuen Mun Community Green
Station is located in the central portion of the Project Area. As reported by
the site representative and observed during the site walkover, the site
mainly consists of an office (comprising an office area, an activity room and
a toilet) in the centre, a garden in the south, a warehouse and a storage
yard for the temporary storage of recyclables (e.g.
paper, plastics and aluminum cans) in the northern portion of the site.
Except for the landscaped areas, the entire site was
paved with no stains / stressed vegetation observed. A chemical
waste storage room for temporary storage of spent fluorescent lamp tubes
and batteries was observed in the west of the warehouse. As reported by the site representative, the spent fluorescent lamp
tubes and batteries are delivered off-site regularly for recycling. A hydraulic waste baler
was also observed in the northwest of the warehouse. Based on site
observations and information reported by the site representative, hydraulic
oil is used for the operation of the baler and the oil is stored in the hydraulic oil tank
within the baler machine at least 2 m above ground
level. The entire warehouse was paved with
intact concrete in good condition with no signs of oil stains / chemical
spillage observed. No potentially
contaminating activities were observed at the site during the site walkover. Based on EPD information, a valid CWP
record registered for government facility was identified for the site. Based on FSD/EPD information, there
were no DG / fire incident / spillage records for the site. |
C1502/C/TME/ACM/M55/020 |
Open storage (year 2003 to 2019) Suspected industrial land use & electrical
substation (year 1993 to 2002) |
2,760 |
Yes ﹞
Potential land
contamination issues associated with past land uses. ﹞
Given the storage
of spent batteries and fluorescent lamps in the chemical waste storage room
was only temporary as these chemical wastes are reportedly delivered off-site
regularly, and the hydraulic oil tank is located within the baler machine at
least 2m above ground level, and the entire warehouse was paved with concrete
in good conditions with no signs of oil stains / chemical spillages observed,
no potential land contamination issues associated with these two areas to the
Project are anticipated. |
Metals,
VOCs, SVOCs, PCRs and PCBs |
Viaduct and railway station |
Industrial |
TME-S2 Wu Shan Road Car Park |
Open car park and vegetated land |
An open car
park is located in the south of the Project Area,
which was largely concrete paved. No vehicle maintenance activities were
observed at the site. The site also comprises vegetated land. No potentially
contaminating activities were identified at the site during the site walkover.
Based on FSD/EPD information, there
were no DG / chemical wastes / fire incident / spillage records for the site.
|
Photo 0966, 2506, 0970 and 2522 in
C1502/C/TME/ACM/M55/022 |
Open storage (year 1993 to 2002) |
7,220 |
Yes2 |
Metals,
VOCs, SVOCs, and PCRs |
Riverside open space and potential underground car
park |
Lower of Industrial or Public Park |
TME-S3 Tuen Mun Swimming Pool (GLA-TM 47) |
Swimming pool, squash
courts, car park and garden |
The site mainly comprises
swimming pool facilities (e.g. pools and changing
rooms), a plant room (comprising water boilers, water pumps and tanks, a
refuse store and chemical storage rooms for the storage of sodium chloride
(common salt), sodium hypochlorite (bleach) and a small amount of alum), a
fire service water tank, Tuen Mun Swimming Pool Squash Courts (comprising 2
courts and site offices), car park and a garden. As reported by the site
representatives, only the chemicals stored in the chemical storage rooms are
used in the plant room. No potentially contaminating activities were observed
in these areas during the site walkover. An electrical substation (No. 08271-1)
(Site TME-S3) is located within the plant room in the south of the Tuen Mun Swimming
Pool. The substation was concrete paved and housed a transformer (approx. 5m2)
containing transformer oil. The transformer was situated on raised concrete
foundation in good condition with no oil stains observed. Based on information from EPD, FSD and
site representatives, there were no DG / chemical wastes / fire incident /
spillage records for the site. |
C1502/C/TME/ACM/M55/019 |
N/A |
35,660 Transformer: |
Yes Concerned area: ﹞
Transformer ﹞
No land contamination issues anticipated
for the plant room given the chemicals identified (sodium
chloride, sodium hypochlorite and alum) are not considered as land
contaminants. |
Metals,
VOCs, SVOCs, PCRs and PCBs |
Viaduct and railway station |
Urban Residential |
Works site of Contract No. DC/2018/09 |
Works site |
A works site of Contract
No. DC/2018/09 Rehabilitation of
Trunk Sewers in Tuen Mun is located within Tuen Mun Park in the east of the Project Area. The works site mainly comprises a works area for rehabilitation of
underground trunk sewers in the north, a material storage area (for
construction materials and equipment) and a chemical dosing unit in the south
of the site. Apart from the works area, the remaining areas of the works site
was part of the existing paved cycling track. The cycling track was noted to
be in good condition with no stains / stressed vegetation observed. Based on site
observations and as reported by the site representative, no vehicle refueling or vehicle / equipment maintenance activities
are carried out on site. Based on site observations and information provided by the site
representatives, wastewater treatment chemicals including Clarifloc,
polyaluminum chloride (PAC) and sodium bisulfite
are stored in the chemical dosing unit and are used on site. These chemicals
were stored in plastic drums with metal drip trays within the chemical dosing
unit in the east of the works site. The metal drip trays and paved cycling track in the vicinity were in
good condition with no signs of stains / spillage observed. A 60 L diesel generator was observed in the west of the works site.
The generator was located on the existing raised planter of approximately 0.3
m above ground level along the Tuen Mun River Channel and was provided with a
metal drip tray. The drip tray was observed to be intact and in good condition with no
signs of oil stains / spillages in the vicinity of the generator. As reported
by the site staff, diesel and lubricating oils are used for operation of the
generator and are delivered to site as and when required for refueling of the
generator. All lubricating oils and spent lubricating oils were reportedly
stored off-site at another works site outside the Project Area. No chemical
waste / chemical waste storage areas were observed on site during the site
walkover. Based
on EPD information, 1 valid CWP record registered for construction was
identified for the site. Based
on information from FSD, EPD and site representatives, there were no DG /
fire incident / chemical spillage records for the site. |
Photo
2624, 6970, 7456, 7461 and 7463 in C1502/C/TME/ACM/M55/017 |
N/A |
420 Diesel generator: |
Yes Concerned
area: ﹞
Diesel generator ﹞
The wastewater
treatment chemicals (Clarifloc, PAC and sodium bisulfite) are not considered as land contaminants. |
Metals,
VOCs, SVOCs, and PCRs |
Cycling track /
footpath |
Lower of Industrial or Public Park |
Notes:
1. Refer to Figure Nos. C1502/C/TME/ACM/M55/026 to 028 of the CAP (Appendix 7.1 refers) for locations of
the sites.
2. Potential
land contamination impact associated with Site TME-S2 to the Project is not
anticipated if no excavation works would be proposed at the site, subject to
confirmation of the engineering design plan in later stage of the Project.
3.
Where a site would be developed into more than one land use in the future, the
most stringent RBRGs has been adopted.
N/A: Not
Applicable
﹞ Urban residential
﹞ Rural residential
﹞ Industrial
Table
7.3 Sampling and
Testing Plan
Site
ID (Approx.
Area) |
Hotspot (Approx.
Area) |
Grid
Size (m) |
Proposed
Number of Sampling Location |
Rationale |
Sampling
Method |
Sampling
Matrix / Depth(1) |
Testing
Parameters(2) |
|||||
VOC |
SVOC |
Metals |
PCRs |
PCBs |
||||||||
TME-S1 (2,760 m2) |
Whole area of former industrial facility (2,760 m2) |
14 |
16 Borehole ID: ENV-BH01 每 BH16 (refer to Figure No. C1502/C/TME/ACM/M55/029 of the CAP in Appendix 7.1 for
sampling locations) |
Sampling to target the existing site. A grid sampling
approach based on EIA recommendations and the Practice Guide with specified
grid size was adopted for the sampling strategy. Sampling location ENV-BH16 was proposed to target the
former electrical substation (approx. 55 m2). |
Borehole to 2m below the ground-water table or 6m bgl |
Soil |
(i) 0.5m
bgl; (ii) 1.5m bgl; (iii) 3.0m bgl; and (iv) above GW level if present or if no GW encountered, 6m
bgl. |
Full List |
Full List |
Full List |
Full List |
邦 (ENV-BH16
only) |
GW |
If present(3) |
Full List |
Full List |
Mercury only |
Full List |
邦 (ENV-BH16
only) |
||||||
TME-S2(4) |
Whole area of former open storage (7,220 m2) |
17 |
31 Borehole ID: ENV-BH18 每 BH48 (refer to Figure No. C1502/C/TME/ACM/M55/030 of the CAP in Appendix 7.1 for
sampling locations) |
Sampling to target the existing site. A grid sampling
approach based on the Practice Guide with specified grid size was adopted for
the sampling strategy. |
Borehole to 2m below the ground-water table or 6m bgl |
Soil |
(i) 0.5m
bgl; (ii) 1.5m bgl; (iii) 3.0m bgl; and (iv) above GW level if present or
if no GW encountered, 6m bgl. |
Full List |
Full List |
Full List |
Full List |
- |
GW |
If present(3) |
Full List |
Full List |
Mercury only |
Full List |
- |
||||||
TME-S3 (35,660 m2) |
1 transformer on concrete foundation |
- |
1 Borehole ID: ENV-BH17 (refer to Figure No. C1502/C/TME/ACM/M55/029 of the CAP in Appendix 7.1 for
sampling location) |
Sampling to target the transformer located in the
electrical substation. |
Borehole to 2m below the ground-water table or 6m bgl |
Soil |
(i) 0.5m
bgl; (ii) 1.5m bgl; (iii) 3.0m bgl; and (iv) above GW level if present or if no GW encountered, 6m
bgl. |
Full List |
Full List |
Full List |
Full List |
邦 |
GW |
If present(3) |
Full List |
Full List |
Mercury only |
Full List |
邦 |
||||||
TME-S4 (420 m2) |
1 diesel generator |
- |
1 Borehole ID: ENV-BH49 (refer to Figure No. C1502/C/TME/ACM/M55/031
of
the CAP in Appendix 7.1 for sampling location) |
Sampling to target the hotspot area at the existing diesel
generator. |
Borehole to 2m below the ground-water table or 6m bgl |
Soil |
(i) 0.5m bgl; (ii) 1.5m bgl; (iii) 3.0m bgl; and (iv) above GW level if present or if no GW encountered, 6m
bgl. |
Full List |
Full List |
Full List |
Full List |
- |
GW |
If present(3) |
Full List |
Full List |
Mercury only |
Full List |
- |
Notes:
(1)
bgl = Below
ground level; GW = groundwater
(2)
每 Full list refers to the parameters as shown
in Table 2.1 每 RBRGs for Soil & Soil Saturation Limit and Table 2.2 每 RBRGs
for Groundwater and Solubility Limit under VOCs, SVOCs, Metals and PCRs in the
Guidance Manual.
每 Volatile
organic chemicals (VOCs) include BTEX (benzene, toluene, ethylbenzene, and
total xylenes), MTBE (methyl tert-butyl ether), acetone, bromodichloromethane,
2-butanone, chloroform, methylene chloride, styrene, tetrachloroethene, and
trichloroethene.
每
Semi-volatile organic chemicals (SVOCs) include polyaromatic hydrocarbons
(PAHs) (acenaphthene, acenaphthylene, anthracene, benzo(a)anthracene,
benzo(a)pyrene, benzo(b)fluoranthene, benzo(g,h,i)perylene, benzo(k)fluoranthene, chrysene,
dibenzo(a,h)anthracene, fluoranthene, fluorene, indeno(1,2,3-cd)pyrene, naphthalene, phenanthrene and
pyrene), bis-(2-ethylhexyl)phthalate, hexachlorobenzene, and phenol. Since RBRG value of Benzo(a)anthracene,
Benzo(a)pyrene, Benzo(g,h,i)perylene,
Benzo(k)fluoranthene, bis-(2-Ethylhexyl)phthalate, Dibenzo(a,h)anthracene,
Indeno(1,2,3-cd)pyrene and Phenol were not available
for groundwater, the captioned chemicals parameters would not be tested in
groundwater sample.
每 Metals
include antimony, arsenic, barium, cadmium, chromium III, chromium VI, cobalt,
copper, lead, manganese, mercury, molybdenum, nickel, tin
and zinc.
每 Petroleum
carbon ranges (PCRs) include C6 每 C8, C9 每 C16 and C17 每 C35.
每 PCBs -
Polychlorinated biphenyls.
(3)
Samples will only be collected if groundwater
is encountered during SI works.
(4)
No SI works is
required if there would be no excavation works proposed at the site under the
Project, subject to confirmation of the engineering
design plan in later stage of the Project. The relevant design plans will be
provided to EPD for review and agreement should the SI works would not be
proceeded in the future.
﹞ Excavation profiles must be properly
designed and executed with attention to the relevant requirements for
environment, health and safety;
﹞ Excavation shall be carried out
during dry season as far as possible to minimise contaminated runoff from
contaminated soils;
﹞ Supply of suitable clean backfill
material (or treated soil) after excavation;
﹞ Stockpiling site(s) shall be lined
with impermeable sheeting and bunded. Stockpiles shall be fully covered by
impermeable sheeting to reduce dust emission;
﹞ Vehicles containing any excavated
materials shall be suitably covered to limit potential dust emissions or
contaminated wastewater run-off, and truck bodies and tailgates shall be sealed
to prevent any discharge during transport or during wet conditions;
﹞ Speed control for the trucks
carrying contaminated materials shall be enforced;
﹞ Vehicle wheel and body washing
facilities at the site*s exit points shall be established and used; and
﹞ Pollution control measures for air
emissions (e.g. from biopile
blower and handling of cement), noise emissions (e.g. from blower or
earthmoving equipment), and water discharges (e.g. runoff control from
treatment facility) shall be implemented and complied with relevant regulations
and guidelines.