TABLE OF CONTENTS

 

 

9          LANDSCAPE AND VISUAL IMPACT ASSESSMENT. 1

9.1          Introduction. 1

9.2          Scope and Content of the Study. 1

9.3          Environmental Legislation, Standards and Guidelines. 2

9.4          Assessment Methodology. 3

9.5          Review of Planning Control Framework. 8

9.6          Baseline Study. 11

9.7          Landscape Impact Assessment 27

9.8          Visual Impact Assessment 37

9.9          Landscape and Visual Mitigation Measures. 46

9.10        Residual Impacts. 49

9.11        Cumulative Impacts. 65

9.12        Conclusion. 66

 

 

List of tables

Table 9.1            Relationship between Sensitivity and Magnitude of Change in Defining Impact Significance  5

Table 9.2            Relationship between Visually Sensitive Receivers (VSRs) Sensitivity and Magnitude of Change in Defining Impact Significance. 7

Table 9.3            Summary of the Review of Planning and Development Control Framework. 9

Table 9.4            Landscape Resources and Their Sensitivity. 12

Table 9.5            Landscape Character Areas and Their Sensitivity. 18

Table 9.6            Visually Sensitive Receivers (VSRs) and Their Sensitivity. 23

Table 9.7            Magnitude of Landscape Impact during Construction and Operation. 28

Table 9.8            Magnitude of Visual Impact during Construction and Operational Phases. 42

Table 9.9            Proposed Landscape and Visual Mitigation Measures for Construction Phase. 46

Table 9.10         Proposed Landscape and Visual Mitigation Measures for Operational Phase. 48

Table 9.11         Significance of Landscape Impact during Construction and Operational Phases. 54

Table 9.12         Significance of Visual Impact during Construction and Operational Phases. 60

 

 

List of Figures

C1502/C/TME/ACM/M57/101

Landscape and Visual Impact Study Boundary

C1502/C/TME/ACM/M57/102

Existing Planning & Development Framework (OZP) within the Study Boundary

C1502/C/TME/ACM/M57/103

Landscape Resources

C1502/C/TME/ACM/M57/104

Photographs of Landscape Resources (Sheet 1 of 2)

C1502/C/TME/ACM/M57/105

Photographs of Landscape Resources (Sheet 2 of 2)

C1502/C/TME/ACM/M57/106

Landscape Character Areas

C1502/C/TME/ACM/M57/107

Photographs of Landscape Character Areas

C1502/C/TME/ACM/M57/108

Key Visual Sensitive Receivers

C1502/C/TME/ACM/M57/109

Photomontage Viewpoint Locations

C1502/C/TME/ACM/M57/111

Key Landscape Master Plan

C1502/C/TME/ACM/M57/112

Landscape Mitigation Plan (Sheet 1of 5)

C1502/C/TME/ACM/M57/113

Landscape Mitigation Plan (Sheet 2of 5)

C1502/C/TME/ACM/M57/114

Landscape Mitigation Plan (Sheet 3of 5)

C1502/C/TME/ACM/M57/115

Landscape Mitigation Plan (Sheet 4of 5)

C1502/C/TME/ACM/M57/116

Landscape Mitigation Plan (Sheet 5of 5)

C1502/C/TME/ACM/M57/117

Implementation of mitigation measures ¨C Section

(Sheet 1 of 4)

C1502/C/TME/ACM/M57/118

Implementation of mitigation measures ¨C Section

(Sheet 2 of 4)

C1502/C/TME/ACM/M57/119

Implementation of mitigation measures ¨C Section

(Sheet 3 of 4)

C1502/C/TME/ACM/M57/120

Implementation of mitigation measures ¨C Section

(Sheet 4 of 4)

C1502/C/TME/ACM/M57/121

Photomontage ¨C VP1

C1502/C/TME/ACM/M57/122

Photomontage ¨C VP2

C1502/C/TME/ACM/M57/123

Photomontage ¨C VP3

C1502/C/TME/ACM/M57/124

Photomontage ¨C VP4

C1502/C/TME/ACM/M57/125

Photomontage ¨C VP5

C1502/C/TME/ACM/M57/126

Photomontage ¨C VP6

C1502/C/TME/ACM/M57/127

Photomontage ¨C VP7

C1502/C/TME/ACM/M57/128

Photomontage ¨C VP8

C1502/C/TME/ACM/M57/129

Photomontage ¨C VP9

C1502/C/TME/ACM/M57/141

Existing Planning & Development Framework (OZP) within the Study Boundary ¨C Off-site Mong Wing Street Works Area

C1502/C/TME/ACM/M57/142

Landscape Resources (Off-site Mong Wing Street Works Area)

C1502/C/TME/ACM/M57/143

Photographs of Landscape Resources (Off-site Mong Wing Street Works Area)

C1502/C/TME/ACM/M57/144

Landscape Character Areas (Off-site Mong Wing Street Works Area)

C1502/C/TME/ACM/M57/145

Key Visual Sensitive Receivers (Off-site Mong Wing Street Works Area)

 

 

List of APPENDiCES

Appendix 9.1 Tree Assessment Schedule (Group Survey)


9                  LANDSCAPE AND VISUAL IMPACT ASSESSMENT

9.1              Introduction

9.1.1         The assessment of potential landscape and visual impacts due to construction and operation of the Project is presented in this chapter. 

9.1.2         Landscape and visual impacts were assessed in accordance with the criteria and guidelines as stated in Annexes 10 and 18 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) and the Environmental Impact Assessment ordinance (EIAO) Guidance Note No/ 8/2010 on ¡°Preparation of Landscape and Visual Impact Assessment under the Environmental Impact Assessment Ordinance¡±.

9.2              Scope and Content of the Study

Assessment Area

9.2.1         The assessment area for landscape impact assessment includes all areas within a 100m from the Project boundary including works sites and works areas. The assessment area for the visual impact assessment is defined by the visual envelope of the Project. The landscape and visual impact study boundary are shown in Figure No. C1502/TME/ACM/M57/101.

Review of Planning Framework

9.2.2         Relevant outline development plan(s), outline zoning plan(s), layout plan(s) or planning briefs and studies which may identify areas of high landscape value and visually sensitive areas should be reviewed. The aim is to gain an insight of the future outlook of the affected area so as to assess whether the Project can fit into the surrounding setting. Any conflict with statutory town plan(s) should be highlighted and appropriate follow-up action should be recommended.

Landscape Impact Assessment

9.2.3        The existing landscape resources and character within the assessment area were described, appraised, analyzed and evaluated.  A system is derived for judging landscape and visual impact significance as required under the Technical Memorandum.  The sensitivity of the landscape framework and its ability to accommodate change are particularly focused on.  The degree of compatibility of the Project with the existing and planned landscape setting is identified.  The landscape impact assessment evaluates the potential landscape impact so as to illustrate the significance of such impacts arising from the proposed Project.  Clear mapping of the baseline landscape resources, landscape character areas and the landscape impact are provided.

Visual Impact Assessment

9.2.4         The visual impact of the Project was assessed.  For aboveground structures of the Project, clear illustrations including mapping of visual impact are provided.  The assessment adopts a systematic methodology and includes the following:

I.        Identification and plotting of visual envelope of the proposed Project within the assessment area.

II.      Identification of the key groups of sensitive receivers within the visual envelope and their views at both ground level and elevated vantage points.

III.     Description of the visual compatibility of the Project with the surrounding and the planned setting, and its obstruction and interference with the key views of the adjacent areas.

IV.    Description of the severity of visual impact in terms of distance, nature and number of sensitive receivers.  The visual impact of the Project with and without mitigation measures are included so as to demonstrate the effectiveness of the proposed mitigation measures.

V.      Clear evaluations and explanation with supportive arguments of all relevant factors considered in arriving at the significant thresholds of visual impact.

Landscape and Visual Mitigation Measures

9.2.5         The merit of preservation in total or in parts of existing landscape and the establishment of a new landscape character are evaluated.  Alternative construction methods and / or Project-related works or structure(s) that would avoid or reduce the identified landscape and visual impacts are considered and evaluated for comparison before adopting other mitigation or compensatory measures to alleviate the impacts.  The mitigation measures proposed are not only concerned with damage reduction but also included consideration of potential enhancement of the existing landscape and visual quality.  Mitigation measures to minimise the adverse effects identified, including provision of a landscape design are recommended. 

9.2.6         The mitigation measures such as the preservation and tree transplanting as far as practical, control of night-time lighting glare, erection of decorative screen hoarding that compatible with the surrounding setting, reinstatement of the affected hard and soft landscape area in like-for-like basis, aesthetic design of aboveground structure, provision of finishes to structure, colour scheme and texture of material used, tree compensation, provision of screen planting, roadside amenity planting, roof greening and reprovision of open spaces.  Parties are identified for the on-going management and maintenance of the proposed mitigation works to ensure their effectiveness throughout the operation of the Project.  A practical programme and funding proposal for the implementation of the recommended measures are provided.

Significance of Landscape and Visual Impact

9.2.7         Annotated illustration such as coloured perspective drawings, plans and section/elevation diagrams, oblique aerial photographs, photographs taken at vantage points and computer-generated photomontage are adopted where appropriate to illustrate the significance of the landscape and visual impacts of the aboveground ancillary structures of the Project.

9.3              Environmental Legislation, Standards and Guidelines

9.3.1         The following legislation, standards and guidelines are applicable to landscape and visual impact assessment associated with the construction and operation of the Project:

¡¤           Environmental Impact Assessment Ordinance (EIAO) (Cap.499 S.16) and the Technical Memorandum on EIA Process (EIAO-TM), particularly Annexes 10 and 18;

¡¤           Environmental Impact Assessment Ordinance Guidance Note No. 8/2010; 

¡¤           Town Planning Ordinance (Cap. 131); 

¡¤           Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586); 

¡¤           Forests and Countryside Ordinance (Cap 96) and its subsidiary legislations;

¡¤           Plant Varieties Protection Ordinance (Cap. 490);

¡¤           Hong Kong Planning Standards and Guidelines (HKPSG) Chapters 4, 10 and 11; 

¡¤           AFCD Nature Conservation Practice Note No. 2 - Measurement of Diameter at Breast Height (DBH); 

¡¤           AFCD Nature Conservation Practice Note No. 3 ¨C The Use of Plant Names; 

¡¤           DEVB TC(W) No. 2/2012 - Allocation of Space for Quality Greening on Roads; 

¡¤           DEVB TC(W) No. 6/2015 - Maintenance of Vegetation and Hard Landscape Features; 

¡¤           DEVB TC(W) No. 4/2020 - Tree Preservation; 

¡¤           DEVB TC(W) No. 5/2020- Registration and Preservation of Old and Valuable Trees; 

¡¤           DEVB TC(W) No. 9/2020 Blue-Green Drainage Infrastructure;

¡¤           LAO PN 2/2020 - Tree Preservation and Removal Proposal for Building Development in Private Projects Compliance of Tree Preservation Clause under Lease;

¡¤           Guidelines on Tree Transplanting (September 2014) issued by Greening, Landscape and Tree Management (GLTM) Section of DevB;

¡¤           Guidelines on Tree Preservation during Development (April 2015) issued by GLTM Section of DevB; and

¡¤           Study on Landscape Value Mapping of Hong Kong. 

9.3.2        The Outline Zoning Plan (OZP) gazette under the Town Planning Ordinance provides the statutory framework for land use development.  Reference was made to the Tuen Mun Outline Zoning Plan No. S/TM/35 gazette under section 9(1)(a) of Town Planning Ordinance on 21 December 2018.

9.4              Assessment Methodology

Landscape Impact Assessment Methodology

9.4.1        The landscape impact was assessed according to the following procedures

¡¤         Identification and description of the baseline landscape resources (LRs) and landscape characters area (LCAs) found within the Assessment area.  This is achieved by site visits and desktop study of topographical maps, information databases and photographs.

¡¤         Assessment of the degree of sensitivity of the landscape resources (LRs) and landscape character areas (LCAs).  This is influenced by a number of factors including whether the resource/character is common or rare, whether it is considered to be of local, regional, national or global importance, whether there are any statutory or regulatory limitations/requirements relating to the resource, the quality of the resource/character, the maturity of the resource and the ability of the resource/character to accommodate change. 

The sensitivity of each LR and LCA is classified as follows:

High:

Important landscape resources and landscape character of particularly distinctive in character or high importance, sensitive to relatively small change.

Medium:

Landscape resources and landscape character of moderately valued landscape characteristics reasonably tolerant to change.

Low:

Landscape resources and landscape character, the nature of which is largely tolerant to change.

¡¤         Identification of potential sources of landscape changes.  These are the various elements of the construction works and operation procedures that would generate landscape impact. 

Assessment of the potential magnitude of landscape changes.  Factors considered include:

-   the compatibility with the surrounding landscape;

-   the duration of the impact under construction and operational phases;

-   scale of development; and

-   reversibility of change.

 

The magnitude of landscape changes is classified as follows:

Large:

The landscape resources and landscape character would incur a major change.

Intermediate:

The landscape resources and landscape character would incur a moderate change.

Small:

The landscape resources and landscape character would incur slight or barely perceptible change.

Negligible:

The landscape resources and  landscape character would incur no discernible change.

¡¤         Identification of potential landscape mitigation measures.  These may take the form of adopting basic engineering design to prevent and/or minimise adverse landscape impact before adopting other mitigation or compensatory measures to alleviate the impacts.  Potential mitigation measures should also include the preservation of vegetation and natural landscape resources, transplanting trees with good condition and high amenity value, enhancement of existing landscape quality by providing of planting with screening, shading and ornamental value, re-vegetation of disturbed lands, compensatory planting, aesthetic design of aboveground structures including provision of finishes, colour scheme, texture of materials used and any measures to mitigate the impact on the existing and planned land use and visually sensitive receivers.  A programme for the mitigation measures is provided.  The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified. 

¡¤         Prediction of the significance of impacts before and after the implementation of the mitigation measures. Potential mitigation measures suggested would alleviate the landscape impact and enhance the landscape quality by reinstating the disturbed lands and improve the compatibility with the surrounding. By synthesizing the magnitude of the change and the sensitivity of the various LRs and LCAs, it is possible to categorise impacts in a logical, well-reasoned and consistent fashion.  Table 9.1 shows the rationale for dividing the degree of significance into four thresholds, namely insubstantial, slight, moderate, and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of change and a low-medium-high degree of sensitivity of landscape resource and character. 


 

Table 9.1      Relationship between Sensitivity and Magnitude of Change in Defining Impact Significance

Magnitude of Change

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Insubstantial / Slight

Slight / Moderate

Moderate

Negligible

Insubstantial

Insubstantial

Insubstantial

 

Low

Medium

High

Sensitivity of Landscape Resource and Landscape Character Area

Note:  All impacts are Adverse unless otherwise noted with Beneficial.

The significance of landscape impact is categorised as follows:

Substantial:

Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality.

Moderate:

Adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality.

Slight:

Adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in existing landscape quality.

Insubstantial:

No discernible change in the existing landscape quality.

¡¤         Prediction of Acceptability of Impacts.  An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM.

Visual Impact Assessment Methodology

9.4.2        The visual impact was assessed according to the following procedures

¡¤         Identification of the Visual Envelope during the construction and operational phases of the project.  This is achieved by site visit and desktop study of topographic maps, photographs and preparation of cross-sections to determine visibility of the Project from various locations. 

¡¤         Appraisal of existing visual resources and character.  The existing visual resources and character as well as the future outlook of the visual system of the assessment area would be appraised.  Visual resources such as key views, viewing corridors/viewing directions, harbour and ridgelines, and visual characters would also be identified on plans

¡¤         Identification of the VSRs within the Visual Envelope at construction and operational phases.  These are the people who would reside within, work within, play within, or travel through, the Visual Envelope.

Assessment of the degree of sensitivity of the VSRs.  Factors considered include: 

-   the type of VSRs, which is classified according to whether the person is at home, at work, at play, or travelling.  Those who view the change from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life.  Those who view the impact from their workplace are considered to be only moderately sensitive as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life.  The degree to which this applies depends on whether the workplace is industrial, retail or commercial.  Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity.  Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel.

-   the relative numbers of VSRs will be expressed in terms of whether there are ¡°many¡±, ¡°medium¡± and ¡°few¡± VSRs in any one category of VSR 

-   other factors which are considered (as required by EIAO GN 8/2010) include the number of VSRs, the value and quality of existing views, the availability and amenity of alternative views, the duration or frequency of view, and the degree of visibility. 

The sensitivity of VSRs is classified as follows:

High:

The VSR is highly sensitive to any change in their viewing experience.

Medium:

The VSR is moderately sensitive to any change in their viewing experience.

Low:

The VSR is only slightly sensitive to any change in their viewing experience.

 

¡¤         Identification of potential sources of visual changes.  These are the various elements of the construction works and operation that would generate visual changes.

Assessment of the potential magnitude of visual changes.  Factors considered include:

-   the compatibility with the surrounding landscape;

-   the duration of the impact;

-   the potential blockage of view;

-   the reversibility of the impact;

-   the scale of the impact and distance of the source of impact from the viewer; and

-   the degree of visibility of the impact, and the degree of which the impact dominates the field of vision of the viewer. 

The magnitude of visual changes is classified as follows: 

Large:

The VSRs would suffer a major change in their viewing experience.

Intermediate:

The VSRs would suffer a moderate change in their viewing experience.

Small:

The VSRs would suffer a small change in their viewing experience.

Negligible:

The VSRs would suffer no discernible change in their viewing experience.

¡¤         Identification of potential visual mitigation measures.  These may take the form of adopting basic engineering design to prevent and/or minimise adverse visual impact before adopting other mitigation or compensatory measures to alleviate the impacts.  Potential mitigation measures should also include the preservation of vegetation and natural landscape resources, provision of screen planting, re-vegetation of disturbed lands, compensatory planting, aesthetic design of aboveground structures including provision of finishes, colour scheme, texture of materials used and any measures to mitigate the impact on the existing and planned land use and visually sensitive receivers.  A programme for the mitigation measures is provided.  The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified. 

¡¤         Prediction of the significance of visual impacts before and after the implementation of the mitigation measures.  By synthesizing the magnitude of the various visual impact and the sensitivity of the VSR, it is possible to categorise the degree of significance of the impacts in a logical, well-reasoned and consistent fashion.  Table 9.2 shows the rationale for dividing the degree of significance into four thresholds, namely, insubstantial, slight, moderate and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of change and a low-medium-high degree of sensitivity of VSRs. 

 

Table 9.2      Relationship between Visually Sensitive Receivers (VSRs) Sensitivity and Magnitude of Change in Defining Impact Significance

Magnitude of Change

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Insubstantial / Slight

Slight / Moderate

Moderate

Negligible

Insubstantial

Insubstantial

Insubstantial

 

Low

Medium

High

Sensitivity of Visually Sensitive Receivers (VSRs)

Note:  All impacts are Adverse unless otherwise noted with Beneficial.

The significance of visual impact is categorised as follows:

Substantial:

Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing visual quality.

Moderate:

Adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing visual quality.

Slight:

Adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in existing visual quality.

Insubstantial:

No discernible change in the existing visual quality.

¡¤         Prediction of Acceptability of Impacts.  An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM. 

9.5              Review of Planning Control Framework

9.5.1         A review of the existing and planned development framework for the proposed works and for the surroundings was considered.  It aims to gain an insight to the outlook of area affected, identify potential resources and sensitive receivers, and evaluated the compatibility between the Project and the existing and planned landuse setting.

9.5.2         The assessment area is covered by Approved Tuen Mun Outline Zoning Plan No. S/TM/35. The review of OZPs has not only included a review of the plans, but also the ¡®Notes¡¯ and ¡°Explanatory Statements¡± which accompany these plans. The proposed development is overlaid on the affected OZPs are shown in Figure No. C1502/C/TME/ACM/M57/102. The land uses zones to be potentially affected by the Project and the future outlook of the area is discussed in Table 9.3.

9.5.3         A16 Station is currently located within the Government, Institution or Community (GIC) Zone and Open Space (O) Zone of the Approved Tuen Mun Outline Zoning Plan No. S/TM/35.  The proposed aboveground structures in Area 16 including the station, entrances, the siding, viaduct and cooling tower would have conflicts with the current use of facilities such as Hoi Wong Road Pet Garden, Community Green Station, Tuen Mun Swimming Pool, KMB Tuen Mun (South) Depot and Citybus Tuen Mun Depot, etc.   The affected facilities will be relocated within the Tuen Mun District to serve the need of local users.

9.5.4         The TMS Station, the viaduct, ventilation shafts, entrances and plant buildings are generally located along the Wu King Road. The proposed pick-up drop-off (PUDO) area and Entrance C of TMS Station are generally within Open Space (O) Zone of the Approved Tuen Mun Outline Zoning Plan No. S/TM/35.  Majority of temporary works areas / sites in Tuen Mun South during the construction phase will be reinstated upon completion of works.  The affected Tuen Mun Public Toilet and Wu King Road Garden are planned to be re-provided in like for like basis in Tuen Mun Promenade and Wu King Road Garden respectively. Proposed use of planting to mitigate the potential impacts will be ensure that the structure is integrated and compatible with the landscape planning context of the area.

9.5.5         The Tuen Mun River Bridge between A16 and TMS Station are located within the Open Space (O) Zone of the Approved Tuen Mun Outline Zoning Plan No. S/TM/35. Upon completion of the works, the disturbed garden area will be reinstated to provide public space for passive recreational uses serving the need of local users as well as the general public.

9.5.6         Temporary platforms would be constructed to support the foundation and piers construction works along the embankment edge of Tuen Mun River Channel.

 

 

 

Table 9.3        Summary of the Review of Planning and Development Control Framework

OZP Plan

Title and No.

Land Use Zoning

Approx. Area within 100m Assessment Area (ha)

Area Affected (ha)

(Approximate % of Zoning Affected) 

Potential Change to the OZP and the Anticipated Future Outlook of the Area due to the Project

Approved Tuen Mun Outline Zoning Plan No. S/TM/35 (21/12/2018)

Open Space (O)

25.75

Approx. 10.25

(39.4%)

 

 

 

Some of the open space will be temporarily affected. One of the open spaces, Hoi Wong Road Pet Garden will be permanently demolished due to the construction of A16 Station and viaduct structure but will be relocated at the area adjacent to the Tuen Mun River (Eastern Bank) Garden. The original site of pet garden will be pending for future residential development. Since the future residential development is under a separate project, any recommendation to the change in OZP should be made in separate report.

Besides, other open space, Wu King Road Garden will be temporarily removed for the proposed works site of TMS Station. Half of the Garden will be reinstated while half of it will be converted into pick-up drop off (PUDO) area.

In addition, open space along the Tuen Mun River Promenade on both side of the river channel, open space in Pui To Road Garden, Tuen Mun Waterfront Promenadem Tuen Mun Road Safety Town  will be temporarily affected. Existing vegetation will be removed due to construction of temporary work platforms and the viaduct. The affected area will be reinstated in like-for-like basis.  Therefore, there will be no potential change to these area within this zone.  

Green Belt (GB)

3

0

(0%)

The existing natural hillside woodland in GB Zone located behind Tin Hau Temple will not be affected by the Project. There will be no potential change to this zone. 

Industrial (I)

3.9

0

(0%)

The existing industrial buildings/uses along Tun Hau Road, San Ping Circuit and Wu Shan Road adjacent to Tuen Mun Typhoon Shelter will not be affected by the proposed development. There will be no potential change to this zone. 

Residential Group A (R(A))

18.0

Approx. 0.31

(1.72%)

A small portion of space within Zone R(A) will be temporarily converted into the proposed works sites.  Area included the existing pedestrian path along the western side of the Wu King Road.  Upon the completion of the works, the existing facilities will be reinstated.  There will be no potential change to this zone. 

Government, Institution or Community (G/IC)

17.61

Approx. 7.26

(41.2%)

The existing Tuen Mun Swimming Pool and the short-term tenancy car parking area at Tuen Yee Street will be permanently demolished due to the construction of A16 Station and viaduct structure and will be pending for future residential development and the planned sports ground. Since these developments are under separate projects, any recommendation to the change in OZP should be made in separate report(s). 

Besides, the existing short-term tenancy car parking at Wu Shan Road opposite to the Yuent Wu Villa will be temporarily affected by the proposed works area. The affected car park will be reinstated in like-for-like basis. Therefore, there will be no potential change to this zone.

Other Specific Uses (OU)

3.10

Approx.0.08

(2.58%)

A small portion of area within Zone OU will be temporarily used as the proposed works area. Upon the completion of the construction works, the existing facilities will be reinstated. There will be no potential change to this zone. 

Residential (Group B) (R(B))

1.16

0.05

(4.31%)

A small portion of area within Zone R(B) will be temporarily used as the proposed works sites. Upon the completion of the construction works, existing facilities will be reinstated. There will be no potential change to this zone. 

 

Undetermined (U)

4.35

Approx. 1.11

(25.5%)

This area adjoins Mong Wing Street and a portion of area within this zone will be temporarily used as an off-site works area for site office, material storage and temporary tree nursery.  Currently, it is used as a site office for the project ¡°Tuen Mun ¨C Chek Lap Kok Link (TM-CLKL)¡± and would be handed over by HyD in 2024 tentatively.   There will be no potential change to this zone. 

 

9.5.7         In general, majority of the affected areas within the Approved Tuen Mun Outline Zoning Plan No. S/TM/35 include the area within Open Space (O) Zone and GIC Zone.  A portion of the area within the GIC Zone will be potentially changed due to the future developments including residential development and the planned Sports Ground at Area 16.  Since these future developments are under separate projects, any recommendation to the change in OZP should be made in separate report(s).  For the other zoning area, the area affected will be reinstated and would be no potential changes to the OZP.

9.6              Baseline Study

9.6.1        The baseline condition of existing landscape resources is described below.

Physical Landscape Resources

Landform

9.6.2        The assessment area for on-site works areas generally comprises flat reclaimed land. The only topographical feature is the natural hillside at the back of the Tin Hau Temple.

Water Body

9.6.3        The channelised Tuen Mun River Channel and Tuen Mun Typhoon Shelter are the main water bodies identified within the assessment area.

Open Spaces

9.6.4        The assessment area is densely urbanised area with. provision of open spaces. Public open spaces are identified within the assessment boundary, varying from small sitting out rest garden, riverside garden, pet garden, and promenade to district open space such as Tuen Mun Park, Wu King Road Garden, Wu Shan Riverside Park and Tuen Mun Promenade, etc. In general, all public open spaces within a densely urbanised area are considered to be of high to medium value and sensitivity due to their importance and maturity of the landscape resources within the city.

Existing Trees

9.6.5         A broad brush tree survey was carried out within the assessment area. There is approximately 2,209 nos. of trees within the proposed works areas.  None of these are Registered Old and Valuable Trees (OVTs) on the records Greening, Landscape and Tree Management Section (GLTMS) of DevB. Tree species included Acacia confusa, Aleurites moluccana, Archontophoenix alexandrae, Bauhinia x blakeana, Callistemon viminalis, Caryata mitis, Cinnamomum camphora, Delonix regia, Ficus microcarpa, Lagerstroemia speciose, Livistona chinensis, Melaleuca cajuputi subsq. Cumingiana, Phoenix roebelenii, Roystonea regia and Tabebuia chrysanthus, etc. Among the identified species, there are no endangered or rare plant species. There are three trees, two of which are Ficus microcarpa and the other Ficus virens, with DBH over 1m which are identified as Tree of Particular Interest (TPI). Besides, Lagerstroemia species (i.e. Lagerstroemia indica and Lagerstroemia speciosa) and Magnoliaceae species (i.e. Michelia x alba) are also listed under Cap. 96, however, they are not considered as species of conservation importance in this assessment as they are widely planted as ornamental trees in Hong Kong and are likely to be imported and planted for amenity purpose. Many of trees were found within LCSD open spaces and amenity areas along the roadside. They were generally of medium to high amenity value and sensitivity.  The locations of the tree group are presented in Appendix 9.1.

Landscape Resources (LRs)

9.6.6         Baseline landscape resources (LR) which will be potentially affected by the Project are described and appraised together with their sensitivity are analysed and evaluated in Table 9.4.  The locations of landscape resources are mapped in Figure No. C1502/C/TME/ACM/M57/103. Photo views showing the landscape resources are illustrated in Figure No. C1502/C/TME/ACM/M57/ 104 to 105.

Table 9.4      Landscape Resources and Their Sensitivity

ID No.

Landscape Resources

Descriptions

Sensitivity

LR 1.1

Tuen Mun Park

Tuen Mun Park is an important open space that serves as a district open space to Tuen Mun neighbourhood. Approximate 6,400 sqm. of this open space is within the proposed works site. Approx. 331 nos. of trees were found within the Tuen Mun Park and planter along the riveside,  including Acacia confusa, Cinnamomun camphora, Delonix regia, Melaeuca cajuputi subsq, cumingiana and Ficus mircrocarpa, etc. In addition, there is one TPI identified which is Ficus virens. The  tree is identified with DBH over 1m while with fair health and structural condition. The tree species found are common amenity species for ornamental purpose. The diversity and maturity of vegetation contribute to the landscape context. This Park has high landscape quality and is of district importance. The ability to accommodate change is considered as low.

High

LR 1.2

Pui To Road (South) Rest Garden

This LR consists of densely planted semi-mature to mature sized Ficus spp. while trees in various species and size and ornamental shrubs with good health and amenity quality are found. Approx. 158 nos. of trees were identified within the LR including Delonix regia, Ficus benjamina, Ficus mircocarpa, Livistona chinensis and Peltophorum pterocarpum, etc. Recreational facilities such as covered seats and children play facilities are provided for leisure purpose. The quality of this landscape resource is high.  The ability to accommodate change is considered as low.

High

LR 1.3

Promenade along the southern bank of Tuen Mun River Channel

This LR is located along the southern bank of the Tuen Mun River Channel which include the landscaping area adjacent to the Tuen Mun Park, Yau Oi Estates, Tuen Mun Swimming Pool, and Community Green Station. This LR feature with bike trail and tree planting area along the promenade. Approx. 155 nos. of trees were found including Acacia confusa, Albizia lebbek, Bauhinia x blakeana, Cinnamomum camphora and Delonix regia, etc.  The vegetations are semi-mature in size and fair in amenity quality. The quality of the landscape resource is medium. The ability to accommodate change is considered as medium.

Medium

LR 1.4

Tuen Mun River (Eastern Bank) Garden

Area of this sitting out garden is approx. 770 sqm. and is relatively new (established in 2018) in comparing to other open spaces. The garden features with ornamental shrubs, pavilions and elderly fitness station for recreational usage. No trees were found within this LR. The quality of landscape resources is considered as medium. The ability to accommodate change is considered as medium.

Medium

LR 1.5

Hoi Wong Road Garden and Pet Garden

This pet garden is a local open space (approx. 3,500 sqm.) adjacent to the existing Tuen Mun Swimming Pool, with covered seating, raised planters and lawn area to pet for recreational purpose. Approx. 98 nos. of trees were found within the LR, which include Araucaria heterophylla, Bauhinia variegate, Caryata mitis, Delonix regia, Dypsis lutescens and Spathodea campanulate, etc. These tree are common species of Hong Kong and in general planted for mainly ornamental and screening purpose. The quality of this resources is medium and has moderate ability to accommodate change. The landscape quality of this resource is medium. The ability to accommodate change is considered as medium.

Medium

LR 1.6

Wu Shan Riverside Park

The area of riverside park is approx. 12,600sqm. running through Tuen Mun River Channel from Wong Chui Road to Wu Shan Recreation Playground. The riverside park features with several pocket spaces, children play and elderly fitness facilities and planting area for diverse ornamental trees and shrubs. Considering the landscape riverside park is relatively less mature, the quality of the landscape resources is considered as medium.  The ability to accommodate change is considered as medium.

Medium

LR 1.7

Riverside landscape adjacent to Tuen Mun Road Safety Town

The LR connects to the Tuen Mun Road Safety Town and Wu Shan Riverside Park, while feature with at-grade shrub and tree planting area for screening and ornamental purpose. Approx. 22 nos. of trees within this LR are common species of Hong Kong including Hibiscus tiliaceus, Lagerstroemia speciosa and Mangifera indica, etc. The quality of the landscape resource is medium. The ability to accommodate change is considered as medium.

Medium

LR 1.8

Tuen Mun Road Safety Town of Wu Shan Recreation Playground

This recreational space is part of component of the Wu Shan Recreation Playground (approx. 10,800 sqm.), where features with densely planted mature trees, vegetated earth mount and facilities that simulated road environment for educational purpose. Approx. 470 nos. of trees were found within the LR, which are common species of Hong Kong for amenity planting such as Acacia confusa, Bauhinia x blakeana, Callistemon viminalis, Cinnmomum camphora, Delonix regia, Ficus altissima, Ficus benjamina, Syzygium jambos, etc.   The quality of this resources is high and has low ability to accommodate change due to the maturity of the existing vegetation. The landscape sensitivity is considered as high.

High

LR 1.8B

Wu Shan Cycle Park of Wu Shan Recreation Playground

This LR is part of the component of the Wu Shan Recreation Playground. This LR features with cycle path, soccer pitch, basketball courts and children playground. The facilities are surrounded by densely planted mature trees which bring significant vegetation contribution to landscape context. The quality of this resources is high and has low ability to accommodate change due to the maturity of the existing vegetation. The landscape sensitivity is considered as high.

High

LR 1.9

Wu King Road Garden

This local open space is approx. 4,900 sqm. that feature with pavilions, seating areas, and at-grade planting area for amenity purpose. Approx. 47 nos. of trees were found including Hibiscus tiliaceus, Lagerstroemia speciosa, Plumeria rubra and Terminalia mantaly, which are common species of Hong Kong as ornamental planting. The trees are of a generally medium height and size and are of medium health and amenity quality. The quality of the landscape resources is medium.  The ability to accommodate change is considered as medium.

Medium

LR 1.10

Tuen Mun Promenade

This LR is one of the major entrances between Wu King Road to the Promenade which feature with Tuen Mun Public Toilet and raised planter with seating out area for public leisure. The raised planter consists of densely planted trees and shrub in various species, size and height and are generally good in health and amenity purpose. Approx. 103 nos. of trees were found within the LR including Archontophoenix alexandrae, Casuarina equisetifolia, Cocos nucifer, Ficus microcarpa, Junipers chinensis Kaizuca, Plumeria rubra, Pongamia pinnata and Ravenala madagascariensis, etc. Among these tree species, several semi-mature to mature Ficus spp. are found along one side of the promenade while newly planted trees are found on another side of the promenade. The quality of this landscape resource is high.  The ability to accommodate change is considered as low.

High

LR 2

Landscape area in Tin Hau Temple and adjacent Hillside

This LR comprises of the civic plaza in front of the Tin Hau Temple and natural hillside at the back of the Temple. The civic plaza features with multiple newly built structure including covered seating area, public toilet, and Fa Pau Exhibition hall.  The vegetation is mainly located at the edge of the plaza feature with mostly standard sized trees and tall shrubs for screening and ornamental purpose. Approx. 10,000 sqm. of natural hillside found within the LR.  At the back of the Temple is densely planted with various plant species. The quality of landscape resource is considered as high.  The ability to accommodate change is considered as low.

High

LR 3

Landscape area along Riverside

Tuen Mun River Channel had been channelised since the 1970s. The river was channelised into concrete riverbed and embankment. Small cluster of weed and self-seeding plant such as Leucaena leucocephala can be found along river channel. Considered that the vegetation is mostly undesirable species with low amenity value. The landscape quality of this resource is low. The ability to accommodate change is considered as high.

Low

LR 4

Landscape area in urban development areas

This LR is largely given over to residential land use in Tuen Mun. The landscape resources are mainly characterised by trees and shrub planting around residential estates for ornamental purpose.  The trees are of a generally various height and size and are of fair to good health and amenity quality. The quality of this landscape resource is medium. The ability to accommodate change is considered as medium. 

Medium

LR 5.1

Roadside Landscape along Tin Hau Road

The roadside amenity along Tin Hau Road contains the individual tree pit planting. The trees are of a generally various height and size and are of fair health and amenity quality.  The quality of this landscape resource is low. The ability to accommodate change is considered as high.

Low

LR 5.2

Roadside Landscape adjacent to Northern side of Wong Chu Road

The roadside amenity area at the North side of Wong Chu Road consists of several trees and ornamental shrub plantings on hydroseeding surface for roadside beautification and greenery purpose. Approx. 58 nos. of trees were found including Callistemon viminalis, Ficus bengamina ¡®Veriegata¡¯, Melaleuca bracteate ¡®Revolution Gold¡¯, Tabebuia argentea and Tabebuia rasea , etc.  Approximately 4,500 sqm. of this LR is within the assessment boundary.  The amenity value of this area is considered as medium, thus the landscape quality of this resource is medium. The ability to accommodate change is considered as medium.

Medium

LR 5.3

Roadside Landscape along Wu King Road

The roadside amenity area along Wu King Road consists of semi-mature to mature trees and shrub planting. Approx. 183 nos. of trees were found which are common species of Hong Kong including Callistemon viminalis, Grevillea robusta, Melaleuca cajuputi subsq. Cumingiana and Livistona chinensis, etc.  Trees in this area have medium amenity value.  The landscape quality of this resource is medium. The ability to accommodate change is considered as medium.

Medium

LR 6.1

Vegetation within Temporary Construction site

This LR adjoins to Tin Hau Road and is currently a temporary construction site. Small cluster of vegetation can be found at the edge of this LR. Approx. 49 nos. of trees identified in this area and are  mainly self-seeding plants such as Leucaena leucocephala and other wild grass. The quality of the landscape resources is low and very commonly found in Hong Kong. The ability to accommodate change is considered as high.

Low

LR 6.2

Vegetation around the Hong Kong Institute of Construction (HKIC), Tuen Mun Training Ground and bus depot

Small cluster of vegetation can be found at the edge of the training ground and bus depot for screening function. Approx. 52 nos. of trees including Bombax ceiba, Celtis sinensis, Macaranga tanarius var. tomentosa, Leucaena leucocephala and wild grass were found. The quality of the landscape resources is low and very commonly found in Hong Kong. The ability to accommodate change is considered as high.

Low

LR 6.3

Vegetation surrounding the Temporary Car Park

There are some cluster of vegetation and individual trees found at the edges of this LR.  Approx. 197 nos. of trees including Celtis sinensis, Ficus microcarpa, Ficus religiosa, Leucaena leucocephala and Melia azedarach, etc were found within this LR. Considered that the vegetation found are mainly comment species and self-seeding plants such as Leucaena leucocephala. The quality of the landscape resources is low and very commonly found in Hong Kong.  The ability to accommodate change is considered as high.

Low

LR 6.4

Amenity planting in Tuen Mun Swimming Pool

Trees and vegetation found in this LR are mainly semi-mature in size. Approx. 359 nos. of trees were found and species included Acacia confusa, Araucaria heterophylla, Bischofia javanica, Callistemon viminalis, Dypsis lutescens, Platycladus orientalis, Livistona chinensis, Ficus microcarpa, Lagerstroemia speciosa and Roystonea regia. These trees are common species of Hong Kong and in fair to good quality. In addition, there are two TPI identified which are Ficus microcarpa. These two trees are identified with DBH over 1m while with fair health and structural condition. In general, the sensitivity is considered as medium as trees found are common amenity planting of Hong Kong in various size. The ability to accommodate change is considered as medium.

Medium

 

LR 6.5

Amenity planting in Community Green Station

Cluster of vegetation and individual trees can be found in this LR which mainly provides ornamental value to the general public. Approx. 21 nos. of trees were found and mostly are relatively young or newly planted. Species included Ficus microcarpa, Livistona chinensis, Magnolia grandiflora, Michelia x alba and Tabebuia chrysanthus.  The quality of this landscape resources is low.  The ability to accommodate change is considered as high.

Low

LR 6.6

Vegetation along the edges of the construction works area

Cluster of vegetation and individual trees can be found in this LR which are mainly Acacia confusa on slope area or self-seeding species and shrubs planting along the edges of the construction works area. No trees were identified within the proposed off-site works area. The quality of this landscape resources is considered as fair to low and the ability to accommodate change is considered as high.

Low

LR 7

Coastal Water

This LR included a vast water body between Tuen Mun and Tung Chung. The shoreline was modified with rock and boulders. No vegetation can be found along the seashore. The quality of this landscape resources is considered as fair to good. The ability to accommodate change is considered as medium. 

Medium

LR 8

Landscaping area along Mong Fa Street and Mong Wing Street

This LR included a section of modified water course. Vegetation can be found surrounding the modified water course. Species included Acacia confusa, Casuarina equisetifolia, Leucaena leucocephala, Macaranga tanarius, etc. The quality of this landscape resources is considered as fair and the ability to accommodate change is considered as medium.

Medium

 

Landscape Character Areas (LCAs)

9.6.7        Landscape character areas were identified within the assessment area in accordance with the ¡°Study on Landscape Value Mapping of Hong Kong¡±.  Landscape character areas which will be potentially affected by the Project are described and appraised together with their sensitivity analysed and evaluated in Table 9.5.  The locations of landscape character areas are mapped in Figure No. C1502/C/TME/ACM/M57/106.  Photo views showing the landscape character are illustrated in Figure No. C1502/C/TME/ACM/M57/107.

Table 9.5      Landscape Character Areas and Their Sensitivity

ID No.

Landscape Character Area

Descriptions

Sensitivity

LCA 1

Mixed Modern Comprehensive Urban Development Landscape

These are areas of urban landscape characterised by relatively low density and mixed scales of development.  Tuen Mun Swimming Pool, Tuen Mun Community Green Station and other G/IC facilities such as Castle Peak Bay Ambulance Depot and Fire Station are identified. Vegetation included amenity planting and occasional parks. This LCA is very common throughout Hong Kong.

Medium

LCA 2

Residential Urban Landscape

This is a LCA which is largely given over to residential land use in Tuen Mun. It is developed on flat reclaimed land and characterised by its medium to high-rise residential estates, set amongst open space, together with associated highways, footbridges, school or community facilities and retail facilities. Vegetation includes roadside trees and shrub planting and planting in open spaces and around residential estates.  The result is a fairly homogenous, ordered landscape comprising largely built elements softened to a certain extent by the effects of surrounding planting and greenery. The landscape resources are common species of Hong Kong and no rare species are identified.  This is a medium quality landscape in urban area with medium sensitivity.

Medium

 

LCA 3

Transportation Corridor Landscape

This LCA is characterised by the major highways and railways corridors.  Major features include flyovers, footbridges, railway line and associated uses. Between the roads and railways are landscaped embankments, generally with standard sized vegetation of trees and shrubs. This type of LCA is common to Hong Kong and is generally less sensitive to railway development.

Low

LCA 4

Park Urban Landscape

This is a large recreational landscape which provides both passive recreation such as ornamental planting, lawns, pathways, sitting areas, water features and pavilions; and active recreation facilities such as tennis courts etc.  It is a high quality landscape character to Tuen Mun District.

High

LCA 5

Riverside Landscape

This LCA is characterised by the channelised Tuen Mun River featuring with 5 Tuen Mun footbridges. This is an extensive recreational landscape providing both passive and active recreational spaces such as bicycle trail, riverside garden and seating out area. It is a medium quality landscape character to Tuen Mun District.

Medium

LCA 6

Industrial Urban Landscape

This LCA is characterised by the industrial buildings constructed side by side in very dense arrangements, bus depot, and associated uses on extensive flat area. Limited vegetation and roadside trees can be found. This LCA is generally low quality landscape in urban area.

Low

LCA 7

Residential Urban Fringe Landscape

This LCA is mainly characterised by the small-scaled structures of Tin Hau Temple and several construction sites and feature with a small portion of natural hillside woodland. Common plant species such as Ficus macrocarpa, Ficus variegata, Macaranga tanarius and Melia azedarach can be found within the vegetated hillside. Apart from the vegetated hillside, limited vegetation can be found within the construction sites. This LCA is generally low to medium quality landscape in urban area with low sensitivity. 

Low

 

LCA 8

Miscellaneous Urban Fringe Landscape

This LCA found on the periphery of the Tuen Mun District which comprising roads, highway structures, vegetated hillside, construction works area, etc.  This LCA characterized by low-density structure and mixture of undeveloped area. This LCA is generally low to medium quality landscape in urban area with low sensitivity.

Low

 

Visual Envelope

9.6.8        Visual Envelopes were identified by site visit and desktop study of topographic maps and photographs to determine visibility of the Project from various locations. Two Visual Envelopes are identified in the project area:

¡¤         The project area for the TME alignment is located within the high dense developed urban areas of Tuen Mun. The visual envelope of the Project is starching from Tuen Mun Station to the north; Tuen Mun Promenade to the south; high rise residential buildings and open space such as Tuen Mun Park and Wu Shan Recreation Playground to the west and east.  The key visual resources within or in the vicinity of visual envelope include are the existing greenery in open space along the Tuen Mun River Channel such as Tuen Mun Park, Pui To Road (South) Garden, Wu Shan Riverside Park, Wu Shan Cycle Park, and the entire riverside promenade along the river channel and existing hillside close to Tin Hau Temple Plaza. Considered that the Project comprises of the aboveground structures during both construction and operational phases, the visual envelope will be confined by the existing buildings around the works area and the front row of high-rise buildings. The visual envelope of the Project during the construction and operational phases is illustrated in Figure No. C1502/C/TME/ACM/M57/101 and Figure No. C1502/C/TME/ACM/M57/109.

¡¤         For the off-site works area in Mong Wing Street, it is surrounding by slope buffer greening and low-rise developments such as warehouse and G/IC facilities. The visual envelope of this area is confined from densely vegetated slope at north and west, Lung Mun Road and warehouse structure in south and Tuen Mun-Chek Lap Kok Link in the east.  The visual envelope of the off-site works area during the construction is illustrated in Figure No. C1502/C/TME/ACM/M57/145.

 

Visually Sensitive Receivers (VSRs)

9.6.9        Within the visual envelope, a number of key VSRs were identified during construction and operational phases. They are listed, together with their baseline assessment and sensitivity, in Table 9.6 and mapped in Figure No. C1502/C/TME/ACM/M57/108 & Figure No. C1502/C/TME/ACM/M57/145

9.6.10      The sensitivity of VSRs is assessed in accordance with EIAO Guidance Note No. 8/2010.  Key factors including type of VSRs, number of individuals of the VSRs, quality of existing view, availability of alternative views, degree of visibility, duration of view and frequency of view of the VSRs are evaluated.

9.6.11      Types of VSRs are generally categorised in accordance with the landuse of the areas where the VSRs are located.  There are mainly 6 types of VSRs, namely Recreational, Residential, Institutional, Industrial, Commercial and Travelling VSRs

9.6.12      O1, O2, O4, O6 to O8, O11 to O13 and O15 are recreational VSRs with many to medium number of individuals. The quality of existing view is good to fair. They all have alternative views and partial to full degree of visibility. They have medium to long duration of view and occasional to frequent view. Their sensitivity is considered as medium to high.

9.6.13      O9 and O10 are recreational VSRs with many to medium number of individuals. The quality of existing view is good. They all have alternative views and only have glimpse degree of visibility as the open spaces are surrounded by densely planted vegetations. They have short duration of view and rare view. Their sensitivity is considered as low.

9.6.14      O3, O5 and O14 are recreational VSRs with few numbers of individuals. The quality of existing view is fair. They all have alternative views and have partial to full degree of visibility. They have short duration of view and rare to occasional view. Their sensitivity is considered as low.

9.6.15      R1 to R10 are residential VSRs with many numbers of individuals. The quality of existing view is good. They all have full degree of visibility to the Project with long and frequent viewing duration. Although they all have alternative views, the change of the view from their homes will have effect on their perception of view, thus their sensitivity is considered as high.

9.6.16      GIC1 to GIC7 are institutional VSRs with few to medium number of individuals. The quality of existing view is fair to good. They all have alternative views and have full to partial degree of visibility. They have medium duration of view and occasional view. Considered that viewers engaged in working activities are less sensitive to change, thus their sensitivity is considered as medium. 

9.6.17      I1 is the industrial VSRs with many numbers of individuals. The quality of existing view is good that the viewers can view the entire Tuen Mun River Channel. The viewers have full degree of visibility, and medium and occasional viewing duration to the view.  Although this VSRs are generally of lower sensitivity, given this VSR group will be right next to the Project with direct views, it is considered to have medium sensitivity.

9.6.18      I2 to I3 are industrial VSRs with medium numbers of individuals. The quality of existing view is fair. They have short to medium duration of view and rare to occasional viewing frequency. Due to shielding by natural topography and buildings, views to the Project are considered partial and glimpse, thus these VSR is considered to have medium to low sensitivity. 

9.6.19      C1 is a commercial VSR with many numbers of individuals. The quality of existing view is fair. The views are likely to be partial given other structures and vegetation shielding it. The duration of view is considered as medium with occasional viewing frequency. Therefore, its sensitivity is considered as medium.

9.6.20      T1 to T5 is traveller VSRs with few to many numbers of individuals. The quality of existing view is fair. They all have alternative views and have partial to full degree of visibility. They have short to medium duration of view and occasional to frequent view. Their sensitivity is considered as low to medium.

 


Table 9.6       Visually Sensitive Receivers (VSRs) and Their Sensitivity

VSR ID.

Visually Sensitive Receiver (VSR)

Type of VSRs

Number of Individuals (Many/ Medium/ Few)

Quality of Existing View

(Good/Fair/ Poor)

Availability of Alternative Views

(Yes/No)

Degree of Visibility

(Full/ Partial/ Glimpse)

Duration of View (Long/ Medium/ Short)

Frequency of View (Frequent/ Occasional/ Rare)

Sensitivity

(Low, Medium, High)

O1

Recreational users in Tuen Mun Park

Recreational

Many

Good

Yes

Partial

Medium

Occasional

High

O2

Recreational users in Pui To Road (South) Rest Garden

Recreational

Medium

Good

Yes

Full

Medium

Occasional

Medium

O3

Recreational users in Tin Hau Temple

Recreational

Few

Fair

Yes

Partial

Short

Rare

Low

O4

Recreational users along the riverside promenade, including the users in Tuen Mun River (Eastern Bank) Garden

Recreational

Many

Good

Yes

Full

Long

Frequent

High

O5

Potential recreational users in the reprovision of Hoi Wong Road Pet Garden

Recreational

Few

Fair

Yes

Partial

Short

Rare

Low

O6

Recreational users in Wu Shan Riverside Park

Recreational

Medium

Good

Yes

Full

Medium

Occasional

Medium

O7

Recreational users in Tuen Mun Road Safety Town and along the riverside promenade, adjacent to Wu Shan Cycle Park

Recreational

Medium

Good

Yes

Full

Medium

Occasional

Medium

O8

Potential recreational users in planned Sports Ground

Recreational

Medium

Good

Yes

Full

Medium

Occasional

Medium

O9

Recreational users in Wu Shan Cycle Park

Recreational

Medium

Good

Yes

Glimpse

Short

Rare

Low

O10

Recreational users in Wu Shan Recreation Playground

Recreational

Many

Good

Yes

Glimpse

Short

Rare

Low

O11

Recreational users in Wu King Road Garden

Recreational

Medium

Good

Yes

Full

Medium

Frequent

High

O12

Recreational users in Soccer Pitch adjacent to Wu Yuet House

Recreational

Medium

Fair

Yes

Partial

Medium

Occasional

Medium

O13

Recreational users along the Tuen Mun Promenade close to the Tuen Mun Pier

Recreational

Many

Good

Yes

Full

Medium

Frequent

High

O14

Potential recreational users of the planned open space at the junction of Tin Hau Road and Yip Wong Road

Recreational

Few

Fair

Yes

Full

Short

Occasional

Low

O15

Recreational users of Yau Oi Sports Centre

Recreational

Medium

Fair

Yes

Partial

Short

Frequent

Medium

R1

Residents of Century Gateway, Kam Wah Garden and Trend Plaza

Residential

Many

Good

Yes

Full

Long

Frequent

High

R2

Residents of Planned public housing estate at Tin Hau Road

Residential

Many

Good

Yes

Full

Long

Frequent

High

R3

Residents of Yau Oi Estate

Residential

Many

Good

Yes

Full

Long

Frequent

High

R4

Residents of Lung Mun Oasis, Glorious Garden, The Esplanade and Sun Tuen Mun Centre

Residential

Many

Good

Yes

Full

Long

Frequent

High

R5

Residents of Goodview Garden, Oceania Heights and Nerine Cove

Residential

Many

Good

Yes

Full

Long

Frequent

High

R6

Residents of Regency Bay and planned residential property development at Hang Fu Street

Residential

Many

Good

Yes

Full

Long

Frequent

High

R7

Residents of Wu King Estate

Residential

Many

Good

Yes

Full

Long

Frequent

High

R8

Residents of Tuen Mun Wu Hong Police Quarters

Residential

Many

Good

Yes

Full

Long

Frequent

High

R9

Residents of Yuet Wu Villa and Sui Hei Court

Residential

Many

Good

Yes

Full

Long

Frequent

High

R10

Residents of Richland Garden and Pierhead Garden

Residential

Many

Good

Yes

Full

Long

Frequent

High

R11

Potential residential users in future property development in A16

Residential

Many

Good

Yes

Full

Long

Frequent

High

GIC1

Tuen Mun Division Police Station

Institutional

Medium

Good

Yes

Full

Medium

Occasional

Medium

GIC2

PCCW Tsing Shan Wan Hing On Lane Exchange Building

Institutional

Few

Fair

Yes

Partial

Medium

Occasional

Medium

GIC3

Tuen Mun Wu Hong Clinic

Institutional

Medium

Fair

Yes

Full

Medium

Occasional

Medium

GIC4

Users of Yan Chai Hospital Law Chan Chor Si Primary School, Tung Wah Group of Hospitals Sun Hoi Directors¡¯ College and Taoist Ching Chung Primary School (Wu King Estate) 

Institutional

Medium

Fair

Yes

Full

Medium

Occasional

Medium

GIC5

Castle Peak Police Station

Institutional

Medium

Fair

Yes

Full

Medium

Occasional

Medium

GIC6

Users of Yan Chai Hospital Ho Sik Nam Primary School

Institutional

Medium

Fair

Yes

Full

Medium

Occasional

Medium

GIC7

Customs and Excise Department Harbour And River Trade Division and Pillar Point Fire Station

Institutional

Medium

Fair

Yes

Full

Medium

Occasional

Medium

I1

Users in industrial buildings, including Mai Kei Industrial Building, Win Sun Manufacturing Building and Yau Tak Industrial Building

Industrials

Many

Good

Yes

Full

Medium

Occasional

Medium

I2

Users in Nan Fung Industrial City

Industrials

Medium

Fair

Yes

Partial

Medium

Occasional

Medium

I3

Users in MTR Tuen Mun Depot

Industrials

Medium

Fair

Yes

Glimpse

Short

Rare

Low

C1

Siu Hei Market

Commercial

Many

Fair

Yes

Partial

Medium

Occasional

Medium

T1

Travellers at the adjacent riverside cycle track

Traveller

Few

Fair

Yes

Partial

Short

Occasional

Low

T2

Travellers at Wong Chu Road

Traveller

Many

Fair

Yes

Partial

Short

Occasional

Low

T3

Travellers at Hoi Wong Road

Traveller

Many

Fair

Yes

Partial

Short

Occasional

Low

T4

Travellers along Wu King Road

Traveller

Many

Fair

Yes

Full

Short

Frequent

Medium

T5

Travellers along Tuen Mun Chek Lap Kok Tunnel Road

Traveller

Medium

Fair

Yes

Full

Short

Occasional

Low

Note: R = Residential; C=Commercial, GIC=Government/Institution/Community; I=Industrial; O=Open Space; T=Transport Related/ Traveller


9.7              Landscape Impact Assessment

Sources of Landscape Impact

9.7.1        The sources of landscape impact due to the Project would create various levels of landscape impact during construction and operational phases of the Project. Potential impacts would result from the temporary and permanent works during construction phase and permanent aboveground structure elements during operational phase.

9.7.2        The sources of landscape impact in the construction phase would include:

¡¤         Modification of overrun section connecting to TUM Station;

¡¤         Construction of temporary platforms for construction of foundation and piers along the embankment edge of Tuen Mun River Channel;

¡¤         Construction of the viaduct and finishing works;

¡¤         Construction of A16 Station;

¡¤         Demolition of existing structure Tuen Mun Swimming Pool, Community Green Station and Tuen Mun Pier Public Toilet;

¡¤         Construction of TMS Station;

¡¤         Temporary access path along the Tuen Mun Promenade;

¡¤         Temporary site access areas, site cabins and heavy machinery;

¡¤         Loss of existing trees and other vegetation due to the construction works; and

¡¤         Changes of landscape character temporarily due to the construction works.

9.7.3        The sources of landscape impact in the operational phase would include:

¡¤         Operation of A16 Station, TMS Station and viaduct structures;

¡¤         Permanent removal of existing trees and other vegetation; and

¡¤         Changes of landscape character permanently due to the Project.

 

Magnitude of Landscape Impact

9.7.4        The magnitude of unmitigated landscape impact associated with the construction and operational phases of the Project were assessed and are described in Table 9.7.


 

Table 9.7       Magnitude of Landscape Impact during Construction and Operation

ID No.

Landscape Resources/ Landscape Character Areas

Description of Works

Description of Impacts

Magnitude of Change

(Large/ Intermediate/ Small/ Negligible)

Construction

Operation

Landscape Resources

LR 1.1

Tuen Mun Park

Proposed works site with maintenance works such as tree pruning only

 

Maintenance works such as tree pruning will be required at Tuen Mun Park during the construction phase.  The tree pruning works, if required, will be evaluated and conducted by corresponding maintenance parties/certified arborist, so to minimize the impact to the existing trees.  Considered that the maintenance works will be conducted as necessary during the construction phase, it is expected that only a small number of trees may be affected by the maintenance works and no trees within this LR will be removed or transplanted.

Small

Small

LR 1.2

Pui To Road (South) Rest Garden

Temporary works for construction of site access to temporary platform, site office, and piling up construction materials.

Reinstatement of the Garden in like-for-like basis upon completion of works.

No permanent works are proposed during operational phase. 

 

An area of approx. 4,600 sqm. Within this LR will be proposed as works area.

Temporary alienation of existing trees during construction phase to temporary usage of space for site office and/or pilling up of construction materials.

About 50 nos. of trees including the existing Ficus Spp. and other ornamental tree species will be affected and proposed to be removed or transplanted.

Intermediate

Intermediate

LR 1.3

Promenade along the southern bank of Tuen Mun River Channel

Temporary footpath and cycling track diversion works near Tuen Mun Park  and Yau Oi Estate during construction phase.

Temporary works sites for construction access, construction of viaduct,  A16 Station and Tuen Mun River Bridge.

 

Reinstatement of landscaping area along the promenade in like-for-like basis upon completion of works.

 

No permanent works are proposed during operational phase. 

Temporary alienation of existing trees and vegetation during construction phase to temporary usage of space for construction access.

The entire LR (approx. 2,375 sqm.) will be proposed as works site and approx. 158 nos. of trees will be affected and proposed to be removed or transplanted.

Intermediate

Intermediate

LR 1.4

Tuen Mun River (Eastern Bank) Garden

Temporary works for construction of viaduct and piling up construction materials.

Reinstatement of the Garden area in like-for-like basis upon completion of works.

No permanent works are proposed during operational phase.  

Temporary alienation of existing vegetation during construction phase for temporary storage use.

Entire LR (approx. 820 sqm.) will be proposed as works site. As no trees were found within this LR, thus only the existing ornamental shrub planting will be removed or transplanted.

Intermediate

Intermediate

LR 1.5

Hoi Wong Road Garden & Pet Garden

Temporary Works for the construction of A16 Station and piling up construction material.

The Garden will permanently be demolished and replaced by the cooling tower of Station A16 during operational phase.

Permanent localised alienation for A16 Station construction and associated works.

Entire LR (approx. 3,500 sqm.) and approx. 98 nos. of trees will be affected and proposed to be removed or transplanted.

 

Large

Large

LR 1.6

Wu Shan Riverside Park

Nil

Nil

Negligible

Negligible

LR 1.7

Riverside amenity area adjacent to Tuen Mun Road Safety Town

Temporary works for construction of viaduct and Tuen Mun River Bridge.

Reinstatement of the riverside in like-for-like basis upon completion of works.

No permanent works are proposed during operational phase.  

Temporary alienation of existing vegetation during construction phase.

Approx. 15 nos. of tree to be affected by construction works will be proposed to be removed or transplanted.

 

Small

Small

LR 1.8

Tuen Mun Road Safety Town of Wu Shan Recreation Playground

Demolition of existing Tuen Mun Road Safety Town.

Temporary Works for the construction of viaduct connecting the Tuen Mun River Bridge during construction phase.

Reinstatement of Tuen Mun Road Safety Town.

No permanent works are proposed during operational phase.

During construction phase, approx. 10,800 Sqm. of this open space will be temporarily alienated.

Approx. 169 nos. of trees to be affected by construction works will be proposed to be removed or transplanted.

Reinstatement of Tuen Mun Road Safety Town will be carried out after the construction of the viaduct.

During operational phase, there would not be any net permanent loss of open space.

Intermediate

Intermediate

LR 1.8B

Tuen Mun Cycle Park of Wu Shan Recreation Playground

Nil

Nil

Negligible

Negligible

LR 1.9

Wu King Road Garden

Demolition of existing Wu King Road Garden and associated structures.

Temporary Works for the construction of TMS Station and piling up construction materials.

Provision of Pick-Up Drop-Off (PUDO) area and MTR structure buildings.

Reinstatement of Wu King Road Garden in like-for-like basis upon completion of works.

No permanent works are proposed during operational phase. 

During construction phase, the Garden (approx. 4,900 sqm.) will permanently be demolished

Tree planting within the Garden will be temporarily alienated. Approx. 47 nos. of trees to be affected by construction works.

Wu King Road Garden will be partially re-provided. Part of the Garden will be replaced by the provision of PUDO area.

Large

Large

LR 1.10

Tuen Mun Promenade

Demolition of existing Tuen Mun Public Toilet and associated structures, temporary works for construction of TMS Station and associated structures during construction phase.

Reprovision of Tuen Mun Public Toilet and surrounding landscaping area upon completion of works.

No permanent works are proposed during operational phase. 

 

During construction phase, the existing landscaping area adjacent to Tuen Mun Public Toilet will be removed.

Approx. 5,000 Sqm. of this LR and approx. 43 nos. of trees will be affected.

Pruning of existing Ficus Spp. for opening up sufficient headroom for access of heavy machines.

Small

Small

LR 2

Landscape area in Tin Hau Temple and Adjacent Hillside

Nil

Nil

Negligible

Negligible

LR 3

Landscape Area along Riverside

Construction of temporary works platform as construction access for temporary works of A16 Station and associated viaduct structure

A portion of viaduct structure will be permanently located along the riverside.

 

Temporary alienation of existing vegetation on the embarkment during construction phase. Vegetation such as the undesirable species and self-seeding vegetation will be removed.

Small

Small

LR 4

Landscape area in urban development areas

Nil

Nil

Negligible

Negligible

LR 5.1

Roadside Landscape along Tin Hau Road

Nil

Nil

Negligible

Negligible

LR 5.2

Roadside Landscape adjacent to Northern side of Wong Chu Road

Temporary works for supporting the construction of the Project.

No permanent works are proposed during operational phase. 

During construction phase, approx. 1,200 sqm.  of roadside amenity area will be affected. Approx. 19 nos. of trees to be affected by the proposed work.

Small

Small

LR 5.3

Roadside Landscape along Wu King Road

Temporary works for construction of TMS Station, road modification, demolition of existing footbridges and utilities diversion during construction phase

No permanent works are proposed during operational phase. 

During construction, approx. 20,000 Sqm. of this LR, including approx. 154 nos. of roadside trees will be affected during construction. Tree species include Melaleuca cajuputi subsq. Cumingiana, Livistona chinensis, and Callistemon viminalis, etc.

Large

Large

LR 6.1

Vegetation within Temporary Construction site

Temporary works for supporting viaduct construction and piling up construction materials.

No permanent works are proposed during operational phase.

Temporary alienation of existing vegetation during construction phase.

Approx.2,500 Sqm. of this LR and approx. 49 nos. of trees to be affected by construction works will be proposed to be removed or transplanted.

 

Small

Small

LR 6.2

Vegetation around the HKIC, Tuen Mun Training Ground and bus depot

Temporary works for supporting A16 Station construction and piling up construction materials.

 

Temporary alienation of existing vegetation during construction phase.

Approx. 24,000 Sqm. of this LR with around 52 nos. of trees to be affected by construction works.

 

Small

Small

LR 6.3

Vegetation surrounding the temporary car park

Temporary works for inspection of precast segment, loading and unloading construction materials and contractor¡¯s site office.

No permanent works are proposed during operational phase.

Approx. 18,500 Sqm. of this LR will be used for the proposed works.

 

Small

Small

LR 6.4

Amenity planting in Tuen Mun Swimming Pool

Demolition works of Tuen Mun Swimming Pool.

Temporary works for the construction of A16 Station and viaduct structures, cooling tower and associated E&M buildings.

No permanent works are proposed during operational phase.

 

During the construction phase,  approx. 38,000 Sqm. of this LR with around 359 nos. of existing trees will be permanently loss due to the construction of A16 Station and viaduct structures.

Trees to be affected by the construction will be proposed to be removed or transplanted. Tree species include Acacia confusa, Archontophoenix alexandrae, Bischofia javanica, Cinnamomum camphora, Dypsis lutescens, Livistona chinensis and Platycladus orientalis, etc. 

Two TPI will be inevitably affected and would be transplanted within the A16 area as far as practicable. The tree transplanting arrangement will be reviewed during detailed design stage.

Large

Large

LR 6.5

Amenity planting in Community Green Station

Demolition works of Community Green Station.

Temporary works for the construction of A16 Station and viaduct structures.

 

During the construction phase, approx. 2,800 Sqm. of this LR will be permanently affected due to the construction of A16 Station and viaduct structures.

Approx. 21 nos. of trees to be affected by the construction will be proposed to be removed or transplanted.

Small

Small

LR 6.6

Vegetation along the edges of the construction works area

Currently used as a site office for the project ¡° Tuen Mun ¨C Chek Lap Kok Link (TM-CLKL) and would be handed over by Highway Department in 2024 tentatively.

Temporary off-site works area for the Project, only be used as site office, material storage for pre-cast unit (non-dusty material) and temporary tree nursery.

No excavation works, earthworks and stockpiling of dusty material to be conducted.

During the construction phase, approx.11,000 sqm. of this LR will be temporarily used as off-site works area.

Vegetation found within the off-site works area are mainly shrubs and self-seeding species. No trees were identified. Hence, it is assuming no impact on the landscape resources.

Negligible

Negligible

LR 7

Coastal Water

Nil

Nil

Negligible

Negligible

LR 8

Landscaping area along Ming Fat Street and Mong Wing Street

Nil

Nil

Negligible

Negligible

Landscape Character Areas

LCA 1

Mixed Modern Comprehensive Urban Development Landscape

Demolition of Tuen Mun Swimming Pool.

Construction works for viaduct structures and A16 Station.

 

During construction phase, approx. 42,000 Sqm. of this LCA existing trees will be permanently affected due to the construction viaduct structures and A16 Station. Approx. 380 nos. of trees will be affected and to be removed or transplanted.

The construction works are temporary and localised, therefore the impact of this LCA due to the Project will be intermediate.

Intermediate

Intermediate

LCA 2

Residential Urban Landscape

Temporary works for the construction of TMS Station and associated structures,  viaducts, Road modification and re-provision of Wu King Road Garden.

Approx. 40,700 sqm of this LCA will be affected during the construction phase. Among the affected LCA, there will approx. 413 nos. of trees will be affected.

Since the nature of the Project is similar to existing LCA which is considered as localised alienation of existing infrastructure, the impact on this LCA due to the Project will be small.

Small

Small

LCA 3

Transportation Corridor Landscape

Construction works for viaduct structures and A16 Station.

                                                                                                    

Approx. 4,500 Sqm. of this LCA will be permanently affected by the construction works. Among this LCA, there will be approx. 19 nos. of trees affected.

Temporary and localised alienation of the construction of viaduct structures and for A16 Station.

Subject to the demolition of existing Hoi Wong Road Pet Garden, new pet garden will be re-provided upon the completion of viaduct construction.   

Small

Small

LCA 4

Park Urban Landscape

Nil

Nil

Negligible

Negligible

LCA 5

Riverside Landscape

Temporary Works for the construction of Tuen Mun River Bridge, temporary platform as work sites for A16 Station and viaduct structures between TUM and A16 Station during the construction phase. 

During the operational phase, abutment and piers of the viaduct, A16 Station and the Tuen Mun River Bridge will permanently be located along the river channel.                                                             

During the construction, temporary platform will be built in the middle of the river channel and along river channel as work sites for viaduct and station construction between TUM and A16 Station, and the Tuen Mun River bridge. Approx. 370 nos. of trees will be affected.

During operational phase, a portion of the LCA will be permanently alienated by the viaduct structures, A16 Station and Tuen Mun River Bridge.

Small

Small

LCA 6

Industrial Urban Landscape

Temporary works for the construction of viaduct structures.

                                                                                                           

During the construction phase, approx. 22,800 Sqm. of this LCA will become work sites for supporting the construction of viaduct structures, A16 Station and Tuen Mun River Bridge.  

 

The existing facilities and vegetation including approx. 52 nos. of existing trees will be permanently loss due to the Project.  This area will be handed over to other for property development and planned Sports Ground after the construction of the Project. The entire character of this LCA will be changed permanently with residential and commercial complex buildings with open space for public usage.

 

However, the changes on this LCA due to the Project is relatively small in scale and localised. Therefore the magnitude of change during both construction and operational phases is considered as small.

Small

Small

LCA 7

Residential Urban Fringe Landscape

Nil

Nil

Negligible

Negligible

LCA 8

Miscellaneous Urban Fringe Landscape

Currently used as a site office for the project ¡° Tuen Mun ¨C Chek Lap Kok Link (TM-CLKL) and would be handed over by Highway Department in 2024 tentatively.

Temporary off-site works area for the Project, only be used as site office, material storage for pre-cast unit (non-dusty material) and temporary tree nursery.

No excavation works, earthworks and stockpiling of dusty material to be conducted.

During the construction phase, approx.11,000 sqm. of this LCA will be temporarily used as off-site works area.  Considered that the proposed usage is in a same nature of current usage.

Therefore, the magnitude of change during both construction and operational phases is considered as negligible

 

Negligible

Negligible

 

Significance of Unmitigated Landscape Impact 

9.7.5        The significance of landscape impact, before implementation of mitigation measures, in the construction and operational phases are assessed and presented in Table 9.11.

9.7.6        The significance of unmitigated impacts on the affected LRs and LCAs would vary from substantial to insubstantial.  They are described as below. 

9.7.7        LR 1.1 ¨C Tuen Mun Park is an open space with high sensitivity subject to its maturity of the trees and dense vegetation coverage. Since this LR is close to the proposed works in LR 1.3, maintenance works such as tree pruning will be required at Tuen Mun Park during the construction phase. The tree pruning works, if required, will be evaluated and conducted by corresponding maintenance parties/certified arborist, so to minimize the impact to the existing trees.  Considered that the maintenance works will be conducted as necessary during the construction phase, it is expected that only a small number of trees may be affected by the maintenance works and no trees within this LR will be felled. Therefore, the magnitude of impact on this LR due to the Project is considered as small and the resultant unmitigated impact during construction and operational phases is moderate.

9.7.8        LR¨C1.2 - Pui To Road (South) Rest Garden is an open space with high sensitivity. This garden will be acquired as access path to the temporary platform of the construction viaduct of the alignment from TUM to A16 station. During construction phase, a portion of existing trees will be affected for providing space for inspection works on precast segment and construction of viaduct. Upon the completion of works, the disturbed garden will be reinstated in like for like basis. The magnitude of impact on this LR due to the Project is considered as intermediate and the resultant unmitigated impact during construction and operational phases is substantial. 

9.7.9        LR 1.3 ¨C Promenade along the southern bank of Tuen Mun River Channel features with bicycle track and pedestrian trail is identified with medium sensitivity. A portion of promenade will be acquired for providing space for construction access and viaduct construction. Upon the completion of works, the affected landscape resources will be reinstated in like for like basis. The magnitude of impact on this LR due to the Project is considered as intermediate and the resultant unmitigated impact during construction and operational phases is moderate.

9.7.10      LR 1.4 ¨C Tuen Mun River (Eastern Bank) Garden is an open space along the promenade of Tuen Mun River Channel with medium sensitivity.  The garden will be acquired for providing space for viaduct construction. Upon the completion of works, the disturbed garden will be reinstated in like for like basis. The magnitude of impact on this LR due to the Project is considered as intermediate and the resultant unmitigated impact during construction and operational phases is moderate. 

9.7.11      LR 1.5 ¨C Hoi Wong Road Pet Garden is an open space with medium sensitivity. The existing garden will be acquired for the construction of the aboveground structure of the alignment from the south of the existing TUM to A16 Station. The existing pet garden will be relocated in the proposed area in LR 5.2, adjacent to the Tuen Mun River (Eastern Bank) Garden.  Existing trees will be inevitably affected by the Project.  Upon completion of the construction of the aboveground structure, a portion of the area will be handed over to developer of the planned property development at Area 16. Considered that the entire LR will be permanently and irreversibly lost due to the construction of the Project, the magnitude of impact on this LR due to the Project is considered as large and the resultant unmitigated impact during construction and operational phases is moderate. 

9.7.12      LR 1.7 ¨C Riverside amenity area adjacent to Tuen Mun Road Safety Town is an open space with medium sensitivity. The existing trees are the key resource of this LR while it will be inevitably affected by the construction of viaduct and the Tuen Mun River Bridge. This area will be temporarily alienated during construction phase and a number of trees within this LR will be removed or transplanted.  This impact is considered as small. The unmitigated landscape impact on these LRs during construction and operational phases is slight.

9.7.13      LR 1.8 ¨C Tuen Mun Road Safety Town of Wu Shan Recreational Playground is one of the landscape components of Wu Shan Recreational Playground with high sensitivity. A portion of the open space will be acquired for the construction of the aboveground structure of Tuen Mun River Bridge. During the construction phase, demolition work of Tuen Mu Road Safety Town will be conducted for providing spaces for track and trip works, and construction of viaduct and Tuen Mun River Bridge.  Upon completion of the construction, reinstatement of Tuen Mun Road Safety Town including hard and soft landscape will be carried out.  As such, impact on this LR due to the Project is limited to construction phase.  The magnitude of impact is considered as intermediate and the resultant unmitigated impact is moderate.

9.7.14      LR 1.9 ¨C Wu King Road Garden is an open space with medium sensitivity. A portion of the open space will be acquired for the construction of the aboveground structure of TMS Station. During the construction phase, demolition work of Wu King Road Garden will be conducted for providing spaces for track and trip works, and construction of viaduct and TMS Station.  Upon completion of the construction, reinstatement of Wu King Road Garden including hard and soft landscape will be carried out.  As such, impact on this LR due to the Project is limited to construction phase.  The magnitude of impact is considered as large and the resultant unmitigated impact is moderate.

9.7.15      LR 1.10 ¨C Tuen Mun Promenade is an open space with medium sensitivity. During the construction phase, there will be works site for station entrance construction. The existing Tuen Mun Ferry Pier Public Toilet and covered walkway will be demolished for construction of TMS Station. Upon the completion of Project, the facilities will be re-provided at similar location for serving public usage.  Existing semi-mature to mature trees will be inevitably and permanently loss due to the construction of the Project. A portion of LR will be acquired as works site for construction access for the station entrance construction. Some of the existing trees will potentially be pruned to provide sufficient headroom for the access of the powered mechanical equipment.  This impact is considered as small.  The unmitigated landscape impact on these LRs during construction and operation of the Project is moderate. 

9.7.16      LR 3 ¨C Landscaping area along Riverside is part of the landscape resources found along the embarkment of Tuen Mun Riverside. Small cluster of vegetation found mainly undesirable species (i.e. Leucaena leucocephala) or self-seeding plant which are common resources in Hong Kong and considered as low sensitivity to change. During construction phase, a portion of LR will be acquired as works site for temporary platform for viaduct construction between Tuen Mun Station and A16 Station. Existing vegetation found along the embarkment of Tuen Mun Riverside will therefore be inevitably removed. This impact is considered as small. The unmitigated landscape impact on these LRs during construction and operation of the Project is insubstantial. 

9.7.17      LR 5.2 ¨C Roadside landscape adjacent to the northern side of Wong Chu Road is part of the landscaping along the Wong Chu Road. The trees in this LR are common species for roadside beautification purpose and of average standard size. The sensitivity of this LR is considered as medium.  One third of the site will be the works site for viaduct construction.  Some of the existing trees within the works area will be removed from the site.  The impact is considered as small and the resultant unmitigated impact is slight during construction and operation of the Project.

9.7.18      LR 5.3 ¨C Roadside landscape along Wu King Road is the key resources of this LR. The trees found are common species for roadside beautification purpose and of average semi-mature size. The sensitivity of this LR is considered as medium.  Within this LR, there will be works site for permanent road modification, construction of TMS Station and associated structure such as viaduct, entrance, and utilities buildings, etc. Due to the road modification works, most of the trees within this LR will be inevitably and permanently removed or transplanted. Upon the completion of construction works, the amenity area will be reinstated along the Wu King Road. The impact is considered as large.  The unmitigated impact on this LR during construction and operation of the Project is substantial.

9.7.19      LR 6.1 ¨C Vegetation within Temporary Construction Site is the key landscape resources of this LR. The vegetation found is mainly self-seeding plant and weed which are commonly found in Hong Kong with low amenity value. The sensitivity of this LR is considered as low. This LR will be a works site for site access to temporary platform and viaduct construction for the alignment between TUM and A16 Station. Existing vegetation on site will be removed. The magnitude of impact to this LR is considered as small. The unmitigated landscape impact on this LR during construction and operational phases is slight.

9.7.20      LR 6.2 ¨C Vegetation around the HKIC, Tuen Mun Training Ground and bus depot is the key landscape resources of this LR. The vegetation found is mainly self-seeding plant and trees in standard size. The sensitivity of this LR is considered as low. This LR will be a works site for viaduct construction during the construction stage and the existing vegetation will be removed.  The magnitude of impact to this LR caused by the construction works is considered as small. The unmitigated landscape impact on this LR during construction and operational phases is slight.

9.7.21      LR 6.3 ¨C Vegetation surrounding the Temporary Car Park is the key landscape resources of this LR. The vegetation found is mainly self-seeding plant and trees in standard to semi-mature size. The sensitivity of this LR is considered as low. This LR will be a works area for unloading of precast segment and contractor¡¯s site office. Considered most of the trees found located at the edge of the LR, trees will be potentially retained. The magnitude of impact to this LR is considered as small. The unmitigated landscape impact on this LR during construction and operational phases is slight.

9.7.22      LR 6.4 ¨C Amenity planting in Tuen Mun Swimming Pool is the key landscape resources of this LR. The vegetation found are mainly semi mature to mature sized trees and palm trees for ornamental, screening, and shading function. The sensitivity of this LR is considered as medium. This LR will be the works sites for construction of A16 Station and viaduct structure.  Existing trees and vegetation will be removed. The two TPI would potentially be transplanted within the A16 area as far as practicable subject to approval of Tree Preservation and Removal Proposal (TPRP).   The magnitude of impact to this LR is considered as large. The unmitigated landscape impact on this LR during construction and operational phases is moderate.

9.7.23      LR 6.5 ¨C Amenity planting in Community Green Station is the key landscape resources of this LR. The vegetation in this LR are mainly newly planted and standard sized trees for ornamental use. The sensitivity of this LR is considered as low. The LR will be a works sites for construction of A16 Station and viaduct structure. Existing trees and vegetation will be removed.  The magnitude of impact to this LR is considered as small. The unmitigated landscape impact on this LR during construction and operational phases is slight.

9.7.24      LCA 1 ¨C The Mixed Modern Comprehensive Urban Development Landscape features with amenity planting within the Tuen Mun Swimming Pool and Community Green and other GIC building structures.  The sensitivity of this LCA is considered as medium. This LCA will be the temporary works sites for A16 Station and viaduct structures. Existing buildings structures and tree will be permanently removed.   The magnitude of impact to this LCA is considered as intermediate. The unmitigated landscape impact on this LCA during construction and operational phases is moderate.

9.7.25      LCA 2 ¨C The Residential Urban Landscape features with residential buildings and amenity planting within the residential housing for ornamental usage. The sensitivity of this LCA is considered as medium. A small portion of this LCA will be the temporary works sites for the construction of TMS Station and associated structures. Existing trees to be affected will be removed permanently or transplanted. Considered that the temporary construction works are localised and the changes to the surrounding is relatively small, therefore the magnitude of impact to this LCA is considered as small. The unmitigated landscape impact on this LCA during construction and operational phases is slight.

9.7.26      LCA 3 ¨C The Transportation Corridor Landscape features with roadside facilities and amenity planning area for roadside beautification purpose. The sensitivity of this LCA is considered as low. The existing vegetation will be removed permanently due to the temporary works sites for construction of A16 Station and viaduct structures. Considered that the temporary construction works are localised and the changes to the surrounding is relatively small, therefore the magnitude of impact to this LCA is considered as small. The unmitigated landscape impact on this LCA during construction and operational phases is slight.

9.7.27      LCA 5 ¨C This LCA features with the channelised river and open spaces on both sides of the channel. The sensitivity of this LCA is considered as medium. Only the vegetation along the eastern side of the river channel will be affected, the scale of the impact area is localised and to be reinstated in like-for-like basis in the operational phase. Therefore the magnitude of impact to this LCA is considered as small. The unmitigated landscape impact on this LCA during construction and operational phases is considered as slight.

9.7.28      LCA 6 ¨C Most of the vegetation will be permanently removed due to the A16 Station and viaduct construction works. The affected area will be handed over to other parties for the future developments (i.e. planned sports ground and residential development at Area 16) after completion of construction works.  Considered that the change of this LCA due to the Project is relatively small in scale. The magnitude of impact to this LCA is considered as small. The unmitigated landscape impact on this LCA during construction and operational phases is considered as slight.

9.8              Visual Impact Assessment

Sources of Visual Impact

9.8.1        The sources of visual impact due to the Project would create varying levels of visual impact during construction and operational phases of the Project. Potential impacts would result from the temporary works during construction phase and permanent aboveground structure elements during operational phase.

9.8.2        The sources of visual impact in the construction phase would include:

¡¤         Modification of overrun section connecting to TUM Station;

¡¤         Construction of temporary platforms for construction of foundation and piers along the embankment edge of Tuen Mun River Channel;

¡¤         Construction of the viaduct and finishing works;

¡¤         Construction of A16 Station;

¡¤         Demolition of existing structure Tuen Mun Swimming Pool, Community Green Station, Tuen Mun Pier Public Toilet, Wu King Road Garden and Tuen Mun Road Safety Town;

¡¤         Construction of TMS Station;

¡¤         Temporary access path along the Tuen Mun Promenade;

¡¤         Temporary site access areas, site cabins and heavy machinery;

¡¤         Loss of existing trees and other vegetation due to the construction works;

¡¤         Changes of landscape character temporarily due to the construction works; and

¡¤         Reinstatement of the affected garden, park, riverside promenade and roadside amenity area, including the Pui To Road (South) Rest Garden, Tuen Mun Riverside (Eastern Bank) Garden, Hoi Wong Road Pet Garden, Riverside promenade adjacent to Tuen Mun Park, Tuen Mun Road Safety Town, Wu King Road Garden, and Tuen Mun Promenade.

9.8.3        The sources of visual impact in the operational phase would include:

¡¤         Aboveground structures including A16 Station, TMS Station and viaduct structures;

¡¤         Permanent removal of existing trees and other vegetation; and

¡¤         Changes of landscape character permanently due to the Project.

Magnitude of Visual Impact  

9.8.4        The magnitude of impacts during construction and operational phases was assessed based on the viewing distance, compatibility of the Project with the surrounding landscape, duration of impacts, scale of development, reversibility of change and potential blockage of view as shown in Table 9.8. 

9.8.5        During the construction of the northern section of the Project (i.e. between TUM and A16 Stations), the proposed temporary platform at Tuen Mun River Channel, temporary works sites at Pui To Road (South) Rest Garden, along the Riverside adjacent to Tuen Mun Park, Riverside adjacent to Yau Oi Estate and Tuen Mun River (Eastern Bank) Garden, construction of viaduct structures between TUM and A16 Stations are generally low to medium compatibility to the surrounding landscape.  Both the duration of impact and the scale of the works is medium. The changes are irreversible During the operational phase, the sources of impact on the VSRs comes from the viaduct structures only. The compatibility of this section to the surrounding landscape is considered as medium. The duration of impact is long and the scale is still considered as medium but localised. The changes are considered as not reversible.  Considered that the viaduct is aboveground structure and visible to the VSRs in both construction and operational phases, the magnitude of impact would be considered similar in both phases. There would be small magnitude of impact on VSRs, O3, R1, R2, I2 and T1 in both phases as there would be partially blockage and the viewing distance is relatively far. There would be intermediate magnitude of impact on VSRs O1, O2, O5, R3, GIC1 and I1 in both phases as there would be partial to no potential blockage of view and VSR O14 in operational phase only as the reprovision of planned open space to be provide after the completion of the Projects. There would be large magnitude of impact on VSR O4 in both phases who view the viaduct structures and temporary works sites at a closer distance.

9.8.6        During construction of A16 Station, the demolition of existing Tuen Mun Swimming Pool, Community Green Station and Hoi Wong Road Pet Garden, works sites for viaduct construction, road works and construction of A16 Station are generally medium compatibility to the surrounding landscape. Both the duration of impact and the scale of the works is medium. The changes are irreversible. During the operational phase, the sources of impact on these VSRs comes from the aboveground structures (i.e. A16 Station and viaduct) . The compatibility of this section is considered as medium and localised. The duration of impact is long and scale is considered as medium.  The changes are considered as not reversible. The magnitude of impact on VSRs from the Project in both construction and operational phases are considered as similar as they are all aboveground structures and visible in both phases. There would be small magnitude of impact on VSRs R5, R6 and I3 in both phases and VSR O8 in operational phase as they view from relatively far distance with no or partial potential blockage of view.  There would be intermediate magnitude of impact on VSRs O6, O15, R4, GIC2, GIC6, T2 and T3 in both phases.

9.8.7        During construction of the section between Tuen Mun River Bridge and viaduct structures connecting to TMS Station, the temporary works proposed in Wu Shan Recreation Playground and a portion of adjacent riverside promenade, construction of Tuen Mun River Bridge and viaduct structures connecting to TMS Station are general low compatibility to the surrounding landscape.  The duration of impact is medium and the scale of this section is medium. The changes are irreversible. During the operational phase, the source of impact on the VSRs comes from the aboveground structures including Tuen Mun River Bridge and viaduct structures. The compatibility to the surrounding landscape is medium. The duration of impact is long and the scale of development is medium but localised. The changes are irreversible. The magnitude of impact on VSRs in both construction and operational phases are considered as similar as they are all aboveground development and visible in both phases. There would be small magnitude of impact on VSR O10 who view from relatively far distance with no potential blockage of view. There would be intermediate magnitude of impact on VSR O9 as there would be partial potential blockage of view. There would be large magnitude of impact on VSR O7 as there would be partial potential blockage of view in short viewing distance.

9.8.8        During construction phase of TMS Station, the temporary works along the Wu King Road, demolition of existing footbridges crossing Wu King Road and Wu King Road Garden, road modification works and station construction are general low compatibility to the surrounding landscape. The duration of impact is medium and scale of this section is large to medium. The changes are irreversible. During operation, the sources of impact on the VSRs come from TMS Station and the compatibility to the surrounding landscape is medium. The duration of impact is long and the scale of this section is medium to large due to the close viewing distance between the VSRs and the station. The changes are irreversible. The magnitude of impact on VSRs from this section in both construction and operational phases are considered as similar as they are all aboveground structure and visible in both phases in similar location. There would be intermediate magnitude of impact on VSRs O12, R9, R10, GIC5 and C1 as there would be partial potential blockage of view. There would be large magnitude of impact on VSRs O11, O13, R7, R8, GIC3, GIC4 and T4 as the view will be partially or fully blocked by this section and they can view this section in a closely viewing distance toward the station.

9.8.9        During construction phase of the Project, the proposed off-site works area at Mong Wing Street will be only be used as site office, material storage for pre-cast unit and temporary tree nursery.  The compatibility of this off-site works area to the surrounding landscape is considered as medium and localised. The duration of impact is medium, and the scale of this development is medium. The changes are irreversible. Since the proposed usage is same as the current usage of the area, the magnitude of change on VSRs T5 and GIC7 in both construction and operational phases are considered as negligible.

Representative Viewpoints  

9.8.10      Photomontages at representative locations showing comparison between existing conditions, proposals on Day 1 after completion without mitigation measures, on Day 1 after completion with mitigation measures, and in Year 10 of Operation with mitigation measures were prepared in accordance with EIAO Guidance Note No. 8/2010.

9.8.11      The criteria for the selection of representative viewpoints for photomontages include: 

¡¤       the viewpoints which cover the aboveground structure viewed from major public viewpoint represents key VSRs or VSR groups who would be potentially affected by the proposed permanent structures; and

¡¤       the viewpoints should be able to represent the worst case scenarios and demonstrate the compatibility of the aboveground structures to the adjacent visual context and illustrate the visual effect during Day 1 without mitigation measures, Day 1 with mitigation measures and Year 10 with mitigation measures.

9.8.12      Based on the locations of the proposed aboveground structures, the proposed viewpoint from key representative VSRs are mapped in Figure No. C1502/C/TME/ACM/M57/109 and shown in Figure Nos. C1502/C/TME/ACM/M57/121 to 129, with their descriptions provided as follow:

¡¤         VP 1 ¨C View from the riverside promenade adjacent to Tuen Mun Park viewing the proposed viaduct structures connecting to TUM Station. This viewpoint is selected to represent the view of VSRs O1 and R1;

¡¤         VP 2 ¨C View from the riverside close to Tin Hau Temple, viewing at the proposed viaduct structures connecting to TUM Station. This viewpoint is selected to represent the view of VSRs T1, O2, O3, O14, R2, I1, I2 and GIC1;

¡¤         VP 3 ¨C View from Wu Shan Riverside Park looking toward Area A16 viewing the proposed A16 Station and viaduct structures. This viewpoint is selected to represent the view of VSRs along the western side of the Tuen Mun River Channel including VSRs R4, O6, O9 and I3;

¡¤         VP 4 ¨C View from the riverside close to Tuen Mun Road Safety Town looking toward Tuen Mun River Bridge and A16 Station. This viewpoint is selected to represent the view of VSRs close to the Tuen Mun River Bridge such as VSRs O7 and O10;

¡¤         VP 5 ¨C View close to the Wu King Road Garden viewing the viaduct structures and TMS Station. This viewpoint is selected to represent the view of VSRs from the eastern side of Wu King Road including VSRs GIC3, GIC5, R8, R9, C1, T4 and O11;

¡¤         VP 6 ¨C View from the Wu King Road adjacent to Wu Boon House viewing the west facing side of the TMS Station. This viewpoint is selected to represent the view of VSRs along the western side of the Wu King Road including VSRs R7, GIC4 and O12;

¡¤         VP 7 ¨C View from Tuen Mun Promenade looking toward the entrance/exit of TMS Station. This viewpoint is selected to represent the view of VSRs along the Tuen Promenade including the VSRs R10 and O13;

¡¤         VP 8 ¨C View from the planned Sports Ground in Area A16 toward the proposed A16 Station. This viewpoint is selected to represent the view of VSRs along the western side of the Hoi Wong Road including the VSRs O8, R6, R5, R11, GIC2 and T3; and

¡¤         VP 9 ¨C View from the site proposed for reprovisioning of Hoi Wong Road Pet Garden, adjacent to Tuen Mun River (Eastern Bank) Garden, looking toward viaduct structures. This viewpoint is selected to represent the view of VSRs close to Wong Chu Road including VSRs T2, O4, O5, O15, R3 and GIC6.


Table 9.8          Magnitude of Visual Impact during Construction and Operational Phases

VSR ID.

Visually Sensitive Receiver (VSR)

Source of Visual Impact

Approx. Viewing Distance

(m)

Compatibility of the Project with the Surrounding Landscape

(High/ Medium/ Low)

Duration of Impacts

(Long/ Medium/ Short)

Scale of Development

(Large/ Medium/ Small)

Reversibility of Change

(Yes/ No)

Potential Blockage of View

(Full/ Partial/ Nil)

Magnitude of Change

(Large/ Intermediate/ Small/ Negligible)

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

O1

Recreational users in Tuen Mun Park

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

15-100

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

O2

Recreational users in Pui To Road (South) Rest Garden

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

75

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

O3

Recreational users in Tin Hau Temple

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

100-150

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

O4

Recreational users along the riverside promenade, including the users in Tuen Mun River (Eastern Bank) Garden

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

15

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

O5

Potential recreational users in the reprovision of Hoi Wong Road Pet Garden

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

65

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

O6

Recreational users in Wu Shan Riverside Park

A16 Station

120

Medium

Medium

Medium

Long

Medium

Medium

No

No

partial

partial

Intermediate

Intermediate

O7

Recreational users in Tuen Mun Road Safety Town and along the riverside promenade, adjacent to Wu Shan Cycle Park

Viaduct Construction between Tuen Mun River Bridge and TMS Station

0

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

O8

Potential recreational users in planned Sports Ground

A16 Station

120

-

Medium

-

Long

-

Medium

-

No

-

Nil

-

Small

O9

Recreational users in Wu Shan Cycle Park

Viaduct Construction between Tuen Mun River Bridge and TMS Station

100

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

O10

Recreational users in Wu Shan Recreation Playground

Viaduct Construction between Tuen Mun River Bridge and TMS Station

230

Low

Medium

Medium

Long

Medium

Medium

No

No

Nil

Nil

Small

Small

O11

Recreational users in Wu King Road Garden

TMS Station, re-provision of part of the Wu King Road Garden

50

Low

Medium

Medium

Long

Medium

Medium

No

No

Full

Full

Large

Large

O12

Recreational users in Soccer Pitch adjacent to Wu Yuet House

TMS Station

70

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

O13

Recreational users along the Tuen Mun Promenade close to the Tuen Mun Pier

TMS Station

0

Low

Medium

Medium

Long

Medium

Medium

No

No

Full

Full

Large

Large

O14

Potential recreational users of planned open space at the junction of Tin Hau Road and Yip Wong Road

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

80

-

Medium

-

Long

-

Medium

-

No

-

Partial

-

Intermediate

O15

Recreational users of Yau Oi Sports Centre

A16 Station

150

Medium

Medium

Medium

Long

Medium

Medium

No

No

Full

Full

Intermediate

Intermediate

R1

Residents of Century Gateway, Kam Wah Garden and Trend Plaza

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

250

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

R2

Residents of Planned public housing estate at Tin Hau Road

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

150

Medium

Medium

Long

Long

Medium

Medium

No

No

Nil

Nil

Small

Small

R3

Residents of Yau Oi Estate

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

40-150

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

R4

Residents of Lung Mun Oasis, Glorious Garden, The Esplanade and Sun Tuen Mun Centre

A16 Station

150

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

R5

Residents of Goodview Garden, Oceania Heights and Nerine Cove

A16 Station

300

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

R6

Residents of Regency Bay and planned residential property development at Hang Fu Street

A16 Station

230

Medium

Medium

Medium

Long

Medium

Medium

No

No

Nil

Nil

Small

Small

R7

Residents of Wu King Estate

TMS Station

45

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

R8

Residents of Tuen Mun Wu Hong Police Quarters

TMS Station

45

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

R9

Residents of Yuet Wu Villa and Sui Hei Court

TMS Station

70-150

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

R10

Residents of Richland Garden and Pierhead Garden

TMS Station

50-150

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

R11

Potential residential users in future property development in A16

A16 Station

0-80

-

Medium

-

Long

-

Medium

-

No

-

Partial

-

Intermediate

GIC1

Tuen Mun Division Police Station

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

200

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

GIC2

PCCW Tsing Shan Wan Hing On Lane Exchange Building

A16 Station, planned Sports Ground and future property development

150

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

GIC3

Tuen Mun Wu Hong Clinic

TMS Station

50

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

GIC4

Users of Yan Chai Hospital Law Chan Chor Si Primary School, Tung Wah Group of Hospitals Sun Hoi Directors' College and Taoist Ching Chung Primary School (Wu King Estate) 

TMS Station

45

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

GIC5

Castle Peak Police Station

TMS Station

90

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

GIC6

Users of Yan Chai Hospital Ho Sik Nam Primary School

A16 Station

150

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

GIC7

Customs and Excise Department Harbour And River Trade Division and Pillar Point Fire Station

Temporary off-site works area including site office, material storage area and temporary nursery tree planting

200-250

Medium

Medium

Medium

Long

Medium

Medium

No

No

Nil

Nil

Negligible

Negligible

I1

Users in industrial buildings, including Mai Kei Industrial Building, Win Sun Manufacturing Building and Yau Tak Industrial Building

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

100

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

I2

Users in Nan Fung Industrial City

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

320

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

I3

Users in MTR Tuen Mun Depot

A16 Station

200

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

C1

Siu Hei Market

TMS Station

30

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

T1

Travellers at the adjacent riverside cycle track

Viaduct Construction between TUM and A16 Station, Construction of temporary platform

75

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Small

Small

T2

Travellers at Wong Chu Road

A16 Station

50-100

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

T3

Travellers at Hoi Wong Road

A16 Station

120-230

Medium

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Intermediate

Intermediate

T4

Travellers along the Wu King Road

TMS Station

0

Low

Medium

Medium

Long

Medium

Medium

No

No

Partial

Partial

Large

Large

T5

Travellers along Tuen Mun Chek Lap Kok Tunnel Road

Temporary off-site works area including site office, material storage area and temporary nursery tree planting

120

Medium

Medium

Medium

Long

Medium

Medium

No

No

Nil

Nil

Negligible

Negligible

Note: R = Residential; C=Commercial, GIC=Government/Institution/Community; I=Industrial; O=Open Space; T=Transport Related/ Traveller

Remark: 1. There is no rating (-) on the sensitivity, magnitude of impact, impact significance before mitigation measures and significance of residual impact in Day 1 and Year 10 of operation for some planned VSRs during construction phase because the planned VSRs do not exist during the construction phase.


9.9              Landscape and Visual Mitigation Measures

Landscape and Aesthetic External Design Measures in the Proposed Scheme

9.9.1          The design of aboveground structures should attempt to pose a positive gesture to integrate with the surrounding urban environments in an elegant manner.  All the aboveground elements should have a consistency in architectural articulation and material palette so that they are easily recognizable as part of the MTR system.

9.9.2          The proposed landscape and visual mitigation measures, together with an indication of Funding, Implementation and Maintenance Agencies, during the construction and operational phases are listed in Table 9.9 and Table 9.10 below and illustrated in Figure Nos. C1502/C/TME/ACM/M57/111 to 120.

Table 9.9          Proposed Landscape and Visual Mitigation Measures for Construction Phase

ID No.

Landscape and Visual Mitigation Measures

Funding Agency (1)

Implementation Agency

CM1

Trees unavoidably affected by the works should be transplanted as far as possible in accordance with DEVB TC(W) 4/2020 ¨C Tree Preservation.

MTR Corporation

MTR Corporation

CM2

Control of night-time lighting glare to prevent light overspill to the nearby VSRs and into the sky.  Relevant best practices as suggested in the "Charter on External Lighting"   and ¡°Guidelines on Industry Best Practices for External Lighting Installations¡± promulgated by ENB shall be adopted.

MTR Corporation

MTR Corporation

CM3

Erection of decorative screen hoarding or hoarding compatible with the surrounding setting.

MTR Corporation

MTR Corporation

CM4

Management of facilities on work sites which give control on the height and disposition/arrangement of all facilities on the works site to minimise visual impact to adjacent VSRs.

MTR Corporation

MTR Corporation

CM5

All hard and soft landscape areas disturbed temporarily during construction should be reinstated on like-to-like basis, to the satisfaction of the relevant Government Departments.

MTR Corporation

MTR Corporation

CM6

Tree without impact from proposed works should be retained as far as possible in accordance with DEVB TC(W) 4/2020 ¨C Tree Preservation. Any existing trees to be pruned by the Project should follow the Tree Management Practice Note No. 3: Tree Pruning issued by GLTMS of DEVB.

MTR Corporation

MTR Corporation

 


 

Table 9.10        Proposed Landscape and Visual Mitigation Measures for Operational Phase

ID No.

Landscape and Visual Mitigation Measures

Funding Agency (1)

Implementation Agency

Maintenance/ Management Agency

OM1

Aesthetically pleasing design as regard to the form, material and finishes should be incorporated to Entrance, Plant Buildings, Ventilation Shafts and associated engineering facilities so as to blend in the structures to the adjacent landscape and visual context. 

MTR Corporation

MTR Corporation

MTR Corporation

OM2

Tree Planting and shrub planting should be incorporated to provide screening to the Station building, viaduct and associated engineering facilities and serves as roadside amenity planting to provide ornamental value and enhance the landscape character of the streets.

MTR Corporation

MTR Corporation

MTR Corporation / LCSD (Subject to the affected areas and related maintenance parties)

OM3

Roof Greening should be proposed to the roof area of the propose structures as far as practical to enhance the landscape quality of the structures and mitigate any potential visual impact on adjacent VSRs.

MTR Corporation

MTR Corporation

MTR Corporation

OM4

Roadside soft landscape should be incorporated to the station buildings and associated engineering facilities. Shade tolerant plants with tall to medium height should be planted to under the viaduct to soften the hard building edges and provide screening.

MTR Corporation

MTR Corporation

HyD/ LCSD

OM5a

Provision of new open space for recreational use.

MTR Corporation

MTR Corporation

LCSD

OM5b

Provision of new hard and soft landscape area ¨C provision of street furniture and tree pit planting along the pedestrian as streetscape improvement.

MTR Corporation

MTR Corporation

HyD/ LCSD

OM6

Compensatory tree planting should be provided in accordance with DEVB TC(W) 4/2020 ¨C Tree Preservation to compensate for felled trees and maintained until end of the establishment period. Compensatory shrub planting should be provided to compensate for the loss of shrub planting in amenity areas. 

MTR Corporation

MTR Corporation

MTR/ HYD/ LCSD (subject to the affected areas and related maintenance parties)

 

9.9.3          The construction phase mitigation measures listed above should be adopted from the commencement of construction and should be in place throughout the entire construction period.  The operational phase mitigation measures listed above should be adopted during the detailed design and should be built as part of the construction works so that they are in place at the date of commissioning of the Project.  However, it should be noted that the full effect of the soft landscape mitigation measures would not be appreciated for several years.

9.9.4          Viewpoint locations of the photomontages are shown in Figure No. C1502/C/TME/ACM/M57/109.  The photomontages intend to demonstrate only the scale and massing of the Project and the effect of the proposed mitigation measures.  The architectural design finishes or any other related detailed design components are subject to refinement and changes during the detailed design stage.  Photomontages of the Project without and with mitigation measures illustrating the appearance on day 1 and after 10 years of the Project are shown in Figure Nos. C1502/C/TME/ACM/M57/121 to 129. 

9.10           Residual Impacts

Residual Landscape Impact

9.10.1        After implementation of mitigation measures, residual landscape impact of significance during construction and operational phases are described below.

Landscape Resources

9.10.2        For LR 1.6, LR 1.8B, LR 2 to LR 5.1 and LR 7, there would be no residual impact on these LRs during construction and operation as no construction works would be conducted in these LRs. For LR 1.1,  maintenance works such as tree pruning will be proposed for those existing trees interfering with the adjacent proposed construction site. The impact significance before mitigation is considered as moderate subject to its high sensitivity and small magnitude of changes. It is assumed that only a small portion of trees will be affected and there will be no removal of existing trees.  The residual impact on this LR is moderate during construction phase but reduced to slight and insubstantial in Day 1 and Year 10 of operation respectively.

9.10.3        For LR 1.2, Pui To Road (South) Rest Garden will be temporarily alienated during construction phase.  Most of the existing trees would be affected by the temporary works for site access to temporary platform, site office and piling up construction materials.  Tree compensation will be provided at this LR and this open space will be fully reinstated on a like-for-like basis during the operational phase. It is considered that residual impact on this LR is substantial during construction phase but moderate in Day 1 and slight in Year 10 of operation with the implementation of mitigation measures.

9.10.4        For LR 1.3, the Promenade along the eastern bank of Tuen Mun River Channel will be temporarily alienated during construction phase. A portion of the existing trees would be affected by the proposed works including for construction access, construction of viaduct, A16 Station and Tuen Mun River Bridge.  During the operational phase, this promenade will be fully reinstated on a like-for-like basis. It is considered that residual impact on this LR is moderate during construction phase and slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.5        For LR 1.4, Tuen Mun River (Eastern Bank) Garden will be temporarily alienated during viaduct construction and storage of construction materials. Considered the open space is recently renovated, existing vegetation which is mainly shrubs, would be affected by the proposed works. During the operational phase, this open space will be fully reinstated on a like-for-like basis. It is considered that residual impact on this LR is moderate during construction phase but slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.6        For LR 1.5, Hoi Wong Road Park Garden will be permanently loss due to the proposed works for station construction and storage of construction materials.  All of the existing trees will be removed or transplanted. During operational phase, this open space will be handed over to other party for future property development and the trees lost will be compensated based on the future landscape provision of the property development. It is considered that residual impact on this LR is moderate during construction phase but slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.7        For LR 1.7, the riverside amenity area adjacent to Tuen Mun Road Safety Town will be temporarily and localised alienated due to the proposed works sites for construction of viaduct and Tuen Mun River Bridge.  Existing trees along the riverside will be partially removed or transplanted due to the construction of temporary work platform for the construction of Tuen Mun River Bridge.  During operational phase, trees will be compensated, and open space will be fully reinstated on a like-for-like basis. With the implementation landscape mitigation measures, the residual impact on this LRs would be reduced to slight in Day 1 and insubstantial in Year 10 of operation.

9.10.8        For LR 1.8, Tuen Mun Road Safety Town of Wu Shan Recreation Playground will be temporarily and localised alienated due to the proposed works for construction of viaduct connecting the Tuen Mun River Bridge.  Existing trees along side of the viaduct will be affected and to be removed or transplanted. During operational phase, trees will be compensated, and open space will be fully reinstated on a like-for-like basis. With the implementation landscape mitigation measures, the residual impact on this LRs would be moderate and will be reduced to slight in Day 1 and insubstantial in Year 10 of operation.

9.10.9        For LR 1.9, the Wu King Road Garden will be temporarily alienated during construction.  All the existing trees would be affected by the proposed works including construction of TMS Station and PUDO Area and piling up construction materials. After the completion of the temporary works, half of the Garden will be reinstated on a like-for-like basis and trees will be compensated on site. It is considered that the residual impact on this LR is moderate during construction phase, but slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.10   For LR 1.10, Tuen Mun Promenade will be temporarily and localised alienated due to the proposed works for TMS Station construction, demolition works of existing Tuen Mun Pier Public Toilet and construction access for station construction.   Existing trees and vegetation would be affected, of which the palm trees will be transplanted and the semi-mature Ficus spp. along the seaside will be pruned, while the rest of the trees would be removed or transplanted.  During operational phase, trees will be compensated, and open space will be fully reinstated on a like-for-like basis.  With the implementation of landscape mitigation measures, the residual impact on this LRs would be moderate during construction phase, slight in Day 1 and insubstantial in Year 10 of operation.

9.10.11      For LR 5.2, the roadside landscape adjacent to Northern side of Wong Chu Road will be partially temporarily and localised alienated due to the proposed works for supporting the construction of the Project. Upon the completion of viaduct construction, approx. 2400sqm. of this LR will be the work sites of reprovisioning of Hoi Wong Road Pet Garden on a like-for-like basis. Based on the proposed landscape design of the reprovisioning of Hoi Wong Road Pet Garden, most of the existing trees would be retained in-suit. New trees would be planted as tree compensatory planting. It is considered that the residual impact on this LR is slight during construction phase, slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.12      For LR 5.3, the roadside landscape along the Wu King Road will be temporarily and alienated due to the proposed works for construction of TMS Station, road modification, demolition of existing footbridges and utility diversion. Most of the existing trees along the central median greening zone and eastern side of the Wu King Road would be removed or transplanted. Upon the completion of station construction, roadside amenity area would be proposed while new trees would be planted as tree compensatory planting. In a view of the scale of the development and impact caused by the construction, it is considered that the residual impact on this LR is substantial during construction phase, but moderation in Day 1 and slight in Year 10 of operation with the implementation of mitigation measures.

9.10.13      For LR 6.1, the vegetation within the temporary construction site adjacent to Tuen Mun River Channel will be temporarily alienated due to the propose work for supporting viaduct construction and storage of construction materials. Vegetation found are mainly self-seeding plants which are proposed to be removed.  In view of current site condition, the impact caused by the construction is small.  It is considered that the residual impact on this LR is slight during construction phase, slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.14      For LR 6.2, the existing HKIC Tuen Mun Training Ground will be temporary affected by the construction works for supporting A16 Station and storage of construction materials.  Vegetation found are mainly self-seeding plants and cluster of trees along the edges of the LRs which are all proposed to be removed.  Upon the completion of the station construction, affected area will be provided for future development. The trees lost will be compensated based on the future landscape provision of the future development. It is considered that the residual impact on this LR is slight during construction phase, slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.15      For LR 6.3, the short-term tenancy car parking area along Wu Shan Road will be temporarily alienated due to the propose works area for inspection of precast segment, loading and unloading construction materials and contractor¡¯s site office. Vegetation found are mainly self-seeding plants such as Leucaena leucocephala and small cluster of trees along the edges of the LRs which are all proposed to be removed.  Upon the completion of the station construction, car parking area will be reinstated while trees and vegetation distributed will be compensated within the proposed landscaping area. It is considered that the residual impact on this LR is slight during construction phase, slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.16      For LR 6.4, the Tuen Mun Swimming Pool will be permanently loss due to the proposed construction of A16 Station and viaduct structures, cooling tower and associated E&M buildings.  Existing trees will be inevitability affected by the proposed works, in which most of the existing trees will be removed or transplanted. This area will be handed over to other party for future property development and the trees lost will be compensated based on the future landscape provision of the property development.  During the operational phase, this resource will be transformed to a new landscape area of A16 Station. The existing Tuen Mun Swimming Pool will be reprovisioned in other area in Tuen Mun district and the reprovisioning works is considered as concurrent project. It is considered that the residual impact on this LR is moderate, but slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.17      For LR 6.5, Community Green Station will be permanently loss due to the propose works for viaduct and station construction. Existing newly planted trees will be inevitability affected by the proposed works and will be removed or transplanted. During the operational phase, this resource will be transformed to a new landscape area of A16 Station. The existing Community Green Station will be reprovisioned in other area in Tuen Mun district and the reprovisioning works is considered as concurrent project. It is considered that the residual impact on this LR is slight in construction stage, slight in Day 1 and insubstantial in Year 10 of operation with the implementation of mitigation measures.

9.10.18      The tree number and description of tree species to be affected in each LRs will be provided in the later stage.  Exact number of trees to be retained, transplanted and removed to be determined during TPRP under DEVB TC(W) No. 4/2020.

Landscape Character Areas

9.10.19      There would be moderate residual landscape impact on LCA 1 ¨C Mixed Modern Comprehensive Urban Development Landscape during the construction phase due to the demolition of Tuen Mun Swimming Pool and Community Green Station, temporary works for station and viaduct construction. Upon the completion of the viaduct construction, a large of portion of this LCA will be transformed as works sites of future planned property development.  During the operational phase, the impact caused by the A16 Alignment becomes slight in Day 1 and insubstantial in Year 10 with implementation of landscape mitigation measures.

9.10.20      During the construction phase, there would be slight residual landscape impact on LCA 2 ¨C Residential Urban Landscape due to demolition works of Wu King Road Garden and footbridges on Wu King Road, road modification, station and viaduct construction along the Wu King Road for TMS Station, and temporary works in Tuen Mun Road Safety Town for the construction of Tuen Mun River Bridge and viaduct structures.  Upon the completion of the construction, the disturbed streetscape and vegetation will be re-provided, including the reinstatement of half of the Wu King Road Garden and reinstatement of landscaping area of Tuen Mun Road Safety Town. During the operational phase, the impact caused by the alignment of TMS Station becomes slight in Day 1 and insubstantial in Year 10 with implementation of landscape mitigation measures. 

9.10.21      There would be slight residual landscape impact on LCA 3 ¨C Transportation corridor landscape due to the removal of a small portion of roadside amenity and reprovision works of Hoi Wong Road Pet Garden during the construction phase. During the operational phase, the impact caused becomes slight in Day 1 and insubstantial in Year 10 with implementation of landscape mitigation measures.

9.10.22      During construction phase, there would be slight landscape impact on LCA 5 ¨C Riverside Landscape due to the temporary and localised alienation of existing open space including the Pui To Road (South) Rest Garden, riverside promenade adjacent to Tuen Mun Park and Yau Oi Estate, Hoi Wong Road Garden and Pet Garden and Tuen Mun River (Eastern Bank) Garden. The disturbed landscape area will be reinstated upon the completion of the construction works. During the operational phase, the residual landscape impact would be insubstantial in both Day 1 and Year 10 of operation when the compensatory planting and landscape reinstatement work become mature. 

9.10.23      There would be slight landscape impact on LCA 6 - Industrial Urban Landscape due to temporary works for viaduct construction during the construction phase. The disturbed landscape will be re-provided during the construction of the planned Sports Ground by other party in the future.  During the operational phase, the residual landscape impact would be slight in Day 1 and reduce to insubstantial in Year 10 of operation when the compensatory planting and landscape reinstatement work become mature.

9.10.24      During construction phase, there would be no residual landscape impact on LCA4 ¨C Park Urban Landscape and LCA 7 ¨C Residential Urban Fringe Landscape as there is no works to be conducted in these LCAs. During the operational phase, the residual landscape impact would be insubstantial in both Day 1 and Year 10 of operation. 

 

 

 

 

 

 


Table 9.11        Significance of Landscape Impact during Construction and Operational Phases

ID  No.

Landscape Resource / Landscape Character Areas

Sensitivity

  (Low, Medium, High)

Magnitude of Change (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation (Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Significance of Residual Impact after Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Year 10

Landscape Resources (LRs)

LR 1.1

Tuen Mun Park

High

High

Small

Small

Moderate

Moderate

CM6

Moderate

Slight

Insubstantial

LR 1.2

Pui To Road (South) Rest Garden

High

High

Intermediate

Intermediate

Substantial

Substantial

CM1, CM5, CM6, OM6

Substantial

Moderate

Slight

LR 1.3

Promenade along the southern bank of Tuen Mun River Channel

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM5, CM6, OM2, OM6

Moderate

Slight

Insubstantial

LR 1.4

Tuen Mun River (Eastern Bank) Garden

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM5, OM2

Moderate

Slight

Insubstantial

LR 1.5

Hoi Wong Road Garden & Pet Garden

Medium

Medium

Large

Large

Moderate

Moderate

OM4, OM6

Moderate

Slight

Insubstantial

LR 1.6

Wu Shan Riverside Park

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 1.7

Riverside amenity area adjacent to Tuen Mun Road Safety Town

Medium

Medium

Small

Small

Slight

Slight

CM5, OM2, OM4, OM6

Slight

Slight

Insubstantial

LR 1.8

Tuen Mun Road Safety Town of Wu Shan Recreation Playground

High

High

Intermediate

Intermediate

Moderate

Moderate

CM5, CM6, OM2, OM4, OM6

Moderate

Slight

Insubstantial

LR 1.8B

Wu Shan Cycle Park of Wu Shan Recreation Playground

High

High

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 1.9

Wu King Road Garden

Medium

Medium

Large

Large

Moderate

Moderate

CM1, CM5, OM6

Moderate

Slight

Insubstantial

LR 1.10

Tuen Mun Promenade

High

High

Small

Small

Moderate

Moderate

CM1, CM5, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

LR 2

Landscape area in Tin Hau Temple and adjacent Hillside

High

High

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 3

Landscape area along riverside

Low

Low

Small

Small

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 4

Landscape area in urban development areas

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 5.1

Roadside Landscape along Tin Hau Road

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 5.2

Roadside Landscape adjacent to Northern side of Wong Chu Road

Medium

Medium

Small

Small

Slight

Slight

CM5, CM6, OM4, OM5b, OM6

Slight

Slight

Insubstantial

LR 5.3

Roadside Landscape along Wu King Road

Medium

Medium

Large

Large

Substantial

Substantial

OM2, OM3, OM4, OM5b, OM6

Substantial

Moderate

Slight

LR 6.1

Vegetation within Temporary Construction site

Low

Low

Small

Small

Slight

Slight

OM5b, OM6

Slight

Slight

Insubstantial

LR 6.2

Vegetation around the HKIC, Tuen Mun Training Ground and bus depot

Low

Low

Small

Small

Slight

Slight

CM6, OM4   

Slight

Slight

Insubstantial

LR 6.3

Vegetation surrounding the Temporary Car Park

Low

Low

Small

Small

Slight

Slight

CM6

Slight

Slight

Insubstantial

LR 6.4

Amenity planting in Tuen Mun Swimming Pool

Medium

Medium

Large

Large

Moderate

Moderate

CM1, OM2, OM3, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

LR 6.5

Amenity planting in Community Green Station

Low

Low

Small

Small

Slight

Slight

CM1, OM2, OM4, OM5b, OM6

Slight

Slight

Insubstantial

LR 6.6

Vegetation along the edges of the construction works area

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 7

Coastal Water

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LR 8

Miscellaneous Urban Fringe Landscape

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

Landscape Character Area (LCAs)

LCA 1

Mixed Modern Comprehensive Urban Development Landscape

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM6, OM2, OM3 OM4, OM5b, OM6

Moderate

Slight

Insubstantial

LCA 2

Residential Urban Landscape

Medium

Medium

Small

Small

Slight

Slight

CM1, CM5, CM6, OM2, OM3, OM4, OM5b, OM6

Slight

Slight

Insubstantial

LCA 3

Transportation Corridor Landscape

Low

Low

Small

Small

Slight

Slight

CM1, CM6, OM2, OM4, OM5a, OM6

Slight

Slight

Insubstantial

LCA 4

Park Urban Landscape

High

High

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LCA 5

Riverside Landscape

Medium

Medium

Small

Small

Slight

Slight

CM5, CM6, OM2, OM4, OM6

Slight

Insubstantial

Insubstantial

LCA 6

Industrial Urban Landscape

Low

Low

Small

Small

Slight

Slight

CM6, OM4   

Slight

Slight

Insubstantial

LCA 7

Residential Urban Fringe Landscape

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial

LCA 8

Miscellaneous Urban Fringe Landscape

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

NA

Insubstantial

Insubstantial

Insubstantial


Residual Visual Impact

9.10.25      After implementation of the recommended mitigation measures, residual visual impact of significance during construction and operational phases are described below.

9.10.26      During the construction phase, with the implementation of proposed mitigation measures for the viaduct construction between A16 and TUM Station, there would be slight residual impact on VSRs O5, GIC1, I1 and T1. The impact would be reduced to insubstantial in both Day 1 and Year 10 of operation with the adoption of aesthetically design on the viaduct structure for VSRs GIC 1 and I1. However, since the proposed viaduct traverse along Tuen Mun River and traverse above the existing footbridges which are visually prominent and can be viewed by the cyclist and along some sections of the riverside and potential recreational users in the reprovision of Hoi Wong Road Pet Garden. Hence, the residual impact in both Day 1 and Year 10 of operation will be considered as slight for VSRs T1 and O5. There would be substantial residual impact on VSR O4 during the construction phase and will be reduced to moderate residual impact in both Day 1 and Year 10 operation as the current openness of  the river scene will be diminished in long term by the proposed viaduct structures.  There would be moderate residual impact on VSRs O1, O2, R1, R2 and R3 during construction phase and will be reduced to slight residual impact in Day 1 operation for VSRs O2, R1, R2 and R3 upon the completion of reinstatement and reprovision of landscape areas in Pui To Road (South) Rest Garden, Tuen Mun River (Eastern Bank) Garden and along the riverside promenade. Since the VSR O1 is relatively more sensitivity to the magnitude of changes brought by the proposed construction works, the residual impact in Day 1 operation will be remained as moderate.  The impact would be slight or insubstantial in Year 10 of operation when the tree planting proposed become mature.  The residual impact on VSRs O3 and I2 are considered as insubstantial during construction phase with the implementation of proposed mitigation measures. The residual impact would become insubstantial during construction, both Day 1 and Year 10 of operation as the main source of visual impact is partially blocked and relatively far away from these VSRs.

9.10.27      During the construction phase, the residual impact for VSRs O6, R4, R5, R6, GIC2, T2 and T3 is considered as moderate due to the relatively close viewing distance to the Project. With the implementation of the mitigation measures, the residual impact will reduce to slight in Day 1 and insubstantial in Year 10 of operation for all VSRs except VSRs O6 and R4. Since the existing view toward the mountain backdrop will be partially blocked permanently by the A16 Station and will be visually disturbed by the proposed viaduct along Tuen Mun River in long term, the residual impact in both Day 1 and Year 10 of the operation with the implementation of proposed mitigation measures will be considered as moderate for VSRs O6 and R4.  Together with the planned VSR O8, the residual impact would be further reduced to insubstantial in Year 10 of operation when the proposed trees planting become mature. For VSR I3, the main source of visual impact is relatively far away from this VSR and have no blockage of existing view, thus the residual impact during construction phase on VSR I3, is considered as insubstantial during construction, both Day 1 and Year 10 of operation with the implementation of proposed mitigation measures.

9.10.28      With the implementation of proposed mitigation measures for the viaduct construction of Tuen Mun River Bridge, there would be slight residual impact on VSR O9 and substantial residual impact on VSR O7 during the construction phase.  After the implementation of aesthetic design treatment on proposed aboveground structure and reinstatement of landscaping area in Tuen Mun Road Safety Town, the residual impact on VSR O9 will be further reduced to slight in Day 1 and insubstantial in Year 10 of the operation.  However, since the proposed viaduct would traverse the Tuen Mun Road Safety Town and the riverside promenade, the sense of openness of the open space for VSR O7 will diminished permanently.  The residual impact for VSR O7 in both Day 1 and Year 10 of operation will considered as moderate.   For VSR O10, there is no blockage of existing view. The residual impact during construction phase on VSRs O10, is considered as insubstantial during construction, both Day 1 and Year 10 of operation with the implementation of mitigation measures such as control of night-time lighting glare and adoption of aesthetic design approach.

9.10.29      There would be moderate to substantial residual impact during construction phase on VSRs O11, O12, O13, GIC3, GIC4, GIC5, C1 and T4. With the aesthetic design treatment on TMS Station, reprovision of roadside amenity along Wu King Road and reinstatement of half of the Wu King Road Garden, the impact would become slight to moderate on Day 1 and further reduce to slight to insubstantial in Year 10 of operation when the trees planting along the Wu King Road and Wu King Road Garden become mature. Besides, there would be moderate residual impact during the construction phase on VSRs R7, R8, R9 and R10 with the implementation of propose mitigation measures. However, it is considered that the residual impact would be maintained as moderate during Day 1 and Year 10 of operation as the main source of visual impact will remain unchanged apart from the proposed aesthetic design on the TMS Station structures.

9.10.30      There would be insubstantial residual impact during construction phase on VSRs GIC7 and T5. Since the proposed off-site works area is temporarily use only and usage will be same as the current usage as site office for other project at Mong Wing Street while the current view to the hillside backdrop will not be blocked, the residual impact during Day 1 and Year 10 of operational phase is considered as insubstantial.


Table 9.12        Significance of Visual Impact during Construction and Operational Phases

ID  No.

Visually Sensitive Receivers

Sensitivity

  (Low, Medium, High)

Magnitude of Change (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation (Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Significance of Residual Impact after Mitigation

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Year 10

O1

Recreational users in Tuen Mun Park

High

High

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM6

Moderate

Moderate

Slight

O2

Recreational users in Pui To Road (South) Rest Garden

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, OM1, OM6

Moderate

Slight

Slight

O3

Recreational users in Tin Hau Temple

Low

Low

Small

Small

Slight

Slight

CM2, CM3, CM4, OM1

Insubstantial

Insubstantial

Insubstantial

O4

Recreational users along the riverside promenade, including the user in Tuen Mun River (Eastern Bank) Garden

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, OM1, OM2, OM4

Substantial

Moderate

Moderate

O5

Potential recreational users in the reprovision of Hoi Wong Road Pet Garden

Low

Low

Intermediate

Intermediate

Slight

Slight

CM1, CM2, CM3, CM4, OM1, OM2, OM4, OM5a, OM6

Slight

Slight

Slight

O6

Recreational users in Wu Shan Riverside Park

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Moderate

Moderate

O7

Recreational users in Tuen Mun Road Safety Town and along the riverside promenade, adjacent to Wu Shan Cycle Park

Medium

Medium

Large

Large

Substantial

Substantial

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM6

Substantial

Moderate

Moderate

O8

Potential recreational users in planned Sports Ground

-

Medium

-

Small

-

Slight

CM2, CM3, CM4, OM1, OM2, OM4, OM5a

-

-

Insubstantial

O9

Recreational users in Wu Shan Cycle Park

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM6

Slight

Slight

Insubstantial

O10

Recreational users in Wu Shan Recreation Playground

Low

Low

Small

Small

Slight

Slight

CM2, CM3, CM4, CM5, CM6, OM1

Insubstantial

Insubstantial

Insubstantial

O11

Recreational users in Wu King Road Garden

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, OM1, OM2, OM6

Substantial

Moderate

Slight

O12

Recreational users in Soccer Pitch adjacent to Wu Yuet House

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

O13

Recreational users along the Tuen Mun Promenade close to the Tuen Mun Pier

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM6

Substantial

Moderate

Slight

O14

Potential recreational users of planned open space at the junction of Tin Hau Road

-

Low

-

Intermediate

-

Moderate

CM2, CM3, CM4, CM5b, OM6

-

-

Slight

O15

Recreational users of Yau Oi Sports Centre

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM6

Moderate

Slight

Insubstantial

R1

Residents of Century Gateway, Kam Wah Garden and Trend Plaza

High

High

Small

Small

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM6

Moderate

Slight

Insubstantial

R2

Residents of Planned public housing estate at Tin Hau Road

High

High

Small

Small

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

R3

Residents of Yau Oi Estates

High

High

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM6

Moderate

Slight

Insubstantial

R4

Residents of Lung Mun Oasis, Glorious Garden, The Esplanade and Sun Tuen Mun Centre

High

High

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM3, OM4, OM5b, OM6

Moderate

Moderate

Moderate

R5

Residents of Goodview Garden, Oceania Heights, and Nerine Cove

High

High

Small

Small

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM6

Moderate

Slight

Insubstantial

R6

Residents of Regency Bay and planned residential property development at Hang Fu Street

High

High

Small

Small

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM6

Moderate

Slight

Insubstantial

R7

Residents of Wu King Estate

High

High

Large

Large

Substantial

Substantial

CM2, CM3, CM4, OM1, OM2, OM3, OM4, OM6

Moderate

Moderate

Moderate

R8

Residents of Tuen Mun Wu Hong Police Quarters

High

High

Large

Large

Substantial

Substantial

CM2, CM3, CM4, CM5, CM6, OM1, OM2, OM3, OM4, OM5b, OM6

Moderate

Moderate

Moderate

R9

Residents of Yuet Wu Villa and Sui Hei Court

High

High

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM5b, OM6

Moderate

Moderate

Moderate

R10

Residents of Richland Garden and Pierhead Garden

High

High

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM5b, OM6

Moderate

Moderate

Moderate

R11

Potential residential users in future property development in A16

-

High

-

Intermediate

-

Moderate

CM2, CM3, CM4, OM1, OM2, OM3, OM4, OM6

-

-

Moderate

GIC1

Tuen Mun Division Police Station

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM6

Slight

Insubstantial

Insubstantial

GIC2

PCCW Tsung Shan Wan Hing On Ln Exchange Building

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

GIC3

Tuen Mun Wu Hong Clinic

Medium

Medium

Large

Large

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

GIC4

User of Yan Chai Hospital Law Chan Chor Si Primary School, Tung Wah Group of Hospitals Sun Hoi Directors' College and Taoist Ching Chung Primary School (Wu King Estate) 

Medium

Medium

Large

Large

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

GIC5

Castle Peak Police Station

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM5, OM1, OM2, OM3, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

GIC6

Users of Yan Chai Hospital Ho Sik Nam Primary School

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM6

Moderate

Slight

Insubstantial

GIC7

Customs and Excise Department Harbour And River Trade Division and Pillar Point Fire Station*

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

-

Insubstantial

Insubstantial

Insubstantial

I1

Users in industrial buildings, including Mai Kei Industrial Building, Win Sun Manufacturing Building and Yau Tak Industrial Building

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4,  CM5, CM6, OM1, OM2, OM6

Slight

Insubstantial

Insubstantial

I2

Users in Nan Fung Industrial City

Medium

Medium

Small

Small

Slight

Slight

CM2, CM3, CM4, OM1, OM2, OM5b, OM6

Insubstantial

Insubstantial

Insubstantial

I3

Users in MTR Tuen Mun Depot

Low

Low

Small

Small

Slight

Slight

CM2, CM3, CM4, OM1

Insubstantial

Insubstantial

Insubstantial

C1

Siu Hei Market

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1, OM2, OM4, OM5b, OM6

Moderate

Slight

Insubstantial

T1

Travellers at the adjacent riverside cycle track

Low

Low

Small

Small

Slight

Slight

CM2, CM3, CM4, CM5, OM1, OM2, OM5b, OM6

Slight

Slight

Slight

T2

Travellers at Wong Chu Road

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, CM6, OM1, OM2, OM4, OM5a, OM6

Moderate

Slight

Insubstantial

T3

Travellers at Hoi Wong Road

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM2, CM3, CM4, OM1

Moderate

Slight

Insubstantial

T4

Travellers along Wu King Road

Medium

Medium

Large

Large

Substantial

Substantial

CM2, CM3, CM4, CM5, OM1, OM2, OM4, OM5b, OM6

Substantial

Moderate

Slight

T5

Travellers along Tuen Mun Chek Lap Kok Tunnel Road

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

-

Insubstantial

Insubstantial

Insubstantial


9.11           Cumulative Impacts

9.11.1       Cumulative landscape and visual impacts during construction and operational phases from other projects in the vicinity were assessed. Key concurrent projects including the Planned Public Housing Development at Yip Wong Road, Hang Fu Street and Wu Shan Road, Planned Property Development at Area 16, Reprovision of Pet Garden and Community Green Station, Sports Ground and Open Space in Area 16 and Cycle Track between Tsuen Wan and Tuen Mun which might potentially cause cumulative impact to the Project were assessed. 

Planned Public Housing Development at Yip Wong Road and Hang Fu Street

9.11.2       The planned public housing developments at Yip Wong Road and Hang Fu Street are located at the western side of the alignment, opposite to the Tuen Mun River (Eastern Bank) Garden and the northern side of Regency Bay, facing the future planned property development at Area 16 respectively. They are the two of the five planned housing sites for site formation and infrastructure works for public housing developments at Tuen Mun Central. For the development in Yip Wong Road, the construction of the foundation works commenced in May 2021 and completed in July 2021 while the building works commenced in June 2021 for substantial completion in 2024.  For the development in Hang Fu Street, the construction off the foundation works commenced in 2020 and the substantial completion for building works will be in 2024.

9.11.3       Considered that the heavy construction works would be completed before the end of 2023, there would be slight adverse cumulative impact to the existing landscape resources and slight adverse cumulative visual impact to the surrounding VSRs, mainly the residents in Yau Oi Estates and workers in the Nan Fung Industrial City.  With the implementation of the proposed mitigation measures (i.e. tree compensation and preservation, control of night-time glare, decorative hoarding etc.) during construction phase, it is considered that there would not be any insurmountable cumulative impact during construction phase. During the operational phase, the construction of planned public housing development in Yip Wong Road is completed, with the implementation of aesthetic design at the planned public housing, it is considered that there would not be any adverse cumulative impact during operational phase.

9.11.4       The construction of the planned public housing developments at Hang Fu Street is currently under work in progress, existing landscape resources had been removed for the construction works.  Therefore, there would be no cumulative landscape impact but slight cumulative visual impact to the surrounding VSRs, mainly the residents of Regency Bay, Nerine Cove and Oceania Heights during the construction phase of the Project.  With the implementation of the proposed mitigation measures (i.e. tree compensation and preservation, control of night-time glare, decorative hoarding etc.) during construction phase, it is considered that there would not be any insurmountable cumulative impact during construction phase.  During the operational phase, the construction of planned public housing would be completed, with the implementation of aesthetic design at the planned public housing, it is considered that there would not be any adverse cumulative impact during operational phase.

Planned Property Development at Area 16, Tuen Mun

9.11.5       The construction of planned property development in Area 16 will take place after the completion of the construction of the Project, therefore there would not be any cumulative impact during construction phase.   During operational phase, the cumulative impact caused by the planned property development at Area 16 will be assessed in the later stage by other relevant parties.

Provision of Pet Garden

9.11.6       The existing Hoi Wong Road Park and Pet Garden will be demolished during the construction phase and will be proposed to be reinstated in the amenity area at the northern side of Wong Chu Road.  The construction of the pet garden is scheduled to commence and completed within 2023.  It is considered that there would be slight adverse cumulative impact to the existing landscape resources due to the construction of the Project. Considered the construction works is closed to the residential building, there would be slight adverse cumulative impact to the adjacent VSRs.  With the implementation of proposed mitigation measures (i.e. tree compensation and preservation, control of night-time glare, decorative hoarding etc.) during construction phase, it is considered that there would not be any insurmountable landscape and visual impact during construction phase.

Planned Sports Ground and open space

9.11.7       The planned Sports Ground will be located adjacent to the A16 Station, occupying the existing HKIC Tuen Mun Training Ground. There would be potential cumulative landscape impact on existing vegetation and LCA6 ¨C Industrial Urban Landscape. Meanwhile, there would be potential cumulative visual impact on the adjacent VSRs, mainly the residents of the adjacent residential buildings. As this project is still under planning stage and the construction schedule is yet to be available, the potential cumulative impact caused should be subject to the construction programme and to be assessed by other relevant parties.

9.12           Conclusion

9.12.1       The Project will inevitably result in some landscape and visual impacts during construction and operational phases. These impacts were minimised through the consideration on minimization of works areas, incorporation of aesthetic external designs and landscape treatments of all the proposed aboveground structures including the station and viaduct structures, and reinstatement of disturbed landscape area including the amenity area along the riverside promenade and open space such as Hoi Wong Road Pet Garden, Tuen Mun River (Eastern Bank) Garden, Wu King Road Garden and Pui To Road (South) Rest Garden.

9.12.2       The Project is generally located within the GIC or O Zones of Approved Tuen Mun Outline Zoning Plan No. S/TM/35 and develop in a linear alignment along the river channel and existing transportation corridor as an extension of TML.  It is considered that the Project would fit in with the current and would not conflict with statutory town plans of the areas.

9.12.3       Approximately 2,209 existing trees identified within the works area, of which approx. 975 nos. of existing trees would not be affected by the proposed works will be retained while approx. 1,234 nos. of trees, including the undesirable species (i.e. leucaena leucocephala would be directly affected by the proposed works will be proposed to be removed or transplanted as far as practicable.  Two TPI identified within the amenity planting in Tuen Mun Swimming Pool (i.e LR 6.4) will be inevitably affected and would be transplanted within the A16 area as far as practicable.  Exact number of trees to be retained, transplanted and felled to be determined during TPRP under DEVB TC(W) No. 4/2020.  There are neither OVT, rare species nor endangered species affected by the proposed works, and the affected trees mainly are common tree species. Opportunities for tree compensation within the Project boundary have been fully explored and incorporated in the proposed mitigation measures as much as practicable.  Given that the site area of the Project is confined and limited and hence tree compensation requirement of 1:1 in terms of number should be carried out as far as practicable and heavy standard size of trees is not feasible. Detailed Tree Preservation and Removal Proposals should be submitted to relevant government departments in accordance with DEVB TC(W) No. 4/2020 to compensate the trees to be removed.  Details of tree compensation is shown in Appendix 9.1.

9.12.4       Landscape area in Tuen Mun Swimming Pool, Community Green Station, and a small portion of HKIC Tuen Mun Training Ground would be permanently alienated due to the construction and operation of the Project.  Upon the completion of construction works, the works site will be handed over to others for the construction of the planned Sports Ground and future topside property development. The alienation of the landscape area is proposed to compensate within the Project.

9.12.5       Under the Project, there would be permanently loss of Hoi Wong Road Park and Pet Garden due to the construction of A16 Station, while partial loss of Wu King Road Garden is expected due to the construction of TMS Station and provision of PUDO area.  Some of the open space and amenity areas such as Pui To Road (South) Rest Garden, Tuen Mun Road Safety Town, Tuen Mun Promenade, Tuen Mun River (Eastern Bank) Garden, the riverside promenade adjacent to Tuen Mun Park, Yau Oi Estate and Wu Shan Recreation Playground and roadside greenery along Wu King Road will be temporarily alienated during construction of the Project. These open spaces and amenity areas will be reinstated on a like-for-like basis after completion of temporary construction works. Approximately 2,400 sqm. of planting area close to the Wong Chu Road will be partially affected and this resource will be transformed to a new pet garden for reprovision of Hoi Wong Road Park and Pet Garden.  With the implementation of the landscape mitigation measures, it is considered that the residual impacts on these landscape resources are slight to insubstantial in Year 10 of the operation. 

9.12.6       The majority of the proposed permanent works are located in LCA 1, LCA 2, LCA3, LCA 5 and LCA6.  During construction phase, due to the proposed works in these LCAs, there would still be slight to moderate residual impact with the implantation of mitigation measures. However, during the operational phase, the residual landscape impact would be reduced to insubstantial to slight in Day 1 and further reduced to insubstantial in Year 10 when the compensatory planting and landscape reinstatement works become mature.

9.12.7       During the construction phase, there would still be substantial residual visual impact on the Recreational VSRs of O4, O7, O11, O13 and Traveller VSRs T4 as these VSRs oversee TMS Station/Tuen Mun River Bridge/the viaduct at pedestrian level in a relatively close distance, and the proposed engineering structures have significantly altered the visual context of the area.  During construction phase, there would still be substantial residual impact with the implantation of mitigation measures. However, with the implementation of mitigation measures for operational phase including aesthetic design of aboveground structures, trees planting and provision of amenity area surrounding the aboveground structure, the residual visual impact on these VSRs would be moderate in Day 1 and further reduced to slight in Year 10 of operation when the proposed trees planting become mature for VSRs O11, O13 and T4.  For VSRs O4 and O7, the residual visual impact will be maintained as moderate in both Day 1 and  Year 10 of operation as the current openness of  the river scene will be diminished in long term by the proposed viaduct structures

9.12.8       There would still be moderate residual visual impact on VSRs including the Recreational VSRs of O1, O2, O6, O12 and O15, the residential VSR R4, the Institutional VSRs of GIC2, GIC3, GIC4, GIC 5 and GIC6, the Commercial VSR C1 and the Traveller VSRs T2 and T3 during the construction phase, as these VSRs oversee the proposed alignment at pedestrian level with medium to close viewing distance.  With the implementation of mitigation measures for operational phase including aesthetic design of aboveground structures, trees planting and provision of amenity area surrounding the aboveground structure, the residual visual impact on these VSRs would be slight to moderate in Day 1 and further reduced to slight to insubstantial in Year 10 of operation when the proposed trees planting become mature except for VSRs O6 and R4. The residual visual impact for VSRs O6 and R4 will be maintained as moderate in both Day 1 and Year 10 of operation as the existing visual context will be disturbed by the proposed viaduct along Tuen Mun River in long term.

9.12.9       Besides, there would still be moderate residual visual impact on most of the Residential VSRs during the construction phase as these VSRs oversee the entire TME Alignment at high level with various viewing distance. Subject to the visual context of these VSRs will be permanently altered while tree planting may not able to reduce the residual impact, therefore, the residual impact would be remained moderate in both Day 1 and Year 10 of operation for the Residential VSRs of R7, R8, R9, R10 and R11.  On the other hands, subject to the geographical location of some Residential VSRs such as R1, R2, R3, R5 and R6 where the view to the TME Alignment may partially blocked and viewing distance is relatively far away from the TME Alignment, residual impact would be slight in Day 1 and further reduced to insubstantial in Year 10 of operation after the implementation of the mitigation measures.

9.12.10    Residual impacts on other VSRs due to the Project are considered as slight to insubstantial during construction phase as the other VSRs have relatively far viewing distance, and partial to no blockage of existing view. Therefore, the residual impact in Day 1 would be slight to insubstantial and would be further reduced to insubstantial in Year 10 when the proposed landscape mitigations mature.

9.12.11    Cumulative landscape and visual impacts from other concurrent projects during the construction and operational phases of the Project were assessed.  Based on the implementation programme of other concurrent projects and the anticipated landscape and aesthetic design of concurrent projects including the planned Public Housing Development at Yip Wong Road, Provision of Pet Garden in Wong Chu Road and the Planned Sports Ground and open spaces in Area 16, insurmountable cumulative landscape and visual impacts would not be anticipated.

9.12.12    In view of the above, it is considered that the overall landscape and visual impact associated with the construction and operation of the Project are acceptable with the implementation of the appropriate mitigation measures.