TABLE OF
CONTENTS
1.4 Structure
of the EM&A Manual
2.2 Monitoring
Parameters and Equipment
2.3 Laboratory
Measurement / Analysis
3.3 Operation
Noise – Fixed Plant
3.4 Operation
Noise – Railway Noise
11.2 Compliance
with Legal and Contractual Requirements
11.3 Choice
of Construction Method
12.2 Baseline
Monitoring Report
12.4 First
Monthly EM&A Report
12.5 Subsequent
Monthly EM&A Reports
12.6 Final
EM&A Report - Construction Phase
12.8 Interim
Notifications of Environmental Quality Limit Exceedances
List of tables
Table 2.1 Proposed Dust Monitoring Stations
Table 2.2 Summary of Construction Dust Monitoring Programme
Table 2.3 Proposed Action and Limit Levels for Impact Monitoring
Table 2.4 Event and Action Plan for Construction Dust Monitoring
Table 3.1 Noise Monitoring Stations during Construction Phase
Table 3.2 Action and Limit Levels for Construction Noise Impact
Monitoring
Table 3.3 Event and Action Plan for Construction Noise
Monitoring
Table 3.4 Acceptable Noise Levels for Airborne Railway Noise
Table 3.5 Noise Monitoring Stations For Railway Noise
Table 4.2 Action and Limit Levels for Water Quality
Table 4.3 Event and Action Plan for Water Quality
LISTS OF FIGURES
C1502/C/TME/ACM/M50/101 Proposed TME Alignment
C1502/C/TME/ACM/M60/201 Locations of Dust Monitoring Stations
C1502/C/TME/ACM/M60/301 Locations of Noise Monitoring Stations
(Construction Phase)
C1502/C/TME/ACM/M60/302 Locations of Noise Monitoring Stations
(Operation Phase)
C1502/C/TME/ACM/M60/401 Locations of Water Quality Monitoring
Stations
LIST OF Appendices
Appendix A Project Organisation
Appendix B Project Implementation Schedule
Appendix C Sample Record Sheets
Appendix D Complaint Handling Procedure
Appendix E Sample of the Interim Notification
· Construction and operation of 2.4-km
extension of the viaduct structure from TUM Station to the new TMS Station;
· Construction and operation of two
new stations, namely TMS Station and A16 Station;
· Construction and operation of
Stations associated facilities; and
· Construction and operation of a
railway siding adjacent to A16 Station.
· Responsibilities of the Contractor,
the Engineer or Engineer’s Representative (ER), the Environmental Team (ET),
and the Independent Environmental Checker (IEC) with respect to the
environmental monitoring and audit requirements during the course of the
Project;
· Project organization for the EM&A
works;
· The
basis for, and description of the broad approach underlying the EM&A
programme;
· Details of the methodologies to be
adopted, including all field laboratories and analytical procedures, and
details on quality assurance and quality control programme;
· The rationale on which the
environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit
levels;
· Establishment of Event and Action
plans;
· Requirements for reviewing pollution
sources and working procedures required in the event of non-compliance with the
environmental criteria and complaints; and
· Requirements for presentation of
environmental monitoring and audit data and appropriate reporting procedures.
Engineer
or Engineer’s Representative (ER)
· Supervise the Contractor’s
activities and ensure that the requirements in the EM&A Manual are fully
complied with;
· Inform the Contractor when action is
required to reduce environmental impacts in accordance with the Event and
Action Plans;
· Participate in joint site
inspections and audits undertaken by the ET; and
· Adhere to the procedures for
carrying out exceedance and complaint investigations.
The
Contractor
· Implement the EIA recommendations
and requirements;
· Strictly adhere to the guidelines
and requirements in this EM&A Manual;
· Provide assistance to the ET in
carrying out relevant environmental monitoring and auditing, and investigation
related to complaints and non-compliance (Section
11 of this Manual refers);
· Participate in the site inspections
undertaken by ET, and undertake correction action(s);
· Provide information / advice to ET
regarding works activities which may contribute, or be continuing to the
generation of adverse environmental condition(s);
· Submit proposals on mitigation
measures in case of exceedances of Action and Limit levels, in accordance with
the Event and Action Plans as detailed in this EM&A Manual;
· Implement measures to reduce
environmental impacts where Action and Limit levels are exceeded until the
events are resolved; and
· Adhere to the procedures for
carrying out environmental complaint investigation in accordance with Section 11 of this Manual.
Environmental
Team (ET)
· Set up all the required
environmental monitoring stations;
· Monitor the various environmental
parameters as required in the EM&A Manual;
· Carry out regular and ad hoc site
inspections to investigate and audit the Contractor’s site practice, equipment
and work methodologies with respect to pollution control and environmental
mitigation measures, and anticipate environmental issues for proactive and
practicable action before problems arise;
· Analyse the EM&A data, review
the success of EM&A programme to confirm the adequacy of mitigation
measures implemented and the validity of the EIA predictions, and to identify
any adverse environmental impacts arising and report EM&A results to the
Contractor, IEC, and the ER;
· Liaise with IEC on all environmental
performance matters, and timely submission of all relevant EM&A proforma
for IEC's approval;
· Audit the relevant
document(s)/record(s) and prepare reports on the environmental monitoring data
and the site environmental conditions;
· Review the proposals of remedial
measure from the Contractor in the case of exceedances of Action and Limit
levels, in accordance with the Event and Action Plans;
· Advise the Contractor on
environmental improvement, awareness, enhancement matters, etc., on site;
· Submit the EM&A report(s) to the
Project Proponent and the EPD timely; and
· Adhere to the procedures for
carrying out environmental complaint investigation in accordance with Section 11 of this Manual.
Independent
Environmental Checker (IEC)
· Review and audit at not less than
monthly intervals in an independent, objective and professional manner in all
aspects of the EM&A programme;
· Validate and confirm the accuracy of
monitoring results, monitoring equipment, monitoring locations, monitoring
procedures and locations of sensitive receivers;
· Audit the EIA recommendations and
requirements against the status of implementation of environmental protection
measures on site;
· Review the effectiveness of
environmental mitigation measures and project environmental performance;
· On as-needed basis, verify and
certify the environmental acceptability of the Environmental Permit (EP)
holder’s construction methodology (both temporary and permanent works),
relevant design plans and submissions under the EP;
· Carry out random sample check and
audit on monitoring data and sampling procedures, etc;
· Conduct random site inspection;
· Verify the investigation results of
environmental complaint cases and the effectiveness of corrective measures;
· Verify EM&A report that has been
certified by the ET leader; and
· Provide feedback on the audit
results to the ET, the ER or the Project Proponent according to Event and
Action Plans in the EM&A Manual.
· Section 2 –Sets out EM&A requirement
for air quality;
· Section 3 –Sets out EM&A
requirement for noise;
· Section 4 –Sets out EM&A
requirement for water quality;
· Section 5 – Details auditing
requirement for waste management;
· Section 6 – Details auditing
requirement for land contamination;
· Section 7 – Sets out EM&A
requirement for terrestrial ecology;
· Section 8 – Details auditing
requirement for landscape and visual impact;
· Section 9 – Details auditing
requirement for cultural heritage;
· Section 10 – Details auditing
requirement for hazard to life;
· Section 11 – Describes scope and
frequency of environmental site audits and sets out the general requirements of
the EM&A programme; and
· Section 12 – Details the EM&A
reporting requirements.
· 0.6 - 1.7 m3 per minute
(20 - 60 standard cubic feet per minute) adjustable flow range;
· equipped with a timing / control
device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter
with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum
exposed area of 406 cm2 (63 in2);
· flow control accuracy: ± 2.5% deviation over 24-hour sampling
period;
· incorporated with an electronic mass
flow rate controller or other equivalent devices;
· equipped with a shelter to protect
the filter and sampler;
· equipped with a flow recorder for
continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter
paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously
for 24-hour period.
· the wind sensors shall be installed
on masts at an elevated level 10m above ground so that they are clear of
obstructions or turbulence caused by the buildings;
· the wind data shall be captured by a
data logger. The data recorded in the
data logger shall
be downloaded periodically for analysis at least once a month;
· the wind data monitoring equipment
shall be re-calibrated at least once every six months; and
· wind direction shall be divided into
16 sectors of 22.5 degrees each.
Table 2.1 Proposed
Dust Monitoring Stations
ASR ID in EIA
Report |
ASR
Description |
|
AM1 |
A7 |
Islamic Primary School |
AM2 |
A9 |
Oi Lai House, Yau Oi Estate |
AM3 |
A21 |
Yan Chai Hospital Law Chan Chor Si Primary School |
AM4 |
A28 |
Wu Tsui House, Wu King Estate |
AM5 |
A41 |
Tuen Mun Swimming Pool (TMSP)(2) |
Note:
(1)
1-hour
TSP impact monitoring should be conducted at the monitoring stations when there
are Project-related major construction activities including site formation and
piling works being undertaken within a radius of 500m from the monitoring
stations.
(2)
Dust
monitoring at Tuen Mun Swimming Pool will be ceased when it is closed or it is
demolished. Upon the commencement of
demolition of TMSP, the dust monitoring will be conducted at Castle Peak Bay
Ambulance Depot (ASR ID. A34).
· Monitoring at ASRs close to the
major site activities which are likely to have air quality impacts;
· Monitoring as close as possible to
the ASRs as defined in the EIAO-TM;
· Assurance of minimal disturbance to
the occupants and working under a safe condition during monitoring; and
· Take into account the prevailing
meteorological conditions.
· A horizontal platform with
appropriate support to secure the samplers against gusty wind should be
provided;
· Two samplers should not be placed
less than 2m apart;
· the distance between the sampler and
an obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
· a minimum of 2m separation from
walls, parapets and penthouses is required for rooftops samplers;
· a minimum of 2m separation from any
supporting structure, measures horizontally is required;
· no furnace or incinerator flue is
located nearby the samplers;
· airflow around the sampler is
unrestricted;
· the sampler is more than 20m from
the dripline;
· any wire fence and gate to protect
the sampler, should not cause any obstruction during monitoring;
· permission must be obtained to set
up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is
needed to operate the samplers.
Table 2.2 Summary
of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline
Monitoring |
Consecutive
days of at least 2 weeks before commencement of major construction works |
1 hour TSP |
3 times
per day |
Impact
Monitoring |
Throughout
the construction phase(1) |
1 hour TSP |
3 times in
every 6 days |
Note:
(1) Impact monitoring should be conducted at the
monitoring stations for 1-hour TSP monitoring when there are Project-related
major construction activities being undertaken within a radius of 500m from the
monitoring stations.
Table 2.3 Proposed
Action and Limit Levels for Impact Monitoring
Parameter |
Action
Level (1) |
Limit
Level |
1-hour TSP |
·
For BL £ 384μg m-3, AL = (BL * 1.3 + LL)/2 ·
For BL > 384μg m-3, AL = LL |
500μg m-3 |
Note:
(1)
BL = Baseline level, AL = Action level,
LL = Limit level.
Table 2.4 Event
and Action Plan for Construction Dust Monitoring
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
Exceedance
for one sample |
1.
Repeat measurement to confirm findings; 2.
If exceedance is confirmed, inform the
Contractor, IEC and ER; 3.
Identify
source(s), investigate the causes of exceedance and propose remedial measures; and 4.
Increase monitoring frequency. |
1.
Check monitoring data submitted by the ET; 2.
Check Contractor’s working method; and 3.
Discuss with ET, ER and Contractor on possible remedial measures; and 4.
Review and advise the ET and ER on the
effectiveness of the proposed remedial measures. |
1.
Confirm receipt of notification of exceedance
in writing. |
1.
Identify
source(s), investigate the causes of exceedance and propose remedial
measures; 2.
Implement
remedial measures; and 3.
Amend working methods agreed with the ER as
appropriate. |
Exceedance
for two or more consecutive samples |
1.
Repeat
measurements to confirm findings; 2.
If exceedance is confirmed, inform Contractor, IEC and ER; 3.
Identify
source(s), investigate the causes of exceedance and propose remedial measures; 4.
Increase
monitoring frequency to daily; 5.
Advise
the Contractor and ER on the effectiveness of the proposed remedial measures; 6.
Discuss
with IEC and Contractor on remedial actions required; 7.
If
exceedance continues, arrange meeting with Contractor, IEC and ER to discuss the
remedial measures to be taken;
and 8.
If exceedance
stops, cease additional monitoring. |
1.
Check monitoring data submitted by the ET; 2.
Check Contractor’s working method; 3.
Discuss with ET, ER and Contractor on
possible remedial measures; 4.
Review and advise the ET and ER on the effectiveness
of the proposed remedial measures; and 5.
Supervise Implementation of remedial
measures. |
1.
Confirm
receipt of notification of exceedance in writing; 2.
In consultation with the ET and IEC agree
with the Contractor on the remedial measures to be implemented; and 3.
Supervise implementation of remedial
measures. |
1. Identify source(s) and investigate the
causes of exceedance; 2. Submit
proposals for remedial measures to the ER, ET and IEC
within three working days of notification
for agreement; 3. Implement the agreed proposals; and 4. Amend proposal as appropriate. |
LIMIT LEVEL |
||||
Exceedance
for one sample |
1. Repeat measurement to confirm findings; 2. If
exceedance is confirmed, inform the Contractor, IEC, EPD and ER; 3. Identify source(s), investigate the causes
of exceedance and propose remedial; 4. Increase monitoring frequency to daily; and 5. Discuss with the ER, IEC and Contractor on
the remedial measures and assess effectiveness. |
1.
Check monitoring data submitted by the ET; 2.
Check Contractor’s working method; 3.
Discuss with the ET, ER and Contractor on
possible remedial measures; 4.
Review and advise the ET and ER on the effectiveness of the proposed remedial
measures; and 5.
Supervise
implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance
in writing; 2.
Review and agree on the remedial measures
proposed by the Contractor; and 3.
Ensure
remedial measures properly implemented. |
1.
Identify source(s) and investigate the causes
of exceedance; 2.
Take immediate action to avoid further
exceedance; 3.
Submit proposals for remedial measures to ER, ET and IEC
within three working days of notification
for agreement; 4.
Implement the agreed proposals; and 5.
Amend proposal if appropriate. |
Exceedance for two or
more consecutive samples |
1.
Repeat measurement to confirm findings; 2.
If exceedance is confirmed, inform IEC, ER,
Contractor and EPD; 3.
Identify source(s), investigate the causes of
exceedance and propose remedial measures; 4.
Increase monitoring frequency to daily; 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6.
Arrange meeting with IEC and ER to discuss
the remedial actions to be taken; 7.
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; and 8.
If exceedance stops, cease additional
monitoring. |
1.
Check monitoring data submitted by the ET; 2.
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 3.
Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; and 4.
Supervise the implementation of remedial
measures. |
1.
Confirm
receipt of notification of exceedance in writing; 2.
In
consultation with the ET and IEC, agree with the Contractor on the remedial
measures to be implemented; 3.
Supervise
the implementation of remedial measures; and 4.
If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1. Identify source(s) and investigate the
causes of exceedance; 2. Take immediate action to avoid further
exceedance; 3. Submit proposals for remedial measures to
the ER, IEC and ET within three working days of
notification for agreement; 4. Implement the agreed proposals; 5. Revise and resubmit proposals if problem
still not under control; and 6. Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
Noise
Parameters
Monitoring
Equipment and Methodology
Noise
Monitoring Stations
Table 3.1 Noise Monitoring Stations
during Construction Phase
Monitoring Station No.(1) |
NSR ID in EIA
Report |
NSR Description |
CN1 |
CG |
Tower 1, Century Gateway Phase 1 |
CN2 |
IPS |
Islamic Primary School |
CN3 |
LMO |
Block 13, Lung Mun Oasis |
CN4 |
HSNPS |
Yan Chai Hospital Ho Sik Nam Primary School |
CN5 |
TCC |
Taoist Ching Chung Primary School |
CN6 |
OH |
Tower 1, Oceania Heights |
CN7 |
PG |
Block 1, Pierhead Garden |
CN8 |
WF |
Wu Fai House |
CN9 |
GG |
Block 8, Glorious Garden |
CN10 |
OL |
Oi Lai House, Yau Oi Estate |
CN11 |
WT |
Wu Tsui House |
Note:
(1) Construction noise impact monitoring should
be conducted at the monitoring stations when there are Project-related major
construction activities being undertaken within a radius of 300m from the
monitoring stations.
· Monitoring at locations close to the
major site activities of the Project that are likely to arise noise impacts;
· Monitoring as close as possible to
the NSRs as defined in the EIAO-TM; and
· Assurance of minimal disturbance to
the occupants and working under a safe condition during monitoring.
Impact
Monitoring
Event
and Action Plan
Table 3.2 Action and Limit Levels for
Construction Noise Impact Monitoring
Time Period |
Action Level |
Limit Level |
0700-1900 hours on
normal weekdays |
When one documented
complaint is received |
75 dB(A) for
residential premises |
70 dB(A) for schools
and 65 dB(A) during
examination period |
Table 3.3 Event
and Action Plan for Construction Noise Monitoring
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action Level |
1.
Investigate the complaint and propose
remedial measures; 2.
Discuss with the ER and Contractor on the
remedial measures required; and 3.
Increase monitoring frequency to check
mitigation effectiveness. |
1.
Review the investigation results submitted by
the Contractor; and 2.
Review and advise the ET and ER on the
effectiveness of the remedial measures proposed by the Contractor. 3.
Supervise the
implementation of remedial measures. |
1.
Notify the Contractor, ET, IEC and Confirm
receipt of notification of complaint in writing; 2.
Review and agree on the remedial measures
proposed by the Contractor; and 3.
Supervise implementation of remedial
measures. |
1.
Investigate the complaint and propose
remedial measures; 2.
Report the results of investigation to the
IEC, ET and ER; 3.
Submit noise mitigation proposals to the ER, IEC and
ET within three working days of
notification for agreement; and 4.
Implement noise mitigation proposals. |
Limit Level |
1.
Notify the Contractor, IEC, EPD and ER; 2.
Repeat measurement to confirm exceedance; 3.
Identify source and investigate the causes of
exceedance; 4.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 5.
Arrange meeting with the IEC and ER to
discuss the remedial measures to be taken; 6.
Review the effectiveness of Contractor’s
remedial measures and keep IEC, EPD and ER informed of the results; and 7.
If exceedance stops, cease additional
monitoring. |
1.
Check monitoring data submitted by the ET; 2. Check the Contractor’s working method; 3.
Discuss with the ER, ET and Contractor on the potential remedial
measures; and 4.
Review and advise the ET and ER on the
effectiveness of the remedial measures proposed by the Contractor. 5.
Supervise the implementation of remedial
measures. |
1.
Confirm receipt of notification of exceedance
in writing; 2.
In consultation with the ET and IEC, agree
with the Contractor on the remedial measures to be implemented; 3.
Supervise the implementation of remedial
measures; and 4.
If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1.
Identify source and investigate the causes of
exceedance; 2.
Take immediate action to avoid further
exceedance; 3.
Submit proposals for remedial measures to the
ER, IEC and ET within three working days of notification
for agreement; 4.
Implement the agreed proposals; 5.
Revise and resubmit proposals if problem
still not under control; and 6.
Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
Noise
Parameter and Criteria
Table 3.4 Acceptable
Noise Levels for Airborne Railway Noise
Time Period |
Noise Criteria (Leq, 30min, dB(A)) |
||
ASR A |
ASR B |
ASR C |
|
Daytime and Evening (0700 to 2300 hours) |
60 |
65 |
70 |
Night-time (2300 to 0700 hours) |
50 |
55 |
60 |
Monitoring
Equipment and Methodology
Noise
Monitoring Stations
Table 3.5 Noise
Monitoring Stations For Railway Noise
Monitoring Station No.(1) |
NSR ID in EIA
Report |
NSR Description |
ASR(2) |
ON1 |
OT |
Oi Tak House, Yau Oi Estate |
B |
ON2 |
WHPQ |
Tuen Mun Wu Hong Police Quarters |
B |
ON3 |
WB |
Wu Boon House, Wu King Estate |
B |
Notes:
(1) One set of 30-minute measurement at the
designated monitoring station should be conducted during night-time (2300 –
0700 hours). Relevant noise criterion
should be adopted for compliance checking accordingly.
(2) The corresponding ASR of the NSR is
determined based on the best available information and is for indicative
assessment only. The Noise Control Authority shall determine noise impact from
concerned noise sources on the basis of prevailing legislation and practices
being in force, and the ASR determined in this report should not bind the
Authority when enforcing the NCO based on the contemporary conditions.
The ASR would be reviewed as necessary based on the contemporary
conditions/situations.
· Monitoring at locations close to the
major operation activities of the Project that are likely to arise noise
impacts;
· Monitoring as close as possible to
the NSRs as defined in the EIAO-TM; and
· Assurance of minimal disturbance to
the occupants and working under a safe condition during monitoring.
Construction
Phase
Operation
Phase
4.1.1
Potential water quality impacts arising from the
construction and operation phases of the Project were identified and assessed
in the EIA Report. With the implementation of
the recommended mitigation measures, no adverse water quality impacts from
the Project would be expected during the construction and operation phases of
the Project. Nevertheless, water quality
monitoring and site audit is recommended during construction phase to ensure
that all the recommended mitigation measures are properly implemented. No monitoring or audit is required in the
operation phase.
Monitoring
Parameters
Monitoring
Schedule and Stations
4.2.3
The proposed water quality monitoring schedule
should be submitted to EPD at least two weeks before the first day of the
monitoring month. EPD should also be
notified immediately for any changes in schedule. The monitoring stations proposed in this
section are indicative and are subject to further review before commencement of
construction works at Tuen Mun River Channel.
The locations of monitoring stations may change after issuing this
Manual. The proposed monitoring
locations should be submitted four weeks before commencement of baseline
monitoring for IEC and EPD approval.
4.2.4
When alternative monitoring locations are proposed,
they should be chosen based on the following criteria:
· Close to the sensitive receptors which are directly or likely to be
affected;
· For monitoring locations located in the vicinity of the sensitive
receptors, care should be taken to cause minimal disturbance during monitoring;
· Two or more control stations which should be at representative locations
of the Project site in its undisturbed condition. Control stations should be
located, as far as practicable, both upstream and downstream of the works area.
4.2.5
A total of 11 water quality monitoring locations
are proposed in the Tuen Mun River channel (W1 to W11) during ebb tide and
flood tide. Impact stations are
designated in the vicinity of piling works and pile cap construction works
within the Tuen Mun River Channel to measure any elevation of pollutant levels
(e.g. SS level) due to the Project. As
the water flow direction in the river channel is dominated by the tidal forcing
from the southern entrance of the sea channel, the upstream station (i.e. W1)
and downstream station (i.e. W8) of Tuen Mun River Channel would be served as
control stations according to the tidal condition to compare the water quality
near the works sites with the ambient water quality during the ebb tide and
flood tide. All the proposed water quality monitoring stations are listed in Table 4.1 and their locations are shown
in Figure No. C1502/C/TME/ACM/M60/401.
Table 4.1 Proposed River Water Quality Monitoring
Stations for Baseline and Construction Phase Monitoring
Station ID. |
Description(1) |
Easting |
Northing |
Ebb Tide |
|||
W1 |
Control Station |
815248 |
828328 |
W2 |
Impact Station |
815152 |
827793 |
W3 |
Impact Station |
814910 |
827397 |
W4 |
Impact Station |
814842 |
827316 |
W5 |
Impact Station |
814729 |
826983 |
W6 |
Impact Station |
814732 |
826890 |
W7 |
Impact Station |
814715 |
826771 |
Flood Tide |
|||
W8 |
Control Station |
814789 |
826682 |
W9 |
Impact Station |
814693 |
826816 |
W10 |
Impact Station |
814717 |
826927 |
W11 |
Impact Station |
814759 |
827168 |
W3 |
Impact Station |
814910 |
827397 |
W2 |
Impact Station |
815152 |
827793 |
W1 |
Impact Station |
815248 |
828328 |
Note:
(1) Monitoring will be conducted when piling
works and pile cap construction works are being conducted at Tuen Mun River
Channel. As impact stations are
designated in the vicinity of piling works and pile cap construction works
within the Tuen Mun River Channel, the water quality monitoring will only be
conducted at the designated stations that are located in the vicinity of piling
works and pile cap construction works.
Monitoring
Requirements
· Measurement should be taken at 3 water depths, namely, 1m below water
surface, mid-depth and 1m above sea bed, except where the water depth less that
6m, the mid-depth station may be omitted.
Should the water depth be less than 3m, only the mid-depth station will
be monitored. The ET should agree with
EPD on all the monitoring stations.
· Duplicate in-situ measurements and water samples collected from
each independent monitoring event are required for all parameters to ensure a
robust statistically interpretable dataset.
· No sampling should be carried out when typhoon signal No. 3 or above or
black rainstorm signal is hoisted.
· At each measurement depth, two consecutive measurements should be
taken. The probes would be retrieved out
of the water after the first measurement and then redeployed for the second
measurement. When the difference in
value between the first and second measurement of on-site parameters is more
than 25% of the value of the first reading, the reading should be discarded and
further readings should be taken.
Baseline
monitoring
4.2.7
Baseline conditions for river water quality should
be established and agreed with EPD prior to the commencement of works at Tuen
Mun River Channel. The purpose of the
baseline monitoring is to establish ambient conditions prior to the
commencement of the construction works at Tuen Mun River Channel and to
demonstrate the suitability of the proposed monitoring stations. The baseline monitoring report should be
submitted to EPD at least 4 weeks before the commencement of construction works
at Tuen Mun River Channel for agreement.
The baseline monitoring report should be certified by the ET Leader and
verified by IEC before submission to EPD.
4.2.8
The baseline conditions should be established by
measuring water quality parameters as specified in Section 4.2.1 and 4.2.2 at the designated monitoring
stations as shown in Table 4.1. The measurement depths should follow those
specified in Section 4.2.6. The measurements should be taken at all designated
monitoring stations including control station, 3 days per week, at mid-flood
and mid-ebb tides, for at least 4 weeks prior to the commencement of
construction works at Tuen Mun River Channel.
There should not be any construction activities in the vicinity of the
stations during the baseline monitoring.
The interval between 2 consecutive sets of monitoring should not be less
than 36 hours.
Impact
Monitoring
4.2.9
During the construction period of the bored piling
works and construction of pile caps at Tuen Mun River Channel, impact
monitoring should be undertaken 3 days per week, at mid-flood and mid-ebb
tides, with sampling/measurement at all designated monitoring stations
including control station as specified in Table 4.1. The interval between 2 consecutive sets of
monitoring should not be less than 36 hours except where there are exceedances
of Action and/or Limit levels, in which case the monitoring frequency will be
increased. The monitoring parameters and
measurement depths should follow those specified in Section 4.2.1, 4.2.2 and 4.2.6.
4.2.10
If the impact monitoring data collected at the
monitoring stations (i.e. Stations W2, W3, W4, W5, W6 and W7 during ebb tide;
Stations W1, W2, W3, W9, W10, W11 during flood tide) exceed that the Action or
Limit levels as shown in Table 4.2, analysis should be conducted
to identify whether the exceedance is caused by Project activities. If the data analysis results indicate that
the exceedance is caused by the Project, appropriate actions including lowering
the working rate, or rescheduling of works should be taken and additional
mitigation measures should be implemented as necessary.
Post-Construction
Monitoring
4.2.11
Upon completion of all construction works at Tuen
Mun River Channel, a post-project monitoring should be carried out for 4 weeks
in the same manner as the impact monitoring.
Monitoring
Equipment
4.2.12
The following equipment and facilities should be
provided by the ET and used for the monitoring of water quality impacts.
Monitoring
Position Equipment
4.2.13
A hand-held or boat-fixed type digital Differential
Global Positioning System (DGPS) with way point bearing indication or other
equipment instrument of similar accuracy, should be provided and used during
water quality monitoring to ensure the monitoring vessel is at the correct
location before taking measurements.
DGPS or the equivalent instrument, calibrated at appropriate checkpoint
(e.g. Quarry Bay Survey Nail at Easting 840683.49, Northing 816709.55) should
be provided and used to ensure the monitoring station is at the correct
position before taking measurement and water samples.
Sampler
4.2.14
A water sampler is required. It should comprise a transparent PVC
cylinder, with a capacity of not less than 2 litres, which can be effectively
sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the selected
water depth (for example, Kahlsico Water Sampler or an approved similar
instrument).
Water
Depth Detector
4.2.15
A portable, battery-operated echo sounder should be
used for the determination of water depth at each designated monitoring
station. This unit can either be hand
held or affixed to the bottom of the work boat, if the same vessel is to be
used throughout the monitoring programme.
Dissolved
Oxygen and Temperature Measuring Instrument
4.2.16
The instrument should be a portable and
weatherproof DO measuring instrument complete with cable and sensor, and use a
DC power source. The equipment should be
capable of measuring:
· a DO-level in the range of 0 - 20 mg/L and 0 - 200% saturation; and
· a temperature of 0 - 45 degree Celsius with a capability of measuring to
±0.1 degree Celsius.
4.2.17
It should have a membrane electrode with automatic
temperature compensation complete with a cable.
Sufficient stocks of spare electrodes and cables should be available for
replacement where necessary. (For example, YSI model 59 meter, YSI 5739 probe,
YSI 5795A submersible stirrer with reel and cable or an approved similar
instrument).
4.2.18
Should salinity compensation not be built-in to the
DO equipment, in-situ salinity should be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity
Measuring Instrument
4.2.19
Turbidity should be measured in-situ by the
nephelometric method. The instrument
should be portable and weatherproof using a DC power source complete with
cable, sensor and comprehensive operation manuals. It should have a photoelectric sensor capable
of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or
an approved similar instrument). The
cable should not be less than 25m in length.
The meter should be calibrated in order to establish the relationship
between NTU units and the levels of suspended solids. The turbidity measurement should be carried
out on split water sample collected from the same depths of suspended solids
samples.
Salinity
Measuring Equipment
4.2.20
A portable salinometer capable of measuring
salinity in the range of 0 - 40 parts per thousand (ppt) should be provided for
measuring salinity of the water at each monitoring location.
pH
Measuring Equipment
4.2.21
The instrument should consist of a potentiometer, a
glass electrode, a reference electrode and a temperature-compensating
device. It should be readable to 0.1 pH
in a range of 0 to 14. Standard buffer
solutions of at least pH 7 and pH 10 should be used for calibration of the
instrument before and after use. Details
of the method should comply with APHA, 19th Edition 4500-HTB.
Sample
Containers and Storage
4.2.22
Water samples for SS determination should be stored
in high density polythene bottles with no preservative added,
packed in ice (cooled to 4℃ without being frozen) and
delivered to the laboratory and analysed as soon as possible after
collection. Sufficient volume of samples
should be collected to achieve the detection limit.
Calibration
of in-situ Instruments
4.2.23
All in-situ monitoring instruments should be
checked, calibrated and certified by a laboratory accredited under HOKLAS or
any other international accreditation scheme before use and subsequently
re-calibrated at three monthly intervals throughout all stages of the water
quality monitoring programme. Responses
of sensors and electrodes should be checked with certified standard solutions
before each use. Wet bulb calibration
for a DO meter should be carried out before measurement at each monitoring
location.
4.2.24
For the on-site calibration of field equipment, the
BS 127:1993, Guide to Field and On-Site Test Methods for the Analysis of Water
should be observed.
4.2.25
Sufficient stocks of spare parts should be
maintained for replacements when necessary.
Backup monitoring equipment should also be made available so that
monitoring can proceed uninterrupted even when some equipment is under
maintenance, calibration, etc.
Field
Log
4.2.26
A sample data record sheet is shown in Appendix C for reference.
Laboratory
Measurement / Analysis
4.2.27
Analysis of SS level should be carried out in a
HOKLAS (or other international accredited laboratory that is
HOKLAS-equivalent). Sufficient water
samples of not less than 2 litres should be collected at the monitoring
stations for carrying out the laboratory SS determination. All samples should be assigned a unique code
and accompanied by Chain of Custody (COC) sheets.
4.2.28
The SS determination work should start within 24
hours after collection of the water samples.
The SS analyses should follow the standard method APHA 2540D with a
detection limit of 1 mg/L as described in APHA Standard Methods for the
Examination of Water and Wastewater, 21st Edition, unless otherwise specified.
4.2.29
Detailed testing methods, pre-treatment procedures,
instrument use, Quality Assurance/Quality Control (QA/QC) details (such as
blank, spike recovery, number of duplicate samples per batch, etc.), detection
limits and accuracy should be submitted to IEC and EPD for approval prior to
the commencement of monitoring programme.
EPD may also request the laboratory to carry out analysis of known
standards provided by EPD for quality assurance. The testing methods and related proposal
should be checked and certified by IEC before submission to EPD for approval.
4.2.30
Additional duplicate samples may be required by EPD
for inter laboratory calibration.
Remaining samples after analysis should be kept by the laboratory for 3
months in case repeat analysis is required.
If in-house or non-standard methods are proposed, details of the method
verification may also be required to submit to EPD. In any circumstance, the sample testing
should have comprehensive quality assurance and quality control
programmes. The laboratory should
prepare to demonstrate the programmes to EPD or his representatives when
requested.
Event
and Action Plan
4.2.31
The Action and Limit (AL) Levels for water quality
are defined in Table 4.2. The actions in accordance with the Event and
Action Plan in Table 4.3 should be carried out if the
defined Action and/or Limit levels for water quality are exceeded at any
designated monitoring points.
Table 4.2 Action and Limit Levels for Water Quality
Parameters |
Action
Level |
Limit
Level |
DO (mg/L) |
Surface, Middle and Bottom 5 percentile of baseline data |
Surface, Middle and Bottom 4 mg/L, or 1 percentile of baseline data |
SS (mg/L) |
Depth Average 95 percentile of baseline data and
120% of upstream control station at the same tide of the same day |
Depth Average 99 percentile of baseline data and
130% of upstream control station at the same tide of the same day |
Turbidity (NTU) |
Depth Average 95 percentile of baseline data
and 120% of upstream control station at the same tide of the same day |
Depth Average 99 percentile of baseline data
and 130% of upstream control station at the same tide of the same day |
Notes:
(1) "Depth Average" is
calculated by taking the arithmetic means of reading of all sampling depths.
(2) For DO, non-compliance of the
water quality limits occurs when monitoring result is lower than the limits.
(3) For turbidity and SS,
non-compliance of the water quality limits occurs when monitoring result is
higher than the limits.
(4) All the figures given in the table
are used for reference only and the EPD may amend the figures whenever it is
considered as necessary.
Table 4.3 Event and Action Plan for Water Quality
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action level being exceeded by one sampling day |
1.
Repeat in-situ measurement on next day
of exceedance to confirm findings; 2.
Identify reasons for non-compliance and
source(s) of impact; 3.
Inform IEC and Contractor; and 4.
Check monitoring data, all plant, equipment
and Contractor’s working methods. |
1.
Check monitoring data submitted by ET and
Contractor(s)’s working methods. |
1.
Confirm receipt of notification of exceedance
in writing. |
1.
Inform the ER and confirm notification of the
non-compliance in writing; 2.
Check all plant and equipment and rectify
unacceptable practice. |
Action level being exceeded by two or more
consecutive sampling days |
1.
Repeat in-situ measurement on next day
of exceedance to confirm findings; 2.
Identify reasons for non-compliance and
source(s) of impact; 3.
Inform IEC and Contractor; 4.
Check monitoring data, all plant, equipment
and Contractor's working methods; 5.
Discuss additional mitigation measures with
IEC and Contractor and ensure mitigation measures are implemented; and 6.
Prepare to increase the monitoring frequency
to daily. |
1.
Discuss with ET and Contractor on the
mitigation measures and advise the ER accordingly; 2.
Assess the effectiveness of the implemented
mitigation measures; and 3.
Check monitoring data submitted by ET and Contractor(s)’s
working methods. |
1.
Confirm receipt of notification of exceedance
in writing 2.
Discuss with IEC on the proposed mitigation
measures and agree on the mitigation measures to be implemented; 3.
Ensure additional mitigation measures are
properly implemented; and 4.
Assess the effectiveness of the implemented
mitigation measures. |
1.
Inform the ER and confirm notification of the
non-compliance in writing; 2.
Check all plant and equipment and rectify
unacceptable practice; 3.
Consider changes of working methods; 4.
Discuss with ET and IEC and propose
mitigation measures to IEC and ER within 3 working days; and 5.
Implement the agreed mitigation measures. |
Limit level being exceeded by one sampling day |
1.
Repeat in-situ measurement on next day
of exceedance to confirm findings; 2.
Identify reasons for non-compliance and
source(s) of impact; 3.
Inform IEC, Contractor and ER; 4.
Check monitoring data, all plant, equipment
and Contractor's working methods; 5.
Discuss additional mitigation measures with
IEC, ER and Contractor and ensure mitigation measures are implemented; and 6.
Increase the monitoring frequency to daily
until no exceedance of limit level. |
1.
Discuss with ET and Contractor on the
mitigation measures; 2.
Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; 3.
Assess the effectiveness of the implemented
mitigation measures. |
1.
Confirm receipt of notification of exceedance
in writing 2.
Discuss with IEC, ET and Contractor on the
proposed mitigation measures and agree on the mitigation measures to be
implemented; 3.
Ensure additional mitigation measures are
properly implemented; 4.
Assess the effectiveness of the implemented
mitigation measures; and 5.
Request Contractor to critically review the
working methods. |
1.
Inform the ER and confirm notification of the
non-compliance in writing; 2.
Check all plant and equipment and rectify
unacceptable practice; 3.
Consider changes of working methods; 4.
Discuss with ET and IEC and propose
mitigation measures to IEC and ER within 3 working days; and 5.
Implement the agreed mitigation measures. |
Limit level being exceeded by two or more
consecutive sampling days |
1.
Repeat in-situ measurement on next day
of exceedance to confirm findings; 2.
Identify reasons for non-compliance and
source(s) of impact; 3.
Inform IEC, Contractor and ER; 4.
Check monitoring data, all plant, equipment
and Contractor's working methods; 5.
Discuss additional mitigation measures with
IEC, ER and Contractor and ensure mitigation measures are implemented; and 6.
Increase the monitoring frequency to daily
until no exceedance of limit level. |
1.
Discuss with ET and Contractor on the
mitigation measures; 2.
Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3.
Assess the effectiveness of the implemented
mitigation measures. |
1.
Confirm receipt of notification of exceedance
in writing 2.
Discuss with IEC, ET and Contractor on the
proposed mitigation measures and agree on the mitigation measures to be
implemented; 3.
Ensure additional mitigation measures are
properly implemented; 4.
Assess the effectiveness of the implemented
mitigation measures; 5.
Request Contractor to critically review the
working methods; and 6.
Consider and instruct, if necessary, the
Contractor to slow down or to stop all or part of the construction activities
until no exceedance of Limit level. |
1.
Inform ER and confirm notification of
non-compliance in writing; 2.
Check all plant and equipment and rectify
unacceptable practice; 3.
Consider changes of working methods; 4.
Discuss with ET and IEC and propose
mitigation measures to IEC and ER within 3 working days; 5.
Implement the agreed mitigation measures; and 6.
As directed by the ER, to slow down or to
stop all or part of the construction activities. |
4.3.1
Mitigation measures for construction phase water
quality impacts have been recommended in the EIA Report. The Contractor should be responsible for the
design and implementation of the mitigation measures.
4.4.1
Monitoring of the treated effluent quality from the
Project site is required during the construction phase of the Project. The monitoring should be carried out at the
pre-determined discharge point.
Compliance audits aims to ensure that a valid discharge licence has been
issued by EPD prior to the discharge of effluent from the Project site. The monitoring frequency and parameters
specified in the discharge licence under WPCO should be fully considered during
the monitoring.
Pre-Construction
Ecological Survey
Ardeid
Night Roost Monitoring
· The EIA Report and EM&A
recommendations on environmental protection and pollution control mitigation
measures;
· Ongoing results of the EM&A
programme;
· Works progress and programme;
· Individual works methodology
proposals (which should include the proposal on associated pollution control
measures);
· Contract specifications on
environmental protection and pollution prevention control;
· Relevant environmental protection
and pollution control legislations; and
· Previous site inspection results
undertaken by the ET and others.
· The Contractor to log complaint and
date of receipt onto the complaint database and inform the ER, ET and IEC
immediately;
· The Contractor to investigate, with
the ER and ET, the complaint to determine its validity, and assess whether the
source of the problem is due to construction works of the Project with the
support of additional monitoring frequency and stations, if necessary;
· The Contractor to identify remedial
measures in consultation with the IEC, ET and ER if a complaint is valid and
due to the construction works of the Project;
· The Contractor to implement the
remedial measures as required by the ER and to agree with the ET and IEC any
additional monitoring frequency and stations, where necessary, for checking the
effectiveness of the remedial measures;
· The ER, ET and IEC to review the
effectiveness of the Contractor's remedial measures and the updated situation;
· The ET/Contractor to undertake
additional monitoring if necessary and audit to verify the situation, and
oversee that circumstances leading to the complaint do not recur;
· If the complaint is referred by the
EPD, the Contractor to prepare interim report on the status of the complaint
investigation and follow-up action stipulated above, including the details of
the remedial measures and additional monitoring identified or already taken,
for submission to EPD within the time frame assigned by the EPD; and
· The ET to record the details of the
complaint, results of the investigation,
subsequent actions taken to address the complaint and updated situation
including the effectiveness of the remedial measures, supported by regular and
additional monitoring results in the monthly EM&A reports.
(i)
up
to half a page of executive summary;
(ii)
brief
description of project background information;
(iii)
drawings
showing locations of the baseline monitoring stations;
(iv)
monitoring
results (in both hard and soft copies) together with the following information:
monitoring
methodology
name of
laboratory and types of equipment used and calibration details
parameters
monitored
monitoring
locations (and depth)
monitoring
date, time, frequency and duration
quality
assurance (QA) /
quality control (QC) results and detection
limits
(v)
details
of influencing factors, including:
major
activities, if any, being carried out on the Project site during the period
weather
conditions during the period
other
factors which might affect the
monitoring results
(vi)
determination
of the Action and Limit Levels (AL levels) for each monitoring parameter and
statistical analysis of the baseline data;
(vii)
revisions
for inclusion in the EM&A Manual; and
(viii)
comments
and conclusions.
(i)
executive
summary (1-2 pages):
breaches of
Action and Limit levels;
complaint
log;
notifications
of any summons and successful prosecutions;
reporting
changes; and
future key
issues.
(ii)
basic
project information:
project
organization including key personnel contact names and telephone numbers;
construction
programme;
management
structure; and
works
undertaken during the reporting month.
(iii)
environmental
status:
advice on
the status of statutory environmental compliance, such as the status of
compliance with the EP conditions under the EIAO, submission status under the
EP and implementation status of mitigation measures;
works
undertaken during the reporting month with illustrations (e.g. location of
works, etc); and
drawings
showing the Project area, any environmental sensitive receivers and the
locations of the monitoring stations.
(iv)
summary
of EM&A requirements:
all
monitoring parameters;
environmental
quality performance limits (Action and Limit levels);
Event and
Action Plans;
environmental
mitigation measures, as recommended in the EIA Report; and
environmental
requirements in contract documents.
(v)
implementation
status:
advice on
the implementation status of environmental protection and pollution control/mitigation
measures as recommended in the EIA Report.
(vi)
monitoring
results (in both hard and soft copies) together with the following information:
monitoring
methodology;
name of laboratory
and types of equipment used and calibration details;
monitoring
parameters;
monitoring
locations;
monitoring
date, time, frequency and duration; and
graphical
plots of the monitoring parameters in the reporting month annotated against the
following;
a) major activities being carried out on site during the reporting
period;
b) weather conditions during the reporting period;
c) any other factors which might affect the monitoring results; and
d) QA/QC results and detection limits.
(vii) report on non-compliance, complaints,
notifications of summons and status of prosecutions:
record of
all non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit levels);
record of
all complaints received, including locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
record of
all notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
review of
the reasons for and the implications of non-compliances, complaints, summons
and prosecutions including review of pollution sources and working procedures;
and
description
of the actions taken in the event of non-compliance and deficiency reporting
and any follow-up procedures related to earlier non-compliance.
(viii)
others:
an account
of the future key issues as reviewed from the works programme and method
statements of works;
advice on
the solid and liquid waste management status;
record of
any project changes from that originally proposed as described in the EIA
Report
(e.g. construction methods, mitigation proposals, design changes, etc); and
comments
(e.g. the effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
(i)
executive
summary (1-2 pages):
breaches of
Action and Limit levels;
complaint
log;
notifications
of any summons and successful prosecutions;
reporting
changes; and
future key
issues.
(ii)
basic
project Information:
project
organization including key personnel contact names and telephone numbers;
construction
programme;
management
structure;
works
undertaken during the reporting month; and
any updates
as needed to the scope of works, and construction methodologies.
(iii)
environmental
status:
advice on
the status of statutory environmental compliance, the status of compliance with
the EP conditions under the EIAO, submission status under the EP and
implementation status of mitigation measures;
works
undertaken during the reporting month with illustrations (such as location of
works, etc); and
drawings
showing the Project area, any environmental sensitive receivers and the
locations of the monitoring stations.
(iv)
implementation status:
advice on
the implementation status of environmental protection and pollution
control/mitigation measures as recommended in the EIA Report.
(v)
monitoring
results (in both hard and soft copies) together with the following information:
monitoring methodology;
name of
laboratory and types of equipment used and calibration details;
monitoring
parameters;
monitoring
locations (and depth);
monitoring
date, time, frequency and duration; and
graphical
plots of the monitoring parameters in the reporting month annotated against the
following;
a) major activities being carried out on site during the reporting
period;
b) weather conditions during the reporting period;
c) any other factors which might affect the monitoring results; and
d) QA/QC results and detection limits.
(vi)
report
on non-compliance, complaints, notifications of summons and status of
prosecutions:
record of
all non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit levels);
record of
all complaints received, including the locations and nature of complaints
investigation, liaison and consultation undertaken, actions and follow-up
procedures taken, results and summary;
record of
all notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
review of
the reasons for and the implications of non-compliance, complaints, summons and
prosecutions including review of pollution sources and working procedures; and
descriptions
of the actions taken in the event of non-compliances and deficiency reporting
and any follow-up procedures related to earlier non-compliance.
(vii)
others:
an account
of the future key issues as reviewed from the works programme and method
statements of works;
advice on
the solid and liquid waste management status;
record of
any project changes from that originally proposed as described in the EIA (e.g.
construction methods, mitigation proposals, design changes, etc); and
comments
(e.g. the effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
(viii)
appendix:
Action and
Limit levels;
graphical
plots of trends of the monitoring parameters over the past four reporting
periods for the representative monitoring stations annotated against the
following:
a) major Project activities being carried out on site during the
reporting period;
b) weather conditions during the reporting period; and
c) any other factors that might affect the monitoring results.
monitoring
schedule for the present and next reporting period;
cumulative
statistics on notifications of summons and successful prosecutions; and
outstanding
issues and deficiencies.
(i)
executive
summary (1 - 2 pages);
(ii)
drawings
showing the Project area, environmental sensitive receivers and locations of
the monitoring stations;
(iii)
basic
project information including a synopsis of the project organisation, contacts
of key management, and a synopsis of works undertaken during the course of the
Project;
(iv)
a
brief summary of EM&A requirements including:
environmental
mitigation measures, as recommended in the EIA Report;
environmental
impact hypotheses tested;
environmental
quality performance limits (Action and Limit levels);
all
monitoring parameters; and
Event and
Action Plans;
(v)
a
summary of the implementation status of environmental protection and pollution
control / mitigation measures, as recommended in the EIA Report, summarised in
the updated implementation schedule;
(vi)
advice
on the solid and liquid waste management status;
(vii)
graphical
plots and the statistical analysis of the trends of monitoring parameters over
the course of the Project, including the post-project monitoring for all
monitoring stations annotated against:
the major
activities being carried out on site during the reporting period;
weather
conditions during the reporting period; and
any other
factors which might affect the monitoring results;
(viii)
a
summary of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit levels);
(ix)
a
review of the reasons for and the implications of non-compliance including
review of pollution sources and working procedures as appropriate;
(x)
a
description of the actions taken in the event of non-compliance;
(xi)
a
summary record of all complaints received, liaison and consultation undertaken,
actions and follow-up procedures taken;
(xii)
a
summary record of notifications of summons and successful prosecutions for
breaches of the current environmental protection / pollution control
legislation, locations and nature of the breaches, investigation follow-up
actions taken and results;
(xiii)
a
review of the validity of EIA predictions and identification of shortcomings of
the recommendations proposed in EIA Report; and
(xiv)
comments
(for example, a review of the effectiveness and efficiency of the mitigation
measures and of the performance of the environmental management system, that
is, of the overall EM&A programme); and
(xv)
recommendations
and conclusions (for example, a review of success of the overall EM&A
programme to cost-effectively identify deterioration and to initiate prompt
effective mitigation action when necessary).