Contents
Page
2.3 Predicted Future Without the Proposed Development
2.4 Development and Environmental Opportunities
2.6 Formulation of Development Options
2.7 Examination of Development Options
2.8 Recommended Development Parameters and Land Use in Sub-Area 1
2.9 Land Use in Sub-Area 2 to 4
2.11 Proposed Construction Methodologies and Alternatives
TABLES
Table 2.1 Key Comments Received during Public Inspection Period of Project Profile 2-5
Table 2.2 Summary of Evaluation of Development Options 2-13
Table 2.3 Summary of Development Parameters2-14
Table 2.4 Comparison of Benefits and Disbenefits between Different Construciton Methods for Retaining Structures in the Housing Site 2-16
Table 2.5 Summary of Tentative Implementation Programme 2-20
FIGURES
Figure 2.1 Delineation of Sub-Area 1 to Sub-Area 4
Figure 2.2 Notional Layout Plan of Proposed Housing Development
Figure 2.3 Notional Layout Plan of Proposed Housing Development - Section
· Sub-Area 1 is located at the northernmost part of PDA, it extended up to the edge of woodland adjacent to the Fanling Raw Water Pumping Station. This piece of land is generally regular and is adjacent to high density housing development such as Cheung Lung Wai Estate;
· Sub-Area 2 is bounded by the above-mentioned woodland, which is extended up to the existing access road of On Po in the south side. There is a man-made pond in this Sub-Area to provide water source for wildlife.
· Sub-Area 3 is bounded by the existing access road of On Po in the north and the narrow edge adjacent to Tai Lung Experimental Farm at the south. This piece of land is irregular in shape and there are a number of tree clusters at the sides and in the middle of the Sub-Area; and
· Sub-Area 4 is located at the southernmost part of PDA. It is bounded by the boundary of Sub-Area 3 to the Site boundary of PDA.
Existing Condition
Predicted Future Conditions without Project
Predicted Future Conditions with this Project
Development and Environmental Opportunities
Housing Type, Public and Private
Flat Production and Population
Table 2.1 Key Comments Received from Public and Green Group
Aspects |
Key Comments |
Responses |
Traffic Infrastructural Support |
Commenters showed their concerns about additional loading to roads and transport infrastructure due to the project; and suggested to assess based on avoiding the risk of affecting the swamp and hydrology which would be caused by widening Fan Kam Road. |
A comprehensive Traffic Impact Assessment has been conducted under this Study to ensure that there is no insurmountable impact to the existing transport infrastructure. With consideration to the Public’s concern, the major access to the proposed development is provided at Ping Kong Road so as to minimize the traffic impact to Fan Kam Road. |
Community and Transportation Facilities |
Commenters were generally concerned about the insufficiency of the G/IC and transportation facilities in coping with the existing and future population under FGC development. |
While formulating the development options, advice has been sought from relevant departments such as Social Welfare Department to ensure that the facilities provided are sufficient to serve the additional population under FGC development. |
Air Quality and Noise Nuisance |
There were concerns about air and noise pollution in the surrounding areas during construction phase and operation phase. |
The air quality and noise impacts during the construction and operation phases of the Project have been assessed quantitatively in the EIA. The mitigation measures for air quality including watering once per hour on active works areas, exposed areas and haul roads are proposed for dust suppression. Other site management measures such as, good site practices, and environmental monitoring and audit (EM&A) programme are recommended. Air quality impact from vehicular emission associated with the Project and the existing and planned road network, and industrial emissions in the vicinity of the Project during operation phase has been assessed. The results concluded that the predicted cumulative air quality impacts at all air sensitive receivers (ASRs) would comply with the Air Quality Objectives (AQOs). Therefore, no adverse air quality impact during operation phase is anticipated. Regarding the construction noise, the construction noise associated with the use of powered mechanical equipment (PME) for different stages of construction has been assessed. With the implementation of practical mitigation measures including good site management practices, use of Quality Powered Mechanical Equipment (QPME), use of movable noise barrier, noise enclosure and noise insulating fabric and provision of minimum separations from the affected educational institutions or avoidance of any noisy construction activities during the school examination period, the predicted construction noise impact would comply with the criteria stipulated in the EIAO-TM. Hence, no adverse impact arising from the construction of the Project would be anticipated. During the operation phase, at source direct mitigation measures, including the application of low noise road surfacing material have been proposed to mitigate the noise impacts to the sensitive receivers such as Cheung Lung Wai Estate, HKCKLA Buddhist Wisdom Primary School, Tung Wah Group of Hospitals Ma Kam Chan Memorial Primary School, Elegantia College. With the implementation of proposed mitigation measures as discussed in Section 3 and Section 4 4 of the EIA report, no adverse air quality and noise impact is anticipated during construction and operation phases. |
Water Quality and Hydrology |
Commenters showed their concerns about the changes and cumulative impacts to the water flow and water quality due to the proposed development, including diversions of streams and underground water. Some suggested taking cautions on surface runoff during the construction and operation phase. In addition, there are small watercourse connected to the nearby AFCD Tai Lung Experimental Farm and should be examined and determine the impact. |
Diversion of watercourses will only be occurred in Sub-Area 1. Impacts to water flow and water quality due to the proposed development are not anticipated. Besides, as there are no deep tunnel under this Project, the change of groundwater table is therefore not anticipated. During construction phase, proper site management measures should be implemented to control site runoff and drainage, and thereby prevent high sediment loadings from reaching downstream sections of the river/stream. Suitable facility such as portable chemical toilets, will be provided for the workforce on-site. The key potential source of impact on water quality during the operation phase of the Project would include the road run-off, sewage and wastewater effluents and storm run-off from building. Mitigation measures with adequate maintenance are recommended to remove grits and grease from the runoff during operation. In addition, all sewage and wastewater generated from these facilities would be properly collected and diverted to public sewer. Only landscaping works are proposed near the AFCD Tai Lung Experimental Farm, impact to the nearby watercourse is therefore not anticipated. |
Sewerage |
Commenters showed their concerns about whether the development could accommodate the increased sewerage due to increased population. |
In view of the public concerns, the development layout and parameters have been optimised to ensure that no insurmountable impact will be posed by the development. |
Landscape and Visual |
Commenters showed their concerns about the trees, especially on OVT (Old Valuable Tree) and they shall be valued and assessed with complex ecological and biodiversity values under Development Bureau handbook on Tree Management. .
|
According to database of Old and Valuable Tree (OVT) provided by LCSD and our site tree survey, there is currently no registered OVTs found within the study area (Sub-Areas 1 to 4).
However, a detailed tree survey has been conducted in Sub-Area 1 to identify the potential Old and Valuable Trees that may be affected. Mitigation measures such as retaining the Potential OVTs in-situ and transplantation are proposed in our development. Besides, landscape resources and characters within the study area have been identified and evaluated in the Landscape and Visual Impact Assessment.
Assessment of landscape resources is based on the criteria of distinctiveness, maturity and quality of the landscape resources. The importance of each resource has been evaluated in the Landscape and Visual Impact Assessment.
|
Cultural Heritage |
Commenters showed their concern on the historic/heritage value and cultural significance of FGC and golfing in Hong Kong, also with its reactional function. Those were suggested to be assessed per international standards. Moreover, some commenters showed their concerns about the historical and social significance of ancestral graves in FGC and suggested to provide linkage and points of reference between identification on culture and tradition. Furthermore, some comments that FGC has wide significant impact in terms of historical, social and cultural significance. |
A Cultural Heritage Impact Assessments is conducted with reference to the Antiquities and Monuments Ordinance (Cap.49) and Guidelines for Cultural Heritage Impacts Assessment (CHIA) issued by AMO and follow where appropriate, paragraph 4.3.1(c), item 2 of Annex 10, items 2.6 to 2.9 of Annex 19 and other relevant parts of the EIAO-TM on EIA Process, S.16. Assessments are undertaken by heritage experts with local expertise and / or qualified archaeologists if archaeology is involved.
Fanling Golf Course, The Hong Kong Golf Club is a New Item proposed for grading assessment by Antiquities Advisory Board (AAB). The cultural heritage impact assessment concludes the impact of the proposed works on the New Item is undetermined pending grading assessment. Mitigation measures will be recommended to minimize the impact arising from the proposed development to the New Item. 4 graded historic buildings and 1 new item, 11 not-graded historic buildings and 17 of Clan graves have been identified within the CHIA study area. 1 ancestral grave was identified in Sub-Area 1.
The ancestral graves within the potential development areas were taken into considerations while selecting the development options. In the latest proposed development layout the ancestral graves are mostly preserved and the impact to those graves was kept minimal. |
Ecology - general |
Ecology at Sub-Area 2 serves as a habitat for the faunas species of conservation importance. Therefore, massive development at Sub-Area 2 should be avoided. |
Only recreational and ancillary facilities with minimal new structure/change to existing site conditions are proposed in Sub-Area 2 & Sub-Area 3 so as to prevent the damages to the habitat of fauna species. Considering the ecology at Sub-Area 1 is of relatively lower ecological value, only Sub-Area 1 is proposed for housing development. |
|
|
Sub-Area 4 will be preserved the most in order not to disturb the habitat of the species of conservation importance Glyptostrobus pensilis. Sub-Area 3 will also be preserved and served as a buffer area to conserve Sub-Area 4. |
Ecology - flora |
The commenters recognized that the ecology, particularly the group of critically endangered Glyptostrobus pensilis (Chinese Swamp Cypress, which are exotic to Hong Kong) in the swampy woodland, at Sub-Area 4 (i.e. the most southern portion of the site) is of high conservation value and should be preserved.
Besides, there were concerns about Ardisia villosa, which is also a rare species.
Those species contain large historical values and significant to FGC. Their special conservation importance documented by scientific studies raised commenters concern and consider the ecological impact to those flora species. Commenters also concern about the combination of tree species within the area. |
Due to the rarity and conservation importance of Chinese Swamp Cypress, the development has been avoided affecting this species directly and indirectly. The housing development will be around 1km from the woodland of Chinese Swamp Cypress (Swampy Wodoland). While Ardisia villosa was recorded near the housing development, but the woodland where Ardisia villosa located will be preserved and no direct impact to this species is expected. Should Ardisia villosa is found within the development area during the detailed design stage, transplantation to a suitable location may be proposed. |
Ecology - fauna |
Concerns were raised on Malayan Night Heron and other fauna species including bats and insects which are with strong connection within FGC wetlands. Commenters suggested to carry out comprehensive avifauna surveys and thoughtful ecological surveys. |
Comprehensive avifauna and other fauna surveys were conducted for period over 12 months covering both wet and dry seasons. Due to the ecological importance of wetland habitats within the Project Site (i.e. swampy woodland, marsh, pond), all of these important habitats are proposed to be preserved in the adopted development option. Potential impacts to the species rely on wetland habitats are considered insignificant. |
(1) For Development Option 1, housing development with high density and low density scattered in Sub-Area 1, Sub-Area 2 and Sub-Area 3 respectively.
(2) For Development Option 2, public housing development is proposed in Sub-Area 1 of PDA only. Sub-Areas 2 to 4 are proposed to be preserved with minimal works Sub-Areas 2 to 3 and no works in Sub-Area 4.
(3) For Development Option 3, PDA is fully developed with housing development in all four Sub-Areas. This option targets on maximizing housing provisions to meet the pressing housing needs.
2.8.2 Based on the chosen development option, the development layout is developed and presented in Figure 2.2. The proposed public housing development is at the northern part of PDA (i.e. Sub-Area 1) with an approximate net site area of 80,000 m2. The Site is estimated to provide a maximum of 12,000 flats, accommodating a population of approx. 33,600. Alongside with a number of social welfare facilities, kindergartens, a special school and community hall are proposed to serve the population. Meanwhile, local retail and other non-domestic facilities will also be provided within the Site. The latest development parameters for the Site are summarized in Table 2.3 as follows:-
Public Housing Development at Sub-Area 1 |
|
Net Site Area (m2) (about) |
80,000 |
Domestic Plot Ratio |
6.5 |
Domestic Gross Floor Area (m2) (about) |
520,000 |
Average Flat Size (m2) |
43 (TBC) |
Maximum Flat Production (about) |
12,000 (TBC) |
Average Household Size |
2.8 |
Estimated Design Population |
33,600 |
Number of Domestic Blocks |
12 |
Preliminary Building Heights in mPD and No. of Storeys (subject to fine adjustment in next stage of the project) |
127mPD to 164mPD 37 to 43 storeys (TBC) |
Non-Domestic Plot Ratio |
0.5 |
Proposed Non-Domestic GFA (m2) (about) |
40,000 |
Local Retail (GFA) (m2)(about) |
10,000 |
Other Non-Domestic Facilities (GFA) (m2)(about) |
26,540 |
Kindergarten (GFA) (m2)(about) |
2,200 |
Community Hall (GFA) (m2)(about) |
1,260 |
Social Welfare Facilities (Exempted from GFA) (m2) (about) |
18,100 |
Reserved Area of Provision of Social Welfare Facilities (Exempted from GFA) (m2) (about) |
7,900
|
Public Car Park (Nos. of Parking Space) (Exempted from GFA) |
300 |
Public Transport Interchange (Exempted from GFA) |
1 |
Earliest Target Completion |
2029 |
School Site |
|
Site area (m2) (about) |
8,500 |
2.9.1 With due consideration to preserving the diverse habitats found within Sub-Area 2 to Sub-Area 4, land uses such as Other Specific Uses have been considered. Recreational and ancillary facilities with minimal new structure/change to existing site conditions to support the recreation activity will primarily be provided in Sub-Area 2 . Landscaping works including but not limited to planting and transplanting works that are compatible with existing habitats are also anticipated within the Sub-Areas 2 to 3. For Sub-Area 4, no works is anticipated in order to preserve its ecology. Subject to further investigation, the actual land use will be further confirmed and a proper management plan with management approach including establishment of conservation area will also be formulated to preserve the existing valuable habits.
2.9.2 Uses in Column 1 and Column 2 of “Other Specified Uses” annotated “Recreation cum Conservation” are listed as follows:
Column 1 (Uses always permitted)
Field Study/Education/Visitor Centre
Golf Course
Nature Reserve
Nature Trail
Park and Garden
Picnic Area
Playground/Playing Field
Column 2 (Uses that may be permitted with or without conditions on application to the Town Planning Board)
Eating Place
Government Use
Holiday Camp
Place of Entertainment
Place of Recreation, Sports or Culture
Public Utility Installation
Public Vehicle Park (excluding container vehicle)
Shop and Services
(1) Site formation works;
(2) Building works (i.e. foundation works and superstructure);
(3) Slope works and other geotechnical works;
(4) Roadworks;
(5) Waterworks;
(6) Sewerage works;
(7) Drainage works;
(8) Landscaping works;
(9) Public Transport Interchange (PTI); and
(10) Other infrastructure works including laying of utilities, etc.
Table 2.4 Comparison of Benefits and Disbenefits between Different Construction Methods for Retaining Structures in the Housing Site
|
L-shaped Retaining Wall |
Piled Retaining Wall |
Cut Slope |
Landscape Impact |
Higher Substantial temporary works is required during construction and only minor landscape mitigation measures (i.e. vertical greening) could be adopted
|
Less Minimal temporary works is required during construction and only minor landscape mitigation measures (i.e. vertical greening) could be adopted
|
Less Substantial temporary works is required during construction but major landscape mitigation measures such as hydro-seeding can be adopted to improve the landscape and visual |
Construction Duration |
Longer Substantial excavation and substantial temporary works are required. Long construction period is anticipated. |
Shorter Without the substantial excavation works and minor temporary works, shorter construction period is anticipated. |
Medium Without substantial excavation works and with substantial temporary works, the construction duration is anticipated to be between L-shape retaining wall and pile retaining wall. |
Construction Noise |
Less General excavation would induce minimal construction noise |
Higher Piling would induce intensive construction noise |
Less General excavation would induce minimal construction noise |
Pros |
Cons |
· Large structural capacity · Generate relatively less noise and vibration during pile installation · Relatively easy to overcome underground obstructions · Higher flexibility in designing longer piles to suit design requirements |
· Risk of loosening of surrounding soil, causing ground movement and structural impacts on the adjacent structures; and · Larger working space is required |
Pros |
Cons |
· Pile installation method is relatively simple and degree of redundancy can be easily incorporated to provide flexibility to deal with any unexpected ground condition; and · Pile type can be designed to withstand high bending and tensile stresses. |
· Generate relatively high noise and vibration, which may be sensitive to nearby sensitive receivers; and · Longer construction period is anticipated; · Highly affected by unforeseeable ground condition |
Stage |
Works Components |
Time Line |
Stage 1 |
Public Housing Development in Sub-Area 1 · Site clearance and site formation works · Construction of internal Road · Pipe works and utilities works · Construction and building works of public housing site · Construction of public transport interchange (PTI) and bus terminus |
2024 - 2029 |
Stage 2 |
School Site Development in Sub-Area 1 · Site clearance and site formation works · Construction of internal Road · Pipe works and utilities works · Construction of special school |
2024 - 2028 |
Stage 3 |
Associated Road Works outside PDA · Junction improvement works at Po Kin Road / Ping Kong Road · Minor road improvement works at Ping Kong Road |
2024 - 2029 |
Stage 4 |
Associated Infrastructure Works outside PDA · Pipe works and utilities works |
2024 - 2029 |
Stage 5 |
Recreational cum Conservation Area in Sub-Areas 2 to 4 |
To be further reviewed |