13. SUMMARY OF ENVIRONMENTAL OUTCOMES
13.2 Environmental Benefits of the
Project
13.3 Environmental-Friendly Design
Recommended
13.4 Environmentally Sensitive Areas
Protected
13.5 Key Environmental Problems
Avoided and Compensation Areas Included
13.6 Environmental Benefits of
Environmental Protection Measures Recommended
Tables |
|
Table 13.1 |
Summary of Key Environmental Problems Avoided and Sensitive Areas Protected |
Table 13.2 |
Key Recommended Mitigation Measures and
Associated Environmental Benefits |
Avoidance / Minimization of
Construction Disturbance on Ping Che Egretry
·
Avoidance of encroachment into recognized sites of
conservation importance;
·
Avoidance of loss of trees and retaining trees as many
as practicable
·
Minimisation of disturbance of ecological habitats
·
Minimisation of the number of environmental sensitive
receivers to be affected
Table 13. 1 Summary of Key Environmental Problems Avoided and Sensitive Areas
Protected
Design Approach |
Environmental
Problems Avoided and Sensitive Areas Protected |
Avoid excavation works in the existing watercourses
during March to August |
·
Adverse impacts on water quality would be avoided |
Avoid noisy construction works during ardeids
breeding season of Egretry |
·
Adverse impacts on ecology would be avoided |
Adopt environmentally friendly construction
methods, e.g. offsite precast structures / modular integrated construction |
·
Adverse impacts on air quality, noise, water
quality, waste and ecology would be avoided |
Implementation of environmental monitoring
and auditing system during construction phase |
·
Ensure that all the recommended mitigation measures
are properly implemented |
Table 13. 2 Key Recommended Mitigation Measures and Associated Environmental
Benefits
EIA
Aspects |
Key Recommended Mitigation Measures |
Associated Environmental Benefits |
Air Quality |
Construction
Phase ·
Regular
maintenance of construction equipment deployed on-site should be conducted to
prevent black smoke emission. ·
Connect
construction plant and equipment to mains electricity supply and avoid use of
diesel generators and diesel-powered equipment as far as practicable to
minimize the emission impact from these machineries on nearby residents. ·
Proper storage, handling, transporting
and timely disposal of odorous excavated materials. ·
Maintain site cleanliness and tidiness
of construction site and control on NRMMs. Operation
Phase · No
mitigation measures would be required. |
· Protect
air sensitive receivers by reducing construction dust emission and odour nuisance |
Noise |
Construction
Phase ·
Good
site practices; ·
Use
of quiet PME; ·
Adoption
of temporary noise barrier or noise enclosure; ·
Scheduling
of PME / construction activities. Operation
Phase · No
mitigation measures would be required. |
· Protect
noise sensitive receivers by reducing construction and operational noise
impacts |
Water Quality |
Construction
Phase · Adopt
good site practices. · Implementing
proper site management measures to control site runoff and drainage following
the guidelines provided in ProPECC PN 1/94. · Use
of containment structures and diversion channels to facilitate a dry or at
least confined excavation within the watercourses. · Proper
treatment of wastewater before discharge in accordance with WPCO. · Proper
storage, handling and disposal of chemicals. · Response
procedures for accidental spillage or leakage of chemicals · Water
quality monitoring during construction. Operation
Phase · Maintenance
for removal of excessive silt, vegetation, debris and obstruction. |
· Protect
the downstream water sensitive receivers |
Waste Management |
Construction
Phase · Avoidance,
minimization, recycling, treatment and safe disposal of waste. · Good
waste management and control practices to avoid generation of excessive
amount of waste. · C&D
materials should be excavated, transported and disposed of in a manner to
minimize adverse environmental impacts. · Proper
storage, handling and disposal of chemical waste. · Proper
storage, recycling and disposal of general refuse. Operation
Phase · The
screenings, silt materials and debris collected during operation and
maintenance should be properly packed and transported to the designated
landfill for disposal as soon as possible. · All chemical waste should be properly stored,
labelled and removed by licensed waste collectors in accordance with Waste
Disposal (Chemical Waste) (General) Regulation. |
· Minimize
waste generation · Ensure
proper handling and disposal of C&D material · Ensure
proper handling of general refuse & chemical waste |
Land Contamination |
Construction
Phase · A
review of Contamination Assessment Plan (CAP) should be conducted to confirm
whether the proposed site investigation (SI) works are still valid and
provide fine adjustments of the sampling locations and number of boreholes
for Areas A, B1 and B2 prior to commencement of site investigation (SI)
works. Supplementary CAP(s) for the Project Area, to document the
re-appraisal, review the proposed sampling location(s) and outline the
proposed sampling arrangement as well as testing parameters, should be
submitted to EPD for review and agreement. · SI
works should be carried out according to the supplementary CAP(s) endorsed by
EPD. Contamination Assessment Report
(CAR) should be prepared to present the findings of the SI works. · If
contamination is confirmed, the CAR will be accompanied by a Remediation
Action Plan (RAP) to provide details of the remedial actions for the
identified contamination. The CAR and
RAP will be submitted to EPD for agreement. · Remediation
Report (RR) will be prepared and submitted to EPD for endorsement prior to commencement
of any proposed construction works upon completion of remediation works, if
necessary. Operation
Phase No mitigation
measures would be required. |
· Ensure
proper handling contaminated soil |
Ecology |
Construction
Phase · Avoid
impact to recognized sites of conservation importance. · Consideration
of alternative construction method to minimize ecological impact. · Careful
phasing of construction activities. · Adopt
mitigation measures for air, noise and water impacts. · Carry
out update vegetation and aquatic surveys. · Translocation
and transplantation of species of conservation importance prior to
commencement of construction works. · Provision
of animal corridors. Operation
Phase · No
mitigation measures would be required. |
· Avoid
impact to recognized sites of conservation importance · Minimize
ecological impact · Mitigate
ecological impact · Ecological
enhancement opportunity |
Fisheries |
Construction
Phase · Implement
water quality mitigation measures. Operation
Phase · No
mitigation measures would be required. |
· Protect
fisheries resources |
Cultural Heritage |
Construction
Phase · Implement
mitigation measures such as pre-construction baseline condition survey and
baseline vibration monitoring and evaluate on the necessary construction
monitoring and structural strengthening measures for AMO's consideration and
provision of proper access and space. Operation
Phase · No
mitigation measures would be required. |
· Protect
close proximity graded historic buildings, new items
for Grading Assessment and built heritage items during construction |
Landscape and Visual |
Construction
Phase · Minimise disturbance by implementing good site
practices. · Erection
of decorative construction hoarding. · Control
of night time lighting. · Tree
preservation, tree transplantation and compensatory tree planting. · Buffer
planting. · Enhance
river meander Operation
Phase · Enhanced
design to river sides / bed, streetscape, river crossing. · Use
of natural bedding substrate. · Use
of gabion mattress
at river bed. · Adopt
lighter colours for the structures to reduce the
visibility · Street
lightings to minimize light spill and glare. · Implementation
of plantation scheme. |
· Enhance
the landscape quality and visual appearance of the project |