2. PROJECT DESCRIPTION AND PROJECT CONSIDERATION
2.2 Site
History and Project Location
2.8 Relevant
Technical Circulars / Guidelines
2.9 Essential
Design Considerations / Principles Adopted.
2.11 Alternative
Location of Stormwater Drains and Discharge Points.
2.12 Alternative
Design Options for Watercourse TKL04 and TKL05.
2.13 Evaluation
of Design Options
2.14 Recommended
Drainage Options
2.15 Alternative
Channel Bed Lining / Embankment Lining Options.
2.16 Alternative
Dry Weather Flow Channel
2.22 Consideration
of Alternative Construction Methods
2.23 Consideration
of Alternative Construction Sequence
2.24 Scope
of Works during Operational Phase
2.27 Cumulative Environmental Impact
2.28 Sustainability
Considerations
2.29 Continuous
Public Involvement (CPI)
Figures |
|
Alternative Project Alignment Options |
|
Design Option 1 – Conforming Design (General Layout Plan) |
|
Design Option 1 – Conforming Design (Typical Sections) |
|
General Layout Plan for Proposed Channel at Ta Kwu Ling |
|
Typical Sectional View of Proposed Drainage Channel TKL04 |
|
Typical Sectional View of Proposed Drainage Channel TKL05 (Sheet 1 of 2) |
|
Typical Sectional View of Proposed Drainage Channel TKL05 (Sheet 2 of 2) |
|
River Park Phase 1 Sections (Miscellaneous Details) |
|
Design Option 3 – Bypass Box Culvert Scheme (General Layout Plan) |
|
Design Option 3 – Bypass Box Culvert Scheme (Typical Sections and Details) |
|
Design Option 4 – Drainage Tunnel with Pumping Station (General Layout Plan) |
|
Design Option 4 – Drainage Tunnel with Pumping Station (Typical Sections) |
|
Design Option 4 – Drainage Tunnel with Pumping Station (Typical Sections of Pumping Section and Bypass System) |
|
Design Option 5 – Widening and Deepening Scheme (General Layout Plan) |
|
Design Option 5 – Deepening Scheme with Pump Station (Widening Scheme) |
|
Schematic Diagram of Alternative Drainage Options |
|
Photos of Lining Options (1/2) |
|
Photos of Lining Options (2/2) |
|
Working Sections in Project Site |
|
Location Plan |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (1 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (2 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (3 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (4 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (5 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (6 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (7 of 8) |
|
Proposed Drainage Improvement Works at Ta Kwu Ling (8 of 8) |
|
Existing River General Layout Plan – TKL04 |
|
Existing River General Layout Plan – TKL04 (Portion A) |
|
Existing River General Layout Plan – TKL04 (Portion B) |
|
Existing River General Layout Plan – TKL04 (Portion C) |
|
Existing River Cross Section – TKL04 (Sheet 1 of 2) |
|
Existing River Cross Section – TKL04 (Sheet 2 of 2) |
|
Existing River General Layout Plan – TKL05 |
|
Existing River General Layout Plan – TKL05 (Portion A) |
|
Existing River General Layout Plan – TKL05 (Portion B) |
|
Existing River General Layout Plan – TKL05 (Portion C) |
|
Existing River General Layout Plan – TKL05 (Portion D) |
|
Existing River General Layout Plan – TKL05 (Portion E) |
|
Existing River Cross Section – TKL05 (Sheet 1 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 2 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 3 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 4 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 5 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 6 of 7) |
|
Existing River Cross Section – TKL05 (Sheet 7 of 7) |
|
Typical Water Diversion Scheme for Construction of Channel TKL05 (1/3) |
|
Typical Water Diversion Scheme for Construction of Channel TKL05 (2/3) |
|
Typical Water Diversion Scheme for Construction of Channel TKL05 (3/3) |
|
Project Interfacing Plan |
Alignment;
Location of stormwater drains and discharge points;
Design Options;
Channel bed and embankment lining;
Dry season weather flow; and
Construction methods and sequence.
ETWB Technical Circular
(Works) No. 5/2005 – Protection of Natural Streams / Rivers from Adverse
Impacts Arising from Construction Works
DSD Technical Circular No.
2/2004 – Protection of
DSD Practice Note No. 3/2021
- Guidelines on Design for Revitalisation of River
Channel
Adequate flow capacity – the size of the river channels
should have adequate capacities to convey design flood flows within bank to
achieve the design flood protection standard.
Public safety – bank stabilisation
work is required for unstable banks and where houses and structures are located
very close to the existing riverbanks.
Existing conditions of the riverbanks – some sections of the
existing river banks loose surfaces and are prone to erosion and scouring.
Land constraints – physical features such as road carriageway
at one side of the existing river control the widening of the channel at that
side.
Accessibility for maintenance – provision of adequate access
for future long-term maintenance of the completed channels is necessary.
Disturbance to the public – resumption of private domestic
houses / any commercial use lands / factories needs to be minimize as much as
possible.
Blue Green Infrastructure design – it is a form of
development aiming at improvement of the sustainability and resilience of Hong
Kong’s drainage system to meet the contemporary public aspirations in respect
of the natural environment and protection of the local culture and rural
lifestyle.
Option 2 – Widening and Deepening Scheme
Option 3 – Bypass Box Culvert Scheme
Option
4 – Drainage Tunnel with Pumping Station Scheme
Option 5 – Deepening Scheme with Pumping Station
Table 2.1 Alternative Design Options
Considered for the Proposed Watercourses
Approach* |
Option* |
DSD Practice Note No. 1/2015* |
ETWB TCW No. 5/2005** |
|
Avoidance |
1 |
Two-stage (or multi-stage)
channels |
N/A |
|
Minimization |
2 |
Enlargement of channel by widening
and deepening |
iii) enlargement of channel by modifying one bank only; (iv) enlargement of channel by modifying/ widening both banks; (v)
enlargement of channel by deepening; |
|
Avoidance |
3 |
Relief or by-pass channels |
N/A |
|
Avoidance (Modify from Option 3) |
4 |
Relief or by-pass channels (or
by-pass tunnel) with pumping system |
N/A |
|
Minimization (Modify from Option
2) |
5 |
Enlargement of channel by widening
and deepening with pumping system |
iii) enlargement of channel by modifying one bank only; (iv) enlargement of channel by modifying/ widening both banks; (v)
enlargement of channel by deepening; |
|
Notes: |
||||
* |
Options as
promulgated/modified in DSD Practice Note No. 1/2015 – Guidelines on
Environmental Considerations for River Channel Design |
|||
** |
Options as promulgated/modified
in ETWB TCW No. 5/2005 – Protection of natural streams / rivers from adverse
impacts arising from construction works - Appendix C (A) |
|||
Table 2.2 Evaluation of the Proposed Options
|
Option 1 – Conforming Design |
Option 2 – Widening and Deepening Scheme |
Option 3 – Bypass Box Culvert Scheme |
Option 4- Drainage Tunnel with Pump Station Scheme |
Option 5- Widening and Deepening Scheme with Pump
Station |
Land Matters |
· Affected land
lots area about 55,000m² |
· Affected land
lots area about 26,000 m² |
· Affected land
lots area about 33,000m² |
· Affected land
lots area about 43,000 m² |
· Affected land
lots area about 17,000 m² |
Operation and Maintenance
Concerns |
· Routine
maintenance of the proposed watercourses and detention ponds is
required. · Frequency of maintenance
are anticipated to be low. |
· Routine
maintenance of the proposed watercourses and detention ponds is
required. · Frequency of
maintenance are anticipated to be low. |
· Routine
maintenance for by-pass box culvert, proposed watercourses and detention ponds
is required. · Frequency of
maintenance are anticipated to be medium. |
· Routine
maintenance of the existing watercourses. · Routine
maintenance of tunnel system and bypass facilities. · Routine
operation and maintenance of the pump station and the associated equipment. · Maintain stable
power supply · Frequency of
maintenance are anticipated to be high. |
· Routine
maintenance of the proposed watercourses and detention ponds is
required. · Routine
operation and maintenance of the pump station and the associated equipment. · Maintain stable
power supply · Frequency of
maintenance are anticipated to be high. |
Public Concerns |
· Land resumption
extent · Nuisance during
construction · Watercourses
become wider and deeper |
· Land resumption
extent · Nuisance during construction · Watercourses
become wider and deeper |
· Land resumption
extent · Nuisance during
construction · Existing
watercourses generally maintained |
· Land resumption
extent · Nuisance during
construction · Existing
watercourses generally maintained · Nuisance from pump
station |
· Land resumption
extent · Nuisance during
construction · Watercourses
become wider and deeper · Nuisance from
pump station |
Major Environmental Considerations |
|||||
Air |
·
No additional emission of
dust and odour |
·
No additional emission of
dust and odour |
· No additional emission of dust and odour |
·
May slightly emit dust and
odour during plant operation |
·
May slightly emit dust and
odour during plant operation |
Noise |
·
No additional noise source
created |
·
No additional noise source
created |
· No additional noise source created |
·
Additional noise source
from PME in plant |
·
Additional noise source
from PME in plant |
Water Quality |
·
No generation of new
pollution loads |
·
No generation of new
pollution loads |
·
No generation of new
pollution loads |
·
May generate new pollution
loads due to accidentally leakage of chemicals from plant |
·
May generate new pollution
loads due to accidentally leakage of chemicals from plant |
Waste |
·
silt material and debris
in maintenance ·
Generate C&D materials
from excavation of widening the watercourse |
·
silt material and debris
in maintenance ·
Generate C&D materials
mainly from excavation of widening and deepening the watercourse |
· silt material and debris in maintenance · Generate C&D materials mainly from excavation of construction of
underground box culvert |
·
silt material and debris
in maintenance ·
Small amount of screenings
and chemical waste in maintenance ·
Generate C&D materials
mainly from tunneling and construction of foundation for pump station |
·
silt material and debris
in maintenance ·
Small amount of screenings
and chemical waste in maintenance ·
Generate C&D materials
mainly from excavation of widening and deepening of watercourses and construction of foundation
for pump station |
Ecology |
·
Slightly change of
ecological habitat due to relatively large footprint |
·
Enhance ecological value
due to provision of woodland and wetland as well as the large planting scale |
· Maintain existing ecological habitat |
·
Slightly change of
ecological habitat due to impact from pump station ·
Tunneling works may
slightly affect the underground habitat |
·
Slightly change of
ecological habitat due to impact from pump station |
Visual and landscape |
·
Minor visual and landscape
impact due to construction of aboveground embankments |
·
No adverse visual impact ·
Relatively minor landscape
impact due to construction of embankments below existing ground level |
· No adverse visual impact · Relatively minor landscape impact due to construction of embankments
and underground box culvert |
·
Visual and landscape
impact due to construction of pump station |
·
Visual and landscape
impact due to construction of pump station |
Environmental Benefits |
·
No excavation of the
existing stream will be required, and hence permanent loss of the natural
stream bed habitat will be avoided. ·
Different flood regimes
and water tables result in the development of different types of habitat. ·
Depending on the design,
excavated rocks and soils could be reuse as channel |
·
Enhance environmental
value by proposed wetland and woodland and reformation of natural river ·
Excavation volume will be
minimized as the improvement works will be carried out along the existing
watercourse. ·
Less construction plant is
required for this option due to the lower excavation volume and hence the
potential air quality and noise impacts will be less significant. ·
The environmental
condition of the proposed drainage channel can be improved with suitable design
on lining and bedding to enhance the ecological value. ·
As the improvement works
will be carried out along existing streams, it can minimize major resumption
of land and reduce environmental impacts imposed to other areas away from the
existing stream |
·
Only small-scale changes
to the condition of existing watercourses, ease to preserve ecological
habitat ·
No excavation of the
existing stream will be required. ·
The existing stream will
be left untouched and hence the stream and riparian habitats will be preserved
with aquatic life left undisturbed. |
·
Only small-scale changes
to the condition of existing watercourses, ease to preserve ecological
habitat ·
No excavation of the
existing stream will be required. ·
The existing stream will
be left untouched and hence the stream and riparian habitats will be
preserved with aquatic life left undisturbed. |
·
The least excavation
materials will be generated ·
Excavation volume can
further be minimized by comparing to Option 2 where the hydraulic needs is
replaced by a pump station. ·
Generally similar to
Option 2 |
Environmental Disbenefits |
·
There may be potential
loss of stream banks and riparian habitats depending on design adopted. |
·
Construction nuisances
including dust and noise will affect all sensitive receivers along entire
works alignment. ·
Impacts on the existing
stream are unavoidable. The hydrology
of the whole river changed |
·
Construction nuisances
including dust and noise will affect all sensitive receivers along entire
works alignment ·
Construction of by-pass
channels on existing land will involve larger excavation volume. |
·
Longer period of
environmental disturbance ·
Operation nuisances from
pump station including waste and noise will affect all sensitive receivers ·
Construction of by-pass
channels on existing land will involve larger excavation volume. |
·
Operation nuisances from
pump station including waste and noise will affect all sensitive receivers ·
Generally similar to
Option 2 |
Construction Method |
· Excavation by
open cut method |
· Excavation by
open cut method |
· Excavation by
open cut method |
· Tunneling works · Piling works for
pumping station · Civil,
structural and E&M works for pumping station · Excavation by
open cut method |
· Piling works for
pumping station · Civil,
structural and E&M works for pumping station · Excavation by
open cut method |
Construction Sequence |
· Flow diversion · Excavation in
dry season · Backfill and
landscaping works |
· Flow diversion · Excavation in dry
season · Backfill and
landscaping works |
· Excavation for
construction of box culvert · Installation of
water collection system at dry season · Connection to
existing watercourses at dry season |
· Excavation for
launching and receiving pit · Tunneling works · Installation of
water collection system at dry season · Connection to
existing watercourses at dry season · Foundation works
of pumping station · Construction of
plant and connection to tunnel |
· Flow diversion · Excavation in
dry season · Backfill and
landscaping works · Foundation works
of pumping station · Construction of
plant and connection to the watercourse TKL05 |
Programme |
· About 54 months
for construction works |
· About 54 months
for construction works |
· About 54 months
for construction of box culvert works |
· About 60 months
for the pumping station, drainage tunnel system |
· About 54 months
for the pumping station, river improvement works |
Costs |
Medium: · Large scale of
exaction works for widening river and construction of flood wall |
Low: · Exaction works
for widening and deepening of river |
Medium: · Construct
underground box culvert and associated piping system |
High: · Construct
pumping station, drainage tunnel system |
Medium: · Construct
pumping station, small scale of excavation for widening and deepening of
river |
Sustainability |
· Construction of
detention pond with area about
63,400m² |
· Construction of
detention pond with area about 10,000
m² |
· Construction of
detention pond with area about 20,500
m² |
· Installation of
additional pump sets |
· Installation of
additional pump sets |
Reliability |
· High – the
capacity of the existing watercourses is improved by hydraulic means (i.e. by
widening and deepening) |
· High – the
capacity of the existing watercourses is improved by hydraulic means (i.e. by
widening and deepening) |
· High – the
capacity of the existing watercourses is improved by hydraulic means (i.e. by
widening and deepening) |
· Low – the
capacity of the existing watercourses is improved by pumping |
· Medium – the
capacity of the existing watercourses is improved by semi-hydraulic means
(i.e. by widening and deepening with pumping) |
Recommendation |
· Not recommended,
as a large amount of private lots are required to be resumed. · More than 30% of
existing watercourse has been channelised and is
thus not suitable to adopt this option. |
· Recommended, as
widening and deepening can substantially increase the flow capacity. · Meanders can be
recreated |
· Not recommended,
as a large amount of private lots are required to be resumed · Large area to be
resumed for drainage channel will limit the potential for future development
of the area into other uses. |
· Not recommended,
as construction of pump station may bring up long term and costly
environmental impact |
· Not recommended,
although the land resumption of private land lot reduced, construction of
pump station may bring up long term and costly environmental impact |
Table 2.3 Summary of the Evaluation of
Alternative Channel Bed / Embankment Lining Options
Option |
Environmental Benefits |
Environmental Dis-benefits |
Other Considerations / Recommendation |
Natural /unlined |
· Disturbance to
natural stream habitats can be minimized or avoided. · Better for
retaining sediments and establishment of vegetation on banks. · Very minimum
impact during construction. · Visually
acceptable. |
· Prone to
scouring during flood flows. · Erosion of banks |
· Not favorable to
hydraulic performance and high roughness. · Suitable only at
where the flow velocity is low · Recommend
adopting for riverbed design to reduce the disturbance to natural stream
habitats. |
Rip-rap lining |
· Provides
surfaces/ habitats with greater complexity for aquatic communities. · Minimum impact
during construction. · Better for
retaining sediments and establishment of vegetation on banks. · Visually
acceptable |
· Prone to little
scouring during flood flows. |
· Not favorable to
hydraulic performance and high roughness. · Recommend
adopting for riverbed design subject to the flow velocity, suitable for dry
weather flow |
Gabion / mattress lining |
· Provides
surfaces /habitats with greater complexity for aquatic communities. · Better for
retaining sediments and establishment of vegetation on banks. · Visually
acceptable |
· Prone to damage
if poorly designed. |
· Better hydraulic
performance · High maintenance
efforts and costs in replacement · Susceptible to
corrosion · Recommend for
formation of riverbed slope |
Rubbles / Stones embedded in concrete /
mortar |
· Slightly better
aesthetic appearance than concrete. |
· Offer
featureless habitat with low ecological value |
· Better hydraulic
performance · Little
maintenance required. · Generally
applied in watercourses’ sections |
Geotextile reinforced grass lining |
· Good aesthetic
appearance. |
· Offer habitat
with low ecological value |
· High maintenance
cost · Not recommended. |
Grassed cellular concrete paving lining |
· Slightly better appearance
than concrete. |
· Offer habitat · with low · ecological value |
· Fast conveyance
of flood flows. · Better
structural integrity. · Little
maintenance · Applied to
maintenance access only. |
Concrete lining |
· Environmental-friendly
construction material |
· Poor aesthetic
appearance. · Offer
featureless habitat with low ecological value. · Fast conveyance
of flood flows may lead to increase in suspended solid level and biochemical
oxygen demand downstream |
· Good hydraulic
performance · Fast conveyance
of flood flows · Little
maintenance · Applied to box
culvert and river crossings |
Eco-bag lining |
· Provides
surfaces for vegetation. · Better for
retaining sediments and establishment of vegetation on banks. · Visually
acceptable |
· Prone to
scouring if poorly designed. · Erosion of banks |
· Not favorable to
performance and high roughness. · Suitable only at
where the flow velocity is relatively low. · Recommend to
combine using with gabion mattress to form the riverbed slop |
Table 2.4 Configuration of Proposed
Watercourses TKL04 and TKL05
Watercourse |
Approx.
Length (m) |
Approx.
Chainage |
Structure
Form |
Lining
Type |
Base
Widths (m) |
Average
Depth (m) |
TKL04 |
230 |
1200 – 1400 |
Channel |
Combined* |
6.2 |
3 |
TKL04 |
1178 |
0 – 1200 |
Channel |
Combined* |
3 |
3.5 |
TKL05 |
119 |
1800 – 2100 |
Retaining Wall |
Combined* |
17.5 |
3.5 |
TKL05 |
700 |
1100 – 1800 |
Retaining Wall |
Combined* |
10.5 |
3.5 |
TKL05 |
1100 |
0 – 1100 |
Retaining Wall |
Combined* |
6.5 |
3.5 |
Notes: * the slope of watercourse lined with concrete in form of
channel/retaining wall and the riverbed lined with gabion with eco-bag as well
as rip-rap with natural substrate.
(i)
the
improvement of two sections of Ping Yuen River, namely TKL04 (about 1.4km long)
and TKL05 (about 2.1km long), in Ta Kwu Ling;
(ii)
the
drainage improvement works at Ping Yeung Village, Ta Kwu
Ling (about 1050m long in total); and
(iii) the construction of road drainage system at
part of Ping Che Road, Ta Kwu Ling (about 1150m long in total).
Watercourse
TKL04 and TKL05
Table 2.6 Configuration of Existing and Proposed Watercourse TKL04 and TKL05
Approx.
Length (m) |
Approx. Chainage |
Existing
Lining Type |
Proposed
Lining Type |
Existing
Average Width (m) |
Proposed
Average Width (m) |
Existing
Average Depth (m) |
Proposed
Average Depth (m) |
TKL04 |
|||||||
300 |
0-300 |
Natural |
Natural Bedding Material* |
7.0 |
5.0 |
1.6 |
3 |
700 |
300-1000 |
Natural |
Natural Bedding Material* |
4.7 |
5.0 |
0.9 |
3 |
200 |
1000-1200 |
Concrete |
Natural Bedding Material* |
1.6 |
5.0 |
1.5 |
3 |
200 |
1200 – 1400 |
Concrete |
Natural Bedding Material* |
6.2 |
9.0 |
1.7 |
3.5 |
TKL05 |
|||||||
300 |
0-300 |
Natural |
Natural Bedding Material* |
7.3 |
10.0 |
1.6 |
3 |
600 |
300-900 |
Natural |
Natural Bedding Material* |
11.0 |
10.0 |
1.7 |
3 |
500 |
900-1400 |
Natural |
Natural Bedding Material* |
10.7 |
14.0 |
1.9 |
3.5 |
400 |
1400-1800 |
Natural & Concrete |
Natural Bedding Material* |
7.9 |
14.0 |
1.89 |
3.5 |
300 |
1800-2100 |
Natural |
Natural Bedding Material* |
14.3 |
21.0 |
1.6 |
3.5 |
Notes: * the slope of watercourse
lined with concrete in form of channel/retaining wall and the riverbed lined with gabion with eco-bag as well as rip-rap with natural substrate.
Proposed
Gabion Mattress for Riverbed
Proposed
Natural Substrate for Riverbed
Channels and Drains at Ping Yeung Village and Ping Che Road
Table 2.7 Summary of the proposed drainage pipes and u-channels at Ping
Che Road and Ping Yeung Village
Ping Yeung Village |
||
U-Channel/ Drainage Pipe |
Size (mm) |
Gradient |
U-channel |
1050 |
200 |
U-channel |
2x1200 |
150 |
U-channel |
1050 |
150 |
U-channel |
1200 |
200 |
Drainage Pipe |
1200 |
250 |
U-channel |
825 |
150 |
Ping Che Road |
||
U-Channel/ Drainage Pipe |
Size (mm) |
Gradient |
U-channel |
750 |
150 |
U-channel |
1050 |
150 |
U-channel |
900 |
150 |
Drainage Pipe |
1200 |
150 |
Table
2.8 Summary of the proposed gullies in Ping Che Road
Ping Che Road |
|
Type of gully |
Standard double triangular grating
(type GA1 - 450) |
Design gully spacing |
7 m |
Maintenance
Access Road
Crossings
General
Descriptions
·
Temporary
River Diversion;
·
Excavation
Works;
·
Construction
of Embankment;
·
Construction
of Channel Lining;
·
Construction
of Maintenance Access;
·
Re-provision
of Existing Pedestrian and Vehicular Accesses/Crossings;
·
Landscaping
Works; and
·
Construction
of Site Access.
Temporary
River Diversion
Excavation
Works
Embankment
Construction
Construction
of Channel Lining
Construction
of Maintenance Access Ramps
Re-provision
of Existing Pedestrian and Vehicular Accesses/Crossings
Landscaping
Works
Site
Access
Channels
Crossings
/ Bridges
Drainage
Pipe
Table 2.5 Environmental Benefits and Dis-Benefits of
Alternative Construction Methods
Options |
Environmental Benefits |
Environmental Dis-Benefits |
Open-Cut
Method |
· Faster construction progress and hence the period of
environmental disturbance is reduced. |
· Construction nuisances including dust and noise will
affect all sensitive receivers along entire works alignment. |
Trenchless
Method |
· Excavation is only required at launching and
receiving pit locations. Hence localized construction nuisances are limited
to the sensitive receivers near the working pits only. · Comparatively less excavated materials will be
generated. |
· Longer period of environmental disturbance due to
slow construction progress. |
Table 2.9 Tentative Key Milestone Dates
Date (season/year) |
|
Completion of Design Phase |
Q4/ 2022 |
Commencement of Tender Phase |
Q3/ 2023 |
Commencement of Works Contract |
Q1/ 2024 |
Substantial Completion of Works Contract |
Q3/ 2028 |
Table 2.10 Summary of Concurrent Project
Government Department /
Enterprise |
Project Name |
Construction Programme |
Water Supplies Department (WSD) |
Implementation of Water
Intelligent Network (WIN), Remaining District Metering Areas and Pressure
Management Areas in Yuen Long and Sheung Shui & Fanling
Major Supply Zones – Investigation, Design and Construction |
October 2020 to Q2/2024. |
Highway Department (HyD) |
Widening of the Western Section
and Eastern Section of Lin Ma Hang Road (Ping Yuen River to Ping Che Road /
Tsung Yuen Ha to Lin Ma Hang) |
February 2020 to Q4/2023 |
Planning Department (PlanD) and Civil Engineering and Development Department
(CEDD) |
Preliminary Feasibility Study
on Developing the New Territories North (NTN) |
NA |
Drainage Services Department
(DSD) |
Upgrading of existing sewage
and leachate pumping stations and the associated trunk sewerage at North East
New Territories (NENT) |
Q4/2021 to Q2/2027 |
Drainage Services Department
(DSD) |
4165CD - Drainage Improvement
Works at North District |
2021 to 2027 |
Implementation
of Water Intelligent Network (WIN), Remaining District Metering Areas and
Pressure Management Areas in Yuen Long and Sheung Shui & Fanling Major Supply Zones – Investigation, Design and
Construction – WSD
Widening
of the Western Section and Eastern Section of Lin Ma Hang Road (Ping Yuen River
to Ping Che Road / Tsung Yuen Ha to Lin Ma Hang) – HyD
Preliminary
Feasibility Study on Developing the New Territories North (NTN)– PlanD & CEDD
Upgrading
of existing sewage and leachate pumping stations and the associated trunk
sewerage at North East New Territories (NENT)
Drainage
improvement works at North District
Table 2.11 Summary
of Continuous Public Involvement
Date/Period |
Activities |
Concerned Parties |
5 October 2018 |
Liaison Meeting |
Green Groups |
2 October 2019 to
14 October 2019 |
Preliminary
Dialogues |
Local Farmers,
Schools & Local Associations, Agricultural Expert & Historians |
24 October 2020
to 9 May 2020 |
In-depth
Interviews |
Residents, Local
Farmers, Community Activists, Schools & Local Associations, Green Groups,
North District Council Members, Agricultural Expert & Historians,
Engineering Professionals |
19 December 2019
to 29 May 2020 |
Field Visits |
Resident,
Community Activists, Green Groups, Engineering Professionals |
21 January 2020
to 30 June 2020 |
Focus Group
Meeting |
Residents, Local
Farmers, Community Activists, Schools & Local Associations, Green Groups |
10 December 2019
to 16 June 2020 |
Community
Briefings |
Residents,
Community Activists, |
19 March 2020 |
Rural Committee
Meeting |
Rural Committee
Members |
Table 2.12 Summary of Public
Concerns and Analysis
Major Comment/Concern |
Design Consideration |
Alleviate flooding issue/ Effectiveness of
flood prevention |
According to
the flood protection standard formulated by the Government, the design
standard of this project is classified as village drainage for 1 in 10 years
return period. The size of drainage channels is designed mainly based on the
above criteria. |
Impact on water source for irrigation/
sustainable water supply for farming activities |
Water-well will be re-provided at identified locations and the proposed wetland can also support the local farming activities apart from environmental value. |
Disturbance/ change of residence rural
lifestyle |
The proposed
alignment of the drainage improvement works will follow the existing
watercourses as far as practicable in order to reduce disturbance of surrounding.
|
Integration between the watercourses and
surrounding environment/ preservation of natural environment |
Formation of
natural riverbed and enhancement of greening cover at river slope and river
blank by a planning scheme will be introduced. Also, Woodland and wetland are
proposed to keep the existing environmental connection. |
Maintaining water quality |
Regular
inspection and maintenance of the watercourses will be carried out. If there
is any illegal discharge observed, cases will be reported and transferred to
relevant law enforcement parties. |
Promotion of cultural heritage in Ta Kwu Ling |
Selective
information of cultural heritage will be displayed in form of signage,
showcase and display board etc. to promote local characteristic. |
Avoid introduction of exotic and/or invasive
species |
The planting
scheme will include this consideration in the detail design stage. |
Management of abandoned meander (including
ecological and hydrological functions etc.) |
Under the current design scheme, all the abandoned meander will be filled up or recharged by water to become part of the proposed open space and wetland. |
Suggest using natural bottom lining,
provision of shallow ponds and aquatic planting bays at the base of the
channels to compensate or enhance riparian ecology. |
A planting
scheme will be implemented in the proposed river channel design to enhance
the riparian ecology. The scheme will cover the riverbank, river slope and
riverbed. Details of the scheme will be developed in detail design. |
END OF TEXT