4.2 Relevant Legislation and Guidelines
4.3 Description of the Noise Environment
4.5 Identification for Potential Impacts
4.11 Monitoring and Audit Requirements
Noise Sensitive Receivers |
|
|
|
Tables |
|
Table 4.1 |
EIAO-TM Day-time Construction Noise Standards (Leq, 30 min dB(A)) |
Table 4.2 |
Area Sensitivity Ratings |
Table 4.3 |
Basic Noise Levels for General Construction Works (BNL, Leq, 5 min dB(A)) |
Table 4.4 |
Summary of Options for Watercourse TKL04 and TKL05 |
Table 4.5 |
Comparisons of the Proposed Options |
Table 4.6 |
Representative Noise Sensitive Receivers (NSRs) |
Table 4.7 |
Tentative Construction Activities Schedule |
Table 4.8 |
Predicted Construction Noise Levels (Without Mitigation) |
Table 4.9 |
Sound Power Level of Quiet PME |
Table 4.10 |
Summary of Screening Structures for Each PME |
Table 4.11 |
Predicted Construction Noise Levels (Mitigated Scenario) |
Preliminary Construction Programme |
|
Construction Plant Inventory (Without Mitigation) |
|
Summary of Predicted Noise Levels during Daytime Period (Without mitigation) |
|
Construction Plant Inventory (With Mitigation) |
|
Summary of Predicted Noise Levels during Daytime Period (With mitigation) |
|
Construction Noise Assessment
(With Mitigation) |
|
Photos of Existing Representative Noise
Sensitive Receivers |
|
Schematic Configuration of Noise
Barrier |
|
Letter of Confirmation from
Project Proponent |
4.1.1 This Section assesses the potential noise impacts associated with the construction of the Project in accordance with the requirements stated in Clause 3.4.11 of the EIA Study Brief (ESB-322/2019). It presents the potential construction noise impacts to the identified Noise Sensitive Receivers (NSRs) for the Project.
4.1.2 During the operation of the Project, the drainage channel does not involve any pumping system/mechanical/electrical equipment. Small-scale maintenance shall be conducted which is small-scale in nature. Therefore, the Project does not have a noise pollution source during operation and therefore noise impact arising from the Project during operation phase is not anticipated and not included in this Section.
4.2.1 The principal legislation relating to the control of construction noise is the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO, provides guidelines and noise criteria for evaluating the noise impact. The guideline referred is:
·
EIAO
Guidance Note No. GN 9/2010 - Preparation of Construction Noise Impact
Assessment.
4.2.2 The Noise Control Ordinance (NCO) (Cap. 400) also provides means to assess the construction noise impact. Various Technical Memoranda (TMs), which stipulate control approaches and criteria, have been issued under the NCO. The following TMs are applicable to the control of noise impact from construction activities:
· Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and
·
Technical Memorandum on Noise
from Construction Work in Designated Areas (DA-TM).
4.2.3 Under the EIAO, potential noise impact arising from general construction works during normal working hours (i.e. 07:00 to 19:00 hrs on any day not being a Sunday or public holiday) at 1 m from the external façade of the uses, which rely on opened windows for ventilation, is to be assessed in accordance with the noise criteria specified in the EIAO-TM. The EIAO-TM noise standards are presented in Table 4.1.
Table 4.1 EIAO-TM Day-time
Construction Noise Standards (Leq, 30
min dB(A))
Use |
Noise
Standard (dB(A)) |
Domestic Premises |
75 |
Educational
Institutions (normal periods) Educational Institutions (during examination periods) |
70 65 |
Notes: (a)
The above standards apply to uses
which reply on opened windows for ventilation. (b)
The above standards shall be
viewed as the maximum permissible noise levels assessed at 1m from the
external façade. |
4.2.4 When
assessing a Construction Noise Permit (CNP) application for the use of Powered
Mechanical Equipment (PME) during the restricted hours, the Noise Control
Authority will compare the Acceptable Noise Levels (ANLs), as promulgated in GW-TM,
and the Corrected Noise Levels (CNLs) (i.e. after accounting for factors such
as barrier effects and reflections) associated with the proposed PME
operations. The ANLs are obtained with
corrections for the duration of the CNP and multiple permit situations, if
applicable, to the Basic Noise Levels (BNLs).
The BNLs are related to the noise sensitivity of the area in question
and different Area Sensitivity Ratings (ASR) have been established to reflect
the background characteristics of different areas. The appropriate ASR for the Noise Sensitive
Receiver (NSR) is determined with reference to Table 4.2.
Table 4.2 Area Sensitivity
Ratings
Types of Area Containing NSR |
Degree to which NSR is affected by
Influencing Factor (IF) |
||
Not Affected |
Indirectly
Affected |
Directly
Affected |
|
Rural
area, including Country Parks or village type developments |
A |
B |
B |
Low density residential area consisting
of low-rise or isolated high-rise developments |
A |
B |
C |
Urban area |
B |
C |
C |
Area other than those above |
B |
B |
C |
Notes: The following definitions apply: (a)
"Country
Park" means an area that is designated as a country park pursuant to
section 14 of the Country Parks Ordinance; (b) "directly
affected" means that the NSR is at such a location that noise generated
by the IF is readily noticeable at the NSR and is a dominant feature of the
noise climate of the NSR; (c)
"indirectly
affected" means that the NSR is at such a location that noise generated
by the IF, whilst noticeable at the NSR, is not a dominant feature of the
noise climate of the NSR; (d)
"not
affected" means that the NSR is at such a location that noise generated
by the IF is not noticeable at the NSR; and (e)
"urban
area" means an area of high density, diverse development including a
mixture of such elements as industrial activities, major trade or commercial
activities and residential premises. |
4.2.5 The
relevant BNLs are shown in Table 4.3.
Table 4.3 Basic Noise Levels for
General Construction Works (BNL, Leq, 5 min dB(A))
Time period |
Area Sensitivity Rating (dB(A)) |
||
A |
B |
C |
|
All days during the evening (i.e. 19:00-23:00 hrs)
and general holidays (including Sundays) during the day and evening (i.e.
07:00-23:00 hrs) |
60 |
65 |
70 |
All days during the night-time (i.e. 23:00-07:00
hrs) |
45 |
50 |
55 |
4.2.6 The Noise Control Authority will consider a well-justified CNP application, for construction works within restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into account adjoining land uses and any previous complaints against construction activities at the site before making a decision. Nothing in this EIA Report shall bind the Noise Control Authority in making its decision. The Noise Control Authority may include any conditions in a CNP that it considers appropriate. Failure to comply with any such conditions may lead to cancellation of the CNP and prosecution action under the NCO.
4.3.1 The Project is located in a remote rural area in Ping Che, New Territories, with some villages scattered within the Study Area (i.e. within 300m from the Project Site). Site inspection was conducted to confirm its existing condition. Background noise levels are typical of a general rural environment in the vicinity of village environment and agricultural use with some small-scale industrial establishments, such as storage yards and workshops scattered in and around the villages. The major existing noise sources were identified as traffic noise from Ping Che Road and local roads. Noise from the small scale industrial establishment also contribute to the ambient noise level.
4.3.2
In
accordance with the Outline Zoning Plan (OZP) for Ping Che and Ta Kwu Ling (No.S/NE-TKL/14) and Ta Kwu Ling North (No.S/NE-TKLN/2),
the land uses of the surrounding areas were zoned as “Agriculture” (AGR),
“Green Belt” (GB), “Government/Institution/Community” (GIC), “Industrial (Group
D)” (I(D)), “Recreation” (REC), “Open Space” (O), “Open Storage” (OS) and
“Village Type Development” (V).
4.3.3
Four
improvement options were formulated and investigated to determine the optimal
scheme of improvement, taking due consideration of the design factors, such as
physical and site constraints, capital costs, programme
of works, land issues, environmental impacts, traffic impacts, geotechnical
issues, interfacing issues with other projects and pubic concerns. The general
description of the different alignment options and their key merits and
constraints are provided in Table 4.4 below.
Table
4.4 Summary of Options for Watercourses TKL04 and TKL05
Option |
Description |
Option 1 – Conforming Scheme |
Two-stage river design concept was adopted
basically for the drainage improvement works for the existing watercourses of
TKL04 and TKL05. The existing watercourse are designed remaining undisturbed
as far as practicable while the area adjacent to the stream was served as
floodplain with embankment provided at the both sides. |
Option 2 – Widening and
Deepening Scheme |
The major concept of this option is to upgrade
the hydraulic performance by widening and deepening the existing watercourses
and hence, to increase the flow capacity for catering the required rainfall
return period. |
Option 3 – Bypass Box Culvert Scheme |
The design concept of this
option is to carry the over-flow water from upstream of the watercourses of
TKL04&05 to the upstream of Ping Yuen River through the underground box
culverts adjacent to the existing watercourses. To minimize the impact to the
public and by consideration of the constructability, open cut excavation
method would be proposed for construction of box culvert and the associated
by-pass pipe. The proposed box culvert is designed for catering 50 years
Rainfall Events so that it could minimize the land disturbs or land
requirement in the future development. As the existing watercourses is
proposed to be retain, the impact to the ecology and natural view of the
existing watercourses is considered minimal. For the open space above the
proposed box culvert, it is recommended to be opened for public use (e.g.
recreation, education, O&M, environmental and walkability enhancement
purposes). |
Option 4 – Drainage Tunnel with Pumping Station Scheme |
The major concept of this
option is to provide a drainage tunnel system along TKL04 and TKL05 for
collection of excessive stormwaters from TKL04 and TKL05 and to discharge the
collected stormwater to Ping Yuen River directly by a pumping station with
estimated flow rate of 90m3/s. The existing watercourses of TKL04 and TKL05
will be maintained except the downstream section of TKL05 between Ping Yuen
River and the junction of TKL04 and TKL05. Flood walls will be constructed
along this downstream section of TKL05 to avoid backwater effect from Ping
Yuen River. |
Option 5 – Deepening Scheme with Pumping Station |
The major concept of this
option is similar to Option 2 which is to upgrade the hydraulic performance
by widening and deepening the existing watercourse and hence, to increase the
flow capacity for catering the required rainfall return period. The major
difference is the scale of widening in a section of watercourse near Lei Uk Tsuen and the reduction of widening scale is
compensated with a pump station. |
4.3.4
A comparison
of the options is summarized in Table 4.5 below.
Table 4.5 Comparison of the
Options
Options* |
Major
Noise Source before Construction |
Environmental
Benefit |
Additional
Noise Source after Construction |
Option 1 |
Traffic Noise from Ping Che
Road and local roads, Noise from small-scale industrial establishment |
Provide a more pleasant
acoustic environment through improvement of water channel and surrounding
environment, provision of open space, and associated landscaping works |
NO |
Option 2 |
NO |
||
Option 3 |
NO |
||
Option 4 |
E&M Noise from Pump
Station |
||
Option 5 |
E&M Noise from Pump
Station |
Note: *As
briefly described in Section 2 of this EIA, Option 2 is the final design
option.
4.4.1
In accordance with the requirements stated in Clause 3.4.11.2 of the EIA Study Brief, the Study Area for the
noise impact assessment covered an area of 300 m from the boundary of the
Project. Only the first layer of
representative NSRs located along the Project site boundary was included in the
assessment as the NSRs behind were located further away from the Project and/or
were screened. The area considered in
the assessment is shown in Figure 4.1.
4.4.2 The
300m assessment boundary is within the No.S/NE-TKL/14
(Ping Che and Ta Kwu Ling) and No. No.S/NE-TKLN/2 (Ta Kwu Ling
North) of the Outline Zoning Plan (OZP). The relevant OZP, Development
Permission Area Plans, Outline Development Plans, Layout Plans and other relevant
published land use plans, including plans and drawings published by the Lands
Department and any land use and development applications approved by the Town
Planning Board have been reviewed. The selected existing representative NSRs
that may potentially be affected by the construction of the Project include
Ping Yeung, Tong Fong, Lei Uk, Sing Ping Village, Tai
Po Tin, Ping Che, Caritas Fung Wong Fung Ting Home in Ping Che Road, two
temporary shelters, and the Wun Chuen
Sin Kwoon at Ping Che. No planned NSRs were
identified within the Study Area. No planned or committed NSRs have been
identified within the Study Area.
4.4.3 The
locations of the identified representative NSRs are presented in Figure
4.1. Photographs showing the representative NSRs are also presented in Appendix 4.8.
4.4.4 Descriptions of the representative NSRs are provided in Table 4.6.
Table 4.6
Representative Noise Sensitive Receivers (NSRs)
Description |
Minimum Horizontal Separation Distance away from
the Project (m) |
Type of Use |
Noise Criteria Leq
30-min, dB(A) |
|
NSR1 |
307
Ping Yeung |
5 |
Residential |
75 |
NSR2 |
17
Ping Yeung |
4 |
Residential |
75 |
NSR3 |
362
Ping Yeung |
5 |
Residential |
75 |
NSR4 |
331 Ping
Yeung |
4 |
Residential |
75 |
NSR5 |
156B
Ping Yeung |
7 |
Residential |
75 |
NSR6 |
Temporary
Shelter near TKL04 |
3 |
Residential |
75 |
NSR7 |
20
Sing Ping Village |
36 |
Residential |
75 |
NSR8 |
Caritas
Fung Wong Fung Ting Home |
6 |
Home
for the Elderly |
75 |
NSR9 |
5
Tong Fong |
67 |
Residential |
75 |
NSR10 |
55
Lei Uk |
33 |
Residential |
75 |
NSR11# |
Wun Chuen Sin Kwoon |
35 |
Temple |
75 |
NSR12 |
200
Tai Po Tin |
42 |
Residential |
75 |
NSR13 |
323
Tai Po Tin |
32 |
Residential |
75 |
NSR14 |
118
Tai Po Tin |
36 |
Residential |
75 |
NSR15 |
103
Ping Che |
87 |
Residential |
75 |
NSR16 |
Temporary
Shelter near TKL05 |
2 |
Residential |
75 |
NSR17 |
60
Tong Fong |
29 |
Residential |
75 |
NSR18 |
Village
house in Tai Po Tin |
3 |
Residential |
75 |
NSR19 |
124A
Ping Yeung |
2 |
Residential |
75 |
NSR20 |
196
Ping Che |
36 |
Residential |
75 |
NSR21 |
Village
house at Lei Uk Tsuen |
33 |
Residential |
75 |
NSR22 |
Temporary
Shelter |
9 |
Residential |
75 |
NSR23 |
Ta Kwu Ling Farm house |
8 |
Residential |
75 |
NSR24
|
House
223 Ping Che Road |
8 |
Residential |
75 |
Notes:
#Choice of temple as a noise sensitive receiver has
been referenced Table 4.7 of an approved EIA report (AEIAR-207/2017). Noise
criteria Woon Chuen Sin Kwoon is assumed similar to residential premises. (https://www.epd.gov.hk/eia/register/report/eiareport/eia_2452016/SKTSTW%20EIA_HTML/EIA%20HTML/Chapter%2004%20Noise.htm)2. Selected
NSRs are the proposed construction noise assessment points.
4.5.1
Potential
impacts to the NSRs during the construction phase of the Project will mainly
arise from the use of PME. The major
construction activities will include:
Improvement Works to Tributary Sections
TKL04/TKL05
·
Site clearance;
·
Excavation to formation level;
·
Construction of Channel Base/Lining
and Crossings; and
·
Backfilling.
Road Drainage System at Ping Che Road
·
Earth Works;
·
Trench support and ground compaction;
·
Pipe-laying works; and
·
Backfilling & Surfacing.
Drainage Improvement Works at Ping
Yeung Village
·
Earth Works;
·
Trench support and ground compaction;
·
Pipe-laying works; and
·
Backfilling & Surfacing.
4.5.2 All the works types will
be conducted in stages and implemented concurrently. Estimated durations of the
construction work are provided in Table 4.7. The proposed works will be
conducted during non-restricted hours only, i.e. between 07:00 and 19:00 hours
on any day expect Sunday and general holiday.
Table
4.7 Tentative Construction Activities Schedule
Work Stage |
Construction Activities |
Estimated Duration per
Section |
Works Type 1- Improvement
Works to Tributary Sections TKL04 |
||
Stage 1 |
Site Clearance |
42 months |
Stage 2 |
Form work of Temporary
Channel |
|
Stage 3 |
Excavation to Formation Level |
|
Stage 4 |
Construction of Channel and
Crossings |
|
Stage 5 |
Backfilling & Landscaping |
|
Works Type 2 - Improvement Works to Tributary Sections TKL05 |
||
Stage 1 |
Site Clearance |
54 months |
Stage 2 |
Form work of Temporary
Channel |
|
Stage 3 |
Excavation to Formation Level |
|
Stage 4 |
Construction of Channel and
Crossings |
|
Stage 5 |
Backfilling & Landscaping |
|
Construction of Road Drainage
System at Ping Che Road |
||
Stage 1 |
Earth Works |
24 months |
Stage 2 |
Trench support and ground
compaction |
|
Stage 3 |
Pipe-laying works |
|
Stage 4 |
Backfilling & Surfacing |
|
Drainage Improvement Works at
Ping Yeung Village |
||
Stage 1 |
Earth Works |
24 months |
Stage 2 |
Trench support and ground
compaction |
|
Stage 3 |
Pipe-laying works |
|
Stage 4 |
Backfilling & Surfacing |
4.5.3
According to the preliminary construction programme, the normal working hours of the construction
works will be between 07:00 and 19:00 hrs from Monday
to Saturday (except general holidays). Should
evening and night works between 19:00 and 07:00 hrs
or on public holidays (including Sundays) be required, the Contractor will
submit a CNP application which will be assessed by the Noise Control
Authority.
4.5.4 During the
operation phase, there will be no pumping system/station and mechanical/
electrical equipment. Only minor maintenance works such as regular clearance,
and repair of damages to the channel bed and sides are expected. Therefore, it
is anticipated that the potential noise impacts arising from these maintenance
works would be minimal.
4.6.1 The construction noise impact assessment was undertaken in accordance with the procedures outlined in the GW-TM, which is issued under the NCO, the EIAO-TM and the EIAO GN No. 9/2010. The assessment methodology is summarised as follows:
·
Identify the
representative NSRs that may be affected by the construction of the Project;
· Determine the plant teams for corresponding construction activities, based on the agreed plant inventory;
· Assign sound power levels (SWLs) to the PME proposed based on the GW-TM and list of SWLs of other commonly used PME ([a])
· Calculate the correction factors based on the distance between the NSRs and the notional noise source positions of different works areas;
· Apply corrections in the calculations, such as potential screening effects and acoustic reflection, if any;
· Predict the construction noise levels at NSRs in the absence of any mitigation measures; and
· Add a positive 3 dB(A) façade correction to the predicted noise levels in order to account for the facade effect at each NSR.
4.6.2
In reality, not all PME items within a works
area will be operating at all times. The
construction noise assessment was undertaken based on the proposed construction
works programme and plant inventory, and appropriate utilization rates of the
PME items (see Appendix 4.1 and Appendix 4.2). The
Engineer and Project Proponent have reviewed the programme
and plant inventory with appropriate utilization rates, and have confirmed that
they are reasonable and practicable
for completing the Project within the scheduled timeframe (see Appendix 4.10). The
proposed methods for the construction of the Project are common in Hong Kong
and the PMEs proposed are available in the Hong Kong market.
4.6.3
The works area of the Project are shown in Figure
4.1. The total SWL associated
with each construction activity for corresponding sections was
established. The potential noise impacts
at NSRs were evaluated by comparing the predicted noise levels with the EIAO-TM day-time construction noise
limits (Leq, 30min dB(A)), as
outlined in Section 4.2.
Scheduling of PME/Construction Activities
4.6.4 The construction activities will be divided into sections, and further divide into sub-sections of about 50m length per each. To ensure no adverse noise impact will be imposed to the surrounding NSRs, at most 3 works front will be conducted at the same time for each sub-sections. Separation of works areas are shown in Appendix 4.1. The construction works at Ping Che Road and Ping Yeung Village shall carry out at only one work front in each divided section. Such arrangement is confirmed by Project Engineer to be practicable for completing the works in scheduled timeframe.
Cumulative Noise Impact
4.6.5 The cumulative noise impact from North East New Territories Sewerage System is included in the assessment. Other concurrent projects are discussed in Section 4.9.
4.7.1
The predicted construction noise levels during
day-time period for the construction of the Project are presented in Table 4.8. Summaries of the
predicted noise levels and details of the noise calculations are presented in Appendix 4.3 and Appendix
4.4, respectively.
Table 4.8 Predicted
Construction Noise Levels dB(A) (Without Mitigation)
NSR |
Description |
Maximum
Predicted Noise Level(a), dB(A) |
Noise
Criteria, Leq, 30min, dB(A) |
Compliance
(Y/N) |
NSR1 |
307 Ping Yeung |
89 |
75 |
N |
NSR2 |
17 Ping Yeung |
90 |
75 |
N |
NSR3 |
362 Ping Yeung |
92 |
75 |
N |
NSR4 |
331 Ping Yeung |
89 |
75 |
N |
NSR5 |
156B Ping Yeung |
90 |
75 |
N |
NSR6 |
Temporary Shelter near TKL04 |
92 |
75 |
N |
NSR7 |
Sing Ping Village |
83 |
75 |
N |
NSR8 |
Caritas Fung Wong Fung Ting
Home |
91 |
75 |
N |
NSR9 |
5 Tong Fong |
77 |
75 |
Y |
NSR10 |
55 Lei Uk |
82 |
75 |
N |
NSR11 |
Wun Chuen
Sin Kwoon |
77 |
75 |
N |
NSR12 |
200 Tai Po Tin |
77 |
75 |
N |
NSR13 |
323 Tai Po Tin |
85 |
75 |
N |
NSR14 |
118 Tai Po Tin |
82 |
75 |
N |
NSR15 |
103 Ping Che |
74 |
75 |
Y |
NSR16 |
Temporary Shelter near TKL05 |
93 |
75 |
N |
NSR17 |
60
Tong Fong |
82 |
75 |
N |
NSR18 |
Village
house in Tai Po Tin |
92 |
75 |
N |
NSR19 |
124A
Ping Yeung |
90 |
75 |
N |
NSR20 |
196
Ping Che |
78 |
75 |
N |
NSR21 |
Village
house at Lei Uk Tsuen |
82 |
75 |
N |
NSR22 |
Temporary
Shelter |
93 |
75 |
N |
NSR23 |
Ta Kwu Ling Farm house |
82 |
75 |
N |
NSR24 |
House
223 Ping Che Road |
85 |
75 |
N |
Notes:
(a) All predicted noise levels dB(A)were corrected with
3dB(A) for façade reflection.
4.7.2 The results indicate the construction noise levels at all of the representative NSRs exceeded the EIAO-TM noise criteria in daytime during the course of the construction period, except NSR15(103 Ping Che) . Mitigation measures will therefore be required to mitigate the construction noise impact.
4.8.1 In view of the predicted noise exceedances during the construction of the Project, the following mitigation measures have been considered. The “Recommended Pollution Control Clauses for Construction Contracts” promulgated by EPD will also be added to the Contract for future contractors to follow.
·
Good site practice;
·
Use of quiet PME;
·
Adoption of temporary noise barrier or noise
enclosure; and
· Scheduling of PME/construction activities.
Good Site Practices
4.8.2 Good site practices and noise management can considerably reduce the potential noise impact of construction activities on nearby NSRs. The noise benefits of these practices can vary according to specific site conditions and operations. Since the effect of the good construction site practices could not be quantified, the mitigated noise levels calculated in the subsequent sections have not taken account of this effect. The following site practices should be followed during the construction of the Project:
· Only well-maintained plant will be operated on-site and plant will be serviced regularly during the construction phase;
· Silencers or mufflers on construction equipment will be utilized where required and will be properly maintained during the construction phase;
· Mobile plant, if any, will be sited as far away from NSRs as possible;
· Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down to a minimum;
· Plant known to emit noise strongly in one direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs; and
· Material stockpiles and other structures will be effectively utilised, wherever practicable, in screening noise from on-site construction activities.
Use of Quiet PME
4.8.3 The
use of quiet PME is considered to be a practicable means to mitigate the
construction noise impact. Quiet PME is
defined as a PME having actual SWL lower than the value specified in the
GW-TM. The total SWL of all plant items
to be used on-site at each works area will be specified so that flexibility is
allowed for the Contractor to select plant items to suit the construction
needs. The Contractor shall select plant items with total SWL equal to or lower
than the total SWL specified in the plant inventory in Appendix 4.5 in
order to meet the relevant noise criteria. Quiet PME that have been adopted in
the assessment are summarised in Table 4.9..
Table 4.9 Sound Power Level of Quiet PME
PME |
EPD QPME Reference(a)(b) |
Sound Power Level, dB(A) |
Excavator, mini-robot mounted (electric) |
(a) |
94 |
Hand-held Percussive Breaker |
EPD-04212 |
99 |
Dump truck, with grab, 5.5 tonne <gross vehicle weight <=38 tonne |
(a) |
105 |
Roller, vibratory |
EPD-09720 |
94 |
Poker, vibratory, hand-held (electric) |
(a) |
102 |
Giken
Piler |
(c) |
94 |
Air blower (electric) |
(a) |
95 |
Mobile Crane |
EPD-07164 |
92 |
Super Silenced Generator |
CNP
103 |
95 |
Note:
(a)
Extracted from EPD document namely, "Sound power levels of other
commonly used PME"
(b)
Extracted from EPD database namely, "Quality powered mechanical
equipment"
(https://www.epd.gov.hk/cgi-bin/npg/qpme/search_gen.pl?lang=eng&st=sim&valid=Y)
(c)
Extracted from approved EIA report "Tsim
Sha Tsui Station Northern Subway" (Register No.: AEIAR-127/2008), and
approved by Engineer. (https://www.epd.gov.hk/eia/register/report/eiareport/eia_1542008/EIA%20Report/html/Appendices/App_4-4_Final.pdf)
Adoption of Temporary Noise Barriers or
Noise Enclosure
4.8.4 The use of noise barriers will be an effective means to mitigate the noise impact arising from the construction works in the works area, particularly for low-rise NSRs. Temporary Noise Barriers of appropriate height with skid footing should be used and located within a few metres of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. It is anticipated that the major noise source of all PMEs, including movable and large PMEs, will be located at a level lower than the top of the proposed movable barriers. All movable barriers are expected to provide at least a 5 dB(A) noise reduction for mobile plant such as excavator, poker and roller; fixed barriers are capable to produce higher noise reduction of 10 dB(A) for stationary plant, such as air blower and winch. With reference to A Practical Guide for the Reduction of Noise from Construction Works, the noise barrier material should have a superficial surface density of at least at least 14 kg/m2, without openings or gap.
4.8.5 The use of noise enclosure is to cover stationary PMEs, such as generator which will be completely screened. The construction material of the noise enclosure should have a minimum surface density of 14 kg/m2 and without openings or gaps. This can achieve at least a 15 dB(A) noise reduction according to the EIAO Guidance Note No.9/2010.
4.8.6 The Project Engineer has confirmed that the use of quieter PME in Table 4.8 and adoption of noise barrier/enclosure at the work sites are practicable.
4.8.7 The summary of screening structures proposed for each PME is presented in Table 4.10 below. Schematic configuration of the noise barrier is presented in Appendix 4.9.
Table 4.10 Summary of
Screening Structures for Each PME
PME |
Type of Screening Structures |
Noise reduction, dB(A) |
Excavator, mini-robot mounted (electric) |
Temporary Noise Barrier |
-5 |
Dump truck, with grab, 5.5 tonne <gross
vehicle weight <=38 tonne |
Temporary Noise Barrier |
-5 |
Hand-held Percussive Breaker |
Temporary Noise Barrier |
-5 |
Generator, super silenced, 70dB(A) at 7m |
Enclosure |
-15 |
Crane, mobile |
Temporary Noise Barrier |
-5 |
Bar Bender and Cutter (Electric) |
Temporary Noise Barrier |
-10 |
Water pump, submersible (electric) |
Temporary Noise Barrier |
-10 |
Concrete mixer (electric) |
Temporary Noise Barrier |
-5 |
Poker, vibratory, hand-held (electric) |
Temporary Noise Barrier |
-5 |
Roller, vibratory |
Temporary Noise Barrier |
-5 |
Giken Piler and Power Pack |
Temporary Noise Barrier |
-5 |
Winch (electric) |
Temporary Noise Barrier |
-10 |
Air blower (electric) |
Temporary Noise Barrier |
-10 |
Good Construction Site Practices, Use of
Quiet PME, Noise Barriers and Enclosures
4.8.8 With the implementation of the good construction site practices, use of quiet PME, noise barriers and enclosures (as shown in Appendix 4.5), the mitigated noise levels at the representative NSRs were calculated and the results are summarized in Table 4.11. Summaries of predicted mitigated noise levels and detailed calculations are presented in Appendix 4.6 and Appendix 4.7, respectively.
Table 4.11 Predicted Construction Noise Levels (With
Mitigation)
NSR |
Description |
Maximum Predicted Noise Level(a), dB(A) |
Noise Criteria, Leq,
30min, dB(A) |
Compliance (Y/N) |
NSR1 |
307
Ping Yeung |
71 |
75 |
Y |
NSR2 |
17
Ping Yeung |
73 |
75 |
Y |
NSR3 |
362
Ping Yeung |
75 |
75 |
Y |
NSR4 |
331
Ping Yeung |
72 |
75 |
Y |
NSR5 |
156B
Ping Yeung |
73 |
75 |
Y |
NSR6 |
Temporary
Shelter near TKL04 |
73 |
75 |
Y |
NSR7 |
Sing
Ping Village |
65 |
75 |
Y |
NSR8 |
Caritas
Fung Wong Fung Ting Home |
72 |
75 |
Y |
NSR9 |
5
Tong Fong |
63 |
75 |
Y |
NSR10 |
55
Lei Uk |
63 |
75 |
Y |
NSR11 |
Wun Chuen Sin Kwoon |
65 |
75 |
Y |
NSR12 |
200
Tai Po Tin |
64 |
75 |
Y |
NSR13 |
323 Tai
Po Tin |
66 |
75 |
Y |
NSR14 |
118
Tai Po Tin |
63 |
75 |
Y |
NSR15 |
103
Ping Che |
59 |
75 |
Y |
NSR16 |
Temporary
Shelter near TKL05 |
74 |
75 |
Y |
NSR17 |
60 Tong Fong |
71 |
75 |
Y |
NSR18 |
Village house in Tai Po Tin |
73 |
75 |
Y |
NSR19 |
124A Ping Yeung |
73 |
75 |
Y |
NSR20 |
196 Ping Che |
65 |
75 |
Y |
NSR21 |
Village house at Lei Uk
Tsuen |
63 |
75 |
Y |
NSR22 |
Temporary Shelter |
74 |
75 |
Y |
NSR23 |
Ta Kwu Ling Farm house |
70 |
75 |
Y |
NSR24 |
House 223 Ping Che Road |
72 |
75 |
Y |
Notes:
(a)
All predicted
noise levels were corrected with 3dB(A) for façade reflection.
4.8.9 Table 4.11 shows that the predicted noise levels at all NSRs comply with the noise criteria after the mentioned effective mitigation. Therefore, no adverse noise impact is expected to arise from the construction activities.
4.8.10 The future contractor will be required through contract specifications to provide and implement sufficient mitigation measures with reference to the recommendations in this report or the future detailed design to achieve acceptable noise levels on the nearby NSRs. The future contractor will also be required to prepare a construction noise management plan with reference to Section 8 and Annex 21 of the EIAO-TM, and EM&A Manual as well as this EIA Report. The construction management plan shall identify the inventory of noise sources and assess the effectiveness and practically of all mitigation measures considered during the design and tendering stage to minimize the construction noise impact. The construction management plan should confirm and summarise the mitigation measures to be implemented for the Project, and shall be submitted two months prior to the commencement of construction.
4.9.1 The potential for cumulative construction noise impact during the construction phase has been checked against the following known committed/existing projects at the time the EIA is prepared. The Project construction programme may overlap with the following concurrent projects:
·
Implementation
of Water Intelligent Network (WIN), Remaining District Metering Areas and
Pressure Management Areas in Yuen Long and Sheung Shui & Fanling Major Supply Zones;
·
Widening
of the Western Section and Eastern Section of Lin Ma Hang Road (Ping Yuen River
to Ping Che Road / Tsung Yuen Ha to Lin Ma Hang).
4.9.2 Implementation of WIN will fall within the Study Area while the works will be confined into localised works area. The WIN project consists of the minor works to install flow meters, pressure reducing valves (PRV), PRV controllers and data logger, which will not create adverse noise impacts to the surrounding environment. However, the Contractor shall also keep close liaison with the nearby construction site to avoid cumulative noise impact. On the other hand, the widening of the Western Section and Eastern Section of Lin Ma Hang Road (Ping Yuen River to Ping Che Road / Tsung Yuen Ha to Lin Ma Hang is over 300m from the nearest NSR. Therefore, the potential of causing adverse cumulative noise impacts from these projects is not anticipated.
4.9.3 In addition to the above projects, there are also three planning studies with study areas within and in the vicinity of the Project Site, which included the following:
·
Preliminary Feasibility Study
on Developing the New Territories North (NTN);
·
Drainage Improvement
Works in Hang Tau, Kong Ha and Sha Tau Kok Town, and
Lower Ping Yuen River; and
·
North East New
Territories Sewerage System Upgrade.
4.9.4 No sufficient information on the Preliminary Feasibility Study on Developing the New Territories North (NTN) is available for assessing the construction noise impacts and hence it is not included in the assessment.
4.9.5 For Drainage Improvement Works in Hang Tau, Kong Ha, Sha Tau Kok Town and Lower Ping Yuen River, the predicted noise level from the Project at the nearest NSRs, i.e. NSR9, NSR10 and NSR17, to the works area of this concurrent project is 58 dB(A), 63 dB(A) and 62 dB(A) respectively, which are far below the noise criterion of 75 dB(A). Besides, other NSRs are located more than 300m away from the works area of this concurrent project. Therefore, adverse cumulative construction noise impact is not anticipated.
4.9.6 For North East New Territories Sewerage System Upgrade, the cumulative noise assessment is included in the assessment above. The above information is collected from Drainage Service Department.
4.9.7 Overall, it is expected that the cumulative impacts from the construction of the proposed works and other concurrent projects will not lead to exceedance of construction noise criteria. As such, no adverse cumulative environmental impacts are envisaged during both construction and operation phase of the Project.
4.10.1 With the implementation of the recommended noise mitigation measures, the cumulative construction noise levels from the Project and the concurrent projects would comply with the EIAO-TM day-time noise criteria. No residual impact is anticipated.
4.11.1 Noise monitoring is recommended during the construction phase to ensure compliance with the noise criterion at the NSRs. Weekly noise monitoring will be undertaken at the representative NSRs (NSR3 362 Ping Yeung, NSR6 Temporary Shelter near TKL04, NSR8 Caritas Fung Wong Fung Ting Home, NSR11 Wun Chuen Sin Kwoon and NSR16 Temporary Shelter near TKL05). Monthly site inspections and audits will be conducted to ensure that the recommended mitigation measures are properly implemented during the construction stage.
4.12.1 Owing to the close proximity of some of the NSRs to the works area of the Project, mitigation measures are required to be implemented to all representative NSRs to mitigate the construction noise impacts. Practicable mitigation measures, including good construction site practices, use of quiet PME, temporary noise barriers and noise enclosures are recommended. With the implementation of the recommended mitigation measures, the mitigated construction noise levels at the representative NSRs will comply with the daytime construction noise criterion of 75 dB(A) throughout the construction period. Noise monitoring during the construction stage is recommended to ensure compliance with the relevant noise criterion.