CONTENTS
1.
INTRODUCTION
1.1 Project Background
1.2 Need of the Project
1.3 Existing Environment
1.4 Objectives of the EIA Study
1.5 Organisation of the Report
2.
DESIGN CONSIDERATION AND PROJECT DESCRIPTION
2.1 Project
Objectives
2.2 Site
History and Project Location
2.3 Benefits
of the Project 2-2
2.4 Without
Project Scenario
2.5 With
Project Scenario
2.6 Design
Consideration
2.7 Design
Return Period
2.8 Relevant
Technical Circulars / Guidelines
2.9 Essential
Design Considerations / Principles Adopted
2.10 Alternative
Alignment
2.11 Alternative
Location of Stormwater Drains and Discharge Points
2.12 Alternative
Design Options for Watercourse TKL04 and TKL05
2.13 Evaluation
of Design Options
2.14 Recommended
Drainage Options
2.15 Alternative
Channel Bed Lining / Embankment Lining Options
2.16 Alternative
Dry Weather Flow Channel
2.17 Project
Scope
2.18 Project
Design
2.19 Ancillary
Infrastructure
2.20 Landscaping
Works
2.21 Construction
Method
2.22 Consideration
of Alternative Construction Methods
2.23 Consideration
of Alternative Construction Sequence
2.24 Scope
of Works during Operational Phase
2.25 Construction
Programme
2.26 Concurrent
Projects
2.27 Cumulative
Environmental Impact
2.28 Sustainability
Considerations
2.29 Continuous
Public Involvement (CPI)
3.
AIR QUALITY IMPACT ASSESSMENT
3.1 Introduction
3.2 Statutory Requirements and Evaluation Criteria
3.3 Study Area
3.4 Identification of Air Sensitive Receivers
3.5 Baseline Condition and Background Air Quality
3.6 Assessment Methodology
3.7 Evaluation of Impacts during Construction Phase
3.8 Evaluation of Impacts during Operation Phase
3.9 Mitigation Measures
3.10 Potential for Cumulative Impacts
3.11 Residual Impacts
3.12 Monitoring and Audit Requirements
3.13 Conclusion
4.1 Introduction
4.2 Relevant Legislation and Guidelines
4.3 Description of the Noise Environment
4.4 Noise Sensitive Receivers
4.5 Identification for Potential Impacts
4.6 Assessment Methodology
4.7 Evaluation of Impacts
4.8 Mitigation Measures
4.9 Cumulative Impact
4.10 Residual Impacts
4.11 Monitoring and Audit Requirements
4.12 Conclusion
5.
WATER QUALITY IMPACT ASSESSMENT
5.1 Introduction
5.2 Environmental Legislation, Policies, Standards and Criteria
5.3 Baseline Water Quality Conditions
5.4 Assessment Methodology
5.5 Water Sensitive Receivers
5.6 Potential Sources of Impacts
5.7 Impact Assessment
5.8 Mitigation Measures
5.9 Residual Impacts
5.10 Cumulative Impacts
5.11 Monitoring and Audit Requirement
5.12 Conclusion
6.1 Introduction
6.2 Relevant Legislation, Policies, Standards and Criteria
6.3 Assessment Methodology
6.4 Expected Waste Sources
6.5 Waste Management Assessment
6.6 Mitigation Measures
6.7 Residual Environmental Impacts
6.8 Environmental Monitoring and Audit Requirements
6.9 Conclusion
7.1 Introduction
7.2 Statutory Requirements and Evaluation Criteria
7.3 Description of the Proposed Project
7.4 Future Land Use
7.5 Assessment Methodology
7.6 Historical and Current Land Uses of Project Area
7.7 Potential Land Contamination Hotspots
7.8 Site Investigation Programme
7.9 Evaluation of Land Contamination Impacts
7.10 Cumulative Impacts
7.11 Recommendation of Further Works
7.12 Residual Impact Evaluation and Mitigation Measures
7.13 Conclusion
8.
ECOLOGICAL IMPACT ASSESSMENT
8.1 Introduction
8.2 Relevant Legislation and Guidelines
8.3 Literature Review
8.4 Ecological Baseline Survey Methodology
8.5 Ecological Baseline Survey Results
8.6 Evaluation of Habitats and Species of Conservation Importance.
8.7 Impact Assessment
8.8 Mitigation Measures
8.9 Summary of Mitigation Measures
8.10 Evaluation of Residual Ecological Impacts
8.11 Environmental Monitoring and Audit Programme
8.12 Conclusion
8.13 Reference
9.
FISHERIES IMPACT ASSESSMENT
9.1 Introduction
9.2 Environmental Legislation, Standards and
Guidelines
9.3 Assessment Area
9.4 Assessment Methodology
9.5 Baseline Condition
9.6 Impact Assessment
9.7 Mitigation Measures
9.8 Potential for Cumulative Impact
9.9 Evaluation of Residual Impact
9.10 Environmental Monitoring and Audit
9.11 Conclusion
9.12 References
10.
CULTURAL HERITAGE IMPACT ASSESSMENT
10.1 Introduction
10.2 Relevant Legislation and Guidelines
10.3 Assessment Methodology
10.4 Cultural Heritage Baseline Condition
10.5 Cultural Heritage Impact Assessment
10.6 Mitigation Measures
10.7 Residual and Cumulative Impacts
10.8 Environmental Monitoring & Audit
10.9 Conclusions
10.10 Bibliography
11.
LANDSCAPE AND VISUAL IMPACT ASSESSMENT
11.1 Introduction
11.2 Environmental Legislation, Standards,
Guidelines and Criteria
11.3 Principal Work Elements
11.4 Assessment Methodology
11.5 Planning and Development Control Framework
11.6 Landscape Baseline Condition
11.7 Tree Survey Baseline Condition
11.8 Visual Baseline Condition
11.9 Potential Landscape and Visual Impacts
11.10 Landscape Impact Assessment
11.11 Visual Impact Assessment
11.12 Mitigation Measures
11.13 Cumulative Impacts
11.14 Conclusion
11.15 Environmental Monitoring & Audit
11.16 Bibliography
12.
ENVIRONMENTAL MONITORING AND AUDIT MEASURES
12.1 Introduction
12.2 EM&A Manual
12.3 Air Quality
12.4 Noise
12.5 Water Quality
12.6 Waste Management
12.7 Land Contamination
12.8 Ecology
12.9 Fisheries
12.10 Cultural Heritage
12.11 Landscape and Visual
12.12 Implementation Schedule
13.
SUMMARY OF ENVIRONMENTAL OUTCOMES
13.1 Introduction
13.2 Environmental Benefits of the Project
13.3 Environmental-Friendly Design Recommended
13.4 Environmentally Sensitive Areas Protected
13.5 Key Environmental Problems Avoided and
Compensation Areas
Included
13.6 Environmental
Benefits of Environmental Protection Measures Recommended
14.
CONCLUSION
14.1 Introduction
14.2 Air
Quality Impact
14.3 Noise
Impact
14.4 Water
Quality Impact
14.5 Waste
Management
14.6 Land
Contamination
14.7 Ecological
Impact
14.8 Fisheries
Impact
14.9 Cultural
Heritage Impact
14.10 Landscape
and Visual Impact
14.11 Environmental
Monitoring and Audit (EM&A)
14.12 Overall
Conclusion
List of Tables
Table
2.1 |
Alternative
Design Options Considered for the Proposed Watercourses |
Table
2.2 |
Evaluation
of the Proposed Options |
Table
2.3 |
Summary
of the Evaluation of Alternative Channel Bed / Embankment Lining Options |
Table
2.4 |
Configuration
of Proposed Watercourses TKL04 and TKL05 |
Table
2.5 |
Environmental
Benefits and Dis-Benefits of Alternative Construction Methods |
Table
2.6 |
Configuration
of Existing and Proposed Watercourse TKL04 and TKL05 |
Table
2.7 |
Summary
of the proposed drainage pipes and u-channels at Ping Che Road and Ping Yeung
Village |
Table
2.8 |
Summary
of the proposed gullies in Ping Che Road |
Table
2.9 |
Tentative
Key Milestone Dates |
Table
3.1 |
Hong
Kong Air Quality Objectives |
Table
3.2 |
Identified
Representative Air Sensitive Receivers |
Table
3.3 |
5-year Averaged
Annual Background Concentration of Air Pollutants recorded at Tai Po Station
by EPD for the Period of 2016-2020 |
Table
3.4 |
Background
Air Pollutants at Year 2025 by PATH v2.1 Model (μg/m3) |
Table
4.1 |
EIAO-TM
Day-time Construction Noise Standards (Leq, 30 min
dB(A)) |
Table
4.2 |
Area
Sensitivity Ratings |
Table
4.3 |
Basic
Noise Levels for General Construction Works (BNL, Leq,
5 min dB(A)) |
Table
4.4 |
Summary
of Options for Watercourse TKL04 and TKL05 |
Table
4.5 |
Comparisons
of the Proposed Options |
Table
4.6 |
Representative
Noise Sensitive Receivers (NSRs) |
Table
4.7 |
Tentative
Construction Activities Schedule |
Table
4.8 |
Predicted
Construction Noise Levels (Without Mitigation) |
Table
4.9 |
Sound
Power Level of Quiet PME |
Table
4.10 |
Summary
of Screening Structures for Each PME |
Table
4.11 |
Predicted
Construction Noise Levels (Mitigated Scenario) |
Table
5.1 |
Key
Water Quality Objectives of the Deep Bay WCZ for Ping Yuen River and Shenzhen
River |
Table
5.2 |
Summary
of River Water Quality Monitoring Data collected by EPD River Water Quality
Monitoring Programme for Stations GR1 and GR2 of Ping Yuen River (2018 -
2020) |
Table
5.3 |
Water
Sensitive Receivers |
Table
6.1 |
Government
Facilities for Disposal of C&D Materials |
Table
6.2 |
Waste
Type Classification |
Table
6.3 |
Estimated
Quantities of C&D Materials generated during Site Clearance of TKL04
&TKL05 |
Table
6.4 |
Estimated
Quantities of C&D Materials generated during Channel Excavation and
Construction of TKL04 and TKL05 |
Table
6.5 |
Estimated
Quantities of C&D Materials generated during Excavation and Construction
of Road Drainage in Ping Che Road and Ping Yeung Village |
Table
6.6 |
Estimated
Quantity of Inert C&D Materials to be Reused on Site |
Table
6.7 |
Types
of C&D Materials and Construction Wastes Generated by the Proposed Works |
Table
6.8 |
Summary
of the Quantities of C&D Materials and Construction Wastes Arising from
the Proposed Channels |
Table
6.9 |
Summary
of the Quantities and Disposal Routes of C&D Materials and Waste Arising
from the Project |
Table
6.10 |
Preliminary
Disposal Programme of the C&D Materials |
Table
7.1 |
Summary
of Historical Land Uses |
Table
7.2 |
Summary
of Current Land Uses |
Table
7.3 |
Summary
of SI Programme |
Table
8.1 |
Nesting
Populations of Ardeid in Ping Che Egretry since
2009 |
Table
8.2 |
Species
of Conservation Importance Recorded within the Study Area from the Reviewed
Literature |
Table
8.3 |
Ecological
Survey Programme |
Table
8.4 |
Habitats
within the Study Area |
Table
8.5 |
Ping
Che Egretry Activity from March to August 2020 |
Table
8.6 |
Evaluation
of Habitats within the Proposed Works Limit |
Table
8.7 |
Evaluation
of Abandoned Agricultural Land within the Study |
Table
8.8 |
Evaluation
of Agricultural Land within the Study Area |
Table
8.9 |
Evaluation
of Channel within the Study Area |
Table
8.10 |
Evaluation
of Developed Area within the Study Area |
Table
8.11 |
Evaluation
of Fung Shui Wood within the Study Area |
Table
8.12 |
Evaluation
of Plantation within the Study Area |
Table
8.13 |
Evaluation
of Pond within the Study Area |
Table
8.14 |
Evaluation
of Shrubland/Grassland within the Study Area |
Table
8.15 |
Evaluation
of Wasteland within the Study Area |
Table
8.16 |
Evaluation
of Watercourse within the Study Area |
Table
8.17 |
Evaluation
of Woodland within the Study Area |
Table
8.18 |
Evaluation
of Flora Species of Conservation Importance Recorded within the Study Area |
Table
8.19 |
Evaluation
of Fauna Species of Conservation Importance Recorded within the Study Area |
Table
8.20 |
Potential
Direct Habitat Loss in Proposed Works Limit |
Table
8.21 |
Direct
Ecological Impacts on Species of Conservation Importance |
Table
8.22 |
Potential
Disturbance on Habitats in Study Area |
Table
8.23 |
Indirect
Disturbance to Ping Che Egretry |
Table
8.24 |
Summary
of Predicted Ecological Impacts |
Table
10.1 |
Site of
Archaeological Interest in the CHAA |
Table
10.2 |
Summary
of Previous Archaeological Works Conducted and the Archaeological Discovery |
Table
10.3 |
Archaeological
Potential Evaluation |
Table
10.4 |
Identified
Graded Historic Buildings |
Table
10.5 |
Identified
Built Heritage Items |
Table
10.6 |
Impact
Assessment on Built Heritage Items within 50m from The Works Area |
Table
10.7 |
Recommended
3As levels for Grade 3 Heritage Sites from The Works Area |
Table
11.1 |
Matrix
of Impact Significance |
Table
11.2 |
Details
of Administrative Planning Zones |
Table
11.3 |
Sensitivity
of Landscape Character Areas |
Table
11.4 |
Sensitivity
of Landscape Resources |
Table
11.5 |
Summary
table of affected trees in Landscape Resources |
Table
11.6 |
Details
of Visually Sensitive Receivers |
Table
11.7 |
Summary
of Magnitude of Change on LCAs and LRs |
Table
11.8 |
Summary
of Impact Significance on LRs and LCAs before mitigation |
Table
11.9 |
Summary
of Magnitude of Change on VSRs |
Table
11.10 |
Summary
of Impact Significance on VSRs before mitigation |
Table
11.11 |
Proposed
Mitigation Measures for Landscape and Visual Impacts |
Table
11.12 |
Summary
of Impact Significance on LRs and LCAs, both before and upon mitigation |
Table
11.13 |
Summary
of Impact Significance on VSRs, both before and upon mitigation |
Table
11.14 |
Sensitivity
of Landscape Resources |
Table
11.15 |
Summary
table of affected trees in Landscape Resources |
Table
13.1 |
Summary
of Key Environmental Problems Avoided and Sensitive Areas Protected |
Table
13.2 |
Key
Recommended Mitigation Measures and Associated Environmental Benefits |