Agreement No. CE 72/2019 (EP) Executive Summary for the New
Contaminated Sediment Disposal Facility to the West of Lamma Island July
2022 |
CONTENTS
1.2 Purpose
& Nature of Project
1.3 Purpose
and Objectives of the EIA Study
2. Objectives and Benefits of the
Project and Consideration of Alternatives
2.1 Need
for Disposal of Contaminated Sediment
2.3 Objectives
and Benefits of the Project
2.4 Scenarios
with and without the Project
3.1 Key
Area Identified for Assessment
3.3 Key
Construction and Operation Activities of the Project
3.4 Tentative
Implementation Programme
4. Legislative Requirements, Evaluation
Criteria and Sensitive Receivers
5. Summary of Environmental Impacts
5.9 Environmental Monitoring and Audit
List of Tables
Table
3.1 Tentative Programme of the Project (Indicative for the
first three CMPs)
Table
5.1 Summary of Environmental Impacts
List of Figures
Figure 3.1.... Key
Area and Preliminary Layout for Contaminated Mud Pits at West of Lamma Island
Since 1992, the Civil Engineering and Development Department (CEDD) of the Hong Kong Special Administrative Region (HKSAR) Government has been managing a number of contaminated sediment disposal facilities in Hong Kong waters, including the contaminated mud pits (CMPs) to the east of Sha Chau (ESC) and the south of The Brothers (SB). These facilities consist of some series of seabed pits, formed by the removal of existing marine sediments, for disposal of contaminated dredged/ excavated sediment generated from works within Hong Kong. When their designed capacities have been reached, the pits would be sealed off from the adjoining environment by a layer of uncontaminated sediment (or naturally excavated materials) of no less than 3 m thick. Operations at these facilities are monitored through the implementation of a purposely designed environmental monitoring and auditing programme. Monitoring results for the existing CMPs at ESC and exhausted CMPs at SB indicate that operations at these facilities are environmentally acceptable.
According to the latest estimate, the total remaining capacity of the existing disposal facility at ESC can only cope with the demand up to 2027 for the disposal of contaminated sediment generated from routine harbour / channel / river maintenance dredging works and future projects. The existing CMPs cannot be expanded further due to the limited usable seabed in the vicinity based on the findings of two previous studies ([1]) ([2]). A new sediment disposal facility has to be planned for in order to meet the sediment disposal demand after 2027 arising from routine harbour / channel / river maintenance dredging works and other projects.
To address the sediment disposal
requirements upon the exhaustion of the existing CMPs, CEDD commissioned a
preliminary study in 2017 to assess the potential sites suitable for developing
into future CMPs. The study has
identified that a portion of the seabed in the West Lamma Channel, between
Cheung Chau and Lamma Island, has good potential for developing into a new
contaminated sediment disposal facility (“the Project”). Based on the finding of this study, the
Government decided in 2017 to take forward the Project.
The Project covers a new marine contaminated
sediment disposal facility in the
West Lamma Channel, which is capable of disposing of sediments categorized as
Type 1 – Open Sea Disposal (Dedicated Sites), Type 2 – Confined Marine Disposal
and Type 3 – Special Treatment/ Disposal under the Environment, Transport and Works Bureau
Technical Circular (Works) (ETWB TC(W)) No. 34/2002, involving:
n Dredging of the seabed for the formation of CMPs;
n Disposal of contaminated sediment ([3]) in the formed CMP; and
n Capping of the exhausted CMP by uncontaminated sediment ([4]) up to the original seabed level.
The following
elements of the Project are classified as Designated Projects under the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and therefore a
statutory environmental impact assessment (EIA) is required.
n Item C.10 of Schedule 2, Part I of the EIAO, which specifies “A marine dumping area”; and
n Item C.12 of Schedule 2, Part I of the EIAO, which specifies “A dredging operation exceeding 500,000m3”.
The Study Area for the Project is presented in Figure 1.1.
In accordance with the requirements of Section 5(1) of the EIAO, application for EIA study brief with the Project Profile for the New Contaminated Sediment Disposal Facility to the West of Lamma Island (No. PP-594/2019) was submitted to the Environmental Protection Department (EPD) on 9 December 2019. The EIA Study Brief of the Project (No. ESB-328/2019) were then issued by EPD on 20 January 2020.
The purpose of this EIA Study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the Project and associated works that will take place concurrently. This information will contribute to decisions by the Director of Environmental Protection on:
n The overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project and associated works;
n The conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
n The acceptability of residual impacts after the proposed mitigation measures are implemented.
The detailed requirements of the EIA Study are set out in Clause 3 of the EIA Study Brief. As specified in the EIA Study Brief, the EIA Study has addressed the key environmental issues associated with the construction and operation of the Project.
The EIA Report has been produced in
accordance with the requirements in the EIA Study Brief (No. ESB-328/2019) and
the Technical Memorandum on Environmental
Impact Assessment Process issued under the EIAO (EIAO-TM) for the Project,
the aim being to obtain an Environmental Permit (EP) under the EIAO. The description of the Project presented in
the EIA Report has been based on the best available information compiled by
CEDD that describes the relevant construction activities, operational details
and baseline information describing the conditions relating to the Project and
its surrounding environment.
As stated in the Environment, Transport and Works Bureau Technical Circular (Works) (ETWB TC(W)) No. 34/2002, prior to dredging / excavation of sediments, each project proponent has to provide the rationale for sediment removal. The Marine Fill Committee (MFC) will only consider granting allocation when the need for removal of sediment has been satisfactorily demonstrated. Although non-dredged methods are encouraged for construction of infrastructure projects in Hong Kong, dredging is necessary for essential maintenance works for harbours, fairways, anchorage or drainage channels. According to the latest estimate of the MFC, the annual average contaminated sediment disposal demand is about 0.6 Mm3, with major contribution from the maintenance dredging works, even when project proponents are required to avoid, minimise, reduce dredging where practicable, and reuse sediment if possible. It is therefore not possible to completely eliminate the need of sediment disposal and it is important to maintain a disposal facility for contaminated sediment arising from routine harbour / channel / river maintenance dredging works and other projects.
There are various approaches for management of dredged sediment worldwide. The benefits and dis-benefits of several contaminated mud disposal options including contained aquatic disposal (CAD), confined disposal facility (CDF) and upland disposal have been discussed in Section 2.4 of the EIA Report.
Upland disposal options were not recommended because of the following reasons:
n The use of an existing landfill was deemed impractical because the large quantities requiring disposal of sediment would result in a significant reduction of capacity for the landfills.
n The technology used in Chemical Waste Treatment Centre and the Sludge Treatment Facility was considered not appropriate for materials that are contaminated with high levels of inorganics (i.e. metals), which is typically the case for contaminated dredged/excavated sediment in Hong Kong.
n Given the apparent suitability of many existing options, and the large land requirement for a new upland facility, development of a new dedicated upland containment facility for contaminated materials was not recommended as suitable.
CAD is preferred over CDF for the contaminated sediment disposal facility with reasons as follows.
n Hong Kong's experience in handling contaminated materials using CAD is among the most extensive and well documented in the world, which provides a sound engineering and environmental basis for continuing with this option. On the other hand, the implementation of the CDF option in Hong Kong would require a formulation, and perhaps testing, of an appropriate design and further trials may be required before full-scale implementation;
n CAD facilities allow more planning flexibility as they can be developed in phases according to the disposal demand, whereas the size of a CDF will be governed in the early planning phase and it will be more difficult to alter at later stage; and
n CAD facilities will result in temporary loss of marine habitats and fishing ground, and benthic recolonisation is expected to take place after completion of capping based on experience from the ESC and SB CMP facilities, whereas CDF development will result in permanent loss of marine habitats and fishing ground.
In addition, identification of available areas, selection of the Study Area and suitability assessment of the Study Area are discussed in Section 2.5 of the EIA Report. In view of the ecological sensitivities, seasonal monsoon, water depth and hydrodynamic conditions, the eastern Hong Kong waters are generally not suitable for the development of Contained Aquatic Disposal (CAD) facilities. The western Hong Kong waters, except the waters of the existing CMPs at ESC and SB, are not suitable for the development of CAD facilities due to strong current flow from Pearl River Estuary. The south-western Hong Kong waters are also not suitable for the development of CAD facilities due to the ecological sensitivities and planning of marine parks. The southern and central waters remain to be feasible for CAD development. With reference to the latest available information, there is no other planned development within the portions of southern waters between Cheung Chau and Lamma Island. Therefore, it is considered that area to the west of Lamma Island would have potential for housing a new CAD facility. Constraint mapping, considering environmental, physical and social constraints for the development of CAD facility, was undertaken to identify usable areas for the potential CAD site (i.e. the Study Area). A suitability assessment was also conducted to confirm the suitability of the Study Area for development of CAD facility based on criteria of environmental, engineering and planning factors.
The Study Area for CAD development is located in the West Lamma Channel to the west of Lamma Island and to the east of the recommended Traffic Separation Scheme (TSS) between south of Kau Yi Chau (KYC) and Fan Lau (route via south of Cheung Chau), in the order of approximately 600 hectares, with decreasing seabed levels from -8 metres above Chart Datum (mCD) to -14 mCD from north to south (Figure 1.1). The Study Area has been selected to avoid key marine ecological habitats, including marine mammals and areas with high fisheries production.
The Project aims to plan and design the new contaminated sediment disposal facility at the west of Lamma Island (WL Facility). The proposed WL Facility aims to meet the sediment disposal demand upon the anticipated exhaustion of the existing CMPs at ESC in 2027, arising from routine harbour / channel / river maintenance dredging works and other projects. The WL Facility is intended to cater for an estimated annual average disposal demand of 0.6 Mm3 of contaminated sediment within the Study Area.
The environmental benefits of the Project have been considered in detail in Section 2.2 of the EIA Report and are summarised as follows:
n Following the spirit of the "Convention on the Prevention of Marine Pollution by Dumping of Wastes and Other Matter" (commonly known as the "London Convention", to which China is a signatory), a centralised management and monitoring scheme has been set up to provide overall control over the disposal of marine mud in Hong Kong.
n Dedicated marine contaminated mud disposal facilities adopting CAD design has been implemented at ESC and SB since 1990s, and the associated environmental monitoring and audit programmes have demonstrated that the operation of the facilities did not cause adverse environmental impacts to the surroundings.
n The WL Facility would adopt a similar CAD design and continue to serve as a centralised facility in Hong Kong, providing an overall control for the disposal of contaminated sediment in an environmentally acceptable manner.
n Based on the previous experience from the ESC and SB facilities, benthic recolonisation occurs after the completion of the final capping layer with uncontaminated sediments and/or natural uncontaminated soil and the site is expected to return to the pre-dredged state within a relatively short period of time.
The existing CMPs at ESC are anticipated to be exhausted by 2027 and they cannot be expanded further due to the limited usable seabed in the vicinity. If new disposal facility is not developed in time to meet the forecasted disposal demand, flood protection works, harbour maintenance dredging works, and the implementation of on-going and planned building/ infrastructure projects will either come to a halt or not be able to proceed. It will also result in navigation risks to marine traffic due to insufficient water depth along the channel if maintenance dredging work could not be carried out in time.
With the Project in place, sediments could be disposed of at the WL Facility after the existing CMPs at ESC are exhausted by 2027. Given the Project is the only sediment disposal facility for disposal of contaminated sediment after the exhaustion of the existing CMPs, it is crucial to have such facility in place taking into account the usage of existing CMPs and the anticipated disposal demand of contaminated sediment in the coming years. To cater for possible surge of disposal demand which may expedite the exhaustion of existing CMPs and any unforeseeable interruption to the project progress, it is necessary to have the new facility ready for disposal by 2025, allowing a transitional period of about two years before the anticipated exhaustion of the existing CMPs. An uninterrupted disposal service could therefore be maintained and flood protection works, harbour maintenance dredging works and the implementation of the on-going and planned building/ infrastructure projects will be able to proceed.
As the Study Area of approximately 600 ha
is relatively large, the area for potential CMP development has been refined with
reference to the site investigation and other baseline information of the Study
Area. The key area identified for
potential CMP development (“the Key
Area”) is presented in Figure 3.1. The Key Area has a size of ~ 235 ha with water depth ranged from -8
mCD to -10 mCD from north to south.
There is no submarine gas pipeline/ utilities within and in the vicinity
of the Key Area and thus no impacts to these facilities are expected from the
Project. The proposed sediment disposal
facility will consist of individual CMPs within the Key Area. The impact assessment discussed in the EIA
Report focuses on the Key Area where the CMPs will be located.
The preliminary layout of the CMPs for the WL Facility is illustrated in Figure 3.1. Each CMP has an area ranged from ~23 ha to ~33 ha and each of them is able to handle ~2-4 Mm3 contaminated sediments. The total maximum capacity for contaminated sediment disposal of the proposed CMPs within the Key Area is 20 Mm3. A total of about 24 Mm3 uncontaminated sediment is estimated to be dredged for the construction of proposed CMPs within the Key Area. The pit walls will have a shallow slope gradient and each CMP will be separated from each other for at least 50 m. The detailed layout and configurations of the proposed CMPs will be subject to review and optimisation in the design and implementation stage.
The CMPs will be formed and used one by one taking into consideration of the latest forecasted demand of sediment disposal, and no more than three pits will be active (dredging / backfilling / capping) at any one time. Details of the construction and operation of the Project are discussed in Section 2.6.4 of the EIA Report. A summary of key construction and operation activities of the Project is presented below.
n Construction activities – dredging of the seabed for the formation of CMP: Either one trailing suction hopper dredger (TSHD) with a maximum working rate of 256,200 m3/week, or up to two grab dredgers with a total maximum working rate of 100,000 m3/week, would be deployed. Each CMP will be dredged down to ~15-20 m below seabed to form a pit with a disposal capacity of about 2-4 Mm3. The construction of each CMP would take about 1 - 2 years, depending on the dredging rate. It should be noted that the WL Facility will be implemented in phases. Timing of dredging the next CMP would depend on the actual contaminated sediment disposal demand. Given the long service lifetime of the WL Facility, the dredging schedule / rate in reality could be adjusted in view of the interface with other concurrent activities / projects as appropriate to minimise potential environmental impacts. Depending on the sediment quality based on the chemical and biological test results, the dredged sediments will be disposed of at open sea or confined marine disposal sites. Based on the available sediment quality data from the ground investigation works, it is expected the dredged sediments would require Type 1 open sea disposal and the sediments could be disposed at the South of Cheung Chau, the South of Tsing Yi, the East of Ninepin, the East of Tung Lung Chau, ESC as capping materials, as well as within WL Facility as capping materials when any CMP of the WL Facility reached its capacity in receiving contaminated sediments. The dredged sediment will be transported to the disposal sites using TSHD or hopper barges with tug boats.
n Operation activities – disposal of contaminated sediment in the formed CMP: With reference to the typical arrangement of the existing CMP, disposal barges are typically instructed to dispose of sediments within the CMP area and located at least 50 m away from the CMP boundaries. The actual disposal location will depend on the water current speed and direction, as well as the sub-area usage to ensure an even backfill level. With reference to the disposal arrangement at the CMPs to ESC and SB, the maximum disposal rate for the Project is assumed to be 26,700 m3/day using TSHD or hopper barges with tug boats. It should be noted that the maximum working rate used in the assessment adopts a conservative approach. Assuming the estimated annual average contaminated sediment disposal demand of 0.6 Mm3 (equivalent to an average of ~1,650 m3/day) for future operation, the actual working rate under normal situation can be much lower throughout most of the service lifetime of the WL Facility. The disposal procedures follows the same procedures that were introduced in 1997 during the backfilling of CMP IIId at ESC as well as the recent CMP at SB and CMP V at ESC.
n
Operation activities - capping of the exhausted CMP by
uncontaminated sediment up to the original seabed level: Once the CMP of the WL Facility is backfilled with contaminated
sediments to 3 m below original seabed level, the CMP will be capped with
uncontaminated sediments using the same disposal procedure for backfilling as
disposal of contaminated sediment, until the CMP is capped to the original
seabed level. With reference to the
capping arrangement at the CMPs to ESC and SB, the maximum capping rate for the
Project is assumed to be 26,700 m3/day using TSHD or hopper barges
with tug boats. It should be noted that
the maximum working rate used in the assessment adopts a conservative
approach. The actual working rate under
normal situation is expected to be much lower throughout most of the service
lifetime of the WL Facility depending on the availability of uncontaminated
sediments for capping.
The first CMP of the Project is planned to start construction in 2024 for operation by 2025/2026, allowing a transitional period of about two years before the anticipated exhaustion of the existing CMPs at ESC in 2027. Each CMP is expected to provide disposal service for approximately 3 years. The tentative programme as shown in Table 3.1 demonstrates the typical construction and operation cycle for the first three CMPs of the proposed WL Facility, which covers a total period of about 10 years (including dredging, backfilling and capping). As the CMPs will be constructed and operated sequentially depending on the disposal demand, the duration for dredging, backfilling and capping of a CMP is estimated for presentation purpose only. Overall, subject to future disposal demand, the proposed WL Facility is expected to have a service lifetime for up to 20 years. The remaining CMPs are anticipated to follow a similar implementation programme for use upon exhaustion of the first three CMPs. It should be noted that no more than three CMPs will be active (dredging / backfilling / capping) at any one time. While backfilling of contaminated sediment is expected to be carried out throughout the operation of the Project, the exact schedule/ working rates of dredging and capping works would be adjusted to minimise potential environmental impacts in view of actual disposal demand of contaminated sediment, availability of uncontaminated sediment for capping and the interface with concurrent projects/ activities, etc.
Table 3.1 Tentative Programme of the
Project (Indicative for the first three CMPs)
Pit |
Construction/Operation |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
Year 6 |
Year 7 |
Year 8 |
Year 9 |
Year 10 |
Year 11 |
Year 12 |
Year 13 |
1st |
Dredging |
|
|
|
|
|
|
|
|
|
|
|
|
|
Backfilling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capping |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2nd |
Dredging |
|
|
|
|
|
|
|
|
|
|
|
|
|
Backfilling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capping |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3rd |
Dredging |
|
|
|
|
|
|
|
|
|
|
|
|
|
Backfilling |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capping |
|
|
|
|
|
|
|
|
|
|
|
|
|
The EIA Study has described the potential impacts associated with the construction and operation activities of the Project on water quality that have been identified and analysed for compliance with the prevailing Water Quality Objectives (WQOs) stipulated under the Water Pollution Control Ordinance (WPCO) and the Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-ICW), and the criteria and guidelines stated in the EIAO-TM Annexes 6 and 14, and Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN1/94), respectively.
The Assessment
Area for water quality impact assessment covers the Southern Water Control Zone
(WCZ), Western Buffer WCZ and Victoria Harbour WCZ. Water Sensitive Receivers (WSRs) were
identified in the Assessment Area, including fish culture zone (FCZ), existing/
potential marine parks, coral communities, Site of Special Scientific Interest
(SSSI), Green Turtle nesting ground, secondary contact recreation subzones,
habitat for Finless Porpoise (FP), nursery area and spawning ground for
commercial fisheries resources, gazetted and non-gazetted bathing
beaches, seawater intakes, typhoon shelters and Water Supplies Department (WSD)
flushing intakes (see Section 3 of the EIA Report
for further details). The potential impacts arising from the
construction and operation activities of this Project to these WSRs have been
evaluated.
The potential impacts of the construction and operation activities of this Project on marine ecology have been assessed in this EIA Report. The impacts have been identified and analysed for compliance with the criteria and guidelines stated in the Annexes 8 and 16 of the EIAO-TM respectively.
The Assessment Area and sensitive receivers for marine ecology are the same as those identified in Section 4.1. Known important habitats and species for marine ecology within the Assessment Area include coral and benthic communities, FP, Green Turtle, as well as the potential South Lamma Marine Park.
Marine ecological surveys, which include coral, subtidal benthos and marine mammal surveys, were conducted during the dry and wet seasons of 2021 to fill the identified data gap and update the latest ecological conditions of marine habitats and assemblages in the Assessment Area. Findings from the surveys confirmed the findings of the literature review, and are presented below:
n
Recognized sites of
conservation importance – these include the potential South Lamma Marine Park,
Sham Wan Site of Special Scientific Interest (SSSI) and the Sham Wan Restricted
Area.
n Coral communities – the survey results indicated that common and widespread species, including hard corals, ahermatypic hard corals and octocorals, were recorded in low percentage cover (< 10%) in the Assessment Area.
n
Subtidal benthos assemblages –
subtidal benthos species reported are common and widespread in Hong Kong with
no species of conservation importance. Overall, the abundance and diversity
of infauna within the Study Area is similar to other areas in west of Lamma and
southern waters of Hong Kong in other studies.
n Finless Porpoise (FP) – FP are present in South Lantau waters year-round and their occurrence is greater and more widespread in these waters in the dry season (December to May). FP use a broad swathe of South Lantau waters, particularly extending across the waters between the Soko Islands and Shek Kwu Chau, with the proposed CMP to be located at the east of their main habitat, where FP densities are recorded to be low from the literature review and the field surveys. The area within and in the vicinity of the Study Area is not a key occurrence habitat for FP.
n
Green Turtles – the literature
review suggested the presence of Green Turtle Chelonia mydas in the Assessment Area. Very occasional records of a few animals were
reported previously and no opportunistic sightings of Green Turtle occurred
during the marine ecological surveys for this EIA study. The major nesting site for Green Turtle in
Hong Kong is at Sham Wan, southern Lamma Island, which is more than 5 km from the Key Area for potential CMP
development.
Based on the baseline data, the ecological
importance of subtidal soft benthos assemblages and marine waters of the Study
Area, as well as the subtidal hard bottom habitat in the vicinity of the
Project are considered low. Although FPs are present in the Assessment
Area, the area within and in the vicinity of the
Study Area is not a key occurrence habitat for FP. Potential South Lamma Marine Park, and Sham Wan SSSI
and Restricted Area are considered to range between
moderate and high ecological importance. The potential impacts
arising from the construction and operation phases of this Project to these
sensitive receivers have been evaluated.
The potential impacts to fisheries caused by the construction and operation activities of this Project have been assessed in this EIA Report. The impacts have been identified and analysed for compliance with the criteria and guidelines stated in the EIAO-TM Annexes 9 and 17 respectively.
The Assessment Area and sensitive receivers for fisheries are the same as those identified in Section 4.1 above. A review of baseline information on commercial fisheries resources, habitats and fishing operations surrounding the waters of the proposed Project from available literature and field surveys has been undertaken. Results from the review indicate that the Study Area falls within an area with moderate to high level of fishing operations and provides low to moderate capture fisheries production. Sensitive receivers, including spawning ground and nursery area of commercial fisheries resources in southern waters, FCZs in Sok Kwu Wan, Lo Tik Wan, Cheung Sha Wan and Ma Wan, and artificial reefs in the Lo Tik Wan FCZ have been identified. The potential impacts arising from the construction and operation activities of this Project to these sensitive receivers have been evaluated.
The potential waste management implications caused by construction and operation activities of this Project have been assessed in this EIA Report. The impacts have been identified and analysed for compliance with the criteria and guidelines stated in the Annex 7 and Annex 15 of the EIAO-TM respectively.
A review of sediment quality data and further sediment sampling were undertaken as part of this EIA Study to investigate sediment quality along the vertical profile of the Key Area. The sediment testing results were compared against the relevant sediment quality criteria specified in ETWB TCW No. 34/2002 – Management of Dredged/ Excavated Sediment. All the marine sediments to be dredged within the Key Area were found to be uncontaminated.
The potential impacts to cultural heritage, in particular marine archaeology, associated with the construction and operation activities of this Project have been assessed in this EIA Report. The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the Annexes 10 and 19 of EIAO-TM respectively.
A Marine Archaeological Investigation
(MAI), including a desktop review supplemented with marine geophysical survey,
has been undertaken. The MAI confirmed
that the Key Area identified for potential CMP development under the Project
has no sites of archaeological potential. The potential impacts on cultural
heritage arising from the construction and operation activities of this Project
have been evaluated.
The potential hazards arising from the
construction and operation activities of the Project have been evaluated with
reference to the guidelines of the US Environmental Protection Agency (EPA) and
incorporated a four-step approach involving problem formulation,
characterisation of exposure, characterisation of human health effects, and
risk characterisation. The intent of
this evaluation is to determine the potential risks to the various populations
of Hong Kong, resulting from contaminated sediment disposal at the proposed WL
Facility. The exposure pathway is
assumed to be consumption of food by members of the various populations in the
assessment including Hong Kong people in general, Hong Kong fishermen, and WL
fishermen. Evaluation of carcinogenic
risk and an estimate of the hazard (i.e. non-carcinogenic risk) to the three
populations through the consumption of contaminated seafood have been conducted
in the EIA Report.
This EIA Study has
examined the impacts to air quality during construction and operation activities
of the Project. The impacts have been identified and analysed for compliance
with the prevailing Air Quality Objectives (AQOs) stipulated under the Air Pollution Control Ordinance (APCO)
and the criteria and guidelines stated in the Annexes 4 and 12 of the EIAO-TM respectively.
The Assessment Area for air quality is defined as an area within 500 m from the boundary of the Project (i.e. Key Area identified for potential CMP development). No existing or planned Air Sensitive Receiver (ASR) have been identified within the Assessment Area. A total of seven representative ASRs beyond the Assessment Area (at least 2.5 km away) have been identified. The potential impacts arising from the construction and operation activities of this Project have been evaluated.
The potential
impacts of noise from the construction and operation activities of the Project
have been assessed in this EIA Report.
The impacts have been identified and analysed for compliance with the
criteria and guidelines stated in the Annexes
5 and 13 of the EIAO-TM respectively and the applicable
criteria stipulated under the Noise
Control Ordinance (NCO).
The Assessment Area for noise covers a distance of 300 m from the boundary of the Project (i.e. the Key Area identified for potential CMP development). No existing or planned Noise Sensitive Receiver (NSR) was identified within the Assessment Area. The nearest existing NSR is located at more than 2.8 km from the Project site. The potential impacts arising from the construction and operation activities of this Project have been evaluated.
Computational modelling has been conducted to predict various potential water quality impacts from the proposed marine dredging during construction, as well as backfilling and capping during operation under this Project, and relevant concurrent projects. The construction activities (dredging) could overlap with operation activities (backfilling and capping). Key water quality issues, including changes in water quality due to construction and operation activities, marine vessel discharges and changes in flow regime have been assessed. Cumulative impacts arising from relevant concurrent projects has also been taken into account during the assessment.
Full compliance is predicted at all
identified WSRs for all parameters in both dry and wet seasons. Key results are
outlined below:
n
The
sediment loss rates under the
construction and operation activities were assumed at the respective maximum,
and all the identified concurrent marine works would be conducted with their
maximum allowed sediment loss rates. The
maximum suspended solid (SS) elevation of 1.1 mg L-1 is predicted to
occur at MP1-C (Potential South Lamma MP) for dry season, and the maximum of 0.8
mg L-1 was predicted at MP1-B (Potential South Lamma MP) and CR01
(corals at Cheung Chau) for wet season, of which are well below their
respective WQO criteria. The predicted
sedimentation flux at nearby coral locations are also well below the corresponding
assessment criterion of 100 g/m2/day and thus no unacceptable
impacts to coral communities are expected due to sediment deposition from the
Project.
n
As sediment samples collected
within the Key Area was identified as uncontaminated sediment, risk of release
of sediment-bounded contaminant from dredging works of the Project is
minimal.
n
The
maximum predicted dissolved oxygen (DO) depletion level based on
conservative assumptions using maximum SS elevation is around 0.03 mg L-1 (at MP1-C),
which is considered to be insignificant.
No unacceptable water quality impact from DO depletion is anticipated.
n Results of water quality modelling also indicated the predicted release of sediment-bounded contaminants as well as nutrients would be limited at the identified WSRs and are below the corresponding assessment criteria. No unacceptable water quality impact associated with release of sediment-bounded contaminants as well as nutrients is anticipated.
n Considering the relatively small scale of operation and vessel movements, standard site practices as well as the suitable collection and disposal of wastewater / sewage, no unacceptable water quality impact associated with marine vessel discharges is expected.
n
Results of
hydrodynamic modelling indicated that the change in flow regime would be
minimal. No unacceptable change in flow
regime on the surrounding water would be expected due to the presence of the Project.
To further minimise potential water
quality impact associated with the Project, mitigation measures such as
installation of cage-type silt curtain around closed grab, no overflow from
TSHD, the Lean Mixture Overboard (LMOB) system of TSHD will only be in
operation at the beginning and end of the dredging cycle when the drag head is
being lowered and raised, control of dredging / backfilling / capping rates, as
well as other standard measures and good site practices are recommended to be
implemented.
Marine water quality
monitoring at selected WSRs is recommended for marine dredging, backfilling and
capping of the Project. Sediment quality
monitoring is also recommended for backfilling of the CMPs. Regular site audit would also be conducted
throughout the Project.
Potential impacts to marine ecological resources that may arise from the construction and operation activities are assessed. The temporary habitat loss and disturbance within and in the vicinity of the Key Area throughout the construction and operation activities of the Project is expected. Considering the low ecological value of the associated benthic assemblages, and the recolonization of similar organisms following completion of capping works of the CMP, unacceptable impacts on the benthic communities are not expected.
Considering the temporary nature of the disturbance on the non-key FP occurrence habitat and with controlled work rates for dredging, backfilling and capping works, impacts on FP are expected to be of minor significance. Upon cessation of the disturbance, no significant change in marine mammal distribution, abundance and usage pattern in the wider Hong Kong waters is expected. Considering the major nesting site (Sham Wan) for Green Turtles in Hong Kong is located > 5 km away from the Key Area for potential CMP development, and given the occurrence of Green Turtles is highly opportunistic, it is unlikely that the waters within and in the vicinity of the Key Area represent unique habitats that the species would rely on. Unacceptable impacts on Green Turtles are not expected.
Dredging, backfilling and capping works of the CMPs are expected to result in a minor increase in underwater sound. The waters within the Assessment Area and its vicinity is subject to relatively high levels of marine traffic by similar types of vessels. It is reasonable to assume the marine invertebrates and Green Turtles in these waters are habituated to a relatively high background level of underwater sound. FP would be expected to respond to sound generating activities by avoiding a localised works area near the CMPs and the effect would be limited to behavioural disturbance impacts on affected individuals only without affecting the functionality of key habitats such as the waters between the Soko Islands and Shek Kwu Chau. No significant long-term change in marine mammal distribution, abundance and usage pattern in the wider Hong Kong waters is expected. Unacceptable adverse impacts of increased underwater sound level on FP are not anticipated.
Unacceptable impacts to the marine ecological resources including coral and benthic communities, Green Turtles, FP and the potential South Lamma Marine Park are not expected due to the changes in water quality from construction and operation activities, including SS elevation, DO depletion, release of sediment-bounded nutrients as well as contaminants.
The risk of marine mammals being killed or injured by vessel collisions in Hong Kong is mainly associated with high-speed vessels such as high-speed ferries. Given the slow-moving nature of the relatively small number of works vessels involved in the Project, unacceptable adverse impacts of increased marine traffic on FP are not anticipated. A small increase in vessel activity associated with the construction and operation activities of this Project is not anticipated to result in unacceptable impacts on these marine ecological resources.
The lighting on works vessels for the CMPs is expected to be similar to the nearby marine traffic travelling around the Project area through the nearby fairways. Unacceptable adverse impacts from increased marine traffic, glare effect of light sources of construction and operation activities on Green Turtles are not anticipated.
With the small quantities of chemicals and fuel used in works vessels and construction plants, and with implementation of precautionary measures, unacceptable impacts on marine ecological resources, including coral and benthic communities, Green Turtles, FP and the potential South Lamma Marine Park, due to accidental spillage or leakage of fuel/ chemicals are not expected.
The mitigation
measures designed to reduce impacts to water quality to acceptable levels and
complying with WQOs during construction and operation activities of the Project
are also expected to mitigate impacts to marine ecological resources, FP, Green
Turtles and the potential South Lamma Marine Park. Other mitigation and precautionary measures
designed to reduce impacts include site selection to avoid impacts to
ecologically sensitive habitats as far as practicable, proper planning and
design of the CMPs, control of work rates for dredging, backfilling and
capping, briefing to vessel operators and the use of predefined and regular
routes. With the implementation of
mitigation and precautionary measures during construction and operation
activities of the Project, potential impacts on marine ecological resources
will be further minimised.
Potential sources of impacts to fisheries
resources and fishing operations arising from the Project may occur during both
construction (dredging) and operation (backfilling and capping) activities. The construction and operation activities are
expected to result in a temporary loss of access to potential fishing ground of
up to 120 ha within the Key Area at any one time. It should be noted that only a relatively small number of works vessels will occupy the active
CMP areas, and the frequency/ trip of works vessels would also be relatively
low in general depending on the sediment disposal demand. It is expected that the disturbance to fisheries habitats will be temporary at
discrete work locations of the active CMPs.
Once dredging, backfilling and capping works for a CMP of the Project
are completed, the seabed and hydrodynamic regime is expected to restore to
their original condition. Recolonisation
of benthos is expected to occur at the capped pits and the habitats are
expected to return to pre-dredged conditions. Considering
the temporary and reversible nature of the disturbance, small extent of the
area affected at any one time which is of low to moderate fisheries production
despite the moderate to high level of fishing operation, impacts are considered to be of minor to
moderate significance and unacceptable impacts on fisheries resources, habitats and
fishing activities are not expected.
The water quality
modelling results have indicated that predicted levels of SS, DO, contaminant and
nutrient concentrations as a result of dredging, backfilling and capping works
of this Project are anticipated to be in compliance with the relevant
assessment criteria. Impacts are considered to be of minor
significance. Unacceptable indirect
water quality impacts from sediment release on fisheries resources, habitats (including spawning
ground and nursery area) and fisheries sensitive receivers are not
expected to occur.
The underwater sound generated by a small increase in vessel activity
associated with the construction and operation of this Project is not
anticipated to result in unacceptable impacts on fisheries resources in the
Assessment Area.
The construction and operation of the Project have been designed to
reduce potential impacts on water quality which will, in turn, reduce impacts
on fisheries resources. Water quality mitigation measures (e.g.
deployment of cage-type silt curtain during dredging works by grab dredgers,
good site practices) will be implemented to further avoid/reduce potential
impacts. Safety / precautionary measures
such as issuance of Marine Department Notice or other notifications is expected
to reduce the risk of collision of increased marine traffic and fishing vessels
to within acceptable levels. During
construction and operation of the CMPs, works area will be established within
and in the vicinity of the active CMP(s) within Key Area only
to minimize the actual extent of fisheries habitats and fishing ground affected
at any one time.
During construction and operation of the Project, the main activities that generate wastes will be the marine dredging of the seabed for the formation of the proposed CMPs. The typical waste types associated with the construction and operation activities include dredged marine sediment from the formation of the proposed CMPs, chemical waste from maintenance of plant and equipment (e.g. dredgers), and general refuse from marine-based workforce.
It is estimated that about 24 Mm3 in situ volumes of uncontaminated sediment will be dredged under the Project. It is expected the dredged sediments would require Type 1 open sea disposal. Possible on-site reuse will also be explored to dispose of the dredged sediments within the WL Facility as capping materials when any CMP of the WL Facility reached its capacity in receiving contaminated sediments. Generation of other wastes, including chemical waste, and general refuse are anticipated to be small. With the implementation of the mitigation measures recommended, no adverse environmental impacts, and hazards from storage, handling, collection, transport and disposal of these wastes are expected.
During dredging works of the Project, site audits will be undertaken by the Project Proponent and the Contractor regularly to determine if wastes are being managed in accordance with the recommended good site practices in this EIA Report. Waste monitoring and audit programme for the operation activities of the Project will not be required. Adverse environmental impacts arising from the management and disposal of waste during the construction and operation activities of the Project are not anticipated.
The desktop review supplemented with the results of geophysical survey conducted for the Project concluded that there are no sites of archaeological potential in the Key Area for potential CMP development for the Project. Further marine archaeological investigations are considered not necessary. No marine archaeological impact is identified during the Project construction and operation. No marine archaeological mitigation measure is required.
Loss of contaminated
sediment will occur during disposal activities, and as the area serves as
fishing grounds, seafood originated within and in the vicinity of the Study
Area where the CMPs are located could bioaccumulate contaminants and in turn
represents a potential hazard to human health by way of ingestion of organisms
with contaminant residues. The
carcinogenic risk assessment has indicated that the lifetime risks associated
with consumption of seafood are below the acceptability criterion for both the
WL Facility and the reference areas.
Results of the hazard (i.e. non-carcinogenic risk) assessment indicated
that risks associated with consumption of seafood were low for both the WL and
reference areas.
The major construction activities of the Project involve dredging of marine sediment to form CMPs. Dredging activities are marine based and thus dust emissions from the dredged sediment would be minimal. The dredged marine sediment will also be transported away from the Project site immediately after excavated. Adverse fugitive dust impact during construction phase is not anticipated. Considering the transient nature of any potential odour emissions, the large separation distance between the Project site and the identified ASRs (more than 2.5 km apart), sufficient separation distance between the vessel routes and ASRs along the vessel routes, as well as between the sediment disposal facilities (SDFs)/ CMPs and nearby ASRs (more than 500 m apart), adverse odour impact during construction phase is not expected. In view of the limited number of vessel trips per day, the sufficient separation distance from the ASRs, and the transient nature of the marine emissions, adverse air quality impact due to marine emissions during the construction phase of the Project is not anticipated. Air quality monitoring is considered not necessary for the construction phase of the Project. Regular site audits are recommended to check implementation of the specific mitigation measures throughout the construction phase.
The major operation
activities of the Project involve disposal of contaminated sediment in the
formed CMPs (i.e. backfilling) and capping of the exhausted CMPs by
uncontaminated sediment up to the original seabed level. As the contaminated / uncontaminated sediment
in transportation to the formed CMPs for backfilling and capping will be
generally wet before its disposal, adverse fugitive dust impact during
operation phase is not anticipated.
Considering the transient nature of any potential odour emissions, the large separation distance between the Project site and the
identified ASRs (more than 2.5 km apart), sufficient separation distance between the
vessel routes and ASRs along the vessel routes, adverse odour impact during operation phase is not expected. In view of the limited number of vessel trips
per day, the sufficient separation distance from the ASRs, and the transient
nature of the marine emissions, adverse air quality impact during the operation
phase of the Project is not anticipated.
Air quality monitoring is considered not
necessary for the operation phase of the Project. Regular site audits are recommended to check
implementation of the specific mitigation measures throughout the operation phase.
No existing or
planned NSR was identified within the Assessment Area for the Project. Since
the nearest NSR is located at least 2.8 km away from the Project site,
quantitative noise assessment for the construction and operation of the Project
is considered not necessary. Due to
large separation distance, adverse noise impact associated with the
construction and operation of the Project is not anticipated.
Mitigation measures and noise monitoring are therefore
considered not necessary during both the construction and operation phases of
the Project.
A summary of the environmental impacts is presented in Table 5.1. The EIA Study of the Project has been demonstrated to comply with the EIAO-TM requirements. Actual impacts during the construction works will be monitored through a detailed EM&A programme. Full details of the programme are presented in the EM&A Manual associated with the EIA Report. This programme will provide management actions and supplemental mitigation measures to be employed should any impacts arise, thereby ensuring the environmental acceptability of the construction and operation of this Project.
Marine water quality monitoring at selected WSRs will be necessary to assess the effectiveness of measures implemented to mitigate potential construction and operation impacts for dredging, backfilling and capping of CMPs. Sediment quality monitoring is also recommended for backfilling of the CMPs.
A benthic recolonisation monitoring programme is recommended to verify the expected recolonisation of the natural benthic assemblage on the capped CMPs.
Monitoring of fisheries resources and biomonitoring programme are recommended to address stakeholders’ concerns on the level of fisheries resources and contamination of seafood in the vicinity of the Project.
During construction and operation of the Project, regular site inspections and audits will be conducted to confirm the effective and timely implementation of the recommended mitigation measures. Regular waste audits will be conducted to determine if wastes are being managed in accordance with the recommended good site practices.
Table 5.1 Summary of Environmental Impacts
Sensitive Receivers/ Assessment Points |
Relevant Standards and Criteria |
Results of Impact Predictions |
Extents of Exceedances Predicted |
Impact Avoidance Measures Considered |
Mitigation Measures Proposed |
Residual Impacts (After Mitigation) |
Water Quality |
||||||
Water Sensitive Receivers (WSRs) within: ■
Southern WCZ ■
Western Buffer WCZ ■
Victoria Harbour
WCZ |
■
Annexes 6 and 14 of the EIAO-TM ■
Water Pollution Control Ordinance ■
Technical Memorandum for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters ■
Practice Note for Professional Persons, Construction Site Drainage ■
WQOs for: o
Southern WCZ o
Western Buffer WCZ o
Victoria Harbour WCZ |
With implementation of mitigation measures,
potential impacts due to construction and operation activities of CMPs: ■
Changes in water quality due to
construction and operation activities of CMPs - SS dispersion and
sedimentation; DO depletion; release of sediment-bounded contaminants;
release of sediment-bounded nutrients - No unacceptable impacts ■
Marine Vessel Discharges - No unacceptable
impacts ■
Changes in Flow Regime - No unacceptable
impacts |
No |
■
Location of the Project is selected to
avoid existing, proposed and potential marine parks as
far as practicable ■
Adoption of
appropriate work rates for dredging/ backfilling/ capping works |
■
Cage-type silt curtain will be installed
around closed grab to control sediment loss from grab dredging ■
No overflow is permitted from TSHD. ■
The LMOB system of TSHD will only be in
operation at the beginning and end of the dredging cycle when the drag head
is being lowered and raised. ■
Dredging should be conducted by either one
TSHD at a maximum rate of 256,200 m3/week or no more than two grab
dredgers at a total maximum rate of 100,000 m3/week ■
Maximum rate of backfilling is 26,700 m3/day ■
Maximum rate of capping is 26,700 m3/day ■
Standard measures and good
site practices |
No
adverse residual impacts are anticipated. |
Marine Ecology |
||||||
Marine Ecological Sensitive Receivers within: ■
Southern WCZ ■
Western Buffer WCZ ■
Victoria Harbour
WCZ |
■
Annexes 8 and 16 of the EIAO-TM ■
EIAO Guidance Notes No. 6/2010, 7/2010,
10/2010 and 11/2010 ■
Marine Parks Ordinance ■
Wild Animals Protection
Ordinance ■
Protection of Endangered
Species of Animals and Plants Ordinance (Cap. 586) ■
Town Planning Ordinance
(Cap. 131) ■
Hong Kong Planning
Standards and Guidelines Section 10 (HKPSG) ■
United Nations Convention
on Biological Diversity (CBD) ■
The Convention on
International Trade in Endangered Species of Wild Fauna and Flora of Wild
Fauna and Flora (CITES) ■
The International Union
for Conservation of Nature (IUCN) Red List of Threatened Species ■
Peoples’ Republic of
China (PRC) Regulations and Guidelines |
■
Ecological impacts to Marine Ecological
Resources (Excluding FP) o
Temporary habitat loss
and disturbance on coral and
benthic communities, and Green Turtles – Minor significance o
Underwater sound
from construction and operation activities on
marine invertebrates, Green Turtles, and potential South Lamma Marine Park – Minor significance o
Changes in water quality from
construction and operation activities on
coral and benthic
communities, Green Turtles, and potential South Lamma Marine Park – Minor
significance o
Increased marine traffic from construction and operation activities
on Green Turtles – Minor significance o
Effects of glare from light
sources of construction and operation activities on Green Turtles
– Minor
significance o
Accidental spillage/leakage of
fuels/ chemicals on coral and benthic communities, Green Turtles
and potential South Lamma Marine Park – Negligible significance ■
Ecological impacts to FP o
Temporary habitat loss and disturbance due
to construction and operation activities of the CMPs – Minor significance o
Underwater sound
from construction and operation activities – Minor
significance o
Increased marine
traffic from construction and operation activities – Minor
significance o
Changes in water quality from
construction and operation activities – Minor
significance o
Accidental spillage/leakage of
fuels/ chemicals – Negligible significance |
No |
■
Location of the Project is selected to
avoid ecologically sensitive habitats as far as practicable ■
Proper
planning and design of the CMPs, e.g. CMPs to be developed within Key Area,
CMPs to be constructed and operated sequentially and no more than three pits
will be active at any one time ■
Adoption of appropriate
work rates and mitigation measures for dredging, backfilling and capping to
confirm compliance with the assessment criteria at sensitive receivers and
control water quality impacts to within acceptable levels |
■
Water quality mitigation measures as stated
above. ■
Other precautionary measures to further reduce impacts: o
Vessel operators will be
required to control and manage all effluent from vessels. These kinds of wastewater shall be brought
back to port where possible and discharged at appropriate collection and
treatment system to prevent avoidable water quality impacts o
A policy of no dumping of
rubbish, food, oil, or chemicals will be strictly enforced o
Only well-maintained and
inspected vessels would be used to limit any potential discharges to the
marine environment o
Safe storage, handling
and disposal of chemicals and oils to prevent the release into the marine
environment o
Bunding of machinery
areas and availability of spill clean-up kits would be in place to
prevent spillage or leakage of fuel/chemical to reach the marine environment o
The vessel operators for
the construction activities of this Project will be required to use
predefined and regular routes, make use of designated fairways to access the
active CMPs, and would avoid traversing sensitive habitats such as existing
and proposed marine parks. This
measure will further serve to minimise disturbance to Green Turtles and FP
due to vessel movements o
The vessel operators
working on the construction activities of the Project will be given a
briefing, alerting them to the possible presence of FP in the active CMP
areas, and the guidelines for safe vessel operation in the presence of these
animals. The vessels will avoid using
high speed as far as possible. By
observing the guidelines, vessels will be operated in an appropriate manner
so that FP will not be subject to undue disturbance or harassment |
No adverse residual impacts are expected. |
Fisheries |
||||||
Fisheries Sensitive Receivers within: ■
Southern WCZ ■
Western Buffer WCZ ■
Victoria Harbour WCZ |
■
Annexes 9 and 17 of the EIAO-TM ■
Fisheries Protection Ordinance ■
Marine Fish Culture Ordinance ■
Water Pollution Control Ordinance |
■
Direct disturbances of fisheries habitat
and loss of access to fishing ground – Minor to
moderate significance ■
Perturbations to key
water quality parameters from marine construction and operation activities –
Minor significance ■
Underwater sound – Minor
significance |
No |
■
Relevant avoidance measures as detailed
above for the water quality and ecology aspects ■
Avoid areas of high
fisheries importance through site selection ■
Proper
planning and design of the CMPs, with phased implementation ■
Adoption of appropriate work
rates and mitigation measures for dredging, backfilling and capping to
confirm compliance with the assessment criteria at sensitive receivers and
control water quality impacts to within acceptable levels ■
Appropriate notification, communications,
site protection and marking would be adopted to reduce navigation risks with
fishing vessels |
■
Water quality mitigation measures as stated
above ■
Marine ecological mitigation measures as
stated above ■ Issuance
of Marine Department Notice or other notifications is expected to reduce the
risk of collision of increased marine traffic and fishing vessels to within
acceptable levels as
safety / precautionary measures ■
During construction and operation of the
CMPs, works area will be established within and in the vicinity of the active
CMP(s) within Key Area only to minimize the actual extent of fisheries
habitats and fishing ground affected at any one time |
No adverse residual fisheries impacts are
expected |
Waste |
||||||
Key Area identified for potential CMP
development under the Project |
■
Annexes 7 and 15 of the EIAO-TM ■
Waste Disposal Ordinance (WDO) ■
Waste Disposal (Chemical Waste) (General)
Regulation ■
Land (Miscellaneous Provisions) Ordinance ■
Public Health and Municipal Services
Ordinance - Public Cleansing and Prevention of Nuisances Regulation ■
Dumping at Sea Ordinance ■
Merchant Shipping (Prevention and Control
of Pollution) Ordinance |
■
Dredged marine sediment –
total about 24Mm3 (in situ volume) of Category L sediment ■
Chemical waste – a few
litres per month ■
General refuse – about
32.5 kg per day |
No |
■
On-site reuse to be explored to dispose the
dredged sediments within WL Facility as capping materials |
■
Standard measures and good site practices |
Adverse environmental impacts arising from the
management and disposal of waste are not anticipated |
Cultural Heritage |
||||||
Key Area identified for potential CMP
development under the Project |
■
Annexes 10 and 19 of the EIAO-TM ■
Antiquities and Monuments Ordinance (AM
Ordinance) ■
Hong Kong Planning Standards and Guidelines
■
Guidelines for Marine Archaeological
Investigation (MAI) |
■
No marine archaeological potential within
the Project’s impact area – No marine archaeological impact is expected |
No |
■
No marine archaeological resources
identified |
■
No mitigation measure is required |
No adverse residual impacts are expected |
Hazard to Health |
||||||
Members of various populations of Hong Kong |
■
Guidelines of the US Environmental
Protection Agency (EPA) |
■
Risks associated with
exposure to carcinogens – lifetime
risks are below the acceptability criterion ■
Hazards to human health
associated with exposure to non-carcinogens – risks were low |
No |
■
Relevant avoidance measures as detailed
above for the water quality, ecology, and fisheries aspects ■
Adoption of appropriate work
rates and mitigation measures for dredging, backfilling and capping to
confirm compliance with the assessment criteria at sensitive receivers and
control water quality impacts to within acceptable levels |
■
No mitigation measure is required |
No adverse residual impacts are expected |
Air Quality |
||||||
Air Sensitive Receivers (ASRs) within 500m from
the Key Area |
■
Annex 4 of EIAO-TM ■
Air Pollution Control Ordinance (APCO) ■
Air Quality Objective (AQO) |
■
Adverse fugitive dust or odour impact during
construction and operation phase is not anticipated ■
Adverse air quality impact due to marine
emissions during the construction and operation phase is not anticipated |
No |
Project site located in remote locations avoiding
impacts to ASRs |
■
Implement dust control measures stipulated
in the Air Pollution Control
(Construction Dust) Regulation (Cap. 311R) during the construction phase
where appropriate. ■
Requirements stipulated in the Air
Pollution Control (Fuel Restriction) Regulations, Air Pollution Control
(Marine Light Diesel) Regulation, Air Pollution Control (Fuel for Vessels)
Regulation and Air Pollution Control (Non-road Mobile Machinery) (Emission)
Regulation will be followed. ■
Ultra-low sulphur diesel (ULSD) will be
used for all PMEs, as defined as diesel fuel containing not more than 0.005%
sulphur by weight) as stipulated in Environment, Transport and Works Bureau
Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on
Construction Sites ■
The engine of the PMEs during idling shall
be switched off ■
Regular maintenance of PMEs shall be
conducted to prevent black smoke emission ■
All PMEs shall comply with the prescribed
emission standards and approved with a proper label by EPD ■
Number of trips would be monitored and
vessel travelling routes would be kept away from the ASRs as far as possible ■
Loading of the dredged sediment to the TSHD
and hopper barges should be controlled to avoid splashing and overflowing of
the sediment slurry to the surrounding water ■
Dredged sediment on board the TSHD and
hopper barges should be properly covered as far as practicable to minimise
the exposed area and potential fugitive dust and odour emissions during its
transportation. If the dredged
sediment is found to be malodorous, it shall be removed from site as soon as
possible ■
Dredged sediment on board the TSHD and
hopper barges should be transferred to disposal sites at the SDFs/ CMPs as
capping materials as soon as possible to minimise potential fugitive dust and
odour emissions |
No adverse residual impacts are expected |
Noise |
||||||
Noise Sensitive Receivers (NSRs) within 300m from
the Key Area |
■
Annexes 5 and 13 of EIAO-TM ■
Noise Control Ordinance (NCO) ■
Technical Memorandum on Noise from
Construction Work other than Percussive Piling
(GW-TM) ■
Technical Memorandum on Noise From Places
Other than Domestic Premises, Public Places or Construction Sites (IND-TM) |
Adverse noise impacts are not expected
during both construction and operation phases of the Project |
No |
Project site located in remote locations avoiding
impacts to NSRs |
■
Noise mitigation measures are not required
for the construction and operation phases |
No adverse residual impacts are expected |
This EIA
Study has critically assessed the overall acceptability of the environmental
impacts likely to arise from the construction and operation activities of the
Project. It has demonstrated the acceptability of any residual impacts
from this Project and the protection of the population and the environmentally
sensitive resources. The EIA Study concluded that, with the
implementation of the recommended mitigation measures, the Project would be
environmentally acceptable and in compliance with the relevant assessment
standards/criteria of the EIAO-TM. Where appropriate,
EM&A mechanisms have been recommended to verify the accuracy of the EIA
predictions to ensure the effectiveness of the recommended mitigation measures.
While non-dredged methods are encouraged for construction of
infrastructure projects in Hong Kong, dredging is
necessary for essential maintenance works for harbours, fairways, anchorage or
drainage channels. The existing CMPs at ESC are anticipated to
be exhausted by 2027 and they cannot be expanded further due to the limited
usable seabed in the vicinity. The
implementation of this Project can allow an
uninterrupted disposal service to be maintained and flood protection works,
harbour maintenance dredging works and the implementation of the on-going and
planned building/ infrastructure projects will be able to proceed.
([1])
Agreement No. CE 105/98 – Strategic Assessment and
Site Selection Study for Contaminated Mud Disposal
([2])
Agreement No. CE 12/2002 (EP) – Detailed Site Selection
Study for a Proposed Contaminated Mud Disposal Facility within the Airport
East/East of Sha Chau Area