Sha Tin Water Treatment Works
LPG Storage Installation
Plate 11.1 Location of the LPG Compound
Objectives
(a) Identify hazardous scenarios associated with the on-site transport, storage and use of gas as defined in the Gas Safety Ordinance (Cap. 51) at the LPG Storage Installation and then determine a set of relevant scenarios to be included in a Quantitative Risk Assessment (QRA);
(b) Execute a QRA of the set of hazardous scenarios determined in (a), expressing population risks in both individual and societal terms;
(c) Compare individual and societal risks with the criteria for evaluating hazard to life as stipulated in Annex 4 of the TM; and
(d) Identify and assess practicable and cost-effective risk mitigation measures.
EIAO TM Risk Criteria
Plate 11.2 Societal Risk Guidelines
(a) Data / Information Collection and Update: collect relevant data / information that is essential for the hazard assessment;
(b) Hazard Identification: identify credible set of hazardous scenarios associated with the operation of the LPG Compound;
(c) Frequency Estimation: estimate the frequencies of each hazardous event leading to fatalities based on the collected data and operation data for LPG Compound with the support of justifications from reviewing historical accident data and previous hazard assessments;
(d) Consequence Analysis: analyze the consequences of the identified hazardous scenarios;
(e) Risk Assessment and Evaluation: evaluate the risks associated with the identified hazardous scenarios. The evaluated risks will be compared with HKRG to determine their acceptability. Where necessary, risk mitigation measures will be identified and assessed to comply with the “as low as reasonably practicable” (ALARP) principle used in the HKRG; and
(f) Identification of Mitigation Measures: review the recommended risk mitigation measures from previous studies. Practicable and cost-effective risk mitigation measures will be identified and assessed as necessary. The risk outcomes of the mitigated case will then be reassessed to determine the level of risk reduction.
· Year 2033 without Project (Base case) – The risk imposed by the LPG Compound to the planned population in 2033, in the absence of the Project.
· Year 2033 with Project (Construction phase) – The risk imposed by the LPG Compound to the planned population in 2033. This also accounts for the presence of the construction workers operating in close vicinity of the LPG Compound and any potential impacts associated with the construction activities.
· Year 2041 (Operation phase) – The risk imposed by the LPG Compound to the planned population in 2041 upon completion of the Project.
Study Area
Description of the LPG Compound
LPG Storage
LPG Delivery and Transfer
Population
Plate 11.3 Location of Population Groups in relation to LPG Compound
Proposed Road Works for the Project
· Site clearance
· Slope formation works
· Noise barrier & pipe pile wall/ L-shape retaining wall installation
· Roadworks, drainage, utilities, water mains
· Landscape works for slope
Land and Building Population
(a) According to 2016-based TPEDM data, a negative growth rate of -0.27% is observed for the average domestic household size in Sha Tin District (i.e. PDZ 209) from 2016 to 2041, which decreases from 3.26 to 3.05. To be conservative, the average domestic household size in the future assessment years are assumed to remain the same as those in Year 2016 (i.e. 3.26).
(b) For Pok Oi Hospital Chan Kai Memorial College, the number of students was estimated based on the maximum capacity per classroom (i.e. max. capacity of 45 students for 26 classrooms)[1], while the number of staff recorded as of year 2020 is 56[2].
(c) For Anfield School, the number of students was estimated based on the maximum capacity per classroom (i.e. max. capacity of 25 students for 12 classrooms and max. capacity of 15 for 1 classrooms)[3], while the number of staff is estimated as 47[4].
(d) School populations was estimated based on the maximum student intake per class. Furthermore, it is anticipated that majority of students attending Anfield School and Pok Oi Hospital Chan Kai Memorial College reside within Sha Tin District. According to 2016-based TPEDM data, a negative growth rate for residential population is generally observed for PDZ 209 and the surrounding populations (i.e. PDZ 205, 206, 208, 210, 211, 384 and 385). As such, the changes in school populations is expected to be minimal.
Occupancies of different population groups at different time modes are summarised in Table 11.5. In general,
(e) The weekday and weekend night-time population are assumed to be 100% of the maximum residential population.
(f) The weekday and weekend daytime population are assumed to be 50% and 70% of the residential population, respectively.
(g) The weekday daytime population is assumed to be 100% of the maximum school population.
(h) An average of 5% outdoor populations is considered for both residential and school population group.
(i) For the proposed Project works area, the weekday and weekend daytime population are assumed to be 100% and 50%, respectively and 100% outdoor population is considered.
Table 11.1 Land and Building Population Data
ID |
Description |
Population |
|
||
Year 2033 – Base Case [Note 1, 2] |
Year 2033 – Construction Phase |
Year 2041 – Operation Phase |
|
||
1 |
Pine Court, Worldwide Gardens |
98 |
98 |
98 |
|
2 |
Hibiscus Court, Worldwide Gardens |
261 |
261 |
261 |
|
3 |
Lily Court, Worldwide Gardens |
261 |
261 |
261 |
|
4 |
Laurel Court, Worldwide Gardens |
274 |
274 |
274 |
|
5 |
Bauhinia Court, Worldwide Gardens |
137 |
137 |
137 |
|
6 |
Anfield School |
362 |
362 |
362 |
|
7 |
Begonia Court, Worldwide Gardens |
150 |
150 |
150 |
|
8 |
Cypress Court, Worldwide Gardens |
150 |
150 |
150 |
|
9 |
Pok Oi Hospital Chan Kai Memorial College |
1226 |
1226 |
1226 |
|
10 |
Sheung Sum House, Lung Hang Estate |
||||
10a |
Low Block |
1109 |
1109 |
1109 |
|
10b |
High Block |
1275 |
1275 |
1275 |
|
11 |
Wai Sum House, Lung Hang Estate |
||||
11a |
Low Block |
1109 |
1109 |
1109 |
|
11b |
High Block |
1275 |
1275 |
1275 |
|
12 |
Proposed Project Works Area [Note 3] |
0 |
186 |
0 |
|
Note 1: Populations for residential were estimated based on domestic household size in 2016-based TPEDM.
Note 2: School population for Pok Oi Hospital Chan Kai Memorial College and Anfield School was estimated based on the school information from the Education Bureau and school website.
Note 3: It was assumed that there will be a maximum of 186 construction workers in the nearby construction activities during the construction phase.
Road Population
Table 11.2 Estimated Road Population (Year 2033)
Population ID |
Description |
Maximum Population [Note 1] |
|
Daytime |
Night-time |
||
R1 |
Lion Rock Tunnel Road |
895 |
431 |
R2 |
Hung Mui Kuk Road |
711 |
341 |
R3 |
Chung Pak Road & Lung Pak Street |
10 |
8 |
R4 |
Fu Kin Street |
11 |
9 |
R5 |
Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
20 |
15 |
R6 |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
8 |
8 |
Note 1: Road population was estimated based on Traffic Impact Assessment forecasted for Year 2034. This was conservatively applied for the assessed scenarios (i.e. Year 2033 – Base Case and Year 2033 – Construction Phase).
Table 11.3 Estimated Road Population (Year 2041)
Population ID |
Description |
Maximum Population [Note 1] |
|
Daytime |
Night-time |
||
R1 |
Lion Rock Tunnel Road |
901 |
432 |
R2 |
Hung Mui Kuk Road |
711 |
341 |
R3 |
Chung Pak Road & Lung Pak Street |
10 |
8 |
R4 |
Fu Kin Street |
11 |
9 |
R5 |
Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
20 |
15 |
R6 |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
8 |
8 |
Note 1: Road population was estimated based on Traffic Impact Assessment forecasted for Year 2041 and this was applied for Year 2041 – Operation Phase.
Time Modes and Occupancies of Population Groups
Table 11.4 Definitions of Time Modes
Time Period |
Definition |
Proportion of Time |
Weekday Day |
Mon-Fri, 7am-7pm |
35.71% |
Weekday Night |
Mon-Fri, 7pm – 7am |
35.71% |
Weekend Day |
Sat-Sun, 7am-7pm |
14.29% |
Weekend Night |
Sat-Sun, 7pm – 7am |
14.29% |
Table 11.5 Occupancies of Population Groups at Different Time Modes
Population Group |
Percentage of Occupancy at Different Time Modes |
Indoor Ratio |
|||
Weekday (Day) |
Weekday (Night) |
Weekend (Day) |
Weekend (Night) |
||
Residential |
50% |
100% |
70% |
100% |
95% |
School |
100% |
0% |
0% |
0% |
95% |
Proposed Project Works Area |
100% |
0% |
50% |
0% |
0% |
Lion Rock Tunnel Road/ Hung Mui Kuk Road |
100% |
50% |
100% |
50% |
0% |
Chung Pak Road & Lung Pak Street/ Fu Kin Street/ Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
100% |
80% |
100% |
80% |
0% |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
100% |
100% |
100% |
100% |
0% |
Table 11.6 Stability Category-Wind Speed Frequencies at Sha Tin Station
Daytime |
|||||||
Wind Speed (m/s) |
A |
B |
C |
D |
E |
F |
Total (%) |
0.0-1.9 |
10.41 |
6.96 |
0.00 |
9.47 |
0.00 |
11.99 |
38.83 |
2.0-3.9 |
7.69 |
18.85 |
8.33 |
9.84 |
4.38 |
0.73 |
49.82 |
4.0-5.9 |
0.00 |
4.75 |
3.38 |
2.31 |
0.11 |
0.00 |
10.55 |
6.0-7.9 |
0.00 |
0.00 |
0.21 |
0.57 |
0.00 |
0.00 |
0.78 |
Over 8.0 |
0.00 |
0.00 |
0.02 |
0.00 |
0.00 |
0.00 |
0.02 |
All (%) |
18.10 |
30.56 |
11.94 |
22.19 |
4.49 |
12.72 |
100.00 |
Night-time |
|||||||
Wind Speed (m/s) |
A |
B |
C |
D |
E |
F |
Total (%) |
0.0-1.9 |
0.00 |
0.00 |
0.00 |
2.24 |
0.00 |
63.72 |
65.96 |
2.0-3.9 |
0.00 |
0.00 |
0.00 |
8.84 |
17.21 |
3.26 |
29.31 |
4.0-5.9 |
0.00 |
0.00 |
0.00 |
4.25 |
0.34 |
0.00 |
4.59 |
6.0-7.9 |
0.00 |
0.00 |
0.00 |
0.14 |
0.00 |
0.00 |
0.14 |
Over 8.0 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
All (%) |
0.00 |
0.00 |
0.00 |
15.47 |
17.55 |
66.98 |
100.00 |
Table 11.7 Weather Class-Wind Direction Frequencies at Sha Tin Station
Direction |
2B |
1D |
3D |
6D |
2E |
1F |
Total (%) |
0 – 30 |
5.21 |
1.05 |
2.52 |
0.00 |
1.78 |
1.21 |
11.77 |
30 – 60 |
13.45 |
1.05 |
4.47 |
0.05 |
1.28 |
1.07 |
21.37 |
60 – 90 |
5.66 |
1.31 |
3.14 |
0.12 |
1.05 |
1.69 |
12.97 |
90 – 120 |
6.70 |
1.02 |
4.11 |
0.00 |
1.59 |
1.31 |
14.73 |
120 – 150 |
5.23 |
0.40 |
2.81 |
0.02 |
0.86 |
0.38 |
9.70 |
150 – 180 |
1.12 |
0.14 |
0.67 |
0.00 |
0.17 |
0.21 |
2.31 |
180 – 210 |
1.26 |
0.24 |
0.78 |
0.00 |
0.31 |
0.52 |
3.11 |
210 – 240 |
7.42 |
0.29 |
6.51 |
1.50 |
0.78 |
0.43 |
16.93 |
240 – 270 |
2.54 |
0.24 |
1.66 |
0.19 |
0.38 |
0.21 |
5.22 |
270 – 300 |
0.26 |
0.10 |
0.07 |
0.00 |
0.00 |
0.10 |
0.53 |
300 – 330 |
0.02 |
0.05 |
0.00 |
0.00 |
0.00 |
0.24 |
0.31 |
330 – 360 |
0.45 |
0.19 |
0.07 |
0.00 |
0.05 |
0.29 |
1.05 |
All (%) |
49.32 |
6.08 |
26.81 |
1.88 |
8.25 |
7.66 |
100.00 |
Night-time |
||||||
Direction |
1D |
4D |
6D |
2E |
1F |
Total (%) |
0 – 30 |
0.50 |
1.09 |
0.00 |
5.04 |
6.22 |
12.85 |
30 – 60 |
0.30 |
1.86 |
0.02 |
5.59 |
6.10 |
13.87 |
60 – 90 |
0.17 |
1.99 |
0.02 |
5.14 |
8.86 |
16.18 |
90 – 120 |
0.15 |
1.34 |
0.00 |
5.84 |
6.12 |
13.45 |
120 – 150 |
0.10 |
0.82 |
0.00 |
3.06 |
4.80 |
8.78 |
150 – 180 |
0.00 |
0.30 |
0.05 |
0.84 |
3.80 |
4.99 |
180 – 210 |
0.02 |
0.12 |
0.00 |
0.92 |
3.31 |
4.37 |
210 – 240 |
0.00 |
4.90 |
0.22 |
5.34 |
2.29 |
12.75 |
240 – 270 |
0.05 |
2.16 |
0.02 |
2.34 |
1.64 |
6.21 |
270 – 300 |
0.05 |
0.00 |
0.00 |
0.15 |
1.69 |
1.89 |
300 – 330 |
0.07 |
0.00 |
0.00 |
0.02 |
1.37 |
1.46 |
330 – 360 |
0.17 |
0.00 |
0.00 |
0.32 |
2.71 |
3.20 |
All (%) |
1.58 |
14.58 |
0.33 |
34.60 |
48.91 |
100.00 |
Spontaneous Failures
Failure of Storage Vessel
(a) Spontaneous failure due to corrosion, fatigue, etc.
(b) Overfilling
(c) Earthquake
Failure of Road Tanker
Guillotine Failure of Liquid Filling Line to Storage Vessel
Guillotine Failure of Liquid Supply Line to Vaporizers
Failure of Vaporizers
Guillotine Failure of Liquid Line from Tanker Pipe to Loading Hose
Failure of Flexible Hose
(a) Fatigue
(b) Hose misconnection
(c) Hose disconnection during loading or unloading process
(d) Operator / driver error
Loading / Unloading Failures
(a) Hose misconnection and disconnection error
(b) Tanker drive away error
(c) Road tanker collision
(d) Vehicle impact with road tanker during unloading
(e) Storage vessel overfilling
(f) Over-pressurization of pipework.
Hose Misconnection and Disconnection Error
Tanker Drive away Error
Road Tanker Collision
Vehicle Impact with Road Tanker during Unloading
Storage Vessel Overfilling
Over-pressurization of Pipework
External Events
(a) Earthquake
(b) Aircraft crash
(c) Landslide
(d) Severe environmental event such as typhoon or tsunami and subsequent outcomes such as falling trees
(e) Subsidence
(f) Lightning
(g) High wind loading
Earthquake
Aircraft Crash
Landslide
Severe environmental event
Subsidence
Lightning and High wind loading
Safety Features
(a) Non-return valve
(b) Excess flow valve
(c) Emergency shutdown system
(d) Breakaway coupling
(e) Manual isolation system
(f) Double-check filler valve
(g) Relief valve
Non-return Valve
Excess Flow Valve
Emergency Shutdown System
Breakaway Coupling
Manual Isolation System
Double-check Filler Valve
Relief Valve
Human Error
Fire Protection / Fighting System
Chartek Coating
Water Spray System
Fire Service
Escalation
(a) Cold partial failure of road tanker
(b) Guillotine failure of liquid filling line to vessel
(c) Guillotine failure of liquid supply line to vaporizer
(d) Flexible hose during loading to storage vessel
(e) Liquid line from tanker to loading hose
(f) Vaporizer failure
Summary
Table 11.8 Identified Failure Case of the LPG Compound
Failure Types |
Failure Cases |
Spontaneous Failure of Pressurized LPG Equipment |
· Storage Vessel Failure · Road Tanker Failure · Pipework Failure · Hose Failure · Vaporizer Failure |
External Event |
· Earthquake MMI VIII · Aircraft Crash |
Delivery Failure |
· Hose Misconnection Error · Hose Disconnection Error · Tanker Drive-away Error · Road Tanker Collision during Unloading · Vehicle Impact with Road Tanker during Unloading · Storage Vessel Overfilling · Over-pressurization of pipework |
Safety System Failure |
· Pressure Relief Valve Failure · Non-return Valve Failure · Excess Flow Valve Failure · Emergency Shutdown System Failure · Double-check Filler Valve Failure · Breakaway Coupling Failure · Human Error · Manual Isolation Valve Failure |
Fire Fighting System Failure |
· Fire Services Failure · Chartek Coating Failure |
(a) Hazard identification and selection of the “Significant Failure Events”
(b) Construction of fault tree
(c) Quantitative evaluation of the fault tree
Frequency Estimation
Spontaneous Failure of Pressurized LPG Equipment
Storage Vessel Failure
Road Tanker Failure
Pipework Failure
Vaporizer Failure
Hose Failure
External Events
Earthquake MMI VIII
Aircraft Crash
Loading / Unloading Failures
Hose Misconnection Error
Hose Disconnection Error
Tanker Drive-away Error
Tanker Collision during Unloading
Vehicle Impact with Road Tanker during Unloading
Overfilling of Storage Vessel
Over-pressurization of Pipework
Safety System Failure
Pressure Relief Valve Failure
Pump Overpressure Protection System
Non-return Valve Failure
Excess Flow Valve Failure
Emergency Shutdown System Failure
Breakaway Coupling Failure
Double-check Filler Valve Failure
Manual Isolation Valve
Human error
Fire Fighting System Failure
Water Spray System Failure
Failure of Fire Services
Chartek Coating Failure
Table 11.9 Summary of Identified Failure Cases and Their Associated Failure Rates
Failure Cases |
Failure Rates |
Reference Source |
Spontaneous Failure of Pressurized LPG Equipment |
||
Catastrophic Failure of Storage Vessel |
1.8×10-7 per vessel year |
Reference [4] |
Partial Failure of Storage Vessel |
5.0×10-6 per vessel year |
Reference [4] |
Catastrophic Failure of Road Tanker |
2.0×10-6 per tanker year |
Reference [4] |
Partial Failure of Road Tanker |
5.0×10-6 per tanker year |
Reference [4] |
Guillotine Failure of Pipework |
1.0×10-6 per meter per year |
Reference [4] |
Vaporizer Failure |
1.0×10-6 per meter per year |
Reference [4] |
Hose Failure |
1.8×10-7 per transfer or 9.0×10-8 per hour |
Reference [4] |
External Event |
||
Earthquake MMI VIII |
1.0×10-5 per year |
Reference [4] |
Aircraft Crash |
2.87×10-10 per year |
Refer to Section 11.7.15 to 11.7.17 |
LPG Loading Failure |
||
Hose Misconnection Failure |
3.0×10-5 per operation |
Reference [4] |
Hose Disconnection Failure |
2.0×10-6 per operation |
Reference [4] |
Tanker Drive-away Error |
4.0×10-6 per operation |
Reference [4] |
Road Tanker Collision |
1.5×10-4 per operation |
Reference [4] |
Vehicle Impact into Tanker During Unloading |
1.0×10-8 per operation |
Reference [4] |
Storage Vessel Overfilling |
2.0×10-2 per operation |
Reference [4] |
Safety Features Failure |
||
Pressure Relief Valve Failure |
1.0×10-4 per demand |
Reference [4] based on ESD system |
Failure of Pump Over-pressurization Protection |
1.0×10-4 per demand |
Based on pressure relief valve |
Non-return Valve Failure |
0.013 per demand |
Reference [4] |
Excess Flow Valve Failure |
1.00 per demand for liquid filling line and flexible hose 0.13 per demand for line to vaporizer |
Reference [4] |
Manual Isolation Valve Failure |
0.5 per demand |
Reference [4] |
Emergency Shutdown System Failure |
1.0×10-4 per demand |
Reference [4] |
Breakaway Coupling Failure |
0.013 per demand for tanker
|
Reference [4] Conservative estimate, based on breakaway coupling for road tanker |
Double-check Filler Valve Failure |
2.6×10-3 per demand |
Reference [4] |
Operator fails to rectify problem |
1.5×10-3 per demand |
Reference [3] |
Fire Protection / Fighting System Failure |
||
Water Spray System Failure |
1.00 per demand |
There is no water spray system |
Failure of Fire Services |
0.5 per demand |
Reference [4] |
Chartek Coating Failure |
0.1 |
Reference [4] |
Failure Probability |
||
Catastrophic failure of vessel provided over-pressurization |
0.01 |
Reference [3] |
Partial failure of vessel provided over-pressurization |
0.1 |
Reference [3]; 10 times of catastrophic failure |
Probability of catastrophic / guillotine failure due to aircraft crash [Note 1] |
1 |
Assume 100% failure leading to rupture / guillotine failure |
Probability of partial failure due to aircraft crash [Note 1] |
0 |
Assume 100% failure leading to rupture / guillotine failure |
Probability of equipment failure due to earthquake |
0.01 |
Reference [5] |
Probability of catastrophic / partial failure in earthquake |
0.5 / 0.5 |
It is more likely that an earthquake leads to failure of pipeline connection rather than vessel failure while washed sand provides buffering effect to prevent vessel from damages. Pipeline failure has already been accounted in other hazardous events. Therefore, the 50:50 split is conservatively adopted in vessel failure events. |
Note 1: The probability of road tanker rupture and road tanker partial failure due to aircraft crash are considered as 1 and 0 respectively, which assumes only catastrophic failure of road tanker will be resulted in the event of aircraft crash. The probability for storage vessel failure due to aircraft crash will be significantly less as compared to other equipment since storage vessels are located underground. Hence, 0.01 and 0.09 are adopted for catastrophic and partial failure of storage vessels respectively.
Escalation
Fault Tree Analysis
Event Tree Analysis
Table 11.10 Event Outcome Frequencies of Significant LPG Releases
Ref |
Event Description |
Hole Size (mm) |
Outcome Event [Note 1] |
Event Frequency per year |
Outcome Probability |
Probability of Failure to isolate |
Total Outcome Frequency /year |
F1.1 |
Cold Catastrophic Failure of Storage Vessel 1 |
Rupture |
FBL |
4.10E-07 |
9.00E-01 |
1.00E+00 |
3.69E-07 |
F1.1 |
Cold Catastrophic Failure of Storage Vessel 1 |
Rupture |
VCE |
4.10E-07 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F1.1 |
Cold Catastrophic Failure of Storage Vessel 1 |
Rupture |
FFR |
4.10E-07 |
1.00E-01 |
1.00E+00 |
4.10E-08 |
F1.2 |
Cold Catastrophic Failure of Storage Vessel 2 |
Rupture |
FBL |
4.10E-07 |
9.00E-01 |
1.00E+00 |
3.69E-07 |
F1.2 |
Cold Catastrophic Failure of Storage Vessel 2 |
Rupture |
VCE |
4.10E-07 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F1.2 |
Cold Catastrophic Failure of Storage Vessel 2 |
Rupture |
FFR |
4.10E-07 |
1.00E-01 |
1.00E+00 |
4.10E-08 |
F2.1 |
Cold Partial Failure of Storage Vessel 1 |
25 |
JFI |
1.01E-05 |
5.00E-02 |
1.00E+00 |
5.03E-07 |
F2.1 |
Cold Partial Failure of Storage Vessel 1 |
25 |
BLEVE |
1.01E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2.1 |
Cold Partial Failure of Storage Vessel 1 |
25 |
VCE |
1.01E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2.1 |
Cold Partial Failure of Storage Vessel 1 |
25 |
FFR |
1.01E-05 |
9.50E-01 |
1.00E+00 |
9.55E-06 |
F2.2 |
Cold Partial Failure of Storage Vessel 2 |
25 |
JFI |
1.01E-05 |
5.00E-02 |
1.00E+00 |
5.03E-07 |
F2.2 |
Cold Partial Failure of Storage Vessel 2 |
25 |
BLEVE |
1.01E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2.2 |
Cold Partial Failure of Storage Vessel 2 |
25 |
VCE |
1.01E-05 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F2.2 |
Cold Partial Failure of Storage Vessel 2 |
25 |
FFR |
1.01E-05 |
9.50E-01 |
1.00E+00 |
9.55E-06 |
F3 |
Cold Catastrophic Failure of Road Tanker |
Rupture |
FBL |
6.89E-09 |
9.00E-01 |
1.00E+00 |
6.20E-09 |
F3 |
Cold Catastrophic Failure of Road Tanker |
Rupture |
VCE |
6.89E-09 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F3 |
Cold Catastrophic Failure of Road Tanker |
Rupture |
FFR |
6.89E-09 |
1.00E-01 |
1.00E+00 |
6.89E-10 |
F4 |
Cold Partial Failure of Road Tanker |
25 |
JFI |
1.75E-08 |
4.75E-02 |
1.00E+00 |
8.30E-10 |
F4 |
Cold Partial Failure of Road Tanker |
25 |
BLEVE |
1.75E-08 |
1.20E-02 |
1.00E+00 |
2.10E-10 |
F4 |
Cold Partial Failure of Road Tanker |
25 |
VCE |
1.75E-08 |
0.00E+00 |
1.00E+00 |
0.00E+00 |
F4 |
Cold Partial Failure of Road Tanker |
25 |
FFR |
1.75E-08 |
1.81E-01 |
1.00E+00 |
3.16E-09 |
F5.1 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Tanker) |
25 |
JFI |
1.11E-07 |
5.00E-02 |
1.18E-04 |
6.51E-13 |
F5.1 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Tanker) |
25 |
BLEVE |
1.11E-07 |
1.20E-04 |
1.18E-04 |
1.56E-15 |
F5.1 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Tanker) |
25 |
VCE |
1.11E-07 |
0.00E+00 |
1.18E-04 |
0.00E+00 |
F5.1 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Tanker) |
25 |
FFR |
1.11E-07 |
1.90E-01 |
1.18E-04 |
2.47E-12 |
F5.2 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Vessel) |
25 |
JFI |
1.11E-07 |
5.00E-02 |
2.60E-03 |
1.43E-11 |
F5.2 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Vessel) |
25 |
BLEVE |
1.11E-07 |
1.20E-04 |
2.60E-03 |
3.44E-14 |
F5.2 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Vessel) |
25 |
VCE |
1.11E-07 |
0.00E+00 |
2.60E-03 |
0.00E+00 |
F5.2 |
Guillotine Failure of Liquid filling Line to Vessel (fed from Vessel) |
25 |
FFR |
1.11E-07 |
1.90E-01 |
2.60E-03 |
5.45E-11 |
F6 |
Guillotine Failure of Liquid Supply Line to Vaporizer |
25 |
JFI |
1.81E-05 |
5.00E-02 |
1.30E-01 |
1.17E-07 |
F6 |
Guillotine Failure of Liquid Supply Line to Vaporizer |
25 |
BLEVE |
1.81E-05 |
1.20E-04 |
1.30E-01 |
2.82E-10 |
F6 |
Guillotine Failure of Liquid Supply Line to Vaporizer |
25 |
VCE |
1.81E-05 |
0.00E+00 |
1.30E-01 |
0.00E+00 |
F6 |
Guillotine Failure of Liquid Supply Line to Vaporizer |
25 |
FFR |
1.81E-05 |
1.90E-01 |
1.30E-01 |
4.46E-07 |
F7 |
Guillotine Failure of Liquid Filling Line to Flexible Hose |
25 |
JFI |
1.60E-08 |
5.00E-02 |
7.80E-03 |
6.23E-12 |
F7 |
Guillotine Failure of Liquid Filling Line to Flexible Hose |
25 |
BLEVE |
1.60E-08 |
2.40E-04 |
7.80E-03 |
2.99E-14 |
F7 |
Guillotine Failure of Liquid Filling Line to Flexible Hose |
25 |
VCE |
1.60E-08 |
0.00E+00 |
7.80E-03 |
0.00E+00 |
F7 |
Guillotine Failure of Liquid Filling Line to Flexible Hose |
25 |
FFR |
1.60E-08 |
1.90E-01 |
7.80E-03 |
2.37E-11 |
F8 |
Vaporizer Failure |
25 |
JFI |
1.01E-05 |
5.00E-02 |
1.30E-01 |
6.55E-08 |
F8 |
Vaporizer Failure |
25 |
BLEVE |
1.01E-05 |
1.20E-06 |
1.30E-01 |
1.57E-12 |
F8 |
Vaporizer Failure |
25 |
VCE |
1.01E-05 |
0.00E+00 |
1.30E-01 |
0.00E+00 |
F8 |
Vaporizer Failure |
25 |
FFR |
1.01E-05 |
1.90E-01 |
1.30E-01 |
2.49E-07 |
F9.1 |
Guillotine Failure of Flexible Hose (fed from Tanker) |
25 |
JFI |
6.70E-06 |
5.00E-02 |
7.55E-03 |
2.53E-09 |
F9.1 |
Guillotine Failure of Flexible Hose (fed from Tanker) |
25 |
BLEVE |
6.70E-06 |
2.40E-04 |
7.55E-03 |
1.21E-11 |
F9.1 |
Guillotine Failure of Flexible Hose (fed from Tanker) |
25 |
VCE |
6.70E-06 |
0.00E+00 |
7.55E-03 |
0.00E+00 |
F9.1 |
Guillotine Failure of Flexible Hose (fed from Tanker) |
25 |
FFR |
6.70E-06 |
1.90E-01 |
7.55E-03 |
9.60E-09 |
F9.2 |
Guillotine Failure of Flexible Hose (fed from Vessel) |
25 |
JFI |
6.70E-06 |
5.00E-02 |
1.30E-03 |
4.35E-10 |
F9.2 |
Guillotine Failure of Flexible Hose (fed from Vessel) |
25 |
BLEVE |
6.70E-06 |
2.40E-04 |
1.30E-03 |
2.09E-12 |
F9.2 |
Guillotine Failure of Flexible Hose (fed from Vessel) |
25 |
VCE |
6.70E-06 |
0.00E+00 |
1.30E-03 |
0.00E+00 |
F9.2 |
Guillotine Failure of Flexible Hose (fed from Vessel) |
25 |
FFR |
6.70E-06 |
1.90E-01 |
1.30E-03 |
1.65E-09 |
Note 1: FBL – Fireball; BLEVE – Boiling Liquid Expanding Vapour Explosion; VCE – Vapour Cloud Explosion; JFI – Jet fire; FFR – Flash Fire
(a) Rupture of storage vessel
(b) Rupture of road tanker
(c) Partial failure of storage vessel
(d) Partial failure of road tanker
(e) Guillotine failure of liquid filling line to flexible hose
(f) Guillotine failure of flexible hose
(g) Guillotine failure of liquid filling line to storage vessel
(h) Guillotine failure of supply line to vaporizers
(i) Vaporizer failure
(j) BLEVE of road tanker
Point Sources
Line Sources
(a) Probability of ignition for a vehicle was taken as 0.4 in 60 seconds;
(b) Traffic density was based on the projected traffic flow adopted for population estimation, as detailed in Appendix 11.2.
Table 11.11 Summary of Line Ignition Source (Year 2033)
Line Source |
Traffic Density (veh / hr) |
Average Traffic Speed (km / hr) |
|
Daytime |
Night-time |
||
Lion Rock Tunnel Road |
8,001 |
3,521 |
80 |
Hung Mui Kuk Road |
3,885 |
1,673 |
50 |
Chung Pak Road & Lung Pak Street |
368 |
155 |
50 |
Fu Kin Street |
213 |
92 |
50 |
Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
361 |
169 |
50 |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
291 |
115 |
50 |
Table 11.12 Summary of Line Ignition Source (Year 2041)
Line Source |
Traffic Density (veh / hr) |
Average Traffic Speed (km / hr) |
|
Daytime |
Night-time |
||
Lion Rock Tunnel Road |
8,114 |
3,567 |
80 |
Hung Mui Kuk Road |
3,897 |
1,678 |
50 |
Chung Pak Road & Lung Pak Street |
369 |
156 |
50 |
Fu Kin Street |
214 |
92 |
50 |
Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
363 |
170 |
50 |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
291 |
116 |
50 |
Area Source
Protection afforded to persons indoors in a building
Protection afforded to persons by being on the upper floors of building
Shielding by buildings
Risk Level
Acceptability
Plate 11.4 Individual Risk Contours
Risk Level
(a) Unacceptable – a region within which the risks may be regarded as unacceptable
(b) Acceptable – a region within which the risks may be regarded as acceptable
(c) ALARP – a region between the two in which measures should be taken to demonstrate the risks as “as low as reasonably practicable” (ALARP). In other words, consideration is given not only to the level of risk but also the cost and practicality of reducing it
(a) 1 chance in 1,000 per year of an incident resulting in 1 or more fatalities;
(b) 1 chance in 10,000 per year of an incident resulting in 10 or more fatalities;
(c) 1 chance in 100,000 per year of an incident resulting in 100 or more fatalities; and
(d) not more than 1,000 fatalities at a frequency of greater than 1 chance in a billion (1,000,000,000) per year.
Plate 11.5 FN Curves for the LPG Compound
Acceptability
Table 11.13 Societal Risk Data for the LPG Compound covering all Assessed Scenarios
No. Fatalities |
Frequency (/year) |
||
Year 2033 – Base Case |
Year 2033 – Construction Phase |
Year 2041 – Operation Phase |
|
1 |
6.29E-06 |
6.29E-06 |
6.29E-06 |
2 |
4.64E-06 |
4.65E-06 |
4.64E-06 |
3 |
3.65E-06 |
3.65E-06 |
3.65E-06 |
4 |
2.68E-06 |
2.68E-06 |
2.68E-06 |
5 |
2.31E-06 |
2.31E-06 |
2.31E-06 |
6 |
1.68E-06 |
1.68E-06 |
1.68E-06 |
8 |
1.20E-06 |
1.21E-06 |
1.20E-06 |
10 |
9.58E-07 |
9.58E-07 |
9.58E-07 |
12 |
7.98E-07 |
7.99E-07 |
7.98E-07 |
15 |
5.72E-07 |
5.72E-07 |
5.72E-07 |
20 |
1.65E-07 |
1.65E-07 |
1.65E-07 |
25 |
1.47E-07 |
1.47E-07 |
1.47E-07 |
30 |
1.28E-07 |
1.28E-07 |
1.28E-07 |
40 |
9.48E-08 |
9.49E-08 |
9.48E-08 |
50 |
5.99E-08 |
6.00E-08 |
5.99E-08 |
60 |
5.36E-08 |
5.36E-08 |
5.36E-08 |
80 |
4.59E-08 |
4.59E-08 |
4.59E-08 |
100 |
3.79E-08 |
3.79E-08 |
3.79E-08 |
120 |
3.00E-08 |
3.00E-08 |
3.00E-08 |
150 |
1.64E-08 |
1.64E-08 |
1.64E-08 |
200 |
6.14E-09 |
6.14E-09 |
6.14E-09 |
Table 11.14 Breakdown of PLL for the LPG Compound by Population Groups (Year 2033 – Construction Phase)
Population |
Potential Loss of Life (PLL) / per year |
% of Total PLL |
|
ID |
Description |
||
8 |
Cypress Court, Worldwide Gardens |
1.23E-05 |
31.96% |
6 |
Anfield School |
1.22E-05 |
31.90% |
R3 |
Chung Pak Road & Lung Pak Street |
8.01E-06 |
20.86% |
5 |
Bauhinia Court, Worldwide Gardens |
1.87E-06 |
4.88% |
7 |
Begonia Court, Worldwide Gardens |
1.64E-06 |
4.27% |
4 |
Laurel Court, Worldwide Gardens |
1.07E-06 |
2.80% |
2 |
Hibiscus Court, Worldwide Gardens |
5.00E-07 |
1.30% |
3 |
Lily Court, Worldwide Gardens |
4.54E-07 |
1.18% |
R5 |
Slip road (Lion Rock Tunnel Road to Hung Mui Kuk Road) |
1.66E-07 |
0.43% |
1 |
Pine Court, Worldwide Gardens |
1.25E-07 |
0.33% |
12 |
Proposed Project Works Area |
2.87E-08 |
0.07% |
R1 |
Lion Rock Tunnel Road |
3.14E-09 |
<0.01% |
R2 |
Hung Mui Kuk Road |
7.22E-10 |
<0.01% |
10 |
Sheung Sum House, Lung Hang Estate |
3.74E-10 |
<0.01% |
R4 |
Fu Kin Street |
1.78E-11 |
<0.01% |
R6 |
Slip road (Hung Mui Kuk Road to Lion Rock Tunnel Road) |
5.50E-12 |
<0.01% |
11 |
Wai Sum House, Lung Hang Estate |
1.97E-12 |
<0.01% |
9 |
Pok Oi Hospital Chan Kai Memorial College |
1.25E-13 |
<0.01% |
Total |
3.84E-05 |
100% |
Table 11.15 Breakdown of PLL for the LPG Compound by Major Events (All Assessed Scenarios)
Event Description |
Outcome [Note 1] |
Year 2033 – Base Case |
Year 2033 – Construction Phase |
Year 2041 – Operation Phase |
|||
Potential Loss of Life (PLL) / per year |
% of Total PLL |
Potential Loss of Life (PLL) / per year |
% of Total PLL |
Potential Loss of Life (PLL) / per year |
% of Total PLL |
||
Cold Partial Failure of Storage Vessel 2 |
FFR |
1.68E-05 |
43.83% |
1.68E-05 |
43.83% |
1.68E-05 |
43.83% |
Cold Partial Failure of Storage Vessel 1 |
FFR |
1.68E-05 |
43.83% |
1.68E-05 |
43.83% |
1.68E-05 |
43.83% |
Cold Catastrophic Failure of Storage Vessel 1 |
FBL |
1.00E-06 |
2.62% |
1.00E-06 |
2.62% |
1.00E-06 |
2.62% |
Cold Catastrophic Failure of Storage Vessel 2 |
FBL |
1.00E-06 |
2.62% |
1.00E-06 |
2.62% |
1.00E-06 |
2.62% |
Cold Catastrophic Failure of Road Tanker |
FBL |
8.15E-07 |
2.12% |
8.15E-07 |
2.12% |
8.15E-07 |
2.12% |
Cold Partial Failure of Storage Vessel 1 |
JFI |
6.12E-07 |
1.60% |
6.12E-07 |
1.59% |
6.12E-07 |
1.60% |
Cold Partial Failure of Storage Vessel 2 |
JFI |
6.12E-07 |
1.60% |
6.12E-07 |
1.59% |
6.12E-07 |
1.60% |
Vaporizer Failure |
FFR |
2.48E-07 |
0.65% |
2.48E-07 |
0.65% |
2.48E-07 |
0.65% |
Cold Catastrophic Failure of Storage Vessel 1 |
FFR |
1.32E-07 |
0.34% |
1.32E-07 |
0.34% |
1.32E-07 |
0.34% |
Cold Catastrophic Failure of Storage Vessel 2 |
FFR |
1.32E-07 |
0.34% |
1.32E-07 |
0.34% |
1.32E-07 |
0.34% |
Others |
- |
1.73E-07 |
0.45% |
1.75E-07 |
0.45% |
1.73E-07 |
0.45% |
Total |
3.84E-05 |
100% |
3.84E-05 |
100% |
3.84E-05 |
100% |
Note 1: FBL – Fireball; JFI – Jet fire; FFR – Flash Fire
Risk Mitigation Measure Identification
· Installation of onsite gas detectors at the construction site;
· Establishment of emergency response plans;
· Safety/ emergency response training and drills for all personnel at the construction site; and
· Maintain the number of construction workers onsite to a minimum.
Cost-Benefit Analysis
ICAF = |
Cost of Mitigation Measure |
(Reduction in PLL Value × Design Life of Mitigation Measure) |
Risk Mitigation Measure Evaluation
· Establishment of emergency response plans;
· Safety/ emergency response training and drills for all personnel; and
· Maintain the number of construction workers onsite to a minimum.
[2] Transport Department. (September 2020). The Annual Traffic Census 2019.
[3] ERM (1996). Quantitative Risk Assessment of 18 LPG Installations in Public Housing Estates: Choi Po Court.
[4] Reeves, A.B., Minah, F.CC. and Chow, V.H.K. (1997). “Quantitative Risk Assessment Methodology for LPG Installations”, Conference on Risk & Safety Management in the Gas Industry, EMSD & HKIE, Hong Kong.
[5] Ling Chan + Partners Limited. (2001). Environmental Impact Assessment for Proposed Headquarters and Bus Maintenance Depot in Chai Wan (BDEIA) (AEIAR-045/2001).
[7] MEMCL (2003). Quantitative Risk Assessment for the Proposed Petrol cum LPG Filling Station at Cornwall Street
[8] Technica Limited (1989). Tsing Yi Island Risk Assessment. A report prepared for the Electrical and Mechanical Services Department of Hong Kong Government.
[9] HKO. A Wake Up Call from Mangkhut. https://www.hko.gov.hk/en/blog/00000216.htm
[10] Health and Safety Executives (1997). The Calculation of Aircraft Crash Risk in the UK. J P Byrne
[11] Health and Safety Executive (HSE), Application of QRA in Operational Safety Issues, RR025 (2002).
[1] Education Bureau, https://applications.edb.gov.hk/schoolsearch/permittedaccommodation.aspx?langno=1&scrn=190764000133 [Accessed on 23rd March 2021]
[2] School website, http://www.pohck.edu.hk/webpage1920/SubCoordinator2019-2020.pdf [Accessed on 23rd March 2021]
[3] Education Bureau, https://applications.edb.gov.hk/schoolsearch/permittedaccommodation.aspx?langno=1&scrn=587567000123 [Accessed on 23rd March 2021]
[4] School website, http://www.anfield.edu.hk/taiwai/aboutus.php?id=6 [Accessed on 23rd March 2021]