TABLE OF CONTENTS
Page
1.2 Designated Projects under EIAO
1.3 Purpose of the Executive Summary
2.1 Objective and Scope of the Project
2.3 Consideration of Alternative Options
2.4 Construction Methodologies
3 Key Findings of the environmental impact Assessment
3.4 Waste Management Implication
3.6 Ecological Impact (Terrestrial)
3.8 Landscape and Visual Impact
4 environmental monitoirng and audit (EM&A)
List of Tables
Table 1.1..... Schedule 2 Designated Projects in this Project
Table 2.1..... Tentative Phasing of Major Construction Works
Table 2.2..... Summary of Concurrent Projects
Table 2.3..... Summary of Concerns and Follow Up Actions
Table 5.1 .... Summary of Environmental Impacts
List of Figures
60604728/R44b/Figure 2.1 Location Plan of the Project
60604728/R44b/Figure 2.2 General Layout (Sheet 1 of 4)
60604728/R44b/Figure 2.3 General Layout (Sheet 2 of 4)
60604728/R44b/Figure 2.4 General Layout (Sheet 3 of 4)
60604728/R44b/Figure 2.5 General Layout (Sheet 4 of 4)
Abbreviation |
Full title |
ACABAS |
The Advisory Committee on the Appearance of Bridges and Associated Structures |
AFCD |
Agriculture, Fisheries and Conservation Department |
AMO |
Antiquities and Monuments Office |
CEDD |
Civil Engineering and Development Department |
CLP |
China Light and Power Company Limited |
DC |
District Council |
DEVB |
Development Bureau |
DSD |
Drainage Services Department |
ENB |
Environment Bureau |
EPD |
Environmental Protection Department |
ETWB |
The Environment, Transport and Works Bureau |
FSD |
Fire Services Department |
GEO |
Geotechnical Engineering Office of the Civil Engineering and Development Department |
HKPF |
Hong Kong Police Force |
HKSAR |
Hong Kong Special Administrative Region |
HyD |
Highways Department |
LandsD |
Lands Department |
LCSD |
Leisure and Cultural Services Department |
LegCo |
Legislative Council |
MTRCL |
MTR Corporation Limited |
PFC |
Public Fill Committee |
PlanD |
Planning Department |
STDC |
Sha Tin District Council |
T&TC |
Traffic and Transport Committee |
TD |
Transport Department |
WSD |
Water Supplies Department |
Abbreviation |
Full Expression |
AAA |
Alert, Alarm and Action |
ADB |
Administration Building |
AFA |
Automatic Fire Alarm |
AFCD NCPN |
Agriculture, Fisheries and Conservation Department Nature Conservation Practice Note |
ANPR |
Automatic Number Plate Recognition |
AOI |
Area of Influence |
API |
Aerial Photograph Interpretation |
APS |
Air Purifier System |
AQO |
Air Quality Objectives |
ASRs |
|
AVI |
Automatic Vehicle Identification |
BIM |
Building Information Modeling |
BS |
Backend System |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CASET |
Computer-Aided Sustainability Evaluation Tool |
CMCS |
Central Monitoring and Control System |
COCs |
Chemicals of Concerns |
CoP |
Code of Practice |
CRTN |
UK Department of Transport Calculation of Road Traffic Noise |
CV |
Curriculum Vitae |
CZ |
Consultation Zone |
C&D |
Construction and Demolition |
C&DMMP |
Construction and Demolition Material Management Plan |
DEP |
Director of Environmental Protection |
DEVB TC(W) |
Development Bureau Technical Circular (Works) |
DFC |
Design Flow to Capacity |
DI |
Departmental Instruction |
DIA |
Drainage Impact Assessment |
DLOs |
District Lands Offices |
DMP |
Drainage Master Plan |
DR |
Director’s Representative |
E/B |
eastbound |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIAO-TM |
Technical Memorandum on Environmental Impact Assessment Process |
ELS |
Excavation and Lateral Support |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
ERA |
Estimating Method Using Risk Analysis |
ETWB TC(W) |
Environment, Transport and Works Bureau Technical Circular (Works) |
FFTS |
Free-Flow Tolling System |
FS |
Front-End System |
FSI |
Fire Service Installation |
FSP |
Fine Suspended Particulates |
GA |
Geotechnical Assessment |
GEO TGN |
Technical Guidance Notes issued by GEO |
GI |
Ground Investigation |
HA |
Hazard Assessment |
HDC |
Horizontal Directional Coring |
HLC |
Historical landslide catchments |
HKPSG |
Hong Kong Planning Standards and Guidelines |
ICM |
Integrated Catchment Modeling |
ISO |
International Organization for Standardization |
IVU |
In-Vehicle Unit |
LAOI |
Lands Administration Office Instruction |
LED |
Light-Emitting Diode |
LPG |
Liquefied Petroleum Gas |
LRCP |
Lion Rock Country Park |
LRT |
Lion Rock Tunnel |
LRTR |
Lion Rock Tunnel Road |
LT |
Laboratory Testing |
LVIA |
Landscape and Visual Impact Assessment |
MoA |
Means of Access |
MoE |
Means of Escape |
N/B |
northbound |
NCO |
Noise Control Ordinance |
NEC |
New Engineering Contract |
NO2 |
Nitrogen Dioxide |
NOX |
Nitrogen Oxides |
NTH |
Natural Terrain Hazard |
NSRs |
Noise Sensitive Receivers |
OH |
Open Hillside |
OHVD |
Overhead Ventilation Ducts |
OSCG |
On-site Chlorine Generation |
OVT |
Old and Valuable Tree |
PDS |
Project Definition Statement |
PFRFs |
Public Fill Reception Facilities |
PME |
Powered Mechanical Equipment |
PoC |
Proof of Concept |
PR |
Public Relations |
ProPECC PN |
Professional Persons Environmental Consultative Committee Practice Note |
RAP |
Remediation Action Plan |
RC |
Reserve Capacity |
RFID |
Radio Frequency Identification |
RPZ |
Railway Protection Zone |
RR |
Remediation Report |
RSP |
Respirable Suspended Particulates |
SA |
Sustainability Assessment |
SAI |
Sites of Archaeological Interest |
S/B |
southbound |
SCAS |
Shui Chuen Au Street |
SCL |
Shatin to Central Link |
SDM |
Stormwater Drainage Manual |
SDMHR |
Structures Design Manual for Highways and Railways |
SoA |
Schedule of Accommodation |
SI |
Site Investigation |
SMTR |
Shing Mun Tunnel Road |
SSSI |
Site of Special Scientific Interest |
STR |
Sha Tin Road |
T4 |
Revised Trunk Road T4 and Associated Improvement Works in Sha Tin |
T&C |
Testing and Commissioning |
TBM |
Tunnel Boring Machine |
TC |
Technical Circular |
TCH |
Tate’s Cairn Highway |
TCSS |
Traffic Control and Surveillance Systems |
TFS |
Technical Feasibility Statement |
TSP |
Total Suspended Particulates |
The Assignment |
Improvement of Lion Rock Tunnel |
The Project |
Improvement of Lion Rock Tunnel Project |
TIA |
Traffic Impact Assessment |
TPDM |
Transport Planning and Design Manual |
TSH |
Tsing Sha Highway |
TTMS |
Temporary Traffic Management Scheme |
TTU |
Tsang Tai Uk |
TX |
Transformer |
UPS |
Uninterrupted Power Supply |
VB |
Ventilation Building |
VM |
Value Management |
VOCs |
Volatile Organic Compounds |
VR |
Virtual Reality |
VSRs |
Visually sensitive receivers |
WBTC |
Technical circulars issued by the Works Bureau, the then Works Branch, the then Lands & Works Branch or the then Public Works Department |
WTW |
Water Treatment Works |
· the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
· the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
· the acceptability of residual impacts after the proposed mitigation measures are implemented.
Table 1.1 Schedule 2 Designated Projects in this Project
Schedule 2 Designated Project |
Designated Project Element under the Project |
|
Item A.1, Part I |
A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing roads.
|
The road sections under the Project comprises of: (i) construction of a new vehicular bridge next to existing K7A Vehicular Bridge. The new vehicular bridge will connect existing Waterloo Road northbound (N/B) to Lion Rock Tunnel Road N/B which are “trunk road” under TD’s classification, therefore, this new vehicular bridge is classified as “trunk road”. (ii) widening/re-alignment the existing roads including Lion Rock Tunnel Road which is considered as major extensions or improvement to existing roads. |
Item A.7, Part I |
A road or railway tunnel more than 800 m in length between portals.
|
(i) The proposed new tunnel is more than 800m in length between portals. (ii) Enlargement of the existing Kowloon bound tunnel, which is more than 800m in length between portals (an exempted DP).
|
Item Q.1, Part I |
All projects including new access roads, railways, sewers, sewage treatment facilities, earthworks, dredging works and other building works partly or wholly in an existing country park.
|
The proposed re-aligned southbound LRT Road at Shatin area partly in existing Lion Rock Country Park. |
· Section 2 presents purpose and nature of the Project, consideration of alternative options and construction methods for the Project;
· Section 3 presents the key findings of the environmental impact assessment;
· Section 4 describes the proposed environmental monitoring and audit for the Project; and
· Section 5 presents the conclusions.
(a) Construction of a three-lane road tunnel of approximately 1.4 km long between the two existing tunnel tubes of the LRT;
(b) Enlargement of the existing Kowloon bound tunnel tube to a three-lane road tunnel, together with the construction of cross passages linking the new Kowloon bound tunnel tube with the new tunnel;
(c) Carry out refurbishment works on the existing Shatin bound tunnel tube and replacement/rehabilitation of the existing fire services provisions;
(d) Provision of equipment including Traffic Control and Surveillance Systems (TCSS) for operation of the tunnels;
(e) Demolish the existing toll plaza together and provision of equipment and facilities for free-flow tolling;
(f) Re-provision of tunnel buildings including tunnel administration building (ADB), ventilation buildings (VBs) etc., construction of a vehicular crossover bridge to support tunnel operations, and construction of footbridges and any other tunnel support facilities;
(g) Widening of LRT Road at Kowloon side to dual three-lane from slip roads of Lung Cheung Road interchange to LRT Kowloon portal and construct a single lane vehicular bridge crossing over Lung Cheung Road for the Shatin bound direction;
(h) Widening of the slip road from Lion Rock Tunnel Road southbound (S/B) to Lung Cheung Road E/B to two lanes, and realigning the slip road from Lung Cheung Road E/B to Lion Rock Tunnel Road N/B;
(i) Widening of LRT Road at Sha Tin side to dual three-lane between the existing tunnel portal to Fung Shing Court (except a section of the northbound carriageway between the slip roads to and from Hung Mui Kuk Road which would remain two lanes);
(j) Reprovisioning of Footbridge NF74 near Fung Shing Court;
(k) Provision of noise barriers / enclosures to mitigate the road traffic noise impact on noise sensitive receivers; and
(l) Ancillary works including slope works, water mains diversion, road lighting, drainage, landscaping works, etc.
2.3.1 Assessments have been carried out to ensure that the Project will yield the most environmental benefits. In order to carry out the improvement works, the need for a new third tunnel was explored. If the new tunnel is not constructed, the one-tube-two-way traffic arrangement (i.e. similar to the existing arrangement during routine tunnel maintenance after midnight) will have to be implemented full-time while works are in progress in one of the existing tunnel tubes to ensure safety to the tunnel users. This will reduce the traffic capacity of the LRT, and traffic queues and congestions are expected along the tunnel connecting roads (e.g. Lion Rock Tunnel Road, Waterloo Road, Lung Cheung Road etc.) which in turn will lead to increase in air quality and noise impact during construction phase. Hence a new third tunnel is needed to facilitate uninterrupted traffic during construction. Consideration has also been given for an adoption of tunnelling works instead of traditional open-cut method for the provision of additional carriageways so as to avoid direct impacts on aboveground habitats within LRCP.
Alignment of the New Tunnel
2.3.2 Three alignment options for the new tunnel, to the west, east or in between the existing LRT tubes (namely the West Option, East Option and Middle Option respectively) were studied. The Middle Option is selected as the preferred option. The Middle Option has the shortest tunnel length and therefore will generate the least Construction and Demolition (C&D) materials. In addition, this option will have the lowest construction cost, shortest construction time and hence the least number of construction vehicles needed (i.e. least impacts to noise and air quality sensitive receivers). The Middle Option is also expected to have the least visual, landscape and ecological impacts among the three tunnel alignment options as it does not involve surface excavation within the Lion Rock Country Park (LRCP), hence least impact to the hillside vegetation (i.e. least impacts to valuable visual and landscape resources and natural habitat). Direct loss of LRCP and natural habitats are anticipated to be smaller, hence adverse ecological impacts on LRCP and natural habitats would be comparatively smaller if the middle option is adopted.
2.3.3 The West Option will comprise a much longer tunnel length than the Middle Option and the portal at Kowloon for this tunnel alignment will be directly adjacent to Vista Panorama thereby increasing air quality and noise impacts to the sensitive receivers along Waterloo Road. The East Option will, on the other hand, require extensive surface excavation within the Lion Rock Country Park at Shatin side for the construction of the tunnel portal and connecting roads. This will lead to much more woodland loss and tree felling relative to the Middle Option.
Tunnel Ancillary Facilities
2.3.4 The tunnel ancillary facilities such as the tunnel administration buildings (including on-site sewage treatment facility), ventilation buildings, depot, workshops, car parking facilities etc. will have to be located near the tunnel portals. In order to facilitate future tunnel operations, a crossover bridge is proposed near the existing toll plaza. Avoidance of Lion Rock Country Park (LRCP) was explored. However, a minor portion of the tunnel ancillary facilities (e.g. car parking facilities) would unavoidably be located at the developed area and an engineered slope at the fringe of the LRCP south of the existing toll plaza. Alternative locations outside LRCP (i.e. the downslope area at feature no. 7SW-D/FR33, Tei Lung Hau and agricultural land adjacent to the Shatin South Fresh Water Service Reservoir) were also considered and discussed in Chapter 2 of the EIA Report, it is concluded that those alternative locations do not fulfil the operational need of the LRT while the current adopted layout at Shatin has avoided an encroachment into woodland. Furthermore, more site formation works (with respect to within LRCP) will be required if the tunnel facilities are proposed at these alternative locations. Aside from the increased construction cost and time, such large-scale construction on steep hilly terrains will pose much greater construction difficulties and also safety hazards to both workers (e.g. falling from height) and the public (e.g. falling objects to Ka Tin Court downslope). In addition, the extent of woodland and green area losses are also envisaged to be greater at these alternative locations. The new ventilation buildings are proposed to be located outside the boundary of the Lion Rock Country Park.
Alignment of the Road Widening Works
2.3.5 The road widening works at Shatin side are proposed to be carried out at the downhill side of Lion Rock Tunnel Road (i.e. the downhill option). This will avoid and minimise encroaching on Lion Rock Country Park to the maximum possible extent. Considerations were previously given to locate the road widening works at the uphill section within the Lion Rock Country Park (i.e. the uphill option). Nevertheless, the woodland loss and number of trees felled of the downhill option are envisaged to be much lower than the uphill option. The downhill option will also generate much less C&D materials than the uphill option, and the associated filling works could facilitate the reuse of excavated materials (say from tunnel portal excavation). In addition, unlike the downhill option where access to the road widening site / works area could be via the downhill local roads, access to the road widening site / works area for the uphill option could only be accessed via the busy Lion Rock Tunnel Road. Furthermore, the excavation works uphill will require the partial closure of the nearside traffic lane of the southbound carriageway which could lead to congestion and in turn could increase air quality and noise impacts along Lion Rock Tunnel Road. In addition, the vegetation along the hillside of the Lion Rock Country Park are valuable landscape and visual resources. The uphill option will inevitably destroy a much larger extent of it than the downhill option.
2.3.6 Nevertheless, the widened road of the downhill option will be nearer to the developments located downhill of Lion Rock Tunnel Road at Shatin side. Noise mitigation measures such as noise barriers and noise enclosures will be provided but such measures will pose visual impacts to the nearby visually sensitive receivers. Appropriate aesthetic pleasing design shall be applied to mitigate the impact.
Area for Stockpiling
Construction of the road widening works along LRT Road
Sequence of Works
Table 2.1 Tentative Phasing of Major Construction Works
Major Works |
Tentative Schedules |
Construction of tunnel ancillary facilities and other misc. works such as watermain diversion at Shatin Portal (including testing and commissioning)
Construction of tunnel ancillary facilities at Kowloon Portal (including testing and commissioning)
|
Shatin Portal: Q1 2025 to Q2 2031
Kowloon Portal: Q3 2025 to Q4 2030 |
Tunnelling works (including testing and commissioning): § Construction of new middle third tunnel tube by TBM § Enlargement of existing Kowloon bound tunnel tube by drill & break method § Refurbishment of the existing Shatin bound tunnel tube |
New middle third tunnel tube: Q1 2025 to Q1 2029 (Construction) Q4 2032 to Q4 2033 (Closed for demolition of partition wall) Kowloon bound tunnel tube: Q2 2029 to Q4 2032 Existing Shatin bound tunnel tube: Q1 2034 to Q4 2034 |
Road widening works and road widening associated works at Shatin and Kowloon: |
Q1 2025 to Q4 2034 |
Table 2.2 Summary of Concurrent Projects
Project Name |
Target Works Commencement Dates |
Target Work Completion Dates |
Cumulative Impact Considered / Addressed |
Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Cavern (WSD) |
2022 |
2027 |
Construction Phase: Air Quality, Noise, Ecology, Visual and Landscape
Operational Phase: Nil |
Revised Trunk Road T4 (CEDD) |
2023 |
September 2028 |
Construction Phase: Ecology and Landscape and Visual
Operational Phase: Air Quality, Noise, Ecology and Landscape and Visual |
In-situ Reprovisioning of Sha Tin Water Treatment Works – South Works (WSD) |
2020 |
2027 (Major works completed by Jan 2025) |
Construction Phase: Nil
Operational Phase: Nil |
Proposed Drainage Improvement Works at Chui Tin Street and Chui Tin Street Soccer Pitch (Drainage Services Department (DSD)) |
2023 |
2031 |
Construction Phase: Nil
Operational Phase: Nil |
Table 2.3 Summary of Concerns and Follow Up Actions
Concerns / Issues |
Follow Up Actions to be Taken |
§ Road traffic noise impact due to the additional traffic generated from the Project |
§ Noise mitigation measures including noise barriers and noise-enclosure are proposed along Lion Rock Tunnel Road. As such, the predicted noise levels at nearby NSRs will comply with the road traffic noise criteria.
Please refer to Section 3.2 for road traffic noise impact assessment. |
§ Adverse water quality of watercourses near project area due to construction activities from the Project |
§ Proper site management practices and the mitigation measures as recommended in the EIA would be implemented. As such, no adverse water quality impact would be anticipated during construction phase.
Please refer to Table 5.1 for mitigation measures for minimizing water quality impact. |
§ Loss of surrounding natural habitat due to encroachment of project into LRCP |
§ Middle Option for alignment of new tunnel and downhill road widening at LRTR was adopted to reduce encroachment into LRCP and reduce loss of habitat to a minimum extent. § Woodland compensatory planting is provided near Project Boundary for any unavoidable woodland loss within LRCP would be compensated off-site.
Please refer to Table 5.1 for mitigation measures for minimizing ecology impact. |
§ Increased air pollutant concentration due to construction activities and additional traffic generated from the Project |
§ Construction and operation phase air quality impact assessment was conducted in compliance with the requirements set out in the EIAO-TM. Suitable mitigation measures will be implemented during construction stages as recommended in the EIA.
Please refer to Section 3.1 for air quality impact assessment. |
§ Adverse impact to cultural heritage site (Tsang Tai Uk) from construction activities |
§ Project road alignment is revised. Tsang Tai Uk is now located at substantial distance from Project Site. No adverse impact is anticipated during construction phase.
Please refer to Section 3.7 for details of Cultural Heritage Impact Assessment. |
§ Removal of trees within LRCP and surrounding areas due to the Project |
§ Middle Option for alignment of new tunnel and downhill road widening at LRTR was adopted to reduce encroachment into LRCP and minimize removal of trees within LRCP. § Compensatory tree planting is proposed for trees affected in LRCP near the tunnel portal area and toll plaza administration area. Off-site woodland compensatory planting is also provided.
Please refer to Table 5.1 for details of landscape and visual mitigation measures.
|
§ Potential hydrological impacts on natural watercourses arising from construction activities |
§ Appropriate water control strategies should be implemented to minimize the groundwater infiltration during the tunnel construction.
Please refer to Table 5.1 for details of mitigation measures for minimizing groundwater infiltration.
§ Surface water level monitoring of natural watercourses in the vicinity of the underground tunnel improvement works area should be conducted during the construction and operation stages.
Please refer to Section 3.6 for the details of monitoring on surface water level of natural watercourses. |
Table 5.1 Summary of Environmental Impacts
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance Predicted (Without Mitigation) |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of Mitigation Measures) |
Air Quality Impact |
|||||
Construction Impact |
|||||
Representative existing residential, commercial developments and government uses within 500m from the boundary of the Project Site |
TSP · The highest 1-hr average conc.: 135 – 1165 μg/m3 RSP · 10th highest 24-hr average conc: 62 – 128 μg/m3 · Annual average: 26 – 53 μg/m3 FSP · 19th highest 24-hr average conc: 30 – 44 μg/m3 · Annual average: 14 – 19 μg/m3 |
· Annexes 4 and 12 of the EIAO-TM TSP 1-hr average conc.: 500 μg/m3
· Air Quality Objectives (AQO) RSP · 24-hr average conc.: 100 μg/m3 (Number of exceedances allowed: 9) · Annual average conc.: 50 μg/m3 FSP · 24-hr average conc.: 50 μg/m3 (Number of exceedances allowed: 18) · Annual average conc.: 25 μg/m3 |
TSP · The highest 1-hr average conc.: Exceedances of EIAO-TM TSP criterion up to 665 μg/m3 RSP · 10th highest 24-hr average conc: Exceedances of AQO up to 28 μg/m3 · Annual average: Exceedances of AQO up to 3 μg/m3 FSP · 19th highest 24-hr average conc: No exceedance was predicted · Annual average: No exceedance was predicted |
Watering once
every 2 hours on work areas, exposed surface and unpaved road to reduce dust
emission. Provide sealed door and dust collector with dust removal efficiency of at least 80% at the opening of tunnel mined by drill and break.
Dust suppression measures and good site practices · Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather. · Use of frequent watering for particularly dusty construction areas and areas close to ASRs. · Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines. · Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs. · Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations. · Establishment and use of vehicle wheel and body washing facilities at the exit points of the site. · Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading area of barging point, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods. · Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit. · Imposition of speed controls for vehicles on site haul roads. · Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs. · Implementation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise. |
· No adverse residual impacts anticipated
|
Operation Impact |
|||||
Existing and planned residential, commercial developments and government uses within 500m from the boundary of the Project Site |
NO2 · 19th highest 1-hr average conc.: 91– 135 μg/m3 · Annual average conc.: 16– 34 μg/m3 RSP · 10th highest 24-hr average conc: 61 – 64 μg/m3 · Annual average: 26 – 27 μg/m3 FSP · 19th highest 24-hr average conc: 30 – 33 μg/m3 · Annual average: 14 – 15 μg/m3 |
· AQO NO2 · 1-hr average conc.: 200 μg/m3 (Number of exceedances allowed: 18) · Annual average conc.: 40 μg/m3 RSP · 24-hr average conc.: 100 μg/m3 (Number of exceedances allowed: 9) · Annual average conc.: 50 μg/m3 FSP · 24-hr average conc.: 50 μg/m3 (Number of exceedances allowed: 18) · Annual average conc.: 25 μg/m3 |
NO2, RSP and FSP · No exceedance was predicted |
· No mitigation measure is required. |
· No adverse residual impacts anticipated
|
Noise Impact |
|||||
Construction Airborne Noise Impact |
|||||
Representative residential developments and education institution within 300m from the boundary of the Project Site |
· 62 – 91 dB(A) |
· Annexes 5 and 13 of the EIAO-TM · Leq(30 min) 75dB(A) at 1m from the façade of residential dwellings · Leq(30 min) 70dB(A) at 1m from the façade of Educational Institutions and 65 dB(A) during examinations |
· Exceedance of the noise criteria by up to 16 dB(A) |
· Use of Quality Powered Mechanical Equipment · Use of Movable Noise Barrier, Purpose-built Noise Barrier, Noise Insulating Fabric and Noise Enclosure · Sequencing Operation of Construction Activates at critical works area · Reduction of PME at critical works area · Avoid to carry out particularly noisy construction activities during examination periods · Good site practices - Only well-maintained plant should be operated on site and plant should be serviced regularly. - Silencers or mufflers on construction plant should be utilized and should be properly maintained. - Mobile plant should be sited as far away from sensitive uses as possible. - Machines and plant that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum. - Plant known to emit noise strongly in one direction should, where possible, be orientated so that noise is directed away from the nearby sensitive uses. - Material stockpiles and other structures should be effectively utilized to screen noise from on-site construction activities. |
· No adverse residual impacts anticipated |
Construction Ground-borne Noise Impact |
|||||
Representative residential developments within 300m from the boundary of the Project Site |
· 49 – 58 dB(A) |
· Leq(30 min) 65dB(A)
|
· No exceedance predicted |
· No mitigation measure required |
· No adverse residual impacts anticipated. |
Operation Impact |
|||||
Representative existing and planned residential developments within 300m from the boundary of the Project Site |
Road Traffic Noise Impact · Predicted overall noise levels: 52 – 86 dB(A) · Predicted road traffic noise levels of the Project roads: <10 – 83 dB(A) · Maximum contribution from Project roads (when the overall noise level exceeds respective criterion): 23.3 dB(A) Fixed Noise Sources Impact · Predicted noise level: 55 dB(A) |
Road Traffic Noise · Annexes 5 and 13 of the EIAO-TM · EIAO-GN 12/2010 · L10(1 hour) 70dB(A) at 1m from the façade of residential dwellings · L10(1 hour) 65dB(A) at 1m from the façade of educational institute and place of worship Fixed Noise Sources Impact · Annexes 5 and 13 of the EIAO-TM · IND-TM under Noise Control Ordinance · Leq (30-min) 65 dB(A) during day and evening time · Leq (30-min) 55 dB(A) during night-time |
Road Traffic Noise · Exceedance of the noise criteria by up to 16 dB(A) · The exceedances are dominantly contributed by the other existing roads. Fixed Noise Sources Impact · No exceedance predicted. |
Road Traffic Noise · Provision of polymer modified friction course (PMFC) (i.e. a type of low noise road surfacing) as standard surfacing material · Provision of a total of 170m long vertical barrier, 240m long cantilever noise barriers, and 1300m long semi-enclosure on Project Road sections. Fixed Noise Sources Impact · No mitigation measure required. |
· No adverse residual impacts anticipated. |
Water Quality Impact |
|||||
Construction Impact |
|||||
Representative water sensitive receivers in the vicinity of the Project and within 500m from the boundary of the Project, covers the Tolo Harbour and Channel WCZ as well as the Victoria Harbour WCZ as designated under the WPCO |
The potential sources of water quality impact associated with the construction works would include: · Wastewater from general construction activities; · Construction site run-off; · Sewage from construction workforce; · Accidental spillage of chemicals; · Groundwater infiltration arising from tunnel boring; · Water pollution from culvert modification works; · Construction works in close proximity of inland watercourses; and · Groundwater from Contaminated Areas and Contaminated Site Runoff. |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for the Victoria Harbour (Phase Two) Water Control Zone (WCZ), Tolo Harbour and Channel WCZ and Tolo Harbour Supplementary WCZ · Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) · Practical Note for Professional Persons (ProPECC) PN 1/94 and 5/93 · Hong Kong Planning Standards and Guidelines · Environmental, Transport and Works Bureau (ETWB) Technical Circular (Works) No. 5/2005 |
· N/A |
· Mitigation measures and good site practices in ProPECC PN 1/94 “Construction Site Drainage” · Waste Disposal Ordinance · Provision of temporary sanitary facilities, such as chemical toilets, for construction workforce · Precaution measures in ETWB Technical Circular (Works) No. 5/2005 · Groundwater infiltration minimisation strategies and post-grouting · Proper interception and treatment of contaminated site runoff and wastewater from land decontamination in compliance with the TM-DSS · Proper treatment or recharge of contaminated groundwater in compliance with the TM-DSS |
· No adverse residual impacts anticipated |
Operation Impact |
|||||
· Representative water sensitive receivers in the vicinity of the Project and within 500m from the boundary of the Project, covers the Tolo Harbour and Channel WCZ as well as the Victoria Harbour WCZ as designated under the WPCO |
Potential water quality impacts associated with the operation phase include: · Non-point source surface run-off from road/bridge/viaduct; · Sewage effluent from the new administration building and ventilation buildings; · Wastewater generated from washing and maintenance operation; and · Tunnel run-off and drainage |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for the Victoria Harbour (Phase Two) WCZ, Tolo Harbour and Channel WCZ and Tolo Harbour Supplementary WCZ · Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) · ProPECC PN 5/93 · Guidelines for the Design of Small Sewage Treatment Plant |
· N/A |
· Adequate design in on-site STP adopted MBR with UV disinfection, an emergency storage tank with 2 hours of ADWF capacity and grease trap for sewage and wastewater generated from administration building which designed with reference to EPD’s “Guidelines for the Design of Small Sewage Treatment Plant” · Provision of dual or standby power supply, standby sewage treatment units, flow sensors and alarm systems for the on-site STP. · Provision of spare parts such as electrical and mechanical components of the on-site STP in case of break down / emergency. · Adequate design in septic tank with soakaway system and active carbon filter for sewage and wastewater generated from ventilation buildings which take into account the guidelines in ProPECC PN 5/93. · Adequate design in on-site STP, petrol interceptor and sedimentation tank for wastewater generated from washing and maintenance operation. · Regular test, maintenances and replacement of membranes or equipment to maintain a good operation condition. · Regular maintenance to all wastewater treatment system, including the on-site STP, septic tank with soakaway system, grease traps, active carbon filter system, petrol interceptor, sedimentation tank, etc. |
· No adverse residual impacts anticipated |
Waste Management Implications |
|||||
Construction Impact |
|||||
C&D materials, chemical wastes and general refuse
|
· Around 107,044 m3 of non-inert C&D materials and 1,338,050 m3 of inert C&D materials will be generated from tunnelling works, excavation, site formation works, construction of adits, ventilation/shafts buildings and new administration building and demolition of the existing administration building. · Small quantity of chemical wastes in the order of a few cubic metres per month will be generated from plant operations and maintenance, maintenance of mechanical equipment and potential asbestos waste from demolition of existing administration building. · Around 325 kg per day of general refuse will be generated from construction works and on-site staff and workers |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C) · Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) · Land (Miscellaneous Provisions) Ordinance (Cap. 28) · Public Health and Municipal Services Ordinance (Cap. 132BK) – Public Cleansing and Prevention of Nuisances Regulation · Air Pollution Control Ordinance (APCO) |
· N/A |
· Implementation of good site practices, waste reduction measures and proper storage, collection and transport of waste |
· No adverse residual impact anticipated |
Operation Impact |
|||||
Screening & grits, sludge, chemical wastes and general refuse |
· Small quantity of chemical wastes in the order of a few cubic metres per month will be generated from maintenance of facilities and equipment · Around 97.5 kg per day of general refuse will be generated from on-site staff and office activities · The total quantity of screening and grits generated from the on-site STP is expected to be less than 0.01 m3/day · About 1m3/day of sewage sludge will be generated from the on-site STP |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C) Public Health and Municipal Services Ordinance (Cap. 132BK) – Public Cleansing and Prevention of Nuisances Regulation |
· N/A |
· Implementation of waste reduction measures and proper storage, collection and transport of waste |
· No adverse residual impact anticipated |
Land Contamination |
|||||
Onsite construction workers and future occupants |
· A total of 11 facilities / areas were identified with potential land contamination concerns at the tunnel portal areas within the Project Area. |
· Annex 19 of the EIAO-TM · Guidance Note for Contaminated Land Assessment and Remediation (EPD, 2007) · Practice Guide for Investigation and Remediation of Contaminated Land (EPD, 2011) · Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (EPD, 2007) |
· N/A |
· A sampling and testing programme, targeting the potential hotspots identified within the Project Area, had been proposed. · Site re-appraisal should be carried out for the whole Project Area at a later stage of the Project in order to address any new contamination issues caused by the (i) changes in operation of the identified potentially contaminated site and (ii) changes in land use within the Project Area. The submission of supplementary CAP(s), associated SI works and any necessary remediation should be carried out at the concerned facilities and any new contaminated area identified in the site re-appraisal, prior to the commencement of construction at the potentially contaminated area(s). The further assessment and remediation works would follow EPD’s prevailing guidelines. · Any soil / groundwater contamination would be identified and properly treated prior to the construction works. |
· No adverse residual impact anticipated. |
Ecological Impact (Terrestrial) |
|||||
Construction Impact |
|||||
Natural/Semi-natural habitats including woodland, mixed woodland, shrubland and the associated wildlife (including species of conservation importance)
|
· Permanent loss (14.80 ha) and temporary loss (2.75 ha) of habitats · Affect about 0.16 ha woodland, 0.17 ha plantation, less than 0.01 ha modified watercourse and 0.81 ha developed area located at the LRCP permanently · Potential impact to four flora species of conservation importance (including one individual of Incense Tree, nine individuals of Butulang Canthium, 19 individuals of Ailanthus and nine individuals Rhodoleia) recorded within the Project footprint · Potential direct injury/mortality to wildlife and bird collision · Indirect disturbance impact (e.g. dust, noise, glare, site runoff, groundwater infiltration) on natural habitats and associated wildlife in the vicinity |
· Annexes 8 and 16 of the EIAO-TM · EIAO Guidance Notes Nos. 3/2010, 6/2010, 7/2010 and 10/2010 |
· N/A |
· Avoidance of encroachment on recognised sites of conservation importance (i.e. LRCP (about 197 ha) and Beacon Hill SSSI (about 34 ha)) within the assessment area as far as possible · Carefully design the detailed layout of the construction works to avoid/minimise direct impact on flora species of conservation importance recorded in the project footprint. If direct impact is unavoidable, mitigation measures to (e.g. transplant, compensate) the flora species of conservation importance should be conducted, where possible, according to Final Plant Preservation and Transplantation Proposal to be submitted at later stage · Reinstatement of temporarily affected area within the Project footprint (about 1.48 ha), including those within LRCP (about 0.25 ha), by woodland mix planting according to the Final Reinstatement Plan to be submitted at later stage · Direct impact on fauna species of conservation importance and their key habitats are avoided. Precautionary measure such as a pre-construction survey in natural habitats within and in the surrounding of the Project footprint is recommended (e.g. woodland, mixed woodlands and natural watercourse within and near the Project footprint) prior to the commencement of construction activities. In case any fauna species of conservation importance recorded would be directly impacted, a Protection and Translocation Proposal should be prepared to recommend suitable mitigation measures at later stage. · Compensate the unavoidable loss of woodland within Lion Rock Country Park (LRCP) (0.25 ha) by provision of compensation woodland in a ratio not less than 1:1 in terms of area (at least 0.25 ha) in accordance with the Final Woodland Compensation Plan to be submitted at later stage · Implementation of good site practices (e.g. provision of screening, control of glare / lighting, groundwater infiltration minimization measures, etc), regular site inspection and monitoring requirement · Implementation of groundwater infiltration minimization measures (e.g. groundwater control strategies, post-grouting) as stated in the Water Quality Section above · Adoption of NTHMMs with smaller footprint (rigid barriers and flexible barriers) to avoid and minimize the potential impacts to LRCP, natural habitats and associated vegetation |
· No adverse residual impact anticipated |
Operation Impact |
|||||
Natural/Semi-natural habitats including woodland, mixed woodland, shrubland and the associated wildlife (including species of conservation importance)
|
· Disturbance impacts (e.g. dust, noise, glare) to the natural/semi-natural habitats and the associated wildlife (including species of conservation importance) in the vicinity of Project site · Direct mortality (e.g. road kill) and bird collision |
· Same as construction phase |
· N/A |
· Implementation of mitigation measures (e.g. planting of peripheral screening plants/vertical green, control of glare / lighting) measures · Carefully design the noise barrier (e.g. location, use of tinted materials and superimposing dark patterns or strips on the noise barrier) |
· No adverse residual impact anticipated |
Cultural Heritage Impact |
|||||
Construction Impact |
|||||
Cultural heritage resources, Site of Archaeological Interest |
· Indirect impacts of ground-borne vibration, settlement and tilting would be anticipated on the Ex Beacon Hill Tunnel (Government Historic Site) · Direct impact would be anticipated to the two Lion Rock tunnels and associated buildings |
· EIAO-TM Annexes 10 and 19 · Guidelines for Cultural Heritage Impact Assessment · Antiquities and Monuments Ordinance (A&MO) (Cap.53) |
· N/A |
· As a precautionary measure, AMO should be informed immediately in case of discovery of antiquities or supposed antiquities in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with AMO
Monitoring of vibration, settlement and tilting · Monitoring of vibration, settlement and tilting incorporated with a set of Alert, Alarm and Action (AAA) system shall be employed for Ex Beacon Hill Tunnel during the construction phase, measuring inside the tunnel tube at locations closest to the proposed construction works. · Monitoring proposal should be submitted to AMO for agreement before commencement of works. · Records of monitoring should be submitted regularly to AMO. · AMO should be alerted in case any irregularities are observed. Pre and post condition survey · Pre and post condition survey of Ex Beacon Hill Tunnel (Government Historic Site) should be conducted by professional qualified building surveyor or engineer. · Survey results shall be submitted to AMO for record. Adopt similar fonts of the name of the tunnel and colour scheme of associated buildings · Fonts on both sides of the portals of the two tunnels should be kept or replicated and placed on similar position as the current setting · The colour scheme of associated buildings could be adopted to the new administrative buildings in order to maintain the original sentiment. · The two commemorative plaques marking the opening ceremony of the tunnel should be kept at prominent position at the new administrative buildings visible to all guests. Conduct detailed photographic recording · Detailed photographic recording on the Lion Rock Tunnel and its associated buildings (both exterior and interior) should be conducted before any works to commence. A copy of the photographic documentation should be provided to AMO for record. |
· No adverse residual impact anticipated |
Operation Impact |
|||||
Cultural heritage resources, Site of Archaeological Interest |
· No adverse impact would be anticipated on both built heritages and archaeology during the operational phase. |
· EIAO-TM Annexes 10 and 19 · Guidelines for Cultural Heritage Impact Assessment |
· N/A |
· No mitigation measure would be required |
· No adverse residual impact anticipated |
Landscape and Visual Impacts |
|||||
Construction Impact |
|||||
Landscape Resources (LRs) |
· Substantial landscape impact on LR-3.2 (Vegetation on Roadside Engineered Slopes from Tai Wai to Sha Tin Tau) · Moderate landscape impact on LR-1.1 (Vegetation on Natural Terrain), LR-1.2 (Vegetation in Village Areas near Kak Tin), LR-3.1 (Vegetation on Roadside Engineered Slopes in Kowloon Tong), LR-3.3 (Vegetation in Other Roadside Areas) and LR-4.2 (Lung Cheung Road Park) · Slight landscape impact on LR-6.1 (Vegetated Areas in Service Reservoirs and Associated Landscape Areas in Kowloon Side) and LR-6.3 (Vegetated Areas in Fenced-off Area (e.g. vacant land, construction site)) · No discernible change in other LRs identified within the study boundary of the Project |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Preservation of Existing Vegetation · Control of Night-time Lighting Glare · Erection of Decorative Screen Hoarding · Management of Construction Activities and Facilities · Reinstatement of Temporarily Disturbed Landscape Areas · Minimize the Direct Conflict with Lion Rock Country Park · Minimize Disturbance on Watercourses |
· Moderate residual landscape impact on LR-1.1, LR-1.2, LR-3.1, LR-3.2, LR-3.3 and LR-4.2 · No discernible change in other LRs identified within the study boundary of the Project |
Landscape Character Areas (LCAs) |
· Substantial landscape impact on LCA-1.2 (Tai Wai Lion Rock Upland and Hillside LCA) and LCA-5.2 (Hung Mui Kuk to Sha Tin Tau Residential Urban LCA) · Moderate landscape impact on LCA-1.1 (Kowloon Tong Lion Rock Upland and Hillside LCA), LCA-1.3 (Sha Tin Tau Lion Rock Upland and Hillside LCA), LCA-1.4 (Kowloon Tong Urban Fringe Upland and Hillside LCA), LCA-2.1 (Kowloon Tong Transportation Corridor LCA), LCA-2.2 (Tai Wai LRT Road Transportation Corridor LCA), LCA-3.2 (Tei Lung Hau Miscellaneous Urban Fringe LCA) and LCA-5.1 (Tai Wai Residential Urban LCA) · Slight landscape impact on LCA-4.1 (Kowloon Tong Residential Urban Fringe LCA) · No discernible change in other LCAs identified within the study boundary of the Project |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Preservation of Existing Vegetation · Control of Night-time Lighting Glare · Erection of Decorative Screen Hoarding · Management of Construction Activities and Facilities · Reinstatement of Temporarily Disturbed Landscape Areas · Minimize the Direct Conflict with Lion Rock Country Park · Minimize Disturbance on Watercourses |
· Moderate residual landscape impact on LCA-1.1, LCA-1.2, LCA-1.3, LCA-1.4, LCA-2.1, LCA-2.2, LCA-3.2, LCA-5.1 and LCA-5.2 · Slight residual landscape impact LCA-4.1 · No discernible change in other LCAs identified within the study boundary of the Project |
Visually Sensitive Receivers (VSRs) |
· Substantial visual impact on R-03, R-04, R-07, I-01, O-04 and T-02 · Moderate visual impact on R-02 and R-06 · Slight visual impact on R-01, R-10, O-01, O-03, T-01, T-03 and T-05 · Insubstantial visual impact on other VSRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Preservation of Existing Vegetation · Control of Night-time Lighting Glare · Erection of Decorative Screen Hoarding · Management of Construction Activities and Facilities · Reinstatement of Temporarily Disturbed Landscape Areas · Minimize the Direct Conflict with Lion Rock Country Park |
· Moderate residual visual impact on R-02, R-03, R-04, R-06, R-07, I-01, O-04 and T-02 · Slight residual visual impact on R-01, R-10, O-01, O-03, T-01, T-03 and T-05 · Insubstantial residual visual impact on other VSRs |
Operation Impact |
|||||
Landscape Resources (LRs) |
· Substantial landscape impact on LR-3.2 (Vegetation on Roadside Engineered Slopes from Tai Wai to Sha Tin Tau) · Moderate landscape impact on LR-1.1 (Vegetation on Natural Terrain), LR-1.2 (Vegetation in Village Areas near Kak Tin), LR-3.1 (Vegetation on Roadside Engineered Slopes in Kowloon Tong), LR-3.3 (Vegetation in Other Roadside Areas) and LR-4.2 (Lung Cheung Road Park) · Slight landscape impact on LR-6.1 (Vegetated Areas in Service Reservoirs and Associated Landscape Areas in Kowloon Side) and LR-6.3 (Vegetated Areas in Fenced-off Area (e.g. vacant land, construction site)) · No discernible change in other LRs identified within the study boundary of the Project |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Compensatory Tree Planting (min. 145 heavy standard trees) for Loss of approximate 2,925 nos. of Existing Trees · Compensatory Woodland Mix Planting (7,720m.sq.) within site (about 2,070 tree whips) and provision of off-site compensation woodland (about 0.3 ha or 1,200 native seedlings/whip trees) · Aesthetically pleasing design of Aboveground Structures · Aesthetically pleasing design of Highways Structures and Slope Associated Structures · Aesthetically pleasing design of footbridges, noise barriers and noise enclosures · Provision of Green Roof · Provision of Buffer Planting / Roadside Planting · Greening Works on Slopes and associated structures |
· Slight residual impact during day 1 of operation and insubstantial residual impact during year 10 of operation on LR-1.1, LR-1.2, LR-3.1, LR-3.2, LR-3.3 and LR-4.2 · Insubstantial residual impact during day 1 and year 10 of operation on other LRs |
Landscape Character Areas (LCAs) |
· Substantial landscape impact on LCA-1.2 (Tai Wai Lion Rock Upland and Hillside LCA) and LCA-5.2 (Hung Mui Kuk to Sha Tin Tau Residential Urban LCA) · Moderate landscape impact on LCA-1.1 (Kowloon Tong Lion Rock Upland and Hillside LCA), LCA-1.3 (Sha Tin Tau Lion Rock Upland and Hillside LCA), LCA-1.4 (Kowloon Tong Urban Fringe Upland and Hillside LCA), LCA-2.1 (Kowloon Tong Transportation Corridor LCA), LCA-2.2 (Tai Wai LRT Road Transportation Corridor LCA), LCA-3.2 (Tei Lung Hau Miscellaneous Urban Fringe LCA) and LCA-5.1 (Tai Wai Residential Urban LCA) · Slight landscape impact on LCA-4.1 (Kowloon Tong Residential Urban Fringe LCA) · No discernible change in other LCAs identified within the study boundary of the Project |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Compensatory Tree Planting (min. 145 heavy standard trees) for Loss of approximate 2,925 nos. of Existing Trees · Compensatory Woodland Mix Planting (7,720m.sq.) within site (about 2,070 tree whips) and provision of off-site compensation woodland (about 0.3 ha or 1,200 native seedlings/whip trees) · Aesthetically pleasing design of Aboveground Structures · Aesthetically pleasing design of Highways Structures and Slope Associated Structures · Aesthetically pleasing design of footbridges, noise barriers and noise enclosures · Provision of Green Roof · Provision of Buffer Planting / Roadside Planting · Greening Works on Slopes and associated structures |
· Slight residual impact during day 1 of operation and insubstantial residual impact during year 10 of operation on LCA-1.1, LCA-1.2, LCA-1.3, LCA-1.4, LCA-2.1, LCA-2.2, LCA-3.2, LCA-4.1, LCA-5.1 and LCA-5.2. · Insubstantial residual impact during day 1 and year 10 of operation on other LCAs |
Visually Sensitive Receivers (VSRs) |
· Substantial visual impact on R-03, R-04, R-07, I-01, O-04 and T-02 · Moderate visual impact on R-02 and R-06 · Slight visual impact on R-01, R-10, O-01, O-03, T-01, T-03 and T-05 · Insubstantial visual impact on other VSRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
· N/A |
· Compensatory Tree Planting (min. 145 heavy standard trees) for Loss of approximate 2,925 nos. of Existing Trees · Compensatory Woodland Mix Planting (7,720m.sq.) within site (about 2,070 tree whips) and provision of off-site compensation woodland (about 0.3 ha or 1,200 native seedlings/whip trees) · Aesthetically pleasing design of Aboveground Structures · Aesthetically pleasing design of Highways Structures and Slope Associated Structures · Aesthetically pleasing design of footbridges, noise barriers and noise enclosures · Provision of Green Roof · Provision of Buffer Planting / Roadside Planting · Greening Works on Slopes and associated structures |
· Moderate residual impact during day 1 of operation and during year 10 of operation on VSRs R-04, R-07, I-01, O-04 and T-02 · Slight residual impact during day 1 of operation and during year 10 of operation on VSRs R-02 and O-03 · Slight residual impact during day 1 of operation and insubstantial residual impact during year 10 of operation on VSRs R-01, R-03, R-06, R-10, O-01, T-01, T-03 and T-05 · Insubstantial residual visual impact during day 1 and year 10 of operation on other VSRs |
Hazard to Life |
|||||
Existing and planned population in the vicinity of the LPG Compound and Project |
· The off-site individual risk level is far below 1×10-5 per year and the societal risk partially falls into the “ALARP” region |
· Annex 4 of the EIAO-TM |
· N/A |
· No adverse impact is anticipated. Nonetheless, implementation of good safety practices during construction phase are recommended. These include: - Establishment of emergency response plans; - Safety/ emergency response training and drills for all personnel; and - Maintain the number of construction workers onsite to a minimum. |
· No adverse residual impact anticipated |