4 Water
Quality Impact. 1
4.1 Introduction.. 1
4.2 Legislation,
Standards, Guidelines and Criteria. 1
4.3 Water
Sensitive Receivers. 8
4.4 Description
of the Environment. 10
4.5 Consideration
of Concurrent Projects. 14
4.6 Identification of Potential Impacts. 16
4.7 Assessment Methodology.. 26
4.8 Evaluation
of Potential Impacts – Construction Phase. 35
4.9 Evaluation
of Potential Impacts – Operational Phase (Project Effluent Discharge). 37
4.10 Evaluation
of Potential Impacts – Operational Phase (Other Water Pollution Sources). 52
4.11 Mitigation
Measures – Construction Phase. 53
4.12 Mitigation
Measures – Operational Phase. 56
4.13 Evaluation
of Cumulative Impacts. 58
4.14 Residual
Water Quality Impacts. 58
4.15 Environmental
Monitoring and Audit (EM&A) Requirements. 58
4.16 Conclusions. 60
List of TABLES
Table 4.1.... Water Quality Objectives for
Tolo Harbour and Channel WCZ.. 4-2
Table 4.2.... Water
Quality Objectives for Victoria Harbour (Phases One, Two and Three) WCZs. 4-4
Table 4.3.... WSD’s
Target Seawater Quality Objectives at Flushing Water Intakes. 4-5
Table 4.4.... Water
Quality Objectives at Seawater Intake of Marine Science Laboratory of CUHK.. 4-6
Table 4.5.... Water
Quality Criteria for Fish Culture Zones. 4-8
Table 4.6.... Baseline
Water Quality Condition for Victoria Harbour WCZ in 2020.. 4-11
Table 4.7.... Baseline
Water Quality Condition for Tolo Harbour and Channel WCZ in 2020.. 4-12
Table 4.8.... Effluent
Standards of Existing TPSTW and Proposed Project. 4-18
Table 4.9.... Reclaimed
Water Requirements – WSD Water Quality Objectives. 4-18
Table 4.10. TPSTW
Discharge (2018 – 2020). 4-20
Table 4.11. Typical
Dry Weather Diurnal Flow Pattern of TPSTW in 2018.. 4-22
Table 4.12. Estimated
Overflow Quantities under Normal Operation.. 4-23
Table 4.13. Proposed
Water Quality Modelling Scenarios. 4-29
Table 4.14. Projects
Affecting Coastline Configurations. 4-32
Table 4.15. Projects
Affecting Bathymetry.. 4-33
Table 4.16. Predicted
Water Quality at Selected WSD Flushing Water Intakes. 4-41
Table 4.17. Predicted
Water Quality at Cooling Water Intakes. 4-41
Table 4.18. Predicted
Water Quality at KTTS / Potential Water Sports Area and To Kwa Wan Typhoon
Shelter 4-42
List of ExhibitS
Exhibit 4.1 Daily
Flow Record of TPSTW in 2018.. 4-19
Exhibit 4.2 Surplus Flow of TPSTW in 2018.. 4-20
Exhibit 4.3 Surplus Flow of TPSTW in 2019.. 4-20
Exhibit 4.4 Surplus Flow of TPSTW in 2020.. 4-21
Exhibit 4.5 Projected Daily Discharge Rate of TPSTW –
Baseline “Do-nothing” Scenario.. 4-22
Exhibit 4.6 Projected Hourly Overflow at Ultimate Design
Stage. 4-23
List of FIGURES
Figure
4.1 Layout of Tolo Harbour
Effluent Export Scheme
Figure
4.2 Location of Existing
Emergency Outfall
Figure
4.3 Water Sensitive
Receivers in Victoria Harbour
Figure
4.4 Water Sensitive
Receivers in Tolo Harbour and Tolo Channel
Figure
4.5 Water Bodies near the
Project site
Figure
4.6 Proposed Interception
and Pumping Scheme
List of Appendices
Appendix
4.1 Correspondences from Intake
Operators
Appendix
4.2A THMB Model Grid Layout and
Coverage
Appendix
4.2B VH Model Grid Layout and
Coverage
Appendix
4.3 Contour Plots of Water Quality
Modelling Results for Victoria Harbour
Appendix
4.4 Contour Plots of Water Quality
Modelling Results for Tolo Harbour and Tolo Channel
Appendix
4.5 Water Quality Modelling
Results for Water Sensitive Receivers in Tolo Harbour and Tolo Channel
Appendix
4.6 Time Series Plots of Water
Quality Modelling Results for THEES Maintenance Discharge
Appendix
4.7 Comparison of Historical Red
Tide and Chlorophyll-a Data Before, During and After Past THEES Maintenance
Discharge
Appendix
4.8 Time Series Plots of Water
Quality Modelling Results for Emergency Discharge
Appendix
4.9 DSD’s Existing Contingency
Plan for Incidents Possibly Encountered in Sewage Treatment Facilities
4
Water Quality Impact
4.1.1
This section presents the
findings of the assessment of potential water quality impacts associated with
the construction and operation of the Project. Suitable mitigation measures
have been recommended to minimize the potential adverse impacts and to ensure
the acceptability of any residual impact after mitigation.
4.2.1
The Technical Memorandum on EIA
Process (EIAO-TM) was issued by EPD under Section 16 of the EIAO. It specifies the assessment method and
criteria that are to be followed in an EIA Study. Reference sections in the EIAO-TM provide the
details of assessment criteria and guidelines that are relevant to the water
quality impact assessment, including:
n
Annex 6 – Criteria for Evaluating Water Pollution; and
n
Annex 14 – Guidelines for Assessment of Water Pollution
4.2.2
The Water Pollution Control
Ordinance (WPCO) provides major statutory framework for the protection and
control of water quality in Hong Kong.
According to the Ordinance and its subsidiary legislation, Hong Kong
waters are divided into ten Water Control Zones (WCZs). Corresponding statements of Water Quality
Objectives (WQOs) are stipulated for different water regimes (marine waters,
inland waters, bathing beaches subzones, secondary contact recreation subzones
and fish culture subzones) in the WCZs based on their beneficial uses.
4.2.3
The Project site is located in
the Tolo Harbour and Channel WCZ. Under
normal operation, the existing TPSTW effluent is discharged to the Victoria
Harbour (Phase Two) WCZ via the THEES.
The Victoria Harbour WCZ has been divided into three phases (namely
Phases One, Two and Three respectively) and the associated marine WQOs for all
the three phases as defined under the WPCO are the same. WQOs for the Tolo Harbour and Channel WCZ and
Victoria Harbour (Phases One, Two and Three) WCZ are listed in Table 4.1 and
Table 4.2
respectively.
Table 4.1 Water Quality Objectives for Tolo Harbour
and Channel WCZ
Parameters
|
Objectives
|
Sub-Zone
|
Offensive odour, tints
|
Not
to be present
|
Whole zone
|
Visible foam, oil scum, litter
|
Not
to be present
|
Whole zone
|
Colour
|
Should
not cause the colour of waters of the subzone to exceed 50 Hazen units at any
time.
|
Inland Waters in Shing Mun (A, C, D,
E, H, I), Tai Po (B, C) subzones and other watercourses
|
Should
not cause the colour of waters of the subzone to exceed 30 Hazen units at any
time.
|
Inland Waters in Shing Mun (B, F,
G), Lam Tsuen (C, D), Tai Po (A)subzones
|
Dissolved oxygen (DO)
|
Not
less than 2mg/L within two metres of the bottom, or not less than 4mg/L in
the remainder of the water column
|
Marine Waters in Harbour Subzone
|
Not
less than 3mg/L within two metres of the bottom, or not less than 4mg/L in
the remainder of the water column
|
Marine Waters in Buffer Subzone
|
Not
less than 4mg/L at any point in the water column
|
Marine Waters in Channel Subzone
|
Not
less than 4 mg/L or 40% saturation (at 150C) at any time
|
Inland Waters
|
pH
|
Not
to cause the normal pH range to be extended by more than ±0.5 pH units at any
time.
|
Marine Waters in Harbour Subzone
|
Not
to cause the normal pH range to be extended by more than ±0.3 pH units at any
time.
|
Marine Waters in Buffer Subzone
|
Not
to cause the normal pH range to be extended by more than ±0.1 pH units at any
time.
|
Marine Waters in Channel Subzone
|
Not
exceed the normal pH range of 6.5 – 8.5 at any time
|
Inland Waters in Shing Mun (A, B, C,
F, G, H), Lam Tsuen (C, D) and Tai Po (A, B, C) subzones
|
Not
exceed the normal pH range of 6.0 – 9.0 at any time
|
Inland Waters in Shing Mun (D, E, I)
subzones and other watercourses
|
Light Penetration
|
Should
not reduce light transmission by more than 20% of the normal level at any
location or any time.
|
Marine Waters in Harbour Subzone
|
Should
not reduce light transmission by more than 15% of the normal level at any location
or any time.
|
Marine Waters in Buffer Subzone
|
Should
not reduce light transmission by more than 10% of the normal level at any
location or any time.
|
Marine Waters in Channel Subzone
|
Salinity
|
Not
to cause the normal salinity range to be extended by more than ±3 parts per
thousand at any time.
|
Marine Waters
|
Temperature
|
Not
to cause the natural daily temperature range to be extended by greater than
±1.0 °C at any location or time. The rate
of temperature change shall not exceed 0.5 °C per hour at any location,
unless due to natural phenomena.
|
Marine Waters
|
Not
to cause the natural daily temperature range to be extended by greater than
±2.0 °C at any location or time.
|
Inland Waters
|
Chemical oxygen
demand (COD)
|
Not
exceed 15 mg/L at any time
|
Inland Waters in Shing Mun (B, F,
G), Lam Tsuen (C, D) and Tai Po (A) subzones
|
Not
exceed 30 mg/L at any time
|
Inland Waters in Shing Mun (A, C, D,
E, H, I), Tai Po (B, C) subzones and other watercourses
|
5-day biochemical
oxygen demand (BOD5)
|
Not
exceed 3 mg/L at any time
|
Inland Waters in Shing Mun (B, F,
G), Lam Tsuen (C, D) and Tai Po (A) subzones
|
Not
exceed 5 mg/L at any time
|
Inland Waters in Shing Mun (A, C, D,
E, H, I), Tai Po (B, C) subzones and other watercourses
|
Suspended solids (SS)
|
Not
to cause the annual median level to exceed 20 mg/L.
|
Inland Waters in Shing Mun (A, B, C,
F, G, H), Lam Tsuen (C, D) and Tai Po (A, B, C) subzones
|
Not
to cause the annual median level to exceed 25 mg/L.
|
Inland Waters in Shing Mun (D, E, I)
subzones and other watercourses
|
Settleable Material
|
Bottom
deposits or submerged objects should not adversely influence bottom-living
communities, alter the basic Harbour geometry or shipping channels, present
any hazard to shipping or diving activities, or affect any other beneficial
use of the waters.
|
Whole zone
|
Ammonia Nitrogen (NH3-N)
|
Not
to exceed 0.5 mg/L at any time
|
Inland Waters
|
E.
coli
Bacteria
|
Not
exceed 610 per 100mL, calculated as the geometric mean of all samples
collected in one calendar year
|
Secondary Contact Recreation Subzone
and Fish Culture Subzones
|
Not
exceed 1000 per 100mL, calculated as a running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days (or 14 and 42
days)
|
Inland Waters in Shing Mun (A, C, D,
E, H, I) and Tai Po (B, C) subzones and other watercourses
|
Not
exceed 0 per 100mL, calculated as a running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days (or 14 and 42
days)
|
Inland Waters in Shing Mun (B, F,
G), Lam Tsuen (C, D) and Tai Po (A) subzones
|
Chlorophyll-a
|
Not
to cause the level of chlorophyll-a
in waters of the subzone to exceed 20 mg/m3, calculated as a
running arithmetic mean of 5 daily measurements for any single location and
depth.
|
Marine Waters in Harbour Subzone
|
Not
to cause the level of chlorophyll-a
in waters of the subzone to exceed 10 mg/m3, calculated as a
running arithmetic mean of 5 daily measurements for any single location and
depth.
|
Marine Waters in Buffer Subzone
|
Not
to cause the level of chlorophyll-a
in waters of the subzone to exceed 6 mg/m3, calculated as a
running arithmetic mean of 5 daily measurements for any single location and
depth.
|
Marine Waters in Channel Subzone
|
Toxic substances
|
Should
not attain such a level as to produce significant toxic effects in humans,
fish or any other aquatic organisms.
|
Whole zone
|
Source: Statement of Water Quality Objectives (Tolo Harbour and
Channel Water Control Zone).
Note: The
delineation of Shing Mun River, Lam Tsuen River and Tai Po River Subzones are
defined in the following website: https://www.elegislation.gov.hk/hk/cap358F!en
Table 4.2 Water
Quality Objectives for Victoria Harbour (Phases One, Two and Three) WCZs
Parameters
|
Objectives
|
Sub-Zone
|
Offensive odour, tints
|
Not
to be present
|
Whole
zone
|
Visible foam, oil scum, litter
|
Not
to be present
|
Whole
zone
|
Colour
|
Should
not cause the colour of waters to exceed 50 Hazen units
|
Inland Waters
|
Dissolved oxygen (DO) within 2m of
the seabed
|
Not
less than 2 mg/L for 90% of the sampling occasions during the whole year
|
Marine
Waters
|
Depth-averaged DO
|
Not
less than 4 mg/L for 90% of the sampling occasions during the whole year
|
Marine
Waters
|
Not
less than 4 mg/L
|
Inland
Waters
|
pH
|
To
be in the range of 6.5 - 8.5, human activity should not cause the natural pH
range to be extended by more than 0.2
|
Marine
Waters
|
Not
exceed the normal pH range of 6.0 – 9.0
|
Inland
Waters
|
Salinity
|
Change
due to human activity not to exceed 10% of ambient salinity level
|
Whole
zone
|
Temperature
|
Change
due to human activity not to exceed 2°C
|
Whole
zone
|
Chemical oxygen demand (COD)
|
Not
exceed 30 mg/L
|
Inland Waters
|
5-day biochemical oxygen demand (BOD5)
|
Not
exceed 5 mg/L
|
Inland Waters
|
Suspended solids (SS)
|
Not
to raise the ambient level by more than 30% caused by human activity, nor
give rise to accumulation of suspended solids which may adversely affect
aquatic communities
|
Marine
Waters
|
Not
to cause the annual median level to exceed 25 mg/L.
|
Inland
Waters
|
Unionized ammonia (UIA)
|
The
un-ionized ammoniacal nitrogen level should not be more than 0.021 mg/L
calculated as the annual average (arithmetic mean)
|
Whole
zone
|
Nutrients
|
Shall
not cause excessive or nuisance growth of algae or other aquatic plants
|
Marine
Waters
|
Total inorganic nitrogen (TIN)
|
Annual
mean depth-averaged inorganic nitrogen not to exceed 0.4 mg/L
|
Marine
Waters
|
E.
coli
Bacteria
|
Not
exceed 1000 per 100mL, calculated as the geometric mean of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days
|
Inland Waters
|
Toxic substances
|
Should
not attain such levels as to produce significant toxic, carcinogenic, mutagenic
or teratogenic effects in humans, fish or any other aquatic organisms, with
due regard to biologically cumulative effects in food chains and to
interactions of toxic substances with each other
|
Whole
zone
|
Human
activity should not cause a risk to any beneficial use of the aquatic
environment
|
Whole
zone
|
Source: Statement of Water Quality Objectives
(Victoria Harbour (Phases One, Two and Three) WCZ)
4.2.4
The Hong Kong Planning
Standards and Guidelines (HKPSG), Chapter 9 (Environment), provides additional
guidelines against water pollution for sensitive uses such as aquaculture and
fisheries zones, bathing waters and other contact recreational waters.
4.2.5
The Water Supplies Department
(WSD) has specified a set of target seawater quality objectives for their
flushing water intakes. The list is
shown in Table 4.3 below. These target objectives will be applied only
at the points of seawater abstraction along the coastlines of inner Tolo
Harbour and Victoria Harbour for flushing purpose.
Table 4.3 WSD’s Target Seawater Quality Objectives at
Flushing Water Intakes
Parameter (in mg/L unless otherwise
stated)
|
WSD’s Target Water Quality Limit at
Flushing Water Intake
|
Colour (Hazen Unit)
|
<
20
|
Turbidity (NTU)
|
<
10
|
Threshold Odour Number (odour unit)
|
<
100
|
Ammonia Nitrogen (NH3-N)
|
<
1
|
Suspended Solids (SS)
|
<
10
|
Dissolved Oxygen (DO)
|
>
2
|
5-Day Biochemical Oxygen Demand (BOD5)
|
<
10
|
Synthetic Detergents
|
<
5
|
E.
coli
(no./100mL)
|
<
20,000
|
Remark:
The above objectives are only applicable to flushing water intakes from
seawater.
4.2.6
The water quality criteria for
cooling water intakes are different from that for the WSD’s intakes as their
beneficial uses are different (the former is used for cooling water system and
the latter for flushing purpose).
Victoria Harbour
4.2.7
There are a number of cooling
water intakes identified in Victoria Harbour. Cooling water intakes in vicinity
of the Project discharge point include the existing and planned cooling water
intakes for Kai Tak District Cooling System
(DCS), cooling water intakes for Yau Tong Bay Ice
Plant, North Point Government Office and Taikoo Place. Based on the information
available from the past relevant EIAs e.g. EIA for Kai Tak Development
(approved in 2009) and EIA for Sha Tin Cavern Sewage Treatment Works (CSTW)
(approved in 2016), no specific water quality requirement is available for
these cooling water intakes. Regarding
the two planned cooling water intakes of Kai Tak DCS at Kai Tak River and Kai
Tak Approach Channel respectively (which are closest to the Project discharge
point) as well as the existing cooling water intake of Kai Tak DCS at Kowloon
Bay, their operator, i.e. Electrical and Mechanical Services Department (EMSD),
has been confirmed under this EIA that no specific water quality criteria are
available for these three DCS intakes. Correspondence from EMSD is provided in Appendix 4.1.
Tolo Harbour
Seawater Intake for Mariculture
4.2.9
One existing seawater intake in
Tolo Harbour is operated by the Marine Science Laboratory of the Chinese
University of HK (CUHK) for experimental maricultural purpose. A summary of the
target seawater quality objectives at this intake point (provided by the intake
operator) is given in Table 4.4 below. Supporting document from CUHK
is attached in Appendix 4.1.
Table 4.4 Water Quality Objectives at Seawater Intake
of Marine Science Laboratory of CUHK
Parameter
|
Target Water Quality Objectives
|
Salinity
|
No more than +/- 2
practical salinity unit (psu) from ambient level;
< 2 psu change
over 1 hour
|
Turbidity
|
<
5 NTU
|
pH
|
7
to 9
|
Unionized
Ammonia (UIA)
|
<
0.05 mg/L
|
Suspended
Solids (SS)
|
<
20 mg/L
|
Dissolved
Oxygen (DO)
|
>
5 mg/L
|
Temperature
|
No more than +/- 2oC
from ambient level; < 2oC change over 1 hour
|
Faecal
coliforms
|
<
10,000 colony forming unit (cfu) per 100 mL
|
Ammonia
Nitrogen (NH3-N)
|
<0.2
mg/L
|
Nitrate
Nitrogen (NO3-N)
|
<
0.5 mg/L
|
Nitrite
Nitrogen (NO2-N)
|
<
0.05 mg/L
|
Hydrogen
Sulphide
|
<0.001
mg/L
|
Source:
Marine Science Laboratory of CHUK
Technical Memorandum on Effluent
Discharge Standard
4.2.10
Besides setting the WQOs, the WPCO
controls effluent discharging into the WCZs through a licensing system.
Guidance on the permissible effluent discharges based on the type of receiving
waters (foul sewers, stormwater drains, inland and coastal waters) is provided
in the Technical Memorandum on Standards for Effluents Discharged into Drainage
and Sewerage Systems, Inland and Coastal Waters (TM-DSS). The limits given in the TM cover the
physical, chemical and microbial quality of effluents. Any effluent discharge during the construction
and operational stages should comply with the relevant standards as stipulated
in the TM-DSS.
Professional Persons Environmental
Consultative Committee Practice Notes
4.2.11
The Professional Persons
Environmental Consultative Committee Practice Note on Construction Site
Drainage (ProPECC PN 1/94) provides good practice guidelines for dealing with
various types of discharge from a construction site. Practices outlined in the ProPECC PN 1/94 should be followed as far as possible
during construction to minimize the water quality impact due to construction
site drainage. The Professional Persons Environmental Consultative Committee
Practice Note on Drainage Plans subject to Comments by Environmental Protection
Department (ProPECC PN 5/93) provides guidelines and practices for handling,
treatment and disposal of various effluent discharges to stormwater drains and
foul sewers. The design of site drainage and disposal of various site effluents
generated within the development area should follow the relevant guidelines and
practices as given in the ProPECC PN 5/93.
4.2.12
Potential impacts on benthic
organisms, including corals, may arise through excessive sediment
deposition. The magnitude of the
potential impacts will be assessed based on the predicted sedimentation rate.
4.2.13
There is no existing
legislative standard on sedimentation rate available. According to Pastorok and Bilyard and Hawker and Connell, a sedimentation rate higher than 100 g/m2/day would
introduce moderate to severe impact upon corals. This sedimentation rate
of no more than 100 g/m2/day will be adopted as the assessment
criterion for protecting the sediment sensitive ecological resources, following
the approach used in the approved EIAs for “CSTW”, “Development of a Bathing
Beach at Lung Mei, Tai Po”, “TPSTW Stage V”, “Wan Chai Development Phase II and
Central-Wan Chai Bypass” and “Sha Tin to Central Link - Hung Hom to Admiralty
Section” etc. This sedimentation rate
criterion is considered to offer sufficient protection to marine ecological
sensitive receivers and is anticipated to guard against unacceptable impacts. This protection has been confirmed by
previous EM&A results which have indicated no adverse impacts to corals
have occurred when this assessment criterion has been adopted.
4.2.14
This sedimentation criterion is
used for protection of important subtidal habitats (e.g. corals) only and hence
it is not applicable to other Water Sensitive Receivers (WSRs) such as bathing
beach users and seawater intakes where the main concern would be on the surface
/ mid-depth water quality.
4.2.15
Several Fish Culture Zones
(FCZs) are identified in the Tolo Harbour as shown in Figure 4.4 below. The water quality criteria for FCZs will follow the Water
Quality Objectives (WQOs) for Tolo Harbour and Channel WCZ stipulated under the
Water Pollution Control Ordinance (WPCO). Table
4.5 summarizes the water quality criteria at FCZs with reference to the
statutory WQOs.
Table 4.5 Water
Quality Criteria for Fish Culture Zones
Parameter (in
mg/L unless otherwise stated)
|
Tolo Harbour and Channel WCZ
|
Harbour Subzone
|
Buffer Subzone
|
Channel Subzone
|
Yim Tin Tsai FCZ
|
Yim Tin Tsai East FCZ
|
Yung Shue Au and Lo Fu Wat FCZs
|
DO Level within
2m from bottom
|
≥ 2
|
≥ 3
|
≥ 4
|
DO Level in remainder
of water column
|
≥ 4
|
≥ 4
|
≥ 4
|
Annual
Geometric Mean E. coli Level
(no./100mL)
|
≤ 610
|
≤ 610
|
≤ 610
|
Running
Arithmetic Mean of 5 daily Measurements of Chlorophyll-a Level
|
≤ 20
|
≤ 10
|
≤ 6
|
Remark: The above water quality criteria
are in accordance with the statutory WQOs for Tolo Harbour and Channel WCZ.
Full descriptions of the WQOs are provided in Table 4.1.
4.3.1
Beneficial uses of the water
system(s) and Water Sensitive Receivers (WSRs) in the assessment areas have
been identified with reference to the relevant topographic maps, aerial photos, Outline Zoning Plans as
well as other published plans and relevant studies as presented below.
Victoria Harbour Water
Control Zone
4.3.2
The treated sewage effluent
from daily operation of the TPSTW would be discharged into the marine water
within the Victoria Harbour WCZ under the THEES. Major marine WSRs identified in Victoria
Harbour are listed below and their indicative locations are given in Figure 4.3.
n
WSD Flushing Water Intakes;
n
Cooling Water Intakes;
n
Typhoon Shelters; and
n
Potential Water Sports Area at Kai Tak.
4.3.3
The feasibility of locating a potential
water sports center within the Kai Tak Development (KTD) area is being
investigated under the separate KTD project. The potential water sports area is
included as a planned WSR. The existing intake of the first District Cooling
System (DCS) plant at Kai Tak (currently in operation) is located at the
ex-airport runway, which abstracts seawater from Kowloon Bay. A new Kai Tak DCS scheme with different
intake locations is currently being planned under the separate KTD
project. The proposed changes in the DCS
intake locations have been considered in this EIA (see Sections 4.5.13 to 4.5.17). The planned Kai Tak DCS intake points are
located in the lower reach of Kai Tak River and the mid-way of Kai Tak Approach
Channel (KTAC).
4.3.4
Kai Tak River (KTR) is a
man-made concrete nullah in highly developed urban land for drainage purpose.
It is designed to receive treated sewage effluent from THEES, urban runoff from
a large catchment area in Diamond Hill, Tsz Wan Shan, Wong Tai Sin, Kowloon
City, San Po Kong and Kai Tak Development Area. The nullah has been continually
modified and disturbed to suit the development needs in the vicinity. Based on the review of river water quality
monitoring data collected by EPD in 2020, the E.coli levels at all the 6
monitoring stations in KTR significantly exceeded the WQO for inland waters.
The BOD5 levels measured at 3 upstream stations in
KTR also exceeded the WQO for inland waters in 2020. The Kai Tak River
Improvement project including reconstruction of the nullah such as deepening
the nullah bed to increase its drainage capacity was completed in 2018.
Although this improvement project also covered works to revitalize the nullah,
the proposed works did not aim to improve the nullah water quality. There is
currently no plan to change the historic and existing uses of this nullah to
receive treated sewage effluent and urban runoff and to alleviate flooding
problem in urbanized area.
4.3.5
Therefore, it is suitable to
consider KTR as an urban drainage and a non-sensitive receiver for the treated
effluent discharge. The same approach has been adopted in the past relevant
EIAs such as the approved EIAs for “CSTW”, “STSTW Stage III Extension” and
“TPSTW Stage V”.
4.3.6
Following the existing disposal
arrangement, only treated effluent that meets the effluent discharge standards
will be diverted to Victoria Harbour WCZ via the THEES. Based on the findings of the approved EIAs
for “STSTW Stage III Extension”, “TPSTW Stage V” and “CSTW”, the water quality
effect of the THEES effluent would mainly be confined within the water bodies
at or near the Kai Tak Development Area as shown in Figure 4.3. The open channel of Victoria Harbour outside the breakwaters of Kwun
Tong Typhoon Shelter (KTTS) has strong tidal flushing capacity and its water
quality would not be adversely affected by the existing THEES discharge. The
coverage of the study area in Figure 4.3 is considered adequate for the purpose of this EIA.
Tolo Harbour and Channel Water Control Zone
n
WSD Flushing Water Intakes;
n
Cooling Water Intake for the proposed District Cooling System at Hong
Kong Science Park;
n
Seawater Intake of Marine Science Laboratory of CUHK;
n
Gazetted Beach at Lung Mei;
n
Shuen Wan Typhoon Shelter;
n
Various Corals / Mangroves along the Coastlines of Tolo Harbour and Tolo
Channel;
n
Fish Culture Zones (FCZs);
n
Hoi Ha Wan Marine Park /Site of Special Scientific Interest (SSSI);
n
Ting Kok SSSI;
n
Kei Ling Ha Mangal SSSI; and
n
Important Nursery Area for Commercial Fisheries Resources .
4.3.8
The marine water in Tolo
Harbour and Channel WCZ are designated under the WPCO as secondary contact
recreation subzone, which can be used for water sports and water recreational
activities (e.g. sailing, rowing). The E. coli bacteria would be the principle
parameter for assessing the acceptability of using waters for water sports or
secondary contact recreation activities with a WQO of not exceeding 610
no./100mL (calculated as the geometric mean of all samples collected in one
calendar year).
4.3.9
Locations of the ecological resources including the corals, mangroves and
SSSIs were identified from literature review and findings of marine ecological
survey carried out in the intertidal and coastal waters around Tai Po
Industrial Estate (TPIE) under this EIA. Descriptions of ecological and
fisheries resources are separately presented in the ecological impact
assessment and fisheries impact assessment of this EIA.
4.3.10
Inland waters within 500m from the site boundary of the Project includes
two modified watercourses to the north of TPIE as shown in Figure 4.5.
The lower reach of both
watercourses is connected to underground man-made culverts in TPIE, which would
eventually discharge to Tolo Harbour. As these inland watercourses are located
at the upstream of the proposed Project works, they would not be affected by
the Project and therefore are not considered as WSR of this Project.
Introduction
4.4.1
The assessment areas for this
water quality impact assessment cover the Tolo Harbour and Channel WCZ and
Victoria Harbour WCZ designated under the WPCO.
4.4.2
The baseline conditions of the
two WCZs were established from the marine water quality monitoring data
collected by EPD. Descriptions of the baseline conditions provided in the
subsequent sections are extracted from the EPD’s report “Marine Water Quality
in Hong Kong in 2020”.
Victoria Harbour Water Control Zone
4.4.3
The water quality monitoring
results at stations in vicinity of the Project discharge, namely VT4, VT11,
VM1, VM2 and VM4 are shown in Table
4.6 below. The selected marine
water quality monitoring stations are shown in Figure 4.3. Full compliances with the
WQO for TIN, DO (depth average and bottom) and UIA were recorded at VT11, VM1,
VM2, VM4 in 2020. The water quality
recorded at VT4 in 2020 breached the WQO for TIN and DO (depth average) whilst
achieved WQO compliance for DO (bottom layer) and UIA.
Table 4.6 Baseline Water Quality Condition for
Victoria Harbour WCZ in 2020
Parameter
|
Victoria Harbour (East)
|
Victoria Harbour (Central)
|
Kwun Tong Typhoon Shelter
|
To Kwa Wan Typhoon Shelter
|
WPCO WQO
(in marine waters)
|
VM1
|
VM2
|
VM4
|
VT4
|
VT11
|
Temperature
(°C)
|
24.0
(19.4 – 28.9)
|
24.3
(19.4 – 29.0)
|
24.5
(19.6 – 28.9)
|
24.7
(20.3 – 29.1)
|
25.3
(19.6-29.1)
|
Change due to human activity not to exceed 2°C
|
Salinity (part
per thousand, ppt)
|
32.3
(31.0 - 33.6)
|
31.7
(28.9 - 33.2)
|
31.4
(28.7 - 33.1)
|
25.9
(20.0 - 29.8)
|
31.3
(29.6 – 32.3)
|
Change due to human activity not to exceed 10% of natural
ambient level
|
Dissolved Oxygen (mg/L)
|
Depth Average
|
5.8
(4.2 – 7.6)
|
5.7
(4.3 – 6.9)
|
5.7
(4.4 - 6.9)
|
4.5
(2.4 – 6.1)
|
5.3
(4.6 - 6.4)
|
Not less than 4
mg/L for 90% of the sampling occasions during the whole year
|
Bottom
|
5.8
(3.6 – 7.5)
|
5.5
(3.8 – 7.2)
|
5.6
(4.0 – 6.9)
|
4.0
(2.2 – 5.2)
|
4.8
(2.7 – 5.7)
|
Not less than 2
mg/L for 90% of the. sampling occasions
during the whole year
|
Dissolved Oxygen (% Saturation)
|
Depth Average
|
83
(61 - 100)
|
81
(62 - 95)
|
81
(64 - 92)
|
62
(33 - 79)
|
77
(69 – 84)
|
Not available
|
Bottom
|
82
(51 - 104)
|
77
(41 - 100)
|
78
(40 - 96)
|
56
(31 - 70)
|
69
(40 – 84)
|
Not available
|
pH
|
7.9
(7.7 - 8.2)
|
7.9
(7.7 - 8.1)
|
7.9
(7.5 - 8.1)
|
7.5
(6.6 - 8.0)
|
7.9
(7.6 - 8.2)
|
6.5 - 8.5 (±
0.2 from natural range)
|
Secchi Disc Depth (m)
|
2.5
(1.8 – 3.0)
|
2.4
(2.1 – 2.9)
|
2.4
(2.0 – 3.1)
|
2.0
(1.3 – 2.7)
|
1.9
(1.2 – 2.6)
|
Not available
|
Turbidity (NTU)
|
4.0
(1.5 – 5.8)
|
3.5
(1.5 – 5.7)
|
3.4
(1.2 – 6.4)
|
3.6
(1.1 - 4.8)
|
6.8
(2.7 – 15.5)
|
Not available
|
Suspended Solids (SS) (mg/L)
|
7.1
(2.4 – 12.0)
|
7.0
(2.6 – 13.7)
|
7.1
(1.6 – 14.3)
|
5.0
(1.2 – 10.5)
|
11.8
(2.6 – 22.8)
|
Not more than
30% increase
|
5-day Biochemical Oxygen Demand (BOD5) (mg/L)
|
0.9
(0.4 – 3.2)
|
0.8
(0.3 – 1.9)
|
0.8
(0.3 – 1.6)
|
1.8
(1.3 – 2.4)
|
0.7
(0.5 – 1.0)
|
Not available
|
Ammonia Nitrogen (NH3-N) (mg/L)
|
0.072
(0.032 - 0.095)
|
0.091
(0.027 - 0.153)
|
0.112
(0.033 - 0.207)
|
1.020
(0.417 – 1.340)
|
0.167
(0.066 – 0.277)
|
Not available
|
Unionized Ammonia (UIA) (mg/L)
|
0.003
(<0.001 - 0.006)
|
0.003
(<0.001 - 0.006)
|
0.004
(<0.001 - 0.007)
|
0.017
(0.007 - 0.038)
|
0.005
(0.003 – 0.007)
|
Not more than
0.021 mg/L for annual mean
|
Nitrite Nitrogen (NO2-N) (mg/L)
|
0.022
(0.006 - 0.060)
|
0.026
(0.007 - 0.072)
|
0.028
(0.007 - 0.070)
|
0.320
(0.150 - 0.430)
|
0.026
(0.006 – 0.060)
|
Not available
|
Nitrate Nitrogen (NO3-N) (mg/L)
|
0.096
(0.034 - 0.217)
|
0.133
(0.036 - 0.277)
|
0.149
(0.051 - 0.287)
|
0.995
(0.363 – 1.340)
|
0.106
(0.023 – 0.163)
|
Not available
|
Total Inorganic Nitrogen (TIN) (mg/L)
|
0.19
(0.12 - 0.34)
|
0.25
(0.12 - 0.43)
|
0.29
(0.15 - 0.45)
|
2.33
(0.93 –3.06)
|
0.30
(0.09 – 0.46)
|
Not more than
0.4 mg/L for annual mean
|
Total Kjeldahl Nitrogen (TKN) (mg/L)
|
0.56
(0. 20 – 1.23)
|
0.61
(0.36 – 1.20)
|
0.62
(0.35 - 1.07)
|
1.57
(0.85– 1.93)
|
0.63
(0.45 – 0.77)
|
Not available
|
Total Nitrogen (TN) (mg/L)
|
0.68
(0.41 – 1.32)
|
0.76
(0.47 – 1.30)
|
0.80
(0.55 – 1.19)
|
2.88
(1.37 – 3.67)
|
0.76
(0.48 – 0.92)
|
Not available
|
Orthophosphate Phosphorus (PO4) (mg/L)
|
0.014
(0.005 - 0.022)
|
0.017
(0.005 - 0.035)
|
0.019
(0.011 - 0.032)
|
0.339
(0.090 - 0.503)
|
0.019
(0.010 – 0.034)
|
Not available
|
Total Phosphorus (TP) (mg/L)
|
0.05
(0.03 - 0.07)
|
0.05
(0.03 - 0.08)
|
0.06
(0.03 - 0.08)
|
0.42
(0.14 - 0.60)
|
0.07
(0.05 – 0.09)
|
Not available
|
Silica (as SiO2) (mg/L)
|
0.83
(0.35 - 1.37)
|
0.90
(0.32 - 1.73)
|
1.01
(0.33 - 1.77)
|
3.65
(1.61– 6.83)
|
0.86
(0.55 – 1.30)
|
Not available
|
Chlorophyll-a (μg/L)
|
2.3
(0.2 – 9.7)
|
3.2
(<0.2 - 14.0)
|
3.1
(0.4 - 12.1)
|
5.4
(1.3 - 12.4)
|
1.2
(0.2 -2.6)
|
Not available
|
E. coli (no./100mL)
|
150
(51 - 1600)
|
240
(59 - 1600)
|
290
(27 - 1200)
|
15000
(600 - 73000)
|
800
(140 - 11000)
|
Not available
|
Faecal Coliforms (no./100mL)
|
300
(83 - 4100)
|
550
(86 - 3300)
|
740
(89 - 4100)
|
32000
(1100 - 280000)
|
1500
(200 – 19000)
|
Not available
|
Notes:
1.
Data
source: EPD Marine Water Quality in Hong Kong in 2020.
2.
Unless
otherwise specified, data presented are depth-averaged (A) values calculated by
taking the means of three depths: Surface (S), Mid-depth (M), Bottom (B).
3.
Data
presented are annual arithmetic means of depth-averaged results except for E.
coli and faecal coliforms that are annual geometric means.
4.
Data in
brackets indicate the ranges.
Trend of Water Quality in Victoria Harbour
4.4.4
The Victoria Harbour WCZ
achieved an overall WQO compliance rate of 90% in 2020, with full compliance
with the DO and UIA WQOs. Under the
influence of regional background level in the Pearl River Estuary as well as
local pollution sources, only 70% of the monitoring stations in the WCZ met the
TIN WQO.
4.4.5
The E. coli level in the eastern side
of Victoria Harbour has decreased markedly since the implementation of Harbour
Area Treatment Scheme (HATS) Stage 1 in 2001.
The annual Cross Harbour Swim, suspended since 1979 because of poor
water quality, was resumed on the eastern side of the harbour in 2011 after
implementation of the HATS Advance Disinfection Facilities (ADF). With full commissioning of the HATS Stage 2A,
the E.coli level of the central harbour area has been further
reduced. Since 2017, the race route of
the event has returned to the traditional route in the central harbour
area.
Tolo Harbour and Channel WCZ
4.4.6
The water quality monitoring
results at stations closest to the existing emergency outfalls of sewage
effluent discharges in Tolo Harbour, namely TM2, TM3 and TM4 in Harbour Subzone
are shown in Table 4.7
below. The selected marine water quality
monitoring stations are shown in Figure 4.4. Full compliances with the
WQO was recorded at all the three selected stations for DO, chlorophyll-a and E. coli in 2020.
Table 4.7 Baseline Water Quality Condition for Tolo
Harbour and Channel WCZ in 2020
Parameter
|
Harbour Subzone
|
WPCO WQO
(in marine waters)
|
TM2
|
TM3
|
TM4
|
Temperature (°C)
|
26.3
(20.6 - 29.8)
|
25.1
(20.2– 29.5)
|
25.6
(20.0 – 29.6)
|
n
Change due to
waste discharge not to exceed 1°C
n The rate of temperature change not to
exceed 0.5 °C per hour, unless due to natural phenomena
|
Salinity (part per thousand, ppt)
|
29.9
(24.8- 32.8)
|
31.0
(24.9- 33.7)
|
30.8
(27.1- 33.1)
|
Change due to
waste discharge not to be greater than ±3ppt
|
Dissolved Oxygen (mg/L)
|
Depth Average
|
6.1
(5.1 – 7.9)
|
6.4
(5.3– 7.2)
|
6.1
(5.1 – 6.5)
|
Not less than 4
mg/L in the water column (except for the bottom water later within 2 m from
the seabed)
|
Bottom
|
6.2
(4.5 – 8.3)
|
5.9
(3.8 – 7.2)
|
5.4
(2.9 – 6.5)
|
Not less than 2 mg/L within 2 m from the seabed
|
Dissolved Oxygen (% Saturation)
|
Depth Average
|
89
(73 - 112)
|
92
(79 - 104)
|
88
(75 - 97)
|
Not available
|
Bottom
|
90
(70 - 120)
|
86
(58 - 110)
|
78
(38 - 99)
|
Not available
|
pH
|
8.0
(7.7 - 8.3)
|
8.0
(7.6 - 8.3)
|
8.0
(7.8 - 8.2)
|
Change due to
waste discharge not to be greater than ± 0.5 from natural range
|
Secchi Disc Depth (m)
|
2.4
(1.6 - 3.4)
|
2.3
(1.5 - 3.2)
|
2.7
(1.8 – 3.5)
|
Not available
|
Turbidity (NTU)
|
3.1
(1.5 – 5.5)
|
2.3
(0.7 – 4.9)
|
2.5
(1.2 - 4.1)
|
Not available
|
Suspended Solids (SS) (mg/L)
|
8.1
(1.4 – 17.0)
|
8.2
(1.4- 19.3)
|
8.5
(1.0 – 18.7)
|
Not available
|
5-day Biochemical Oxygen Demand (BOD5) (mg/L)
|
1.7
(0.8 – 2.6)
|
1.8
(1.2 – 2.9)
|
1.4
(0.7 – 2.5)
|
Not available
|
Ammonia Nitrogen (NH3-N) (mg/L)
|
0.045
(0.022 - 0.076)
|
0.046
(0.011 - 0.127)
|
0.036
(0.019 - 0.076)
|
Not available
|
Unionized Ammonia (UIA) (mg/L)
|
0.003
(<0.001 - 0.005)
|
0.002
(<0.001 - 0.006)
|
0.002
(<0.001 - 0.004)
|
Not available
|
Nitrite Nitrogen (NO2-N) (mg/L)
|
0.004
(<0.002 - 0.010)
|
0.003
(<0.002 - 0.006)
|
0.003
(<0.002 - 0.006)
|
Not available
|
Nitrate Nitrogen (NO3-N) (mg/L)
|
0.039
(<0.002 - 0.215)
|
0.013
(0.002 - 0.049)
|
0.009
(<0.002 - 0.027)
|
Not available
|
Total Inorganic Nitrogen (TIN) (mg/L)
|
0.09
(0.03 - 0.27)
|
0.06
(0.02 - 0.16)
|
0.05
(0.02 - 0.11)
|
Not available
|
Total Kjeldahl Nitrogen (TKN) (mg/L)
|
0.50
(0.22 - 0.81)
|
0.56
(0.25 - 0.86)
|
0.56
(0.30 - 0.85)
|
Not available
|
Total Nitrogen (TN) (mg/L)
|
0.54
(0.29 - 0.82)
|
0.57
(0.30 - 0.86)
|
0.57
(0.31- 0.85)
|
Not available
|
Orthophosphate Phosphorus (PO4) (mg/L)
|
0.008
(0.002 - 0.026)
|
0.006
(0.003 - 0.014)
|
0.005
(<0.002 - 0.007)
|
Not available
|
Total Phosphorus (TP) (mg/L)
|
0.04
(<0.02 - 0.06)
|
0.04
(<0.02 - 0.06)
|
0.03
(<0.02 - 0.05)
|
Not available
|
Silica (as SiO2) (mg/L)
|
1.48
(0.50 – 4.15)
|
0.84
(0.15 - 2.13)
|
0.82
(0.29 - 1.80)
|
Not available
|
Chlorophyll-a
(μg/L)
|
5.8
(1.4 – 9.2)
|
5.8
(2.1 - 15.7)
|
5.2
(1.5 – 14.3)
|
Not to exceed
20 μg/L for a running arithmetic mean of 5 daily measurements
|
E. coli (no./100mL)
|
13
(<1 - 4500)
|
18
(<1 - 2700)
|
5
(<1 - 490)
|
Not to exceed
610 no./100mL for geometric mean
|
Faecal Coliforms (no./100mL)
|
76
(6 - 32000)
|
76
(1 - 13000)
|
23
(1 - 3100)
|
Not available
|
Notes:
1.
Data
source: EPD Marine Water Quality in Hong Kong in 2020.
2.
Unless
otherwise specified, data presented are depth-averaged (A) values calculated by
taking the means of three depths: Surface (S), Mid-depth (M), Bottom (B).
3.
Data
presented are annual arithmetic means of depth-averaged results except for E.
coli and faecal coliforms that are annual geometric means.
4.
Data in
brackets indicate the ranges.
Trend of Water Quality in Tolo Harbour and Channel
4.4.7
The overall marine WQO
compliance rate for the Tolo Harbour and Channel WCZ in 2020 was 93% as
compared to 79% in 2019. The compliance
rate for the DO WQO maintained at 57%, same as 2018 and 2017. Furthermore, the Tolo Harbour and Channel
WCZ consistently complied with the bacteriological WQO for the secondary
contact recreation uses applicable to the entire marine water of the WCZ.
4.4.8
Tolo Harbour, however, was
subject to a natural hydrological phenomenon of water stratification and
associated lower bottom DO level due to restricted water exchange with open
waters.
4.4.9
Upon the implementation of the
Tolo Harbour Action Plan since the mid-1980s, there has been a marked
improvement in the water quality in Tolo Harbour in the past three
decades.
Project Programme
4.5.1
The construction works of this
Project are tentatively scheduled to commence in 2025 for completion in
2036.
4.5.2
The key components of the THEES
and the existing TPSTW effluent disposal arrangement are described in Section 4.1.2. Currently, the treated effluent from TPSTW
would occasionally exceed the capacity of the TPEPS due to the effect of storm
and hence part of the treated effluent from TPSTW would be discharged to the
Tolo Harbour via the existing emergency bypass outfall at TPSTW. Similarly, the
combined flow from TPSTW and STSTW would also occasionally exceed the capacity
of STEPS due to the storm effect and overflow of the combined effluent would be
discharged into the Tolo Harbour via the existing emergency submarine outfall
of STSTW.
Proposed THEES Upgrading
4.5.6
The proposed THEES upgrading
works involve construction of a new TPEPS, a new submarine pipeline and a new
effluent rising mains. The THEES upgrading works are tentatively scheduled to
commence in 2025 for completion in 2031, subject to the construction programme
of this Project (upgrading of TPSTW) and the CSTW project.
4.5.7
The new submarine pipeline will
be installed by the Horizontal Directional Drilling (HDD) method, which is a
trenchless method with no disturbance to the seabed and marine habitat. The proposed driving pit and reception pit of
the HDD works would be land-based and located at the helipad in TPIE (within
the assessment area) and Pak Shek Kok (outside the assessment area)
respectively. The new rising mains will be laid in the southern TPIE (within
the assessment area) connecting between the new TPEPS and the new submarine
pipeline.
4.5.8
At the time of preparing this
EIA, “Agreement No. CE 13/2015 (DS) Review of Sewerage Infrastructure of THEES
– Feasibility Study” is still on-going and therefore the design of the proposed
THEES upgrading project is subject to further update. The design assumptions
presented in this EIA represent the best available information for use in this
water quality impact assessment.
Proposed Shuen Wan Golf Course
4.5.9
The proposed Shuen Wan Golf
Course (SWGC) is located to the east of the Project site. It mainly involves
the development of a new golf course within the existing Shuen Wan Restored
Landfill (SWRL) site. According to the EIA Report for SWGC, the construction of
the proposed SWGC would be completed by end 2023 prior to the construction of
this Project.
Proposed Organic Waste
Pre-treatment Centre
Proposed District Cooling
System at Hong Kong Science Park
4.5.12
The key water quality concerns
of the proposed DCS operation would be associated with the spent cooling water
discharges including the spreading of thermal plume and release of anti-fouling
agent or biocide (e.g. residual chlorine, C-Treat-6) into the marine
environment. As this Project would not induce any thermal impact nor discharge
of fouling agent/ biocide, there will not be any cumulative water quality
impact due to the DCS operation.
Kai Tak Development – Interception and Pumping Scheme
4.5.14
Based on the latest information
from Agreement No. CE 30/2008 (CE) obtained from Civil Engineering and Development Department (CEDD),
a new Interception and Pumping (IP) Scheme will be implemented under the Kai
Tak Development (KTD). The proposed IP Scheme would involve one cooling water
intake point at the lower reach of KTR and another intake point at the mid-way
of KTAC. The water pumped from KTR and KTAC will be diverted to three Kai Tak
DCS Plants (namely existing DCS South Plant, proposed Additional DCS North
Plant and proposed 3rd DCS Plant) and all the spent water would be
discharged into the Kowloon Bay as shown in Figure 4.6.
4.5.15
The proposed IP scheme would
divert the water in the embayed areas at KTR and KTAC to the more open water in
Kowloon Bay and would therefore improve the water circulation and water quality
in KTAC.
Construction Phase
4.6.2
With reference to Sections 4.1.2 and 4.5.2, during normal operation, any effluent bypass
from TPSTW to the Tolo Harbour will be discharged through the existing
emergency outfall at the seawall (to the south of TPIE) as shown in Figure 4.2. This existing emergency
outfall is in the form of underground sewage pipeline for diverting the
effluent from TPEPS to the seawall. The existing sewage pipeline has been
reviewed to have sufficient capacity to handle the maximum design flow of this
Project. No outfall construction / modification will be required for this
Project. This Project will not disturb the seawall and marine sediments and
will not affect the sediment quality.
4.6.3
Only land-based construction
will be carried out under the Project. The construction works will be
undertaken at TPIE within Tolo Harbour and Channel WCZ only. No construction
works will be undertaken in the Victoria Harbour WCZ. The proposed construction works will not
alter any inland waters such as natural streams, watercourses and ponds as identified
in Section 4.3.10. Decommissioning and demolition of existing
facilities in the proposed expansion site is outside the scope of this Project
and not considered in this assessment.
4.6.4
Potential sources of water
quality impact associated with the Project during the construction phase are
identified as follows:
n
General land-based construction activities;
n
Construction site run-off;
n
Accidental chemical spillage;
n
Sewage effluent from construction workforce;
n
Contaminated site runoff; and
n
Demolition works.
Operational
Phase – Project Effluent Discharge
4.6.6
With reference to the latest
population and employment forecast available from the 2019-based TPEDM, the
proposed design capacity of this Project of 160,000 m3/day has been
reviewed to be sufficient to cater for the sewage flow generated from the
future developments within the catchment of TPSTW in Year 2041. The existing
treatment process of TPSTW is secondary treatment works plus disinfection. The
current treatment levels and the associated effluent standards of the existing
TPSTW will be maintained for this Project as summarized in Table 4.8.
Table 4.8 Effluent Standards of Existing TPSTW and
Proposed Project
Parameter
|
Unit
|
95th
percentile
|
Maximum
|
Annual
Average
|
Monthly
Geometric Mean
|
5-day Biochemical Oxygen
Demand (BOD5)
|
mg/L
|
20
|
40
|
-
|
-
|
Total Suspended Solids
(TSS)
|
mg/L
|
30
|
60
|
-
|
-
|
Total Nitrogen (TN)
|
mg/L
|
-
|
35
|
20
|
-
|
Ammonia Nitrogen (NH3-N)
|
mg/L
|
-
|
10
|
5
|
-
|
E. coli
|
counts/100mL
|
15,000
|
-
|
-
|
1,000
|
Treated Sewage Effluent
Reuse for Non-potable Use
4.6.8
The spent reclaimed water would
be eventually discharged back to the treatment works for treatment again and
would not contribute to additional pollution load to the water environment.
Thus, no additional impact on the water environment will be induced by the TSE
reuse. The reclaimed water
standards provided by Water Supplies Department (WSD) are shown in Table 4.9. Tertiary treatment will be provided in the reuse facility to treat
the TSE. The treated TSE from the reuse facility will meet the WSD’s standards.
Table 4.9 Reclaimed
Water Requirements – WSD Water Quality Objectives
Parameter
|
Unit
|
Reclaimed Water Quality
|
E. coli
|
cfu/100mL
|
Non detectable
|
Total Residual Chlorine
|
mg/L
|
≥1 (existing treatment system)
|
Dissolved Oxygen (DO)
|
mg/L
|
≥2
|
TSS
|
mg/L
|
≤5
|
Colour
|
Hazen Unit (HU)
|
≤20
|
Turbidity
|
NTU
|
≤5
|
pH
|
-
|
6 to 9
|
Odour
|
Threshold odour no.
|
≤100
|
BOD5
|
mg/L
|
≤10
|
NH3-N
|
mg/L as N
|
≤1
|
Synthetic Detergents
|
mg/L
|
≤5
|
Note: Information provided and
confirmed by Water Supplies Department
4.6.9
Some of the treated effluent from
the Project will be directly reused in the sewage treatment process (e.g. for
polymer preparation) within the Project site. Partially treated sewage,
including but not limited to surplus activated sludge (SAS), supernatant from
thickened SAS, primary effluent from the Project, may also be explored for
directly reuse in the treatment process (e.g. for imported sludge dilution)
within the Project site.
4.6.10
Some treated effluent of the
Project will be transferred to the proposed OWPC directly for use in the food
waste pre-treatment process or dilution of food waste.
4.6.11
All the treated effluent and/or
partially treated sewage to be used in the treatment process of this Project
and the proposed OWPC will be conveyed and handled within an automatic
close-loop system without direct human contact. All treated effluent and/or
partially treated sewage will be conveyed through enclosed pipelines. Water quality impact associated with the possible spillage during
transportation of the treated/partially treated sewage effluent is not
expected.
4.6.12
Any spent treated effluent and/or partially treated effluent will be transferred back to sewerage system or the treatment units of this Project by
fully enclosed pipelines for further treatment. No adverse water quality impact
and human health concern will arise.
Treated Effluent
Overflow to Tolo Harbour under Normal Plant Operation
Baseline “Do-nothing” Scenario
4.6.13
Under the baseline scenario, no
upgrading of TPSTW and TPEPS would be carried out. The design capacity of TPSTW
and TPEPS would remain to be 120,000 m3/day and 4,752 m3
per hour respectively. The CSTW project is currently under construction and
will be included in the baseline scenario.
4.6.15
The quantities of overflow
bypass would be subject to the effect of storm. Based on the review of past
overflow records of TPSTW (from 2013 to 2018) conducted under Agreement No. CE
13/2015 (DS)[7], the low flow periods
where storm events are rare occur in 1-16 January and 16-31 December.
4.6.16
The peaking factor analysis
covering the period from 2013 to 2018 carried out under Agreement No. CE
13/2015 (DS) concluded that TPSTW has the highest peaking factor in 2018. The
discharge record for 2018 as shown in Exhibit 4.1 below are therefore used to estimate the
overflow quantities of TPSTW. The recorded average dry weather flow (ADWF) of
TPSTW in 2018 was about 110,300m3/day. This value is used as
benchmark and any days with surplus flow above this ADWF value is assumed to be
wet days with storm events.
Exhibit 4.1 Daily Flow
Record of TPSTW in 2018
4.6.17
4.2 below shows
the surplus flow recorded in 2018. Similar analysis has been conducted
under this EIA using the latest daily flow record of TPSTW in 2019 and 2020.
The resulted surplus flow of TPSTW in 2019 and 2020 is shown in Exhibit 4.3
and Exhibit 4.4. Both the peak surplus flow value and the annual surplus
flow volume in 2019 and 2020 are smaller than those recorded in 2018. Therefore, using the surplus flow of 2018 in
estimation of the overflow quantities is conservative and appropriate. The average and maximum daily discharge of TPSTW from 2018
to 2020 are summarized in Table 4.10.
Table 4.10 TPSTW Discharge
(2018 – 2020)
Year
|
Average
Daily Effluent Flow (m3)
|
Maximum
Daily Effluent Flow (m3)
|
2018
|
118,263
|
212,539
|
2019
|
118,833
|
199,888
|
2020
|
111,607
|
192,466
|
Exhibit 4.2 Surplus Flow
of TPSTW in 2018
Exhibit 4.3 Surplus
Flow of TPSTW in 2019
Exhibit 4.4 Surplus Flow of TPSTW in 2020
4.6.18
The surplus for each wet day is
allocated to the existing design ADWF of TPSTW (i.e. 120,000 m3/day)
on the same day to take into account of the effect of storm events. The plot of
the projected daily discharge rate of TPSTW under the baseline “without
Project” scenario assuming a design daily flow of 120,000 m3/day is shown in Exhibit 4.5.
Exhibit 4.5 Projected
Daily Discharge Rate of TPSTW – Baseline “Do-nothing” Scenario
4.6.19
The typical dry weather diurnal
flow pattern of TPSTW in 2018 is shown in Table 4.11. The percentages in the tables are applied to
the existing design ADWF of TPSTW (i.e. 120,000 m3/day) to derive
the hourly dry weather diurnal flow of TPSTW. Latest dry weather diurnal flow
record after 2018 is not available from DSD.
Table 4.11 Typical Dry Weather Diurnal Flow Pattern of
TPSTW in 2018
Hour
|
% of
Daily Flow
|
Hour
|
% of
Daily Flow
|
Hour
|
% of
Daily Flow
|
Hour
|
% of
Daily Flow
|
0:00
|
4.72%
|
6:00
|
3.08%
|
12:00
|
4.34%
|
18:00
|
4.16%
|
1:00
|
4.13%
|
7:00
|
3.68%
|
13:00
|
4.47%
|
19:00
|
4.24%
|
2:00
|
3.58%
|
8:00
|
4.06%
|
14:00
|
4.83%
|
20:00
|
4.39%
|
3:00
|
3.44%
|
9:00
|
4.66%
|
15:00
|
4.57%
|
21:00
|
4.66%
|
4:00
|
3.32%
|
10:00
|
4.24%
|
16:00
|
4.16%
|
22:00
|
4.97%
|
5:00
|
3.13%
|
11:00
|
4.20%
|
17:00
|
4.01%
|
23:00
|
4.95%
|
Source: Agreement No.
CE 13/2015 (DS)
4.6.20
The storm flow generated from
each wet day is assumed to be contributed from a 4-hour storm event. The
surplus flow for each wet day in Exhibit 4.2 is allocated to the dry weather
diurnal flow on the same day between 20:00 and 23:00. As the highest diurnal
flow rates are observed between 20:00 and 23:00 in Table 4.11,
allocating the surplus flow for each wet day to this period would represent a
reasonable worst case. When the combined volume of surplus flow (if any) and
dry weather diurnal flow of the TPSTW exceeds the existing capacity of TPEPS of
4752 m3/hour, the effluent would overflow into Tolo Harbour. The
hourly overflow rates at the ultimate design stage are estimated for a complete
calendar year as shown in Exhibit 4.6 below. Due to the capacity
constraint of the existing TPEPS, overflow from TPSTW would occur in both dry
and wet seasons. The annual overflow volume under the “do-nothing” scenario is
estimated to be about 6,842,000 m3.
The annual overflow volume estimated under the approved EIA for “TPSTW
Stage V” is larger because a larger design flow of 130,000 m3/day was assumed in that EIA.
“With Project” Scenario
4.6.21
The “with Project” scenario
assumes that the capacities of TPSTW and TPEPS will be upgraded.
4.6.22
The typical dry weather diurnal
flow pattern of TPSTW in Table 4.11 above is applied to the design flow of the Project (i.e.
160,000 m3/day) to derive the hourly dry weather diurnal discharge.
The surplus flow for each wet day estimated in Exhibit 4.2 above is
allocated to the projected dry weather diurnal flow of the Project on the same
day between 20:00 and 23:00. When the combined volume of surplus flow (if any)
and projected dry weather diurnal discharge from the Project exceeds the
capacity of the new TPEPS allowed for
TPSTW of 12,996 m3 per hour (see Section 4.5.4), the
effluent would overflow into Tolo Harbour.
4.6.23
The hourly overflow rates under
the “with Project” scenario are estimated for a complete year as shown in Exhibit
4.6 below.
Exhibit 4.6 Projected Hourly Overflow at Ultimate Design
Stage
4.6.24
The hourly overflow estimated
under the “do-nothing” scenario (as discussed in Sections 4.6.14 to 4.6.20 above) are included in Exhibit 4.6 for
comparison. Under the “do-nothing” scenario, overflow would occur every day
over the entire year with an annual overflow volume of 6,842,000 m3.
Due to the THEES upgrading, the estimated annual overflow volume under the
“with Project” scenario is much smaller and reduced to 632,000 m3
(i.e. reduced by 91% as compared to the baseline “do-nothing” scenario). Under
the “with Project” scenario, overflow would occur occasionally on 30 days of a
year only, and the occurrences would be scattered within the period June to
September (in wet season). The overflow volumes estimated for the “do-nothing”
scenario and the “with Project” scenario are presented in Table 4.12.
Table 4.12 Estimated
Overflow Quantities under Normal Operation
Scenario
|
TSE Discharge of TPSTW (m3
per day)
|
Design Capacity of TPEPS
Allowed for the Project (m3 per hour)
|
Overflow Volume,
June to September
(Wet Season)
(m3)
|
Overflow Volume,
Remaining Months (January
to May and October to December) (m3)
|
Annual Overflow Volume (m3)
|
Baseline “Do-nothing”
Scenario
|
120,000
|
4,752
|
3,481,000
|
3,361,000
|
6,842,000
|
“With Project” Scenario
|
160,000
|
12,996
|
632,000
|
0
|
632,000
|
Percentage Reduction of Overflow Volume:
|
82%
|
100%
|
91%
|
4.6.26
Overflow of treated effluent
from the new CSTW would not arise under normal plant operation (see Section 4.5.3 to 4.5.5).
Treated Effluent Discharge to
Victoria Harbour under Normal Plant Operation
4.6.27
The Treated Sewage Effluent
(TSE) from this Project and the new CSTW will be discharged to the Victoria
Harbour via the THEES. The THEES effluent will be discharged to the KTR and
then eventually to the KTAC. The design flow of this Project (i.e. 160,000 m3/day)
is adopted for discharging to the Victoria Harbour WCZ, assuming that there
would be no TSE reuse as a worst-case scenario.
THEES Maintenance Discharge to Tolo Harbour
4.6.29
During the THEES maintenance
period, effluent bypass from the upgraded TPSTW would occur at the existing
emergency outfall of TPSTW at Tai Po. Effluent bypass from the existing STSTW or the future CSTW would occur at the
existing emergency submarine outfall in Sha Tin Hoi as shown in Figure 4.4. The effluent bypass from
both the future upgraded TPSTW and the future CSTW during THEES maintenance
period would be secondarily treated and disinfected. The key issues of concern
would be the temporary increase in water pollution such as the increase of
nutrients in Tolo Harbour.
4.6.32
The
design flow of this Project (i.e. 160,000 m3/day) is adopted as the daily Project discharge rate during the THEES
maintenance period.
Emergency Discharge of
Partially Treated Sewage Effluent to Tolo Harbour
4.6.33
Water quality impact could
arise from emergency discharge from this Project in case of power / plant
failure. The key issues of concern would be the temporary increase in water
pollution such as the depletion of oxygen and increase of nutrients and E. coli bacteria in Tolo Harbour.
4.6.34
Emergency discharge of sewage
effluent from the future upgraded TPSTW, if any, would be discharged via the
existing emergency outfall of TPSTW.
4.6.35
Based on the past discharge
record of TPSTW, emergency sewage discharge had occurred only once since 1995
due to CLP power supply failure to TPSTW Stage IV inlet works. The duration of the emergency discharge from
TPSTW was less than 3 hours with a total discharge volume of less than 9,000 m3. For modelling purpose of this EIA, emergency
discharge from this Project is assumed to continuously occur for 3 hours.
4.6.36
In accordance with the
Environmental Permit (EP) of “TPSTW Stage V” obtained in 2004, dual power
supply or ring main supply from CLP, standby equipment and treatment units have
been provided for the existing TPSTW to prevent the occurrence of emergency
discharge. Since then, emergency discharge to Tolo Harbour from the existing
TPSTW had never happened again.
4.6.37
If dual power or ring main
supply, standby equipment and treatment units are provided for this Project,
the model assumption of total plant failure for a 3-hour period would be a very
conservative scenario.
4.6.39
Concurrent emergency discharge
from both TPSTW and STSTW had never occurred before. According to the EIA for
“CSTW”, backup power supply, standby equipment and standby treatment units will
also be provided for the future CSTW.
Hence, plant failure from both the upgraded TPSTW and CSTW together is
not expected and will not be further considered in this assessment.
Summary of Potential Impacts
from Treated Sewage Effluent
n
Discharge of TSE from the Project to the Victoria Harbour via THEES under
normal plant operation;
n
Discharge of TSE from the Project to Tolo Harbour under THEES maintenance
event; and
n
Discharge of partially treated sewage from the Project to Tolo Harbour
under emergency situations.
Operational Phase –
Other Water Pollution Sources
n
Possible spillage or rainwater wash off during transportation or handling
of the pre-treated food waste;
n
Wastewater generated from the sludge treatment / dewatering facility,
pre-treated food waste reception facility and the facility for co-digestion
of pre-treated food waste;
n
Non-point source surface run-off from the Project site; and
n
Possible spillage of chemicals (e.g. ferried chloride and polymer) during
the handling, storage and transferring of the chemicals.
Construction Phase
4.7.1
The WSRs that may be affected
by the Project have been identified. Potential
sources of water quality impact that may arise during the construction of the
Project were described. All the
identified sources of potential water quality impact were then evaluated and
their impact significance determined. The need for mitigation measures to
reduce any identified adverse impacts on water quality to acceptable levels was
determined.
Operational Phase –
Project Effluent Discharge
Modelling Tools
4.7.2
Computer modelling is used to
assess the water quality impacts due to the partially treated/ treated or
untreated sewage effluent discharge during the operational phase.
4.7.3
Delft3D suite of models,
developed by Deltares, are used as the modelling platforms with the
Deflt3D-FLOW module and the Delft3D-WAQ module used for hydrodynamic simulations
and water quality simulations respectively.
To simulate the potential impact from the Project on both Tolo Harbour
and Victoria Harbour, two Delft3D models are adopted respectively:
n
Tolo Harbour and Mirs Bay (THMB) Model; and
n
Victoria Harbour (VH) Model.
4.7.4
Delft3D-FLOW is a 3-dimensional
hydrodynamic simulation programme which calculates non-steady flow and
transport phenomena that result from tidal and meteorological forcing on a
curvilinear, boundary fitted grid.
4.7.5
Delft3D-WAQ is a water quality
model tool for numerical simulation of various physical, biological and
chemical processes including the sedimentation and sediment erosion processes
in 3 dimensions. It solves the advection-diffusion-reaction equation for a
predefined computational grid and for a wide range of model substances.
THMB Model
4.7.6
The THMB Model was developed by
EPD under Agreement No. WP01-27 . The model was fully calibrated and verified
by comparing computational results with field measurements. The THMB model was
subsequently accepted by EPD for directly use under the approved EIAs for
“CSTW” and “TPSTW Stage V” for hydrodynamic and water quality modelling in Tolo
Harbour. No changes to the model set up
of the THMB Model such as the grid layout, model parameters and process
coefficients are proposed. The grid layout and coverage of the THMB Model are
shown in Appendix
4.2A.
VH Model
4.7.7
The VH Model is based on the
model setup developed under Agreement No. CE 30/2008 (CE) as presented in the Water
Quality Modelling Report obtained from CEDD in
2020. The model was fully calibrated and verified with field measurement
data. The same model setup was applied
in the latest modelling submissions of KTD obtained from CEDD as well as in the approved EIA for “CSTW” for
hydrodynamic and water quality modelling in KTAC. The grid layout and coverage of the VH Model
are shown in Appendix 4.2B.
Modelling Scenarios
Discharge to Victoria Harbour
4.7.9
Scenario 1a - Baseline “Do-nothing” Scenario (Design Effluent
Quality)
n Normal operation of TPSTW with an
ADWF of 120,000 m3/day to Victoria Harbour.
n Design effluent standards are applied to the ADWF for deriving the THEES loading.
4.7.10
Scenario 1b - “With Project” Scenario (Design Effluent Quality)
n Normal
operation of the Project with an ADWF of 160,000 m3/day to Victoria
Harbour.
n Design effluent
standards are applied to the ADWF for deriving the THEES loading.
4.7.11
Scenario 2a - Baseline “Do-nothing” Scenario (Measured Effluent Quality)
n This is a more realistic worst-case scenario, see Note (6) under Table 4.13.
4.7.12
Scenario 2b - “With Project” Scenario (Measured Effluent Quality)
n Same as Scenario 1b except that the 95th percentile
effluent quality values from actual measurements were employed to derive the
THEES loading.
n This is a more realistic worst-case scenario, see Note (6) under Table 4.13.
Discharge to Tolo Harbour
4.7.13
Scenario 3 – Normal Project Operation
n Occasional overflow of TSE from the Project under normal operation
as illustrated in Exhibit 4.6 and
discussed in Section 4.6.22.
n Normal Project operation will not induce any water quality impact in
Tolo Harbour, see Section 4.6.25. This
scenario serves only as a baseline for comparison with the THEES maintenance
and emergency discharge scenarios.
4.7.14
Scenario 4 - THEES Maintenance
n Discharge of THEES effluent (only TSE involved) into Tolo Harbour
for 4 weeks (outside the algae blooming season), see Section 4.6.31.
n Maintenance discharge from the Project is assumed to be 160,000 m3/day
(with no TSE reuse).
n Background Project discharge under Scenario 3 is adopted outside the
THEES maintenance period.
4.7.15
Scenario 5 - Emergency Discharge
n Emergency discharge of primarily treated / settled effluent from the
Project into Tolo Harbour under complete power / plant failure for 3 hours in
wet season, see Section 4.6.38.
n The total emergency discharge would be about 20,000 m3.
n Background Project discharge under Scenario 3 is adopted outside the
emergency discharge period.
4.7.16
Details of the modelling
scenarios are presented in Table 4.13.
Table 4.13 Proposed
Water Quality Modelling Scenarios
Scenario
|
Phase
|
Effluent Flow
|
Description
|
Effluent
|
BOD5
(mg/L)
|
SS
(mg/L)
|
TKN
(mg/L)
|
TN
(mg/L)
|
NH3-N
(mg/L)
|
E. coli (no./100mL)
|
Victoria Harbour
|
1a (UDS)
|
Baseline “do-nothing” scenario (design effluent
standards)
|
120,000 m3/day (TPSTW) (1) +
340,000 m3/day (CSTW)
|
· Interception and Pumping
(IP) Scheme is adopted to divert some water from KTR and KTAC to Kowloon Bay,
see Sections 4.5.13 to 4.5.17.
· THEES loading based on design effluent standards of TPSTW and CSTW.
|
TPSTW
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (4)
|
1,000 (4)
|
CSTW
|
20 (5)
|
30 (5)
|
13.28 (5)
|
20 (5)
|
5 (5)
|
1,000 (5)
|
1b (UDS)
|
“With Project” Scenario (design effluent standards)
|
160,000 m3/day (upgraded TPSTW) +
340,000 m3/day (CSTW)
|
· IP Scheme is
adopted to divert some water from KTR and KTAC to Kowloon Bay, see Sections 4.5.13 to 4.5.17.
· THEES loading based on design effluent standards of this Project and
CSTW.
|
This Project
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (4)
|
1,000 (4)
|
CSTW
|
20 (5)
|
30 (5)
|
13.28 (5)
|
20 (5)
|
5 (5)
|
1,000 (5)
|
2a (UDS)
|
Baseline “do-nothing” scenario (measured effluent
quality)
|
120,000 m3/day (TPSTW) (1) +
340,000 m3/day (CSTW)
|
· IP Scheme is
adopted to divert some water from KTR and KTAC to Kowloon Bay, see Sections 4.5.13 to 4.5.17.
· THEES loading
input based on actual performance of TPSTW and STSTW (with the same treatment
level of this Project and CSTW)
|
TPSTW
|
6.60(6)
|
14.25 (6)
|
9.37 (6)
|
14.08 (6)
|
7.22 (6)
|
1,000 (4)
|
CSTW
|
9.40 (5)
|
20.15 (5)
|
5.04 (5)
|
17 (5)
|
2.64 (5)
|
1,000 (5)
|
2b (UDS)
|
“with Project” Scenario (measured effluent quality)
|
160,000 m3/day (upgraded TPSTW) +
340,000 m3/day(CSTW)
|
· Use of IP Scheme
to divert some water from KTR and KTAC to Kowloon Bay, see Sections 4.5.13 to 4.5.17.
· THEES loading
input based on actual performance of TPSTW and STSTW (with the same treatment
level of this Project and CSTW)
|
This Project
|
6.60(6)
|
14.25 (6)
|
9.37 (6)
|
14.08 (6)
|
7.22 (6)
|
1,000 (4)
|
CSTW
|
9.40 (5)
|
20.15 (5)
|
5.04 (5)
|
17 (5)
|
2.64 (5)
|
1,000 (5)
|
Tolo Harbour
|
3
(UDS)
|
Baseline Scenario (with no THEES maintenance and no
emergency discharge)
|
Reduced Project overflow (as shown in Exhibit 4.6
above) was applied as the background discharge
|
· Serves
as a baseline for comparison with Scenarios 4 and 5 to assist in identifying
the water quality impact from THEES maintenance and emergency situations.
|
This
Project
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (4)
|
1,000 (4)
|
4 (UDS)
|
THEES maintenance
|
During THEES Maintenance:
160,000 m3/day (from upgraded TPSTW) +
340,000 m3/day (from CSTW)
Outside THEES Maintenance Period:
Reduced Project overflow (as shown in Exhibit 4.6
above) was applied as the background discharge
|
Temporary bypass of secondarily treated and
disinfected effluent from upgraded TPSTW and CSTW,
see Section 4.6.31.
(for 4 weeks outside algae blooming season)
|
This
Project
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (4)
|
1,000 (4)
|
CSTW
|
20 (5)
|
30 (5)
|
13.28 (5)
|
20 (5)
|
5 (5)
|
1,000 (5)
|
5 (UDS)
|
Emergency discharge
|
Under Emergency Situation:
20,000 m3 per discharge event (from
upgraded TPSTW)
Outside
Emergency Discharge Period:
Reduced Project overflow (as shown in Exhibit 4.6
above) was applied as the background discharge
|
Emergency bypass of primarily treated / settled
effluent from upgraded TPSTW, see
Section 4.6.38.
(for 3 hours in wet season)
|
This Project
|
177 (7)
|
174 (7)
|
57 (7)
|
58 (7)
|
38 (7)
|
2 x107 (8)
|
Notes:
(1) During EIA stage of the
“TPSTW Stage V”, the design capacity of TPSTW was proposed to be 130,000 m3/day.
The design capacity has been reviewed and changed to 120,000 m3/day
according to the latest operation information of TPSTW.
(2) At 95th percentile
value of the effluent standard (refer to Table 4.8). Using the 95th
percentile value as the effluent concentration for continuous discharge was
considered conservative, given that the effluent concentrations would be lower
than the 95th percentile value for most of the times.
(3) Based on the ratio
of TKN : Total N adopted in the approved EIAs for CSTW and TPSTW Stage V.
(4)
At mean value of the effluent standard (refer to Table
4.8). Unlike the WQO for DO which is a 10th percentile value,
the WQOs for TIN and UIA is an annual mean objective. The WQO for chlorophyll-a is a 5-day running averaged value. The
WQO for E. coli in Tolo Harbour is a
geometric mean objective. Thus, using the mean effluent standard in model
prediction is considered appropriate for comparison with the relevant WQOs. The
same approach has been adopted in the EIA for CSTW and the latest modelling
submissions of Agreement No. CE 30 /2008 (CE).
(5)
Based on the same effluent values adopted in the
approved EIA for CSTW.
(6) Based on maximum of
all moving yearly 95th percentile values from latest measurements of
effluents from TPSTW between January 2017 and July 2021. A yearly 95th percentile value is
defined as the 95th percentile value over a one-year period (e.g.
from 1 August 2020 to 31 July 2021). Use of the measured 95th percentile value
for continuous input is conservative. This represents a reasonable worst case for
impact assessment. The same approach is adopted in the EIA for CSTW as well as
under the latest 2020 modelling submissions of Agreement CE 30/ 2008 (CE).
(7) Maximum value of
monthly averaged data measured in primarily treated / settled effluent of TPSTW
(between 2017 and 2021).
(8) Typical design
concentrations adopted in the approved EIAs for CSTW and TPSTW Stage V.
Simulation
Periods
4.7.17
For both THMB Model and VH
Model, water quality simulations (using Delft3D-WAQ) for operational stages are
conducted for 1 complete calendar year.
4.7.18
The simulations (using
Delft3D-FLOW) are performed for both dry and wet seasons. For each season, the simulation period of the
hydrodynamic model covers a 15-day full spring-neap cycle (excluding the spin-up
period). The hydrodynamic results are
used repeatedly to drive the water quality simulations for one complete
calendar year (excluding the spin-up period).
Spin-up Periods
4.7.19
For THMB Model, a spin-up
period of 1 complete calendar year is provided for each of the hydrodynamic
simulation and water quality simulation.
4.7.20
For VH Model, a spin-up period
of 23 days and 45 days is provided for hydrodynamic simulation and water
quality simulation respectively.
4.7.21
These spin-up periods were
tested to be adequate for producing acceptable model result.
4.7.22
Tolo Harbour is a land-locked
water body with a narrow exit to the open water. Also, the opening of the Tolo
Channel is not facing directly to the incoming tides (from the South China
Sea). Therefore, the influences on the hydrodynamics and water quality of Tolo
Harbour due to changes in the environmental settings outside Tolo Harbour
including major reclamation projects (e.g. the Third Runway project) and STW
projects (e.g. Harbour Area Treatment Scheme) would be negligible.
4.7.23
The hydrodynamic boundary
conditions of the THMB Model were developed under Agreement No. WP01-27 from
the actual forcing of wind, rainfall and temperature. These boundary conditions
were found to be reliable from other past relevant EIAs. Hence, the same set of hydrodynamic boundary
conditions will be used in this EIA.
4.7.24
The water quality boundary
condition of the THMB Model has been derived from the water quality monitoring
results of the nearest EPD station to the open boundaries, namely MM16.
VH Model
4.7.25
The VH Model is linked to or
nested within the regional Update Model developed by EPD under Agreement No. CE
42/97 . The Update Model was fully
calibrated and verified. It has been updated according to the latest changes of
coastline configurations, bathymetry and pollution loading. Computations are
firstly carried out using the Update Model and the results are used to provide
open boundary conditions to drive the VH Model. The Update Model covers the
outer regions of Pearl River Estuary, Macau, Ma Wan Channel, Cheung Chau, East
Lamma Channel, Victoria Harbour, Tathong Channel, Nine Pin Islands, Po Toi
Island, Tolo Harbour and Tolo channel. All
major influences on hydrodynamics and water quality in the outer regions
including the Pearl River discharges would be incorporated into the VH
Model.
Coastline Configurations
4.7.26
The construction works of this
Project are tentatively scheduled to commence in 2025 for completion in
2036.
Victoria Harbour
4.7.27
Following the existing THEES
arrangement, only TSE from the Project would be discharged to Victoria Harbour.
The on-going or planned projects as listed in Table 4.14 below would be completed
before commissioning of this Project and therefore incorporated into the
modelling exercise.
Table 4.14 Projects Affecting
Coastline Configurations
4.7.28
The implementation programme
and layout for Container Terminal 10 Development at Southwest Tsing Yi and
other Potential Reclamation Sites (PRS) in western waters (proposed under
“Increasing Land Supply by Reclamation and Rock Cavern Development cum Public
Engagement – Feasibility Study”) are currently unconfirmed. These potential
reclamations are excluded in this modelling exercise.
4.7.29
The treatment level of this Project
would be secondary with disinfection. Based on the results of all past relevant
studies e.g. EIA for “CSTW”, the effect of secondarily treated and disinfected
effluent would be highly localized and confined within the water bodies at or
near Kai Tak Development Area. The
effect of other potential reclamation sites (e.g. in western waters) would
unlikely affect the overall conclusion of this assessment.
4.7.30
The coastal projects
“Intermodal Transfer Terminal - Bonded Vehicular Bridge and Associated Roads”
and “Cross Bay Link (CBL), Tseung Kwan O” are not considered in the modelling.
Both projects would not involve reclamation but would include the construction
of bridge piers only with limited effect on the tidal flushing (as predicted in
their approved EIAs). It is considered that these bridge project would not
affect the overall modelling results for the present EIA.
4.7.31
Based on the latest
information, the wide (600m) opening at the former airport runway as proposed
in the approved EIA for “KTD” will be superseded by the IP Scheme proposed
under Agreement No. CE 30/2008 (CE) as discussed in Section 4.5. The 600m
runway opening will not be considered in this EIA. Based on the past relevant model results,
opening a wide (600m) gap at the former airport runway would result a greater
water quality improvement and flushing at the KTAC as compared to the IP Scheme
and therefore will be a less critical case for cumulative water quality
impacts. Under the IP Scheme, there would be 3 DCS plants at Kai Tak with 2 intakes
(in KTR and KTAC) and 3 outfalls (in Kowloon Bay) as shown in Figure 4.6 above. The design flow rates of the 3 DCS plants
available from Agreement No. CE 30/2008 (CE) are used in the modelling as both
the seawater intake rates and the spent effluent discharge rates at the
outfalls. The combined water intake rates (at KTR and KTAC) would be equal to
the combined discharge rates in Kowloon Bay.
Tolo Harbour
4.7.32
No confirmed and planned
reclamation is identified within the coverage of THMB Model. The layout and implementation programme of
the PRS at Ma Liu Shiu are currently unconfirmed and will not be considered in
the modelling. This PRS is located in
the most inner zone of Tolo Harbour near Sha Tin Hoi. It is at the southernmost
point of Tolo Harbour farthest from the Tolo Channel opening. It is also
relative far away from the Project discharge point at Tai Po and will not block
any tidal flow along the coast of Tai Po.
This PRS would not affect the overall conclusion of this assessment.
Model Bathymetry
4.7.33
The model bathymetry
schematization was checked against the depth data from the latest marine charts
produced by the Hydrographic Office of Marine Department. In addition, major EIA projects that would
affect the bathymetry are listed in Table 4.15. All these projects are either completed or
under construction and therefore incorporated into the bathymetries of this
modelling exercise.
Table 4.15 Projects
Affecting Bathymetry
Background Pollution Loading
Introduction
4.7.34
The approach in compiling the
background pollution loading is summarized below. Details of the loading inventory are given in
the Working Paper on Water Quality Impact Assessment .
Kai Tak Development Area
4.7.35
The inventory of background
storm pollution loading to the KTAC and Kwun Tong Typhoon Shelter (KTTS) for
the year of 2018 developed under Agreement No. CE 30/2008 (CE) was obtained from the CEDD and is directly adopted in this EIA.
This loading inventory was compiled using the results of storm pollution survey
carried out in 2018 and also taking account of the rainfall related loading.
Since the Government will continue to remove the pollution sources and rectify
expedient connections, it is expected that the future storm pollution
situations during operational phase of this Project would not be worse than the
2018 conditions. It is appropriate to adopt the 2018 storm loading inventory
for the present EIA.
Tolo Harbour
n
Total Population in the catchment area in UDS = Year 2041 Population Data
x 1.1;
n
Total Pollution Load (TPL) generated in the catchment area in UDS = Total
Population in the catchment area in UDS x Per Head Load Factor; and
n
Pollution Load discharged to
marine water from the catchment area in UDS for model input = TPL generated in
the catchment area in UDS x (5% sewage lost to the
drainage system).
Other Background Sources
4.7.39
The UDS is also used as the
time horizon for other background loading outside the catchments of KTAC, KTTS
and Tolo Harbour. The background discharges are compiled theoretically by
applying the relevant per capita load factors to the projected population from
2016-based TPEDM or based on the design flow and load information of major STW
from other EIA projects. The population used for the UDS is based on a 10%
extrapolation of the projected population for 2041 to address the uncertainties
of the population forecast. The inventory also incorporates the effect of storm
events and other minor point source discharges in Hong Kong such as those from
individual fish cultural zones.
Model Limitations
4.7.40
The Delft3D water quality
modelling tools adopted for the assessment are not red tide modelling tools,
which are not designed for the purpose of predicting the rise and fall of a red
tide. Thus, the secondary water quality impact brought by the red tide
occurrence, such as DO depletion, may not be truly reflected by the Delft3D
module.
4.7.41
It should also be noted that
the use of monthly averaged meteorological data (e.g. in terms of solar
radiation and temperature) as well as the averaged pollution loading
(calculated theoretically) for model input (under the existing EIA practice)
may not be able to reflect the episodic events (e.g. stratification induced by
extreme air temperature) as well as the day-to-day and year-to-year fluctuation
of the pollution discharge into the sea.
These are the model limitations that may cause a deviation between the
model prediction and the actual situation, which need to be observed when
reviewing the model results of this assessment.
Operational Phase – Other
Water Pollution Sources
4.7.42
Other potential sources of
water quality impacts that may arise during the operational phase are presented
in Section 4.6.41. All
the identified sources of potential water quality impact were qualitatively
evaluated and their impact significance determined. The need for mitigation
measures to reduce any identified adverse impacts on water quality to
acceptable levels was determined.
General Land-based
Construction Activities
4.8.1
Various types of construction activities
may generate wastewater. These include general cleaning and polishing, wheel
washing, dust suppression sprays and utility installation. These types of
wastewater would contain high concentrations of SS. Effluent discharged from
various construction site facilities would be controlled to prevent direct
discharge to the neighbouring inland waters and storm drains.
4.8.2
Construction works would also
generate debris and rubbish such as packaging, construction materials and
refuse. Uncontrolled discharge of site
effluents, rubbish and refuse generated from the construction works could lead
to deterioration in water quality. Debris and rubbish would be properly managed
and controlled to avoid accidental release to the local storm system and inland
waters.
4.8.3
Adoption of the guidelines and
good site practices for handling and disposal of construction site discharges
and refuse as specified in Section 4.11 would minimize the potential impacts.
4.8.4
Potential pollution sources of
site runoff may include:
n
Runoff and erosion of exposed bare soil and earth, drainage channel,
earth working area and stockpiles;
n
Release of any bentonite slurries, concrete washings and other grouting
materials with construction run-off or storm water;
n
Wash water from dust suppression sprays and wheel washing facilities; and
n
Fuel, oil and lubricants from maintenance of
construction vehicles and equipment.
4.8.5
During rainstorms, site runoff
would wash away the soil particles on unpaved lands and areas with the topsoil
exposed. The runoff is generally
characterized by high concentrations of SS.
Release of uncontrolled site run-off would increase the SS levels and
turbidity in the nearby water environment.
Site runoff may also wash away contaminated soil particles and therefore
cause water pollution.
4.8.6
Windblown dust would be
generated from exposed soil surfaces in the works areas. It is possible that windblown dust would fall
directly onto the nearby water bodies when a strong wind occurs. Dispersion of dust within the works areas may
increase the SS levels in surface run-off causing a potential impact to the
nearby sensitive receivers.
4.8.7
It is important that proper
site practice and good site management (as specified in the ProPECC PN 1/94
“Construction Site Drainage”) be followed to prevent run-off with high level of
SS from entering the surrounding waters.
With the implementation of appropriate measures to control run-off and
drainage from the construction site, disturbance of water bodies would be
avoided and deterioration in water quality would be minimal. Thus, unacceptable impacts on the water
quality are not expected, provided that the relevant mitigation measures as
specified in the ProPECC PN 1/94 “Construction Site Drainage” are properly
implemented.
4.8.8
The use, handling and storage
of chemicals (e.g. engine oil, lubricants, spent acid / alkaline solutions /
solvent etc.) would have the potential to create impacts on the water quality
if spillage occurs. Chemical spillage may infiltrate into the surface soil
layer, or run-off into local storm drains and eventually to the water
environment. Thus, chemicals shall be handled, stored and disposed properly to
avoid and contain spillage. The potential water quality impact associated with
accidental chemical spillage could be mitigated by practical measures and good
site practices as given Section 4.11.
4.8.9
During the construction of the
Project, the workforce on site will generate sewage effluents, which are
characterized by high levels of BOD5, ammonia and E. coli counts. However, this temporary sewage can be adequately
treated by interim sewage treatment facilities, such as portable chemical
toilets. Based on the Drainage Services Department (DSD) Sewerage Manual, the
sewage production rate for construction workers is estimated at 0.35 m3
per worker per day. For every 100 construction workers working simultaneously
at the construction site, about 35 m3 of sewage would be generated
per day. Provided that sewage is not
discharged directly into storm drains or inland waters adjacent to the
construction site, and temporary sanitary facilities are serviced and properly
maintained by a licensed waste collector, it is unlikely that sewage generated
from the site would have a significant water quality impact.
Contaminated Site Runoff
4.8.10
With reference to the land
contamination assessment carried out under this EIA, potential contaminated
lands are identified at the existing TPSTW and the proposed expansion site. Any contaminated material disturbed, or material
which comes into contact with the contaminated material, has the potential to
be washed with site runoff into the nearby drainage system and eventually to
the Tolo Harbour. As a result, the
levels of Chemicals of Concern (CoC) such as petroleum hydrocarbons and metals
in the marine water may be increased.
4.8.11
Mitigation measures will be
required to avoid, control or properly treat any contaminated site runoff. With
proper implementation of the recommended mitigation measures in Section 4.11,
the potential water quality impacts arising from contaminated site run-off
would be minimized.
Demolition Works
4.8.12
The Project would involve
demolition works of some existing structures of TPSTW for construction of new
treatment facilities. The sewage and chemical residues remaining or washed out
from the decommissioned facilities would be a source of water pollution.
4.8.13
Surface runoff and site effluent
may also be generated from the demolition works. Precipitation that falls on unpaved lands and
areas with the topsoil exposed during the demolition would wash away soil
particles. Such surface runoff and
stormwater overflows with high levels of SS (if uncontrolled) which may lead to
water quality impact.
4.8.14
Proper site practice and good site management
as specified in the ProPECC PN 1/94 “Construction Site Drainage” and
recommended in Section 4.11 should be implemented to control site runoff and site
effluent from the demolition works, as well as to prevent wastewater or
chemical residues, if any, in the decommissioned facilities from directly
entering the Tolo Harbour. With proper implementation of the recommended
mitigation measures, unacceptable water quality impacts would not arise.
Normal Project / THEES
Operation – Treated Effluent Discharge to Victoria Harbour
4.9.1
Four modelling scenarios
(namely Scenarios 1a, 1b, 2a, and 2b) were simulated to assess the potential
water quality impacts upon the Victoria Harbour during the normal Project
/THEES operation.
4.9.2
The model results of the 4
scenarios are compared in Appendix 4.3 as contour plots for DO, BOD5,
TIN, UIA, E. coli, SS, and sedimentation rate. All contour plots are presented as annual
arithmetic averages except for the E. coli levels, which are annual
geometric mean. Since the marine WQO in Victoria Harbour for depth-averaged
(DA) DO and bottom DO is defined as not less than 4 and 2 mg/L respectively for
90% of times over a complete calendar year, the contour plots for DO are
presented as 10th percentile (10%ile) DA and bottom values for comparison with
the WQOs. Contour plot for annual mean DA DO values are also presented for
reference.
4.9.3
The predicted 10%ile bottom DO
fully complied with the WQO of no less than 2 mg/L in all assessment areas
including KTAC, KTTS, Kowloon Bay and the open channel of Victoria Harbour
under all scenarios (1a, 1b, 2a and 2b), refer to Figure 03 of Appendix 4.3. Using the discharge license
standards for compiling the THEES effluent loading under Scenarios 1a and 1b,
the predicted 10%ile bottom DO levels ranged from ≥3 mg/L to <4 mg/L
in part of the KTAC and at the corner of KTTS and corners of Kowloon Bay and ≥4
mg/L in the remaining assessment areas. The 10%ile bottom DO patterns are
similar between Scenarios 1a and 1b. Under the more realistic worst-case
scenarios by using the maximum 95%ile values of the measured effluent quality
data for compiling the THEES effluent loading (Scenarios 2a and 2b), the
predicted 10%ile bottom DO levels ranged from ≥3 mg/L to <4 mg/L at
the corner of KTAC and corners of Kowloon Bay and ≥4 mg/L in the
remaining assessment areas. The 10%ile bottom DO patterns are similar between
Scenarios 2a and 2b. No adverse bottom DO impact is predicted.
Depth-averaged (DA) Dissolved
Oxygen (DO)
4.9.4
Using the discharge license
standards for compiling the THEES effluent loading under Scenarios 1a and 1b,
the 10%ile DA DO levels would not comply with the WQO of no less than 4 mg/L in
a small portion of the KTAC water (Figure 02 of Appendix 4.3). The size of non-compliance area in the KTAC
water is slightly larger under Scenario 1b (with Project) as compared to the
baseline condition (Scenario 1a). However, neither biological nor ecological
sensitive receivers that are sensitive to DO depletion are located in
KTAC. No unacceptable DO impact would
be induced by this Project.
4.9.5
Under the more realistic
worst-case scenarios by using the maximum 95%ile values of the measured
effluent quality data for compiling the THEES effluent loading for continuous
discharge (Scenarios 2a and 2b), full compliance with the WQO for DA DO would
be achieved in KTAC (Figure 02 of Appendix 4.3). The predicted 10%ile DA
DO patterns are similar between Scenarios 2a and 2b.
4.9.6
Under all the four scenarios,
full compliance with the WQO for 10%ile DA DO is predicted in KTTS, Kowloon Bay
and the open channel of Victoria Harbour outside the breakwaters of KTTS except
for a small portion at the corners of Kowloon Bay where the 10% DA DO breached
the WQO (Figure 02 of Appendix 4.3). This Project would not cause any adverse DA
DO impact in Victoria Harbour WCZ.
5-Day Biochemical Oxygen Demand
(BOD5)
4.9.7
There is no marine WQO for BOD5 in Victoria Harbour WCZ. Under Scenarios
1a and 1b, the predicted mean BOD5 levels ranged from ≥1 mg/L to <5
mg/L in KTAC (except a small portion at the corner of KTAC with a level of
>5 mg/L), from ≥0.5 mg/L to <1.5 mg/L in KTTS, from <0.5 mg/L to
<5 mg/L in Kowloon Bay (except a small portion at the upper corner with a
level of >5 mg/L) and <0.5 mg/L in the open channel of Victoria Harbour
(except for some localized areas along the coastlines with higher BOD5 levels). Under Scenarios 2a and 2b, the
predicted mean BOD5 levels ranged from ≥0.5 mg/L to
<3 mg/L in KTAC, from ≥ 0.5 mg/L to <1.5 mg/l in KTTS, from <0.5
mg/L to <5 mg/L in Kowloon Bay (except a small portion at the upper corner
with a level of >5 mg/L) and <0.5 mg/L in the open channel of Victoria
Harbour (except for some localized areas along the coastlines with higher BOD5
levels). As shown in the contour plot (Figure 04 of Appendix 4.3), no significant changes
in the overall BOD5 pattern in the KTAC, KTTS, Kowloon Bay
and the open channel of Victoria Harbour would be induced by the Project (under
Scenarios 1b and 2b) as compared to the baseline situation (under Scenarios 1a
and 2a). No adverse BOD5 impact would be resulted from this
Project.
Suspended Solids (SS)
4.9.8
Under all the four assessment
scenarios, the predicted mean SS levels ranged from ≥2 mg/L to <8 mg/L
in KTAC (except a small portion at the corner of KTAC with levels of ≥8
mg/L to <10 mg/L), from ≥4 mg/L to <6 mg/L in KTTS, from ≥4
mg/L to <8 mg/L in Kowloon Bay (except a small portion at corners of Kowloon
Bay with levels of ≥8 mg/L to <20 mg/L) and from ≥2 mg/L to
<6 mg/L in open channel of Victoria Harbour (except for some localized areas
along the coastlines with SS levels of ≥6 mg/L to <8 mg/L). The
overall SS patterns are similar between the “with Project” scenario (Scenario
1b and 2b) and its baseline scenario (Scenario 1a and 2a). By comparing the baseline condition
(Scenarios 1a and 2a) to the “with Project” condition (Scenarios 1b and 2b),
the SS increase in all the assessment areas including the KTAC, KTTS, Kowloon
Bay and the open channel of Victoria Harbour fully complied with the WQO for SS
elevation of no more than 30% (Figure 08 of Appendix 4.3). No adverse SS impacts
would be anticipated.
Unionized Ammonia (UIA)
4.9.9
Under Scenarios 1a and 1b using
the discharge license standards for compiling the THEES effluent load for
continuous discharge, the predicted UIA levels exceed the WQO of no more than
0.021 mg/L in KTAC, inner KTTS and inner Kowloon Bay. Under Scenarios 2a and 2b
(using a more realistically worst THEES effluent loading), the predicted
UIA in KTAC still exceed the WQO of no
more than 0.021 mg/L, whereas the predicted UIA exceedance area is reduced in
KTTS and inner Kowloon Bay compared to Scenario 1a and 1b (Figure 06 of Appendix 4.3).
4.9.10
The predicted UIA levels in in
the open channel of Victoria Harbour and most areas of KTTS, and To Kwa Wan
Typhoon Shelter comply with the WQO under all the four assessment scenarios
(Figure 06 of Appendix 4.3).
4.9.11
Under the IP scheme, an annual
average of over 680,000 m3 per day of water is pumped from Kai Tak
River and KTAC to Kowloon Bay (the average water pumping rate for wet season,
May to September, is over 900,000 m3/day). With consideration of the IP scheme, the size
of UIA exceedance area in KTAC and inner Kowloon Bay are similar with and
without this Project (Figure 06 of Appendix 4.3). The UIA exceedance area
in inner KTTS however increases slightly under “with Project” scenario
(Scenario 1b and 2b) as compared to its baseline scenario (Scenario 1a and
2a).
4.9.12
Although UIA exceedance is
predicted, there are no WSRs such as sites of fisheries or ecological
importance (that are susceptible to UIA increase) in KTAC, KTTS and Kowloon
Bay. No unacceptable UIA impact in Victoria Harbour
WCZ would be anticipated from this Project.
Total Inorganic Nitrogen (TIN)
4.9.13
Under all scenarios (with or
without the Project), the predicted TIN levels exceed the WQO of ≤0.4
mg/L inside KTAC, KTTS and Kowloon Bay.
The predicted TIN levels in the open channel of Victoria Harbour comply
with the WQO (except for some localized areas along the coastlines with TIN
levels of ≥0.4 mg/L to <0.8 mg/L) (Figure 05 of Appendix 4.3).
4.9.14
With consideration of the IP
scheme, the size of TIN exceedance area are similar with and without this
Project (Figure 05 of Appendix 4.3). This Project would not
increase the degree of TIN exceedance as compared to the baseline (without
Project) condition.
4.9.15
Implication of nutrient increase
in marine water would be the possible enhancement of excessive phytoplankton
growth (algal bloom / red tide). From the past red tide
records from Hong Kong Red Tide Database of AFCD available since 1975, there
has been only 1 red tide incident occurred near Kwun Tong Public Pier in KTTS
and 1 red tide incident occurred near Hung Hom in Kowloon Bay. No historic red
tide incident has been recorded in KTAC. Red tide occurrence would not be a key
concern in KTAC, KTTS and Kowloon Bay. In addition, no sites of fisheries or
ecological importance (which are sensitive to red tide) are located in KTAC,
KTTS and Kowloon Bay.
E. coli
4.9.17
There is no WQO for E. coli available in Victoria Harbour
WCZ under the existing situation. The predicted geometric mean E. coli levels under all scenarios are
over 610 no./100mL along the coastlines of Victoria Harbour due to the storm
pollution loading assumed in the modelling.
The predicted geometric mean E.
coli levels in areas away from the coastlines or away from the storm outfalls
in the open channel of Victoria Harbour are below 610 no./100mL (Figure 07 of Appendix 4.3).
4.9.18
Under all the four assessment
scenarios, the predicted geometric mean E. coli levels ranged from ≥180
no. /100mL to <2000 no. /100mL in KTAC and KTTS (except a small portion in
KTAC and KTTS with a level of >2000 no. /100mL) and from <180 no. /100mL
to <8000 no. /100mL in Kowloon Bay (except corners of Kowloon Bay with a
level of >8000 no. /100mL). The overall E.
coli patterns in all the assessment areas including KTAC, KTTS, Kowloon Bay
and open channel of Victoria Harbour are similar under all the 4 modelling
scenarios (Figure 07 of Appendix 4.3). This Project would not
induce any additional E. coli impact in Victoria Harbour WCZ.
4.9.19
There is no statutory WQO for
sedimentation rate available in the marine water. Under all the 4 scenarios,
the predicted mean sedimentation rate in the assessment area are less than 5
g/m2/day except for the upper corner of Kowloon Bay where the
predicted values ranged from ≥5 g/m2/day to <10 g/m2/day
(Figure 09 of Appendix 4.3). The overall
sedimentation patterns in the assessment area are similar with and without this
Project. This Project would not induce
any adverse sedimentation impact.
Impact on WSRs
4.9.20
Following the same approach
adopted under the approved EIAs for KTD and CSTW , the model results are
presented for the WSRs that are within the potential influence zone of the
THEES effluent, including the WSD flushing water intakes at Tai Wan (F6) and
Cha Kwo Ling (F1), the intakes of the Kai Tak DCS (C1 to C3), the cooling water
intake for Yau Tong Bay Ice Plant (C4), the To Kwa Wan Typhoon Shelter as well
as the KTTS and possible water sports area (R1) in KTTS. Other WSRs were found not to be affected by
the Project and are therefore not presented.
WSD Flushing Water Intakes
4.9.21
Based on the model results as
summarized in Table 4.16, full compliance with the WSD target seawater
quality objectives is predicted under all the 4 scenarios at the WSD flushing
water intakes at Tai Wan (F6) and Cha Kwo Ling (F1) except for the maximum SS
levels, which exceeded the WSD target of <10 mg/L. From Table 4.6 above, the measured maximum SS levels in the
main channel of Victoria Harbour (VM1, VM2 and VM4) are also over 10 mg/L in
2020. It is believed that the SS levels at the two flushing intakes (located in
the Victoria Harbour channel) would also occasionally exceed the WSD target
under the existing situation. As shown in Table 4.16, this Project would
not cause any additional SS impact. The predicted SS values under “with
Project” scenario (Scenario 1b and 2b) are the same or slightly lower than the
SS values under its baseline scenario (Scenario 1a and 2a). No adverse SS
impact upon the flushing water intakes at Tai Wan (F6) and Cha Kwo Ling (F1)
would arise from the Project.
Table 4.16 Predicted Water Quality at Selected WSD
Flushing Water Intakes
Parameter
|
Scenario
(see Remarks)
|
WSD Flushing Water Intakes
(see Figure 4.3)
|
Tai Wan (F6)
|
Cha Kwo Ling (F1)
|
Assessment Criteria #
|
Maximum
Ammonia Nitrogen
(mg/L)
|
1a
|
0.45
|
0.36
|
< 1
|
1b
|
0.44
|
0.37
|
2a
|
0.41
|
0.32
|
2b
|
0.42
|
0.34
|
Maximum
Suspended Solids (mg/L)
|
1a
|
17.3
|
15.6
|
< 10
|
1b
|
17.3
|
15.5
|
2a
|
17.3
|
15.6
|
2b
|
17.3
|
15.5
|
Minimum
Dissolved Oxygen (mg/L)
|
1a
|
4.8
|
4.9
|
> 2
|
1b
|
4.9
|
4.9
|
2a
|
4.9
|
5.0
|
2b
|
4.9
|
5.0
|
Maximum
BOD5 (mg/L)
|
1a
|
1.0
|
0.8
|
< 10
|
1b
|
0.9
|
0.8
|
2a
|
0.9
|
0.7
|
2b
|
0.9
|
0.7
|
Maximum
E. coli (no./100mL)
|
1a
|
6014
|
1034
|
< 20,000
|
1b
|
5878
|
1041
|
2a
|
6032
|
1030
|
2b
|
6034
|
1037
|
Remarks: Data presented are in
mid-depth water level. Bolded values indicate non-compliance of WQO.
# WSD’s Target
Seawater Quality Objectives at Flushing Water Intakes
Scenario
1a: Baseline Scenario (THEES
loading based on discharge license standards)
Scenario
1b: “With Project” Scenario
(THEES based on discharge license standards)
Scenario
2a: Baseline Scenario (THEES
based on actual measurement)
Scenario
2b: “With Project” Scenario
(THEES based on actual measurements)
Cooling Water Intakes
4.9.22
There are no specific water
quality criteria/requirements available for the Kai Tak DCS cooling water
intakes and the cooling water intake for Yau Tong Bay Ice Plant. The model results at these cooling water
intakes are tabulated in Table 4.17. The operation of the DCS and Yau Tong Bay Ice
Plant is not sensitive to the water quality changes at their cooling intake
points as confirmed by EMSD or reported in past relevant EIA Reports. No
unacceptable water quality impact upon the cooling water intakes would be resulted
from this Project.
Table 4.17 Predicted
Water Quality at Cooling Water Intakes
Parameter
|
Scenario
(see Remarks)
|
Kai Tak DCS Cooling Water Intakes
|
Yau Tong Bay Ice Plant Cooling Water
Intake
|
C1
|
C2
|
C3
|
C4
|
Maximum Ammonia Nitrogen
(mg/L)
|
1a
|
4.08
|
2.68
|
1.23
|
0.36
|
1b
|
4.67
|
2.82
|
1.14
|
0.37
|
2a
|
3.37
|
2.08
|
0.92
|
0.32
|
2b
|
4.03
|
2.30
|
0.92
|
0.34
|
Maximum Suspended Solids (mg/L)
|
1a
|
20.7
|
14.7
|
18.2
|
15.6
|
1b
|
24.0
|
15.2
|
18.1
|
15.5
|
2a
|
13.6
|
11.6
|
17.7
|
15.6
|
2b
|
14.8
|
11.7
|
17.6
|
15.5
|
Minimum Dissolved Oxygen (mg/L)
|
1a
|
2.2
|
2.9
|
4.7
|
4.9
|
1b
|
2.0
|
3.3
|
4.8
|
4.9
|
2a
|
2.9
|
4.4
|
4.8
|
5.0
|
2b
|
2.7
|
4.2
|
4.8
|
5.0
|
Maximum BOD5 (mg/L)
|
1a
|
16.0
|
6.9
|
2.2
|
0.8
|
1b
|
17.8
|
7.4
|
2.1
|
0.8
|
2a
|
7.8
|
3.3
|
1.4
|
0.7
|
2b
|
8.4
|
3.4
|
1.3
|
0.7
|
Maximum E.
coli (no./100mL)
|
1a
|
38445
|
4165
|
4014
|
1034
|
1b
|
27228
|
4046
|
2767
|
1041
|
2a
|
30844
|
3974
|
4422
|
1030
|
2b
|
26892
|
3938
|
4506
|
1037
|
Remarks: Data presented are in
mid-depth water level.
Scenario
1a: Baseline Scenario (THEES
loading based on design effluent standards)
Scenario
1b: “With Project” Scenario
(THEES based on design effluent standards)
Scenario
2a: Baseline Scenario (THEES
based on actual measurement)
Scenario
2b: “With Project” Scenario
(THEES based on actual measurements)
Kwun Tong Typhoon Shelter /
Potential Water Sports Area at Kai Tak and To Kwa Wan Typhoon Shelter
4.9.23
The feasibility of locating a
potential water sports area in KTTS is being investigated under the separate
KTD project. The WQO laid down for
secondary contact and recreational uses stipulates that the annual geometric
mean E. coli level should not exceed
610 no./100mL. The model results showed that the annual geometric mean E. coli level predicted in most areas of
KTTS (where the potential water sports area is proposed) would be around or
below 610 no./100mL under all the modelling scenarios as shown in Table 4.18 below.
This Project would not induce any additional E. coli impact in
KTTS.
4.9.24
It should be highlighted that
this potential water sports centre is not a confirmed project and its
feasibility is still subject to confirmation under separate studies. If this
potential water sports centre is carried forward under the separate project,
detailed justifications on the acceptability of using the KTTS for water sports
activities will be provided under the separate KTD project.
4.9.25
TIN exceedance is predicted in
KTTS and To Kwa Wan Typhoon Shelter (TKWTS) under all the assessment scenarios.
Since no sites of fisheries or ecological importance are located in KTTS and
TKWTS, the TIN exceedances in KTTS and TKWTS would not induce any unacceptable
water quality impact as discussed in Sections 4.9.13 to 4.9.16. Full
compliances with the WQOs are predicted for other parameters in KTTS and TKWTS.
Table 4.18 Predicted
Water Quality at KTTS / Potential Water Sports Area and To Kwa
Wan Typhoon Shelter
Parameter
|
Scenario
(see Remarks)
|
KTTS / Potential Water Sports Area (R1)
|
To Kwa Wan Typhoon Shelter
|
WQO
|
10%ile Bottom Dissolved Oxygen
(mg/L)
|
1a
|
4.3
|
4.8
|
≥2
|
1b
|
4.2
|
4.9
|
2a
|
4.7
|
4.9
|
2b
|
4.7
|
4.9
|
10%ile Depth-Averaged Dissolved Oxygen
(mg/L)
|
1a
|
4.8
|
5.0
|
≥4
|
1b
|
4.8
|
5.0
|
2a
|
5.1
|
5.1
|
2b
|
5.1
|
5.1
|
Unionized Ammonia
(Annual Average) (mg/L)
|
1a
|
0.020
|
0.011
|
≤0.021
|
1b
|
0.021
|
0.011
|
2a
|
0.016
|
0.009
|
2b
|
0.017
|
0.010
|
Total Inorganic Nitrogen
(Annual Average) (mg/L)
|
1a
|
0.850
|
0.452
|
≤0.4
|
1b
|
0.901
|
0.450
|
2a
|
0.926
|
0.463
|
2b
|
0.991
|
0.469
|
Geometric Mean E. coli (no./100mL)
|
1a
|
557
|
310
|
≤610
(applicable to R1 only)
|
1b
|
553
|
287
|
2a
|
540
|
316
|
2b
|
537
|
318
|
Suspended Solids
(Annual
Average) (mg/L)
|
1a
|
4.9
|
4.7
|
Not to raise the ambient level by more than
30% caused by human activity
|
1b
|
5.0
|
4.7
|
2a
|
4.4
|
4.6
|
2b
|
4.5
|
4.6
|
Remarks: Bolded values indicate
non-compliance of WQO.
Scenario
1a: Baseline Scenario (THEES
loading based on design effluent standards)
Scenario
1b: “With Project” Scenario (THEES
based on design effluent standards)
Scenario
2a: Baseline Scenario (THEES
based on actual measurement)
Scenario
2b: “With Project” Scenario
(THEES based on actual measurements)
THEES Maintenance –
Treated Effluent Discharge to Tolo Harbour
4.9.26
A
continuous THEES maintenance discharge for a period of 4 weeks was simulated
under Scenario 4. During the THEES maintenance period, disinfected secondary
effluent would be discharged to Tolo Harbour from this Project and the
concurrent CSTW project. The THEES maintenance will be scheduled outside the
algae blooming season. The model results for Scenario 4 (with THEES maintenance
discharge) are compared with the model results for Scenario 3 (baseline
scenario without THEES maintenance) to identify the water quality changes due
to the THEES maintenance discharge.
4.9.27
The
water quality simulation results are presented as contour plots and are
compared between Scenario 3 and Scenario 4 in Appendix 4.4 for DO, BOD5, TIN, UIA, E. coli, SS,
chlorophyll-a and sedimentation rate. The water quality at individual WSRs predicted under Scenario 3 and
Scenario 4 are tabulated in Appendix 4.5. Some model results in Appendix 4.4 and Appendix 4.5 are presented as annual mean over the 1-year simulation period to
illustrate that 4-week THEES maintenance discharge would not significantly
affect the average water quality condition over the year and thus the
associated chronic effect on marine life would be minimal. The model simulation period covers at least 1
calendar year including the period from 1 January to 31 December. The THEES maintenance discharge is assumed to
occur in June and / or July outside the algae blooming season (also see Section
4.6.31). The water
quality conditions would return to the levels that are similar to the baseline
range within about 2 to 4 weeks (mostly within 2 weeks and subject to the water
quality parameters of concern) after termination of the discharge. Thus, the full effect of the THEES
maintenance discharge has been incorporated into the annual mean results
presented in Appendix 4.4 and Appendix 4.5.
4.9.28
Although
the maintenance discharge event would inevitably cause an increase in pollution
levels in Tolo Harbour, the potential impact would be reversible according to
the model simulation results. The time for water quality recovery at selected WSRs
or indicator points are presented as time series plots in Appendix 4.6. These time series plots aim to illustrate the spatial changes of
pollution elevations at locations both close to and further away from the THEES
effluent discharge points.
4.9.29
Selected
indicator points include WSD flushing water intake at Tai Po (F7), WSD flushing
water intake at Sha Tin (F8), coral site near TPIE (CR1), coral site near SWGC
(CR2), Yim Tin Tsai Fish Culture Zone (FCZ) (FC1), mangrove site at Tolo Pond
(M1), EPD monitoring stations (TM3 and TM6), Yim Tin Tsai East FCZ (FC2), Lo Fu
Wat FCZ (FC3) , Yung Shue Au FCZ (FC4) and Lung Mei Beach (B1). Locations of these
WSRs or indicator points are shown in Figure 4.4. Detailed assessment of ecological and fisheries impacts is separately
provided in Section 5 and Section 6 respectively.
Dissolved Oxygen (DO)
4.9.30
The
contour plots (Figure 01 of Appendix 4.4) showed that the THEES maintenance (Scenario 4) would slightly increase
the annual mean Depth Averaged (DA) DO as compared to the baseline condition
(Scenario 3). The overall DA DO patterns are similar with and without THEES
maintenance discharge. The contour plots (Figure 02 and Figure 03 of Appendix 4.4) showed that the THEES maintenance (Scenario 4) would not change the
areas of non-compliance for minimum DA DO and minimum bottom DO as compared to
the baseline condition (Scenario 3).
4.9.31
The
DO levels predicted at all WSRs under Scenario 4 (with THEES maintenance
discharge) fully complied with the WQO or assessment criteria except for the
mangrove site at Tolo Pond (M1) where the minimum surface DO is 1.3 mg/L as
compared to the WQO of ≥ 4 mg/L (Appendix 4.5). As the same minimum surface DO
level of 1.3 mg/L is predicted under the baseline scenario with no THEES
maintenance (Scenario 3), the low DO at M1 was not caused by the THEES
maintenance discharge. The time series plot (Figure 19 of Appendix 4.6) showed that the predicted DO
levels are not depleted at M1 during the 4-week THEES maintenance period. The THEES
maintenance discharge may stimulate algal growth and cause a temporary increase
in the DO level due to photosynthesis of green algae. The minimum surface DO of 1.3 mg/L is the minimum instantaneous value
predicted over the entire 1-year simulation period. The
time series plot showed that the surface DO at M1 would meet the WQO for most
of the times. The THEES maintenance would not cause any additional DO depletion
in Tolo Harbour. No unacceptable DO
impact is predicted.
Nitrogen Related Parameters
4.9.32
There
are no WQOs available for Unionized Ammonia (UIA) and Total Inorganic Nitrogen
(TIN) in the marine water of Tolo
Harbour. The THEES maintenance is predicted to cause no obvious and significant
change to the annual mean UIA and TIN levels at all identified WSRs (Figures 05
and 06 of Appendix 4.4 and Appendix 4.5).
4.9.33
As
shown in the time series plots in Figures 10 to 12 of Appendix 4.6, the TIN levels at some selected WSRs would be elevated during the
THEES maintenance period. Greater TIN increases are predicted at the WSD
flushing water intake at Tai Po (F7), WSD flushing water intake at Sha Tin
(F8), Yim Tin Tsai Fish Culture Zone (FC1), coral site near TPIE (CR1) and
coral site near SWGC (CR2), which are close to the effluent discharge points.
The TIN increases at the important nursery area for commercial fisheries
resources can be reflected by the time
series plots of TM6. Although some TIN elevations are
still observed in TM6, the degree of elevations is significantly lower as
compared to other closer WSRs (F7, F8, CR1 and CR2). FC3 and FC4 are also
located within the important nursery area for commercial fisheries resources.
The predicted TIN increases in FC3 and FC4 are negligible as reflected by the
time series plot in Figure 11 of Appendix 4.6. The predicted TIN increases at the remaining fish culture zone (FC2) and
Lung Mei Beach (B1) are also negligible.
4.9.34
The
time series plots showed that the TIN increases would be localized (in inner
Tolo Harbour). The TIN levels would return to the baseline levels within 2
weeks after termination of the discharge.
Suspended Solids (SS)
4.9.35
The
THEES maintenance discharge (Scenario 4) would not cause any obvious change on
the annual mean SS pattern in the Tolo Harbour as compared to the baseline
condition (Scenario 3) (see Figure 08 of Appendix 4.4).
4.9.36
There
is no WQO available for SS in the marine water of Tolo Harbour and
Channel. As shown in the time series plots in Figures 13 to 15 of Appendix 4.6, the SS levels would be elevated during the THEES maintenance period.
Greater SS elevations were observed at F7, F8, CR1, CR2 and TM3, which are
closer to the THEES effluent discharge locations, whilst the SS increase at the
remaining indicator points including the fish culture zones (FC1 to FC4), EPD
monitoring station (TM6) and Lung Mei Beach (B1) is less significant / not
obvious.
4.9.37
The
time series plots showed that the SS impact at the closest WSRs (F7 and F8)
would return to the levels that are approximately similar to baseline range
within 2 weeks and substantially identical about 4 weeks after the end of the
THEES maintenance period (Figure 13 of Appendix 4.6). The THEES maintenance
frequency would be once in every 5 years (see Section 4.6.30). Mitigation
measures recommended for the THEES maintenance are provided in Sections 4.12.3 and 4.12.4.
5-Day Biochemical Oxygen Demand
(BOD5)
4.9.38
There
is no marine WQO for BOD5 available in
Tolo Harbour and Channel. The maintenance discharge under Scenario 4 would
slightly change the pattern of mean BOD5 levels in Tolo
Harbour as compared to the baseline condition (Scenario 3) (see Figure 04 of
Appendix 4.4). However, the range of mean BOD5 levels in Tolo
Harbour predicted under both scenarios would still be within the same range
(from <2 mg/L to < 4 mg/L).
4.9.39
As
shown in the time series plots in Figures 20 and 21 of Appendix 4.6, the BOD5 levels at the
closest WSRs (F7 and F8) would increase during and after the maintenance
discharge, and can return to a condition similar to the baseline range within
about 2 weeks after the end of the maintenance discharge. The predicted BOD5
level at F7 and F8 would still comply with the target water quality objective
of WSD even the levels would be elevated during and after the THEES maintenance
discharge. The potential impact on F7
and F8 is further discussed in Sections 4.9.46 to 4.9.48.
E. coli
4.9.40
The
annual geometric mean E. coli pattern simulated under the THEES
maintenance discharge scenario (Scenario 4) is the same with that of the
baseline condition (Scenario 3) (Figure 07 of Appendix 4.4). The geometric mean E. coli levels predicted in most of the
assessment area including all the FCZs complied with the WQO of ≤610
no./100mL with or without the THEES maintenance. The geometric mean E. coli
level predicted at Lung Mei Beach (B1) was less than 10 no./100mL under both
scenarios, which complied well with the WQO of ≤180 no. /100 mL for
bathing water (Appendix 4.5).
4.9.41
The
annual geometric mean E. coli level predicted at the coral site in Sha
Tin Hoi (CR5) marginally exceeded the WQO of 610 no./100mL under both the
baseline condition (Scenario 3) and the THEES maintenance scenario (Scenario
4). The degree of exceedance is similar with and without the THEES maintenance
discharge. Impact on marine ecology including the coral communities is
separately assessed in Section 5.
4.9.42
The time series plots in Figures 16 to 18 of Appendix 4.6 showed that the disinfected THEES effluent discharge would cause no
obvious change to the baseline E. coli levels at all the selected WSRs
and indicator points. No adverse E.
coli impact is predicted from the THEES maintenance.
Sedimentation
4.9.43
The
model predicted that the sedimentation in Tolo Harbour and Channel would not be
adversely affected by the THEES maintenance discharge. The sedimentation patterns simulated under
Scenarios 3 and 4 are very similar (Figure 09 of Appendix 4.4). The maximum sedimentation
rates predicted in Tolo Harbour including all the coral sites are well below
the assessment criterion of 100 g/m2/day (Appendix 4.5). No adverse sedimentation
impact is predicted from the THEES maintenance.
Chlorophyll-a
4.9.44
The
WQOs for chlorophyll-a is ≤20 µg/L, ≤10 µg/L and ≤6
µg/L in Harbour Subzone, Buffer Subzone and Channel Subzone of the Tolo Harbour
and Channel WCZ respectively. The delineation of the three subzones are shown
in Figure 10 of Appendix 4.4. Tolo Harbour is a shallow landlocked water body with poor flushing
capacity, which is susceptible to algal formation and accumulation of algae. The predicted maximum 5-day running mean chlorophyll-a levels
exceed the WQOs under both baseline situation (Scenario 3) and THEES
maintenance (Scenario 4). The maximum values predicted at the WSRs range from
34 – 60 µg/L (in Harbour Subzone), 15 – 39 µg/L (in Buffer Subzone) and 8 – 18
µg/L (in Channel Subzone) under the THEES maintenance (Scenario 4) as compared
to the baseline range of 18 – 40 µg/L (in Harbour Subzone), 13 – 20 µg/L (in
Buffer Subzone) and 8 – 17 µg/L (in Channel Subzone) (under Scenario 3) (Appendix 4.5). The predicted mean chlorophyll-a levels are much lower. The
average chlorophyll-a levels ranged from ≥6 to <15 µg/L in most
areas of Harbour Subzone and from ≥3 to < 10 µg/L in most area of
Buffer Subzone and Channel Subzone under Scenario 4 (Figure 10 of Appendix 4.4).
4.9.45
As
shown in the time series plots in Figures 01 – 09 of Appendix 4.6, the chlorophyll-a elevations caused by the THEES maintenance
discharge would be reversible. The model predicted that the chlorophyll-a
levels can return to the condition similar to the baseline levels within about
2 weeks after termination of the THEES maintenance discharge.
Potential Impact to WSRs
WSD Flushing Water Intakes (F7
and F8)
4.9.47
As
shown in the time series plots in Figure 13 of Appendix 4.6, the SS exceedance of < 3 mg/L is instantaneous and reversible. The
SS levels would comply the WSD target for most of the times during and after
the THEES maintenance discharge. No unacceptable health impacts to the end
users of the intake water would be expected from this minor and instantaneous
SS increase (in view that the average SS levels over the THEES maintenance
period would be much lower than the WSD target). As a general measure to minimize any impact
on the flushing water intakes due to planned maintenance discharge, close
communication between DSD and WSD would be an effective means. Should it appear necessary, silt screen may
be installed at the flushing water intakes to reduce the SS impacts arising
from the planned maintenance discharge.
Seawater Intake of Marine
Science Laboratory (E1)
4.9.49
Full
compliances with the reference criteria provided by the CUHK are predicted at
E1 for UIA, E.coli, NH3-H, NO3-N, NO2-N,
SS and DO (Appendix 4.5) under the THEES maintenance scenario.
Figure 22 of Appendix 4.6 shows that the predicted baseline salinity levels at E1 would not be
affected by the THEES maintenance discharge. Thus, full compliance with the
target salinity objective of no more than +/- 2 psu from the ambient level
and < 2 psu change over 1 hour would
be achieved at E1. The THEES effluent is
fully treated, which is not expected to have adverse odour impact on E1.
Hydrogen sulphide impact upon E1 is not expected. No unacceptable water quality
impact upon the CUHK intake is predicted.
Planned Cooling Water Intake of
Science Park (C16)
4.9.50
The
maximum pollution levels predicted at the cooling water intake (C16) under the
THEES maintenance scenario are tabulated in Appendix 4.5. No specific water quality requirements are available for the cooling
water intake. No unacceptable water
quality impact upon the cooling water intake is predicted.
Ecological and Fisheries
Resources
4.9.51
Based
on the model prediction, the THEES maintenance discharge would cause a more
significant increase in the TIN, SS and chlorophyll-a level in the inner
Tolo Harbour (in Harbour Subzone). The predicted TIN, SS and chlorophyll-a
levels in the Buffer and Channel Subzones are less sensitive to the THEES
maintenance discharge. Other concerned parameters such as the predicted minimum
DO, geometric mean E.coli and maximum sedimentation rates are also not
sensitive to the THEES maintenance and not affected by the THEES effluent.
4.9.52
Nutrients
such as TIN are not toxic to marine life but may stimulate algal growth. The
presence of a certain amount of algae in water is also not harmful to marine
life in general. Only their uncontrolled growth as algal bloom or red tide
would adversely affect the environment. Chlorophyll-a is a green pigment
in plant. The level of chlorophyll-a can
provide an indication of algae or phytoplankton concentration in marine water.
4.9.54
The occurrence of the THEES maintenance would be remote with no more
than once in every 5 years. The 4-week THEES
maintenance assumed in the water quality modelling is a worse-case scenario. It
represents the maximum possible extent of water quality impact in Tolo Harbour.
The historic records showed that over the last 15 years, the
closure of the THEES occurred only for 3 days in December 2010 and 26 hours
only in November 2016.
4.9.55
The historic THEES closure event in December 2010 involved a more
significant volume of effluent discharge to Tolo Harbour. Appendix 4.7 compares the past red tide
occurrences in Tolo Harbour before, during and after this THEES
closure event. The comparison plot showed that there is no marked increase in
the red tide occurrence during and after this historic THEES closure. No red
tide was recorded within 2 months after the THEES maintenance.
4.9.56
Red tides are natural phenomena which occur seasonally in both
polluted and unpolluted waters. The model contour plots in Appendix 4.4 as well as the past water
quality monitoring data in Appendix 4.7 both showed a water
quality gradient with an increasing pollution trend towards the inner Tolo
Harbour, which is closer to the urbanized areas and pollution sources. However,
a significant portion of the red tide
incidents were recorded in the outer Tolo Channel (in Buffer and Channel
Subzones) further away from the pollution sources (Appendix 4.7). No direct correlation between
the increase in water pollution and red tide occurrence is identified. It is
believed that the formation of red tide is a complicated process. It would
depend on a combination of different factors such as the availability of
sunlight, wind condition, flow regime, light penetration, salinity
distribution, nutrient ratios and species competition, etc. From the
past record, the short-term THEES effluent discharge is not a critical factor
for triggering red tide in Tolo Harbour.
4.9.57
The TIN and chlorophyll-a
elevations due to the THEES maintenance are predicted to be reversible. The
baseline levels would be recovered within 2 weeks after the termination of the
discharge. The SS levels would also
return to the levels that are similar to the baseline range within 2 weeks
after the end of the THEES maintenance period.
The THEES maintenance event would be arranged outside the peak algae
blooming seasons to minimize the chance of algal bloom.
4.9.58
Appropriate
mitigation measures and Project-specific water quality monitoring programme as described in Sections 4.12 and 4.15
should be implemented to minimize the impact to the mariculture activities in
the nearby fish culture zones. Detailed assessment of ecological and fisheries
impacts is separately provided in Section 5 and Section 6 respectively. For
information, any potential impacts from red tide or Harmful Algal Blooms (HABs) that may arise in the Tolo
Harbour is currently managed and responded under the routine red tide
monitoring and management protocol and response plan adopted by the Hong Kong
government. AFCD is acting as the coordinator of the Red Tide Reporting
Network, to receive reports of red tide, conduct investigation and provide
warning of the risk associated and appropriate mitigation measures. The objectives of this red tide monitoring
programme are to provide coordination of monitoring and response to red
tides/HABs and fish kills and to compile and synthesize data necessary to
effectively manage fisheries resources and the marine ecosystems. The
existing red tide monitoring and management plan are described in the AFCD website. (https://www.afcd.gov.hk/english/fisheries/hkredtide/management/management.html).
Secondary Contact Recreational
Subzone and Bathing Beach
4.9.59
The
marine water in Tolo Harbour and Channel WCZ is designated under the WPCO as
secondary contact recreation subzone for water sports and water recreational
activities. Since the THEES effluents would be disinfected, the potential
health impact upon the users of the recreational waters due to E.coli
elevations would be minimized. As shown in Appendix 4.5 and Figures 16 to 18 of Appendix 4.6, the maintenance discharge would cause no obvious elevation of E.
coli levels as compared to the baseline condition at all WSRs including the
bathing beach.
Emergency Discharge to
Tolo Harbour
4.9.60
Emergency
discharge due to emergency situations (e.g. power / treatment failure) may
occur during the Project operation. Scenario 5 assumed that an emergency
discharge from the Project would occur for a period of 3 hours in case of power
or plant failure.
4.9.61
The
water quality simulation results are presented as contour plots and are
compared between Scenario 3 and Scenario 5 in Appendix 4.4 for DO, BOD5, TIN, UIA, E.
coli, SS, chlorophyll-a and sedimentation rate. The water quality levels at different WSRs
predicted under Scenario 5 are tabulated in Appendix 4.5. Some model results in Appendix 4.4 and Appendix 4.5 are presented as annual mean over the 1-year simulation period to
illustrate that emergency discharge would not affect the average water quality
condition over the year and thus the associated chronic effect on marine life
would be minimal (also see Section 4.9.27).
4.9.62
The
time required for water quality recovery from the emergency discharge at
selected WSRs is illustrated in the time series plots of Appendix 4.8.
Dissolved Oxygen (DO)
4.9.63
Full
WQO compliance for DO was predicted at all WSRs under the emergency situation
(Scenario 5) except for the mangrove site at Tolo Pond (M1) where the minimum
surface DO was 1.3 mg/L, as compared to the WQO of ≥4 mg/L (Appendix 4.5). However, under the baseline scenario (Scenario 3), the minimum surface
DO level at M1 was also 1.3 mg/L. The low DO level was not caused by the
emergency discharge.
4.9.64
The
time series plots in Figure 19 of Appendix 4.8 showed the THEES effluent would not change nor decrease the DO level at
M1 as compared to the baseline condition. No adverse DO impact would be induced
by the emergency discharge.
Nitrogen Related Parameters
4.9.65
No
statutory WQO is available for UIA and TIN in the marine water of Tolo Harbour
and Channel. The emergency discharge would not change the baseline mean UIA and
TIN levels (Appendix 4.5). The time series plot (Figure 10 of Appendix 4.8) showed that immediate TIN elevation would occur at the two closest
WSRs, namely WSD flushing water intake at Tai Po (F7) and coral site near TPIE
(CR1), right after the emergency discharge. The TIN levels would be recovered
to the baseline condition within about 2 days after termination of the
emergency discharge. The predicted TIN
elevations at the remaining selected WSRs and indicator points (F8, CR2, FC1,
FC2, FC3, FC4, B1, TM3 and TM6) are negligible.
4.9.66
As
shown in Figure 05 and Figure 06 of Appendix 4.4, the emergency discharge (Scenario 5) would not change the annual mean
UIA and TIN patterns in Tolo Harbour as compared to the baseline condition
(Scenario 3).
4.9.67
No
adverse water quality impact associated with the nitrogen parameters would
arise from the emergency discharge.
Suspended Solids (SS)
4.9.68
There
is no WQO available for SS in the marine water of Tolo Harbour and Channel. As
shown in the time series plots (Figures 13 to 15 of Appendix 4.8), the predicted SS elevations caused by the emergency discharge are
minimal or negligible at all selected WSRs.
4.9.69
As
shown in Figure 08 of Appendix 4.4, the emergency discharge (Scenario 5) would not change the annual mean
SS pattern in Tolo Harbour as compared to the baseline condition (Scenario 3).
4.9.70
The
emergency discharge would not cause any adverse SS impact in Tolo Harbour and
Channel.
5-Day Biochemical Oxygen Demand
(BOD5)
4.9.71
There
is no marine WQO for BOD5 available in
Tolo Harbour and Channel. The time series plots in Figure 20 and Figure 21 of
Appendix 4.8 showed that the emergency discharge
would cause no obvious change to the BOD5 level at the
WSD flushing water intakes at Tai Po (F7) and Sha Tin (F8).
4.9.72
As
shown in Figure 04 of Appendix 4.4, the emergency discharge (Scenario 5) would not change the annual mean
BOD5 pattern in Tolo Harbour as compared to the baseline condition (Scenario
3).
4.9.73
No
adverse BOD5 impact would arise from the emergency discharge.
E. coli
4.9.74
The
short-term emergency discharge (Scenario 5) would not affect the annual
geometric mean E. coli levels at all WSRs (Appendix 4.5). The short-term E.coli elevation is predicted at WSRs (F7, CR1)
close to TPIE. The degree of E.coli elevation would be reduced in WSR
(CR2) and indicator point (TM3) further away. The E.coli elevations in
all remaining WSRs are negligible (Figures 16 to 18 of Appendix 4.8).
The baseline levels at F7, CR1, CR2 and TM3 would be recovered within 2 days
after termination of the emergency discharge. As shown in Figure 07 of Appendix 4.4, the annual geometric mean E. coli patterns are similar under
Scenario 5 (with emergency discharge) and Scenario 3 (baseline condition).
Sedimentation
4.9.75
The
short-term discharge under Scenario 5 would not adversely affect the maximum
sedimentation rates in Tolo Harbour and Channel as shown in Appendix 4.5. The maximum sedimentation levels predicted in Tolo Harbour including
all the coral sites fully complied with the criterion of ≤100 g/m2/day
under the emergency situation. As shown
in Figure 09 of Appendix 4.4, the emergency discharge (Scenario 5) would not change the pattern of
annual mean sedimentation rates in Tolo Harbour as compared to the baseline
condition (Scenario 3). No adverse sedimentation impacts would be caused by the
emergency discharge.
Chlorophyll-a
4.9.76
The
short-term discharge under Scenario 5 would not change the maximum 5-day
running mean chlorophyll-a levels in Tolo Harbour as shown in Appendix 4.5. The predicted maximum 5-day running mean chlorophyll-a levels
under Scenario 5 at all selected WSRs are the same as that of the baseline
condition (Scenario 3) as shown in Appendix 4.5.
4.9.77
As
shown in the time series plots in Figures 01 to 09 of Appendix 4.8, the chlorophyll-a levels at all selected WSRs are not sensitive to the
emergency discharge. The emergency discharge
would induce no obvious elevation of chlorophyll-a at all selected WSRs or
indicator points. No adverse chlorophyll-a impact is predicted.
Potential Impact to WSRs
WSD Flushing Water Intakes (F7
and F8)
4.9.78
The
maximum E.coli level predicted at the WSD flushing water intake at Tai
Po (F7) would inevitably increase and reach 36,500 no./100mL under the
emergency situation, as compared to the WSD target objective of 20,000
no./100mL. The maximum E.coli value predicted at the WSD flushing water
intake at Sha Tin (F8) far away was well below the target limit.
4.9.79
As
shown in the time series plots (Figure 16 of Appendix 4.8), significant E. coli elevations are predicted at F7 right after
the emergency discharge. The baseline E. coli levels would be recovered
within about 2 days after termination of the emergency discharge.
4.9.80
The
maximum SS level predicted at the WSD flushing water intake at Sha Tin (F8)
would exceed the WSD target of 10 mg/L but the predicted maximum value (10.9
mg/L) under Scenario 5 is the same as that of the baseline condition (Scenario
3) as shown in Appendix 4.5. As a general measure to minimize any impact on the flushing water
intakes due to emergency discharge, close communication between DSD and WSD
would be an effective means. Should it
appear necessary, silt screen may be installed at the flushing water intakes to
reduce the SS impacts arising from the emergency discharge.
4.9.81
In
case of emergency discharge, WSD would be notified and would take appropriate
actions such as to increase the disinfection level for the seawater extracted
from the flushing water intake at Tai Po as required. With proper
implementation of the mitigation measures and contingency plan for emergency
situation as recommended in Sections 4.12 and 4.15, no
unacceptable health implications to the end users of the flushing water due to E.coli
elevations would arise.
4.9.82
The
emergency discharge would not change the water quality at F7 and F8 for other
parameters of concern.
Seawater Intake of Marine
Science Laboratory (E1)
4.9.83
Full
compliances with the reference criteria provided by the CUHK are predicted at
E1 for UIA, E.coli, NH3-H, NO3-N, NO2-N,
SS and DO (Appendix 4.5) under the emergency discharge scenario. Figure 22 of Appendix 4.8 shows that the predicted baseline salinity levels at E1 would not be
affected by the emergency discharge. Thus, full compliance with the target
salinity objective of no more than +/- 2 psu from the ambient level and < 2 psu change over 1 hour would be
achieved at E1. As indicated in Appendix 4.5, the emergency discharge would not change the baseline water quality
levels for all selected water quality parameters. The short-term emergency
discharge in Tai Po is not expected to affect this distant receiver of over 2
km away. Hydrogen sulphide impact upon E1 is not anticipated. No unacceptable
water quality impact upon the CUHK intake is predicted.
Planned Cooling Water Intake of
Science Park (C16)
4.9.84
The
maximum pollution levels predicted at the cooling water intake (C16) under the
emergency discharge scenario are tabulated in Appendix 4.5. No specific water quality requirements are available for the cooling
water intake. The water quality levels for
all assessment parameters predicted under Scenario 5 at C16 are the same as
that predicted under the baseline condition (Scenario 3). No adverse water
quality impact upon the cooling water intake is predicted.
Ecological and Fisheries
Resources
4.9.85
Based
on the model prediction in Appendix 4.5, the emergency discharge would cause no obvious water quality changes
at the ecological and fisheries resources for all concerned parameters
including the predicted minimum DO, geometric mean E. coil, maximum
sedimentation rates and maximum 5-day running mean chlorophyll-a. Detailed assessment of ecological and fisheries impacts is
separately provided in Section 5 and Section 6 respectively.
Secondary Contact Recreational Subzone
and Bathing Beach
4.9.86
The
marine water in Tolo Harbour and Channel WCZ is designated under the WPCO as
secondary contact recreation subzone for water sports and water recreational
activities. The emergency discharge would not change the geometric mean E.coli
level at all identified WSRs as shown in Appendix 4.5. No health impact upon the users of the recreational waters due to E.coli
elevations would be anticipated.
Handling and
Transportation of Pre-treated Food Waste
4.10.1
The Project would receive
pre-treated food waste from the proposed OWPC (see Section 4.5.10) for co-digestion with sludge generated from
sewage treatment. Pre-treated food waste
would contain high content of nutrients and organic matter, including BOD5 and Chemical Oxygen Demand (COD). Any
spillage or rainwater wash off during transportation or handling of the
pre-treated food waste would potentially generate water pollution. However,
provided that the incoming pre-treated food waste is transferred to the Project
facilities through enclosed pipelines, no adverse water quality impact would be
expected. Also, given that any
pre-treated food waste loading and handling areas in the Project site would be
enclosed within buildings to contain accidental spills, contamination of
surface runoff would not arise.
Wastewater from Sludge / Pre-treated Food Waste
4.10.2
Sludge from daily operation of
the Project in the future would require sludge dewatering before final
disposal. Any wastewater generated from
the sludge treatment facility, pre-treated food waste handling facility and the
facility for co-digestion of pre-treated food waste would contain high BOD5, COD and nutrient content. It may cause
water pollution, if controlled.
Containment and design measures will be adopted to collect the
wastewater for feeding back into the sewage treatment process within the plant.
There will be no discharge of wastewater.
4.10.3
The existing TPSTW is also
receiving wastewater from sludge dewatering process as well as the leachate
from Shuen Wan Landfill, which also have high COD, BOD5 and nutrient content. The TSE of the
existing TPSTW complied well with the effluent discharge standards. Hence, any
wastewater generated from pre-treated food waste handling and co-digestion
facilities can also be practically treated under the Project to meet the
effluent discharge standards.
Non-point Source Surface
Runoff
4.10.4
Potential water quality impact
may arise from contaminated surface runoff during operational phase. Typical surface runoff in the existing TPSTW
may contain small amount of grits and dirt. The proposed expansion site is
currently occupied by waste recycling workshops including the operation of
large machineries and open stockpiles of wastes (e.g. metals, plastics). The
existing surface runoff in the proposed expansion site may be contaminated with
metals, grease, dirt, grits and oil. This Project will not increase the paved
surface areas and will not change the amount of surface runoff generated in the
Project site.
4.10.5
According to the DSD
"Stormwater Drainage Manual", annual rainfall in Hong Kong is around
2,400 mm. However, the EPD study namely
“Update on Cumulative Water Quality and Hydrological Effect of Coastal
Developments and Upgrading of Assessment Tool (Update Study)” suggested that only rainfall events of
sufficient intensity and volume would give rise to runoff and that runoff
percentage is about 44% and 82% for dry and wet season, respectively. Therefore, only 1,512 mm of 2,400 mm annual
rainfall would be considered as effective rainfall that would generate runoff
(i.e. 1,512 mm = 2,400 mm × (82%+44%)/2).
4.10.6
The footprint of the Project
site is about 14 hectares (140,000 m2). Assuming 0.9 as the runoff coefficient (for
concrete surfaces), the non-point source discharge or surface run-off is
estimated to be 522 m3/day (= 0.9 × 1,512 mm/year ×140,000 m2). The nature or quality of the future surface
runoff generated under this Project would be similar to that of the existing
TPSTW. It is anticipated that with proper implementation of best management
practices as recommended in Section 4.12, no adverse water quality impact from
non-point source surface run-off is expected.
Chemical Spillage
4.10.7
A number of chemicals, such as
ferric chloride and polymers, would be stored onsite and used for wastewater
treatment process such as sludge conditioning / dewatering. Chemicals such as lubricants may also be used
for plant operation. Potential water quality impact could arise from
transferring and storage of these chemicals during operational phase, if
uncontrolled. The potential water
quality impact can however be practically minimized through the implementation
of appropriate chemical storage and management measures as recommended in
Section 4.12.
Construction Site Run-off and General Construction Activities
Wheel Washing Water
4.11.3
All vehicles and plant should
be cleaned before they leave a construction site to minimize the deposition of
earth, mud, debris on roads. A wheel washing bay should be provided at every
site exit if practicable and wash-water should have sand and silt settled out
or removed before discharging into storm drains. The section of construction
road between the wheel washing bay and the public road should be paved with
backfall to reduce vehicle tracking of soil and to prevent site run-off from entering
public road drains.
Rubbish and Litter
4.11.4
Good site practices should be
adopted to remove rubbish and litter from construction sites so as to prevent the
rubbish and litter from spreading from the site area. It is recommended to
clean the construction sites on a regular basis.
Construction Site
Run-off
4.11.5
The site practices outlined in
ProPECC PN 1/94 “Construction Site Drainage” should be followed as far as
practicable to minimize surface run-off and the chance of erosion. The
following measures are recommended to protect water quality and sensitive uses
of the coastal area, and when properly implemented should be sufficient to
adequately control site discharges so as to avoid water quality impact.
4.11.6
Surface run-off from
construction sites should be discharged into storm drains via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sedimentation basins. Channels or earth bunds or sandbag barriers should be
provided on site to properly direct stormwater to such silt removal facilities.
Perimeter channels at site boundaries should be provided on site boundaries
where necessary to intercept storm run-off from outside the site so that it
will not wash across the site. Catchpits and perimeter channels should be
constructed in advance of site formation works and earthworks.
4.11.7
Silt removal facilities,
channels and manholes should be maintained and the deposited silt and grit
should be removed regularly, at the onset of and after each rainstorm to
prevent local flooding. Before disposal at the public fill reception
facilities, the deposited silt and grit should be solicited in such a way that
it can be contained and delivered by dump truck instead of tanker truck. Any practical options for the diversion and
re-alignment of drainage should comply with both engineering and environmental
requirements in order to provide adequate hydraulic capacity of all drains.
Minimum distance of 100m should be maintained between the discharge points of
construction site run-off and the existing saltwater intakes.
4.11.8
Construction works should be
programmed to minimize soil excavation works in rainy seasons (April to
September). If excavation in soil cannot be avoided in these months or at any
time of year when rainstorms are likely, for the purpose of preventing soil
erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin,
and temporary access roads should be protected by crushed stone or gravel, as
excavation proceeds. Intercepting channels should be provided (e.g. along the
crest / edge of excavation) to prevent storm runoff from washing across exposed
soil surfaces. Arrangements should always be in place in such a way that
adequate surface protection measures can be safely carried out well before the
arrival of a rainstorm.
4.11.9
Earthworks final surfaces
should be well compacted and the subsequent permanent work or surface
protection should be carried out immediately after the final surfaces are
formed to prevent erosion caused by rainstorms. Appropriate drainage like
intercepting channels should be provided where necessary.
4.11.10
Measures should be taken to
minimize the ingress of rainwater into trenches. If excavation of trenches in
wet seasons is necessary, they should be dug and backfilled in short sections.
Rainwater pumped out from trenches or foundation excavations should be
discharged into storm drains via silt removal facilities.
4.11.11
Construction materials (e.g.
aggregates, sand and fill material) on sites should be covered with tarpaulin
or similar fabric during rainstorms.
4.11.12
Manholes (including newly
constructed ones) should always be adequately covered and temporarily sealed so
as to prevent silt, construction materials or debris from getting into the
drainage system, and to prevent storm run-off from getting into foul sewers.
Discharge of surface run-off into foul sewers must always be prevented in order
not to unduly overload the foul sewerage system.
Licensing of
Construction Site Discharge
4.11.14
Contractor must register as a
chemical waste producer if chemical wastes would be produced
from the construction activities. The
Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular
the Waste Disposal (Chemical Waste) (General) Regulation, should be observed
and complied with for control of chemical wastes.
4.11.15
Any service shop and
maintenance facilities should be located on hard standings within a bunded
area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving
activities with potential for leakage and spillage should only be undertaken
within the areas appropriately equipped to control these discharges.
4.11.16
Disposal of chemical wastes
should be carried out in compliance with the Waste Disposal
Ordinance. The Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes published under the Waste
Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:
n
Suitable containers should be
used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;
n
Chemical waste containers should
be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents; and
n
Storage area should be selected
at a safe location on site and adequate space should be allocated to the storage area.
4.11.18
Notices should be posted at
conspicuous locations to remind the workers not to discharge
any sewage or wastewater into the surrounding environment. Regular environmental audit of the
construction site will provide an effective control of any malpractices and can
encourage continual improvement of environmental performance on site. It is anticipated that sewage generation
during the construction phase of the project would not cause water pollution
problem after undertaking all required measures.
Contaminated Site
Run-off
4.11.19
Any excavated contaminated
material and exposed contaminated surface should be properly housed and covered
to avoid generation of contaminated run-off. Open stockpiling of contaminated
materials should not be allowed. Any
contaminated run-off should be properly collected and treated to reduce the
pollution level to an acceptable standard and remove any prohibited substances
(such as total petroleum hydrocarbon) to an undetectable range. All treated effluent from the wastewater
treatment units shall meet the conditions of the discharge license (see Section
4.11.13) and the requirements as stated in the TM-DSS.
Demolition Works
4.11.20
The decommissioned treatment
facilities shall be cleaned prior to their demolition or removal. All wastewater residues, if any, in the
decommissioned facilities shall be properly collected, contained and treated
within the plant and shall not be discharged directly into the drainage system
or the environment. Chemical residues, if any, in the decommissioned facilities
shall be properly collected, handled and disposed in accordance with the Waste
Disposal (Chemical Waste) (General) Regulations and the Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes published by EPD (as
specified in Sections 4.11.14 to 4.11.16), and should be collected by a licensed
chemical waste collector for proper disposal at the Chemical Waste Treatment
Centre at Tsing Yi.
4.11.21
Proper site practice and good
site management (as specified in the ProPECC PN 1/94 “Construction Site
Drainage”) and presented in Sections 4.11.2 to 4.11.13 above shall be followed to prevent polluted
run-off and site effluent generated from the demolition works areas from
directly entering the surrounding waters.
4.12.1
Mitigation measures as listed
below are recommended to minimize the potential water quality impacts during
the operational phase.
Normal Project / THEES
Operation – Treated Effluent Discharge to Victoria Harbour
4.12.2
No adverse water quality impact
upon the Victoria Harbour WCZ is predicted and no mitigation measures are
therefore required.
THEES Maintenance –
Treated Effluent Discharge to Tolo Harbour
Emergency Discharge to Tolo Harbour
4.12.5
Emergency discharges from the
Project would be the consequence of pump failure, interruption of the electrical
power supply or failure of treatment units.
Dual power supply or ring main supply from CLP should be provided for
the Project to prevent the occurrence of power failure. In addition, standby
facilities for the main treatment units and standby equipment parts /
accessories should also be provided in order to minimize the chance of
emergency discharge. The occurrence of
such emergency events would therefore be very remote.
4.12.6
To provide a mechanism to
minimize the impact of emergency discharges and facilitate subsequent
management of any emergency, an emergency contingency plan has been formulated
by the DSD to clearly state the response procedure in case of pumping stations
or sewage treatment works failure. The
existing contingency plan developed by DSD is given in Appendix 4.9. The plant operators of
the Project should carry out necessary follow-up actions according to the
procedures of this existing contingency plan to minimize any water quality impact
due to emergency discharge. The plant operators of the Project should also
closely communicate with WSD in order to minimize any impact on WSD seawater
intake due to emergency discharge. WSD
may consider shutting down the Tai Po seawater pumping station or provision of
a higher disinfection level for a short period of time in order to minimize any
adverse impacts, should such be necessary.
Handling and Transportation of Pre-treated Food Waste
4.12.7
The incoming pre-treated food
waste should be transferred to the Project facilities through enclosed
pipelines. The pre-treated food waste loading and handling areas of this
Project should be enclosed within buildings to contain any accidental spills.
Wastewater from Sludge / Pre-treated Food Waste
4.12.8
All wastewater generated from
the sludge dewatering process and the pre-treated food waste related facilities
should be fed back into the upgraded TPSTW for treatment before final
disposal. No direct discharge of
wastewater shall be allowed under this Project.
Non-point Source Surface
Runoff
4.12.9
Best Management Practices
(BMPs) for storm water discharge (as listed below) are recommended for the
Project to minimize potential adverse water quality impacts.
Design Measures
n
Exposed surface shall be avoided
within the proposed Project site to minimize soil erosion. Development site shall be either hard paved
or covered by landscaping area where appropriate to reduce soil erosion.
n
The drainage system of the
Project should be designed to avoid any case of flooding.
Devices / Facilities to
Control Pollution
n
Screening facilities such as
standard gully grating and trash grille, with spacing which is capable of
screening off large substances such as fallen leaves and rubbish should be
provided at the inlet of drainage system.
n
Road gullies with standard
design and silt traps should be incorporated during the detailed design of any
new access roads to remove particles present in storm water runoff.
Administrative Measures
n
Good management measures such
as regular cleaning and sweeping of road surface / open areas is proposed. The road surface / open area cleaning should
also be carried out prior to occurrence of rainstorm.
n
Manholes, as well as storm
water gullies, ditches provided among the development areas should be regularly
inspected and cleaned (e.g. monthly).
Additional inspection and cleansing should be carried out before
forecast heavy rainfall.
Chemical Spillage
4.12.10
Chemical storage and handling areas
should be bunded and enclosed within buildings. Separate drainage system should
be provided as appropriate to avoid any spilled chemicals from entering into
the storm drain in case of accidental spillage.
Also, adequate tools for cleanup of spilled chemicals should be stored
on site and appropriate training shall be provided to staff to reduce the
chance of water pollution.
Construction Phase
4.13.1
With proper implementation of
mitigation measures, the potential water quality impact, if any, generated from
the Project would be localized. No unacceptable cumulative water quality with
other concurrent projects (see Section 4.5) would arise.
Operational Phase
4.13.2
The background pollution
loading into the marine water has been estimated and included in the modelling
exercise for cumulative assessment. The
model predicted that this Project would not contribute any unacceptable cumulative
water quality impact with proper implementation of the recommended mitigation
measures.
4.14.1
With proper implementation of
mitigation measures, no residual water quality impact is expected in
construction and operational phases.
Land-based Construction
Works
4.15.1
The potential water quality
impact from the land-based construction works can be controlled by the
recommended mitigation measures. Regular site inspections should be undertaken
during the construction to ensure that the recommended mitigation measures are
properly implemented. Discharge
license(s) should be obtained under the WPCO if there are any construction site
discharges. Monitoring of the
construction site effluent shall be carried out in accordance with requirements
stipulated in the WPCO discharge licenses.
Normal Project / THEES
Operation – Treated Effluent Discharge to Victoria Harbour
Effluent Monitoring
4.15.2
The effluent of the existing
TPSTW and STSTW are being routinely monitored by DSD. It is recommended that
the existing effluent monitoring programme of DSD should be continued and implemented for the upgraded TPSTW and
the future CSTW. Where necessary, the effluent monitoring data can be used for
interpretation of the river and marine water quality monitoring results
collected under this Project. Monitoring of the treated effluent from the
Project should also be carried out in accordance with the requirements
stipulated in the WPCO discharge license.
River and Marine Water
Quality Monitoring in Victoria Harbour
4.15.3
Under normal operation of
THEES, the effluent from the Project would be transported to the Victoria
Harbour for discharge into the KTR and then to the KTAC and KTTS. A one-year impact water quality monitoring
programme covering dry and wet seasons is proposed for KTR at a frequency of
once per month after commissioning of the New West Plant (tentatively in 2029),
see Section 4.6.1. The monitoring results should be compared with the routine
river water quality monitoring data collected by EPD to verify whether there is
any adverse water quality impact at KTR as compared to that before the
implementation of this Project.
4.15.4
Marine water quality monitoring
is also recommended in Victoria Harbour. A one-year baseline monitoring
programme covering dry and wet seasons is proposed at a frequency of twice per
month to establish the baseline water quality conditions at selected monitoring
points in Victoria Harbour. The baseline monitoring programme should be carried
out prior to the commissioning of the New West Plant (see Section 4.6.1). A
one-year impact monitoring in Victoria Harbour covering dry and wet seasons
should be conducted twice per month after commissioning of the New West Plant.
The impact monitoring results shall be compared with the baseline monitoring
results to verify whether there is any adverse marine water quality impact in
Victoria Harbour as compared to that before the implementation of this Project.
4.15.5
In case adverse impact on KTR
or Victoria Harbour is identified from the effluent and water quality
monitoring results, the operating conditions of the upgraded TPSTW and THEES
system should be investigated. After completion of the one-year impact
monitoring programme for KTR and Victoria Harbour, a review shall be conducted
by DSD to determine whether such monitoring shall be continued. The review
results shall be submitted to EPD. Any amendment on the river and marine water
quality monitoring programme shall be agreed by EPD. Details of the monitoring
programme are provided in the standalone EM&A Manual.
THEES Maintenance
Discharge to Tolo Harbour
4.15.6
Marine water quality monitoring
is recommended in Tolo Harbour for the THEES maintenance event. A one-year
baseline monitoring programme covering dry and wet seasons is proposed at a
frequency of twice per month to establish the baseline water quality conditions
at selected monitoring points. The baseline monitoring programme should be
carried out prior to the construction of this Project. In case of THEES
maintenance during the construction phase of the Project and after
commissioning of the New West Plant tentatively scheduled in 2029 (see Section
4.6.1), marine water quality in Tolo Harbour should be monitored daily during
and after the maintenance period. The monitoring should be carried out until
the baseline water quality is restored for at least 2 consecutive days or at
least 4 weeks after termination of the THEES maintenance discharge (whichever
is longer). The flow and quality of the THEES maintenance discharge (from the
existing / upgraded TPSTW and the existing STSTW / CSTW) should also be
monitored daily during the THEES maintenance period.
4.15.7
The monitoring programme for
THEES maintenance should continue throughout the construction phase of the
Project as well as in the first 3 years after commissioning of the New West
Plant. After the first 3 years of the New West Plant operation, a review shall
be conducted by DSD to determine whether such monitoring shall be continued.
The review results shall be submitted to EPD, AFCD, WSD and other relevant
parties. Any amendment on the monitoring programme shall be agreed by EPD, AFCD
and WSD. Details of the monitoring programme and an event and action plan for
the THEES maintenance are provided in the standalone EM&A Manual.
Emergency Discharge to
Tolo Harbour
4.15.8
Marine water quality monitoring
in Tolo Harbour should be carried out for any emergency discharge event. A one-year
baseline monitoring programme covering both dry and wet seasons is proposed at
a frequency of twice per month to establish the baseline water quality
conditions at selected monitoring points prior to the construction of this
Project. The baseline monitoring periods for emergency discharge and THEES
maintenance may be overlapped. In case of emergency discharge during the
construction phase of this Project and after commissioning of the New West
Plant, marine water quality in Tolo Harbour should be monitored daily
throughout the emergency discharge period until the baseline water quality is
restored for at least 2 consecutive days or at least 1 week after termination
of the discharge (whichever is longer). The flow and quality of the emergency
discharge should also be monitored daily during the emergency discharge
period.
4.15.9
The monitoring programme for
emergency discharge shall continue throughout the construction phase of the
Project as well as in the first 3 years after commissioning of the New West Plant.
After the first 3 years of the New West Plant operation, a review shall be
conducted by DSD to determine whether such monitoring shall be continued. The
review results shall be submitted to EPD, AFCD, WSD and other relevant parties.
Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD.
Details of the monitoring programme and an event and action plan for the
emergency discharge are provided in the standalone EM&A Manual.
4.16
Conclusions
Construction Phase
4.16.1
Only land-based construction
will be carried out under the Project. Water quality impacts may result from
the general construction activities, construction site run-off, sewage from
construction workforce, accidental chemical spillage, polluted runoff and
wastewater from contaminated materials and demolition works. The impacts could
be mitigated and controlled by implementing the recommended mitigation
measures. No unacceptable water quality impacts is expected. Regular site
inspections should be undertaken routinely to inspect the construction
activities and works area to ensure the recommended mitigation measures are
proper implemented.
Operational Phase
Project Effluent
Discharge
4.16.2
Potential water quality impacts due to the Project effluent discharge to
marine water have been quantitatively assessed by mathematical modelling.
4.16.3
Following the existing
practice, the treated effluent from the Project will be discharged to the
Victoria Harbour through the THEES under normal operation. The treated effluent
would be discharged into the KTAC and KTTS and eventually into the open channel
of Victoria Harbour. The model results showed that there would be no
unacceptable water quality impacts arising from the Project at all
representative WSRs identified in the assessment area. No adverse water quality impact upon Victoria Harbour would arise from
this Project.
4.16.4
Maintenance of the THEES is required to ensure proper functioning and
integrity of the system. During the inspection or maintenance of the THEES
tunnel, temporary suspension of the normal THEES operation with effluent bypass
into the Tolo Harbour is unavoidable to provide a safe and dry zone within the
tunnel. The model results indicated that the pollution level at certain WSRs in
Tolo Harbour would be temporarily increased during the maintenance period, but
the pollution elevation associated with the maintenance discharge would be
reversible. The THEES maintenance
discharge would be scheduled outside the algae blooming season to minimize the
risk of red tide occurrence. The scheduling of the maintenance discharge would
also take into account any ongoing blooming event in the area, which may occur
outside the blooming season. Furthermore, an event and action plan and a marine
water quality monitoring programme (as presented in the standalone EM&A
Manual) are proposed for the THEES maintenance event to minimize the water
quality impact.
4.16.5
Emergency discharges from the Project would be the consequence of pump
failure, interruption of the electrical power supply or failure of treatment
units. Mitigation measures, including dual power supply or ring main supply
from CLP, standby pumps, treatment units and equipment, would be provided to
avoid the occurrence of any emergency discharge. In case of emergency
situation, the procedures and follow up actions stipulated in the existing
contingency plan formulated by DSD shall be implemented to minimize the impact
of emergency discharges and facilitate subsequent management of the emergency
situation. An event and action plan and
a marine water quality monitoring programme (as presented in the standalone
EM&A Manual) are also proposed for the emergency discharge event to
minimize the water quality impacts.
Others
4.16.6
Potential water quality impacts
may also arise from the handling and transportation of pre-treated food waste,
wastewater generated from the sludge / pre-treated food waste related
processes, non-point source surface runoff from paved areas and accidental
chemical spillage during the operational phase. The potential water quality
impacts can be prevented by implementation of the recommended mitigation
measures. No unacceptable water quality
impacts is expected.