9.2 Relevant
Legislation, Standards and Guidelines. 9-
9.3 Potential
Hazard Associated with Landfill Gas and Leachate
9.4 Landfill
Gas Assessment Criteria and Methodology
9.5 Description
of the Environment
9.6 Qualitative
Landfill Gas Assessment
9.7 Recommended
Precautionary and Protection Measures. 9-
9.8 Evaluation
of Residual Impacts
9.9 Environmental
Monitoring and Audit (EM&A) Requirements
9.10 Contingency
Plan for Construction and Operational Phases
List of TABLES
Table 9.1.... Classification of Risk Categories
Table 9.2.... General
Categorization of Risk
Table 9.3.... Generic
Protection Measures for Planning Stage Categorization
Table 9.4.... Definition
of Control Terms
Table 9.5.... Summary
of LFG monitoring data during 2016 to 2020
Table 9.6.... Summary
of Surface Gas Emissions during 2016 to 2020
Table 9.7.... Summary
of Qualitative Source-Pathway-Target Analysis
Table 9.8.... Actions
in the Event of Gas Being Detected in Excavations
List of Figures
Figure 9.1 Landfill Gas Consultation
Zone for Shuen Wan Restored Landfill
List of Appendices
Appendix 9.1 Geology Map for Project Site
Appendix 9.2 Locations of LFG Monitoring
Appendix 9.3 LFG Monitoring Data for Shuen Wan Restored Landfill
Appendix 9.4 Facilities Surrounding the Project Site
n Section 1.1 (f)
in Annex 7 and Section 3.3 in Annex 19 of Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM);
n Landfill Gas
Hazard Assessment Guidance Note (EPD/TR8/97) (Guidance Note)
n Practice Note
for Professional Person (ProPECC) PN3/96 ¡V Landfill Gas Hazard Assessment for
Developments adjacent to Landfills
n Man-made
pathways e.g. utility connections, stormwater channels, etc.;
n Natural
pathways such as rock jointing planes, fissures, and other naturally occurring
phenomena which may promote or give rise to the transmission of gas over
distances; and
n A combination of
the previous categories. An example of the latter may be, for instance, where a
specific geological feature promotes gas transmission but which stops short of
directly linking the landfill and target. A man-made connection, however, may
also co-exist near the edge of the geological feature, in combination with the
former, may act to link the two sites. In this instance, careful assessment of
the likelihood of the mechanism acting to link the two pathways needs to be
undertaken before assigning an appropriate pathway classification.
n a broad assessment of the specific permeability of the soil;
n spacing,
tightness and direction of the fissures/ joints;
n topography;
n depth and
thickness of the medium through which the gas may migrate (which may be
affected by groundwater level);
n nature of the
strata over the potential pathway;
n number of
different media involved; and
n depth to
groundwater
table and groundwater flow patterns.
High Sensitivity
|
¡P
Buildings and structures with ground level or below
ground rooms/ voids or into which services enter directly from the ground and
to which members of the general public have unrestricted access or which
contain sources of ignition.
¡P
This would include any developments where there is a
possibility of additional structures being erected directly on the ground on
an ad hoc basis and
thereby without due regard to the potential risks.
|
Medium Sensitivity
|
¡P
Other buildings, structures or service voids where there
is access only by authorized, well trained personnel, such as the staff of utility
companies, who have been briefed on the potential hazards relating to
landfill gas and the specific safety procedures to be followed.
¡P
Deep excavations.
|
Low Sensitivity
|
¡P
Buildings/ structures which are less prone to gas ingress
by virtue of their design (such as those with a raised floor slab).
¡P
Shallow excavations.
¡P
Developments which involve essentially outdoor activities
but where evolution of gas can pose potential problems.
|
Table 9.1 Classification
of Risk Categories
Source |
Pathway |
Target Sensitivity |
Risk Category |
Major |
Very short/direct |
High |
Very high |
Medium |
High |
||
Low |
Medium |
||
Moderate short/direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long/indirect |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Medium |
Very short/direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderate short/direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long/indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very low |
||
Minor |
Very short/direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderate short/direct |
High |
Medium |
|
Medium |
Low |
||
Low |
Very low |
||
Long/indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very low |
Table 9.2 General
Categorization of Risk
Category |
Level of Risk |
Implication |
A |
Very
high |
The type of development being
proposed is very undesirable and less sensitive form of development should be
considered. At the very least, extensive engineering measures, alarm systems
and emergency action plans are likely to be required. |
B |
High |
Significant engineering
measures will be required to protect the planned development. |
C |
Medium |
Engineering measures will
be required to protect the proposed development. |
D |
Low |
Some precautionary measures
will be required to ensure that the planned development is safe. |
E |
Very
low |
The
risk is so low that no precautionary measures are required. |
Table 9.3 Generic
Protection Measures for Planning Stage Categorization
Level of Risk |
Generic Protection
Measures |
Very
high |
For the planned development
active control of gas, supported by barriers and detection systems. Another,
less sensitive form of development should also be considered. |
High |
Active control of gas,
including barriers and detection systems. |
Medium |
Use of ¡§semi-active¡¨ or
enhanced passive controls. Detection systems in some situations. |
Low |
Passive control of gas
only. |
Very
low |
No precautionary
measures required. |
Table 9.4 Definition
of Control Terms
Term |
Definition |
Active
control |
Control of gas by
mechanical means e.g. ventilation of spaces with air to dilute gas, or
extraction of gas from the development site using fans or blowers. |
¡§Semi-active
control¡¨ |
Use of wind driven cowls
and other devices which assist in the ventilation of gas but do not rely on
electrically powered fans. |
Passive
control |
Provision of barriers to
the movement of gas e.g. membranes in floors or walls, or in trenches,
coupled with high permeability vents such as no-fines gravel in trenches or
voids/permeable layers below structures. |
Detection
systems |
Electronic systems based
upon, for example, catalytic oxidation or infra-red measurement principles,
which can detect low concentrations of gas in the atmosphere and can be
linked to alarms and/or telemetry systems. |
n Hong Kong Geological
Survey Map (HGM20 series scale 1:20,000) (Edition II ¡V 2008);
n Approved EIA
report of ¡§Shuen Wan Golf Course¡¨ (AEIAR-221/2019);
n Approved EIA
report of ¡§Tai Po Sewage Treatment Works Stage V¡¨ (AEIAR-081/2004);
n Shuen Wan
Landfill
Restoration ¡V Annual Environmental Audit Report (2016-2020)
n An
approximately 800mm ¡V 850mm thick soil layer of general cover, hydroseeded to
act as the growing medium;
n A geocomposite
drainage layer consists of filtration geotextile, high density polyethylene
(HDPE) geonet, very flexible polyethylene (VFPE) geomembrane and cushion
geotextile; and
n A 500mm think
final intermediate soil cover.
Table 9.5 Summary
of LFG monitoring data during 2016 to 2020
Monitoring Year |
CH4 (% v/v) |
CO2 (% v/v) |
||
Range |
Average |
Range |
Average |
|
Multiple Level Gas Monitoring Probes (GMPs) |
||||
2016 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 3.1 |
0.23 |
2017 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 3.7 |
0.13 |
2018 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 2.3 |
0.21 |
2019 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 2.6 |
0.14 |
2020 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V1.7 |
0.17 |
Single Level Gas Monitoring Probes (P-series) |
||||
2016 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 6.9 |
0.22 |
2017 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 6.3 |
0.27 |
2018 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 10.4 |
0.27 |
2019 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V 2.9 |
0.14 |
2020 |
0.0 ¡V 0.0 |
0.0 |
0.0
¡V5.1 |
0.22 |
Standard Compliance Level |
1.0%
v/v (i.e. 1.0% v/v above natural background) |
8.6% v/v (i.e. 1.5% v/v above
natural background) |
||
Level Indicating Significant Migration |
5.0% v/v (i.e. 5.0% v/v above natural background) |
12.1% v/v (5.0% v/v above natural background) |
Note: According
to Annual Environmental Audit Report for Shuen Wan Restored Landfill, the
natural background levels for methane and carbon dioxide are 0.0% v/v and 7.1%
v/v respectively.
Table 9.6 Summary
of Surface Gas Emissions during 2016 to 2020
Monitoring Year |
CH4 (ppm) |
2016 |
6.4 ¡V 9.8 |
2017 |
7.1 ¡V 9.4 |
2018 |
7.0 ¡V 8.6 |
2019 |
7.0 ¡V 8.5 |
2020 |
7.0 ¡V 9.3 |
Action Limit |
1,000
ppm methane |
Target Limit |
1.0% v/v or 10,000 ppm methane |
n Construction and
operation of new treatment facilities, modification / demolition of existing
treatment facilities of TPSTW;
n Providing
effluent reuse facilities; and
n Providing
co-digestion facilities for imported sewage sludge and organic waste /
pre-treated food waste
n Proposed
Buildings (e.g. Administration / Maintenance Building and Electrical Room)
n Proposed Biogas
Recovery and Storage Facilities
n Proposed Sewage
Treatment Facilities
n Proposed
Co-digestion and Sludge Related Facilities
n Proposed
Reclaimed Water Plant
Table 9.7 Summary
of Qualitative Source-Pathway-Target Analysis
Source |
Pathway |
Target |
Risk |
Shuen Wan Restored Landfill (Medium) |
Natural pathways (Very Short/Direct) |
Construction of upgrading
TPSTW (Medium sensitivity) |
Medium |
Operation of upgrading
TPSTW (Medium sensitivity) |
Medium |
||
Man-made pathways (Long/Indirect) |
Construction of upgrading
TPSTW (Medium sensitivity) |
Low |
|
Operation of upgrading
TPSTW (Medium sensitivity) |
Low |
n All personnel who work on site
and all visitors to the site should be made aware of the possibility of
ignition of gas in the vicinity of excavations. Safety notices should be posted
warning of the potential hazards.
n A Safety Officer, trained in
the use of gas detection equipment and landfill gas-related hazards, should be
present on site during the groundworks trenching and construction stages.
n All staff working in the
Consultation Zone should receive appropriate training on working in areas
susceptible to landfill gas, fire and explosion hazards.
n An excavation procedure or code
of practice to minimize landfill gas related risk should be devised and carried
out.
n No worker
should be allowed to work alone at any time in or near to any excavation areas
within the Consultation Zone. At least one other worker should be available to
assist with a rescue if needed.
n Smoking, naked flames and all other sources of ignition should be
prohibited within 15m of any excavation or ground-level confined space. 'No
smoking' and 'No naked flame' notices should be posted prominently on the
construction site, especially in excavation or trenches.
n Welding, flame-cutting or other hot works should be confined to
open areas at least 15m from any
trench or excavation.
n Welding, flame-cutting or other hot works may only be carried out
in trenches or confined spaces when controlled by a 'permit to work' procedure,
properly authorized by the Safety Officer.
n The permit to
work procedure should set down clearly the requirements for continuous
monitoring for methane, carbon dioxide and oxygen throughout the period during
which the hot works are in progress. The procedure should also
require the presence of an appropriately qualified person, in attendance
outside the 'confined area', who shall be responsible for reviewing the gas
measurements as they are made, and who shall have executive responsibility for
suspending the work in the event of unacceptable or hazardous conditions. Only
those workers who are appropriately trained and fully aware of the potentially
hazardous conditions which may arise should be permitted to carry out hot works
in confined areas.
n Ground level
construction plant used within in Consultation Zone should be fitted with vertical
exhausts at least 0.6m above ground level and with spark arrestors.
n Any electrical
equipment, such as motors and extension cords, should be intrinsically safe.
n During piping
assembly or conduiting construction within Consultation Zone, all valves/seals
should be closed immediately after installation. As construction progresses,
all valves/seals should be closed as installed to prevent the migration of
gases through the pipeline/conduit. All piping/conduiting should
be capped at the end of each working day.
n Mobile offices,
equipment stores, mess rooms etc. should be located on an area which has been
proven to be gas free (by survey with portable gas detectors) and ongoing
monitoring / measurement should be carried out, preferably at least at the
beginning of every working day, to ensure that these areas remain gas free.
Alternatively, such buildings should be raised clear of the ground. If
buildings are raised clear of the
ground, a minimum, clear separation distance (as measured from the highest
point on the ground surface to the underside of the lowest floor joist) should
be 500mm.
n Adequate fire
extinguishing equipment, fire-resistant clothing and breathing apparatus sets
should be made available on site.
Fire drills should be organized at
not less than six monthly intervals.
n Periodically
during ground-works construction, the works area should be monitored for
methane, carbon dioxide and oxygen using appropriately calibrated portable gas
detection equipment.
n The monitoring
frequency and areas to be monitored should be set down prior to commencement of
ground-works either by the Safety Officer or by an appropriately qualified person.
n Routine
monitoring should be carried out in all excavations, manholes and chambers and
any other confined spaces that may have been created by, for example, the temporary storage of building materials on
the site surface.
n All
measurements in excavations should be made with the monitoring tube located not
more than 10mm from the exposed ground surface.
n For excavations
deeper than 1m, measurements should be made:
¡P
at the ground surface before excavation commences;
¡P
immediately before any worker enters the
excavation;
¡P
at the beginning of each working day for the entire
period the excavation remains open; and
¡P
periodically through the working day whilst workers
are in the excavation.
n For excavations
between 300mm and 1m deep, measurements should be made:
¡P
directly after the excavation has been
completed; and
¡P
periodically whilst the excavation remains open.
n For excavations
less than 300mm deep, monitoring may be omitted, at the discretion of the
Safety Officer or other appropriately qualified person.
n Depending on
the results of the measurements, actions required will vary and should be set
down by the Safety Officer or other appropriately qualified person. As a
minimum these shall encompass those actions specified in Table 9.8.
Table 9.8 Actions
in the Event of Gas Being Detected in Excavations
Parameter |
Measurement |
Action |
O2 |
< 19% |
¡P
ventilate trench/void to restore O2 to
>19% |
< 18% |
¡P
stop works ¡P
evacuate personnel/prohibit entry ¡P
increase ventilation to restore O2 to >19% |
|
CH4 |
> 10% LEL |
¡P
prohibit hot works ¡P
ventilate to restore CH4 to <10% LEL |
>20% LEL |
¡P
stop works ¡P
evacuate personnel/prohibit entry ¡P
increase ventilation to restore CH4 to
<10% LEL |
|
CO2 |
> 0.5% |
¡P
ventilate to restore CO2 to <0.5% |
> 1.5% |
¡P
stop works ¡P
evacuate personnel/prohibit entry ¡P
increase ventilation to restore CO2 to
<0.5% |
n The hazards from landfill gas during
the construction phase shall be minimized by precautionary measures recommended
in the Guidance Note.
n In any emergency situation, the
Safety Officer or other appropriately qualified person, shall have the necessary authority and shall
ensure that the confined space is evacuated and the necessary works implemented
for reducing the concentrations of gas. The following organizations should also
be contacted as appropriate:
¡P
Hong Kong Police Force (HKPF);
¡P
Fire Services Department (FSD); and
¡P
Landfill Operator
¡P
Descriptions of the proposed LFG hazard
precautionary and protection measures of the Project.
¡P
Guidelines for regular inspection of the
proposed LFG hazard precautionary and protection measures and routine integrity
checking and maintenance of the proposed building protection measures / devices
/ facilities.
¡P
Emergency responses such as evacuation
procedures and rectification procedures to reduce LFG concentration (e.g. by
increasing ventilation rate) and, if required, restore normal operation of the
LFG hazard precautionary and protection measures / facilities or liaison with
the restored landfill operator.
¡P
Roles and responsibilities for implementing
the proposed LFG precautionary and protection measures and contingency plan.
¡P
The contacts of Government Departments (HKPF
and FSD) to be notified and stakeholders (i.e. suitable personnel of
contractor/DSD for implementing the contingency plan and landfill operator) in
case of emergency situations.