2............. Project
description
2.1.......... Purposes
and Objectives of the Project
2.2.......... Project
Site Location and Site History
2.3.......... Proposed
Project Design
2.4.......... The
Need of the Project
2.5.......... Consideration
of Different Development Options
2.6.......... Consideration
of Alternative Construction Methods and Sequences of Works
2.7.......... Construction Programme
2.8.......... Concurrent
Projects
2.9.......... Public
Consultation
LIST
OF TABLES
Table 2.1 Comparison of Alternative Extent of DWFI System
Table 2.2 Potential Interfacing Projects
Table 2.3 Summary of Public Concerns and Follow-up Actions
LIST
OF FIGURES
Figure 2.1 Project Location Plan
Figure 2.2 General Layout Plan of Revitalisation of Fo Tan Nullah
Figure 2.3 Interactions with Other Projects
LIST OF
APPENDICES
Appendix 2.1 Master Layout Plan of Revitalisation of Fo Tan Nullah
Appendix 2.2 Tentative Construction Programme
Appendix 2.3 Confirmation of No Change in EIA Study Brief
(a) beautification of the existing nullah (approximately 1.7 km long and 10 m to 35 m wide) by re-surfacing, greening and modification of channel bed;
(b) provision of Dry Weather Flow Interceptor (DWFI) system;
(c) provision of features for ecological enhancement and installation of underground water storage tank [approximately 10m (W) x 30m (L) x 2.5m (D)] under the existing Kwei Tei Street Garden equipped with two submersible water pumps installed under the nullah bed at mid-stream of FTN and underground water pipes for associated water retention and supplement;
(d) construction of viewing decks and revamp of existing footbridges/bridges;
(e) revamp/provision of footpaths, railings, amenity areas and pavilions along the nullah banks;
(f) improvement/modification of existing planters; and
(g) associated works including landscaping, utility works, etc.
Channel Bed Modification
·
Excavation works; and
·
Re-surfacing
and greening along the nullah.
Improvement of Existing Walkways
·
Construction
of viewing deck / pavilion, renovation of existing footbridges.
Construction of Dry Weather Flow
Interceptor System
·
Connection
works of DWFI system to the existing sewerage system; and
·
Construction
of DWFI channel along the nullah.
Landscaping and Miscellaneous
·
Landscaping
/ greening along nullah bank; and
·
Utility
works.
Desilting at Downstream Tidal Zone
·
Desilting
at downstream tidal zone.
Construction of Underground Water Storage Tank and
Mid-stream Submersible Water Pumps for Ecological Enhancement Associated Water
Retention and Supplement
Underground
Water Storage Tank
· Excavation and lateral support (ELS);
· Foundation works;
· Structural and electrical and mechanical (E&M) installation works for water storage tank; and
· Associated pipeworks.
Mid-Stream Submersible Water Pumps
·
Construction
of pumping facilities (mid-stream submersible water pumps and water pipes along
the nullah) for water supplement.
Water Quality Improvement and Water Friendliness
Greening Enhancement
Ecological Enhancement
· Reprofiling of the low flow channel (from the section south to Kwei Tei Street down to the section with tidal influence near Fo Tan MTR Station) and construction of in-stream weirs to create a meandering alignment along the nullah to mimic natural stream pattern where practicable, providing a series of microhabitats for wildlife in surrounding areas;
· Provision of DWFI system to improve water quality and to support ecological enhancement;
· Introduction of general constructed wetland systems (artificial wetland created to mimic processes in natural wetland ecosystems involving vegetation, soils, and their associated microbes through engineering design) to the channel bed, which can serve as greening and ecological enhancement measures whilst achieving some degree of pollution removal (Section 2.5.1.4 refers);
· Greening along the channel bed and banksides, such as provision of emergent wetland planting (e.g. reed and other aquatic herbs), mangroves, climbing plants, tree and / or grasscrete to the banksides;
· Incorporation of planting designed to attract wildlife species (e.g. birds and butterflies) during revamp of public open space along FTN;
· Provision of nest boxes / hunting perch for wildlife (e.g. birds) along FTN;
· Installation of oyster baskets along the bottom of channel bank at the small portion of Shing Mun Main Channel within the Project site to provide habitats for intertidal species and ardeids; and
· Modification of channel bank at downstream section of FTN to enhance foraging habitats for waterbirds.
Extent of DWFI System
· Option 1 (No Interception) refers to the existing condition where all dry weather flows are discharged to the nullah directly without interception or treatment;
· Option 2 (Full Interception) refers to a full-scale DWFI system that intercepts the dry weather flows from all the drainage outlets identified with polluted discharges along the nullah within Sections 2 (part) to 5 of FTN. Section 6 of FTN is connected to natural catchments whilst Section 1 is surrounded by private housing estates / institutional uses which have well-established sewerage and stormwater drainage systems that expedient connection/misconnection to Sections 1 or 6 of FTN from industrial area or significant polluted surface runoff due to the nature of the catchment area would be unlikely. Likewise, Sections 1 and 2 (part) of the nullah are also subject to tidal influence with the outlets being submerged mostly in water that the discharges cannot be intercepted by the instream DWFI system. DWFI system is hence not considered for Sections 1, 2 (part) and 6 of the nullah.
· Option 3 (Partial Interception) refers to a more site-specific design which takes into account of the water quality condition of each outlet to provide DWFI system only to some drainage outlets with highly polluted discharges and to construct specific treatment wetlands at remaining outlets for in-situ polishing of the less polluted discharges (e.g. outlets connected to the urban roadside drainage system). The water treatment efficiency of the treatment wetlands would be highly dependent on their sizes and retention time of the influent (which is associated with steadiness of water flow at the nullah). Similar to Option 2, DWFI system would be provided along the nullah within Sections 2 (part) to 5 and not be required for outlets in Sections 1, 2 (part) and 6 of the nullah.
Table 2.1 Comparison of Alternative Extent of DWFI
System
Design
Considered |
Environmental Benefits |
Environmental
Disbenefits |
Implications on Revitalisation Design |
Option 1 – No Interception |
· No diversion of additional pollutant
loads to the existing sewerage system |
·
Existing water quality and odour issues due to
polluted discharges from drainage outlets along FTN would remain unresolved |
·
Poor water quality of FTN due to polluted discharges
is undesirable for ecological enhancement, promotion of water friendliness or
improvement of community environment and hence not considered |
Option 2 – Full Interception (Preferred) |
· Improvement
to existing water quality and odour issues by intercepting all dry weather
flows from the drainage outlets identified with polluted discharges along the
nullah within Sections 2 (part) to 5 of FTN |
·
Increase comparatively more pollutant loads to the
existing sewerage system |
·
Polluted discharges would be fully eliminated to improve water
quality of FTN through DWFI system. · Baseflow
of nullah would be reduced and may not be able to support aquatic habitat / wetland creation for
greening and ecological enhancement. ·
Additional water retention and replenish facilities are required to provide sufficient
baseflow for in-stream ecological enhancement |
Option 3 – Partial Interception by
intercepting partial polluted dry weather flows |
·
Improvement to water quality and odour issue by
intercepting partial polluted dry weather flows from some of drainage outlets
identified with highly polluted
discharges along the nullah within Sections 2 (part) to 5 of FTN, but less effective
as compared to Option 2 – Full Interception. |
·
Increase comparatively less pollutant loads to the
existing sewerage system |
·
Polluted discharges would be partially eliminated by DWFI system. While the use of
specific treatment wetlands at the remaining outlets without connecting to
DWFI system could polish the non-intercepted polluted discharges, the
treatment effectiveness would be limited due to the site constraints to provide
sufficient treatment wetlands and the short retention time of influent resulting
from the relatively steep gradient with high flow velocity of FTN. · Baseflow
of FTN would be reduced, while to a smaller extent than Option 2 – Full
Interception, still may not be able to support aquatic habitat / wetland creation. ·
Additional water retention and replenish method is
required to provide sufficient baseflow for in-stream ecological enhancement |
Water Retention and
Replenish Methods and Ecological Enhancement Designs
Dry Weather Flow Interceptor System
Underground Water Storage Tank
Table 2.2 Potential Interfacing Projects
Project |
Tentative Construction Programme |
Potential Cumulative Impacts |
||
Drainage Improvement Works in Sha Tin and Sai Kung |
2023 - 2031 |
Drainage improvement works are proposed in various locations in Sha Tin and Sai Kung under Drainage Improvement Works in Sha Tin and Sai Kung. Based on the latest available
information, the flood walls proposed along Shing Mun River Channel under
this project would fall partly (approximately 100 m long) within the 500m
assessment area of this EIA Study, while no detailed construction programme
of the concerned flood walls was available at time of the preparation of this
EIA Report. During the detailed design
stage, the contractor of this Project should be requested to closely liaise
the contractors of this potential concurrent DSD project in planning the
interfacing works properly to minimise the potential cumulative impacts by
avoiding/minimising repeated and concurrent construction works. |
||
Relocation of Sha Tin Sewage Treatment Works to Caverns – Upstream Sewerage and Pumping Stations |
2020 - 2024 |
Rising main for connecting Sha Tin Main Sewage Pumping Station to the planned Intermediate Sewage Pumping Station along Shing Mun River proposed under the Relocation of Sha Tin Sewage Treatment Works to Caverns – Upstream Sewerage and Pumping Stations would run across and overlap partly with FTN. Based on the latest available information, the planned sewerage works would be scheduled to commence in year 2020 for completion in year 2024 tentatively, but no detailed construction programme of the concerned section of sewerage works overlapping with the Project was available at time of the preparation of this EIA Report. During the detailed design stage, the contractor of this Project should be requested to closely liaise the contractors of this potential concurrent DSD project in planning the interfacing works properly to minimise the potential cumulative impacts by avoiding/minimising repeated and concurrent construction works. |
||
Sewerage Works near Kwei Tei Street |
2020 – 2022 |
The footprint of planned sewerage works near Kwei Tei Street overlaps partly with the Project. However, since it is expected to be completed prior to commencement of the Project construction, no cumulative construction impacts would be anticipated. Cumulative sewerage impact from the proposed DWFI system of the Project and this concurrent project has been taken into account in this EIA Report. |
||
Widening of Tai Po Road (Sha Tin Section) |
Q3 2018 – 2023 |
Widening of Tai Po Road (Sha Tin Section) falls within the 500m assessment area of this EIA. It is expected to be completed prior to commencement of construction of this Project that no cumulative environmental impacts would be anticipated. |
||
Revitalisation of Tai Wai Nullah |
Q1 2024 – Q4 2029 |
TWN is situated at approximate 2.7 km from FTN. Given the large separation distance between the two concurrent revitalisation works of FTN and TWN, insignificant cumulative construction phase air quality and noise impacts would be expected. Potential cumulative water quality and ecological impacts to downstream areas in Shing Mun River Channel and Tolo Harbour during construction phase have been taken into account. Both the Project and Revitalisation of TWN would improve water quality and hygiene of the two nullahs that no unacceptable cumulative operational phase impact would be anticipated. The cumulative sewerage impact from the proposed DWFI system of the Project and Revitalisation of TWN have been taken into account. |
||
Revised Trunk Road T4 in Sha Tin |
Q4 2023 – Q3 2028 |
While Revised Trunk Road T4 is situated at over 2km from this Project, it involves construction of bridge piers within Shing Mun River. Given the large separation distance between the two concurrent projects, insignificant cumulative construction phase air quality and noise impacts would be expected. Based on the approved EIA of Revised Trunk Road T4 in Sha Tin (AEIAR-231/2021), the bridge piers construction is tentatively scheduled from November 2023 to September 2025. Potential cumulative water quality and ecological impacts to downstream areas in Shing Mun River Channel and Tolo Harbour during construction phase have been taken into account. |
||
Redevelopment of Housing Authority’s (HA) Sui Fai Factory Estate for Residential Use |
2023 – 2031 |
The proposed redevelopment site of HA’s Sui Fai Factory Estate falls within the 500m assessment area of this EIA. Based on the latest available information, the site would be redeveloped for residential use and is tentatively planned to be occupied in 2031. No detailed construction programme of the redevelopment of HA’s Sui Fai Factory Estate was available at time of the preparation of this EIA Report. Nonetheless, relevant cumulative environmental impacts, such as noise and water quality have been taken into account. |
||
New Facilities Building of the Hong Kong Sports Institute (HKSI) |
2021 – Mid-2024 |
The New Facilities Building of the Hong Kong HKSI is situated within the 500m assessment area of this EIA adjacent to the downstream section of FTN. Based on the latest available information, the planned development of new facilities building of the HKSI was targeted for completion in mid-2024 tentatively, but no detailed construction programme of the development was available at time of the preparation of this EIA Report. Nonetheless, relevant cumulative environmental impacts, such as air quality and water quality have been taken into account. During the detailed design stage, the contractor of this Project should be requested to closely liaise the contractors of this potential concurrent project in planning the interfacing works properly to minimise the potential cumulative impacts by avoiding/minimising repeated and concurrent construction works. |
· Meeting with Sha Tin District Council in June and July 2018, March 2021
· Meeting with Sha Tin District Council Health and Environmental Committee in March 2019
· Meeting with Green Groups in July 2020
· A series of public engagement exercises (e.g. interviews, workshops and surveys) through the use of Design Thinking Approach between December 2020 to August 2021.
Table 2.3 Summary of Public Concerns and
Follow-up Actions
Key Concerns |
Follow-up Actions |
Avoidance and minimisation of impacts to existing natural watercourses / habitats and associated wildlife |
All identified natural watercourse in vicinity of the Project have been avoided under the revitalisation design that no works would be conducted within any natural watercourse. There are existing mature trees along FTN on pedestrian road within the Project site. Although these tree species are not of conservation importance, the tree specimens are mature with good foliage and tree crown that can potentially provide habitat for fauna species. These mature trees will therefore be retained under the revitalisation design. |
Water quality issues and odour nuisance |
DWFI system are proposed to intercept polluted dry weather flows that are discharged from drainage outlets along both sides of FTN. After implementation of the system, water quality and odour along the nullah would be improved. |
Promotion of water friendliness |
FTN has a narrow and steep channel. Water level would likely rise faster during a heavy rainstorm. The relatively fast rising water level and high flow velocity would pose a greater danger to pedestrians in the nullah. In addition, emergency evacuation would be challenging given the long and narrow setting of the nullah and the lack of adequate access and egress arrangement due to limited land availability. FTN is therefore not suitable to be opened up for public access. However, with the improved water quality, there is an opportunity to enhance user experience along FTN and hence promoting water friendliness culture. Considering the public desire for more public open spaces, revitalisation features including installation of viewing decks along the nullah, as well as improvement and landscaping works to existing walkways and public open spaces to promote water friendliness culture / activities. |
Insufficient baseflow to support proposed ecological enhancement |
As detailed in Sections 2.5.1.6 to Section_2.5.1.8, water retention and replenish methods including construction of in-stream fixed weirs and underground water storage tank, would be incorporated in the revitalisation design in order to maintain sufficient baseflow to support a healthy aquatic habitat and in-channel ecological enhancement. Other ecological enhancement features along bankside and public open space along FTN (e.g. thematic greening along banksides and public open space, provision of nest boxes / hunting perch for wildlife) will also be installed to promote ecological connectivity. |
Improvement on walkability along the nullah and enhancement of public open spaces |
Existing footpaths along both sides of the nullah would be revamped to provide a more comfortable urban walking environment, e.g. partial decking and widening of footpath to create a more spacious walking space; use of planting (e.g. shrubs and/or small trees) as a soft barrier between the footpath and busy carriageway to enhance the walkability of the walkway and to provide more greening and promote environmental friendliness; installation of covered walkways / shelters along footpaths to provide an open space for community activities along the waterscape. In order to promote water friendliness culture and allow public to engage with and enjoy the revitalised waterscape, viewing decks would be constructed along the nullah, the current bankside planters would also be modified to minimise blockage of pedestrians from the nullah. |