TABLE OF CONTENTS

3                  Air Quality Impact. 3-1

3.1              Introduction. 3-1

3.2              Environmental Legislations, Standards and Guidelines. 3-1

3.3              Description of Environment 3-2

3.4              Identification of Air Sensitive Receivers. 3-4

3.5              Identification of Environmental Impacts. 3-5

3.6              Prediction and Evaluation of Environmental Impacts. 3-6

3.7              Mitigation of Adverse Environmental Impacts. 3-10

3.8              Evaluation of Residual Impacts. 3-11

3.9              Environmental Monitoring and Audit 3-11

3.10            Conclusion. 3-11

 

LIST OF TABLES

Table 3.1                  New Hong Kong Air Quality Objectives

Table 3.2                  Average Concentrations of Pollutants in the Recent Five Years (Year 2016 – 2020) at Sha Tin EPD Air Quality Monitoring Station

Table 3.3                  Background Air Pollutants in Year 2025 Extracted from the PATH Model (PATH v2.1)

Table 3.4                  Representative Air Sensitive Receivers

 

LIST OF FIGURE

Figure 3.1              Locations of Air Sensitive Receivers

 

 


3                    Air Quality Impact

3.1                Introduction

3.1.1.1         This section presents the assessment on potential air quality impacts arising from construction and operation of the Project, which has been conducted in accordance with the criteria and guidelines as stated in Section 1 of Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the requirements given in Clause 3.4.4 and Appendix B of the EIA Study Brief (No. ESB-319/2019). 

 

3.2                Environmental Legislations, Standards and Guidelines

3.2.1.1         The relevant legislations, standards and guidelines applicable to the present study for the assessment of air quality impacts include:

·         Air Pollution Control Ordinance (APCO) (Cap. 311) - this provides the power for controlling air pollutants from a variety of stationary and mobile sources and encompasses a number of Air Quality Objectives (AQOs);

·         Air Pollution Control (Construction Dust) Regulation;

·         Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation;

·         Air Pollution Control (Fuel Restriction) Regulation; and

·         Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), EIAO-TM, Annex 4 and Annex 12.

Air Quality Objectives

3.2.1.2         The new set of AQOs which came into effect on 1 January 2022, is tabulated in Table 3.1.

Table 3.1     New Hong Kong Air Quality Objectives

Pollutant

Averaging Time

Concentration Limit, µg/m3 [1]

No. of Exceedances Allowed per Year

Fine Suspended Particulates
(PM2.5 / FSP)
[3]

24-hour

50

18 [5]

Annual [2]

25

Not applicable

Respirable Suspended Particulates (PM10 / RSP) [4]

24-hour

100

9

Annual [2]

50

Not applicable

Sulphur Dioxide (SO2)

10-minute

500

3

24-hour

50

3

Nitrogen Dioxide (NO2)

1-hour

200

18

Annual [2]

40

Not applicable

Photochemical Oxidants

[as Ozone (O3)]

8-hour

160

9

Carbon Monoxide (CO)

1-hour

30,000

0

8-hour

10,000

0

Lead (Pb)

Annual [2]

0.5

Not applicable

Notes:

[1]    All measurements of the concentration of gaseous air pollutants, i.e., sulphur dioxide, nitrogen dioxide, ozone and carbon monoxide, are to be adjusted to a reference temperature of 293 Kelvin and a reference pressure of 101.325 kilopascal.

[2]    Arithmetic mean.

[3]    “Fine suspended particulates” means suspended particles in air with a nominal aerodynamic diameter of 2.5 µm or less.

[4]    “Respirable suspended particulates” means suspended particles in air with a nominal aerodynamic diameter of 10 µm or less.

[5]    Under the new AQOs, the number of exceedances allowed per year for daily FSP is 35 times.  However, for new government projects, the number of exceedances allowed per year for daily FSP is 18 times only.

 

Air Pollution Control (Construction Dust) Regulation

3.2.1.3         With reference to the Air Pollution Control (Construction Dust) Regulation, it specifies processes that require special dust control.  The Contractors are required to inform the EPD and adopt proper dust suppression measures while carrying out “Notifiable Works” (which requires prior notification by the Regulation) and “Regulatory Works” to meet the requirements as defined under the Regulation.

Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation

3.2.1.4         The Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation comes into operation on 1 June 2015.  Under the Regulation, non-road mobile machinery (NRMMs), except those exempted, are required to comply with the prescribed emission standards.  From 1 September 2015, all regulated machines sold or leased for use in Hong Kong must be approved or exempted with a proper label in a prescribed format issued by EPD.  Starting from 1 December 2015, only approved or exempted NRMMs with a proper label are allowed to be used in specified activities and locations including construction sites.  The Contractor is required to ensure the adopted machines or non-road vehicle under the Project could meet the prescribed emission standards and requirement.

Air Pollution Control (Fuel Restriction) Regulation

3.2.1.5         Air Pollution Control (Fuel Restriction) Regulations should also be complied with an aim to prohibit the use of high sulphur content solid and liquid fuel for commercial and industrial appliances.  The Project site is located within the “Sha Tin Fuel Restriction Area” under the Air Pollution Control (Fuel Restriction) Regulations.  Except for construction site or during emergency, only gaseous fuel is allowed to be used in the Sha Tin Fuel Restriction Area.  For any fuel-using equipment that is used or operated in construction site or during emergency in Sha Tin Fuel Restriction Area, Ultra Low Sulphur Diesel (ULSD) is practically the liquid fuel to be used. 

EIAO-TM

3.2.1.6         Annex 4 of EIAO-TM stipulates that hourly Total Suspended Particulate (TSP) level should not exceed 500µg/m³ measured at 298 K and 101.325 kPa (one atmosphere) for the construction dust impact assessment.  It also stipulates that the odour level at air sensitive receiver should meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment.

3.2.1.7           Guidelines for conducting air quality assessment are stipulated in Annex 12 of EIAO-TM, including the determination of air sensitive receivers (ASRs), the assessment methodology, baseline study and impact prediction and assessment.

 

3.3                Description of Environment

3.3.1.1         The Project is to revitalise the existing Fo Tan Nullah (FTN) with an aim to enhance the ecological value of the nullah, provide a greener environment, promote water friendliness and improve the community environment.  The potential construction phase air quality impacts from the Project would likely be dust impacts, gaseous emissions from Powered Mechanical Equipment (PMEs), and potential odour emission from excavated / desilted materials during excavation works at nullah bed /desilting works at downstream tidal zone; while the potential operational phase air quality impacts from the Project would likely be potential odour emission from desilted materials during maintenance desilting works.

3.3.1.2         The Project site covers the existing FTN, which is approximately 1.7 kilometres (km) long and 10 to 35 metres (m) wide, located at the centre of Fo Tan District and is mainly surrounded by industrial buildings on its upper portion and residential developments on its lower portion, as illustrated in Figure 3.1.

3.3.1.3         The dominant existing air emission source within 500m assessment area from the Project area is vehicular emission from Fo Tan Road, Tai Po Road (Shatin) and Sha Tin Road.   Within the 500m assessment area, there was no chimney emission sources identified except that one specified process (SP) under the APCO, Electricity Works (i.e. an Emergency Generator) located at the PCCW Fo Tan Data Centre, was identified at the time of the assessment.  As its emission is controlled under the SP licence and the generator is for emergency use only, no adverse air quality impact arising from this SP is anticipated. 

3.3.1.4         The nearest EPD general air quality monitoring station to the Project area is situated at Sha Tin Government Secondary School.  The recent 5-year (between 2016 and 2020) concentrations of air pollutants measured at the monitoring station relevant to the Project, including Fine Suspended Particulates (FSP), Respirable Suspended Particulates (RSP), Sulphur Dioxide (SO2) and Nitrogen Dioxide (NO2), were extracted and are summarised in Table 3.2.  It is observed that the maximum 24-hour average FSP concentrations and the 10th highest 24-hour average FSP concentrations in the latest 5 years complied with the prevailing AQO.  For RSP, non-compliance of the maximum 24-hour average concentrations were noted in Year 2016 to Year 2018 but the 10th highest values in Years 2016 to 2020 all complied with the prevailing AQO.  Both annual average FSP and RSP concentrations, 10-minutes and 24-hour average SO2, hourly and annual average NO2 complied with prevailing AQOs.  In general, the results showed that there was a decreasing trend in the pollutants levels in the past 5 years.

Table 3.2     Average Concentrations of Pollutants in the Recent Five Years (Year 2016 – 2020) at Sha Tin EPD Air Quality Monitoring Station

Pollutant

Averaging Time

Prevailing

AQO [1]

Data Summary

Year [2]

2016

2017

2018

2019

2020

Fine Suspended Particulates (FSP)

24-hr

75 (9)

Max.

62

90

70

64

56

10th Max.

44

54

40

39

32

No. of Exceedance(s)

0

1

0

0

0

Annual

35

-

20

21

19

17

15

Respirable Suspended Particulates (RSP)

24-hr

100 (9)

Max.

102

103

102

97

71

10th Max.

66

72

65

60

54

No. of Exceedance(s)

2

1

1

0

0

Annual

50

-

29

31

32

28

25

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

83

73

80

35

36

4th Max.

67

53

76

27

31

24-hr

125 (3)

Max.

17

17

20

15

14

4th Max.

16

16

16

12

13

No. of Exceedance(s)

0

0

0

0

0

Nitrogen Dioxide (NO2)

1-hr

200 (18)

Max.

176

178

198

185

183

19th Max.

137

144

149

150

136

No. of Exceedance(s)

0

0

0

0

0

Annual

40

-

38

34

35

32

28

Notes:

[1]    Existing AQOs, which is put in force since 1 January 2014, are referenced to evaluate past air quality conditions.  Values in ( ) mean the number of exceedances allowed per year.

[2]    Bolded values mean exceedance of the AQOs.

[3]    All concentration units are in microgram per cubic metre (µg/m3).

 

3.3.1.5         Apart from the air quality monitoring data, EPD has released a set of background air quality levels extracted from “Pollutants in the Atmosphere and their Transport over Hong Kong” (PATH) model (PATH v2.1) in July 2021.  The PATH model Year 2025 data of the assessment area are summarised in Table 3.3 below.  The 19th highest 24-hour and annual average concentrations of FSP would comply with the new AQOs, and all other pollutants level would also comply with the new AQOs.

Table 3.3     Background Air Pollutants in Year 2025 Extracted from the PATH Model (PATH v2.1)

Pollutant

Averaging Time

AQO [1]

Data Summary

PATH-2020 Grid in Year 2025 [2][5]

41,42

41,43

42,41

42,42

42,43

43,41

43,42

Fine Suspended Particulates (FSP) [3]

24-hr

50 (18)

Max.

65

66

69

65

66

68

69

19th Max.

32

33

33

32

32

33

33

No. of Exceedance(s)

6

6

8

7

6

7

8

Annual

25

-

14

14

15

14

14

15

15

Respirable Suspended Particulates (RSP) [4]

24-hr

100 (9)

Max.

81

82

85

81

82

84

85

10th Max.

62

63

62

64

63

63

64

No. of Exceedance(s)

0

0

0

0

0

0

0

Annual

50

-

26

26

27

26

26

27

27

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

57

52

48

59

60

47

49

4th Max.

57

52

48

59

60

47

49

No. of Exceedance(s)

0

0

0

0

0

0

0

24-hr

50 (3)

Max.

15

15

14

15

14

14

14

4th Max.

10

10

10

10

10

10

10

No. of Exceedance(s)

0

0

0

0

0

0

0

Nitrogen Dioxide (NO2)

1-hr

200 (18)

Max

144

150

156

151

156

149

153

19th Max.

69

63

96

76

65

94

91

No. of Exceedance(s)

0

0

0

0

0

0

0

Annual

40

-

11

11

18

14

12

18

18

Notes:

[1]  New AQOs, which come into effect on 1 January 2022, are referenced to evaluate background air quality conditions.  Values in ( ) mean the number of exceedances allowed per year.

[2]  Bolded values mean exceedance of the AQOs.

[3]  Annual FSP concentration is adjusted by adding 3.5 µg/m3 with reference to Guidelines on Choice of Models and Model Parameters.

[4]  10th highest daily and annual RSP concentration is adjusted by adding 11.0 µg/m3 and 10.3 µg/m3 respectively with reference to “Guidelines on Choice of Models and Model Parameters”.

[5]  All concentration units are in microgram per cubic metre (µg/m3).

 

3.4                Identification of Air Sensitive Receivers

3.4.1.1         In accordance with Clause 3.4.4.2 of the EIA Study Brief, the assessment area is defined by a distance of 500m from the boundary of the Project area as illustrated in Figure 3.1.

3.4.1.2         For identification of the representative ASRs within the assessment area that would likely be affected by the potential impacts from the Project, a review has been conducted based on relevant available information including topographic maps, Outline Zoning Plans (OZPs) (such as the Draft Shatin OZP No. S/ST/35) and other published plans in the vicinity of the Project site.  The representative ASRs are identified and summarised in Table 3.4.

Table 3.4       Representative Air Sensitive Receivers

ASR

Description

Land Use

No. of Storeys

Approximate Horizontal Distance from the Nearest Site Boundary (m)

Existing Air Sensitive Receivers

A1

Kwai Tei New Village

Residential

3

38

A2

Kwai Tei Village

Residential

3

122

A3

Chun Yeung Estate

Residential

34-39

9

A4

Village House

Residential

1

27

A5a

Industrial Buildings in Fo Tan

Industrial

14

10

A5b

Industrial Buildings in Fo Tan

Industrial

15

6

A5c

Industrial Buildings in Fo Tan

Industrial

18

35

A6

The Grandville

Residential

22

217

A7

Pat Tsz Wo Village

Residential

3

230

A8

Wo Liu Hang

Residential

3-4

180

A9

Yuk Wo Court

Residential

47

37

A10

Tao Miao Institute

Educational Institution

4

20

A11

Fo Tan Village

Residential

1-3

5

A12

Sui Wo Court

Residential

36

167

A13

P.L.K. Siu Hon Sum Primary School

Educational Institution

6

194

A14

Fo Tan Railway House

Office

8

5

A15

The Palazzo

Residential

40-42

68

A16

Jockey Club TI-I College

Educational Institution

5-6

46

A17

Hong Kong Jockey Club Shatin Staff Quarters

Residential

20

75

A18

Hong Kong Sports Institute

Educational Institution

11 (the highest building)

20

A19

Hong Kong Institute of Vocational Education (Shatin)

Educational Institution

6

204

A20

Wo Che Estate

Residential

13-40

238

A21

Sha Tin Ambulance Depot/ New Territories Command Headquarters & Sha Tin Fire Station

Office

2

20

A22

City One Shatin

Residential

27-34

236

A23

Ravana Garden

Residential

27-30

252

A24

Leung Kui Kau Lutheran Primary School

Educational Institution

6

373

A25

Fo Tan Cooked Food Market (East)

Commercial

1

0

A26

Fo Tan Cooked Food Market (West)

Commercial

1

0

A27

Shan Mei Street Basketball Court

Recreational

-

3

A28

Shan Mei Street Playground

Recreational

-

5

Planned Air Sensitive Receivers

AP1

Planned Primary School at No. 1-11 Au Pui Wan Street, Fo Tan

Educational Institution

-

70

AP2

Planned Residential Developments at No. 1-11 Au Pui Wan Street, Fo Tan

Residential

39-41

18

 

3.5                Identification of Environmental Impacts

3.5.1            Construction Phase

3.5.1.1         The construction of the Project would commence in January 2024 and complete by November 2029.  Referring to the tentative construction programme in Appendix 2.2, the Project Site would be divided into six work sections for construction, Section 1 to Section 6.  The locations of the six work sections are indicated in Figure 3.1.  The main construction tasks of the Project include:

(a)   Desilting at downstream tidal zone for Work Section 1

(b)   Channel bed modification for Work Section 1 to 5

(c)   Improvement of existing walkways such as construction of viewing deck/pavilion, renovation of existing footbridges for Work Section 1 to 6

(d)   Construction of dry weather flow interceptor (DWFI) system along the nullah and associated connection works to existing sewerage system for Work Section 2 to 6

(e)   Landscape works along nullah bank and utility works for Work Section 1 to 6

(f)    Construction of underground water storage tank for Work Section 6

(g)   Construction of submersible water pumps and underground water pipes (mainly housed within the DWFI system) for ecological enhancement associated water retention and supplement for Work Section 3 to 6 (to be constructed alongside construction of DWFI system)

3.5.1.2         Except the construction of underground water storage tank, the construction works will be carried out section by section, from the downstream to upstream of each work section.  Desilting works at downstream tidal zone would be conducted at the commencement and prior to the completion of the construction works to remove the silting accumulated at the nullah.  Based on the preliminary engineering design, the maximum size of the active construction works area at any one time would not be longer than 100m along the nullah at each work area. 

3.5.1.3         Construction dust is the major concern during construction of the Project.  Fugitive dust generated from various construction activities, including excavation, backfilling, and wind erosion of the excavated areas and stockpiles, would be major dusty activities which would impose potential dust impact on the air sensitive receivers in the vicinity.

3.5.1.4         The operation of powered mechanical equipment (PMEs) within the construction area and the construction vehicles for the transportation of materials would contribute to the gaseous emissions to the surrounding air.

3.5.1.5         Potential odour emission may be generated during the desilting works at downstream tidal zone/excavation of nullah bed and the transfer and disposal of desilted/excavated materials.

3.5.2            Operational Phase

3.5.2.1         The purpose of the Project is to revitalise the existing concrete-lined FTN into a green open space to connect the community with nature.  The beautification and vegetating of the existing nullah would bring positive influence on the surrounding environment.  In view of the Project nature, adverse air quality impact due to the operation of the Project is not anticipated.  With the implementation of DWFI system under the Project, the polluted discharges from drainage outlets along the nullah would be intercepted and diverted to the existing sewerage system for conveying to Shatin Sewage Treatment Works for treatment.  It is expected that the odour nuisance of FTN would be alleviated due to the operation of the Project.

3.5.2.2         Similar to the existing practices by, regular maintenance works for the drainage and sewerage systems along FTN, including maintenance desilting at the nullah and minor maintenance to the DWFI system, would be carried out by the DSD to remove excessive silts, debris and obstruction to safeguard the hydraulic capacity of the nullah would be required.  Maintenance desilting of the nullah would be carried out on an annual basis during dry season (November to March) when the water flow is low, except during emergency situations where the accumulated silt would adversely affect the hydraulic capacity of the nullah or where flooding risk is imminent, or when complaints on environmental nuisance associated with the accumulated silt are received.  Minor maintenance to DWFI system would only be undertaken on an as-needed basis and frequent maintenance (i.e. monthly) would not be required.  The maintenance practices and frequency would be similar to the existing maintenance works undertaken by the DSD.  Minor odour impact from maintenance desilting works may arise, yet not concerning and would be well-controlled through good site practices. 

 

3.6                Prediction and Evaluation of Environmental Impacts

3.6.1            Construction Phase

Fugitive Dust

3.6.1.1         The Project will be constructed in sections by sections.  The construction works at the nullah will be divided into six sections and the construction activities will not be undertaken at the entire work site at the same time.  The construction tasks for each work section would be completed before commencement of the similar construction tasks at another work section.  As mentioned in Section 3.5.1.2, the maximum size of the active construction work area at any one time would not be longer than 100m along the nullah at each work area.  Hence, the active exposed work site would be limited.

3.6.1.2         Various construction activities, including excavation, backfilling, material handling and wind erosion of the excavated areas and stockpiles would be the main sources of fugitive dust.  The production of concrete would be conducted with the use of a concrete lorry mixer, therefore, adverse dust impact is not anticipated.

3.6.1.3         Referring to construction programme in Appendix 2.2, the excavation works for the nullah bed per work section and underground water storage tank under existing Kwei Tei Street Garden would be 1 month and not more than 4 months, respectively.  

3.6.1.4         The excavated materials would be well covered with impervious sheeting and then use for backfilling/re-surfacing along the nullah in the next three months.  According to the engineering design, the total volume of construction and demolition (C&D) materials to be excavated for the whole construction period is estimated to be about 44,400m3, with the majority of about 36,600m3 inert C&D materials to be reused on-site for backfilling, about 4,800m3 inert C&D materials to be delivered to public fill reception facility (PFRF) for beneficial reuse, and about 3,000m3 non-inert C&D materials to be disposed at strategic landfill.  The C&D materials for backfilling or off-site disposal would be temporarily stored on-site and would be well covered with impervious sheeting.  As the excavation works and backfilling along the nullah will be conducted section by sections, the volume of inert C&D materials temporary stored on-site is expected to be not more than 1,000m3 at any time.

3.6.1.5         Due to the small amount of C&D materials to be disposed off-site, the dust generated from construction vehicles for materials handling would generally be limited within the work areas.  In accordance with the preliminary engineering information, for the inert C&D materials, it is proposed to dispose at Tseung Kwan O Area 137 Fill Bank for beneficial reuse in other projects via Lung Cheung Road and Kwun Tong Road or other approved PFRF.  It is estimated that an average of about 1 truck trip per day would be required to dispose these materials off-site.  For non-inert C&D materials, it is planned to deliver to SENT landfill via Lung Cheung Road and Kwun Tong Road or other approved landfills.  It is estimated that an average of about 1 truck trip per day would be required.  Considering the limited number of dump trunk in operation together with tarpaulin covering of these dump trucks and washing the vehicle wheel and body before leaving the construction site, dust nuisance during transportation of the C&D materials would not be anticipated.  

3.6.1.6         For the proposed underground water storage tank in Work Section 6, it is within Kwei Tei Street Garden with works area of approximately 300m2 (10m x 30m).  In order to match the downstream invert level of the nullah, it will be installed at shallow depth with excavation depth of approximately 2.5 m. The foundation and excavation works for the proposed storage tank would be last for 9 months only.  The excavated materials for the tank would be about 750m3 while the total excavated materials from foundation works and construction of associated pipeworks would be about 55m3.  The representative ASRs nearest to the proposed storage tank are ASR A3 and A5a and the separation distances are about 34m and 37m, respectively.  As confirmed by the Engineers, the construction of the storage tank and other construction works in Work Section 6 would not be overlapped to avoid cumulative air quality impact on nearby ASRs.  Considering the limited works area, small amount of excavated materials from excavation works and the avoidance of cumulative impact from other construction works in Work Section 6 together with the implementation of typical dust suppression measures as mentioned in Section 3.7.1 to minimise dust generation, adverse dust impact from the construction of the proposed tank would not be anticipated.

3.6.1.7         Given that the construction works of the Project would be of small-scale and confined in a smaller work area, small influence zone would be expected.  With proper and effective implementation of good site practices and mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation, dust emission from the construction works would be well controlled and minimised.  No adverse construction dust impacts from the Project would therefore be anticipated.

Operation of PMEs

3.6.1.8         The fuel combustion from the use of PMEs during construction works could be a potential source of air pollutants such as PM, NO2, SO2 and CO.  To improve air quality, Air Pollution Control (Fuel Restriction) Regulation and Air Pollution control (Non-road Mobile Machinery) (Emission) Regulation are introduced to regulate SO2 emissions from commercial and industrial processes, and emissions from machines and non-road vehicles respectively.  In addition, all construction plants are required to use ultra-low-sulphur diesel (ULSD) (defined as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No. 19/2005 on Environmental Management on Construction Sites. 

3.6.1.9         The number and type of PMEs to be used on site for each main construction task under Work Sections 1 to 6 are presented in Appendix 4.6.  According to the preliminary engineering design, while there would be several sub-group construction works under each main construction task, the construction periods of these sub-group works would not be overlapped.  Therefore, the PMEs of each sub-group works/construction sequence would not be operated concurrently.  Based on the construction programme presented in Appendix 2.2 and the plant inventory attached in Appendix 4.6, there would be up to 4 concurrent construction tasks, namely “Construction of Viewing Deck / Pavillion, Renovation of Existing Footbridges” (Group 1B-1),  “Landscaping / Greening along Nullah Bank” (Group 1D-1) and “Utility Works” (Group 1D-2) and “Connection Work to the Existing Sewerage System” (Group 2C-1) within 500m assessment area and a total of 13 nos. NRMM in operation.  These 4 tasks would be carried out concurrently in July 2024 (limited for one month).  As the works are divided into small sections, the potential air quality impacts would be limited.  With proper and effective implementation of the good practices as stated in the regulations, no significant dust and gaseous emission impacts from the use of PME would be anticipated.

Odour

3.6.1.10      Desilting works at downstream tidal zone would tentatively be undertaken at the commencement and prior to the completion of the construction works respectively to remove the accumulated silting and debris at the nullah.  Each desilting works would take about two months to complete and about 2,000m3 of desilted materials would be produced.  Potential odour nuisance would be expected during desilting works.  However, the desilted materials will be contained in watertight container on-site immediately and be transported off-site by trucks for disposal of at strategic landfill within one day.  Therefore, the odour emissions are likely to be minimal and localised at a short duration.

3.6.1.11      Excavation of materials at the nullah bed at each work section will be carried out separately and the excavation on each work section would be last for one month.  Potential odour nuisance might be resulted from these construction activities and transportation of these materials for disposal.  However, the excavated materials would be well covered on-site with tarpaulin and located away from ASRs as far as possible and would be removed off-site as soon as possible within 24 hours.  No adverse odour impact would be anticipated with the implementation of mitigation measures as stipulated in Section 3.7.

3.6.1.12      The desilted materials and excavated materials from the nullah bed would be enclosed during trucking, therefore, very minor odour nuisance would be expected during transportation of these materials for disposal.  

Cumulative impacts from concurrent projects

3.6.1.13      As presented in Section 2.8, there are four concurrent projects which would potentially overlap with the construction of the Project is identified within the 500m assessment area, including (i) Drainage Improvement Works in Sha Tin and Sai Kung, (ii) Relocation of Sha Tin Sewage Treatment Works to caverns – Upstream Sewerage and Pumping Stations, (iii) Redevelopment of Housing Authority’s (HA) Sui Fai Factory Estate into for Residential Use, and (iv) New Facilities Building of the Hong Kong Sports Institute (HKSI).  Based on the construction programme of the Project, the cumulative impacts from these concurrent projects have been considered. 

3.6.1.14      The cumulative impacts associated with the project - “Drainage Improvement Works in Sha Tin and Sai Kung”, which is scheduled to construct in 2023-2031, is expected to be minor due to the long separation between the works boundaries of this current project and the Project (more than 280m).  In addition, consider that both projects would implement good site practices and dust suppression measures, no adverse cumulative dust impact would be anticipated.

3.6.1.15      For “Relocation of Sha Tin Sewage Treatment Works to caverns – Upstream Sewerage and Pumping Stations”, it is to construct a new 1,200m diameter pipe along Shing Mun River.  The construction period of this project is from end 2020 to 2024, which would be overlapped with the Project for less than one year.  Since this project would be at its final stage of construction during the overlapping period, extensive excavation works would not be anticipated.  In addition, both projects would implement good site practices and dust suppression measures, no adverse cumulative dust impact would be anticipated.

3.6.1.16      For the “Redevelopment of HA’s (HA) Sui Fai Factory Estate for Residential Use”, it is to demolish the existing Sui Fai Factory Estate and redevelop the site for residential use which is tentatively planned to be occupied in 2031 but no detailed construction programme of the redevelopment project is available at time of the preparation of this EIA Report that potential cumulative environmental impacts associated with this planned development have not been taken into account.  Nonetheless, consider the small and confined scale of the works area of the construction works of this Project, the construction dust impact is expected to be limited and well controlled with proper and effective implementation of good site practices and mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation.  During the detailed design stage, the contractor of this Project should be requested to closely liaise the contractors of this potential concurrent HA project in planning the interfacing works properly to minimise the potential cumulative impacts by avoiding/minimising repeated and concurrent heavy construction works. 

3.6.1.17      For “New Facilities Building of the HKSI”, it is to construct a new building within the HKSI facing the FTN and Shing Mun River.  The planned building is targeted for completion in mid-2024, which would be overlapped with the Project for less than one year.  Since the main works of this building development project would be at its final stage of construction during the overlapping period, excavation works would not be anticipated.  In addition, consider that both projects would implement good site practices and dust suppression measures, no adverse cumulative dust impact would be anticipated.

3.6.2            Operational Phase

3.6.2.1         As mentioned in Section 3.5.2.2, similar to the existing practices by the DSD, regular maintenance works for the drainage and sewerage systems along FTN, including maintenance desilting at the nullah and minor maintenance to the DWFI system, to remove excessive silts, debris and obstruction to safeguard the hydraulic capacity of the nullah would be required.  Maintenance desilting of the nullah should be carried out on an annual basis during dry season (November to March) when the water flow is low, except during emergency situations where the accumulated silt would adversely affect the hydraulic capacity of the nullah or where flooding risk is imminent, or when complaints on environmental nuisance associated with the accumulated silt are received.  Moderate siltation would generally be allowed to accumulate, and removal of excess silt would be carried out at locations where it would impede water flow.  Maintenance works would also be undertaken for the DWFI system on an as-needed basis and frequent maintenance (i.e. monthly) would not be required.  The maintenance practices and frequency would be similar to the existing maintenance works undertaken by the DSD.  Such small-scale maintenance would require only light mechanical equipment such as a small loader and/or a small crane truck.  Hand-held equipment would be used for vegetation removal.  Therefore, adverse impacts from dust and gaseous emission are not expected.

3.6.2.2         While the odour nuisance of FTN is anticipated to be alleviated with the implementation of DWFI system under the Project to intercept the polluted discharges from drainage outlets along the nullah, desilted materials from the maintenance/desilting works may be found to be odorous when exposed to air.  While minor odour impact may arise from maintenance/desilting works, the desilted materials will be properly covered with tarpaulin / contained in watertight container on-site immediately and be located as far away from the ASRs as possible and be transported off-site by trucks for disposal of at strategic landfill within one day.  As such, any odour impact during the maintenance would be temporary and confined to the areas of maintenance works that it would be well-controlled through good site practices described in Section 3.7.  No adverse odour impact would be anticipated. 

 

3.7                Mitigation of Environmental Impacts

3.7.1            Construction Phase

3.7.1.1         Sufficient dust suppression measures as stipulated under the Air Pollution Control (Construction Dust) Regulation (Cap. 311R) and good site practices such as enclosing stockpiles of sand with three-side enclosure, covering the dusty materials with clean impervious sheet, water spraying of all access roads and site areas, and good house-keeping of the site should be properly implemented in order to minimise the construction dust generation.  These measures include the followings:

a)    Use of regular watering, to reduce dust emissions from exposed site surfaces and unpaved roads particularly during dry weather;

b)    Use of frequent watering in particularly dusty construction areas close to ASRs;

c)     Use of frequent watering or water sprinklers for major haul roads, material stockpiling areas and other dusty activities within the construction site;

d)    Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering should be applied to aggregate fines;

e)    For the work sites close to the ASR with a separation distance less than 5m, provide hoardings of not less than 5m high from ground level along the site boundary; for the work sites close to the ASRs with a separation distance between 5m and 10 m, provide hoardings of not less than 3.5 m high from ground level along the site boundary; for other work sites, provide hoardings of not less than 2.4 m high from ground level along the site boundary except for site entrance or exit;

f)      Open temporary stockpiles should be avoided or covered.  Prevent placing dusty material storage plies near ASRs;

g)    Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations;

h)    Establishment and use of vehicle wheel and body washing facilities at the exit point of the site;

i)      Imposition of speed control for vehicles on unpaved site roads.  8 km/hr is the recommended limit;

j)      Routing of vehicles and positioning of construction plants should be at the maximum possible distance from ASRs;

k)     Avoid position of material stockpiling areas, major haul roads and dusty works within the construction site close to concerned ASRs;

l)      Avoid unnecessary exposed earth; and

m)   During or after the de-bagging process, the use of cement or dry pulverised fuel ash should be conducted in a totally enclosed system or facility and effective air pollution control measures should be placed at any exits or exhaust to avoid potential air quality influence.

3.7.1.2         Guidelines stipulated in EPD’s Recommended Pollution Control Clauses for Construction Contracts should be incorporated in the contract documents to abate dust impacts.  The clauses include:

·         The Contractor shall observe and comply with the APCO and its subsidiary regulations, particularly the Air Pollution Control (Construction Dust) Regulation.

·         The Contractor shall undertake at all times to prevent dust nuisance as a result of the construction activities.

·         The Contractor shall ensure that there will be adequate water supply / storage for dust suppression.

·         The Contractor shall devise and arrange methods of working and carrying out the works in such a manner so as to minimise dust impacts on the surrounding environment, and shall provide experienced personnel with suitable training to ensure that these methods are implemented.

·         Before the commencement of any work, the Contractor may be required to submit the methods of working, plant, equipment and air pollution control system to be used on the site for the Engineer inspection and approval.

3.7.1.3         In order to minimise the exhaust emissions from NRMMs during construction phase, the requirements as stipulated in the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation shall be followed.  The following measures are also recommended to be implemented:

·         Connect construction plant and equipment to mains electricity supply and avoid use of diesel generators and diesel-powered equipment;

·         Deploy electrified NRMMs as far as practicable; and

·         Use of exempted NRMMs not allowed.

3.7.1.4         The odorous materials from desilting works at downstream tidal zone should be contained in watertight container on-site and be transported off-site by trucks for disposal of at strategic landfill within one day.  The materials from excavation at nullah bed should be well covered on site with tarpaulin and placed as far away from the ASRs as possible.  These odorous materials should be removed off-site for disposal as soon as possible within 24 hours to avoid any odour nuisance.  During transportation, these odorous materials on the trucks should be properly covered by tarpaulin sheets to minimise the release of any potential odour.   

3.7.2            Operational Phase

3.7.2.1         The temporary stockpile of desilted materials from maintenance works should be located as far away from the ASRs as possible.  The desilted materials should be properly covered with tarpaulin / contained in watertight container on-site immediately and be removed off-site within 24 hours to avoid any odour nuisance arising.

 

3.8                Evaluation of Residual Impacts

3.8.1            Construction Phase

3.8.1.1         With proper and effective implementation of the good site practices and mitigation measures as stipulated in relevant Regulations and proposed in Section 3.7, no adverse residual air quality impact would be expected.

3.8.2            Operational Phase

3.8.2.1         The air quality impacts induced by the small-scale maintenance would be well controlled and no adverse residual impact is anticipated from the operation of the Project with the implementation of the recommended mitigation measures and good construction site practice.

 

3.9                Environmental Monitoring and Audit

3.9.1.1         No adverse air quality impact due to the construction of the Project would therefore be anticipated.  Nonetheless, dust monitoring is recommended during the construction of the underground water storage tank at Kwei Tei Street Playground to ascertain that there would be no adverse dust impacts at the nearby sensitive receivers.  Regular weekly site environmental audit is also recommended to ensure the implementation of recommended mitigation measures during construction phase.  Details of the monitoring and audit programme are contained in a stand-alone EM&A Manual.  No EM&A programme is required during operational phase.

 

3.10              Conclusion

3.10.1.1      The potential air quality impacts arising from the construction of the Project would be related to fugitive dust emissions from construction works and gaseous emissions from the use of PME, and odour nuisance from desilted / excavated materials generated during the desilting at downstream tidal zone / excavation works in the nullah.  In view of the small scale of the Project, the air quality impacts would be localised and minor, and would be well controlled through the implementation of good site practices and dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation as well as the proposed good site practices to minimise the exhaust emissions from NRMMs and odour nuisance from handling of desilting/excavated materials.  Dust monitoring for construction of the underground water storage tank at Kwei Tei Street Garden and regular weekly site audit are recommended to be carried out during construction phase in order to confirm that the mitigation measures are properly implemented and are working effectively.  No adverse air quality impact due to the construction of the Project would therefore be anticipated.

3.10.1.2      No adverse air quality impact due to the operation of the Project would be anticipated.  With the implementation of DWFI system under the Project to intercept and divert the polluted discharges from drainage outlets along the nullah to the existing sewerage system for treatment, the odour nuisance of FTN would be alleviated as a result of the operation of the Project.  Any odour emission generated from exposed desilted materials during the routine maintenance works would be temporary and confined to the areas of maintenance works that it would be well-controlled through good site practices.  No adverse air quality impact due to the operation of the Project would be anticipated.