1.2.......... Project
Scope and Location
1.3.......... Construction
Programme
1.4.......... Purpose
of the Manual
1.5.......... Project
Organisation
2.2.......... Mitigation
Measures
2.3.......... Construction
Phase Monitoring
2.4.......... Audit
Requirements
3.2.......... Mitigation
Measures
3.3.......... Construction
Phase Monitoring
3.4.......... Audit
Requirements
3.5.......... Commissioning Test for Fixed Plant Noise Sources
4.2.......... Mitigation
Measures
4.3.......... Audit
Requirements
5............. Waste
Management
5.2.......... Mitigation
Measures
5.3.......... Audit
Requirement
6............. Land
Contamination
7............. SEWERAGE
AND SEWAGE treatment implications
7.2.......... EM&A
Requirements
8.2.......... Mitigation
Measures
8.3.......... Audit
Requirements
9.2.......... Mitigation
Measures
9.3.......... EM&A
Requirements
10........... Cultural
Heritage
11........... Landscape
& Visual
11.2........ Mitigation
Measures
11.4........ Audit
Requirements
12........... Site
Environmental Audit
12.2........ Compliance
with Legal and Contractual Requirements
12.3........ Environmental
Complaints
13.2........ Electronic
Reporting of EM&A Information
13.3........ Baseline
Monitoring Report
13.4........ Monthly
EM&A Reports
13.5........ Final
Summary EM&A Report
13.7........ Interim
Notifications of Environmental Quality Limit Exceedances
LIST OF TABLES
Table 2.1 Proposed Construction Dust Monitoring Station
Table 2.2 Summary of Construction Dust Monitoring Programme
Table 2.3 Action and Limit Levels for Air Quality (Construction
Dust)
Table 2.4 Event and Action Plan for Air Quality (Construction Dust)
Table 3.1 Proposed Noise Monitoring Stations during Construction
of the Project
Table 3.2 Action and Limit Levels for Construction Noise
Table 3.3 Event and Action Plan for Construction Noise
LIST OF FIGURES
Figure 1.1 Location
of Fo Tan Nullah Revitalisation
Figure 1.2 Project
Organisation
Figure 2.1 Locations
of Proposed Construction Dust Monitoring Stations
Figure 3.1 Locations
of Proposed Noise Monitoring Points
LIST
OF APPENDICES
(a) beautification
of the existing nullah (approximately 1.7 km long and 10 m to 35 m wide) by
re-surfacing, greening and modification of channel bed;
(b) provision
of Dry Weather Flow Intercepting (DWFI) system;
(c) provision
of features for ecological enhancement and installation of underground water
storage tank [10m (W) x 30m
(L) x 2.5m (D)] under the existing Kwai Tei Street Garden equipped
with two submersible water pumps installed under the nullah bed at mid-stream
of FTN and underground water pipes (housed within the
DWFI system) for associated water retention and supplement;
(d) construction
of viewing decks and revamp of existing footbridges/bridges;
(e) revamp/provision
of footpaths, railings, amenity areas and pavilions along the nullah banks;
(f) improvement/modification
of existing planters; and
(g) associated
works including landscaping, utility works, etc.
·
Channel Bed Modification
·
Improvement of Existing Walkways
·
Construction of Dry Weather Flow Interceptor
System
·
Landscaping and Miscellaneous
·
Desilting at Downstream Tidal Zone
·
Construction of Underground Water Storage Tank and Mid-stream Submersible Water Pumps for Ecological
Enhancement Associated Water Retention and Supplement
·
Responsibilities of the Contractor, the Engineer
or Engineer’s Representative (ER), Environmental Team (ET) and Independent
Environment Checker (IEC) with respect to the environmental monitoring and
audit requirements during the course of the Project;
·
Project organisation for the EM&A works;
·
The basis for, and description of the broad
approach underlying the EM&A programme;
·
Details of the methodologies to be adopted,
including all field laboratories and analytical procedures, and details on
quality assurance and quality control programme;
·
The rationale on which the environmental
monitoring data will be evaluated and interpreted;
·
Definition of Action and Limit levels;
·
Establishment of Event and Action plans;
·
Requirements for reviewing pollution sources and
working procedures required in the event of non-compliance with the
environmental criteria and complaints; and
·
Requirements for presentation of environmental
monitoring and audit data and appropriate reporting procedures.
Engineer or Engineer’s Representative (ER)
·
Supervise the Contractor’s activities and ensure
that the requirements in the Environmental Permit (EP), the approved EIA
Report, EM&A Manual are fully complied with;
·
Inform the Contractor when action is required to
reduce environmental impacts in accordance with the Event and Action Plans;
·
Participate in joint site inspection undertaken
by the ET; and
·
Adhere to the procedures for carrying out
complaint investigation.
The Contractor
·
Work within the scope of the contract and other
tender conditions with respect to environmental requirements;
·
Operate and strictly adhere to the guidelines
and requirements in this EM&A programme and contract specifications;
·
Provide assistance to ET in carrying out
monitoring and auditing;
·
Participate in the site inspections undertaken
by ET as required, and undertake correction actions;
·
Provide information / advice to ET regarding
works activities which may contribute, or be continuing to the generation of
adverse environmental conditions;
·
Submit proposals on mitigation measures in case
of exceedance of Action and Limit levels in accordance with the Event / Action
Plans;
·
Implement measures to reduce impact where Action
and Limit levels are exceeded; and
·
Adhere
to the procedures for carrying out complaint investigation.
Environmental Team (ET)
·
Monitor various environmental parameters as
required in this EM&A Manual;
·
Analyse the EM&A data and review the success
of EM&A programme to confirm the adequacy of mitigation measures implemented
and the validity of the EIA predictions, and to identify any adverse
environmental impacts arising;
·
Carry out regular site inspection to investigate
and audit the Contractors' site practice, equipment and work methodologies with
respect to pollution control and environmental mitigation, and effect proactive
action to pre-empt problems; carry out ad hoc site inspections if significant
environmental problems are identified;
·
Audit and prepare monitoring and audit reports
on the environmental monitoring data and site environmental conditions;
·
Report on the EM&A results to the IEC,
Contractor, the ER or its delegated representative and EPD;
·
Recommend suitable mitigation measures to the
Contractor in the case of exceedance of Action and Limit levels in accordance
with the Event and Action Plans;
·
Advice to the Contractor on environmental
improvement, awareness, enhancement matters, etc. on site;
·
Timely submission of the EM&A report to the
Project Proponent and the EPD; and
·
Adhere to the procedures for carrying out
complaint investigation in accordance with Section 12.3 of this EM&A Manual.
Independent Environmental Checker (IEC)
·
Validate and confirm the accuracy of monitoring
results, appropriateness of monitoring equipment, monitoring locations with
reference to the locations of the nearby sensitive receivers, and monitoring
procedures;
·
On an as needed basis, verify and certify the
environmental acceptability of the permanent and temporary works, relevant
plans and submissions required in the EM&A manual and/or under the EP;
·
Review and verify the EM&A works performed
by the ET (at least at monthly intervals);
·
Carry out random sample check and audit the
monitoring activities and results (at least at monthly intervals);
·
Conduct random site inspection;
·
Review the EM&A reports submitted by the ET;
·
Review the effectiveness of environmental
mitigation measures and project environmental performance;
·
Review the proposal on mitigation measures
submitted by the Contractor in accordance with the Event and Action Plans;
·
Check the mitigation measures that have been
recommended in the EIA and this Manual, and ensure they are properly
implemented in a timely manner, when necessary; and
·
Adhere to the procedures for carrying out
complaint investigation, and verify investigation results of complaint cases
and the effectiveness of corrective measures.
·
0.6 - 1.7 m3 per minute (20 - 60 standard cubic
feet per minute) adjustable flow range;
·
equipped with a timing / control device with ± 5
minutes accuracy for 24 hours operation;
·
installed with elapsed-time meter with ± 2
minutes accuracy for 24 hours operation;
·
capable of providing a minimum exposed area of
406 cm2;
·
flow control accuracy: ± 2.5% deviation over
24-hour sampling period;
·
equipped with a shelter to protect the filter
and sampler;
·
incorporated with an electronic mass flow rate
controller or other equivalent devices;
·
equipped with a flow recorder for continuous
monitoring;
·
provided with a peaked roof inlet;
·
incorporated with a manometer;
·
able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
easy to change the filter; and
·
capable of operating continuously for 24-hour
period.
·
The wind sensors shall be installed on masts at
an elevated level 10m above ground so that they are clear of obstructions or
turbulence caused by the buildings;
·
The wind data shall be captured by a data
logger. The data recorded in the data
logger shall be downloaded periodically for analysis at least once a month;
·
The wind data monitoring equipment shall be
re-calibrated at least once every six months; and
·
Wind direction should be divided into 16 sectors
of 22.5 degrees each.
Table 2.1 Proposed
Construction Dust Monitoring Station
Monitoring Station ID |
EIA ASR ID |
Location |
CA_1 |
A3 |
Chun Yeung Estate |
i.
at the site boundary or such locations close to
the major dust emission source;
ii.
close to the air sensitive receivers as defined
in the EIAO-TM;
iii.
proper position/sitting and orientation of the
monitoring equipment; and
iv.
take into account the prevailing meteorological
conditions.
i.
a horizontal platform with appropriate support
to secure the samplers against gusty wind shall be provided;
ii.
two samplers shall be placed less than 2 meters
apart;
iii.
the distance between the sampler and an
obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
iv.
a minimum of 2 metres of separation from walls,
parapets and penthouses is required for rooftop samplers;
v.
a minimum of 2 metres of separation from any
supporting structure, measured horizontally is required;
vi.
no furnace or incinerator flue is nearby;
vii.
airflow around the sampler is unrestricted;
viii.
the sampler is more than 20 metres from the
dripline;
ix.
any wire fence and gate, to protect the sampler,
shall not cause any obstruction during monitoring;
x.
permission must be obtained to set up the
samplers and to obtain access to the monitoring stations; and
xi.
a secured supply of electricity is needed to
operate the samplers.
Table 2.2 Summary
of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline Monitoring |
Consecutive days of at least 2 weeks before commencement of major
construction works |
1-hour TSP |
3 times per day |
Impact Monitoring |
Throughout the construction phase |
1-hour TSP |
Table 2.3 Action
and Limit Levels for Air Quality (Construction
Dust)
Parameter |
Action Level [1] |
Limit Level |
TSP (1-hour average) |
BL <= 384 µgm-3, AL
= (BL * 1.3 + LL)/2 BL > 384 µgm-3, AL =
LL |
500 µgm-3 |
Note:
[1] BL = Baseline level, AL = Action level, LL = Limit level
Table 2.4 Event and
Action Plan for Air Quality (Construction Dust)
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action level
being exceeded by one sampling |
1. Identify source, investigate
the causes of complaint and propose remedial measures; 2. Inform Contractor,
IEC and ER; 3. Repeat measurement
to confirm finding; and 4. Increase
monitoring frequency to daily. |
1. Check monitoring
data submitted by ET; 2. Check Contractor’s
working method; and 3. Review and advise
the ET and ER on the effectiveness of the proposed remedial measures. |
1. Notify Contractor. |
1. Identify
source(s), investigate the causes of exceedance and propose remedial
measures; 2. Implement remedial
measures; and 3. Amend working
methods agreed with the ER as appropriate. |
Action level
being exceeded by two or more consecutive sampling |
1. Identify source; 2. Inform Contractor,
IEC and ER; 3. Advise the
Contractor and ER on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings; 5. Increase
monitoring frequency to daily; 6. Discuss with IEC
and Contractor on remedial actions required; 7. If exceedance
continues, arrange meeting with Contractor, IEC and ER; and 8. If exceedance
stops, cease additional monitoring. |
1. Check monitoring
data submitted by ET; 2. Check Contractor’s
working method; 3. Discuss with ET,
ER and Contractor on possible remedial measures; 4. Advise the ET and ER
on the effectiveness of the proposed remedial measures; and 5. Supervise
Implementation of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing; 2. Notify Contractor; 3. Ensure remedial
measures properly implemented. •
|
1. Identify source
and investigate the causes of exceedance; 2. Submit proposals
for remedial measures to the ER with a copy to ET and IEC within three
working days of notification; 3. Implement the
agreed proposals; and 4. Amend proposal as
appropriate. |
Limit level being
exceeded by one sampling |
1. Identify source,
investigate the causes of exceedance and propose remedial measures; 2. Inform Contractor,
IEC, ER, and EPD; 3. Repeat measurement
to confirm finding; 4. Increase
monitoring frequency to daily; and 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1. Check monitoring
data submitted by ET; 2. Check Contractor’s
working method; 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise the ER on
the effectiveness of the proposed remedial measures; and 5. Supervise
implementation of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing; 2. Notify Contractor; 3. Ensure remedial measures
properly implemented. |
1. Identify source(s)
and investigate the causes of exceedance; 2. Take immediate
action to avoid further exceedance; 3. Submit proposals
for remedial measures to ER with a copy to ET and IEC within three working
days of notification; 4. Implement the
agreed proposals; and 5. Amend proposal if
appropriate. |
Limit level
being exceeded by two or more consecutive sampling |
1. Notify IEC, ER,
Contractor and EPD; 2. Identify source; 3. Repeat measurement
to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry out analysis
of Contractor’s working procedures to determine possible mitigation to be
implemented; 6. Arrange meeting
with IEC and ER to discuss the remedial actions to be taken; 7. Assess effectiveness
of Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results; and 8. If exceedance
stops, cease additional monitoring. |
1. Check monitoring
data submitted by the ET; 2. Discuss amongst
ER, ET, and Contractor on the potential remedial actions; 3. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; and 4. Supervise the
implementation of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing; 2. In consultation
with the ET and IEC, agree with the Contractor on the remedial measures to be
implemented; 3. Supervise the
implementation of remedial measures; and 4. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1. Identify source(s)
and investigate the causes of exceedance; 2. Take immediate
action to avoid further exceedance; 3. Submit proposals
for remedial measures to the ER with a copy to the IEC and ET within three
working days of notification; 4. Implement the
agreed proposals; 5. Revise and
resubmit proposals if problem still not under control; and 6. Stop the relevant portion
of works as determined by the ER until the exceedance is abated. |
Table
3.1 Proposed Noise Monitoring Stations during
Construction of the Project
Noise Monitoring
Point |
Location |
CN_1 |
Chun Yat House, Chun Yeung Estate |
CN_2 |
57 Fo Tan Village |
CN_3 |
Jockey Club TI-I College |
i.
at locations close to the major site activities
which are likely to have noise impacts;
ii.
close to the NSRs; and
iii.
for monitoring locations located in the vicinity
of the sensitive receivers, care shall be taken to cause minimal disturbance to
the occupants during monitoring
Table 3.2 Action and Limit Levels for Construction
Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours |
When one documented complaint is
received |
75 dB(A) for residential premises; |
70 dB(A) for schools and 65 dB(A) during school
examination periods |
Notes:
·
If works are to be carried out during restricted
hours and/or percussive piling is be carried out, the monitoring requirements
and the conditions stipulated in the Construction Noise Permit (CNP) issued by
the Noise Control Authority have to be followed.
Table 3.3 Event and Action Plan
for Construction Noise
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1.
Notify IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the
IEC, ER and Contractor; 4.
Discuss with the Contractor and formulate
remedial measures; and 5.
Increase monitoring frequency to check
mitigation effectiveness. |
1.
Review the analysed results submitted by the
ET; 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly; and 3.
Supervise the implementation of remedial
measures. |
4.
Confirm receipt of notification of failure in
writing; 5.
Notify Contractor; 6.
Require Contractor to propose remedial
measures for the analysed noise problem; and 7.
Ensure remedial measures are properly
implemented. |
8.
Submit noise mitigation proposals to IEC, ET
and ER; and 9.
Implement noise mitigation proposals. |
Limit Level |
10.
Identify source; 11.
Inform IEC,
ER, EPD and Contractor; 12.
Repeat measurements to confirm findings; 13.
Increase monitoring frequency; 14.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 15.
Inform IEC,
ER and EPD the causes and actions taken for the exceedances; 16.
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and
ER informed of the results; and 17.
If exceedance stops, cease additional monitoring. |
18.
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 19.
Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; and 20.
Supervise the implementation of remedial
measures. |
21. Confirm receipt of notification of failure in writing; 22. Notify Contractor; 23. Require Contractor to propose remedial measures for the analysed noise problem; 24. Ensure remedial measures properly implemented; and 25. If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated. |
26.
Take immediate action to avoid further
exceedance; 27.
Submit proposals for remedial actions to IEC within 3
working days of notification; 28.
Implement the agreed proposals; 29.
Resubmit proposals if problem still not under
control; and 30.
Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
·
the EIA and EM&A recommendations on
environmental protection and pollution control mitigation measures;
·
ongoing results of the EM&A program;
·
works progress and programme;
·
individual works methodology proposals (which
shall include proposal on associated pollution control measures);
·
the contract specifications on environmental
protection;
·
the relevant environmental protection and
pollution control laws; and
·
previous site inspection results undertaken by
the ET and others.
·
log complaint and date of receipt onto the
complaint database and inform the IEC immediately;
·
investigate the complaint to determine its
validity, and to assess whether the source of the problem is due to project
works;
·
if a complaint is valid and due to project
works, identify mitigation measures in consultation with the IEC;
·
if mitigation measures are required, advise the
Contractor accordingly;
·
review the Contractor’s response to the
identified mitigation measures, and the updated situation;
·
if the complaint is a referral from EPD, submit
interim report to EPD on status of the complaint investigation and follow-up
action within the time frame assigned by EPD;
·
undertake additional monitoring and audit to
verify the complaint if necessary, and review that any valid reason for complaint
does not recur;
·
Report the investigation results and the
subsequent actions to the complainant (If the source of complain is identified
through EPD, the result should be reported within the time frame assigned by
EPD); and
·
Record the complaint, investigation, the
subsequent actions and the results in the monthly EM&A reports.
i.
up to half a page executive summary;
ii.
brief project background information;
iii.
drawings showing locations of the baseline
monitoring stations;
iv.
an updated construction programme with
milestones of environmental protection / mitigation activities annotated;
v.
monitoring results (in both hard and soft
copies) together with the following information:
·
monitoring methodology;
·
name of laboratory and types of equipment used
and calibration details;
·
parameters monitored;
·
monitoring locations (and depth);
·
monitoring date, time, frequency and duration;
and
·
quality assurance (QA) / quality control (QC)
results and detection limits.
vi.
details on influencing factors, including:
·
major activities, if any, being carried out on
the site during the period;
·
weather conditions during the period; and
·
other factors which might affect results.
vii.
determination of the Action and Limit Levels (AL
levels) for each monitoring parameter and statistical analysis of the baseline
data, the analysis shall conclude if there is any significant difference
between control and impact stations for the parameters monitored;
viii. revisions
for inclusion in the EM&A Manual; and
ix.
comments, recommendations and conclusions.
i.
executive summary (1-2 pages):
·
breaches of AL levels;
·
complaint log;
·
notifications of any summons and successful
prosecutions;
·
reporting changes; and
·
future key issues.
ii.
basic project information:
·
project organisation including key personnel
contact names and telephone numbers;
·
construction programme with fine tuning of
construction activities showing the inter-relationship with environmental
protection/mitigation measures for the month;
·
management structure, and
·
works undertaken during the reporting month.
iii.
environmental status:
·
works undertaken during the month with
illustrations (such as location of works, daily dredging/filling rates,
percentage of fines in the fill materials used, etc.); and
·
drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations (with co-ordinates of the monitoring locations).
iv.
a brief summary of EM&A requirements
including:
·
all monitoring parameters;
·
environmental quality performance limits (AL
levels);
·
Event-Action Plans;
·
environmental mitigation measures, as
recommended in the Final EIA report; and
·
environmental requirements in contract
documents.
v.
implementation status:
·
advice on the implementation status of environmental
protection and pollution control / mitigation measures, as recommended in the
Final EIA report.
vi.
monitoring results (in both hard and soft
copies) together with the following information:
·
monitoring methodology;
·
name of laboratory and types of equipment used
and calibration details;
·
monitoring parameters;
·
monitoring locations;
·
monitoring date, time, frequency, and duration;
·
weather conditions during the period;
·
graphical plots of the monitored parameters;
·
major activities being carried out on site
during the period;
·
any other factors which might affect the
monitoring results; and
·
QA / QC results and detection limits.
vii.
report on non-compliance, complaints,
notifications of summons and successful prosecutions:
·
record of all non-compliance (exceedances) of
the environmental quality performance limits (AL levels);
·
record of all complaints received (written or
verbal) including locations and nature of complaints investigation, liaison and
consultation undertaken, actions and follow-up procedures taken, results and
summary;
·
record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
·
review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
·
description of the actions taken in the event of
non-compliance and deficiency reporting and any follow-up procedures related to
earlier non-compliance.
viii. others:
·
an account of the future key issues as reviewed
from the works programme and work method statements;
·
advice on the solid and liquid waste management
status;
·
a forecast of the works programme, impact
predictions and monitoring schedule for the next reporting month;
·
compare and contrast the EM&A data with the
EIA predictions and annotate with explanation for any discrepancies; and
·
comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
i.
executive summary (1 - 2 pages):
·
breaches of AL levels;
·
complaints log;
·
notifications of any summons and successful
prosecutions;
·
reporting changes; and
·
future key issues.
Basic project
information:
·
project organisation and management structure;
·
construction programme; and
·
works undertaken during the reporting month.
ii.
environmental status:
·
construction programme with fine tuning of
construction activities showing the inter-relationship with environmental
protection / mitigation measures for the month;
·
works undertaken during the reporting month with
illustrations (e.g. location of works,
etc.); and
·
drawing showing the project area, any
environmental sensitive receivers and the locations of the monitoring stations.
iii.
implementation status:
·
advice on the implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation
schedule.
iv.
monitoring results (in both hard and diskette
copies) together with the following information:
·
monitoring methodology;
·
name of laboratory and types of equipment used
and calibration details;
·
parameters monitored;
·
monitoring locations (and depth);
·
monitoring date, time, frequency, and duration;
·
weather conditions during the period;
·
graphical plots of the monitored parameters in
the reporting month;
·
major activities being carried out on site
during the period;
·
any other factors which might affect the
monitoring results; and
·
QA / QC results and detection limits.
v.
report on non-compliance, complaints, and
notifications of summons and successful prosecutions:
·
record of all non-compliance (exceedances) of
the environmental quality performance limits (AL levels);
·
record of all complaints received (written or
verbal) including locations and nature of complaints investigation, liaison and
consultation undertaken, actions and follow-up procedures taken, results and
summary;
·
record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
·
review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
·
description of the actions taken in the event of
non-compliance and deficiency reporting and any follow-up procedures related to
earlier non-compliance.
vi.
others:
·
an account of the future key issues as reviewed
from the works programme and work method statements;
·
advice on the solid and liquid waste management
status;
·
a forecast of the works programme, impact
predictions and monitoring schedule for the next reporting months;
·
compare and contrast the EM&A data with the
EIA predictions and annotate with explanation for any discrepancies; and
·
comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
vii.
appendix
·
Action and Limit levels;
·
graphical plots of trends of monitored
parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following:
-
major activities being carried out on site
during the period;
-
weather conditions during the period; and
-
any other factors that might affect the
monitoring results.
·
cumulative statistics on complaints,
notifications of summons and successful prosecutions;
·
outstanding issues and deficiencies
i.
executive summary (1 - 2 pages);
ii.
basic project information including a synopsis
of the project organisation, contacts of key management, and a synopsis of work
undertaken during the course of the project;
iii.
a brief summary of EM&A requirements
including:
·
monitoring parameters;
·
environmental quality performance limits (AL
levels); and
·
environmental mitigation measures, as
recommended in the Final EIA report.
iv.
A summary of the implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation
status proformas;
v.
drawings showing the project area, environmental
sensitive receivers and the locations of the monitoring
stations;
vi.
graphical plots of the trends of monitored
parameters over the course of the project for all monitoring stations annotated
against:
·
the major activities being carried out on site
during the period;
·
weather conditions during the period; and
·
any other factors which might affect the
monitoring results.
vii.
a summary of non-compliance (exceedances) of the
environmental quality performance limits (AL levels);
viii. a
brief review of the reasons for and the implications of
non-compliance including review of pollution sources and working procedures;
ix.
a summary description of the actions
taken in the event of non-compliance and any follow-up procedures related to
earlier non-compliance;
x.
a summary record of all complaints received
(written or verbal) for each media, liaison and consultation undertaken,
actions and follow-up procedures taken;
xi.
review monitoring methodology adopted and with
the benefit of hindsight, comment on its effectiveness (including cost effectiveness);
xii.
a summary record of notifications of summons and
successful prosecutions for breaches of the current environmental protection/pollution
control legislations, locations and nature of breaches, investigation,
follow-up actions taken and results;
xiii. review
the practicality and effectiveness of the EIA process and EM&A programme
(for examples, a review of the effectiveness and efficiency of the mitigation
measures and the performance of the environmental management system, that is,
of the overall EM&A programme), recommendations (for example, any
improvement in the EM&A programme); and
xiv.
a conclusion to state the return
of ambient and / or the predicted scenario as per EIA findings.