Consultancy Ref.: AFCD/FIS/02/19 Consultancy Service for Environmental Impact Assessment Study for Designation of New Fish Culture Zones Environmental Impact Assessment (EIA) Report for Establishment of Fish Culture Zone at Mirs Bay
November 2022
|
In accordance with Clause 3.4.7 and Appendix F Requirements for Visual Impact Assessment (VIA) of the EIA Study Brief, a VIA has been conducted based on mapping with a Geographic Information System (GIS) and field surveys to help identify the existing conditions so as to be able to assess the potential visual impacts during construction and operation and glare associated with the light sources of the Project. The VIA presented here covers the elements of the Project that are located above sea level.
This VIA has been prepared according to Clause 2.1 (vi), Clause 3.2.1 (vi), Clause 3.4.7 and Appendix F of the EIA Study Brief.
Environmental Impact Assessment Ordinance (EIAO) legislation (Cap.499, S.16) and the Technical Memorandum on EIA Process (EIAO-TM), particularly Annexes 10 (Criteria for Evaluating Visual and Landscape Impact, and Impact on Sites of Cultural Heritage) and 18 (Guidelines for Landscape and Visual Impact Assessment) have been referred to in carrying out this assessment.
In addition, the following standards and guidelines have been referred to for assessing the visual impacts associated with the Project:
n Environmental Impact Assessment Ordinance Guidance Note 8/2010 (Preparation of Landscape and Visual Impact Assessment under the Environmental Impact Assessment Ordinance);
n Hong Kong Planning Standards and Guidelines (HKPSG) issued by the Planning Department (November 2015), in particular Chapter 11 Urban Design Guidelines;
n Study on Landscape Value Mapping of Hong Kong.
The Project site has two main areas, one is located at the waters to the east of Tap Mun (~1,000 m long and ~1,000 m wide; equivalent to ~105 hectares in size) while the other is located at the waters to the east of Kau Lau Wan (~2,000 m long and ~1,500 m wide; equivalent to ~305 hectares in size) (Figure 7.1). The Project Site is located in northeast open waters. It is not covered by any existing outline zoning plan (OZP) (Figure 7.2). To the west of the Project Site is Lung Keng Kan, a pre-longlisted reclamation site, and Kau Lau Wan, which consists of green belt, coastal protection area, and village type development.
The Assessment Area for visual impact assessment shall be defined by the Visual Envelope of the Project. A Visual Envelope is an area within which views of the Project will be possible. Identification of the visual envelope has been achieved by site visit and desk-top study of topographic maps and photographs, and GIS analysis, to determine potential visibility of the Project from various locations. GIS analysis uses known data regarding the proposed built structures to model the area that can potentially see the developments. It should be noted that GIS analysis uses topographic data as a baseline, disregarding existing built forms and vegetation which reduce the actual visual envelope. Figure 7.1 illustrates the GIS Visual Envelope for this Project.
The visual envelope of the Project site is determined based on its potential dimensions of 1,000 m x 1,000 m and 2,000 m x 1,500 m across the horizontal plane, with FCZ facilities no higher than 3 m in height above water (except during maintenance). Considering that the visual impact of this Project would be mainly associated with the horizontal field of view of fish farms, it is proposed to use the horizontal field of view of individual fish farms within the whole FCZ area when assessing the visual extent of impact for this Project.
Figure 7.1 also gives an indication of how far viewers are from the Project site. As a viewer moves further away from the Project site, the visual impact decreases until it is no longer visible. However, before the point of invisibility is reached, the FCZ would have reduced in scale such that it no longer has a significant visual effect on the view.
Boxes 1 and 2 below show that for an individual fish farm, the horizontal field of view will be visually dominant for distance <170 m and insignificant further than 2.3 km away, whereas the vertical field of view will be visually evident for distance <70m and insignificant for distance >340 m. Therefore, the maximum distance which the fish farm is considered insignificant will be at >2.3 km.
|
|
|
Having determined the Assessment Area for the VIA, VSRs have been broadly identified within the visual envelope. VSRs may include the people who would reside, work, play within, or travel through the Assessment Area and be potentially under the impact of the proposed Project.
Subsequently Vantage Points, or Viewpoints (VPs), were selected. VPs are positions selected to represent some potential VSRs from where the proposed Project can be viewed, and are selected to help illustrate the visual change that would be brought about by the proposed Project. The VPs have been selected to ensure that in combination they give a good overall representation of how the Project will appear to different types of VSRs, both near and far and at sea level as well as lower and higher ground elevations.
Assessment of the sensitivity of VSRs is influenced by a number of factors including the following:
n Type of VSR. VSRs are categorized according to whether the viewer is at home, at work or school, at play or leisure, or travelling (ranked by the major VSR types, as described below):
- Residential VSRs – These VSRs are people living in the area and who view the proposed Project from their homes. They are considered the most sensitive VSRs due to the character of the view from their homes having a substantial effect on their perception of quality and acceptability of their home environment and general quality of life.
- Recreational VSRs – These VSRs are people engaging in recreational activities such as hikers on established trails and footpaths, recreational fishers near the coast and outlying islands. Sensitivity of these VSRs depends on duration of stay, nature of the activity and how enclosed the location is.
n Number of individuals (ranked as very many, many, few or very few);
n Quality of existing view (ranked as good, fair or poor);
n Availability of alternative views (ranked as yes or no);
n Degree of visibility (ranked as full, partial or glimpse);
n Duration of view (ranked as long, medium or short); and
n Frequency of view (ranked as frequent, occasional or rare).
The sensitivity of each VSR is based on the values of all the above factors in totality and classified as follows:
n High: The VSR is highly sensitive to any change in their viewing experience.
n Medium: The VSR is moderately sensitive to any change in their viewing experience.
n Low: The VSR is only slightly sensitive to any change in their viewing experience.
The magnitude of change caused by a visual impact is quantified according to a number of factors including the following:
n Distance between the closest source of impact and the VSR (given in meters);
n Scale of the development. This is assessed using a number of factors, including: absolute dimensions of new built structures visible to the VSR; relative dimensions of the new built structures compared to other structures visible to the VSRs in their existing view (ranked as small, medium or large);
n Potential blockage of view (ranked as full, partial or nil);
n Duration of the impacts (ranked as temporary or permanent);
n Compatibility of the Project and associated works with the existing and planned landscape in the vicinity (ranked as good, fair or poor); and
n Reversibility of change (ranked as reversible or irreversible).
The magnitude of change caused by visual impacts on each VSR is based on the values of all the above factors in totality and classified as follows:
n Large: VSRs would suffer a major change in their viewing experience.
n Intermediate: VSRs would suffer a moderate change in their viewing experience.
n Small: VSRs would suffer a small change in their viewing experience.
n Negligible: VSRs would suffer no discernible change in their viewing experience.
By understanding the magnitude of change caused by the various impacts and the sensitivity of the various sensitive receivers, it is possible to categorize impacts in a logical, well-reasoned and consistent fashion. Table 7.1 shows the rationale for dividing the degree of significance into four thresholds, namely insignificant, slight, moderate, and substantial, depending on the combination of a magnitude of change and sensitivity of sensitive receiver.
Table 7.1 Relationship between receptor sensitivity and magnitude of change in defining impact significance
|
|
Magnitude of Change |
||||
|
|
Negligible |
Small |
Intermediate |
Large |
|
Receptor Sensitivity (VSR) |
Low |
Insignificant |
Slight |
Slight/ Moderate* |
Moderate |
|
Medium |
Insignificant |
Slight/ Moderate* |
Moderate |
Moderate/ Substantial* |
||
High |
Insignificant |
Moderate |
Moderate/ Substantial* |
Substantial |
||
*In those instances where the lower level of impact is predicted, this will be justified in the description of the impact
The four thresholds for the degree of significance are explained below. Noting impacts can be either adverse or beneficial, it should be noted that any impacts described in the text of the Report are assumed to be adverse unless specifically identified otherwise.
n Substantial: Adverse / beneficial impact where the proposed Project will cause significant deterioration or improvement in existing landscape quality.
n Moderate: Adverse / beneficial impact where the proposed Project will cause a noticeable deterioration or improvement in existing landscape quality.
n Slight: Adverse / beneficial impact where the proposed Project will cause barely perceptible deterioration or improvement in existing landscape quality.
n Insignificant: No discernible change in the existing landscape quality
Having identified and ranked the significance of potential impacts, measures, if required, will be proposed to mitigate the impacts. Firstly, means by which impacts can be avoided will be considered, then possible means that might reduce the impact magnitude, and also measures that potentially enhance existing visual quality. To ensure their effectiveness throughout the construction and operation phases of the Project and associated works, the relevant responsible parties for the implementation and management / maintenance of the proposed mitigation measures will be identified as appropriate.
As outlined in Section 7.1, the photomontages will illustrate options of design schemes as well as mitigation measures by showing baseline conditions, Day 1 with no mitigation measures, Day 1 with mitigation measures and Year 10 with mitigation measures.
An overall assessment of the acceptability, or otherwise, of visual impacts in accordance with the five criteria set out in Annex 10 of the EIAO-TM will be provided, considering the guidelines in paragraph 3.11 of Environmental Impact Assessment Ordinance GN No. 8/2010.
As detailed in Figure 7.1, Figure 7.3 and Figure 7.4, the indicative location of the Project site is in open waters, east to both Tap Mun and Kau Lau Wan. The Project is located in a relatively open sea area with high degree of visibility to a large area from a visual perspective.
The Project site will be visible to east facing coastline along Tap Mun, north facing coastline along Kau Lau Wan, coastline along Nam She Wan, elevated areas of Sai Kung East Country Park, and Tai Tan Country Trail (Figure 7.1).
Overall, the VSRs have been identified within the predicted Visual Envelope, including two types as identified in the methodology: recreational and residential. The VSRs include receivers at ground level, sea level and on elevated ground. The quality of most existing views for these VSRs affected by the FCZ, are generally good, respectively, with a high degree of visibility to natural views containing limited or no anthropogenic structures. The details of VSRs are summarised in Table 7.2 which includes their sensitivity.
Table 7.2 VSRs within the Predicted Visual Envelope
VSR ID / Representative VP |
Representative VP |
VSR Type |
Distance with the FCZ (m) |
Quality of Existing View |
Alternative Views |
Receiver Population |
Duration of View |
Frequency of View |
Degree of Visibility |
Sensitivity |
VSR 1 – Visitors at Tap Mun campsite |
VP1 |
Recreational |
911 |
Good |
Yes |
Few |
Short |
Occasional |
Full |
Medium |
VSR 2a – Visitors at Kau Lau Wan |
VP2 |
Recreational |
1,526 |
Good |
Yes |
Few |
Short |
Occasional |
Full |
Medium |
VSR 2b –Residents at Kau Lau Wan |
Residential |
Long |
Frequent |
High |
||||||
VSR 3 – Visitors at Nam She Wan beach |
VP3 |
Recreational |
448 |
Good |
Yes |
Few |
Short |
Occasional |
Full |
Medium |
VSR 4 – Hikers / recreational viewers from elevated areas of Nam She Wan and Sai Kung East Country Park |
VP4 |
Recreational |
1,174 |
Good |
Yes |
Few |
Short |
Occasional |
Full |
Medium |
VSR 5 – Hikers at Tai Tan Country Trail |
VP5 |
Recreational |
3,690 |
Good |
Yes |
Few |
Short |
Occasional |
Full |
Medium |
As shown in Figure 7.1, computer modelling suggests sections of coastal areas east of Tap Mun, Kau Lau Wan and north of Nam She Wan are within the visible area for the Project site. Broad VSR areas and specific locations of VPs are illustrated in Figure 7.1 and 7.3. It should be noted that Kung Chau and Port Island to the north of the Project site is not accessible by public transport and there is no dedicated hiking trail at these two locations. Therefore, there is no viewpoint identified to the north of the Project site. In addition, there is no island on the eastern part of the Project site. Therefore, no viewpoint is identified to the east of the Project site.
Generally VPs have been selected to represent the most affected VSRs and a total of 5 nos. of VPs have been selected from which to develop photomontages. Figure 7.1 shows the suggested VP locations and their corresponding details are provided below. Figure 7.4 shows the aerial photos of the suggested VP locations. Figure 7.5a&b – 7.9&b show the existing conditions of VP1- VP5.
VPs selected to represent VSRs of the proposed Mirs Bay FCZ
Views from Country Parks, Outlying Islands and Scenic Lookouts
VP1 - Tap Mun. VP1 is selected to represent visitors at a popular lookout point at Tap Mun. The selected VP is an open area and popular camp site near the south-eastern cliff of Tap Mun which provides a panoramic view of Mirs Bay. It is located approximately 911 m west of the Project site. Table 7.2 shows the value and quality of view of the sea from this VP is considered to be good. This VSR has alternative views to the sea. The number of VSRs is few due to the limited number of visitors at Tap Mun campsite. The duration and frequency of view is short and occasional as this VSR only spends a limited amount of time at the campsite during holidays. This VSR has a full degree of visibility. Therefore, VSR 1 is considered to have medium sensitivity.
VP2 - Kau Lau Wan. VP2 is selected to represent visitors of Kau Lau Wan (VSR 2a) and residents of Kau Lau Wan (VSR 2b). The selected VP is located at the northern coastline of Kau Lau Wan which mainly provides a view of the FCZ located at northern Mirs Bay. It is located approximately 1,526 m southwest of the Project site. Table 7.2 shows the value and quality of view of the sea from this VP is considered to be good. Both VSRs have alternative views to the sea. The number of VSRs is few due to the limited number of visitors (VSR 2a) and residents (VSR 2b) at Tap Mun. This VSR has a full degree of visibility.
For visitors at Kau Lau Wan (VSR 2a), although they have short and occasional view of the Project, they are recreational VSR, who aim to enjoy the view, hence having medium sensitivity. For residents at Kau Lau Wan (VSR 2b), their sensitivity is high, since they live in the area, and their duration of view is long and frequent.
VP3 - Nam She Wan. VP3 is selected to represent visitors at the beach. The selected VP will mainly provide an overall view of the FCZ next to Nam She Wan at sea level. It is located approximately 448 m south of the Project site. Table 7.2 shows the value and quality of view of the sea from this VP is considered to be good. This VSR has alternative views to the sea. The number of VSRs is few due to the limited number of visitors at Nam She Wan beach. The duration and frequency of view is short and occasional as this VSR only spends a limited amount of time at the beach during holidays. This VSR has a full degree of visibility. Therefore, VSR 3 is considered to have medium sensitivity.
VP4 - Sai Kung East Country Park. VP4 is selected to represent hikers visiting the elevated areas along the coastline of Nam She Wan. The selected VP is located at Sharp Peak, a well-known hiking destination at Sai Kung East Country Park. Sharp peak has an elevation of ~460m and provides a panoramic view of Mirs Bay. This VP provides a closer view of the Project site located near Nam She Wan. It is located approximately 1,174 m south of the Project site. Table 7.2 shows the value and quality of view of the sea from this VP is considered to be good. This VSR has alternative views to the sea. The number of VSRs is few due to the limited number of hikers visiting Sai Kung East Country Park. The duration and frequency of view is short and occasional as this VSR only spends a limited amount of time along the trail during holidays. This VSR has a full degree of visibility. Therefore, VSR 4 is considered to have medium sensitivity.
VP5 - Tai Tan Country Trail. VP5 is selected to represent hikers visiting the Tai Tan Country Trail near the coastline of Sai Kung West Country Park. The selected VP is located at a hiking trail and will provide occasional view of the Mirs Bay FCZ from the viewing window between Tap Mun and Kau Lau Wan. It is located approximately 3,690 m west of the Project site. Table 7.2 shows the value and quality of view of the sea from this VP is considered to be good. This VSR has alternative views to the sea. The number of VSRs is few due to the limited number of hikers visiting Tai Tan Country Trail. The duration and frequency of view is short and occasional as this VSR only spends a limited amount of time along the trail during holidays. This VSR has a full degree of visibility. Therefore, VSR 5 is considered to have medium sensitivity.
Section 2 provides an overview of the Project. The key components which may cause visual impacts are listed below. Construction visual impacts are expected to be minimal and may be caused by:
n Setup of fish rafts / cages, which includes: on-site assembly and anchoring of the fish rafts / cages, small number of marine vessels will be used as supporting vessels; and
n Provision of auxiliary facilities, such as storage and shelters for fish farmers.
Operational visual impacts are expected to be minimal and arise from:
n The presence and operation of the FCZ, including night time lighting for the sake of safety purpose.
The construction of the Project site, including towing the fish rafts / cages to the Site, assembly and anchoring of the fish rafts / cages and provision of auxiliary facilities would normally take a few weeks for each fish raft.
During operation phase, as mentioned in Section 2.6.2, four types of advanced aquaculture technologies, i.e. floating gravity cage; submersible gravity cage; integrated multi-trophic aquaculture; and semi-submersible steel truss cage, are considered suitable for this Project. Since the materials adopted in the fish rafts / cages are durable compared to traditional cages, the operation of the fish rafts / cages in the Project site based on advanced aquaculture technologies would be more than 10 years without major repair.
As illustrated in Figures 7.1, 7.3 and 7.4, the predicted Visual Envelope for the Project is relatively large and VSR groups have been identified. Five representative VPs have been selected to represent these VSRs.
Photomontages have been prepared from the VPs to illustrate the existing conditions, as well as conceptual visual impacts, for all of: impacts at Day 1 of operation without implementation of mitigation/ enhancement measures; impacts at Day 1 of operation with implementation of mitigation/ enhancement measures and residual impacts at Year 10 of operation with implementation of mitigation/ enhancement measures. The photomontages supplement the visual changes described in the text. Photomontages showing the presence of the FCZ help illustrate that the magnitude of visual change for all VSRs are negligible to intermediate. Those VSRs that are closer to the FCZ are expected to experience relatively higher magnitude of change. It should be noted that detailed information on the type of advanced aquaculture technologies as well as the number, size and separation distance of the fish rafts / cages is not available at the current stage. Such information will only be available during the later detailed design stage, subject to the mariculturists’ proposals on the type of advanced technologies to suit their business need for agreement with AFCD. The photomontages are thus prepared for illustration purpose only.
The construction of the Project will take a few weeks for each fish raft. However, due to the short distance (911 m) to the Project, the construction activities will be noticeable, and the magnitude of change is considered small. The resulting significance during construction is considered slight.
The photomontage in Figure 7.5a&b shows the Project site from this viewpoint. Since the FCZ facilities will not be higher than 3 m in height above water (except during maintenance), only the upper part of the fish rafts / cages would be exposed above the water, they would only block part of the view. The scale of development is medium as this VP can view both the northern and southern FCZ. As the fish rafts / cages adopt simple design (buoyancy collar system and a weighted net enclosure suspended beneath), they have good compatibility with the surrounding seascape. The duration of impact is temporary during construction phase and permanent during operation phase; and the impact is reversible for both phases. Due to the short distance to the Project (911 m), the Project site will be noticeable, and the magnitude of change is considered small. The resulting significance during operation is considered slight.
The construction of the Project will take a few weeks for each fish raft. Due to the considerable distance (1,526 m) to the Project, the construction activities will not be noticeable, and the magnitude of change is considered negligible. For visitors at Kau Lau Wan (VSR 2a), although they have short and occasional view of the Project, they are recreational VSR, who aim to enjoy the view, hence having medium sensitivity. For residents at Kau Lau Wan (VSR 2b), their sensitivity is high, since they live in the area, and their duration of view is long and frequent. As the magnitude of change is considered negligible, the resulting significance during construction for both VSRs is considered insignificant.
The photomontage in Figure 7.6a&b shows the Project site from this viewpoint. Since the FCZ facilities will not be higher than 3 m in height above water (except during maintenance), only the upper part of the fish rafts / cages would be exposed above the water, they would only block part of the view, and the scale of development is small. In addition, as the fish rafts / cages adopt simple design (buoyancy collar system and a weighted net enclosure suspended beneath), they have good compatibility with the surrounding seascape. The duration of impact is temporary during construction phase and permanent during operation phase; and the impact is reversible for both phases. Given there is considerable distance to the Project (1,526 m), the viewpoint is horizontal to the sea, and the FCZ facilities’ above water heights are limited to 3 m except during maintenance (not visible in horizontal viewing angle), the Project site is inconspicuous, and the magnitude of change is considered negligible. As suggested in the previous section, Kau Lau Wan’s visitors and residents are respectively considered to have medium and high sensitivity. Therefore, the resulting significance during operation is considered insignificant.
The construction of the Project will take a few weeks for each fish raft. However, due to the short distance (448 m) to the Project, the construction activities will be noticeable, and the magnitude of change is considered small. The resulting significance during construction is considered slight.
The photomontage in Figure 7.7a&b shows the Project site from this viewpoint. Since the FCZ facilities will not be higher than 3 m in height above water (except during maintenance), only the upper part of the fish rafts / cages would be exposed above the water, they would only block part of the view, and the scale of development is small. In addition, as the fish rafts / cages adopt simple design (buoyancy collar system and a weighted net enclosure suspended beneath), they have good compatibility with the surrounding seascape. The duration of impact is temporary during construction phase and permanent during operation phase; and the impact is reversible for both phases. Due to the short distance to the Project (448 m), the Project site will be noticeable, and the magnitude of change is considered small. The resulting significance during operation is considered slight.
The construction of the Project will take a few weeks for each fish raft. Despite the considerable distance to the Project (1,174 m), since the viewpoint is at a high altitude, the construction activities will be noticeable for both the northern and southern parts of the FCZ, and the magnitude of change is considered intermediate. The resulting significance during construction is considered moderate.
The photomontage in Figure 7.8a&b shows the Project site from this viewpoint. Since the FCZ facilities will not be higher than 3 m in height above water (except during maintenance), only the upper part of the fish rafts / cages would be exposed above the water, they would only block part of the view. The scale of development is medium as this VP can view both the northern and southern parts of the FCZ. In addition, as the fish rafts / cages adopt simple design (buoyancy collar system and a weighted net enclosure suspended beneath), they have good compatibility with the surrounding seascape. The duration of impact is temporary during construction phase and permanent during operation phase; and the impact is reversible for both phases. Despite the considerable distance to the Project (1,174 m), since the viewpoint is at a high altitude, it can view both the northern and southern parts of the FCZ. The magnitude of change is considered intermediate. The resulting significance during operation is considered moderate.
The construction of the Project site will take a few weeks for each fish raft. Due to the considerable distance to the Project (3,690 m), the construction activities will not be noticeable, and the magnitude of change is considered negligible. The resulting significance during construction is considered insignificant.
The photomontage in Figure 7.9a&b shows the Project site from this viewpoint. Since the FCZ facilities will not be higher than 3 m in height above water (except during maintenance), only the upper part of the fish rafts / cages would be exposed above the water, they would only block part of the view and the scale of development is small. As the fish rafts / cages adopt simple design (buoyancy collar system and a weighted net enclosure suspended beneath), they have good compatibility with the surrounding seascape. The duration of impact is temporary during construction phase and permanent during operation phase; and the impact is reversible for both phases. The VP has a considerable distance to the Project (3,690 m). Hence, the magnitude of change is considered negligible. The resulting significance during operation is considered insignificant.
Table 7.3 Magnitude of Change
VSR ID / Representative VP |
Representative VP |
Distance with the FCZ (m) |
Blockage of View (Full / Partial / Nil) |
Scale of Development (Large / Medium / Small) |
Compatibility with Surrounding Seascape (Good / Fair / Poor) |
Duration of Impact (Temporary / Permanent) |
Reversibility of Impact (Reversible / Irreversible) |
Magnitude of Change (Large / Intermediate / Small / Negligible) |
|
Construction |
Operation |
||||||||
VSR 1 – Visitors at Tap Mun campsite |
VP1 |
911 |
Partial |
Medium |
Good |
Construction phase: Temporary;
Operation phase: Permanent |
Reversible for both construction and operation phases |
Small |
Small |
VSR 2a – Visitors at Kau Lau Wan |
VP2 |
1,526 |
Partial |
Small |
Good |
Construction phase: Temporary;
Operation phase: Permanent |
Reversible for both construction and operation phases |
Negligible |
Negligible |
VSR 2b – Residents at Kau Lau Wan |
|||||||||
VSR 3 – Visitors at Nam She Wan beach |
VP3 |
448 |
Partial |
Small |
Good |
Construction phase: Temporary;
Operation phase: Permanent |
Reversible for both construction and operation phases |
Small |
Small |
VSR 4 – Hikers / recreational viewers from elevated areas of Nam She Wan and Sai Kung East Country Park |
VP4 |
1,174 |
Nil |
Medium |
Good |
Construction phase: Temporary;
Operation phase: Permanent |
Reversible for both construction and operation phases |
Intermediate |
Intermediate |
VSR 5 – Hikers at Tai Tan Country Trail |
VP5 |
3,690 |
Partial |
Small |
Good |
Construction phase: Temporary;
Operation phase: Permanent |
Reversible for both construction and operation phases |
Negligible |
Negligible |
Table 7.4 Visual Impacts Prior to Mitigation
VSR ID / Representative VP |
Representative VP |
VSR Sensitivity |
Magnitude of Change (Large / Intermediate / Small / Negligible) |
Impact Significance threshold BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant) |
||
Construction |
Operation |
Construction |
Operation |
|||
VSR 1 – Visitors at Tap Mun campsite |
VP1 |
Medium |
Small |
Small |
Slight |
Slight |
VSR 2a – Visitors at Kau Lau Wan |
VP2 |
Medium |
Negligible |
Negligible |
Insignificant |
Insignificant |
VSR 2b – Residents at Kau Lau Wan |
High |
|||||
VSR 3 – Visitors at Nam She Wan beach |
VP3 |
Medium |
Small |
Small |
Slight |
Slight |
VSR 4 – Hikers / recreational viewers from elevated areas of Nam She Wan and Sai Kung East Country Park |
VP4 |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
VSR 5 – Hikers at Tai Tan Country Trail |
VP5 |
Medium |
Negligible |
Negligible |
Insignificant |
Insignificant |
The above analysis examined the visual impacts of the Project during daylight hours. Night-lighting will be used for safety purpose in this Project. Detailed night lighting specifications are not available at this preliminary design stage, however, a preliminary assessment can be made based on similar developments. It is assumed that the light sources will generally be of low intensity, the orientation of light will point towards to the fish rafts / cages, and will not be pointing horizontally and to any VSRs. In addition, no mirrors or polished materials will be installed on the fish rafts / cages, reflectance of light will be low. Therefore, the night lighting and glare impact is considered acceptable.
The assessment made in Section 7.8 shows that visual impacts arising from the Project without any mitigation or enhancement measures in place are between insignificant to moderate. The following mitigation measures are proposed to minimise the visual impacts:
n VM1 – Construction period. Pre-construction and construction period for the Project site should be reduced as far as practical to lower visual impact;
n VM2 – Sensitive design of the fish rafts / cages. The new structures will be designed in accordance with relevant marine safety standards and regulations. Sensitive architectural design will be considered where practicable. This should take into account material texture, colour, finishes to structures to ensure the fish rafts / cages blend into the existing context, cause least disturbance to the existing seascape, and are the most visually appealing. Please refer to Figure 7.5b, Figure 7.6b, Figure 7.7b, Figure 7.8b and Figure 7.9b for the implementation of VM2;
n VM3 – Reinstatement. After operation, the open water occupied by the Project site will be reinstated to their former state, i.e. the ‘existing view’ (top photo) shown in Figure 7.5a, Figure 7.6a, Figure 7.7a, Figure 7.8a and Figure 7.9a;
n VM4 – Night-time lighting control. Light intensity and beam directional angle should be controlled at the Project site at the design stage to reduce light pollution and glare (e.g. hooded lights, specific directional focus, etc.). In addition, lighting will be limited to auxiliary structures to reduce night-time impacts.
Table 7.5 Un-mitigated and Mitigated Impacts at the VSRs
VSR ID / Representative VP |
Un-Mitigated Visual Impact |
Recommended Mitigation Measure |
Mitigated Impact (Substantial/ Moderate/ Slight/ Insignificant) |
|||
Construction |
Operation |
|
Construction |
Operation Day 1 |
Operation Year 10 |
|
VSR 1 – Visitors at Tap Mun campsite |
Slight |
Slight |
VM1-4 |
Insignificant to Slight |
Insignificant to Slight |
Insignificant to Slight |
VSR 2a – Visitors at Kau Lau Wan |
Insignificant |
Insignificant |
VM1-4 |
Insignificant |
Insignificant |
Insignificant |
VSR 2b – Residents at Kau Lau Wan |
||||||
VSR 3 – Visitors at Nam She Wan beach |
Slight |
Slight |
VM1-4 |
Insignificant |
Insignificant |
Insignificant |
VSR 4 – Hikers / recreational viewers from elevated areas of Nam She Wan and Sai Kung East Country Park |
Moderate |
Moderate |
VM1-4 |
Slight to Moderate |
Slight to Moderate |
Slight to Moderate |
VSR 5 – Hikers at Tai Tan Country Trail |
Insignificant |
Insignificant |
VM1-4 |
Insignificant |
Insignificant |
Insignificant |
The assessment made in Section 7.7 shows that visual impacts arising from the Project prior to any mitigation or enhancement measures in place, are between insignificant to moderate.
By operation, auxiliary facilities will have been removed. Therefore with sensitive design of the new structures (materials, textures, colours) and careful design of lighting, impacts would further reduce at operation day 1 for the Project site. The new structures are expected to blend in to the seascape and residual visual impacts will be insignificant to slight for VSR 1; insignificant for VSR 2a, VSR 2b, VSR 3 and VSR 5. However, given VSR 4 is an elevated viewpoint without blockage of view, the residual visual impacts would be slight to moderate. As VSR 4 is a recreational VSR, the hikers at Nam She Wan and Sai Kung East Country Park will not stay at the elevated areas for a long time in general. As such, significant adverse visual impacts are not expected.
Overall, no unacceptable residual visual impact is expected.
As Section 7.8.5 mentioned, VP5 can view both this Project’s northern part of the FCZ and also the proposed Outer Tap Mun FCZ. However, with the mitigation or enhancement measures in place, the residual impact would be reduced to insignificant for this VP. The Project may have the potential to interact with the proposed establishment of FCZ at Wong Chuk Kok Hoi, subject to the timing of completion of legislative exercise to amend the Schedule to the Fish Culture Zone (Designation) Order (Cap. 353B). However, due to its considerable distance with Wong Chuk Kok Hoi (6,405 m), cumulative impacts are not anticipated.
A number of measures to be implemented during design and construction of the Project are recommended in Section 7.9, to further enhance the visual elements associated with the Project. Design measures such as for the design of the new fish rafts / cages are recommended to be integrated into the design and construction stage of the Project as early as possible.
As no tree felling, transplanting or compensatory planting is required for the Project and visual enhancement measures would be provided during the construction phase, therefore no specific EM&A programme is required.
A visual impact assessment has been undertaken for Project site at Mirs Bay. The VSRs were identified and assessed based on their sensitivity and magnitude of change. Four visual mitigation measures are proposed to minimise the visual impacts. Given the sensitive design of the new structures, medium scale of development and good compatibility with the surrounding seascape of the structures, residual visual impacts of the Project will be subsequently considered as between insignificant and slight to moderate. No unacceptable residual visual impact is expected.
Regarding cumulative visual impacts, as Section 7.8.5 has mentioned, VP5 can view both this Project’s northern part of the FCZ and also the proposed Outer Tap Mun FCZ. However, with the mitigation or enhancement measures in place, the residual impact would be reduced to insignificant for this VP. Other cumulative visual impacts with the proposed Wong Chuk Kok Hoi FCZ are not anticipated.
According to Annex 10 of the Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM) the visual impacts are considered acceptable with mitigation measures.