Table of ContentS
1
Introduction. 1
1.1 Background. 1
1.2
Project Location and Scope. 1
1.3
Construction Programme. 1
1.4
Purpose of the Manual 2
1.5
Project Organisation. 3
1.6
Structure of the EM&A Manual 5
2 General
Requirements of THE EM&A Programme. 6
2.1 Introduction. 6
2.2 Objectives of the EM&A Programme. 6
2.3 Scope of the EM&A Programme. 6
2.4 Methodology and Criteria. 7
2.5 Environmental Monitoring. 8
2.6 Action and Limit (A/L) Levels. 8
2.7 Event and Action Plans. 8
2.8 Environmental Audit 8
2.9 Enquiries, Complaints and Requests
for Information. 9
2.10 Reporting. 9
2.11 Change or Cessation of the EM&A
Programme. 9
3
AIR QUALITY. 10
3.1 Introduction. 10
3.2 Monitoring Parameters. 10
3.3 Monitoring Equipment 11
3.4 Laboratory Measurement and Analysis. 12
3.5 Monitoring Locations. 12
3.6 Baseline Monitoring. 14
3.7 Impact Monitoring. 15
3.8 Event and Action Plan. 15
3.9 Mitigation Measures. 17
3.10 Audit Requirements. 17
4
NOISE. 18
4.1 Introduction. 18
4.2 General Monitoring Requirement 18
4.3 Monitoring Parameters of
Construction Noise. 19
4.4 Monitoring Locations for
Construction Noise. 19
4.5 Impact Monitoring for Construction
Noise. 20
4.6 Event and Action Plan for
Construction Noise. 20
4.7 Noise Parameters for Operation Road
Traffic Noise. 22
4.8
Monitoring Locations for Road Traffic Noise. 22
4.9 Impact Monitoring for Operation Road
Traffic Noise. 23
4.10 Event and Action Plan for Road
Traffic Noise. 23
4.11 Mitigation Measures. 24
4.12 Audit Requirements. 26
5
WATER QUALITY. 27
5.1 Introduction. 27
5.2 Mitigation Measures. 27
5.3 Construction Site Audits. 27
6
WASTE MANAGEMENT. 29
6.1 Introduction. 29
6.2 Waste Management Approach. 29
6.3 Staff Training. 31
6.4 Audit Requirements. 31
6.5 Mitigation Measures. 31
7
LAND CONTAMINATIOn. 33
7.1 Summary. 33
8
ECOLOGY. 34
8.1 Introduction. 34
8.2 Mitigation Measures. 34
8.3 Audit Requirements. 35
9 LANDSCAPE
AND VISUAL. 36
9.1 Introduction. 36
9.2 Mitigation Measures. 36
9.3 Audit Requirements. 36
10
CULTURAL HERITAGE. 37
10.1 Introduction. 37
10.2 Mitigation Measures. 37
10.3 Audit Requirements. 37
11 Environmental
AUDIT.
39
11.1 Site Inspection. 39
11.2 Compliance with Legal and
Contractual Requirements. 40
11.3 Environmental Complaints. 40
11.4 Log Book. 41
12
REPORTING.. 42
12.1 General 42
12.2 Interim Notification of Environmental
Quality Limit Exceedances. 42
12.3 Baseline Monitoring Report 42
12.4 Monthly EM&A Reports. 43
12.5 Data Keeping. 48
12.6 Electronic Reporting of EM&A
Information. 48
1
Introduction
1.1.1
The title of the Project is “Traffic Improvement
Scheme in Tuen Mun – Widening and Addition of Slip Roads at Lung Fu Road / Tuen
Mun Road / Wong Chu Road / Hoi Wing Road” (hereinafter referred to as the Project).
1.1.2
The Tuen Mun - Chek Lap Kok Tunnel (TM-CLKT) was
commissioned on 27 December 2020. The traffic flow within Tuen Mun (TM)
District, including Tuen Mun Road (Town Centre Section) (TMR (TCS)) and its
slip roads to and from Wong Chu Road (WCR), has been gradually increasing after
the commissioning of TM-CLKT.
1.1.3
After the commissioning of TM-CLKT in 2020, Lung Fu
Road (LFR), WCR and other local roads in Tuen Mun will be operating beyond
capacity after 2026 due to the development in the Northwest New Territories
(NWNT) and development in North Lantau. The concerned roads are currently
very busy especially peak hours. The Project not only helps to relieve traffic
congestion on TM area and other major roads in TM area but it also improves the
capacity of major local road junction roads by directing traffic between NWNT
and North Lantau.
1.2
Project
Location and Scope
1.2.1
The location plan of the Project is provided in Figure 1.1. The
scope of works under the preferred option for the traffic improvement scheme
for the various road links comprises the following:
(a)
Construction of Hoi Wing Road Slip Road (HWRSR) - a
single lane at-grade slip road of approximate 550 meters long connecting Tuen
Mun Road northbound to Castle Peak Road (Castle Peak Bay Section) westbound
near Hoi Wing Road;
(b)
Construction of Lung Fu Road Slip Road Northbound
(LFRSR-NB) - a single lane elevated road of approximate 600 meters long
connecting the existing elevated Lung Fu Road northbound to Tsing Wun Road
(TWR) northbound;
(c) Construction of Lung Fu Road Slip
Road Southbound (LFRSR-SB) – a single lane elevated road of approximate 800
meters long connecting Tsing Wun Road southbound to the existing elevated Lung
Fu Road southbound;
(d) Modification of the
existing at-grade slip road of 150m long approximately connecting TWR SB and
WCR Eastbound (EB) affected by LFRSR SB;
(e)
Modification of the existing at-grade
slip road connecting WCR WB to TWR NB;
(f)
Ancillary works including geotechnical, drainage,
sewerage, water, utilities, lighting, landscaping, electrical and mechanical
works, construction/reconstruction of noise barriers, retaining walls,
slope improvement; and installation of street furniture and traffic aids.
1.3
Construction
Programme
1.3.1
The construction works of the Project will tentatively
commence in mid-2024 for completion by 2031. A preliminary outline
construction programme for the Project is provided in Appendix 1.1.
1.4
Purpose
of the Manual
1.4.1
The purpose of this Environmental Monitoring and Audit
(EM&A) Manual is to guide the set up of an EM&A programme to ensure
compliance with the EIA Study recommendations, to assess the effectiveness of
the recommended mitigation measures and to identify any further need for
additional mitigation measures or remedial action. This EM&A Manual
outlines the environmental monitoring and auditing works for both the
construction and operation phases of the Project. It provides systematic
procedures for the monitoring and auditing of potential environmental impacts
that may arise from the works.
1.4.2
Hong Kong environmental regulations, the Hong Kong
Planning Standards and Guidelines and the recommendations in the EIA Report of
this Project have served as environmental standards and guidelines in the
preparation of this EM&A Manual. In addition, this EM&A Manual
has been prepared in accordance with the requirements stipulated in Annex 21
of the EIAO-TM.
1.4.3
This EM&A Manual contains the following information:
· Responsibilities of the Contractor,
the Engineer or Engineer’s Representative (ER), the Environmental Team (ET) and
the Independent Environmental Checker (IEC) with respect to the environmental
monitoring and audit requirements during the course of the Project;
· Project organisation for the
EM&A works of the Project;
· Requirements with respect to the
construction programme schedule and the necessary environmental monitoring and
audit programme to track the varying environmental impact;
· Details of the methodologies to be
adopted, including all field laboratories and analytical procedures, and
details on quality assurance and quality control programme;
· The rationale on which the
environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit
levels;
· Establishment of Event and Action
Plans (EAPs);
· Requirements for reviewing pollution
sources and working procedures required in the event of non-compliance with the
environmental criteria and complaints;
· Requirements for presentation of
environmental monitoring and audit data and appropriate reporting procedures;
and
· Requirements for review of EIA
predictions and the effectiveness of the mitigation measures/environmental
management systems and the EM&A programme.
1.4.4
This EM&A Manual is a dynamic document that should
be reviewed regularly and to be updated (as necessary) during the
implementation of the Project. The contractor should regularly review the
mitigation measures and project implementation schedule in Appendix 1.2 with
respect to the design developments and construction methodology.
1.4.5
For this EM&A Manual, the “Engineer” refers to the
Engineer as defined in the Contract and the ER, in case where the Engineer’s
power has been delegated to the ER, in accordance with the
Contract. The ET Leader, who should be responsible for and in charge
of the ET, refers to the person delegated the role of executing the
EM&A requirements. The IEC should undertake the auditing role.
1.5.1
The roles and responsibilities of the various parties
involved in the construction phase EM&A programme are outlined below. The
organisation and lines of communication with respect to environmental
management for the Project are shown in Appendix 1.3.
1.5.2
The duties and responsibilities of the respective
parties are as follows:
Engineer or Engineer’s Representative (ER)
1.5.3
The Engineer/ ER is responsible for overseeing
the construction works and for ensuring that the works undertaken by the
Contractor are in accordance with the specification and contractual
requirements.
· Supervise the
Contractor’s activities and ensure that the requirements in the EM&A Manual
are fully complied with;
· Inform the Contractor
when action is required to reduce impacts in accordance with
the EAPs or protocols or those in the Contract Specifications in the
event of exceedance or complaint;
· Participate in joint
site inspections undertaken by the ET; and
· Adhere to the procedures
for carrying out complaint investigation in accordance with this EM&A
Manual.
Contractor
1.5.4
The Contractor should report to the Engineer/ ER:
·
Ensure
thorough implementation of mitigation measures as required;
·
Provide
assistance to the ET in carrying out monitoring and preparing reporting;
·
Accompany
joint site inspections undertaken by ET and implement the corrective /
follow-up actions/recommendations instructed by the Engineer;
·
Follow the
procedures stipulated in the agreed EAPs in the event
of exceedance or complaint;
·
Submit
proposals on mitigation measures in case of exceedances of Action and
Limit levels in accordance with the EAPs;
·
Implement
measures to reduce impact whenever Action and Limit levels are exceeded;
·
Report all
findings of site inspections and corrective/ follow-up actions taken to the ER;
and
·
Adhere to
the procedures for carrying out complaint investigation in accordance with this
EM&A Manual.
Environmental Team (ET)
1.5.5
The ET should conduct the EM&A programme and
ensure the Contractor’s compliance with the Project’s environmental performance
requirements during construction. The ET should be an independent party
from the IEC and the Contractor.
1.5.6
An ET shall be established before the commencement of
construction of the Project. The ET leader should possess at least 7
years of experience in EM&A and/ or environmental management.
1.5.7
The ET should monitor the mitigation measures
implemented by the Contractor on a regular basis to ensure the compliance with
the intended aims of the measures.
· Monitor the various
environmental parameters as required by this or subsequent revisions to the
Manual;
· Provide advice on all
environmental issues to the Contractor;
· Analyse the EM&A
data and review the success of the EM&A programme to cost-effectively
confirm the adequacy of mitigation measures implemented and the validity of the
EIA predictions and to identify any adverse environmental impacts arising;
· Carry out site
inspection to investigate and audit the Contractor’s site practice, equipment
and work methodologies with respect to pollution control and environmental
mitigation, and review the programme of works, in order to anticipate
environmental issues that may require mitigation before the problem arises;
· Audit the environmental
monitoring data and report the status of general site environmental conditions
and the implementation of mitigation measures resulting from site inspections;
· Follow the procedures
stipulated in the agreed EAPs in the event of exceedance or
complaint;
· Report the EM&A
results and wider environmental issues and conditions to the IEC, Contractor,
ER, and Environmental Protection Department (EPD);
· Prepare EM&A Reports
as required in the EM&A Manual
· Recommend suitable
mitigation measures to the Contractor in the case of exceedance of
Action and Limit levels in accordance with the EAPs; and
· Adhere to the procedures
for carrying out complaint investigation in accordance with this EM&A
Manual.
Independent Environmental Checker
(IEC)
1.5.8
An IEC shall be employed before commencement of
construction of the Project. Appointment of IEC shall be approved by EPD.
The IEC shall be an independent party from the Contractor and the ET and
possess at least 7 years’ experience in EM&A and/or environmental
management. The IEC shall report directly to the EPD on matters relating
to the EM&A programme and environmental impacts from the Project.
· Review the EM&A works performed
by the ET (at not less than monthly intervals);
· Carry out random sample check and
audit the monitoring activities and results (at not less than monthly
intervals);
· Conduct random site inspection;
· Report the audit results to the ER
and EPD in parallel;
· Review the EM&A Reports
submitted by the ET;
· Review the effectiveness of
environmental mitigation measures and project environmental performance;
· Review the proposal on mitigation
measures submitted by the Contractor in accordance with the EAPs;
· Check the mitigation measures that
have been recommended in the EIA and this EM&A Manual, and ensure they are
properly implemented in a timely manner, when necessary; and
· Adhere to the procedures for
carrying out complaint investigation in accordance with this EM&A Manual.
1.5.9
Sufficient and suitably qualified professional and
technical staff shall be employed by the respective parties to ensure full
compliance with their duties and responsibilities, as required under the
EM&A programme for the duration of the Project.
1.6
Structure
of the EM&A Manual
1.6.1
The following sections present the EM&A
requirements of various aspects. The structure of the EM&A Manual is
outlined as follows:
·
Section 2 – General Requirements of EM&A
Programme;
·
Section 3 – Sets out EM&A requirements for
air quality;
·
Section 4 – Sets out EM&A requirements for
noise;
·
Section 5 – Sets out EM&A requirements for
water quality;
·
Section 6 – Sets out EM&A requirements for
waste management;
·
Section 7 – Sets out EM&A requirements for
land contamination;
·
Section 8 – Sets out EM&A requirements for
ecology;
·
Section 9 – Sets out EM&A requirements for
landscape and visual;
·
Section 10 – Sets out EM&A requirements for
cultural heritage;
·
Section 11 – Describes the scope and frequency
of environmental site audits and sets out the procedures for handling
environmental complaints; and
·
Section 12 – Details the EM&A reporting
requirements.
2
General Requirements of THE
EM&A Programme
1
2
2.1
2.1.1 General requirements of the EM&A programme
for the Project are presented in this section. The scope of the programme
is developed with reference to the findings and recommendations of the EIA
Report.
2.2
Objectives
of the EM&A Programme
2.2.1
The potential environmental impacts associated with
the Project have been assessed and described in the EIA Report. The EIA
Report also specifies the mitigation measures required to comply with the
environmental criteria. These mitigation measures and their
implementation requirements are presented in the Implementation Schedule (refer
to Appendix 1.2).
The EIA recommends that an EM&A programme be implemented to assess the
effectiveness of measures and to confirm that there will be no adverse
environmental impacts during all phases of the Project. It is also
recommended that regular site audits be undertaken during the construction and
operation phases to check whether good site practices are properly implemented
to prevent adverse environmental impacts. Any activities that have the
potential to cause adverse environmental impacts are identified before the
adverse impacts occurred. Ad-hoc visits should also be undertaken in
response to any complaints or reported non-compliance with environmental
standards in order to enable prompt actions to be taken to address the impacts.
2.2.2
This Manual provides details of the EM&A
requirements that have been recommended in the EIA Report. The main objectives
of the EM&A programme are to:
·
Verify the
environmental impacts predicted in the EIA Report;
·
Monitor the performance
of the Project and the effectiveness of mitigation measures;
·
Determine Project
compliance with regulatory requirements and standards;
·
Provide an early
indication should any of the environmental control measures or practices fail
to achieve the required standards;
·
Take remedial action if
unexpected problems or unacceptable impacts arise;
·
Provide a database
against which any short-term or long-term environmental impacts of the Project
can be determined; and
·
Provide data against
which environmental audits may be undertaken.
2.3
Scope
of the EM&A Programme
2.3.1
The scope of the EM&A Programme is to:
· Establish baseline
construction dust levels at designated locations;
· Implement impact
monitoring programmes for construction dust and noise, and operation road
traffic noise;
· Implement inspection and
audit programmes for air quality, noise, water quality, waste management,
ecology, landscape and visual and cultural heritage issues;
· Liaise with, and provide
environmental advice (as requested or when otherwise necessary) to construction
site staff on the comprehension and consequences of the environmental
monitoring data and exceedances;
· Identify and resolve
environmental issues and other functions as they may arise from the works;
· Check and advice the
Contractor's overall environmental performance, the implementation of EAPs, and
remedial actions taken to mitigate adverse environmental impacts as they may
arise from the works;
· Conduct monthly reviews
of monitored impact data as the basis for assessing compliance with the defined
criteria and to ensure that necessary mitigation measures are identified and
implemented, and undertake additional ad hoc monitoring and auditing as
required by special circumstances;
· Evaluate and interpret
all environmental monitoring data to provide an early indication should any of
the environmental control measures or practices fail to achieve the acceptable
standards, and to verify the environmental impacts assessed in the EIA Study;
· Manage and liaise with
other individuals or parties concerning other environmental issues deemed to be
relevant to the construction process;
· Conduct regular site
inspections to assess:
o The level of the Contractor’s general environmental
awareness;
o The Contractor’s implementation of the
recommendations in the EIA Report;
o The Contractor’s performance as measured by the
EM&A programme;
o The need for specific mitigation measures to be
implemented or the continued usage of those previously agreed;
o To advise the Site Staff of any identified
potential environmental issues; and
· Submit Monthly EM&A
Reports which summarise environmental monitoring and auditing data, with full
interpretation illustrating the acceptability or otherwise of any environmental
impacts and identification or assessment of the implementation status of agreed
mitigation measures.
2.4
Methodology
and Criteria
2.4.1
The environmental issues associated with the
construction phase of the Project will be mitigated through the monitoring and
mitigation measures specified in the EIA Report and this EM&A Manual.
2.4.2
The monitoring of effectiveness of the mitigation measures
will be achieved through the environmental monitoring programme as well as
through site inspections. The inspections will include within scope,
mechanisms to review and assess the implementation of the recommended
mitigation measures, and that the timely resolutions of received complaints are
managed and controlled in a manner consistent with the recommendations given in
the EIA Report and the EM&A Manual.
2.5
Environmental
Monitoring
2.5.1
The environmental monitoring works throughout the
construction period and the first year after the commencement of operation of
the Project should be carried out in accordance with the EM&A Manual and
reported by the ET. Monitoring should be conducted at the chosen and
agreed representative sensitive receivers.
2.6
Action
and Limit (A/L) Levels
2.6.1
Action and Limit (A/L) Levels are defined levels for
impact recorded by the environmental monitoring works, which represent levels
at which a prescribed response is required. These levels are described in
the principle below and later quantitatively defined in the relevant sections
of the EM&A Manual:
· Action Level – beyond which there is
a clear indication of a deteriorating ambient environment for which appropriate
remedial actions are likely to be necessary to prevent environmental quality
from falling outside the Limit Levels, which will be unacceptable.
· Limit Level – statutory limits stipulated
in the relevant pollution control ordinances, Hong Kong Planning Standard
Guidelines, or Environmental Quality Objectives established by the EPD.
If these are exceeded, works should not proceed without appropriate remedial
action, including a critical review of the plant and working methods.
2.7
Event
and Action Plans
2.7.1
The purpose of the EAPs is to provide, in association
with the environmental monitoring activities, procedures for ensuring that if
any significant environmental impacts occur in the form of exceedance of A/L
Levels identified in the EM&A programme, cause(s) will be quickly
identified and remediated.
2.8.1
The ET should undertake environmental audit of
compliance with stipulated procedures and site inspections of on-site
practices. The primary objective is to assess the effectiveness of the
implementation of the environmental mitigation measures as recommended in the
EIA Report and the EM&A Manual.
2.8.2
Whilst environmental audit will complement the
environmental monitoring activity with regard to the effectiveness of dust
suppression and noise attenuation, the criteria against which the audit should
be derived from the clauses within the Contract, which seek to enforce the
recommendations of the EIA Report and the EM&A Manual.
2.8.3
The findings of the environmental audit and site
inspection should be made known to the Contractor at the time of the
audit/inspection to enable rapid resolution of identified non-compliances or
observations. Non-compliances, observations and the corrective/ follow-up
actions undertaken will be reported in the Monthly EM&A Reports.
2.9
Enquiries,
Complaints and Requests for Information
2.9.1
Enquiries, complaints and requests for information
will be expected from a wide range of individuals and organisations including
members of the public, government departments, nearby residents, the press and
community groups.
2.9.2
All enquiries concerning the environmental effects of
the construction works, irrespective of the channel of receipt, will be
directed to the Contractor and copied to the ER and Highways Department
(HyD). Procedures for handling enquiries and complaints should
follow the procedures set out in Section 11.
2.9.3
In all cases, the complainant should be notified of
the findings, and environmental audit and site inspection should be put in
place to minimise the reoccurrence of similar problems.
2.10.1
During the construction phase, Environmental Baseline
Monitoring Reports, Monthly EM&A Reports and Final EM&A Review Reports
should be prepared and certified by the ET Leader and verified by IEC prior to
submission to the Contractor and HyD. In accordance with Annex 21 of
the EIAO-TM, a copy of the monthly EM&A reports and final EM&A
review reports should be made available to the Director of Environmental
Protection. Details of the reporting requirements and submission schedule
should be in accordance with the guidelines set out in Section 12.
2.11
Change
or Cessation of the EM&A Programme
2.11.1
The ET should carry out the EM&A programme in
accordance with the EM&A Manual throughout the construction and operational
phases of the Project. Any change or cessation of the EM&A
programme, or any part of it, should be justified by the ET Leader and verified
by the IEC as conforming to the requirements set out in the EM&A Manual and
should be submitted to the EPD for approval.
3
AIR QUALITY
3.1.1
Potential air quality impacts arising from the
construction and operation phases of the Project on air sensitive receivers
(ASRs) were addressed in the EIA Report. It is concluded that no adverse
air quality impact from the Project would be anticipated during the
construction phase. Dust monitoring is proposed to be conducted
during the construction phase of the Project.
3.1.2
No adverse air quality impact would be anticipated
during the operation phase of the Project. No operation phase air quality
monitoring and audit is therefore considered necessary.
3.1.3
Regular environmental site audit is recommended to be
conducted during the entire construction phase of the Project to ensure proper
implementation of the proposed dust mitigation measures and good site practices
stipulated in the Air Pollution Control (Construction Dust) Regulation
and those recommended in Section 3.9 of EIA Report. The
implementation schedule of mitigation measures is presented in Appendix 1.2.
3.1.4
The dust monitoring criteria specified in this
EM&A manual is TSP of 500µg/m3 (measured at 298K and 1atm)
according to Annex 4 of the EIAO-TM (at the time of writing this EM&A
manual). In view of the upcoming update of EIAO-TM under EIAO review,
there is a chance that the criteria for construction dust monitoring will be
changed ().
In view of this, if there is any future update to the dust monitoring criteria
and requirement (under the update of EIAO-TM) at the time of approval of this
EIA, the Applicant shall separately submit a Construction Dust Monitoring Plan
/ revised EM&A Manual which includes details of the updated monitoring
parameters, monitoring equipment, baseline and impact monitoring procedures,
and event and action plan, etc. for EPD approval before carrying out the
EM&A dust monitoring.
3.2
Monitoring
Parameters
3.2.1
Monitoring of the Total Suspended Particulate (TSP)
levels shall be carried out by the ET to ensure that construction works are not
generating dust that exceeds the acceptable level. 1-hour Total Suspended
Particulates (TSP) concentrations shall be measured to indicate the impacts of
construction dust. The criteria for 1-hour TSP limit is 500µg/m3.
This level is not to be exceeded at any of the ASRs. Timely action should
be taken to rectify the situation if an exceedance is detected.
3.2.2
The 1-hour TSP levels shall be measured by following
the standard high-volume sampling method as set out in Part 50 Chapter 1
Appendix B, Title 40 of the “Code of Federal Regulations” of the USEPA.
Upon approval of the IEC, 1-hour TSP levels can be measured by direct
reading method which is capable of producing comparable results as that by the
high volume sampling method, to indicate short event impacts.
3.2.3
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, special phenomena
and work progress of the site etc., shall be recorded down in detail by the ET.
A sample data sheet is shown in Appendix 3.1.
3.3.1
A high volume sampler (HVS) in compliance with the
following specifications should be used for carrying out the 1-hour TSP
monitoring:
·
0.6-1.7m3/minute
(20-60 Standard Cubic Feet per Minute (SCFM)) adjustable flow range;
·
Equipped with a timing/
control device with ±5-minute accuracy for 24-hour operation;
·
Installed with
elapsed-time meter with ±2-minute accuracy for 24-hour operation;
·
Capable of providing a
minimum exposed area of 406cm2 ;
·
Flow control accuracy:
±2.5% deviation over 24-hour sampling period;
·
Equipped with a shelter
to protect the filter and sampler;
·
Incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
Equipped with a flow
recorder for continuous monitoring;
·
Provided with a peaked
roof inlet;
·
Incorporated with a
manometer;
·
Able to hold and seal
the filter paper to the sampler housing at a horizontal position;
·
Easy to change the
filter; and
·
Capable of operating
continuously for a 24-hour period.
3.3.2
The ET is responsible for the provision, installation,
operation, maintenance, and dismantling of the monitoring equipment. The
ET shall ensure that a sufficient number of HVSs with an appropriate
calibration kit are available for carrying out the baseline monitoring, regular
impact monitoring and ad hoc monitoring. The HVSs shall be equipped with
an electronic mass flow controller and be calibrated against a traceable
standard at regular intervals. All the equipment, calibration kit, filter
papers, etc., shall be clearly labelled.
3.3.3
The flow-rate of the sampler before and after the
sampling exercise with the filter in position shall be verified to be constant
and be recorded in the data sheet as mentioned in Appendix
3.1.
3.3.4
If the ET proposes to use a direct reading dust meter
to measure 1-hour TSP levels, they shall submit sufficient information to the
IEC to prove that the instrument is capable of achieving a comparable result to
the HVS. The instrument should also be calibrated regularly, and the
1-hour sampling shall be determined periodically by the HVS to check the
validity and accuracy of the results measured by direct reading method.
3.3.5
Wind data monitoring equipment shall also be provided
and set up at suitable locations for logging wind speed and wind direction near
the dust monitoring locations. The equipment installation location shall
be proposed by the ET and agreed with the Engineer/ ER and the IEC. For
the installation and operation of wind data monitoring equipment, the following
points shall be observed:
·
The wind sensors shall
be installed on masts at an elevated level 10-metre above ground so that they
are clear of obstructions or turbulence caused by the buildings;
·
The wind data shall be
captured by a data logger. The data recorded in the data logger shall be
downloaded periodically for analysis at least once a month;
·
The wind data
monitoring equipment shall be re-calibrated at least once every six months; and
·
Wind direction should
be divided into 16 sectors of 22.5 degrees each.
3.3.6
In exceptional situations, the ET may propose
alternative methods to obtain representative wind data upon approval from the
ER and agreement from the IEC.
3.4
Laboratory
Measurement and Analysis
3.4.1
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected shall be available for sample
analysis, equipment calibration and maintenance. The laboratory should be
Hong Kong laboratory accreditation scheme (HOKLAS) accredited.
3.4.2
If a site laboratory is set up or a non-HOKLAS
accredited laboratory is hired for carrying out the laboratory analysis, the
laboratory equipment shall be approved by the Engineer/ ER, in consultation
with the IEC. Measurement performed by the laboratory shall be
demonstrated to the satisfaction of the ER and IEC. The IEC shall
regularly audit the measurement performed by the laboratory to ensure the
accuracy of measurement results. The ET shall provide the Engineer/ ER
and the IEC with one copy of the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B for reference.
3.4.3
Filter paper of size 8"x10" shall be
labelled before sampling. It shall be a clean filter paper with no
pinholes and shall be conditioned in a humidity-controlled chamber for over
24-hour and be pre-weighed before use for the sampling.
3.4.4
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the
humidity-controlled chamber followed by accurate weighing by an electronic
balance with a readout down to 0.1mg. The balance shall be regularly
calibrated against a traceable standard.
3.4.5
All the collected samples shall be kept in a good
condition for six months before disposal.
3.5.1
The selected monitoring locations are considered the
worst potentially affected air sensitive receivers located in the vicinity of
construction sites. The proposed air quality monitoring locations during
the construction phase are listed in Table 3.1 below and shown
in Figure 3.1.
Table 3.1
Proposed
Construction Dust Monitoring Stations
Monitoring
Station ID
|
EIA
ID
|
Location
|
Approximate
Horizontal Distance from the Construction Project Site Boundary (m)
|
CDM1
|
A18
|
Kam Fai
Garden
|
20
|
CDM2
|
A24
|
Chung Sing
Benevolent Society
Mrs. Aw Boon Haw Secondary School
|
15
|
CDM3
|
A22
|
Hanford
Garden
|
20
|
CDM4
|
A23
|
Siu Lun
Court
|
30
|
CDM5
|
A13
|
Ju Ching Chu
Secondary School
(Tuen Mun)
|
20
|
CDM6
|
A11
|
Hong Chi
Morninglight School Tuen Mun
|
65
|
CDM7
|
A07
|
Church of
Christ in China (CCC)
Hoh Fuk Tong Primary School
|
50
|
CDM8
|
A06
|
Lung Yat
Estate
|
20
|
CDM9
|
P01
|
Yip Wong
Road PRH Phase 1
|
35
|
CDM10
|
A01
|
Luen Cheong
Can Centre
|
15
|
CDM11
|
A03
|
Nam Fung
Industrial City – Block 2
|
15
|
CDM12
|
A08
|
Lung Mun
Oasis – Block 5
|
35
|
CDM13
|
A19
|
Dragon Inn
Court – Block 2
|
70
|
CDM14
|
A20
|
Palm Cove –
Tower 5
|
100
|
CDM15
|
A16
|
Tsing Shan
Tsuen 83
|
25
|
CDM16
|
A21
|
Sam Shing
Temple
|
45
|
3.5.2
The status and locations of the air quality sensitive
receivers may change after issuing this Manual. In such case, the ET
shall propose updated monitoring locations and seek approval from ER and IEC
and agreement from EPD on the proposal.
3.5.3
When alternative monitoring locations are proposed,
the following criteria, as far as practicable, shall be followed:
·
At the site boundary or
such locations close to the major dust emission source;
·
Close to the air
sensitive receivers as defined in the EIAO-TM;
· Proper position/sitting and orientation of
the monitoring equipment; and
·
Take into account the
prevailing meteorological conditions.
3.5.4
The ET shall agree with the IEC on the position of the
HVS for the installation of the monitoring equipment. When positioning
the samplers, the following points shall be noted:
·
A horizontal platform
with appropriate support to secure the samplers against gusty wind shall be
provided;
·
No two samplers shall
be placed less than 2-metre apart;
·
The distance between
the sampler and an obstacle, such as building, must be at least twice the
height that the obstacle protrudes above the sampler;
·
A minimum of 2-metre of
separation from walls, parapets and penthouses is required for rooftop
samplers;
·
A minimum of 2-metre of
separation from any supporting structure, measured horizontally is required;
·
No furnace or
incinerator flue is nearby;
·
Airflow around the
sampler is unrestricted;
·
The sampler is more
than 20-metre from the dripline;
·
Any wire fence and
gate, to protect the sampler, shall not cause any obstruction during
monitoring;
·
Permission must be
obtained to set up the samplers and to obtain access to the monitoring
stations; and
· A secured supply of electricity is needed
to operate the samplers.
3.6.1
Baseline monitoring shall be undertaken to determine
the ambient 1-hour TSP levels at the monitoring stations prior to the
commencement of construction of the Project. The ET shall carry out the
baseline monitoring of 1-hour TSP levels at all of the designated monitoring
locations listed in Table 3.1 for at least fourteen consecutive days
prior to the commissioning of the construction works of the Project.
1-hour TSP sampling should be done at least three times per day at each
monitoring station.
3.6.2
Before commencing baseline monitoring, the ET shall
inform the IEC of the baseline monitoring programme such that the IEC, if
considered necessary, can conduct on-site audit to ensure the accuracy of the
baseline monitoring results.
3.6.3
During the baseline monitoring, there should not be
any major construction or dust generation activities in the vicinity of the
monitoring stations. General meteorological conditions (wind speed,
direction and precipitation) and notes regarding any significant adjacent dust
producing sources should be recorded throughout the baseline monitoring period.
The baseline monitoring programme is summarised in Table 3.2.
3.6.4
In case the baseline monitoring cannot be carried out
at the designated monitoring locations during the baseline monitoring period,
the ET shall carry out the monitoring at alternative locations which can
effectively represent the baseline conditions at the impact monitoring
locations. The alternative baseline monitoring location shall be agreed
with the ER and the IEC, and approved by the EPD.
3.6.5
In exceptional cases, when insufficient baseline
monitoring data or questionable results are obtained, the ET shall liaise with
the IEC and EPD to agree on an appropriate set of data to be used as a baseline
reference and submit to the ER and IEC for approval.
3.6.6
Ambient conditions may vary seasonally and shall be
reviewed once every three months. If the ET considered that the ambient
conditions have changed and a repeat of the baseline monitoring is required to
be carried out for obtaining the updated baseline levels, the monitoring should
be undertaken at times when the Contractor’s activities are not generating
dust, at least in the proximity of the monitoring stations. The baseline
levels and, in turn, the air quality criteria, should be revised. The
revised baseline levels and air quality criteria should be agreed with the IEC
and the EPD.
3.7.1
The ET shall carry out impact monitoring during the
construction phase of the Project. For 1-hour TSP monitoring, the
sampling frequency of at least three times every six days should be undertaken
when the highest dust impact is expected to occur. In case of
non-compliance with the air criteria, more frequent monitoring, as specified in
the Action Plan in the following section, should be conducted. This
additional monitoring should be continued until the excessive dust emission or
the deterioration in the air quality is rectified. The impact monitoring
programme is summarised in Table 3.2.
3.7.2
The monthly schedule of the impact monitoring
programme should be prepared by the ET one month prior to the commencement of
the scheduled construction period. Before commencing the impact
monitoring, the ET shall inform the IEC of the impact monitoring programme such
that the IEC, if considered necessary, can conduct an on-site audit to ensure
the accuracy of the impact monitoring results.
Table
3.2 Summary of Construction Dust Monitoring Programme
Monitoring Period
|
Duration
|
Sampling Parameter
|
Frequency
|
Baseline
Monitoring
|
Consecutive
days of at least fourteen days before the commencement of major construction
works
|
1-hour TSP
|
three times
per day
|
Impact
Monitoring
|
Throughout
the construction phase
|
1-hour TSP
|
three
times in
every six days
|
3.8
Event and Action Plan
3.8.1
The baseline monitoring results form the basis for
determining the air quality criteria for impact monitoring. The ET shall
compare the impact monitoring results with air quality criteria set up for
1-hour TSP. Table 3.3 shows the air quality criteria, namely action and limit levels to be
used.
3.8.2
Should non-compliance with the air quality criteria
occur, action in accordance with the EAP in Table 3.4 shall be
carried out.
Table 3.3
Action
and Limit Levels for Air Quality (Construction Dust)
Parameter
|
Action
Level (a)
|
Limit
Level
|
TSP (1-hour
averaged)
|
BL ≤384µg/m3, AL =
(BL×1.3+LL)÷2
BL >384µg/m3, AL = LL
|
500µg/m3
|
Note:
(a) BL = Baseline level, AL = Action
level, LL = Limit level
|
Table 3.4
Event
and Action Plan for Air Quality (Construction Dust)
Event
|
Action
|
ET
|
IEC
|
ER
|
Contractor
|
Action level
being exceeded by one sampling
|
1. Identify the source, investigate the causes of the complaint and
propose remedial measures;
2. Inform Contractor, IEC and ER;
3. Repeat measurement to confirm finding; and
4. Increase monitoring frequency to daily.
|
1. Check monitoring
data submitted by ET;
2. Check the
Contractor’s working method; and
3. Review and advise
the ET and ER on the effectiveness of the proposed remedial measures.
|
1. Notify Contractor.
|
1. Identify the source(s), investigate
the causes of exceedance and propose remedial measures;
2. Implement remedial measures; and
3. Amend working methods
agreed upon with the ER as appropriate.
|
Action level
being exceeded by two or more consecutive sampling
|
1. Identify source;
2. Inform Contractor,
IEC and ER;
3. Advise the
Contractor and ER on the effectiveness of the proposed remedial measures;
4. Repeat
measurements to confirm findings;
5. Increase
monitoring frequency to daily;
6. Discuss with IEC
and Contractor on remedial actions required;
7. If exceedance
continues, arrange meetings with the Contractor, IEC and ER; and
8. If exceedance
stops, cease additional monitoring.
|
1.
Check monitoring data submitted by ET;
2.
Check the Contractor’s working method;
3.
Discuss with ET, ER and Contractor on possible remedial measures;
4.
Advise the ET and ER on the effectiveness of the proposed remedial measures;
and
5. Supervise
the Implementation of remedial measures.
|
1. Confirm receipt of
notification of exceedance in writing;
2. Notify Contractor;
3. Ensure remedial
measures are properly implemented.
|
1. Identify the source and investigate
the causes of exceedance;
2. Submit proposals for remedial measures
to the ER with a copy to ET and IEC within three working days of
notification;
3. Implement the agreed proposals; and
4. Amend the proposal as
appropriate.
|
Limit level
being exceeded by one sampling
|
1. Identify the source,
investigate the causes of exceedance and propose remedial measures;
2. Inform Contractor, IEC, ER, and EPD;
3. Repeat measurement to confirm finding;
4. Increase monitoring frequency to
daily; and
5. Assess the effectiveness of the
Contractor’s remedial actions and keep IEC, EPD and ER informed of the results.
|
1. Check monitoring data submitted by ET;
2. Check the Contractor’s working method;
3. Discuss with ET and Contractor on
possible remedial measures;
4. Advise the ER on the effectiveness of
the proposed remedial measures; and
5. Supervise the implementation of
remedial measures.
|
1. Confirm receipt of notification of
exceedance in writing;
2. Notify the Contractor;
3. Ensure remedial measures are properly implemented.
|
1. Identify source(s) and investigate the
causes of exceedance;
2. Take immediate action to avoid further
exceedance;
3. Submit proposals for remedial measures
to ER with a copy to ET and IEC within three working days of notification;
4. Implement the agreed proposals; and
5. Amend the proposal if
appropriate.
|
Limit level
being exceeded by two or more consecutive sampling
|
1. Notify IEC, ER,
Contractor and EPD;
2. Identify source;
3. Repeat measurement to confirm
findings;
4. Increase monitoring frequency to
daily;
5. Carry out an analysis of the
Contractor’s working procedures to determine possible mitigation to be
implemented;
6. Arrange meetings with IEC and ER to
discuss the remedial actions to be taken;
7. Assess the effectiveness of the Contractor’s
remedial actions and keep IEC, EPD and ER informed of the results; and
8. If exceedance stops, cease additional
monitoring.
|
1. Check monitoring data submitted by the
ET;
2. Discuss amongst ER, ET, and Contractor
on the potential remedial actions;
3. Review the Contractor’s remedial
actions whenever necessary to assure their effectiveness and advise the ER
accordingly; and
4. Supervise the implementation of
remedial measures.
|
1. Confirm receipt of notification of
exceedance in writing;
2. In consultation with the ET and IEC,
agree with the Contractor on the remedial measures to be implemented;
3. Supervise the implementation of
remedial measures; and
4. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated.
|
1. Identify source(s) and investigate the
causes of exceedance;
2. Take immediate action to avoid further
exceedance;
3. Submit proposals for remedial measures
to the ER with a copy to the IEC and ET within three working days of
notification;
4. Implement the agreed proposals;
5. Revise and resubmit proposals if the
problem is still not under control; and
6. Stop the relevant
portion of works as determined by the ER until the exceedance is abated.
|
3.9.1
Mitigation measures for construction phase air quality
impact have been recommended in the EIA Report. All recommended
mitigation measures are detailed in the implementation schedule presented
in Appendix 1.2.
The Contractor shall be responsible for the design and implementation of
these measures.
3.10.1
Regular environmental site inspections and audits at
least once per week should be conducted during the entire construction phase of
the Project to ensure the recommended mitigation measures are properly
implemented. The audit programme serves to verify and keep track of the
implementation status of the recommended mitigation measures and effectiveness
of these mitigation measures.
4
NOISE
4.1.1
The potential construction noise impact and road
traffic noise impact during operation of the Project have been assessed in the
EIA.
4.1.2
Recommendations on construction noise mitigation
measures have been given in the EIA to mitigate the noise impact. A noise
monitoring and audit programme is recommended to be undertaken to confirm the
proposed mitigation measures have been implemented properly.
4.1.3
For road traffic noise impact, mitigation measures
including the provision of low-noise road surfacing (LNRS) have been
recommended to be implemented along some of the Project Roads. Road
traffic noise levels should be monitored at representative Noise Sensitive
Receivers (NSRs), which are in the vicinity of the recommended direct
mitigation measures, during the first year after road opening. The
purpose of the monitoring is to ascertain that the recommended mitigation
measures are effective in mitigating the noise impacts.
4.1.4
In this section, the requirements, methodology,
equipment, monitoring locations, criteria and protocols for the monitoring and
audit of noise impacts during the construction phase and operation phase of the
Project are presented.
4.2
General
Monitoring Requirement
4.2.1
With reference to the Technical Memorandum (TM)
issued under the Noise Control Ordinance (NCO), sound level meters in
compliance with the International Electrotechnical Commission Publications
651:1979 (Type 1) and 804:1985 (Type 1) specifications shall be used for
carrying out the noise monitoring. The accuracy of the sound level meter
shall be checked using an acoustic calibrator generating a known sound pressure
level at a known frequency, immediately prior to and following each noise
measurement. Measurements shall be accepted as valid only if the
calibration level from before and after the noise measurement agrees to be
within 1.0dB(A).
4.2.2
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s.
The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.2.3
The ET is responsible for the provision of the
monitoring equipment. The ET shall ensure that sufficient noise measuring
equipment and associated instrumentation are available for carrying out the
regular impact monitoring and ad hoc monitoring. All the equipment and
associated instrumentation shall be clearly labelled. The location of
equipment installation shall be proposed by the ET Leader and agreed with the
IEC and EPD.
4.2.4
The noise monitoring station shall normally be at a
point 1m from the exterior of the sensitive receivers building façade and be a
position of 1.2m above ground. If there is a problem with access to the
normal monitoring position, an alternative position shall be chosen, and a
correction to the measurements shall be made. For reference, a correction
of +3dB(A) shall be made to the free field measurements. The ET shall
agree with the IEC on the monitoring position and the corrections
adopted. Once the positions for the monitoring stations are chosen, the
impact monitoring shall be carried out at the same positions.
4.3
Monitoring
Parameters of Construction Noise
4.3.1
The construction noise levels shall be measured for
the time period between 07:00 and 19:00 on normal weekdays using 30-minute A-weighted equivalent continuous sound pressure level (Leq(30-min))
as the monitoring parameter, other parameters including L10
and L90 should also be taken for reference.
A sample data record sheet for construction noise
monitoring is shown in Appendix
4.1 for reference.
4.4 Monitoring Locations for Construction Noise
4.4.1
The proposed noise monitoring stations during the
construction phase are shown in Figure 4.1. Details of the proposed noise monitoring stations are summarised
in Table 4.1.
Table 4.1
Proposed Noise Monitoring Stations during the Construction Phase of the Project
Noise
Monitoring Point
|
NSR
ID in
EIA Report
|
Location
|
Monitoring
Period
|
CNM1
|
H1
|
Sam Shing
Temple
|
Works at
Zone 4a, 4b
|
CNM2
|
H5
|
Kam Fai
Garden
|
Works at
Zone 4a
|
CNM3
|
H8
|
Chung Sing
Benevolent Society
Mrs. Aw Boon Haw Secondary School
|
Works at
Zone 4a, 4b
|
CNM4
|
H9
|
Four Gospel
Church
|
Works at
Zone 4b
|
CNM5
|
H11
|
Sam Shing
Estate (Chun Yu House)
|
Works at
Zone 4b, 4c
|
CNM6
|
H12
|
Siu Lun
Court
|
Works at
Zone 4b
|
CNM7
|
L27
|
Tsing Shan
Tsuen
|
Works at
Zone 3a, 3b, 3c, 3d
|
CNM8
|
L31
|
Ju Ching Chu
Secondary School
(Tuen Mun)
|
Works at
Zone 3a, 3b, 3c
|
CNM9
|
L32
|
ICAC
Training Camp
|
Works at
Zone 3a, 3b, 3c
|
CNM10
|
L33
|
Hong Chi
Morninglight School /
Hong Chi Morninghill School
|
Works at
Zone 3a, 3b
|
CNM11
|
L36
|
W.F.B.
Avalokitesvara Nursery School
|
Works at
Zone 3a, 3b, 3e
|
CNM12
|
L37
|
Church of
Christ in China (CCC)
Hoh Fuk Tong Primary School
|
Works at
Zone 3a, 3b
|
CNM13
|
L38
|
Lung Yat
Estate
|
Works at
Zone 3a, 3b
|
CNM14
|
PN1 (a)
|
Proposed
Public Housing Site at Tin Hau Road
|
Works at
Zone 3a, 3b, 3c
|
Note:
a) The construction
of the Project is tentatively to be commenced in mid-2024. The construction
of the planned NSR PN1 is expected to be completed in late-2024. Based on this,
future occupants of NSR PN1 may be affected by the construction of the
Project. Noise monitoring at the NSR PN1 shall be carried out upon
occupation when there is construction works at Zone 3a, 3b and/or 3c.
|
4.4.2
The status and location of NSRs may change after
issuing this manual. If such case exists, the ET Leader should propose
updated monitoring locations and seek approval from IEC and ER, and agreement
from EPD before impact monitoring commences.
4.4.3
When alternative monitoring locations are proposed,
the monitoring locations should be chosen based on the following criteria:
·
Alternative locations
should be similarly exposed to potential noise impacts;
·
It should be close to
the NSRs; and
·
It should be located
where there would be minimal disturbance to the occupants.
4.5
Impact Monitoring for Construction Noise
4.5.1
Construction noise monitoring should be carried out at
the designated monitoring stations when there are Project-related construction
activities being undertaken within 300m radius from the monitoring stations.
An initial guide on the monitoring is to obtain one set of 30-minute
measurement at each station between 07:00 and 19:00 hours on normal weekdays at
a frequency of once per week when construction activities are underway.
4.5.2
If construction works are extended to include works
during the hours of 19:00 to 07:00, and/or percussive piling is to be carried
out, applicable permits under NCO shall be obtained by the Contractor.
The monitoring requirements and conditions, if any, stipulated in the
permits have to be followed.
4.5.3
In case of non-compliance with the construction noise
criteria, more frequent monitoring, as specified in the EAP in Table
4.3 shall be carried out. This additional monitoring shall be
continued until the recorded noise levels are rectified or proved to be
irrelevant to the construction activities.
4.6
Event
and Action Plan for Construction Noise
4.6.1
The Action and Limit levels for construction noise are
defined in Table 4.2. Should non-compliance with
the criteria is identified, action in accordance with the EAP in Table
4.3 shall be carried out.
Table 4.2
Action and Limit Levels for Construction Noise
Noise Sensitive Uses
|
Period of Time
|
Action Level
|
Limit Level
|
Domestic
Premise
|
07:00
to 19:00
on normal weekdays
|
When
one documented complaint is received
|
75dB(A)
|
Place
of Public Worship
|
70dB(A)
|
Education
Institution
|
70dB(A)
(b)
|
Notes:
a) If works are to be carried
out during restricted hours (i.e. 19:00 – 07:00) and/or percussive piling is
to be carried out, the monitoring requirements and the conditions, if any,
stipulated in the CNP issued by the Noise Control Authority shall be
followed.
b) Limit Level reduced to
65dB(A) for schools during school examination periods.
|
Table 4.3
Event and Action Plan for Construction Noise
Event
|
Action
|
ET
|
IEC
|
ER
|
Contractor
|
Action Level
|
1. Notify IEC, ER and Contractor;
2. Carry out the investigation;
3. Report the results of the
investigation to the IEC, ER and Contractor;
4. Discuss with the Contractor and
formulate remedial measures; and
5. Increase monitoring frequency to
check mitigation effectiveness.
|
1. Review the analyzed results submitted
by the ET;
2. Review the proposed remedial
measures by the Contractor and advise the ER accordingly; and
3. Supervise the implementation of
remedial measures.
|
1. Confirm receipt of notification of
failure in writing;
2. Notify the Contractor;
3. Require the Contractor to propose
remedial measures for the analyzed noise problem;
4. Review and
agree on the remedial measures proposed by the Contractor for the analyzed
noise problem; and
5. Ensure remedial measures are
properly implemented.
|
1. Submit noise mitigation proposals to
IEC; and
2. Implement noise mitigation
proposals.
|
Limit Level
|
1. Identify source;
2. Inform IEC, ER, EPD and
Contractor;
3. Repeat measurements to confirm
findings;
4. Increase monitoring frequency;
5. Carry out an analysis of the
Contractor’s working procedures to determine possible mitigation to be
implemented;
6. Inform IEC, ER and EPD on the
causes and actions taken for the exceedances;
7. Assess the effectiveness of the
Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results; and
8. If exceedance stops, cease
additional monitoring.
|
1. Discuss amongst ER, ET, and
Contractor on the potential remedial actions;
2. Review the Contractor's remedial
actions whenever necessary to assure their effectiveness and advise the ER
accordingly; and
3. Supervise the implementation of
remedial measures.
|
1. Confirm receipt of notification of
failure in writing;
2. Notify the Contractor;
3. Require the Contractor to propose
remedial measures for the analyzed noise problem;
4. Review and
agree on the remedial measures proposed by the Contractor for the analyzed
noise problem;
5. Ensure remedial measures are
properly implemented; and
6. If exceedance continues, consider
what portion of the work is responsible and instruct the Contractor to stop
that portion of work until the exceedance is abated.
|
1. Take immediate action to avoid
further exceedance;
2. Submit proposals for remedial
actions to IEC within 3 working days of notification;
3. Implement the agreed proposals;
4. Resubmit proposals if the problem is
still not under control; and
5. Stop the relevant portion of works
as determined by the ER until the exceedance is abated.
|
4.7
Noise
Parameters for Operation Road Traffic Noise
4.7.1
Notwithstanding the prediction that the NSRs will not
be subject to adverse noise impact during the operational phase of the Project
with the implementation of the proposed noise mitigation measures, noise
monitoring should be carried out during the first year after opening to ensure
the effectiveness of the recommended mitigation measures.
4.7.2
The traffic noise levels should be measured twice at
six-month intervals within the first year upon operation of the Project.
Measurements should be made in terms of the A-weighted L10 over
three half-hour periods during the peak traffic hour, other parameters
including Leq and L90 should also be taken for reference.
4.8
Monitoring
Locations for Road Traffic Noise
4.8.1 As shown in Table 4.4 and Figure 4.2, three designated monitoring stations are selected for the operational
noise monitoring.
Table 4.4
Proposed Noise Monitoring Stations for Road Traffic Noise
Noise Monitoring Point
|
NSR ID in
EIA Report
|
Location
|
Proposed Mitigation Measures Nearby
|
TNM1
|
L30
|
Yan
Chai No.2 Hospital Secondary School
|
LNRS
|
TNM2
|
L31
|
Ju Ching Chu Secondary
School (Tuen Mun)
|
LNRS
|
TNM3
|
L37
|
The
Church of Christ in China Hoh Fuk Tong Primary School
|
LNRS
|
4.8.2
The monitoring locations should be selected according
to the following criteria:
·
They should be at NSRs in the vicinity of recommended
direct technical remedies; preferably, there should be one representative
monitoring location near proposed mitigation measure (i.e., LNRS);
·
One high floor and one medium floor monitoring point
should be chosen at each location as far as practicable; and
·
Selected monitoring locations should allow monitoring
to be done twice within one year after the implementation of the mitigation
measures during the operation of the Project.
4.8.3
The status and locations of the NSRs may change after
this Manual is issued. If such cases exist, the ET Leader should propose
updated monitoring locations and seek approval from IEC and ER, and agreement
from EPD before commencement of traffic noise monitoring.
4.8.4
When alternative monitoring locations are proposed,
the monitoring locations should be chosen based on the following criteria:
·
Alternative locations should be similarly exposed to
potential noise impacts;
·
It should be close to the NSRs; and
·
It should be located where there would be minimal
disturbance to the occupants.
4.9 Impact Monitoring for Operation Road Traffic Noise
4.9.1
The operational noise monitoring should be carried out
at a distance of 1m from the openable window and 1.2m above the floor level of
the noise sensitive receivers identified. The ET Leader should agree with
the IEC on any necessary corrections adopted.
4.9.2
Traffic noise monitoring should be
carried out at all the designated traffic noise monitoring stations. The
following is an initial guide on the traffic noise monitoring requirements
during the operational phase:
·
One set of
measurements at the morning traffic peak hour on a normal weekday;
· One set of measurements at the
evening traffic peak hour on a normal weekday;
· A concurrent census of traffic flow and
percentage of heavy vehicles shall be conducted for the Project roads and the
existing road network in the vicinity of each measuring point;
· Average vehicle speed estimated for
Project road and the existing road network in the vicinity of each measuring
point; and
· The two sets of monitoring
data should be obtained within the first year of operation.
4.9.3
Measured noise levels should be compared with the
predicted noise levels by applying appropriate conversion corrections to allow
for the traffic conditions at the time of measurement. A sample data
record sheet for traffic noise monitoring during the operational phase is shown
in Appendix 4.2
for reference.
4.9.4
Each set of measurements shall include three
measurements of 30-minute. The parameters L10, Leq,
L90 and Lmax shall be recorded for data
auditing and reference.
4.9.5
The ET shall prepare a monitoring plan for the purpose
of assessing the accuracy of the traffic noise predictions by comparing the noise impact predictions with the actual impacts. The
monitoring plan shall be submitted to EPD at least six months before the
operation of the proposed roads under the Project. The monitoring plan shall
include monitoring locations, monitoring schedules, methodology of noise
monitoring such as noise measurement procedures, traffic counts and speed
checks, and methodology of comparison with the predicted levels. The ET
shall follow the monitoring plan unless with prior justifications. Monitoring
details and results including the comparison between the measured noise levels
and the predicted levels should be recorded in a report to be deposited with
EPD within one month of the completion of the monitoring. The report
should be certified by the ET Leader and verified by the IEC before submitting
it to EPD.
4.10 Event and Action Plan for Road Traffic Noise
4.10.1
The measured road traffic noise levels should be
compared with the predicted results and the predicted traffic flow conditions
(calculated noise levels based on concurrent traffic census obtained). In
case discrepancies are observed, explanations should be given to justify the
discrepancies.
Construction Phase
4.11.1
In order to reduce the noise impact of construction
site activities on nearby NSRs, the following mitigation measures have been
considered:
·
Use of quiet construction method/ Quality Power
Mechanical Equipment (QPME);
·
Use of Noise Barrier, Noise Insulation Fabric and
Noise Enclosure;
·
Good site practices;
·
Scheduling of PME/construction activities; and
·
Construction noise management plan.
Use of Quiet Construction Method / Quality Powered Mechanical Equipment
4.11.2 For sheet piles installation, “Press-in” method is more preferable than
the use of traditional vibratory hammer due to lesser noise and vibration
impact generated. According to the EPD web page, the noise emission of
“Press-in” method is 69 dB(A) at 7 m from the silent piler, which is more than
20 dB(A) quieter than the vibratory hammer. The Contractor should prioritise
the use of “Press-in” method over the traditional method if site conditions
allowed. However, “Press-in” method would also have its own limitations
and thus it should not restrict Contractor to fully adopt the “Press-in” as
long as the Contractor can demonstrate the full compliance of daytime noise
criteria by using vibratory hammer with proper mitigation measures.
4.11.3 Traditional demolition method relies on excavator mounted hydraulic
breaker to break concrete structures, however, operating hydraulic breaker
would inevitably generate significant noise impact to the NSRs nearby. As
confirmed by Project Engineer, it is feasible to adopt quieter demolition
equipment (e.g. hydraulic crusher) in some activities as a mitigation measure.
Using hydraulic crusher would create lesser noise impact to the NSRs.
The Contractor should, subject to the actual site condition, proactively
adopt quieter demolition equipment to carry out the demolition works, where
practicable. Apart from the above, the Contractor will be required to
review and adopt quieter construction methods or technologies to further reduce
the noise at its source as far as they are technically feasible and applicable
for the proposed construction works. These include non-explosive chemical
expansion agent, high pressure water jetting, hand-held concrete crusher,
quieter type blade saw, and quieter type wire saw / diamond wire saw. These
quieter equipment / construction methods, while not adopted in the assessment,
shall be considered during the design, tendering and implementation stage of
the construction works as appropriate.
4.11.4 Apart from the above, the Contractor
will be required to review and adopt quieter construction methods or
technologies to further reduce the noise at its source as far as they are
technically feasible and applicable for the proposed construction works. These
include non-explosive chemical expansion agent, high pressure water jetting,
hand-held concrete crusher, quieter type blade saw, and quieter type wire saw /
diamond wire saw. These quieter equipment / construction methods, while not
adopted in the assessment, shall be considered during the design, tendering and
implementation stage of the construction works as appropriate.
4.11.5
The use of QPME was considered to be a practicable
means to mitigate the construction noise impact. A QPME is defined as a
PME having an actual SWL lower than the value specified in the GW-TM. The
contractors may adopt alternative QPME as long as it can demonstrate that they
would not result in construction noise impacts worse than those predicted in
this assessment.
Use of Noise Barrier, Noise Insulation Fabric and Noise Enclosure
4.11.6 Noise barriers or enclosures would be erected to provide screening from
the construction plant. Noise barriers will become more effective when
located immediately adjacent to the PME and be moved concurrently with the PME
along the work site. The Contractor should be responsible for design of the
noise barrier/enclosure with due consideration given to the size of the PME and
the requirement of intercepting the line of sight between the NSRs and
PME. A typical design which has been used locally is a wooden framed
barrier with a small cantilevered upper portion of superficial density no less
than 14kg/m2 on a skid footing with 25mm thick internal sound
absorptive lining. Noise barriers should be erected/built in such a way with no
openings or gaps on the joints, and should be long enough (e.g. at least five
times greater than its height) or be bent around the noise sources to ensure
the effectiveness. A cantilevered top cover would be required for the noise
barriers to achieve screening benefits at the upper floors of NSRs. It is
anticipated that suitably designed noise barriers/enclosures could achieve at
least 5 to 10 dB(A) reduction for movable and stationary plants, respectively.
4.11.7
In addition, noise insulation fabric (the Fabric)
would be installed for PME such as piling rigs and drilling rigs and the Fabric
should be lapped such that there would be no opening or gaps on the joints.
Good Site Practices
4.11.8 It is also recommended to implement good site practices as far as
practicable so as to further reduce the noise impact at NSRs. The following
good site practices should be followed during the construction phase.
· Only well-maintained plant should be
operated on-site and should be served regularly during construction period;
· Mobile plant, if any, should be
sited as far from NSRs as possible;
· Use of site hoarding as a noise
barrier to screen noise at low level NSRs;
· Machines and plant that may be in
intermittent use should be shut down between works periods or should be
throttled down to a minimum.
· Silencers or mufflers on
construction equipment should be utilized and be properly maintained during
construction;
· Plant known to emit noise strongly
in one direction should, wherever possible, be orientated so that the noise is
directed away from the nearby NSRs; and
· Material stockpiles should be
effectively utilized, wherever practicable, in screening noise from on-site
construction activities.
Scheduling of Construction Works
4.11.9
The Contractor shall liaise with the school
representative(s) to obtain the examination schedule so as to avoid noisy
construction activities during the school examination period. Scheduling
construction works outside the school examination period to less intrusive
periods or restricting critical works areas would reduce the overall
construction noise impacts at the NSRs and ensure compliance with the
construction noise criterion. In addition, since NSRs H1 and H9 are
located in close vicinity to the works area of the Project and Cycle
Track between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat), the Contractor
will continuously liaise with the contractor of the Cycle Track project to
avoid concurrent operation of PMEs.
Construction Noise Management Plan
4.11.10 A
construction noise management plan should be prepared during the design /
tendering and implementation stage of the construction works, to verify the
inventory of noise sources, assess the effectiveness and practicality of all
identified measures and update the construction noise impact assessment and
proposed noise mitigation measures as necessary.
4.11.11 The
implementation schedule for the recommended mitigation measures is presented
in Appendix 1.2.
Operation Phase
Road Traffic Noise
4.11.12 Direct noise mitigation measures including LNRS have been proposed
to alleviate the traffic noise impact. Table 4.5 summarise the
proposed noise mitigation measures.
Table 4.5
List of Proposed Noise Mitigation Measures
Proposed Noise
Mitigation Measures
|
Location
|
Approximate Length (m)
(rounded off to the nearest 10m)
|
LNRS
|
Proposed
slip road LFRSR NB
|
470m
|
LNRS
|
Proposed
slip road LFRSR SB
|
670m
|
4.11.13 In addition to the LNRS, 1.8m
parapet wall is proposed along the western side of LFRSR NB and 0.5m parapet
wall is proposed along remaining sides of LFRSR NB and SB as standard
provisions.
4.11.14 After implementing the proposed LNRS, the predicted overall noise levels
at all NSRs comply with the relevant noise criteria. Based on the
criteria as stated in Section 4.6.14 of the EIA Report, the eligibility test
for indirect noise mitigation measures is conducted. Details of the
eligibility test are given in Appendix 4.14 of the EIA Report.
As no representative existing NSRs would fall within all three testing
criteria, it is considered that no indirect mitigation measures would be
required.
4.11.15 The
feasibility, practicability, programming and effectiveness of the above
mitigation measures have been reviewed and confirmed by the engineer.
Environmental reviews shall be conducted at later design stage to review
and ascertain the proposed provisional noise mitigation measures taking into
account the latest design standard at that time for the suitability and
application of the LNRS materials.
4.11.16 The implementation schedule for the recommended mitigation measures is
presented in Appendix 1.2.
4.12.1
Regular environmental site inspections and audits
during the construction phase of the Project should be conducted at least once
per week to ensure proper implementation of mitigation measures and good site
practices as listed in Appendix
1.2 and the noise control requirements stated in EPD’s "Recommended
Pollution Control Clauses for Construction Contracts” to further minimise
the potential noise nuisance during the construction phase.
5
WATER QUALITY
5.1.1
Potential water pollution sources from the
construction and operation of the Project have been identified including
construction runoff, sewage, possible contamination due to oil and grease, use
of fertilizers, pesticides and waste construction materials. With the
implementation of the recommended mitigation measures, no unacceptable water
quality impacts would be expected. No water quality monitoring is therefore
considered necessary. Regular site inspections and audits are recommended
during the construction phase to ensure the recommended mitigation measures are
properly implemented.
5.2.1
Mitigation measures for water quality control during
the construction phase have been recommended in the EIA Report. The
Contractor should be responsible for the design and implementation of these
measures. Recommended mitigation measures to minimise the adverse impacts
on water quality during the construction activities are listed in the
implementation schedule given in Appendix
1.2.
5.3
Construction
Site Audits
5.3.1
Regular site inspections and audits should be
conducted to ensure that the recommended mitigation measures are properly
implemented during the construction phase of the Project. It can also
provide effective control of any malpractices and therefore achieve continual
improvement of environmental performance on site.
Site Inspections
5.3.2
Regular site inspections shall be carried out by the
ET at least once per week and shall be based on the mitigation measures for
water pollution control recommended in Appendix 1.2. If the recommended mitigation measures are not fully or properly
implemented, the deficiency shall be recorded and reported to the site
management. Suitable actions are to be carried out to:
(i) Investigate the problems
and the causes;
(ii) Issue action notes to
the Contractor who is responsible for the works;
(iii) Implement remedial and corrective
actions immediately;
(iv) Re-inspect the site conditions upon
completion of the remedial and corrective actions; and
(v) Record the event and
discuss it with the Contractor for preventive actions.
Compliance Audits
5.3.3
Monitoring of the treated effluent quality from the
Works Areas is required during the construction phase of the Project. The
monitoring shall be carried out at the pre-determined discharge point.
Compliance audits are to be undertaken to ensure that a valid discharge licence
has been issued by EPD prior to the discharge of effluent from the Project
site. The monitoring frequency and parameters specified in the discharge
licence shall be followed during the monitoring. All monitoring
requirements shall be approved by EPD. The audit results reflect whether
the effluent quality complies with the discharge licence requirements. In
case of non-compliance, suitable actions shall be undertaken to:
(i) Notify the site
management about the non-compliance;
(ii) Identify the sources of
pollution;
(iii) Check the implementation status of
the recommended mitigation measures;
(iv) Investigate the operating
conditions of the on-site treatment systems;
(v) Implement corrective and
remedial actions to improve the effluent quality;
(vi) Increase monitoring frequency until
the effluent quality complies with the discharge licence requirements; and
(vii) Record
the non-compliance and propose preventive measures.
6
WASTE MANAGEMENT
6.1.1
Construction and Demolition (C&D) materials,
chemical waste and general refuse from the workforce would be
generated during the construction phase. This section sets out the
handling, recycling, storage, transportation and disposal measures for these
wastes which are recommended to avoid and minimise potential adverse impacts
associated with waste arising from the construction of the Project.
6.1.2
It is expected that no waste will be generated as a
result of the operation of the Project, and thus there would be no adverse
environmental impacts related to waste management during the operation phase of
the Project. Monitoring and audit programme for the operation phase of
the Project would not be required.
6.2 Waste Management Approach
Management of Waste Disposal
6.2.1
In accordance with the Waste Disposal (Charges
for Disposal of Construction Waste) Regulation, the Contractor should open
a billing account with the EPD. Every construction waste or public
fill load to be transferred to the Government waste disposal facilities, namely
public fill reception facilities, construction waste sorting facilities, and
landfills will require a valid “chit” which contains information of the account
holder (the Contractor) to facilitate waste transaction recording and billing
to the waste producer.
6.2.2
A Construction and Demolition Material Management Plan
(C&DMMP) should be prepared in accordance with Section 4.1.3 of Chapter 4
of Project Administration Handbook (PAH) for Civil Engineering Works (2020
Edition) and submitted to Public Fill Committee (PFC) for approval.
6.2.3
Inert C&D materials generated from the Project
will be transferred to Tuen Mun Area 38 Fill Bank (TMFB), or
other public fill reception facilities, managed by Civil Engineering and
Development Department (CEDD), while the non-inert C&D materials, after
segregation, will be sent to West New Territories Landfill (WENT) or West New
Territories Landfill Extension (WENTX), or other waste disposal facilities,
managed by the EPD.
6.2.4
A trip-ticket system will also be established in
accordance with DevB TC(W) No.6/2010 to monitor the disposal of
construction waste at landfill and to control fly-tipping. In addition,
all dump trucks should be equipped with GPS or equivalent system for monitoring
of their transportation routes and parking locations to prohibit illegal
dumping and landfilling of C&D materials. The Contractor should maintain
a recording system to record the amount of C&D materials generated,
recycled and disposed of at the disposal sites as well as the transportation
routing and parking locations of the dump trucks. The trip-ticket system
and the abovementioned recording system will be included as part of the
contractual requirements and implemented by the Contractor(s).
6.2.5
As per recommendation under ETWB TC(W) No. 19/2005,
a WMP, with details of the amount of waste generated, recycled and disposed of
(including the disposal sites), will be established and implemented during the
construction phase as part of the EMP. The Contractor will be required to
prepare the EMP and submit it to the Engineer/ ER under the Contract for
approval prior to implementation.
Approach to Reduce Waste Generation
Construction and Demolition
(C&D) Materials
6.2.6
C&D materials generated from the construction
works of the Project comprise both inert C&D materials (i.e. excavated
soil, rock, broken concrete) and non-inert C&D materials (i.e. vegetation,
wood, plastics, packaging materials, etc). The inert C&D
materials will be segregated from other non-inert C&D materials and be
sent to TMFB, or other public fill reception facilities. The non-inert C&D
materials will be further segregated into recyclable materials, such as
cardboard, carton box, waste paper and scrap metal for collection by recyclers,
and non-recyclable materials, such as waste timber and packaging materials,
which will be disposed of at WENT/WENTX, or other waste disposal facilities.
General Refuse
6.2.7
General refuse will be generated from daily site
office operations and workforce. Recycling bins should be provided
at strategic locations, such as the entrance of the site office to facilitate
the recovery of aluminium cans and waste paper generated from the
Site. Materials collected in the recycling bins should be collected
by or sold to local recyclers.
Management of Chemical Waste
6.2.8
Chemical wastes likely to be generated from the construction
of the Project may include residual paints and solvents and used lubricant oil
from maintenance of the construction plant. It is anticipated that the
quantity of chemical waste to be generated will be small and in the order of a
few hundred litres per month during the construction phase. These
chemical wastes will be stored and disposed of in an appropriate manner, as
outlined in the Waste Disposal (Chemical Waste) (General) Regulation and
the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes.
6.2.9
The Contractor should register as a chemical waste
producer with the EPD, and handle the chemical waste in accordance with
the Code of Practice on the Package, Labelling and Storage of Chemical
Wastes. A brief summary of the site arrangement should be as
follows:
Storage Containers
·
Be suitable for the
substance they are holding, resistant to corrosion, maintained in a good
condition, and securely closed;
·
Have a capacity of less
than 450L unless specifications have been approved by the EPD; and
·
Display a label in
English and Chinese in accordance with instructions prescribed in Schedule 2 of
the Regulations.
Storage Area
·
Be clearly labelled and
used solely for the storage of chemical waste;
·
Be enclosed on at least
three sides;
·
Have an impermeable
floor and bunding, of a capacity to accommodate 110% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area, whichever is the greatest;
·
Have adequate
ventilation;
·
Be covered to prevent
rainfall entering (with water collected within the bund be disposed of as
chemical waste when necessary); and
·
Be arranged so that
incompatible materials are appropriately separated.
Disposal
·
Be collected by a
licensed chemical waste collector; and
·
Be disposed/transferred
to a facility licensed to receive chemical waste, such as Chemical Waste
Treatment Facility (CWTF) at Tsing Yi or other chemical waste recyclers.
6.3.1
At the commencement of the construction works,
training should be provided to workers on the concepts of site cleanliness and
appropriate waste management procedures, including waste reduction, reuse and
recycling.
6.4.1
In order to review the good site practices of waste
management, regular environmental site inspections and audits should be carried
out by the ET at least once per week to check whether the Contractor has
implemented the recommended good site practices and other mitigation measures. The
inspection should look at all aspects of on-site waste management practices
including waste generation, storage, recycling, transport and
disposal. Apart from site inspection, documents including licences,
permits, disposal and recycling records should be reviewed and audited for
compliance with the legislation and Contract
requirements. Designated staff of the Contractor responsible for
resource allocation, staff training and controlling the relevant documents will
also be interviewed to review the effectiveness of site management.
Good Site Practice
6.5.1
Under the condition of good site practices are
strictly followed, it is anticipated that no adverse waste management-related
impacts would arise. Recommendations for good site practices during
the construction activities include:
·
Nomination of approved
personnel, such as a site manager, to be responsible for the implementation of
good site practices, arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site;
·
Training of site
personnel in site cleanliness, appropriate waste management procedures,
including chemical waste handling procedures, and concepts of waste reduction,
reuse and recycling;
·
Provision of sufficient
waste disposal points and regular collection for disposal;
·
Appropriate measures to
minimise windblown litter and dust during the transportation of waste by either
covering trucks or by transporting wastes in enclosed containers;
·
Separation of chemical
wastes for special handling and appropriate treatment at the CWTF;
·
Regular cleaning and
maintenance programme for drainage systems, sumps and oil interceptors;
·
Implementation with a
recording system for the amount of wastes generated, recycled and disposed
(including the disposal sites; should be proposed; and
·
A waste management plan
(WMP) should be prepared in accordance with ETWB TC No. 19/2005 and
submitted to the ER for approval.
Waste Reduction Measures
6.5.2
Good management and control can prevent the generation
of a significant amount of waste. Waste reduction is best achieved
at the planning and design stage, as well as by ensuring the implementation of
good site practices. Recommendations to achieve waste reduction
include:
·
Segregation and storage
of different types of waste in different containers, skips or stockpiles to
enhance the reuse or recycling of material and their proper disposal;
·
Encourage collection of
aluminium cans and waste paper by individual collectors during construction
with separate labelled bins being provided to allow the segregation of these
wastes from other general refuse generated by the workforce;
·
Any unused chemicals
and those with remaining functional capacity be recycled as far as possible;
·
Use of reusable non-timber
formwork to reduce the amount of C&D materials;
·
Before disposal of
construction waste, wood, steel and other metals should be separated, to the
extent practical for re-use and/or recycling to reduce the quantity of waste to
be disposed to the landfills;
·
Proper storage and site
practices to reduce the potential for damage or contamination of construction
materials; and
·
Plan and stock
construction materials carefully to reduce the amount of waste generated and
avoid the unnecessary generation of waste.
6.5.3
Waste management approach recommended in the EIA Study
is outlined in Appendix 1.2.
6.5.4
In the event of complaints, or non-compliance/area of
improvement is observed, the ET and the Contractor should be responsible for
reviewing the effectiveness of these mitigation measures and for proposing to
ER for approval, designing and implementing alternative or additional
mitigation measures as appropriate.
7
LAND CONTAMINATIOn
7.1.1
The land contamination assessment has examined the
potential contaminating land uses within the Project area and investigated any
potential land contamination impacts arising from the Project.
7.1.2
Based on the site appraisal, no adverse land
contamination impact arising from Project is anticipated. No EM&A
programme is therefore required.
8
ECOLOGY
8.1.1
Potential ecological impacts arising from the
construction and operational phases of the Project were assessed in the EIA
Report. Mitigation measures have been recommended to minimise the potential
impacts to the nearby sensitive habitats and associated wildlife. With the
implementation of appropriate mitigation measures, no unacceptable adverse
residual impacts would be anticipated.
Impact
avoidance
8.2.1
No site or habitat of conservation importance would be
directly impacted. Direct impacts on the flora and fauna species of
conservation importance would also be avoided. Direct impacts on the Tai
Lam Country Park (TLCP) which is located uphill and some distance away from the
Project Site of the proposed Tuen Mun Road / Hoi Wing Road Slip Road (HWRSR) is
also avoided. In the subsequent stage of the Project, any adjustment in Project
Site shall take into consideration of the location of the Country Park and
avoid encroaching onto it.
Minimisation
Minimising habitat and tree loss
8.2.2
Mixed woodland and semi-natural watercourse within the
HWRSR site but outside the road layout will be retained during the construction
phase, which could reduce the ecological impact brought by temporary loss of
these habitats. Efforts will also be made to minimise tree loss brought by the
Project as far as technically feasible during the detailed design stage of the
Project. Temporary loss of plantation affected by the Project will be
reinstated by compensatory planting. Transplantation and provision of
compensation planting is provided in the Compensatory Planting Plan in Appendix
9.2 of EIA.
Minimising indirect disturbance
impacts
Construction Site Runoff
8.2.3
During the construction phase, site runoff would need
to pass through sedimentation tanks to reduce the concentration of suspended
sediment. In accordance with the Practice Note for Professional Persons
on Construction Site Drainage, Environmental Protection Department, 1994
(ProPECC PN 1/94), best management practices should be implemented on site as
far as practicable to control site runoff and drainage at all work sites during
construction, so that the treated runoff will be discharged to public drainage
system in compliance with the WPCO. Construction effluent, site run-off
and sewage should be properly collected and/or treated. Wastewater from a
construction site should be managed. Proper locations for discharge
outlets of wastewater treatment facilities well away from the natural
streams/rivers should be identified. Effluent monitoring should be
incorporated to make sure that the discharged effluent from construction sites
meets the effluent discharge guidelines. The best practices are detailed
in Section 5 – Water Quality.
Good Site Practices
8.2.4
Standard
site practices listed as follows would be implemented to minimise potential
impacts, including dust, noise and site runoff, on the surrounding environment.
Specific good site practices related to air, noise and water are also specified
in the relevant EIA chapters.
· Regular checking should be
undertaken to ensure that the work site boundary is not exceeded and that no damage
occurs to surrounding areas;
· Implementation of mitigation
measures specified in ProPECC PN 1/94 to control site runoff and drainage
during construction;
· Implementation of noise control
measures to reduce impacts of construction noise to wildlife habitats adjacent
works area;
· Implementation of dust control
measures at all construction sites to minimise dust nuisance to adjacent
wildlife habitats during construction activities;
· Construction debris and spoil should
be covered up and/or properly disposed of as soon as possible to avoid being
washed into nearby waterbodies by rain;
· Good site practice and site
precautionary measures will also be implemented to avoid the potential impact
due to site runoff. Construction effluent, site runoff and sewage should be
properly collected and/or treated. Wastewater from a construction site should
be managed with the following approach in descending order;
· Proper locations for discharge
outlets of wastewater treatment facilities well away from the natural
streams/rivers should be identified;
· Effluent monitoring should be
incorporated to make sure that the discharged effluent from construction site
meets the effluent discharge guidelines; and
· Supervisory staff should be assigned
to station on site to closely supervise and monitor the works.
Mitigation
Minimisation of bird collision
8.2.5 In order to minimise bird collision
due to the re-provided noise barriers along the new roads, bird friendly design
should be adopted for the noise barriers, such as using falcon sticker and
tinted materials. Guidelines on Design of Noise Barriers (EPD & HyD,
2003) and Practice Notes No. BSTR/PN/003 (Revision E) Noise Barriers with
Transparent Panels (HyD, 2020) could be referred for the design of the noise
barrier to avoid and minimise bird mortality from collision.
Compensatory
tree planting
8.2.6
The loss of small area of mixed woodland should be
mitigated by compensatory tree planting, which is detailed in Section 9 - Landscape and Visual.
8.3.1
Regular site inspections and audits (i.e. at least
once per week) will serve to check the implementation status of the mitigation
measures and good practices recommended in the EIA report.
9
LANDSCAPE AND VISUAL
9.1.1
The EIA Report has recommended landscape and visual
mitigation measures for the construction and operation phases of the Project.
This section defines the audit requirements to confirm the recommended
landscape and visual impact mitigation measures are effectively implemented.
9.2.1
The landscape and visual mitigation measures should be
incorporated in the detailed design. The mitigation measures during
construction and operation phases as recommended in the EIA Report are
presented in Appendix 1.2. Where feasible, the construction phase mitigation measures should be
implemented as early as possible in order to minimise the landscape impacts in
the construction stage while the mitigation measures for the operation phase
should be adopted during the detailed design and be built as part of the
construction works so that they are in place before commissioning of the
Project.
9.2.2
Any potential conflicts among the proposed mitigation
measures, the Project works, and operational requirements should also be
identified and resolved at early stage. Any changes to the mitigation measures
should be incorporated in the detailed design.
9.3.1
Site audits should be undertaken during the
construction phase and the 12-month establishment period (operation phase) to
check that the proposed landscape and visual mitigation measures are properly
implemented and maintained as per their intended objectives. Site audit for the
off-site woodland compensation should be carried out throughout the agreed
establishment period with LCSD and HyD.
9.3.2
The ET shall audit the implementation of landscape
construction works particularly during site clearance operations when the
proposed tree felling and transplanting will take place and subsequent tree
maintenance operations and planting works.
9.3.3
Site inspections should be undertaken by the ET at
least once every month during the construction period, and once every two
months for the 12-month establishment period during operation phase.
10
CULTURAL HERITAGE
10.1.1
Potential cultural heritage impacts arising from the
construction phase of the Project were identified and assessed in the EIA
Report. With the implementation of the recommended mitigation measures,
no unacceptable cultural heritage impacts would be expected.
10.1.2
Potential cultural heritage impact arising from the
operation phase of the Project is not anticipated. No mitigation
measures, monitoring and audit are considered necessary during the operation
phase of the Project.
10.2.1
As a precautionary measure, the project proponent and
his/her contractor are required to inform AMO immediately when any antiquities
or supposed antiquities under the Antiquities and Monuments Ordinance (Cap. 53)
are discovered during the course of works.
10.2.2
Design proposal, method of works and choice of
machinery should be targeted to minimise potential vibration impact on Shing
Miu (GB-01) and seven other associated building structures. As a precautionary measure, it is recommended that
during the pre-construction phase of the Project and implemented by the works
contractor, a baseline condition survey and baseline vibration impact
assessment be conducted for Shing Miu and the associated building structures by
a qualified building surveyor or qualified structural engineer to evaluate the
necessary construction monitoring and structural strengthening measures for
AMO's consideration.
10.2.3
The temple owner/ manager of the Shing Miu compound
shall be consulted to agree on appropriate mitigation measures to be adopted for
the abandoned Earth God Shrine and access to Shing Miu during the construction
phase of the Project.
10.2.4
The works area shall be reviewed and refined to
exclude the Arch of the Shing Miu compound to avoid the potential impact.
During the construction phase of the Project adjacent to the Arch, it shall be
physically fenced off from the works area to minimise potential physical
disturbance of construction works towards the Arch.
10.2.5
If there are any buildings/structures both at grade
level and underground which were built in or before 1969, the project proponent
is required to alert AMO in an early stage or once identified.
10.2.6
The above mitigation measures for cultural heritage
during the construction phase have been recommended in the EIA Report.
Recommended mitigation measures on cultural heritage during the construction
phase are detailed in the implementation schedule given in Appendix 1.2.
10.2.7
Potential cultural heritage impact arising from the
operation phase of the Project is not anticipated. No mitigation measure
is considered necessary during the operation phase of the Project.
10.3.1
During the pre-construction phase of the Project and
implemented by the works contractor, a baseline condition survey and baseline
vibration impact assessment be conducted for Shing Miu (GB-01) and the
associated building structures by a qualified building surveyor or qualified
structural engineer to define the vibration limit and to evaluate the necessary
construction monitoring and structural strengthening measures for AMO's
consideration.
10.3.2
Regular site inspections and audits should be carried
out by the ET at least once per week during the construction phase to
ensure that the recommended mitigation measures related to cultural heritage
listed in Appendix 1.2 are properly implemented.
11
Environmental AUDIT
11.1.1
Site inspections provide a direct means to assess and
confirm that the Contractor’s environmental protection and pollution control
measures are in compliance with the contract specifications. The site
inspection will be undertaken routinely by the ET to verify that appropriate
environmental protection and pollution control mitigation measures are properly
implemented in accordance with the EIA recommendations. In addition, the
ET will be responsible for defining the scope of the inspections, detailing any
deficiencies that are identified and reporting any necessary action and/or
additional mitigation measures that were implemented as a result of the
inspection.
11.1.2
Site inspections should be carried out at least once
per week. The areas of inspection should not be limited to the general
environmental conditions in the vicinity of the site and the pollution control
and mitigation measures within the site; the environmental conditions outside
the site area which are likely to be affected, directly or indirectly, by site
activities. The ET Leader should make reference to the following
information in conducting the inspections:
·
The EIA Study and
EM&A recommendations on environmental protection and pollution control
mitigation measures;
·
Ongoing results of the
EM&A programme;
·
Works progress and
programme;
·
Individual works method
statements which should include proposals on associated pollution control
measures;
·
Contract specifications
on environmental protection;
·
Relevant environmental
legislation and guidelines; and
·
Previous site
inspection results undertaken.
11.1.3
The Contractor will update the ET with relevant
information on the construction works prior to carrying out the site
inspections. The site inspection results and their associated
recommendations on improvements to the environmental protection and pollution
control works should be submitted to the IEC and the Contractor in two working
days, for reference and for taking immediate action. Should actions be
necessary, the ET will follow up with recommendations on improvements to the
environmental protection and pollution control works and will submit these
recommendations in a timely manner to the IEC and the Contractor. They
will also be presented, along with the remedial actions taken, in the monthly
EM&A report. The Contractor should follow the procedures and
time-frames stipulated in the environmental site inspection for the
implementation of mitigation proposal. An action reporting system will be
formulated and implemented to report on any remedial measures implemented
subsequent to the site inspections.
11.1.4
Ad hoc site inspections will also be carried out by
the ET and site audits by the IEC if significant environmental issues are
identified. Inspections may also be required subsequent to receipt of an
environmental complaint, or as part of the associated investigation work, as
specified in the Action Plan for environmental monitoring and audit.
11.2 Compliance with Legal and
Contractual Requirements
11.2.1
The Contractor should comply with contractual
environmental protection and pollution control requirements, Hong Kong’s
environmental protection and pollution control laws.
11.2.2
In order that the works are in compliance with the
contractual requirements, all works method statements (where relevant to
environmental measures) submitted by the Contractor to the ER for approval
should also be sent to the ET Leader for vetting to see whether sufficient
environmental protection and pollution control measures have been included.
11.2.3
The ET shall review all the progress and programme of
the works to check that relevant environmental laws have not been violated, and
that any foreseeable potential for violating the laws can be prevented.
11.2.4
The Contractor shall regularly copy inspection
relevant documents to the ET Leader so that works checking and auditing process
could be carried out effectively. The relevant documents are expected to
include the updated work progress reports, the updated works programme, the
application letters for different licences/permits under the environmental
protection laws, all valid licences/permits and environmental related
records. The site diary should also be available for the ET Leader’s
inspection upon his request.
11.2.5
After reviewing the documentation, the ET Leader shall
advise the IEC and the Contractor of any non-compliance with the contractual
and legislative requirements on environmental protection and pollution control
for them to take follow-up actions. If the ET Leader’s review
concludes that the current status on licence/permit application and any
environmental protection and pollution control preparation works is
incompatible with the works programme or may result in a potential violation of
environmental protection and pollution control requirements, he should also advise
the Contractor and the ER in due course.
11.2.6
Upon receipt of the advice, the Contractor should
undertake immediate action to remedy the situation. The ER should
follow up to ensure that appropriate action has been taken by the Contractor in
order to satisfy contractual and legal requirements.
11.3
Environmental Complaints
11.3.1
Complaints shall be referred to the ET Leader for action.
The ET Leader shall undertake the following procedures upon receipt of
any environmental complaint:
(i) Log the complaint and date of
receipt onto the complaint database and inform the IEC immediately;
(ii) Investigate the complaint to
determine its validity, and assess whether the source of the problem is due to
works activities;
(iii) Identify mitigation measures in
consultation with the IEC if a complaint is valid and due to works;
(iv) Advise the Contractor if mitigation measures
are required;
(v) Review the Contractor's response to
identified mitigation measures and the updated situation;
(vi) If the complaint is transferred from the
Environmental Protection Department (EPD), submit an interim report to the EPD
on the status of the complaint investigation and follow-up action within the
time frame assigned by the EPD;
(vii) Undertake additional monitoring and audit to
verify the situation if necessary, and review those circumstances leading to
the complaint not recurring;
(viii) Report investigation results and subsequent actions to the complainant
(if the source of complaint is identified through EPD, the results should be
reported within the timeframe assigned by EPD); and
(ix) Record the complaint, investigation, subsequent
actions and the results in the monthly EM&A reports.
11.3.2
A flow chart of the complaint response procedure is
shown in Appendix 11.1.
11.3.3
During the complaint investigation work, the
Contractor and ER shall work with the ET in providing all necessary information
and assistance for the completion of the investigation. If mitigation
measures are identified as required during the investigation by the ET, the
Contractor should promptly carry out the mitigation works. The ER shall
ensure that the measures have been carried out by the Contractor.
11.4.1
The ET Leader will keep a contemporaneous log book of
each and every instance or circumstance or change of circumstances which may
affect the EIA and every non-compliance from the recommendations of the EIA
Report or the EP. The ET Leader will notify the IEC within one working
day of the occurrence of any such instance or circumstance or change of
circumstance. The ET Leader’s log-book will be kept readily available for
inspection by persons assisting in supervision of the implementation of the EIA
Report recommendations (such as IEC and Contractor) or by EPD or his authorised
officers.
12
REPORTING
12.1.1
Upon agreement with the ER and EPD, reports can be
provided in electronic format. This would enable a transition from a
paper/ historic and reactive approach to an electronic/real-time proactive
approach. All monitoring data, including baseline and impact monitoring,
shall also be submitted in electronic format.
12.1.2
The ET Leader shall submit baseline monitoring
reports, monthly EM&A reports and final EM&A review reports. In
accordance with Annex 21 of the EIAO-TM, a copy of the monthly and final review
EM&A reports will be made available to the Director of Environmental
Protection (DEP). The exact details of the frequency,
distribution and time frame for submission shall be agreed with the IEC, the ER
and EPD prior to the commencement of works.
12.2 Interim Notification of
Environmental Quality Limit Exceedances
12.2.1
With reference to the EAPs, when the environmental
quality performance limits are exceeded, the ET Leader shall immediately notify
the IEC, HyD and EPD, as appropriate. The notification shall be followed
up with advice to IEC, HyD and EPD on the results of the investigation,
proposed actions and success of the actions taken, with any necessary follow-up
proposals. A sample template for the interim notifications is presented
in Appendix 12.1.
12.3 Baseline
Monitoring Report
12.3.1
Baseline Environmental Monitoring Report(s) shall be
prepared within ten working days of completion of the baseline monitoring and
then certified by the ET Leader. Copies of the Baseline Environmental
Monitoring Report shall be submitted to the Contractor, the IEC, ER and EPD.
The ET Leader shall liaise with the relevant parties on the exact number
of copies they require. The report format and baseline monitoring data
format shall be agreed upon with the IEC, the ER and EPD prior to submission.
12.3.2
The Baseline Environmental Monitoring Report shall
include, but not be limited to the following information:
(i) Up to half a page executive summary;
(ii) Brief project background
information;
(iii) Drawings showing locations of the
baseline monitoring stations;
(iv) An updated construction programme with
milestones of environmental protection/ mitigation activities annotated;
(v) Monitoring results (in both hard and
soft copies) together with the following information:
· Monitoring methodology;
· Name of laboratory and types of
equipment used and calibration details;
· Parameters monitored;
· Monitoring locations (and depth);
· Monitoring date, time, frequency and
duration; and
· Quality assurance (QA)/ quality
control (QC) results and detection limits.
(vi) Details on influencing factors, including:
· Major activities, if any, are
carried out on the site during the period;
· Weather conditions during the
period; and
· Other factors which might affect
results.
(vii) Determination of the Action and Limit Levels
for each monitoring parameter and statistical analysis of the baseline data,
the analysis shall conclude if there is any significant difference between
control and impact stations for the parameters monitored;
(viii) Revisions for inclusion in the EM&A Manual; and
(ix) Comments, recommendations and conclusions.
12.4 Monthly EM&A Reports
12.4.1
The results and findings of all EM&A works
required in the Manual should be recorded in the monthly EM&A reports
prepared by the ET Leader and verified by the IEC. The first Monthly
EM&A Report should be prepared and submitted to EPD in the month after the
major construction works commence with the subsequent Monthly Reports due
within ten working days of the end of each reporting month. Copies of
each monthly EM&A report shall be submitted to the parties: Contractor,
IEC, HyD and EPD, as well as to other relevant departments as required.
Before submission of the first monthly EM&A Report, the ET shall liaise
with the parties on the exact number of copies and format of the monthly
reports in both hard copy and electronic medium.
12.4.2
The ET leader shall review the number and location of
monitoring stations and parameters every six months, or on an as-needed basis,
in order to cater for any changes in the surrounding environment and the nature
of works in progress.
Contents of First Monthly EM&A
Report
12.4.3
The first monthly EM&A report shall include at
least but not be limited to the following:
(i) Executive summary (1-2 pages), including:
· Breaches of Action and Limit levels;
· Complaint log;
· Notifications of any summons and
successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Basic project information, including:
· Project organisation including key
personnel contact names and telephone numbers;
· Construction programme;
· Management structure; and
· Works were undertaken during the
month;
(iii) Environmental status, including:
· Advice on the status of statutory
environmental compliance, such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
· Works undertaken during the
reporting month with illustrations (such as the location of works, etc.); and
· Drawings showing the Project area,
any environmentally sensitive receivers and the locations of the monitoring
stations;
(iv) A brief summary of EM&A requirements, including:
· All monitoring parameters;
· Environmental quality performance
limits (Action and Limit levels);
· Event and Action Plans;
· Environmental mitigation measures as
recommended in the Final EIA report; and
· Environmental requirements in
contract documents;
(v) Implementation status, including:
· Advice on the implementation status
of environmental protection and pollution control/ mitigation measures, as
recommended in the EIA report;
(vi) Monitoring results (in both hard and electronic copies) with the
following information:
· Monitoring methodology;
· Name of laboratory and types of
equipment used and calibration details;
· Monitoring parameters;
· Monitoring locations and depth;
· Monitoring date, time, frequency,
and duration; and
· Weather conditions during the
period.
(vii) Graphical plots of the monitored parameters in the month annotated
against:
· The major activities being carried
out on-site during the period;
· Weather conditions that may affect
the results;
· Any other factors which might affect
the monitoring results; and
· QA/QC results and detection limits;
(viii) Report
on non-compliance, complaints, notifications of the summons and
successful prosecutions, including; and:
· Record all non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
· Record of all complaints received
(written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
· Record of all notification of
summons and successful prosecutions for breaches of current environmental protection/
pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
· Review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
· Description of the actions taken in
the event of non-compliance and deficiency reporting and any follow-up
procedures related to earlier non-compliance;
(ix) Others:
· Summary of future key issues as
reviewed from the works programme and work method statements;
· Advice on the solid and liquid waste
management status;
· Record of any project changes from
the originally proposed as described in the EIA (e.g. construction methods,
mitigation proposals, design changes, etc.);
· A forecast of the works programme,
impact predictions and monitoring schedule for the next three months;
· Compare and contrast the EM&A
data with the EIA predictions and annotate with an explanation for any
discrepancies; and
· Comments (for example, effectiveness
and efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
Contents of Subsequent Monthly
EM&A Report
12.4.4
Subsequent monthly EM&A reports shall include the
following:
(i) Executive summary (1-2 pages), including:
· Breaches of Action and Limit levels;
· Complaint log;
· Notifications of any summons and
successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Basic project information, including:
· Project organisation including key
personnel contact names and telephone numbers;
· Construction programme;
· Management structure,
· Works were undertaken during the
month; and
· Any updates as needed to the scope
of works and construction methodologies;
(iii) Environmental status, including:
· Advice on the status of statutory
environmental compliance, such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
· Works undertaken during the
reporting month with illustrations (such as the location of works, etc.); and
· Drawing(s) showing the Project site
area, any environmental sensitive receivers and the locations of the monitoring
stations;
(iv) Implementation status, including:
· Advice on the implementation status
of environmental protection and pollution control/ mitigation measures, as
recommended in the EIA report;
(v) Monitoring results (in both hard and electronic copies) with the
following information:
· Monitoring methodology;
· Name of laboratory and types of
equipment used and calibration details;
· Parameters monitored;
· Monitoring locations and depth;
· Monitoring date, time, frequency,
and duration;
· Weather conditions during the
period;
· Any other factors which might affect
the monitoring results; and
· QA/ QC results and detection limits;
(vi) Report on non-compliance, complaints, notifications of the summons and
successful prosecutions, including:
· Record all non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
· Record of all complaints received
(written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
· Record of all notification of
summons and successful prosecutions for breaches of current environmental
protection/ pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
· Review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
· Description of the actions taken in
the event of non-compliance and deficiency reporting and any follow-up
procedures related to earlier non-compliance;
(vii) Others:
· Summary of future key issues as
reviewed from the works programme and work method statements;
· Advice on the solid and liquid waste
management status;
· Record of any project changes from
the originally proposed as described in the EIA (e.g. construction methods,
mitigation proposals, design changes, etc.);
· Comments (for example, effectiveness
and efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions;
(viii) Appendices:
· Action and Limit levels;
· Graphical plots of trends of
monitored parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following:
o Major activities being carried out on-site during the period;
o Weather conditions during the period; and
o Any other factors that might affect the monitoring results.
· Monitoring schedule for the present
and next reporting period;
· Cumulative statistics on complaints
(if any), notifications of the summons and successful prosecutions; and
· Details of complaints, outstanding
issues and deficiencies.
Contents of Final EM&A Review
Report
12.4.5
The final EM&A review report will be prepared by
the ET Leader at the end of the construction phase of the Project. The
final EM&A review report shall be submitted to the following parties: the
IEC, the ER and the EPD. The final EM&A Review Report will contain at
least the following information:
(i) Executive summary (1-2 pages);
(ii) Basic project information including a synopsis
of the project organisation, contacts of key management, and a synopsis of work
undertaken during the course of the project or past twelve months;
(iii) A brief summary of EM&A requirements including:
· Monitoring parameters;
· Environmental quality performance
limits (Action and Limit Levels); and
· Environmental mitigation measures as
recommended in the Final EIA report.
(iv) Advice on the implementation status of environmental protection and
pollution control/ mitigation measures, as recommended in the Final EIA
report, summarised in the updated implementation schedule;
(v) Drawings showing the
project area, any environmentally sensitive receivers and the locations of the
monitoring and control stations;
(vi) Graphical plots of the
trends of monitored parameters over the course of the project, for all
monitoring stations annotated against:
· the major activities being carried
out on-site during the period;
· weather conditions during the period;
and
· any other factors which might affect
the monitoring results.
(vii) Compare and contrast the
EM&A data with the EIA predictions and annotate with an explanation for any
discrepancies;
(viii) Provide clear-cut decisions on the
environmental acceptability of the project with reference to the specific
impact hypothesis;
(ix) Advice on the solid and
liquid waste management status;
(x) A summary of
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
(xi) A brief review of the
reasons for and the implications of non-compliance including a review of
pollution sources and working procedures;
(xii) A summary
description of the actions taken in the event of non-compliance and any
follow-up procedures related to earlier non-compliance;
(xiii) A summary record of all complaints
received (written or verbal) for each media, liaison and consultation
undertaken, actions and follow-up procedures taken;
(xiv) Review the monitoring methodology
adopted and with the benefit of hindsight, comment on its effectiveness
(including cost-effectiveness);
(xv) A summary record of
notifications of the summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, locations and
nature of breaches, investigation, follow-up actions taken and results;
(xvi) Review the practicality and
effectiveness of the EIA process and EM&A programme (for example, a review
of the effectiveness and efficiency of the mitigation measures and the
performance of the environmental management system, that is, of the overall EM&A
programme), recommendations (for example, any improvement in the EM&A
programme); and
(xvii) A conclusion to state the return to ambient and/or the
predicted scenario as the EIA findings.
12.5.1
The site documents (such as monitoring field records,
laboratory analysis records, site inspection forms etc.) are not required to be
included in the EM&A Reports for submission. However, the documents
will be kept by the ET Leader and be ready for inspection upon request. Relevant
information will be clearly and systematically recorded in the documents.
The documents and data (e.g. waste data) will be kept for at least one year
after the completion of the construction contract.
12.6 Electronic Reporting of EM&A
Information
12.6.1
To enable public inspection of the baseline monitoring
report and various EM&A reports via the EIAO Internet website and at the EIAO
register office, electronic copies of these reports shall be prepared in Hyper
Text Markup Language (HTML) (version 4.0 or later) and in Portable Document
Format (PDF Adobe 11 Pro version or later), unless otherwise agreed by EPD and
shall be submitted at the same time as the hard copies. For the HTML
version, a content page capable of providing a hyperlink to each section and
sub-section of these reports shall be included at the beginning of the
document. Hyperlinks to all figures, drawings and tables in these reports
shall be provided in the main text from where the respective references are
made. All graphics in these reports shall be in interlaced GIF format unless
otherwise agreed by EPD. The summary of the monitoring data taken shall
be included in the various EM&A Reports to allow for public inspection via
the EIAO Internet website. The content of the electronic copies of these
reports must be the same as the hard copies.