1.3
Environmental Impact
Assessment Study
1.4
Purpose of the
Executive Summary
2.3
Consideration of Alignment Options. 3
3
KEY FINDINGS OF THE
ENVIRONMENTAL IMPACT ASSESSMENT
3.5 Waste Management Implications
4
ENVIRONMENTAL MONITORING AND AUDIT (EM&A)
(i)
Construction
of a single lane elevated road of approximate 800m long connecting Tsing Wun
Road (TWR) southbound (SB) to the existing elevated Lung Fu Road (LFR) SB (hereinafter referred to as LFRSR-SB);
(ii) Modification of the
existing at-grade slip road of 150m long approximately connecting TWR SB and
WCR Eastbound (EB) affected by LFRSR-SB;
(iii) Construction of a
single lane elevated road of approximate 600m long connecting the existing
elevated LFR northbound (NB) to TWR NB (hereinafter referred to as LFRSR-NB);
(iv) Modification of the
existing at-grade slip road connecting WCR westbound (WB) to TWR NB;
(v) Construction of a
single lane at-grade slip road of approximate 550m long connecting TMR NB to Castle Peak Road (Castle Peak Bay
Section) (CPR (CPBS)) WB, near Hoi Wing Road (HWR) (hereinafter referred to as HWRSR); and
(vi) Ancillary works including
geotechnical, drainage, sewerage, water, utilities, lighting, landscaping, noise mitigation measures, retaining
walls, slopeworks, and traffic improvement works.
·
the overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the Project;
·
the conditions and
requirements for the detailed design, construction and operation of the Project
to mitigate against adverse environmental consequences wherever practicable;
and
·
the acceptability of
residual impacts after the proposed mitigation measures are implemented.
Provision of LFRSR
LFRSR-NB & LFRSR-SB
HWRSR
Table 2.1
Summary of Concurrent Projects
Project [Project Proponent] |
Construction Programme |
Potential Cumulative Impact |
||
Start |
Complete |
Construction Phase |
Operation Phase |
|
Site Formation and Infrastructure Works for Public Housing Developments at Tuen Mun Central – Phase 1 [CEDD] [1] |
2021 |
Q3/2024 |
Cumulative construction dust is not anticipated as heavy construction works of this concurrent project would be completed before commencement of the Project.
Cumulative noise impact was evaluated in Section 4 of this EIA Report. |
Not anticipated in view of the nature of the concurrent project. |
Construction of Public Housing Development (PHD) at Yip Wong Road Phase 1 and Phase 2 [HD] [2] |
2020 |
2024-2025 |
Cumulative dust and noise impacts were evaluated in Section 3 and 4 of this EIA Report respectively. |
Not anticipated in view of the nature of the concurrent project. |
Cycle track between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat Section) [CEDD] [3] |
2023 |
2026 |
Cumulative dust and noise impacts were evaluated in Section 3 and 4 of this EIA Report respectively. |
Not anticipated in view of the nature of the concurrent project. |
Tuen Mun South Extension [MTRCL] [4] |
2023 |
2030 |
Cumulative dust and noise impacts were evaluated in Section 3 and 4 of this EIA Report respectively. |
Not anticipated in view of the nature of the concurrent project. |
Tuen Mun Bypass Project [HyD] |
2026 |
2033 |
Cumulative dust and noise impacts were evaluated in Section 3 and 4 of this EIA Report respectively. |
Cumulative air quality and noise impacts were evaluated in Section 3 and Section 4 of this EIA Report respectively. Due to considerable separation distance between the Project and this concurrent project, the cumulative impact is anticipated to be insignificant. |
Reprovision of Tuen Mun Swimming Pool, Tuen Mun Golf Centre Practice Green, Pet Garden and Community Green Station [MTRCL] [4] |
2023 |
2030 |
Cumulative dust and noise impacts were evaluated in Section 3 and 4 of this EIA Report respectively. |
Not anticipated in view of the nature of the concurrent project. |
Sports Ground and Open Space in Area 16, Tuen Mun [ArchSD] [5] |
2023-2024 |
2027-2028 |
Not Anticipated due to considerable separation distance between the Project and this concurrent project. |
Not anticipated in view of the nature of the concurrent project. |
Notes:
[1]
Source: PWSC Paper at https://www.legco.gov.hk/yr20-21/english/fc/pwsc/papers/p20-18e.pdf
[2] Source: LegCo Paper at https://www.legco.gov.hk/yr2022/english/panels/hg/papers/hg20220207cb1-33-1-e.pdf
[3]
Source: EIA report at https://www.epd.gov.hk/eia/register/report/eiareport/eia_2802022/CONTENT%20PAGE.htm
[4] Source: EPD’s website at https://www.epd.gov.hk/eia/register/profile/latest/esb332/esb332.pdf
[5] Source: ArchSD’s webpage at https://www.archsd.gov.hk/en/projects/capital-projects-under-detail/278RS.html
Concerns / Issues |
Follow Up Actions to be Taken |
More congested traffic on TWR causing noise problems |
The noise impact assessment during both the construction and operation phases conducted for the affected sensitive receivers have complied with the requirements set out in the EIAO-TM. Suitable mitigation measures will be implemented during the construction and operation phases as recommended in the EIA. |
• Air Quality;
• Noise;
• Water Quality;
• Waste Management;
• Land Contamination;
• Ecology;
•
Landscape and Visual; and
•
Cultural Heritage
Visual
Impacts
Table 5.1
Summary
of Environmental Impacts
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without
Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without Mitigation) |
Impact Avoidance Measures/ |
Residual Impacts |
Air Quality
Impact |
|||||
Construction Phase |
|||||
Representative ASRs
within 500m from the boundary of the Project Site |
The potential sources of air
quality impact associated with the construction works include dust generated
from construction sites. |
·
Annexes 4 and 12 of the EIAO-TM |
Not Applicable |
Appropriate
dust control measures stipulated in the Air
Pollution Control (Construction Dust) Regulation and good site practices
will be incorporated into the Contract Specifications and implemented
throughout the construction phase. Regular
dust monitoring (also incorporated into the Contract Specifications) will be conducted
to ensure the relevant legal requirements and standards are complied with
during construction phase of the Project.
|
No adverse residual
impact is anticipated. |
Operation Phase |
|||||
Representative |
Predicted cumulative air pollutant
concentrations (NO2, RSP, FSP) at ASRs with Project operation comply
with the prevailing AQOs. |
·
Annexes 4 and 12 of the EIAO-TM ·
Prevailing
AQOs |
N/A |
No
adverse air quality impact is anticipated during the operation phase of the Project, thus mitigation measure is deemed not necessary. |
No adverse residual
impact is anticipated. |
Noise Impact |
|||||
Construction Phase |
|||||
Representative NSRs
within 300m from the boundary of the Project Site |
71 to 91dB(A) |
·
Annexes
5 and 13 of the EIAO-TM ·
Leq(30-min) 75dB(A) at 1m from the façade of
residential dwellings ·
Leq(30-min) 70dB(A) at 1m from the façade of educational
institutions which rely on an openable window for ventilation (Leq(30-min) 65dB(A) during examinations). |
0 to 16dB(A) |
Implementation of recommended noise mitigation
measures including: · Quality PME prescribed in EPD’s Quality Powered
Mechanical Equipment (QPME) database. · Temporary movable noise barriers, noise enclosure
and noise insulation fabric for PME. · Scheduling of construction activities. · Liaise with the
school’s management for the schedule of construction works to avoid carrying
out noisy construction activities during the examination period. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative NSRs
(including existing and planned) within 300m from the boundary of the Project
Site |
·
Predicted
overall noise levels: ·
Predicted
noise levels of the Project roads: ·
Maximum
Contribution from Project roads: |
·
Annexes
5 and 13 of the EIAO-TM ·
L10(1-hour) 70dB(A)
at 1m from the façade of residential dwellings. ·
65 dB(A)
at 1m from the external façades of schools, places of public worship, courts
of law and places where unaided voice ·
55dB(A)
at 1m from the external façades of hospitals and clinics. |
· Exceedance of the noise criteria by up to 12dB(A). ·
The exceedances are dominantly contributed
by the existing roads at majority of representative NSRs, while at some other
representative NSRs, the exceedances are dominantly contributed by Project
Roads. |
·
LNRS of about 470m and 670m
in length along the proposed LFRSR NB and LFRSR SB, respectively. |
No
adverse residual impact is anticipated. |
Water Quality
Impact |
|||||
Construction Phase |
|||||
Representative Water
Sensitive Receivers within 500m from the boundary of the Project Site. |
The potential sources of
water quality impact associated with the construction works include: ·
Wastewater
from general construction activities; ·
Construction
site run-off; ·
Sewage
from the construction workforce; and ·
Accidental
spillage of chemicals |
·
Annexes
6 and 14 of the EIAO-TM ·
Water
Quality Objectives for the North Western Water
Control Zone (WCZ) ·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS) ·
Practice
Note for Professional Persons (ProPECC) PN1/94 |
Not Applicable |
·
Mitigation
measures and good site practices in ProPECC PN 1/94
“Construction Site Drainage”. ·
Provision
of interim treatment facilities, such as chemical toilets, for the construction
workforce. |
No
adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative Water Sensitive Receivers
within 500m from the boundary of the Project Site. |
Potential water quality impacts associated
with the operation phase include surface run-off from new roads. |
·
Annexes
6 and 14 of the EIAO-TM ·
Water
Quality Objectives for the North Western Water
Control Zone (WCZ) ·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS) ·
Practice
Note for Professional Persons (ProPECC) PN5/93 ·
Environmental,
Transport and Works Bureau (ETWB) Technical Circular (Works) No.5/2005 |
Not
Applicable |
·Adequate design in silt trap for the new road
drainage which takes into account the guidelines in ProPECC
PN5/93. ·Best Storm Water Management Practices and Storm
Water Pollution Control Plan to reduce non-point source pollution. |
No
adverse residual impact is anticipated. |
Waste
Management Implications |
|||||
Construction Phase |
|||||
C&D materials, |
·
Around 4,775m3 of
non-inert C&D materials and 48,167m3 of inert C&D
materials will be generated from different construction works of
the Project, including site clearance, minor slope and excavation works, as
well as piling and superstructure works.
·
A small
quantity of chemical waste in the order of a few hundred litres per month. ·
Around 260kg
per day of general refuse will be generated from construction works and
on-site staff and workers. |
·
Annexes
7 and 15 of the EIAO-TM ·
Waste
Disposal Ordinance (Cap. 354) ·
Waste
Disposal (Chemical Waste) (General) Regulation (Cap. 354C);
·
Waste
Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) ·
Land
(Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public
Health and Municipal Services Ordinance – Public Cleansing and Prevention of
Nuisances Regulation (Cap. 132BK) |
Not
Applicable |
· Implementation of good site practices, waste
reduction measures, Waste Management Plan (WMP) and proper storage,
collection and transport of waste. |
No
adverse residual impact is anticipated. |
Operation Phase |
|||||
Not Applicable |
It is expected that no waste will be
generated during the operation phase of the Project. |
Not Applicable |
Not Applicable |
No mitigation measure is
provided as the Project would not cause adverse impacts. |
No adverse residual
impact is anticipated. |
Land
Contamination |
|||||
Onsite construction workers and future
occupants |
Adverse land contamination impact arising
from the Project is not anticipated. |
· Annex 19 of the EIAO-TM · Guidance Note for Contaminated Land Assessment
and Remediation (EPD, 2007) · Practice Guide for Investigation and Remediation
of Contaminated Land (EPD, 2011) · Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management (EPD, 2007) |
Not Applicable |
As no adverse land
contamination impact arising from the Project is anticipated, no mitigation
measures were considered necessary. |
No adverse residual
impact is anticipated. |
Ecology |
|||||
Construction Phase |
|||||
Representative ecological Sensitive receivers within 500m from
the boundary of the Project Site |
· Temporary habitat loss of about 0.85 of
plantation that is considered of insignificant impact. · Permanent habitat loss of 1.54 ha developed area
and 1.1 ha of plantation that are considered of insignificant potential
impact; permanent loss of 0.08 ha mixed woodland which is considered of minor impact. · Other minor potential ecological impacts. |
Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM) Annexes 8 and 16 |
Not
Applicable |
·
Compensatory planting ·
Reinstatement
of plantation ·
Good
site practice |
Permanent loss of 1.1 ha
of plantation and 0.08 ha of mixed woodland.
The permanent loss of mixed woodland will be mitigated by compensatory
planting. With the recommended
mitigation measures in place, the impact will be minimized to very low level
and acceptable. |
Operation
Phase |
|||||
Representative ecological Sensitive receivers within 500m from
the boundary of the Project Site |
· Potential bird collision along the re-provided
noise barriers which is considered as minor impact. · Other minor potential ecological impacts |
Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM) Annexes 8 and 16 |
Not
Applicable |
·
Adoptation of bird
friendly design for the re-provided noise barriers |
With the recommended
mitigation measures in place, the impact will be minimized to very low level
and acceptable. |
Landscape and
Visual |
|||||
Construction Phase |
|||||
Landscape Resources (LRs) & Landscape
Character Areas (LCAs) |
·
Substantial
landscape impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Moderate
landscape Impact on LR3.1, LCA4 & LCA5 ·
Slight
landscape impact on LR4.1 & LCA3 ·
Insubstantial
landscape impact on other LRs & LCAs |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
Not
Applicable |
·
Preservation
of Existing Vegetation ·
Transplanting
of Affected Trees ·
Control
of Night-time Lighting Glare ·
Good
Site Practice ·
Erection
of Decorative Screen Hoarding |
·
Moderate
landscape Impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Slight
landscape impact on LR3.1, LR4.1, LCA3, LCA4 & LCA5 ·
Insubstantial
landscape impact on other LRs & LCAs |
Visually Sensitive Receivers (VSRs) |
·
Moderate
visual Impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR18, VSR19, VSR20, VSR24 ·
Slight
visual impact on VSR21, VSR22, VSR23 |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
·
Not
Applicable |
·
Preservation
of Existing Vegetation ·
Transplanting
of Affected Trees ·
Control
of Night-time Lighting Glare ·
Good
Site Practice ·
Erection
of Decorative Screen Hoarding |
·
Moderate
visual Impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR24 ·
Slight
visual impact on VSR18, VSR19, VSR20, VSR21, VSR22, VSR23 |
Operation Phase |
|||||
Landscape Resources (LRs) & Landscape
Character Areas (LCAs) |
·
Substantial
landscape impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Moderate
landscape impact on LR3.1, LCA4 & LCA5 ·
Slight
landscape impact on LR4.1 & LCA3 ·
Insubstantial
landscape impact on other LRs & LCAs |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
·
Not
Applicable |
·
Compensatory
Tree Planting (A total of 1,077 nos. of
surveyed trees, including 89 nos. Leucaena leucocephala,
are proposed to be removed. 988 nos.
of trees should be compensated as a result of the proposed works.) ·
Roadside
Planting ·
Provision
of Aesthetic Pleasing Treatment on Noise Barriers ·
Aesthetically
pleasing design for carriageways and other highways structures |
·
Slight
residual impact during day 1 of operation and remain slight residual impact
during year 10 of operation on LR2.3 ·
Slight
residual impact during day 1 of operation and insubstantial residual impact
during year 10 of operation on LR2.1, LR2.2, LR3.1, LCA1, LCA4 & LCA5 ·
Insubstantial
residual impact during day 1 and year 10 of operation on other LRs & LCAs |
Visually Sensitive Receivers (VSRs) |
·
Moderate
visual impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR18, VSR19, VSR20 ·
Slight
visual impact on VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR21, VSR22,
VSR23, VSR24 |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
·
Not
Applicable |
·
Compensatory
Tree Planting (A total of 1,077 nos. of
surveyed trees, including 89 nos. Leucaena leucocephala,
are proposed to be removed. 988 nos. of trees should be compensated as a result
of the proposed works.) ·
Roadside
Planting ·
Provision
of Aesthetic Pleasing Treatment on Noise Barriers ·
Aesthetically
pleasing design for carriageways and other highways structures |
·
Moderate
residual impact during day 1 of operation and during year 10 of operation on
VSR6, VSR7, VSR8, VSR9 ·
Slight
residual impact during day 1 of operation and during year 10 of operation on
VSR2, VSR4, VSR5, VSR15 ·
Slight
residual impact during day 1 of operation and insubstantial residual impact
during year 10 of operation on VSR1, VSR3, VSR10, VSR11 ·
Insubstantial
residual visual impact during day 1 and year 10 of operation on other VSRs. |
Cultural
Heritage |
|||||
Construction Phase |
|||||
Cultural heritage resources |
The proposed works areas
of the Project are located in an area with no archaeological potential. No archaeological survey is required. The potential impact on
archaeological resources is not anticipated. |
·
Annexes
10 and 19 of the EIAO-TM ·
Antiquities
and Monuments Ordinance ·
Hong
Kong Planning Standards and Guidelines (HKPSG) ·
Guidelines
for Cultural Heritage Impact Assessment |
Not Applicable |
· A baseline condition survey and baseline
vibration impact assessment are recommended to be conducted for Shing Miu and
seven other associated building structures including the Castle Peak Sam
Shing Hui Village Office, Hau Shi Tong, Tai Sui
Din, Office of Shing Miu, Fook Tak Tsz, an Earth God Shrine and an Arch by a
qualified building surveyor or qualified structural engineer during
pre-construction phase of the Project to evaluate on the necessary
construction monitoring and structural strengthening measures for AMO's
consideration. · During the construction phase of the Project
adjacent to the Arch, it shall be physically fenced off from the works area
to minimise potential physical disturbance of construction works towards the
Arch. |
With
the implementation of the recommended mitigation measures, no adverse residual
impact is anticipated. |
Operation Phase |
|||||
Cultural heritage resources |
No
impact would be anticipated during the operation phase. |
·
Annexes
10 and 19 of the EIAO-TM ·
Antiquities
and Monuments Ordinance ·
Hong
Kong Planning Standards and Guidelines (HKPSG) ·
Guidelines
for Cultural Heritage Impact Assessment |
Not Applicable |
No
mitigation measure would be required. |
Not Applicable |
Sensitive
Receivers / Assessment Points |
Impact
Prediction Results (Without Mitigation) |
Key
Relevant Standards/Criteria |
Extents of
Exceedance (Without
Mitigation) |
Impact
Avoidance Measures/ |
Residual
Impacts |
Air Quality
Impact |
|||||
Construction Phase |
|||||
Representative ASRs
within 500m from the boundary of the Project Site |
The potential sources of
air quality impact associated with the construction works include dust
generated from construction sites. |
·
Annexes 4 and 12 of the EIAO-TM |
Not Applicable |
Appropriate
dust control measures stipulated in the Air
Pollution Control (Construction Dust) Regulation and good site practices
will be incorporated into the Contract Specifications and implemented
throughout the construction phase.
Regular dust monitoring (also incorporated into the Contract
Specifications) will be conducted to ensure the relevant legal requirements
and standards are complied with during construction phase of the Project.
|
No adverse residual
impact is anticipated. |
Operation Phase |
|||||
Representative |
Predicted cumulative air
pollutant concentrations (NO2, RSP, FSP) at ASRs with Project
operation comply with the prevailing AQOs. |
·
Annexes 4 and 12 of the EIAO-TM ·
Prevailing
AQOs |
N/A |
No
adverse air quality impact is anticipated during the operation phase of the Project, thus mitigation measure is deemed not necessary. |
No adverse residual
impact is anticipated. |
Noise Impact |
|||||
Construction Phase |
|||||
Representative NSRs
within 300m from the boundary of the Project Site |
72 to 91dB(A) |
·
Annexes
5 and 13 of the EIAO-TM ·
Leq(30-min) 75dB(A) at 1m from the façade of
residential dwellings ·
Leq(30-min) 70dB(A) at 1m from the façade of
educational institutions which rely on an openable window for ventilation (Leq(30-min) 65dB(A) during examinations). |
0 to 16dB(A) |
Implementation of recommended noise mitigation
measures including: · Quality PME prescribed in EPD’s Quality Powered
Mechanical Equipment (QPME) database. · Temporary movable noise barriers, noise enclosure
and noise insulation fabric for PME. · Scheduling of construction activities. · Liaise with the
school’s management for the schedule of construction works to avoid carrying
out noisy construction activities during the examination period. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative NSRs (including
existing and planned) within 300m from the boundary of the Project Site |
·
Predicted
overall noise levels: ·
Predicted
noise levels of the Project roads: ·
Maximum
Contribution from Project roads: |
·
Annexes
5 and 13 of the EIAO-TM ·
L10(1-hour) 70dB(A)
at 1m from the façade of residential dwellings. ·
65 dB(A)
at 1m from the external façades of schools, places of public worship, courts
of law and places where unaided voice ·
55dB(A)
at 1m from the external façades of hospitals and clinics. |
·
Exceedance
of the noise criteria by up to 12dB(A). ·
The exceedances are dominantly contributed
by the existing roads at majority of representative NSRs, while at some other
representative NSRs, the exceedances are dominantly contributed by Project
Roads. |
·
LNRS of about 470m and
670m in length along the proposed LFRSR NB and LFRSR SB, respectively. |
No
adverse residual impact is anticipated. |
Water Quality
Impact |
|||||
Construction Phase |
|||||
Representative Water
Sensitive Receivers within 500m from the boundary of the Project Site. |
The potential sources of water
quality impact associated with the construction works include: ·
Wastewater
from general construction activities; ·
Construction
site run-off; ·
Sewage
from the construction workforce; and ·
Accidental
spillage of chemicals |
·
Annexes 6
and 14 of the EIAO-TM ·
Water
Quality Objectives for the North Western Water
Control Zone (WCZ) ·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS) ·
Practice
Note for Professional Persons (ProPECC) PN1/94 |
Not Applicable |
· Mitigation measures and good site practices in ProPECC PN 1/94 “Construction Site Drainage”. · Provision of interim treatment facilities, such
as chemical toilets, for the construction workforce. |
No
adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative Water Sensitive Receivers
within 500m from the boundary of the Project Site. |
Potential water quality impacts associated with
the operation phase include surface run-off from new roads. |
·
Annexes
6 and 14 of the EIAO-TM ·
Water
Quality Objectives for the North Western Water
Control Zone (WCZ) ·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems,
Inland and Coastal Waters (TM-DSS) ·
Practice
Note for Professional Persons (ProPECC) PN5/93 ·
Environmental,
Transport and Works Bureau (ETWB) Technical Circular (Works) No.5/2005 |
Not
Applicable |
·Adequate design in silt trap for the new road drainage which takes
into account the guidelines in ProPECC PN5/93. ·Best Storm Water Management Practices and Storm Water Pollution
Control Plan to reduce non-point source pollution. |
No
adverse residual impact is anticipated. |
Waste
Management Implications |
|||||
Construction Phase |
|||||
C&D materials, |
·
Around
4,775m3 of non-inert C&D materials and 48,167m3 of
inert C&D materials will be generated from different construction
works of the Project, including site clearance, minor slope and excavation
works, as well as piling and superstructure works. ·
A small quantity
of chemical waste in the order of a few hundred litres per month. ·
Around
260kg per day of general refuse will be generated from construction works and
on-site staff and workers. |
·
Annexes
7 and 15 of the EIAO-TM ·
Waste
Disposal Ordinance (Cap. 354) ·
Waste Disposal (Chemical Waste) (General)
Regulation (Cap. 354C); ·
Waste
Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) ·
Land
(Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public
Health and Municipal Services Ordinance – Public Cleansing and Prevention of
Nuisances Regulation (Cap. 132BK) |
Not
Applicable |
·
Implementation
of good site practices, waste reduction measures, Waste Management Plan (WMP)
and proper storage, collection and transport of waste. |
No
adverse residual impact is anticipated. |
Operation Phase |
|||||
Not Applicable |
It is expected that no waste will be
generated during the operation phase of the Project. |
Not Applicable |
Not Applicable |
No mitigation measure is provided
as the Project would not cause adverse impacts. |
No adverse residual
impact is anticipated. |
Land
Contamination |
|||||
Onsite construction workers and future
occupants |
Adverse land contamination impact arising
from the Project is not anticipated. |
·
Annex 19
of the EIAO-TM ·
Guidance
Note for Contaminated Land Assessment and Remediation (EPD, 2007) ·
Practice
Guide for Investigation and Remediation of Contaminated Land (EPD, 2011) ·
Guidance
Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management (EPD, 2007) |
Not Applicable |
As no adverse land contamination
impact arising from the Project is anticipated, no mitigation measures were
considered necessary. |
No adverse residual
impact is anticipated. |
Ecology |
|||||
Construction Phase |
|||||
Representative ecological Sensitive receivers within 500m from
the boundary of the Project Site |
·
Temporary habitat loss of about 0.85 of
plantation that is considered of insignificant impact. ·
Permanent habitat loss of 1.54 ha developed area
and 1.1 ha of plantation that are considered of insignificant potential
impact; permanent loss of 0.08 ha mixed woodland which is considered of minor impact. ·
Other minor potential ecological impacts. |
Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM) Annexes 8 and 16 |
Not Applicable |
·
Compensatory planting ·
Reinstatement of plantation ·
Good site practice |
Permanent loss of 1.1 ha
of plantation and 0.08 ha of mixed woodland.
The permanent loss of mixed woodland will be mitigated by compensatory
planting. With the recommended mitigation measures in
place, the impact will be minimized to very low level and acceptable. |
Operation
Phase |
|||||
Representative ecological Sensitive receivers within 500m from
the boundary of the Project Site |
·
Potential bird collision along the re-provided
noise barriers which is considered as minor impact. ·
Other minor potential ecological impacts |
Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM) Annexes 8 and 16 |
Not
Applicable |
·
Adoptation of bird
friendly design for the re-provided noise barriers |
With the recommended mitigation measures in place,
the impact will be minimized to very low level and acceptable. |
Landscape and
Visual |
|||||
Construction Phase |
|||||
Landscape Resources (LRs) & Landscape Character Areas (LCAs) |
·
Substantial
landscape impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Moderate
landscape Impact on LR3.1, LCA4 & LCA5 ·
Slight
landscape impact on LR4.1 & LCA3 ·
Insubstantial
landscape impact on other LRs & LCAs |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
Not
Applicable |
·
Preservation
of Existing Vegetation ·
Transplanting
of Affected Trees ·
Control
of Night-time Lighting Glare ·
Good
Site Practice ·
Erection
of Decorative Screen Hoarding |
·
Moderate
landscape Impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Slight
landscape impact on LR3.1, LR4.1, LCA3, LCA4 & LCA5 ·
Insubstantial
landscape impact on other LRs & LCAs |
Visually Sensitive Receivers (VSRs) |
·
Moderate
visual Impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR18, VSR19, VSR20, VSR24 ·
Slight
visual impact on VSR21, VSR22, VSR23 |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
·
Not
Applicable |
·
Preservation
of Existing Vegetation ·
Transplanting
of Affected Trees ·
Control
of Night-time Lighting Glare ·
Good
Site Practice ·
Erection
of Decorative Screen Hoarding |
·
Moderate
visual Impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR24 ·
Slight
visual impact on VSR18, VSR19, VSR20, VSR21, VSR22, VSR23 |
Operation Phase |
|||||
Landscape Resources (LRs) & Landscape Character Areas (LCAs) |
·
Substantial
landscape impact on LR2.1, LR2.2, LR2.3 & LCA1 ·
Moderate
landscape impact on LR3.1, LCA4 & LCA5 ·
Slight
landscape impact on LR4.1 & LCA3 ·
Insubstantial
landscape impact on other LRs & LCAs |
·
Annexes 10
and 18 of the EIAO-TM ·
EIAO-GN
8/2010 (Preparation of LVIA under the Environmental Impact Assessment
Ordinance) |
·
Not
Applicable |
·
Compensatory
Tree Planting (A total of 1,077 nos. of
surveyed trees, including 89 nos. Leucaena leucocephala,
are proposed to be removed. 988 nos.
of trees should be compensated as a result of the proposed works.) ·
Roadside
Planting ·
Provision
of Aesthetic Pleasing Treatment on Noise Barriers ·
Aesthetically
pleasing design for carriageways and other highways structures |
·
Slight
residual impact during day 1 of operation and remain slight residual impact
during year 10 of operation on LR2.3 ·
Slight
residual impact during day 1 of operation and insubstantial residual impact
during year 10 of operation on LR2.1, LR2.2, LR3.1, LCA1, LCA4 & LCA5 ·
Insubstantial
residual impact during day 1 and year 10 of operation on other LRs & LCAs |
Visually Sensitive Receivers (VSRs) |
·
Moderate
visual impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR10,
VSR11, VSR18, VSR19, VSR20 ·
Slight
visual impact on VSR12, VSR13, VSR14, VSR15, VSR16, VSR17, VSR21, VSR22,
VSR23, VSR24 |
·
Annexes
10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
Not
Applicable |
·
Compensatory
Tree Planting (A total of 1,077 nos. of
surveyed trees, including 89 nos. Leucaena leucocephala,
are proposed to be removed. 988 nos. of trees should be compensated as a
result of the proposed works.) ·
Roadside
Planting ·
Provision
of Aesthetic Pleasing Treatment on Noise Barriers ·
Aesthetically
pleasing design for carriageways and other highways structures |
·
Moderate
residual impact during day 1 of operation and during year 10 of operation on
VSR6, VSR7, VSR8, VSR9 ·
Slight
residual impact during day 1 of operation and during year 10 of operation on
VSR2, VSR4, VSR5, VSR15 ·
Slight
residual impact during day 1 of operation and insubstantial residual impact
during year 10 of operation on VSR1, VSR3, VSR10, VSR11 ·
Insubstantial
residual visual impact during day 1 and year 10 of operation on other VSRs. |
Cultural
Heritage |
|||||
Construction Phase |
|||||
Cultural heritage
resources |
The proposed works areas
of the Project are located in an area with no archaeological potential. No archaeological survey is required. The potential impact on
archaeological resources is not anticipated. |
·
Annexes
10 and 19 of the EIAO-TM ·
Antiquities
and Monuments Ordinance ·
Hong Kong Planning Standards and Guidelines
(HKPSG) ·
Guidelines
for Cultural Heritage Impact Assessment |
Not Applicable |
· A baseline condition survey and baseline
vibration impact assessment are recommended to be conducted for Shing Miu and
seven other associated building structures including the Castle Peak Sam
Shing Hui Village Office, Hau Shi Tong, Tai Sui
Din, Office of Shing Miu, Fook Tak Tsz, an Earth God Shrine and an Arch by a
qualified building surveyor or qualified structural engineer during
pre-construction phase of the Project to evaluate on the necessary
construction monitoring and structural strengthening measures for AMO's
consideration. · During the construction phase of the Project
adjacent to the Arch, it shall be physically fenced off from the works area
to minimise potential physical disturbance of construction works towards the
Arch. |
With
the implementation of the recommended mitigation measures, no adverse
residual impact is anticipated. |
Operation Phase |
|||||
Cultural heritage
resources |
No
impact would be anticipated during the operation phase. |
·
Annexes
10 and 19 of the EIAO-TM ·
Antiquities
and Monuments Ordinance ·
Hong Kong Planning Standards and Guidelines
(HKPSG) ·
Guidelines
for Cultural Heritage Impact Assessment |
Not Applicable |
No
mitigation measure would be required. |
Not Applicable |