Agreement No. CE 54/2020 (DS)
Drainage Improvement Works in Mui Wo – Investigation
Volume II – Appendices
CONTENTS
Appendix 2.1 Section Drawing for River Reprofiling and Gabion Wall and Conceptual Design of Modified Agricultural Weir
Appendix 2.2 Section Drawing for Flood Wall
Appendix 2.3 Indicative Section Drawing for Stormwater Pumping Station
Appendix 2.4 Tentative Construction Programme
Appendix 4.1 Photos of Existing Representative Noise Sensitive Receivers
Appendix 4.2 Prevailing Noise Monitoring Report
Appendix 4.3 Works Section Plan
Appendix 4.4 Schematic Diagram of Operational Noise Sources
Appendix 4.5 Construction Plant Inventory (Without Mitigation)
Appendix 4.6a Summary of Predicted Noise Levels during Daytime Period (Without Mitigation)
Appendix 4.6b Construction Noise Assessment (Without Mitigation)
Appendix 4.7 Construction Plant Inventory (With Mitigation)
Appendix 4.8a Summary of Predicted Noise Levels during Daytime Period (With Mitigation)
Appendix 4.8b Construction Noise Assessment (With Mitigation)
Appendix 4.9 Operational Plant Inventory
Appendix 4.10 Document for the Noise Data of the Operational Noise Sources
Appendix 4.11 Operational Noise Assessment (Unmitigated)
Appendix 4.12 Operational Noise Assessment (Mitigated)
Appendix 4.13 Schematic Configuration of Noise Barrier
Appendix 7.1 Baseline Ecological Survey Methodology & Detailed Findings
Appendix 7.2 Site Photos of River Reprofiling Section of Tai Tei Tong River
Appendix 8.1 Existing Oblique Aerial Photograph
Appendix 8.2 Broad Brush Tree Survey
Appendix 9.1 Built Heritage Survey Report
Appendix 12.1 Summary of Environmental Impact Associated with the Project
Appendix 12.2 Key Assessment Assumptions and Limitations of Assessment Methodologies