4.2 Relevant Legislation and Guidelines
4.3 Description of the Noise Environment
4.5 Prevailing Background Noise Monitoring
4.6 Identification for Potential Impacts
4.12 Monitoring
and Audit Requirements
Figure
Figure 4.1 Representative Noise Sensitive Receivers
(NSRs) within Assessment Area
Table
Table 4.1 -
EIAO-TM Day-time Construction Noise
Standards (Leq, 30 min dB(A))
Table 4.2 -
Area
Sensitivity Ratings
Table 4.3 -
Basic
Noise Levels (BNLs)
Table 4.5 -
Representative
Noise Sensitive Receivers (NSRs)
Table 4.6 -
Noise
Criteria of Planned Operational Noise Sources
Table 4.7 -
Equipment
Inventory of the Proposed Stormwater Pumping Station
Table 4.8 -
Predicted
Construction Noise Levels (Without Mitigation Measure)
Table 4.9 -
Predicted
Noise Level at the Representative NSRs (Unmitigated)
Table 4.10 - SWL of QPME adopted
for Construction Noise Mitigation
Table 4.11 - Predicted Construction
Noise Levels (With Mitigation Measures)
Table 4.12 - Predicted Noise Level
at the Representative NSRs (Mitigated)
Appendix
4.1 Photos of Existing
Representative Noise Sensitive Receivers
Appendix
4.2 Prevailing Noise Monitoring
Report
Appendix
4.3 Works
Section Plan
Appendix
4.4 Schematic Diagram of
Operational Noise Sources
Appendix
4.5 Construction Plant Inventory
(Without Mitigation)
Appendix
4.6a Summary of Predicted Noise
Levels during Daytime Period (Without Mitigation)
Appendix
4.6b Construction Noise Assessment
(Without Mitigation)
Appendix
4.7 Construction Plant Inventory
(With Mitigation)
Appendix
4.8a Summary of Predicted Noise
Levels during Daytime Period (With mitigation)
Appendix
4.8b Construction Noise Assessment
(With Mitigation)
Appendix
4.9 Operational Plant Inventory
Appendix
4.10 Document for the Noise Data of
the Operational Noise Sources
Appendix 4.11 Operational Noise Assessment (Unmitigated)
Appendix
4.12 Operational Noise Assessment
(Mitigated)
Appendix
4.13 Schematic Configuration of
Noise Barrier
Construction phase
·
Technical
Memorandum on Noise from Construction Work other than Percussive
Piling (GW-TM); and
·
Technical
Memorandum on Noise from Construction Work in Designated Areas (DA-TM).
SPME:
·
Hand-held breaker
·
Bulldozer
·
Concrete lorry mixer
·
Dump truck
·
Hand-held vibratory poker
PCW:
·
Erection or dismantling of formwork or scaffolding
·
Loading, unloading or handling or rubble, wooden boards, steel bars,
wood or scaffolding material
·
Hammering
Table 4.1 - EIAO-TM Day-time
Construction Noise Standards (Leq, 30
min dB(A))
Use |
Noise Standard (dB(A)) |
Domestic Premises, Hotels and Hostels |
75 |
Educational Institutions (normal periods) Educational Institutions (during examination periods) |
70 65 |
Notes:
a)
The above standards apply to uses which rely on opened windows for
ventilation.
b)
The above standards shall be viewed as the maximum permissible noise
levels assessed at 1m from the external façade.
Table 4.2 - Area
Sensitivity Ratings
Degree to which NSR is affected by Influencing Factor (IF) |
|||
Not Affected |
Indirectly Affected |
Directly Affected |
|
Rural area, including Country Parks or village type developments |
A |
B |
B |
Low density residential area consisting of low-rise or isolated high-rise developments |
A |
B |
C |
Urban area |
B |
C |
C |
Area other than those above |
B |
B |
C |
Notes:
The following definitions apply:
a)
"Country Park" means an area that is designated as a country
park pursuant to section 14 of the Country Parks Ordinance;
b)
"directly affected" means that the NSR is at such a location
that noise generated by the IF is readily noticeable at the NSR and is a
dominant feature of the noise climate of the NSR;
c)
"indirectly affected" means that the NSR is at such a location
that noise generated by the IF, whilst noticeable at the NSR, is not a dominant
feature of the noise climate of the NSR;
d)
"not affected" means that the NSR is at such a location that
noise generated by the IF is not noticeable at the NSR; and
e)
"urban area" means an area of high density, diverse
development including a mixture of such elements as industrial activities,
major trade or commercial activities and residential premises.
Table 4.3 - Basic
Noise Levels (BNLs)
Time period
|
BNL for each Area Sensitivity Rating, Leq, 5 min (dB(A)) |
||
A |
B |
C |
|
All days during the evening (i.e. 19:00-23:00 hrs) and general holidays (including Sundays) during the day and evening (i.e. 07:00-23:00 hrs) |
60 |
65 |
70 |
All days during the night-time (i.e. 23:00-07:00 hrs) |
45 |
50 |
55 |
Operation Phase
Time period
|
Leq 30min (dB(A)) |
||
ASR “A” |
ASR “B” |
ASR “C” |
|
Day-time (i.e. 0700 to 1900 hours) |
60 |
65 |
70 |
Evening (i.e. 1900-2300 hours) |
60 |
65 |
70 |
Night-time (i.e. 2300-0700 hours of the next day) |
50 |
55 |
60 |
·
5
dB(A) below the appropriate ANL (as shown in Table 4.4) as specified in
the IND-TM; or
·
The
prevailing background noise levels (for quiet areas with a noise level 5 dB(A)
below the appropriate ANL).
Assessment Area
Baseline Conditions
Table 4.5 -
Representative Noise Sensitive Receivers (NSRs)
Description |
Type of Use |
No. of Storeys |
Noise Assessment Point |
Approx. Separation Distance from the Project Site Boundary (m) |
|
N1 |
Tai Tei Tong |
Residential |
3 |
70 Tai Tei Tong |
17 |
N2 |
Nam Bin Wai |
Residential |
3 |
9 Nam Bin Wai |
≤5 |
N3 |
Ma Po Tsuen |
Residential |
3 |
5 Ma Po Tsuen |
≤5 |
N4 |
Ling Tsui Tau |
Residential |
3 |
20 Ling Tsui Tau |
17 |
N5 |
Tsoi Yuen Tsuen |
Residential |
2 |
21 Tsoi Yuen Tsuen |
23 |
N6 |
Tsoi Yuen Tsuen |
Residential |
2 |
42 Tsoi Yuen Tsuen |
≤5 |
N7 |
Mui Wo Chung Hau St |
Residential |
3 |
39K Mui Wo Chung Hau St |
≤5 |
N8 |
Ngan Ho Court |
Residential |
14 |
Ngan Long House |
72 |
N9 |
Silver View Centre |
Residential |
3 |
13-16 Silver View Centre |
≤5 |
N10 |
Luk Tei Tong |
Residential |
3 |
145 Luk Tei Tong |
16 |
N11 |
Mui Wo School |
Educational Institution |
1 |
Mui Wo School |
≤5 |
N12 |
Church of Christ in China - Mui Wo Church |
Place of Worship |
2 |
Church of Christ in China - Mui Wo Church |
58 |
N13 |
Tin Hau Temple |
Place of Worship |
1 |
Tin Hau Temple |
82 |
N14 |
Hung Shing Temple |
Place of Worship |
1 |
Hung Shing Temple |
21 |
N15 |
Ma Po Tsuen |
Residential |
3 |
32 Ma Po Tsuen |
6 |
N16 |
Ma Po Tsuen |
Residential |
3 |
9 Ma Po Tsuen |
≤5 |
N17 |
Ma Po Tsuen |
Residential |
2 |
13 Ma Po Tsuen |
≤5 |
N18 |
Luk Tei Tong |
Residential |
3 |
183 Luk Tei Tong |
58 |
N19 |
Luk Tei Tong |
Residential |
3 |
46 Luk Tei Tong |
16 |
Notes:
1)
The noise criteria will be reduced to 65dB(A) during school examination
periods.
2)
Construction noise criteria for place of public worship is not specified
in the EIAO-TM. The more stringent
criteria of 70 dB(A) is adopted as a conservative approach.
Table 4.6 - Noise
Criteria of Planned Operational Noise Sources
Noise Monitoring Stations |
Time Periods |
Measured Noise Levels, L90 (1 hour) dB(A) (1) |
Measured Noise Levels with +3 façade correction, L90 (1 hour) dB(A) |
ANL-5 for ASR “A”, dB(A) (3) |
Operational Noise Criteria, dB(A)(4) |
NA1 (near NSR N2) |
Daytime & Evening (2) |
45 |
48 |
55 |
48 |
Night-time (2) |
43 |
46 |
45 |
45 |
|
NA2 (near NSR N4) |
Daytime & Evening (2) |
50 |
53 |
55 |
53 |
Night-time (2) |
44 |
47 |
45 |
45 |
Notes:
1)
The noise measurement descriptor is A-weighted sound pressure level
exceeded for 90% of the time (L90) measured using Type 1 sound level
meter. Measurements were taken free-field. The averaged noise levels (L90)
during the daytime/evening period and night-time period were taken to represent
the prevailing noise levels.
2)
Day and Evening: 0700 to 2300 hours; Night: 2300 to 0700 hours
3)
IND-TM specifies the applicable Acceptable Noise Levels
(ANLs) for assessing potential operational noise impact. The noise
criteria for planned operational noise sources are set out in the EIAO-TM as
follows
-
5 dB(A) below the appropriate ANL (as shown in Table
4.4) as specified in the IND-TM;
or,
-
the prevailing background noise levels (for quiet areas with a noise
level 5 dB(A) below the appropriate ANL).
4)
Operational Noise Criteria at noise monitoring station NA1 have been
adopted for operational noise assessment as it is the nearest NSR towards the
proposed stormwater pumping station, with lowest measured noise levels.
Construction Phase
Construction of Access across Pak Ngan Heung River
·
Site
clearance and Mobilisation
·
Construction
of Crossings bridge
Construction of Stormwater Pumping Station
·
Site
clearance and Mobilisation
·
Excavation
for Stormwater Pumping Station
·
Piling
Works for Wet Well and Pumping Station
·
Concreting
Works for Wet Well
·
Superstructure
for Pumping Station
·
E&M
Installations and Testing for Pumping Station
·
Reinstatement
Construction of Associated Drainage Works (Outlet Channel to River
Silver)
·
Site
Clearance & Mobilisation
·
Excavation
& Temporary Works
·
Formwork
Erection, Reinforcement Fixing and Concreting
·
Formwork
Dismantling and backfilling
Construction of Associated Drains Works (Ling Tsui Tau, Nam Bin Wai and
Ma Po Tsuen)
·
Pipe-laying
Works
·
Backfilling
and Reinstatement
Construction of Associated Drains Works (River Crossing)
·
Construction
of Launching Pit
·
Equipment
setup
·
Trenchless
Operation
·
Construction
of Manhole
·
Reinstatement
& Ancillary Works
Construction Diversion Box Culvert (From Tai Tei Tong River to Luk Tei
Tong Bypass Channel)
·
Site
Clearance & Mobilisation
·
Excavation
& Temporary Works
·
Formwork
Erection, Reinforcement Fixing and Concreting
·
Formwork
Dismantling and Backfilling
Improvement Works Along Tai Tei Tong River
·
Construction
of Flood Walls and Reconstruction of Gabion Walls
·
River
Reprofiling
·
Modification
of Agricultural Weir & Fish Ladders
·
Construction
of Low Flow Device
Improvement Works Along Luk Tei Tong Bypass Channel and Luk Tei Tong River
·
Construction
of Gabion Walls
·
Construction
of Box Culvert
·
Construction
of Mechanical Penstocks
Construction of Tidal Gate and Other Associated Works
·
Construction
of Temporary Barrier across River Silver & Isolation from upstream flows
·
Concreting
Works for Tidal Gate
·
Delivery
and E&M Installations for Tidal Gate
River Revitalisation Works and Associated Works
·
Construction
of Footpath along Luk Tei Tong Bypass Channel
·
Softscape
and Hardscape Works
Operation Phase
Table 4.7 -
Equipment Inventory of the Proposed Stormwater Pumping Station
Equipment |
Location |
No. of Equipment |
Maximum Sound Power Level for Each Equipment, dB(A) |
|
Option 1 |
Option 2 |
|||
Flood pumps |
Pump room |
4 |
4 |
86 |
Ventilation fan (A) facing to the corridor |
Deodorization Room |
1 |
1 |
71 |
Ventilation fan (B) facing to the corridor |
Deodorization Room |
1 |
1 |
71 |
Ventilation fan (H) facing to the corridor |
Plumbing Pumps and Tanks Room & Store Room |
1 |
1 |
71 |
Ventilation fan (F) facing to the corridor |
Motor Room |
3 |
3 |
89 |
Ventilation fan (D) facing to the southeast |
Fuel tank room |
- |
1 |
71 |
Ventilation fan (E) facing to the southeast |
Generator Room |
- |
1 |
71 |
Ventilation fan (G) facing to the southeast |
CLP Transformer Room |
1 |
- |
71 |
Ventilation fan (C) facing to the southwest |
Equipment Hall |
9 |
9 |
71 |
Notes:
1)
Only 4 sets out of total 5 sets of pumps will be operated at any one
time.
2)
Two operation modes:
Option 1 (General Condition):
4 pumps + All fans except the fans for Fuel Tank
Room (D) and Generator Room (E).
Option 2 (Emergency Condition, if CLP power supply
fail):
4 pumps + All fans except the fans for CLP
transformer Room (G).
Construction Phase
·
Identify
the representative NSRs that may be affected by the construction of the
Project;
·
Determine
the plant items for corresponding construction activities, based on the agreed
plant inventory;
·
Assign
sound power levels (SWLs) to the PME proposed based on the GW-TM and list of
SWLs of other commonly used PME;
·
Calculate
the correction factors based on the distance between the NSRs and the notional
noise source positions of different works areas;
·
Apply
corrections in the calculations, such as potential screening effects and
acoustic reflection, if any;
·
Predict
the construction noise levels at NSRs in the absence of any mitigation
measures; and
·
Add
a positive 3 dB(A) façade correction to the predicted noise levels in order to
account for the facade effect at each NSR.
Cumulative Noise Impact
Operation Phase
·
Identify
the types of equipment and their number;
·
Assign
sound power levels (SWLs) to the proposed equipment with reference to noise
data from specification for similar capacity of equipment;
·
Identify
representative NSR as defined by the EIAO-TM based on
existing and committed land uses in the Assessment Area that may be affected by
the works areas of the Project;
·
Calculate
the distance correction factors, using a conservative approach, based on the
horizontal distance between the NSR and the noise sources;
·
Calculate
the corrected noise levels after taking into account other corrections such as
potential screening effects, if any, by adopting standard acoustics principles;
·
A
6dB(A) correction for tonality has been applied to all equipment as a
conservative approach; and
·
Present
the results in terms of Leq, 30min dB(A),
as specified in the IND-TM.
Construction Phase
Table 4.8 -
Predicted Construction Noise Levels (Without Mitigation Measure)
NSR |
Noise Assessment Points |
Predicted Maximum Noise Level (2), (3), dB(A) |
Noise Criteria, Leq, 30min, dB(A) |
Compliance (Y/N) |
N1 |
70 Tai Tei Tong |
82 |
75 |
N |
N2 |
9 Nam Bin Wai |
89 |
75 |
N |
N3 |
5 Ma Po Tsuen |
97 |
75 |
N |
N4 |
20 Ling Tsui Tau |
85 |
75 |
N |
N5 |
21 Tsoi Yuen Tsuen |
77 |
75 |
N |
N6 |
42 Tsoi Yuen Tsuen |
92 |
75 |
N |
N7 |
39K Mui Wo Chung Hau St |
100 |
75 |
N |
N8 |
Ngan Long House |
74 |
75 |
Y |
N9 |
13-16 Silver View Centre |
84 |
75 |
N |
N10 |
145 Luk Tei Tong |
83 |
75 |
N |
N11 |
Mui Wo School |
92 |
65/70 (1) |
N |
N12 |
Church of Christ in China - Mui Wo Church |
74 |
70 (4) |
N |
N13 |
Tin Hau Temple |
71 |
70 (4) |
N |
N14 |
Hung Shing Temple |
82 |
70 (4) |
N |
N15 |
32 Ma Po Tsuen |
87 |
75 |
N |
N16 |
9 Ma Po Tsuen |
95 |
75 |
N |
N17 |
13 Ma Po Tsuen |
90 |
75 |
N |
N18 |
183 Luk Tei Tong |
74 |
75 |
Y |
N19 |
46 Luk Tei Tong |
84 |
75 |
N |
Notes:
1) The
noise criteria will be reduced to 65dB(A) during school examination periods.
2) All predicted
noise levels dB(A)were corrected with 3dB(A) for façade reflection.
3) Predicted
noise levels which exceeded the corresponding criteria are shown as bold and
underlined.
4) Construction
noise criteria for place of public worship is not specified in the EIAO-TM.
The more stringent criteria of 70 dB(A) is adopted as a conservative approach.
Operation Phase
Table 4.9 -
Predicted Noise Level at the Representative NSRs (Unmitigated)
Location |
Predicted Noise Level, dB(A) |
Predicted Maximum Noise Level, dB(A) |
Operational Noise Criteria, dB(A) (2) |
Compliance (Yes/No) |
N2 |
Daytime & Evening (1) |
56 |
48 |
No |
Night-time (1) |
56 |
45 |
No |
|
N4 |
Daytime & Evening (1) |
52 |
48 |
No |
Night-time (1) |
52 |
45 |
No |
|
N16 |
Daytime & Evening (1) |
60 |
48 |
No |
Night-time (1) |
61 |
45 |
No |
Notes:
1) Daytime
and Evening, 0700-2300 hours, Night-time, 2300-0700 hours.
2) Please
refer to Section 4.5.
Construction Phase
·
Good
site practice;
·
Quieter
construction method/ PME; and
·
Adoption
of temporary noise barrier or noise enclosure
·
Scheduling
of Noisy Activities to Avoid Noise Impact on N11
Good Site Practices
·
Only
well-maintained plant will be operated on-site and plant will be serviced
regularly during the construction phase;
·
Silencers
or mufflers on construction equipment will be utilized where required and will
be properly maintained during the construction phase;
·
Mobile
plant, if any, will be sited as far away from NSRs as possible;
·
Machines
and plant (such as trucks) that may be in intermittent use will be shut down
between work periods or will be throttled down to a minimum;
·
Plant
known to emit noise strongly in one direction will, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs; and
·
Material
stockpiles and other structures will be effectively utilised,
wherever practicable, in screening noise from on-site construction activities.
·
The
Project Proponent/ the Contractor will keep close communication with the nearby
sensitive receivers on the schedule of the construction works to minimise
disturbance to the nearby sensitive receivers.
Quieter Construction Method / PME
· Mini-excavator has
been adopted as a mitigation measure to replace traditional excavator in all
construction works.
· Electric poker has
also been adopted to replace traditional type poker in construction of crossing
bridge, concreting works for wet wall, superstructure for pumping station,
concreting works at outlet channel to River Silver, construction of Manhole,
construction of box culvert, modification of agricultural weir and fish
ladders, construction of low flow device and concreting works for tidal gate
(Items 1.1.2, 1.2.4, 1.2.5, 1.3.3, 1.5.4, 2.3, 3.1.3, 3.1.4 and 4.2).
·
For
construction of flood walls and reconstruction of gabion wall along Tai Tei
Tong River (item 3.1.1) pipe-laying works and backfilling & reinstatement
at Ling Tsui Tau, Nam Bin Wai and Ma Po Tsuen (item 1.4.1 and 1.4.2); dump
truck and/or concrete lorry mixer from other works areas located further away
from NSRs will be used, i.e., dump truck will not be used for item 3.1.1 and
item 1.4.2; dump truck and concrete lorry mixer will not be used for item
1.4.1. Material required to delivery or disposal as well as concrete required
for casting will be transported manually to / from other works areas located
further away from NSRs.
Table 4.10 - SWL of
QPME adopted for Construction Noise Mitigation
QPME / Quiet PME |
QPME Reference Number |
Brand |
Model Number |
SWL, dB(A) |
Generator, silenced |
EPD-12580 |
DENYO |
DCA-25LSKE |
88 |
Air Compressor |
EPD-07503 |
AIRMAN |
PDS55S-5C1 |
92 |
Roller, vibratory |
EPD-06779 |
SAKAI |
HV620 |
94 |
Asphalt Paver |
EPD-12854 |
JOSEPH VOEGELE AG / VOEGELE |
SUPER 1603-3 |
104 |
Crane, mobile |
EPD-07646 |
Maeda |
CC1485S-1 |
92 |
Adoption of Temporary Noise Barriers or Noise Enclosure
Scheduling of Noisy Activities to Avoid Noise Impact on N11
Table 4.11 -
Predicted Construction Noise Levels (With Mitigation Measures)
NSR |
Description |
Predicted Maximum Noise Level (2), (3), dB(A) |
Noise Criteria, Leq, 30min, dB(A) |
Compliance (Y/N) |
N1 |
70 Tai Tei Tong |
65 |
75 |
Y |
N2 |
9 Nam Bin Wai |
75 |
75 |
Y |
N3 |
5 Ma Po Tsuen |
72 |
75 |
Y |
N4 |
20 Ling Tsui Tau |
73 |
75 |
Y |
N5 |
21 Tsoi Yuen Tsuen |
62 |
75 |
Y |
N6 |
42 Tsoi Yuen Tsuen |
65 |
75 |
Y |
N7 |
39K Mui Wo Chung Hau St |
75 |
75 |
Y |
N8 |
Ngan Long House |
61 |
75 |
Y |
N9 |
13-16 Silver View Centre |
72 |
75 |
Y |
N10 |
145 Luk Tei Tong |
66 |
75 |
Y |
N11 |
Mui Wo School |
67 (65 during Examination Period) |
65/70 (1) |
Y |
N12 |
Church of Christ in China - Mui Wo Church |
57 |
70 (4) |
Y |
N13 |
Tin Hau Temple |
59 |
70 (4) |
Y |
N14 |
Hung Shing Temple |
62 |
70 (4) |
Y |
N15 |
32 Ma Po Tsuen |
75 |
75 |
Y |
N16 |
9 Ma Po Tsuen |
74 |
75 |
Y |
N17 |
13 Ma Po Tsuen |
70 |
75 |
Y |
N18 |
183 Luk Tei Tong |
62 |
75 |
Y |
N19 |
46 Luk Tei Tong |
72 |
75 |
Y |
Notes:
1) The
noise criteria will be reduced to 65dB(A) during school examination periods.
2) All
predicted noise levels dB(A)were corrected with 3dB(A) for façade reflection.
3) Predicted
noise levels which exceeded the corresponding criteria are shown as bold and
underlined.
4) Construction
noise criteria for place of public worship is not specified in the EIAO-TM.
The more stringent criteria of 70 dB(A) is adopted as a conservative approach.
Table 4.12 -
Predicted Noise Level at the Representative NSRs (Mitigated)
Location |
Predicted Noise Level, dB(A) |
Predicted Noise Level, dB(A) |
Operational Noise Criteria, dB(A) (2) |
Compliance (Yes/No) |
N2 |
Daytime & Evening |
42 |
48 |
Yes |
Night-time |
42 |
45 |
Yes |
|
N4 |
Daytime & Evening |
34 |
48 |
Yes |
Night-time |
34 |
45 |
Yes |
|
N16 |
Daytime & Evening |
44 |
48 |
Yes |
Night-time |
44 |
45 |
Yes |
·
the
ventilation fan exhaust should be orientated to face away from the NSRs as far
as practical, acoustic louvers are proposed to be adopted at all ventilation
fans;
·
quieter
equipment should be selected during procurement; and
·
specifications
on noise level for all equipment and silencers should be included when ordering
equipment.
Desilting Works at River Silver Mui Wo
·
It
is a designated project and governed by Environmental Permit No. EP-589/2021.
In accordance with the Environmental Permit Conditions 2.2 and 2.5, the
desilting works shall only be carried out either manually or by non-diesel
operated PME and shall only be carried out during non-bathing season from
December to February or other dates of Silvermine Bay Beach closure. As
per Section 4.3.1 of the Project Profile, the noise impact would be from the
use of generator, crane and dump truck for which desilted material will be
transported away from the loading area. The proposed desilting area is
surrounded by seawalls which forms a natural noise barrier. The Project Profile
concludes that adverse noise impact from the desilting Works at River Silver
Mui Wo to be minimal. As such, no cumulative environmental impact during
construction phase is anticipated. Close liaison with the Contractor of
this interfacing project will also be taken place, if possible, to minimize the
simultaneous construction activities with this interfacing project.
PWP No. 4353DS – Outlying Islands Sewerage Stage 2 – Extension of
Sewerage System to Other Unsewered Villages in Mui Wo Village Sewerage Works at
Luk Tei Tong and Ma Po Tsuen
·
Relevant
works has started in November 2021 and expected to complete in June 2025. No
significant environmental impact is expected from the operation sewerage
system. In view of the above, no cumulative environmental impact during
construction and operation phase are anticipated.
7414 RO “Improvement Works at Mui Wo – Remaining Phase”
·
Works
area at Mui Wo Ferry Pier is outside the 300m Assessment Area of this Project.
No potential cumulative impact is anticipated.
Construction Phase
Operational Phase