8. Landscape and visual impact assessement
8.2 Environmental Legislation, Standards, Guidelines and Criteria
8.5 Planning and Development Control Framework
8.6 Landscape Baseline Condition
8.9 Tree Survey Baseline Condition
8.10 Visual
Baseline Condition
8.11 Visually
Sensitive Receivers
8.12 Potential
Landscape and Visual Impacts
8.13 Landscape
Impact Assessment
8.18 Environmental
Monitoring & Audit
Figures
Figure 8.1 500 m Assessment Area, Visual
Envelope and Locations of Visually Sensitive Receiver (VSR) and
Vantage Point (VP)
Figure 8.2 Outline Zoning Plan (OZP)
Figure 8.3 Landscape Character Area (LCA)
Figure 8.4 Landscape Resources (LR)
Figure 8.5 Photographic Record of Landscape
Character Area
Figure 8.6a-b Photographic Record of Landscape
Resources
Figure 8.7a-g Photographic Record of Visually Sensitive
Receivers
Figure 8.9a-b Photomontage from VP1 - View from
Footbridge near Ngan Shu Street
Figure 8.10a-b Photomontage from VP2 - View from Luk Tei
Tong Bypass Channel
Figure 8.11a-b Landscape and Visual Mitigation Plan
(Construction Stage), (Operation Stage)
Figure 8.12a-e Illustration for Green Roof and Landscape
Works of Stormwater pumping station Mitigation Measures
Figure 8.13a-b Sections of River Revitalization and Gabion
Wall with Mitigation Measures
Figure 8.14a-c Landscape Character Impacts During
Construction, at Day 1 of Operation and Year 10 of Operation
Figure 8.15a-c Landscape Resources Impacts During
Construction, at Day 1 of Operation and Year 10 of Operation
Tables
Table 8.1 - Matrix of Impact Significance
Table 8.2 - Details of Administrative Planning Zones
Table 8.3 - Sensitivity of Landscape Character Areas
Table 8.4 - Sensitivity of Landscape Resources
Table 8.5 - Details of Visually Sensitive Receivers
Table 8.6 - Summary of Magnitude of Change on LCAs and
LRs
Table 8.7 - Summary of Impact Significance on LRs and
LCAs before mitigation
Table 8.8 - Summary of Magnitude of Change on VSRs
before Mitigation
Table 8.9 - Summary of Impact Significance on VSRs
before Mitigation
Table 8.10 - Proposed Construction Phase Mitigation
Measures for Landscape and Visual Impacts
Table 8.11 - Proposed Operation Phase Mitigation Measures
for Landscape and Visual Impacts
Table 8.12 - Summary of Impact Significance on LRs and
LCAs, both before and upon mitigation
Table 8.13 - Summary of Impact Significance on VSRs, both
before and upon mitigation
Appendices
Appendix
8.1 Existing Oblique Aerial
Photograph
Appendix
8.2 Broad Brush Tree Survey
·
Conduct
landscape and visual baseline studies that describe the existing conditions;
·
Identify
and describe landscape and visual impacts of the areas;
·
Define
the significance and magnitude of these impacts;
·
Propose
mitigation measures by taking local conditions and experience in consideration
and to describe the maintenance and management of these mitigation measures;
and
·
Indicate
the residual impacts after mitigation.
·
Environmental
Impact Assessment Ordinance (Cap.499) and the Technical Memorandum
on EIA Process (EIAO TM), particularly Annexes 10, 11 and 18;
·
EIAO
Guidance Note 8/2010;
·
EIA
Study Brief No. ESB-334/2020;
·
Hong
Kong Planning Standards and Guidelines;
·
Town
Planning Ordinance (Cap 131);
·
Forests
and Countryside Ordinance (Cap. 96) and its subsidiary legislation the Forestry
Regulations;
·
Country
Parks Ordinance (Cap 208);
·
Territorial
Development Strategy Review: 1995;
·
DEVB
TCW No.04/2020 – Tree Preservation; and
·
DEVB
TCW No. 05/2020 – Registration and Preservation of Old and Valuable Trees (OVT);
·
DEVB
TCW No. 6/2015 – Maintenance of Vegetation and Hard Landscape Features; and
·
ETWB
TCW No. 5/2005 – Protection of Natural Streams / Rivers from Adverse Impacts
Arising from Construction Works
Tai Tei Tong River
(a)
Construction
of flood walls;
(b)
Reconstruction
of gabion walls;
(c)
River
reprofiling and associated works;
(d)
Modification
of agricultural weirs; and
(e)
Construction
of fish ladders and associated works.
Nam Bin Wai, Chung Hau, Ling Tsui Tau and Ma Po Tsuen
(a)
Construction
of access across Pak Ngan Heung River;
(b)
Construction
of stormwater pumping station and the associated drainage works;
(c)
Construction
of diversion box culvert from Tai Tei Tong River to Luk Tei Tong Bypass
Channel; and
(d)
Construction
of tidal gate at River Silver and other associated works.
Luk Tei Tong River (South) and Luk Tei Tong Bypass Channel
(a)
Reconstruction
of gabion walls;
(b)
Construction
of box culvert;
(c)
Construction
of mechanical penstock; and
(d)
River
revitalisation and associated works.
Definition of the Assessment Area
Landscape Impact Assessment Methodology
·
Baseline
survey, in this case comprising a tree survey; and
·
Potential
landscape impact assessment.
·
Local
topography;
·
Existing
roadside planting;
·
Woodland
extent and type;
·
Other
vegetation types;
·
Built
form;
·
Patterns
of settlement;
·
Land
use;
·
Scenic
spots;
·
Details
of local materials, styles, streetscapes;
·
Prominent
watercourses; and
·
Cultural
and religious identity.
·
Quality
of landscape characters / resources;
·
Importance
and rarity of special landscape elements;
·
Ability
of the landscape to accommodate change;
·
Significance
of the change in local and regional context; and
·
Maturity
of the landscape.
·
High: Important
landscape or landscape resource with particularly distinctive positive aspects
of character or high rarity value, sensitive to relatively small changes;
·
Medium: Landscape or
landscape resource with moderately distinctive positive aspects of character or
rarity value reasonably tolerant to change; and
·
Low: Landscape or
landscape resource common across Hong Kong with little distinctive positive
character or low rarity value with a high tolerance to change.
·
Compatibility
of the Project with the surrounding landscape;
·
Duration
of impacts under construction and operational phases;
·
Scale
of the development; and
·
Reversibility
of change.
·
Large: A clearly evident,
frequently perceived and continuous change in landscape characteristics
affecting an extensive area. The change may be long term and would not be
reversible;
·
Intermediate: A noticeable
change in landscape character, frequently perceived or continuous and over a
wide area; or a clearly evident change over a restricted area that may be
infrequently perceived. The change may be medium to long term and may not be
reversible;
·
Small: A subtle change in
landscape character over a wide area of a more noticeable change either over a
restricted area or infrequently perceived. The change may be short term; and
·
Negligible: The imperceptible,
barely or rarely perceptible change in landscape characteristics. The change
may be short term.
·
Significant: Negative /
positive impact where the proposal would cause a very noticeable deterioration
or improvement to existing landscape resources / character;
·
Moderate: Negative /
positive impact where the proposal would cause a noticeable deterioration or
improvement to existing landscape resources / character
·
Slight: Negative /
positive impact where the proposal would cause a barely perceptible
deterioration or improvement to existing landscape resources / character; and
·
Insignificant: No discernible
change to existing landscape resources / character.
Table 8.1 - Matrix of Impact Significance
Magnitude of Landscape Impact |
Sensitivity of Landscape Resource |
|||
|
Low |
Medium |
High |
|
Negligible |
Insignificant |
Insignificant |
Insignificant |
|
Small |
Insignificant |
Slight |
Moderate |
|
Intermediate |
Slight |
Moderate |
Significant |
|
Large |
Moderate |
Significant |
Significant |
Tree Survey Methodology
·
Tree
number;
·
Botanical
name;
·
Height;
·
Crown
spread
·
Trunk
girth (measured 1.3 meter from the ground);
·
Trunk
diameter at breast height;
·
An
assessment of form;
·
An
assessment of health;
·
An
assessment of amenity value;
·
Survival
rate after transplantation;
·
The
Government Department responsible for maintaining the tree (where works to
trees are proposed);
·
Proposed
treatment / recommendation;
·
Justification
of treatment proposal; and
·
Other
remarks.
Visual Impact Assessment Methodology
·
Baseline
survey; and
·
Visual
impact assessment.
·
The
visual envelope as has been described above and may contain both open and
partial views of the Project; and
·
The
visually sensitive receivers (VSRs) within the visual envelope whose views will
be affected by the Project. The potential receivers are categorized into four
groups:
a) Residential (R);
b) Occupational (O);
c) Leisure and Cultural
(LC); and
d) Travelling (T)
1) Value and quality of
existing views. In this case, a view from the residential property, which would
normally be considered the most sensitive view may be less so if, for example,
it is degraded by existing development or partially screened by intervening
visual obstacles such as existing vegetation;
2) Availability and
amenity alternative views for the sensitivity of receivers (SRs) are also
assessed. The location and direction of its view relative to the Project also
influences the sensitivity of each group. Typical viewpoints from within each
of the visually sensitive groups are identified and their views described;
3) The type and
estimated number of receiver population is also the factor affecting the
evaluation of visual impact;
4) The duration of
frequency of view from the SRs are also considered under the assessment; and
5) The degree of
visibility from the SRs is also evaluated.
·
Identification
of the sources of visual impacts, and their magnitude, that would be generated
during construction and operation of the Project; and
·
Identification
of the principal visual impacts primarily in consideration of the degree of
change to the baseline conditions.
·
High: The VSR is highly
sensitive to any change in their viewing experience;
·
Medium: The VSR is
moderately sensitive to any change in their viewing experience; and
·
Low: The VSR is only
slightly sensitive to any change in their viewing experience.
·
Compatibility
of the Project with the surrounding landscape forming the view;
·
Duration
of impacts under construction and operational phases;
·
Scale
of the development;
·
Reversibility
of change;
·
Viewing
distance; and
·
Potential
blockage of the view.
·
Large: A clear evident
change in the view at a close distance, affecting a substantial part of the
view, continuously visible for a long duration, or obstructing important
elements of the view. The change may be medium to long term and would not be
reversible;
·
Intermediate: A noticeable
change in the view at an intermediate distance, resulting in either a distinct
new element in a prominent part of the view, or a more wide-ranging, less
concentrated change across an expansive area. The change may be medium to long
term and may not be reversible.
·
Small: A subtle change in
the view, at long distances, or visible for a short distance, perhaps at an
oblique angle, or which blends in to an extent with the existing view. The
change may be short term; and
·
Negligible: A change which is barely or rarely perceptible, at very long
distances, or visible for a short duration, perhaps at an oblique angle, or
which blends in with the existing view. The change may be short term.
Table 8.2 - Details of Administrative Planning Zones
Details |
Works Area within the Zone (ha) |
Assessment Area within the Zone (ha) |
|
AGR |
Agriculture |
0.58 |
19.08 |
G/IC |
Government / Institution / Community |
0.24 |
2.97 |
GB |
Green Belt |
0.00 |
81.47 |
MRDJ |
Major Road and Junction |
0.00 |
1.80 |
O |
Open Space |
0.03 |
1.22 |
R(A) |
Residential (Group A) (R(A)) |
0.00 |
0.77 |
R(D) |
Residential (Group D) (R(D)) |
1.09 |
26.61 |
REC |
Recreation (REC) |
0.92 |
14.61 |
U |
Undetermined (U) |
0.00 |
1.67 |
V |
Village Type Development (V) |
0.22 |
12.65 |
·
LCA1
Bay Landscape at Silver Mine Bay;
·
LCA2
Uplands and Hillsides in West of Mui Wo;
·
LCA3
Rural Inland Plains of Mui Wo and Surrounding Villages; and
·
LCA4
Rural Township Landscapes at Fu Kong Shan.
LCA1 Bay Landscape at Silver Mine Bay
LCA2 Uplands and Hillsides in West of Mui Wo
LCA3 Rural Inland Plains of Mui Wo and Surrounding Villages
LCA4 Rural Township Landscape at Fu Kong Shan
Table 8.3 - Sensitivity of Landscape Character Areas
Ref. |
Works Area within the LCA (ha) |
Assessment Area within the LCA (ha) |
Quality and Maturity (High / Medium / Low) |
Rarity (High / Medium / Low) |
Importance (Local / District / Regional) |
Ability to Accommodate Change |
Sensitivity to Change |
LCA1 Bay Landscapes at Sliver Mine Bay |
N/A |
10.8 |
High |
Medium |
District |
Medium |
High |
LCA2 Uplands and Hillsides in West of Mui Wo |
N/A |
63.5 |
High |
Medium |
District |
Low |
High |
LCA3 Rural Inland Plains of Mui Wo and Surrounding Villages |
3.24 |
125.0 |
Medium |
Medium |
Local |
Medium |
Medium |
LCA4 Rural Township Landscapes at Fu Kong Shan |
0.29 |
39.5 |
Medium |
Low |
Local |
High |
Low |
LR1 – Secondary Woodland
LR2 – Shrubland / Grassland
LR3 – Mangrove
LR4 – Marsh
LR5 – Agricultural Land
LR6 – Plantation
LR7 – Developed Area
LR8 – Pond
LR9 – Semi Natural Water Course
LR10 – Channelized Water Course
LR11 – Sandy Shore
LR12 – Sea Water
Table 8.4 - Sensitivity of Landscape Resources
Works Area within the LR (ha) |
Quality and Maturity (High / Medium / Low) |
Rarity (High / Medium / Low) |
Importance (Local / District / Regional) |
Ability to Accommodate Change |
Sensitivity to Change |
|
LR1 - Secondary Woodland |
0.0 |
Medium |
Medium |
Local |
Medium |
Medium |
LR2 - Shrubland / Grassland |
0.0 |
Medium |
Low |
Local |
Medium |
Medium |
LR3 - Mangrove |
0.0 |
High |
High |
Local |
Low |
High |
LR4 - Marsh |
0.7 |
Medium |
High |
Local |
Medium |
Medium |
LR5 - Agricultural Land |
1.3 |
Medium |
Medium |
Local |
Medium |
Medium |
LR6 - Plantation |
0.0 |
Medium |
Low |
Local |
Medium |
Medium |
LR7 - Developed Area |
0.4 |
Medium |
Low |
Local |
High |
Low |
LR8 - Pond |
0.0 |
Medium |
Low |
Local |
Medium |
Medium |
LR9 - Semi Natural Watercourse |
0.5 |
Medium |
Low |
Local |
Medium |
Medium |
LR10 - Channelised Watercourse |
0.6 |
Medium |
Low |
Local |
High |
Low |
LR11 - Sandy Shore |
0.0 |
Medium |
Medium |
Local |
Medium |
Medium |
LR12 - Sea Water |
0.0 |
Medium |
Medium |
District |
Medium |
Medium |
·
Residential
(R);
·
Occupational
(O);
·
Leisure
and Cultural (LC); and
·
Travelling
(T).
Residential Visually Sensitive Receivers (R1-R15)
R1- Residents of Tai Tei Tong
R2 - Residents of Nam Bin Wai
R3- Residents of Ma Po Tsuen
R4 - Residents of Ling Tsui Tau
R5 - Residents of Tsoi Yuen Tsuen
R6 - Residents of Mui Wo Kau Tsuen
R7 - Residents of Chung Hau
R8 - Residents of Ngan Ho Court
R9 - Residents of Silver View Centre
R10 - Residents of Silver Waves Court
R11 - Residents of Luk Tei Tong
R12 - Residents of Sun Lung Wai
R13 - Residents of Wang Tong
R14 - Residents of Ngan Wan Estate
R15 - Residents of Ngan Wai Court
Occupational Visually Sensitive Receivers (O1 to O6)
O1 - Silver Plaza (including Lai Nursing Centre and Chan Shi Sau
Memorial Social Service Centre)
O2 - Mui Wo Government Office Buildings
O3 - Mui Wo School
O4 - Lick Hang Kindergarten
O5 - Mui Wo Municipal Services Building
O6 - Mui Wo Fire Station
Leisure and Cultural Visually Sensitive Receivers (LC1 to LC11)
LC1 - Pak Tai Temple
LC2 - Church of Christ in China Mui Wo Church
LC3 - Tin Hau Temple
LC4 - Hung Shing Temple
LC5 - Silvermine Beach Hotel
LC6 - Silver Mine Bay Beach
LC7 - Mui Wo Recreation Centre
LC8 - Mui Wo Playground
LC9 - Mui Wo Swimming Pool
LC10 - Mui Wo Rural Committee
LC11 - Mui Wo River Silver Garden
Travelling Visually Sensitive Receivers (T1 to T4)
T1 - Travelers along Ngan Shu Street
T2 Travelers along Tung Wan Tau Road
T3 Travelers along Old Village Path to Luk Tei Tong
T4 Travelers along Islands Nature Heritage Trail - Mui Wo Section
Table 8.5 - Details of Visually Sensitive Receivers
Ref. |
Representative VP |
No. of Individuals (Few / Typical / Many) |
Quality of Existing View (Good / Fair / Poor) |
Distance with the Works Area (m) |
Alternative Views |
Degree of Visibility (Glimpse /Partial / Full) |
Frequency of View (Frequent / Occasional) |
Compatibility of the Project with the Surrounding Landscape (Good / Fair / Poor) |
Sensitive to Change (High / Medium / Low) |
Residential VSRs |
|||||||||
R1 - Residents of Tai Tei Tong |
VP2 |
Typical |
Good |
77 |
Yes |
Partial |
Frequent |
Fair |
Medium |
R2 - Residents of Nam Bin Wai |
VP1 |
Few |
Good |
34 |
Yes |
Full |
Frequent |
Fair |
Medium |
R3 - Residents of Ma Po Tsuen |
VP2 |
Few |
Good |
14 |
Yes |
Full |
Frequent |
Fair |
Medium |
R4 - Residents of Ling Tsui Tau |
VP2 |
Few |
Good |
31 |
Yes |
Full |
Frequent |
Fair |
Medium |
R5 - Residents of Tsoi Yuen Tsuen |
VP2 |
Few |
Good |
59 |
Yes |
Partial |
Frequent |
Fair |
Medium |
R6 - Residents of Mui Wo Kau Tsuen |
VP2 |
Few |
Good |
119 |
Yes |
Partial |
Frequent |
Fair |
Medium |
R7 - Residents of Chung Hau |
N/A |
Few |
Fair |
29 |
Yes |
Partial |
Frequent |
Fair |
Medium |
R8 - Residents of Ngan Ho Court |
VP1 |
Typical |
Fair |
82 |
Yes |
Full |
Frequent |
Fair |
Medium |
R9 - Residents of Silver View Centre |
VP1 |
Few |
Fair |
44 |
Yes |
Full |
Frequent |
Fair |
Medium |
R10 - Residents of Silver Waves Court |
N/A |
Few |
Good |
222 |
Yes |
Glimpse |
Frequent |
Fair |
Low |
R11 - Residents of Luk Tei Tong |
VP2 |
Typical |
Good |
48 |
Yes |
Full |
Frequent |
Fair |
High |
R12 - Residents of Sun Lung Wai |
VP2 |
Typical |
Good |
236 |
Yes |
Glimpse |
Frequent |
Good |
Medium |
R13 - Residents of Wang Tong |
VP1 |
Few |
Good |
242 |
Yes |
Glimpse |
Frequent |
Fair |
Medium |
R14 - Residents of Ngan Wan Estate |
VP1 |
Typical |
Fair |
95 |
Yes |
Full |
Frequent |
Fair |
Medium |
R15 - Residents of Ngan Wai Court |
VP1 |
Typical |
Fair |
139 |
Yes |
Full |
Frequent |
Fair |
Medium |
Occupational VSRs |
|||||||||
O1
- Silver Plaza (including Lai Nursing Centre |
VP1 |
Few |
Good |
116 |
Yes |
Glimpse |
Occasional |
Fair |
Medium |
O2 - Mui Wo Government Office Buildings |
VP1 |
Few |
Fair |
158 |
Yes |
Full |
Occasional |
Fair |
Medium |
O3 - Mui Wo School |
VP1 |
Few |
Good |
14 |
Yes |
Partial |
Occasional |
Good |
Medium |
O4 - Lick Hang Kindergarten |
VP1 |
Few |
Fair |
127 |
Yes |
Glimpse |
Occasional |
Fair |
Medium |
O5 - Mui Wo Municipal Services Building |
VP1 |
Few |
Fair |
28 |
Yes |
Full |
Occasional |
Fair |
Medium |
O6 - Mui Wo Fire Station |
VP1 |
Few |
Fair |
40 |
Yes |
Full |
Occasional |
Fair |
Medium |
Leisure and Cultural VSRs |
|||||||||
LC1 - Pak Tai Temple |
VP1 |
Few |
Fair |
138 |
Yes |
Partial |
Occasional |
Fair |
Medium |
LC2 - Church of Christ in China Mui Wo Church |
N/A |
Few |
Fair |
57 |
Yes |
Glimpse |
Occasional |
Fair |
Low |
LC3 - Tin Hau Temple |
VP2 |
Few |
Good |
89 |
Yes |
Partial |
Occasional |
Fair |
Medium |
LC4 - Hung Shing Temple |
N/A |
Few |
Fair |
56 |
Yes |
Partial |
Occasional |
Fair |
Medium |
LC5 - Silvermine Beach Hotel |
N/A |
Few |
Good |
21 |
Yes |
Glimpse |
Occasional |
Good |
Medium |
LC6 - Silver Mine Bay Beach |
N/A |
Few |
Good |
182 |
Yes |
Glimpse |
Occasional |
Good |
Medium |
LC7 - Mui Wo Recreation Centre |
N/A |
Few |
Fair |
421 |
Yes |
Glimpse |
Occasional |
Fair |
Low |
LC8 - Mui Wo Playground |
N/A |
Few |
Fair |
61 |
Yes |
Full |
Occasional |
Fair |
Medium |
LC9 - Mui Wo Swimming Pool |
N/A |
Few |
Fair |
47 |
Yes |
Full |
Occasional |
Fair |
Medium |
LC10 - Mui Wo Rural Committee |
N/A |
Few |
Fair |
35 |
Yes |
Glimpse |
Occasional |
Fair |
Low |
LC11 - Mui Wo River Silver Garden |
N/A |
Few |
Fair |
62 |
Yes |
Partial |
Occasional |
Fair |
Medium |
Travelling VSRs |
|||||||||
T1 - Ngan Shu Street |
N/A |
Few |
Fair |
Within the Works Area |
Yes |
Glimpse |
Occasional |
Fair |
Medium |
T2 - Tung Wan Tau Road |
N/A |
Few |
Good |
488 |
Yes |
Glimpse |
Occasional |
Good |
Medium |
T3 - Old Village Path to Luk Tei Tong |
VP2 |
Few |
Good |
98 |
Yes |
Glimpse |
Occasional |
Good |
Medium |
T4 - Islands Nature Heritage Trail - Mui Wo Section |
N/A |
Few |
Good |
265 |
Yes |
Glimpse |
Occasional |
Good |
Medium |
Construction Phase
·
Site
clearance and tree removal (felling and transplantation);
·
Flow
diversion;
·
Site
formation works for stormwater pumping station;
·
Erection
of formwork and steel fixing and construction of the proposed channel itself
including embankment formation such as filling gabion baskets with rocks in
situ;
·
Construction
of box culverts and tidal gate;
·
Construction
of proposed cross bridge, stormwater pumping station and tidal gate;
·
Landscaping
works;
·
Presence
and operation of construction vehicles and machinery;
·
Stockpiling
areas; and
·
Contractor’s
temporary Works Areas, including parking areas.
Operation Phase
·
Operation
of tidal gate at channelized River Silver;
·
Operation
of stormwater pumping station and cross bridge; and
·
Landscaping
works.
Landscape Character Area
LCA1 – Bay Landscapes at Silver Mine Bay
LCA2 – Uplands and Hillsides in West of Mui Wo
LCA3 – Rural Inland Plains of Mui Wo and Surrounding Villages
LCA4 – Rural Township Landscapes at Fu Kong Shan
Landscape Resources
LR1 – Secondary Woodland
LR2 – Shrubland / Grassland
LR3 – Mangrove
LR4 – Marsh
LR5 – Agricultural Land
LR6 – Plantation
LR7 – Developed Area
LR8 – Pond
LR9 – Semi Natural Watercourse
LR10 – Channelised Watercourse
LR11 – Sandy Shore
LR12 – Sea Water
Significance of Landscape Impacts
Table 8.6 - Summary of Magnitude of Change on LCAs and LRs
Landscape Character Areas / Landscape Resources |
Sensitivity to Change |
Affected by Works Area (ha) |
Compatibility of Project (Good / Fair / Low) |
Duration of Impacts (Construction/ Operation) |
Reversibility of Change (Construction/ Operation) |
Magnitude of Change (Large/Intermediate/Small/ Negligible) |
|
Construction |
Operation |
||||||
Landscape Character Area |
|||||||
LCA1 – Bay Landscapes at Sliver Mine Bay |
High |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LCA2 – Uplands and Hillsides in West of Mui Wo |
High |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LCA3 – Rural Inland Plains of Mui Wo and Surrounding Villages |
Medium |
3.24 |
Fair |
Temporary / Permanent |
Reversible / Irreversible |
Intermediate |
Intermediate |
LCA4 – Rural Township Landscapes at Fu Kong Shan |
Low |
0.29 |
Fair |
Temporary / Permanent |
Reversible / Irreversible |
Small |
Negligible |
Landscape Resources |
|||||||
LR1 – Secondary Woodland |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR2 – Shrubland / Grassland |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR3 – Mangrove |
High |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR4 – Marsh |
Medium |
0.70 |
Good |
Temporary / Permanent |
Reversible / Irreversible |
Small |
Small |
LR5 – Agricultural Land |
Medium |
1.26 |
Good |
Temporary / Permanent |
Reversible / Irreversible |
Intermediate |
Intermediate |
LR6 – Plantation |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR7 – Developed Area |
Low |
0.44 |
Good |
Temporary |
Reversible / Irreversible |
Small |
Negligible |
LR8 – Pond |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR9 – Semi Natural Watercourse |
Medium |
0.53 |
Good |
Temporary / Permanent |
Reversible / Irreversible |
Intermediate |
Small |
LR10 – Channelised Watercourse |
Low |
0.59 |
Good |
Temporary |
Reversible / Irreversible |
Small |
Negligible |
LR11 – Sandy Shore |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
LR12 – Sea Water |
Medium |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
Table 8.7 - Summary of Impact Significance on LRs and LCAs before mitigation
Landscape Resource / Landscape Character Area
|
Impact Significance BEFORE Mitigation (Significant/Moderate/Slight/Insignificant) |
|
Construction |
Operation (Day 1) |
|
Landscape Character Areas |
||
LCA1 - Bay Landscapes at Sliver Mine Bay |
Insignificant |
Insignificant |
LCA2 - Uplands and Hillsides in West of Mui Wo |
Insignificant |
Insignificant |
LCA3 - Rural Inland Plains of Mui Wo and Surrounding Villages |
Moderate |
Moderate |
LCA4 - Rural Township Landscapes at Fu Kong Shan |
Insignificant |
Insignificant |
Landscape Resources |
||
LR1 - Secondary Woodland |
Insignificant |
Insignificant |
LR2 - Shrubland / Grassland |
Insignificant |
Insignificant |
LR3 - Mangrove |
Insignificant |
Insignificant |
LR4 - Marsh |
Slight |
Slight |
LR5 - Agricultural Land |
Moderate |
Moderate |
LR6 - Plantation |
Insignificant |
Insignificant |
LR7 - Developed Area |
Insignificant |
Insignificant |
LR8 - Pond |
Insignificant |
Insignificant |
LR9 - Semi Natural Watercourse |
Moderate |
Slight |
LR10 - Channelised Watercourse |
Insignificant |
Insignificant |
LR11 - Sandy Shore |
Insignificant |
Insignificant |
LR12 - Sea Water |
Insignificant |
Insignificant |
Photomontage
VP Assessment
VP1 Footbridge near Ngan Shu Street
VP2 Luk Tei Tong Bypass Channel
R2 - Residents of Nam Bin Wai; R4 - Residents of Ling Tsui Tau;
R12 - Residents of Sun Lung Wai;
R8 - Residents of Ngan Ho Court; R9 - Residents of Silver View Centre;
R14 - Residents of Ngan Wan Estate and R15 - Residents of Ngan Wai Court
R1 - Residents of Tai Tei Tong; R3 - Residents of Lei Uk Village; R5 -
Residents of Tsoi Yuen Tsuen; R6 - Residents of Mui Wo Kau Tsuen; R11 -
Residents of Luk Tei Tong; O1 - Silver Plaza (including Lai Lai Nursing Centre and Chan Shi Sau Memorial Social Service
Centre); O3 - Mui Wo School; O4 - Lick Hang Kindergarten; and O6 - Mui Wo Fire
Station and LC1 - Pak Tai Temple; LC3 - Tin Hau Temple; T3 - Old Village Path
to Luk Tei Tong
R7 - Residents of Chung Hau; R10 - Residents of Silver Waves Court; R13
- Residents of Wang Tong; O2 - Mui Wo Government Office Buildings; O5 - Mui Wo
Municipal Services Building; LC2 - Church of Christ in China Mui Wo Church; LC4
- Hung Shing Temple; LC5 - Silvermine Beach Hotel; LC6 - Silver Mine Bay Beach;
LC7 - Mui Wo Recreation Centre; LC8 - Mui Wo Playground; LC9 - Mui Wo Swimming
Pool; LC10 - Mui Wo Rural Committee ; LC11 - Mui Wo River Silver Garden; T1 -
Ngan Shu Street; T2 - Tung Wan Tau Road ; T4 - Islands Nature Heritage Trail -
Mui Wo Section
Significance of Visual Impact
Table 8.8 - Summary of Magnitude of Change on VSRs before Mitigation
VSR Ref |
Representative VP |
Sensitivity to Change |
Closest Viewing Distance to the Project (m) |
Scale
of the Project when viewed from the VSR |
Duration of Impacts (Construction/ Operation) |
Potential Blockage of View (Full/ Partial/ Nil) |
Reversibility of Change (Construction/ Operation) |
Magnitude
of change |
|
Construction |
Operation |
||||||||
R1 - Residents of Tai Tei Tong |
VP2 |
Medium |
77 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
R2 - Residents of Nam Bin Wai |
VP1 |
Medium |
34 |
Medium |
Temporary/ Permanent |
Partial |
Partly reversible/ Irreversible |
Intermediate |
Intermediate |
R3 - Residents of Ma Po Tsuen |
VP2 |
Medium |
14 |
Small |
Temporary/ Permanent |
Partial |
Partly reversible/ Irreversible |
Small |
Small |
R4 - Residents of Ling Tsui Tau |
VP2 |
Medium |
31 |
Medium |
Temporary/ Permanent |
Partial |
Partly reversible/ Irreversible |
Intermediate |
Intermediate |
R5 - Residents of Tsoi Yuen Tsuen |
VP2 |
Medium |
59 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
R6 - Residents of Mui Wo Kau Tsuen |
VP1 |
Medium |
119 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
R7 - Residents of Chung Hau |
N/A |
Medium |
29 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
R8 - Residents of Ngan Ho Court |
VP1 |
Medium |
82 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Intermediate |
Negligible |
R9 - Residents of Silver View Centre |
VP1 |
Medium |
44 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Intermediate |
Negligible |
R10 - Residents of Silver Waves Court |
N/A |
Low |
222 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
R11 - Residents of Luk Tei Tong |
VP2 |
High |
48 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
R12 - Residents of Sun Lung Wai |
VP 2 |
Medium |
236 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Intermediate |
Small |
R13 - Residents of Wang Tong |
N/A |
Medium |
242 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
R14 - Residents of Ngan Wan Estate |
VP1 |
Medium |
95 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Intermediate |
Negligible |
R15 - Residents of Ngan Wai Court |
VP1 |
Medium |
139 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Intermediate |
Negligible |
O1 - Silver Plaza (including Lai Lai Nursing Centre and Chan Shi Sau Memorial Social Service Centre) |
VP1 |
Medium |
116 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
O2 - Mui Wo Government Office Buildings |
VP1 |
Medium |
158 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
O3 - Mui Wo School |
VP1 |
Medium |
14 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
O4 - Lick Hang Kindergarten |
VP1 |
Medium |
127 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
O5 - Mui Wo Municipal Services Building |
VP1 |
Medium |
28 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
O6 - Mui Wo Fire Station |
VP1 |
Medium |
40 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
LC1 - Pak Tai Temple |
VP1 |
Medium |
138 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
LC2 - Church of Christ in China Mui Wo Church |
N/A |
Low |
57 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC3 - Tin Hau Temple |
N/A |
Medium |
89 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
LC4 - Hung Shing Temple |
N/A |
Medium |
56 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC5 - Silvermine Beach Hotel |
N/A |
Medium |
21 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC6 - Silver Mine Bay Beach |
N/A |
Medium |
182 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC7 - Mui Wo Recreation Centre |
N/A |
Low |
421 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC8 - Mui Wo Playground |
N/A |
Medium |
61 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC9 - Mui Wo Swimming Pool |
N/A |
Medium |
47 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC10 - Mui Wo Rural Committee |
N/A |
Low |
35 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
LC11 - Mui Wo River Silver Garden |
N/A |
Medium |
62 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
T1 - Ngan Shu Street |
N/A |
Medium |
Within the Works Area |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
T2 - Tung Wan Tau Road |
N/A |
Medium |
488 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
T3 - Old Village Path to Luk Tei Tong |
VP2 |
Medium |
98 |
Small |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Small |
T4 - Islands Nature Heritage Trail - Mui Wo Section |
VP1 |
Medium |
265 |
Medium |
Temporary/ Permanent |
Nil |
Partly reversible/ Irreversible |
Small |
Negligible |
Table 8.9 - Summary of Impact Significance on VSRs before Mitigation
VSR Ref
|
Impact Significance BEFORE Mitigation (Significant/Moderate/Slight/Insignificant ) |
|
Construction |
Operation |
|
R1 - Residents of Tai Tei Tong |
Slight |
Slight |
R2 - Residents of Nam Bin Wai |
Moderate |
Moderate |
R3 - Residents of Ma Po Tsuen |
Slight |
Slight |
R4 - Residents of Ling Tsui Tau |
Moderate |
Moderate |
R5 - Residents of Tsoi Yuen Tsuen |
Slight |
Slight |
R6 - Residents of Mui Wo Kau Tsuen |
Slight |
Slight |
R7 - Residents of Chung Hau |
Slight |
Insignificant |
R8 - Residents of Ngan Ho Court |
Moderate |
Insignificant |
R9 - Residents of Silver View Centre |
Moderate |
Insignificant |
R10 - Residents of Silver Waves Court |
Insignificant |
Insignificant |
R11 - Residents of Luk Tei Tong |
Moderate |
Moderate |
R12 - Residents of Sun Lung Wai |
Moderate |
Slight |
R13 - Residents of Wang Tong |
Slight |
Insignificant |
R14 - Residents of Ngan Wan Estate |
Moderate |
Insignificant |
R15 - Residents of Ngan Wai Court |
Moderate |
Insignificant |
O1 - Silver Plaza (including Lai Lai Nursing Centre and Chan Shi Sau Memorial Social Service Centre) |
Slight |
Slight |
O2 - Mui Wo Government Office Buildings |
Slight |
Insignificant |
O3 - Mui Wo School |
Slight |
Slight |
O4 - Lick Hang Kindergarten |
Slight |
Slight |
O5 - Mui Wo Municipal Services Building |
Slight |
Insignificant |
O6 - Mui Wo Fire Station |
Slight |
Slight |
LC1 - Pak Tai Temple |
Slight |
Slight |
LC2 - Church of Christ in China Mui Wo Church |
Insignificant |
Insignificant |
LC3 - Tin Hau Temple |
Slight |
Slight |
LC4 - Hung Shing Temple |
Slight |
Insignificant |
LC5 - Silvermine Beach Hotel |
Slight |
Insignificant |
LC6 - Silver Mine Bay Beach |
Slight |
Insignificant |
LC7 - Mui Wo Recreation Centre |
Insignificant |
Insignificant |
LC8 - Mui Wo Playground |
Slight |
Insignificant |
LC9 - Mui Wo Swimming Pool |
Slight |
Insignificant |
LC10 - Mui Wo Rural Committee |
Insignificant |
Insignificant |
LC11 - Mui Wo River Silver Garden |
Slight |
Insignificant |
T1 - Ngan Shu Street |
Slight |
Insignificant |
T2 - Tung Wan Tau Road |
Slight |
Insignificant |
T3 - Old Village Path to Luk Tei Tong |
Slight |
Slight |
T4 - Islands Nature Heritage Trail - Mui Wo Section |
Slight |
Insignificant |
Note: The source of impacts of VSRs along Ngan Shu
Street and Ngan Shek Street are considered generally inconspicuous as the Project
components such as the stormwater drain located at and below the surrounding
ground level. Hence, the recommended mitigation measures during operation
are not available to those VSRs.
Table 8.10 - Proposed Construction Phase Mitigation Measures for Landscape and
Visual Impacts
Mitigation Measure |
Funding Agency |
Implementation Agency |
Management/ Maintenance Agency |
|
|
|
|||||
CM1 |
Minimise Disturbance – temporary structures and construction works should be planned with care to minimise disturbance to vegetation including riparian vegetation along the river as well as existing built structures. The footprint of the Project should be kept to a practical minimum and form, textures and colours selected to be as compatible with the existing surroundings as possible. |
DSD |
DSD/ Contractor |
DSD |
|
CM2 |
Tree Protection and Preservation – Trees/ woodland within the Works Area will be protected and preserved as far as possible in accordance with DEVB TC(W) No. 04/2020. For example, the Project will be designed to avoid tree felling wherever possible. |
DSD |
DSD/ Contractor during construction ([1]) |
DSD/ Contractor during construction (1) |
|
CM3 |
Tree Transplantation – Should removal of trees be unavoidable due to construction impacts, trees will be transplanted or felled ([2]) according to Clause 3.97 of the General Specification of Civil Engineering Works – Section 3 Landscape Softworks and Establishment Works, including ensuring transplanted trees are treated with establishment works immediately after transplanting works, for a period of no less than 12 months. At the detailed design stage the tree transplantation plan should be refined to ensure the locations proposed to receive the transplanted tree is suitable. Established trees of value are to be re-located where practically feasible. The transplant planting will be included in a detailed landscape design and planting plan, which is recommended to be implemented as early as practicable in the Project timeline. |
DSD |
DSD/ Contractor |
Contractor / DSD and LCSD ([3]) |
|
CM4 |
Compensatory Tree Planting - Where loss of existing trees is unavoidable, compensatory planting of trees should be provided in accordance with DEVB TC(W) No. 04/2020 to compensate for those trees felled. Implementation of compensatory tree planting will be of a ratio not less than 1:1. Plants will have 12 months to establish. At the detailed design stage the tree compensation and transplantation plan should be refined to confirm the separation distance of the heavy standard compensatory trees and ensure the outlined areas are sufficient for the planting necessary to compensate for the affected trees. The selection of planting species shall be made with reference to the species identified in the Tree Survey and be predominantly native to Hong Kong or the South China region. The compensatory planting will be applied along the proposed river alignment. But the actual implementation will be subject to detailed landscape design and planting plan, and recommended to be implemented as early as practicable in the Project timeline. |
DSD |
DSD/ Contractor |
DSD |
|
CM5 |
Buffer Planting – Tall screen/buffer trees shall be planted to screen the Luk Tei Tong Bypass Channel and proposed stormwater pumping station. This measure may additionally form part of the compensatory planting and will improve compatibility with the surrounding environment. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
CM6 |
Natural Bedding Substrate – River sediment and / or boulders excavated during river reprofiling works are to be reused at Tai Tei Tong River as natural bedding substrate. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
CM7 |
Screening – Stockpiles of materials should be covered or hoarding erected where possible to reduce undesirable views of the construction site, having consideration for safety and security. It is proposed that screening (via decorative hoarding) be compatible with the surrounding environment and where possible, non-reflective, recessive colours be used. Hoarding should be taken down at the end of the construction period. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
CM8 |
Light Control – The guidelines in “Charter on External Lighting” and “Guidelines on Industry Best Practices for External Lightning Installations” promulgated by ENB for glare control will be implemented. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
CM9 |
River Revitalization and Landscape Work for Infrastructure – River Revitalization work in terms of planting and provision of leisure facilities will be conduct along Luk Tei Tong Bypass Channel to enhance ecological and amenity value of the surrounding. Native species will be selected for planting and landscape works as far as possible. Environmental friendly material and nature colour will be selected for leisure facilities and other associated facilities / hard landscape. Green roof and corresponding landscape work such as planting of climbers, shrubs and bamboo would be carried out for proposed stormwater pumping station in order to enhance the greenery of proposed structure. A minimum 20% greenery is proposed for the areas within the proposed stormwater pumping station boundary. Vertical planting is also proposed for the boundary fence of the proposed stormwater pumping station. Please refer to Figure 8.11 – Landscape and Visual Mitigation Plan for their location and Figure 8.13a for the section. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
Table 8.11 - Proposed Operation Phase Mitigation Measures for Landscape and
Visual Impacts
ID No. |
Mitigation Measure |
Funding Agency |
Implementation Agency |
Management/ Maintenance Agency |
|
|
|||||
OM1 |
Colours of Structures - Colours for the structures e.g. fences should be chosen to complement the surrounding area. Lighter colours such as shades of light grey, off-white and light brown may be utilised where technically feasible to reduce the visibility of the structures. |
DSD |
DSD/ Contractor |
DSD |
|
OM2 |
Tree Transplantation – Should removal of trees be unavoidable due to construction impacts, trees will be transplanted or felled ([4]) according to Clause 3.97 of the General Specification of Civil Engineering Works – Section 3 Landscape Softworks and Establishment Works, including ensuring transplanted trees are treated with establishment works immediately after transplanting works, for a period of no less than 12 months. At the detailed design stage the tree transplantation plan should be refined to ensure the locations proposed to receive the transplanted tree is suitable. Established trees of value are to be re-located where practically feasible. The transplant planting will be included in a detailed landscape design and planting plan, which is recommended to be implemented as early as practicable in the Project timeline. |
DSD |
DSD/ Contractor |
Contractor / DSD and LCSD ([5]) |
|
OM3 |
Compensatory Tree Planting - Where loss of existing trees is unavoidable, compensatory planting of trees should be provided in accordance with DEVB TC(W) No. 04/2020 to compensate for those trees felled. Implementation of compensatory tree planting will be of a ratio not less than 1:1. Plants will have 12 months to establish. At the detailed design stage the tree compensation and transplantation plan should be refined to confirm the separation distance of the heavy standard compensatory trees and ensure the outlined areas are sufficient for the planting necessary to compensate for the affected trees. The selection of planting species shall be made with reference to the species identified in the Tree Survey and be predominantly native to Hong Kong or the South China region. The compensatory planting will be applied along the proposed river alignment. But the actual implementation will be subject to detailed landscape design and planting plan, and recommended to be implemented as early as practicable in the Project timeline. |
DSD |
DSD/ Contractor |
DSD |
|
OM4 |
Buffer Planting – Tall screen/buffer trees shall be planted to screen the Luk Tei Tong Bypass Channel and proposed stormwater pumping station. This measure may additionally form part of the compensatory planting and will improve compatibility with the surrounding environment. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
OM5 |
Natural Bedding Substrate – River sediment and / or boulders excavated during river reprofiling works are to be reused at Tai Tei Tong River as natural bedding substrate.. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
OM6 |
Light Control – The guidelines in “Charter on External Lighting” and “Guidelines on Industry Best Practices for External Lightning Installations” promulgated by ENB for glare control will be implemented. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
OM7 |
River Revitalization and Landscape Work for Infrastructure – River Revitalization work in terms of planting and provision of leisure facilities will be conduct along Luk Tei Tong Bypass Channel to enhance ecological and amenity value of the surrounding. Native species will be selected for planting and landscape works as far as possible. Environmental friendly material and nature colour will be selected for leisure facilities and other associated facilities / hard landscape. Green roof and corresponding landscape work such as planting of climbers, shrubs and bamboo would be carried out for proposed stormwater pumping station in order to enhance the greenery of proposed structure. A minimum 20% greenery is proposed for the areas within the proposed stormwater pumping station boundary. Vertical planting is also proposed for the boundary fence of the proposed stormwater pumping station. Please refer to Figure 8.11 – Landscape and Visual Mitigation Plan for their location and Figure 8.13a for the section. |
DSD |
DSD/ Contractor |
DSD/ Contractor |
|
Table 8.12 - Summary of Impact Significance on LRs and LCAs, both before and
upon mitigation
Table
8.13
- Summary of Impact Significance on VSRs, both before and upon mitigation
Note:
The source of impacts of VSRs along Ngan Shu Street
and Ngan Shek Street are considered generally inconspicuous as the Project
components such as the stormwater drain located at and below the surrounding
ground level. Hence, the recommended mitigation measures during operation
are not available to those VSRs.
Construction Phase
Operational Phase
English
Map
([1])
This measure is only applicable during construction.
([2]) Wood
resulting from tree removal should be recycled as mulch or soil conditioner for
re-use within the Project or in other projects as far as possible e.g. for the
construction of soft landscape work, were practical.
([3])
Contractor responsible for landscaping during the agreed establishment and
maintenance period. Other designated management and maintenance
agents to take up maintenance and management of landscaping after end of agreed
period.
([4])
Wood resulting from tree removal should be recycled as mulch or soil
conditioner for re-use within the Project or in other projects as far as
possible e.g. for the construction of soft landscape work, were practical.
([5])
Contractor responsible for landscaping during the agreed establishment and maintenance
period. Other designated management and maintenance
agents to take up maintenance and management of landscaping after end of agreed
period.