· Air Quality Impact
· Noise Impact
· Water Quality Impact
· Waste Management Implications
· Land Contamination
· Landfill Gas Hazard
· Hazard to Life
· Impact on Cultural Heritage
· Landscape and Visual Impact
Table 14.1 Summary of Key
Environmental Outcomes and Benefits
Environmental Issue |
Description |
Environmental / Social Benefits of
the Project |
· The Project will widen individual road sections of the existing
TWR and construct slip road to relieve the existing traffic congestion and
cope with the anticipated future traffic demand. |
Environmentally
Friendly Design and Options |
· Recommend to adopt precast concrete construction method for
construction of viaduct which is a more environmentally friendly approach. · Implementation
of Environmental Monitoring and Auditing System. |
Air
Quality Impact |
Construction Phase: · Potential dust
impact generated from construction activities, such as site clearance,
demolition of the existing structure, and minor excavation with limited
backfilling for column installation, wind erosion of the limited exposed area,
and emission from PMEs would be minor.
With the implementation of mitigation measures specified in the Air
Pollution Control (Construction Dust) Regulation together with the
recommended dust suppression measures and good site practices, no adverse
dust impact at ASRs due to the construction activities of the Project is
anticipated. Operation Phase: ·
Cumulative air quality impact arising from the operation
of the Project such as vehicular emission from open roads, nearby chimneys and marine emissions within 500m study area has
been assessed. The results concluded
that the predicted cumulative NO2, RSP and FSP concentration on
the identified ASR would comply with AQOs, except for 5 ASRs only. The
results indicate the reduction of the annual NO2 concentration
after the Project is in operation and noise mitigation measures are in place.
As such, no adverse air quality impact arising from the operation of the
Project is anticipated. |
Noise
Impact |
Construction Phase: · The NSRs are
protected with the implementation of quiet PME, movable barriers and full
enclosure as well as good site practices during construction phase. The
predicted mitigated noise levels comply with the noise standards at all NSRs
during non-restricted hours and restricted hours. Operation Phase: ·
Although there is still predicted exceedance of the noise
criteria at some of the NSRs under the mitigated scenario, with the
implementation of noise mitigation measures including LNRS, vertical noise
barriers/cantilevered noise barriers and semi/full enclosures on some Project
roads, the exceedances were dominantly contributed by the nearby existing
roads. The contributions from the Project roads at all NSRs are less than 1.0
dB(A) and the predicted noise levels at NSRs due to the Project roads would
comply with the noise criteria. Thus, no adverse road traffic noise impacts
arising from the Project would be anticipated. ·
The Project does not include any fixed noise source. No
fixed noise impact would arise from the Project. |
Water
Quality Impact |
Construction Phase: · The key
potential sources of water quality impacts during construction phase include
the wastewater from general construction activities, construction site
run-off, construction works in close proximity of
inland watercourses, accidental spillage of chemicals and sewage effluent
from construction workforce. The
potential water quality impacts could be mitigated and controlled by
implementing the recommended mitigation measures. Regular site inspections should be
undertaken to inspect the construction activities and works area to ensure
the recommended mitigation measures are properly implemented. Operation Phase: · The key
potential sources of water quality impacts during operation phase would be
related to non-point source stormwater runoff from the new paved areas. Provided that the recommended mitigation
measures for the drainage system are properly implemented, the associated
water quality impacts are expected to be minimal and acceptable. |
Waste
Management Implications |
Construction Phase: · Waste types
generated by the construction of this Project are likely to include C&D
materials, excavated land-based sediment, chemical waste from maintenance of
construction plant and equipment and general refuse. Provided that these
wastes are handled, transported and disposed of
according to the recommended good site practices, adverse environmental
impacts are not expected. Operation Phase: ·
It is expected that no waste will be generated during the
operation phase of the Project. As such, it is considered that there should
be no adverse environmental impact. |
Land
Contamination |
·
Based on the findings of the site appraisal, no land contamination
impact arising from Project is anticipated. |
Landfill
Gas Hazard |
Construction Phase: Operation Phase: |
Hazard
to Life |
According
to the latest PHI register, YKTWTW is not considered as a PHI. No hazard to
life assessment for liquid chlorine related issue is required for YKTWTW and
no adverse impact during construction and operation phase is anticipated. |
Impact
on Cultural Heritage |
Construction Phase · No built heritage resource is identified within the Project boundary or 100m assessment area. No impact during the construction phase and operation phase would be anticipated. No mitigation measure would be required. · No SAI is identified within assessment area. No archaeological impact would be anticipated. Thus, no mitigation measure would be required. Operation Phase ·
No impact to cultural
heritage from the operation of the Project would be anticipated. Hence, no mitigation measure would be
required for the operation phase. |
Landscape
and Visual |
It
is considered that the residual landscape and visual impact is acceptable
with mitigation measures implemented during construction and operation
phases. |