TABLE
OF CONTENTS
Page
1.3 Consideration of Alternative Options
1.4 Consideration of Different Construction Methods
for Viaduct
2............ Key Findings of the environmental impact
Assessment
2.4 Waste Management Implication
2.8 Impact on Cultural Heritage
2.9 Landscape and Visual Impact
3............ ENVIRONMENTAL MONITORING AND AUDIT
LIST OF Tables
Table
1.1 Summary of Selected
Construction Methods for Viaduct
Table
1.2 Summary of
Concurrent Projects
Table
1.3 Summary of Concerns and Follow-up Actions
Table 2.1 Summary of Environmental Impacts
LIST OF FIGURES
Figure 2.1 Location Plan of the Project
Figure
2.4.1 General Layout Plan
(Sheet 1 of 6)
Figure
2.4.2 General Layout Plan
(Sheet 2 of 6)
Figure
2.4.3 General Layout Plan
(Sheet 3 of 6)
Figure
2.4.4 General Layout Plan (Sheet
4 of 6)
Figure
2.4.5 General Layout Plan
(Sheet 5 of 6)
Figure
2.4.6 General Layout Plan
(Sheet 6 of 6)
·
Item A.1 – A road which is an expressway, trunk road, primary
distributor or district distributor road including new roads, and major
extensions or improvements to existing roads; and
·
Item A.8 – A road or railway bridge more than 100 m in length between
abutments.
(i)
Widening
of a section of an elevated carriageway of TWR between Tai Ho Road and Wing
Shun Street, from a three-lane carriageway to a four-lane carriageway on Kowloon
bound;
(ii)
Widening
of a section of an elevated carriageway of TWR between Wing Shun Street and
Wing Kei Road, from a dual two-lane carriageway to a dual three-lane carriageway;
(iii)
Widening
of a section of an at-grade carriageway of TWR between Wing Kei Road and KTI, from
a dual three-lane carriageway to a dual five-lane carriageway;
(iv)
Widening
of a section of an elevated carriageway of TWR between KTI and Container Port
Road, from a three-lane carriageway to a four-lane carriageway on Kowloon bound
(its implementation is yet to be ascertained and subject to further traffic
review);
(v)
Construction
of a slip road connecting TWR (Kowloon bound) to Tsing Tsuen Road (Slip Road C)
(its implementation is yet to be ascertained and subject to further traffic
review);
(vi)
Construction
of a slip road connecting TWR (Tuen Mun bound) and
Hoi Hing Road (Slip Road E);
(vii)
Provision
of noise mitigation measures including noise barriers/enclosures and low noise surfacing
materials on associated road sections of Tsuen Wan Road; and
(viii)
Ancillary
works including geotechnical, drainage, waterworks, lighting, landscaping works, installation of traffic aid facilities, etc.
Table 1.1 Summary of Selected Construction Method for Viaduct
Construction
Method |
Selection
Reason |
Precast Concrete |
·
Minimise concrete
mixing truck travelling in site area, thus minimise potential air and noise
impact to be surrounding environment. ·
Use steel mould as
formworks to maximise the reuse of formworks, thus less C&D waste/
materials will be generated. ·
Shorten construction
time, bridge deck construction can be non-linear (multiple work fronts), with
minimising on-site potential environmental impacts and cumulative
environmental impacts with concurrent projects. ·
Relatively requires
less temporary steel platform for construction of precast structure, thus
less C&D waste / materials will be generated. ·
Carry out precasting works in fabrication yard away from the site. ·
Better control of
quality and workmanship for works in fabrication yard. ·
More efficient
construction works as the deck segments can be casted off-site concurrently
with substructure works (i.e. allow time overlap of
construction activities). ·
Durable and less
maintenance cost. |
Table 1.2 Summary of Concurrent Projects
Project
Name |
Target
Works Commencement Dates |
Target
Works Completion Dates |
Cumulative
Impact Considered / Addressed |
Improvement Works at Tsuen Tsing Interchange |
2023 |
2026 |
Construction Phase: Nil Operation Phase: Air Quality, Noise, Visual and Landscape |
Proposed Columbarium Building at Site No. 10 Tsing Tsuen Road |
2024 |
2030 |
Construction Phase: Air Quality, Noise, Visual and Landscape Operation Phase: Nil |
Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road |
2021 |
2025 |
Construction Phase: Nil Operation Phase: Air Quality, Noise, Visual and Landscape |
Improvement Works at Tai Chung Road Interchange |
2028 |
2030 |
Construction Phase: Nil Operation Phase: Air Quality, Noise, Visual and Landscape |
Table 1.3 Summary of Concerns and Follow-up Actions
Concerns / Issues |
Follow-up Actions to be Taken |
|
·
Concern on the height of the proposed noise
barriers/enclosures |
·
The height of the proposed noise
barriers/enclosures will be designed to below the lowest residential floor
level of the adjacent residential premises (e.g.
City Point) as far as practicable to minimize the visual impact. |
|
·
Concern on construction noise to the nearby
residential estates during the construction phase of the Project |
·
The construction of the Project will be carried
out with suitable temporary noise mitigation measures in place. Construction
arrangements will be carefully planned in the upcoming project stages such
that construction noise impact to the nearby residential estates will be kept
to minimum during construction of the Project. |
|
·
Concern on the potential glare resulted from the
top of the proposed noise barriers/enclosures |
·
Roof panels of the proposed barriers/enclosures will
be designed in such a way to minimise the potential glare induced. |
|
·
Request for reviewing the form of the originally
proposed noise enclosure fronting the Parc City Block 2 and the Pavilia Bay in view of various environmental concerns (e.g. visual, noise and air quality) |
·
The proposed noise enclosure form at the road
section concerned has been reviewed/refined from the form of semi-enclosure
to full enclosure. The scope of the proposed noise mitigation measures is
given in Section 4 of this Report. |
|
·
Request for extension of the proposed noise
enclosure to cover other sections of TWR fronting the Parc City Block 3 to the
Ocean Pride Block 7 |
·
According to the result of noise impact
assessment, the Project will comply with the EIAO criteria with the proposed
noise mitigation measures in place, of which no noise enclosures are required
at the TWR sections fronting Parc City Block 3 to Ocean Pride Block 7. Therefore, the requested extension of the
noise enclosure is outside the ambit of the Project. The scope of the
proposed noise mitigation measures is given in Section 4 of this Report. |
|
·
Concern on traffic impact on TWR during
construction of the Project |
·
The construction of the Project will be carried
out with suitable temporary traffic arrangements implemented. Construction arrangements will be carefully
planned in the upcoming project stages such that traffic impact on TWR will be
kept to minimum during construction of the Project. |
Table 2.1 Summary of Environmental Impacts.
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without Mitigation) |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of Mitigation
Measures) |
Air Quality Impact |
|||||
Construction Impact |
|||||
Representative existing residential, commercial developments and
government uses within 500m from the boundary of the Project Site |
·
No adverse dust impact from construction activities considering the
small scale of the project, and works will be undertaken at multiple work
fronts at different construction periods. ·
No adverse air quality impact from fuel combustion from use of Powered
Equipment (PME) in view of Air Pollution Control (Non-Road Mobile Machinery)
(Emission) Regulation. |
·
Annexes 4 and 12 of the EIAO-TM ·
Air Quality Objectives (AQO) |
·
N/A |
The
approved non-road mobile machinery (NRMMs) under NRMM Regulation (excluding
exempted NRMMs) would be used on site and NRMMs supplied with mains
electricity instead of diesel-powered should be adopted as far as possible to
minimize the potential emission from NRMMs. Dust
suppression measures and good site practices ·
Use of regular watering to reduce dust emissions from exposed site
surfaces and unpaved roads, particularly during dry weather ·
Use of frequent watering for particularly dusty construction areas and
areas close to ASRs ·
Side enclosure and covering of any aggregate or dusty material storage
piles to reduce emissions. Where this
is not practicable owing to frequent usage, watering shall be applied to
aggregate fines ·
Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs ·
Tarpaulin covering of all dusty vehicle loads transported to, from and
between site locations ·
Establishment and use of vehicle wheel and body washing facilities at
the exit points of the site ·
Provision of wind shield and dust extraction units or similar dust
mitigation measures at the loading area of barging point, and use of water
sprinklers at the loading area where dust generation is likely during the
loading process of loose material, particularly in dry seasons/ periods ·
Provision of not less than 2.4m high hoarding from ground level along
site boundary where adjoins a road, streets or other accessible to the public
except for a site entrance or exit ·
Imposition of speed controls for vehicles on site haul roads ·
Where possible, routing of vehicles and positioning of construction
plant should be at the maximum possible distance from ASRs ·
Instigation of an environmental monitoring and auditing program to
monitor the construction process in order to enforce controls and modify
method of work if dusty conditions arise ·
Locate all the dusty activities away from any nearby ASRs as far as
practicable ·
Erect higher hording at the location with ASRs in immediate proximity
to the project site boundary. ·
All malodorous materials shall be placed as far as possible from any
ASRs. ·
The stockpiled malodorous materials shall be covered entirely by
plastic tarpaulin sheets. ·
The malodorous materials shall be removed from site as soon as
possible and shall not be stockpiled overnight at the site. ·
Loading of the malodorous materials onto the dump trucks shall be
controlled to avoid spillage. |
·
No adverse residual impacts anticipated. |
Operation Impact |
|||||
Existing and planned residential, commercial developments and
government uses within 500m from the boundary of the Project Site |
NO2 ·
1-hr average conc :108 -191 µg/m3 ·
Annual average conc :14.07 -41.52 µg/m3 ·
For the ASRs with exceedance of AQO for annual NO2, there
would be a decrease in annual average NO2 concentration compared
to the “Without Project” Scenario. RSP ·
24-hr average conc :59 - 63 µg/m3 ·
Annual average conc :26 - 29 µg/m3 FSP ·
24-hr average conc :32 - 35 µg/m3 ·
Annual average conc :14 - 17 µg/m3 |
NO2 ·
1-hr average conc :200 µg/m3 (Number of exceedances
allowed: 18) ·
Annual average conc :40 µg/m3 RSP ·
24-hr average conc :100 µg/m3 (Number of exceedances
allowed: 9) ·
Annual average conc :50 µg/m3 FSP ·
24- hr average conc :50 µg/m3 (Number of exceedances
allowed: 18) ·
Annual average conc :25 µg/m3 |
·
N/A |
·
No adverse air quality impact during the operation phase of the
Project is anticipated, thus mitigation measure is deemed not necessary. |
·
No adverse residual impacts anticipated. |
Noise Impact |
|||||
Construction Impact |
|||||
Representative existing noise sensitive developments (e.g. residential)
within 300m from the boundary of the Project Site |
·
63 – 92 dB(A) |
·
Annexes 5 and 13 of the EIAO-TM ·
Leq(30 min) 75dB(A) at 1m from the façade of residential
dwellings ·
Leq(30 min) 70dB(A) at 1m from the façade of educational
institutions which rely on openable window for ventilation (Leq(30 min)
65dB(A) during examinations) |
·
0 – 17 dB(A) |
- Quality PME prescribed in EPD’s
Quality Powered Mechanical Equipment (QPME) database - Temporary movable noise barriers,
full enclosure for PME - Good site practices ·
Only well-maintained plant should be operated on site and plant should
be serviced regularly ·
Silencers or mufflers on construction plant should be utilized and
should be properly maintained ·
Mobile plant should be sited as far away from sensitive uses as
possible ·
Machines and plant that may be in intermittent use should be shut down
between works periods or should be throttled down to a minimum ·
Plant known to emit noise strongly in one direction should, where
possible, be orientated so that noise is directed away from the nearby
sensitive uses ·
Material stockpiles and other structures should be effectively
utilized to screen noise from on-site construction activities |
·
No adverse residual impacts anticipated. |
Operation Impact |
|||||
Representative existing and planned residential developments,
educational institutions, clinic, etc. within 300m from the boundary of the
Project Site |
·
Predicted overall noise levels: 54 – 85 dB(A) ·
Predicted noise levels of the Project roads: 0 – 75 dB(A) ·
Contribution from Project roads: 0 – 13 dB(A) |
·
Annexes 5 and 13 of the EIAO-TM ·
L10(1 hour) 70dB(A) at 1m from the façade of residential
dwellings · 65
dB(A) at 1 m from the external façades of schools, places of public worship,
courts of law, places where unaided voice communication is required |
·
Exceedance of the noise criteria by up to 16 dB(A) ·
The exceedances are dominantly contributed by the existing roads at
some Representative NSRs, while at some other Representative NSRs, the
exceedances are dominantly contributed by Project Roads |
·
Low Noise Road Surfacing ·
Proposed Noise Barriers and
Enclosures |
·
No adverse residual impacts anticipated. |
Water Quality Impact |
|||||
Construction Impact |
|||||
Representative WSRs within 500m from the boundary of the Project Site |
The potential sources of water quality impact associated with the
construction works include: ·
Wastewater
from general construction activities ·
Construction
site run-off ·
Construction
work at modified watercourses in the east and west of Tsuen Tsing
Interchange, plus nearby Kwai Chung Park ·
Sewage
effluent from construction workforce ·
Accidental spillage of chemicals |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for the Western Buffer
and Victoria Harbour (Phase One) WCZs · Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM-DSS) · Practical Note for Professional Persons (ProPECC) PN 1/94 · Environmental, Transport and Works Bureau (ETWB)
Technical Circular (Works) No. 5/2005 · Water Supplies
Department (WSD) Water Quality Criteria (for flushing water intake) |
·
N/A |
·
Mitigation
measures and good site practices in ProPECCPN 1/94
“Construction Site Drainage ·
Practices
in ETWB TC (Works) No. 5/2005 “Protection of natural streams / rivers from
adverse impacts arising from construction works” ·
Waste
Disposal Regulation ·
Provision of interim treatment facilities, such as chemical toilets,
for construction workforce |
·
No adverse residual impacts anticipated. |
Operation Impact |
|||||
Representative WSRs within 500m from the boundary of the Project Site |
Potential water quality impacts associated with the operation phase
include: ·
Non-point source surface run-off from new impervious areas |
·
Annexes 6 and 14 of the EIAO-TM ·
Water
Quality Objectives for the Western Buffer and Victoria Harbour (Phase One)
WCZs ·
Technical Memorandum on Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) ·
ProPECC PN 5/93 |
·
N/A |
·
Adequate design in silt trap for the new road drainage which take into
account the guidelines in ProPECC PN 5/93. ·
Best Storm Water Management Practices and Storm Water Pollution
Control Plan to reduce non-point source pollution. |
·
No adverse residual impacts anticipated. |
Waste Management Implication |
|||||
Construction Impact |
|||||
C&D materials, excavated land-based sediment, chemical wastes and general refuse |
·
Around 900m3 of non-inert C&D materials (of which 800m3
will be reused) and 17,860m3 of inert C&D materials (of which
10,000m3 wil be reused) will be generated from site
clearance/set-up/plant mobilization, excavation/ foundation works, piling
works, pile cap/pier/abutment construction and slopeworks. ·
Around 2,100m3 of excavated land-based sediment expected to be generated
from construction of new bridge piers for modification of existing TWR
viaduct and new supporting columns for proposed noise enclosures. ·
Small quantity of chemical wastes in the order of a few cubic meters
per month. ·
Around 65kg per day of general refuse will be generated from
construction works and on-site staff and workers. |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Charges for Disposal of Construction Waste) Regulation
(Cap. 354N) ·
Land (Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public Health and Municipal Services Ordinance – Public Cleansing and
Prevention of Nuisances Regulation (Cap. 132BK) |
·
N/A |
·
Implementation of good site practices, waste reduction measures and
proper storage, collection and transport of waste. |
·
No adverse residual impact anticipated |
Operation Impact |
|||||
N/A |
·
It is expected that no waste will be generated during the operation
phase of the Project. |
·
N/A |
·
N/A |
·
No mitigation measures to be provided as the Project would not cause
adverse impacts. |
·
No adverse residual impact anticipated. |
Land Contamination |
|||||
Onsite construction
workers and future occupants |
·
No land contamination impact arising from the Project is anticipated. |
·
Annex 19 of the EIAO-TM ·
Guidance Note for Contaminated Land Assessment and Remediation (EPD,
2007) ·
Practice Guide for Investigation and Remediation of Contaminated Land
(EPD, 2011) ·
Guidance Manual for Use of Risk-based Remediation Goals for
Contaminated Land Management (EPD, 2007) |
·
N/A |
·
As no land contamination impact arising from the Project is
anticipated, no mitigation measures were considered necessary. |
·
No residual impact is anticipated. |
Landfill Gas Hazard |
|||||
Construction Phase |
|||||
Workers in excavations or temporary offices, stores, etc (those
directly in contact with the ground) sited within the landfill consultation
zone during construction or future operational maintenance |
·
Landfill
gas can present a number of potential hazards if not
adequately controlled. Landfill gas has the potential to cause asphyxiation, fire or explosion as it migrates into and accumulates in
confined air spaces during excavation and foundation work and/or maintenance
of drains or other underground services.
Other susceptible locations include site huts and similar poorly
ventilated enclosures that exist during construction. |
·
Annex
7 and Annex 19 of the TM ·
ProPECC
PN 3/96 – Landfill Gas Hazard Assessment for Development Adjacent to Landfill
·
EPD/TR8/97
– Landfill Gas Hazard Assessment Guidance Note |
·
Areas within the waste boundary and 250m Consultation Zone of GDBL |
·
Undertaking of a landfill gas
monitoring programme with implementation of actions in the event of
concentrations meeting thresholds stated in the EM&A manual as referenced
from Chapter 8 of the Landfill Gas Hazard Assessment Guidance Note |
·
No residual impacts are anticipated. |
Operation Phase |
|||||
As above in the event that deep excavations are required for future maintenance |
· As
above |
·
Chapter
8 of EPD/TR8/97 |
·
Areas within the waste boundary and 250m Consultation Zone of GDBL |
·
Implementing
measures stated in Chapter 8 of EPD/TR8/97 |
·
No residual impacts are anticipated. |
Impact on Cultural Heritage |
|||||
Construction Impact |
|||||
Cultural heritage
resources |
·
No impact would be anticipated during the construction phase. |
·
Antiquities and Monuments Ordinance
(Cap.53) ·
Environmental Impact Assessment Ordinance (EIAO) (Cap.499) and EIAO-TM
Annexes 10 and 19 ·
Guidance Note on Assessment of Impact on Sites of Cultural Heritage in
Environmental Impact Assessment Studies ·
Hong Kong Planning Standards and Guidelines Chapter 10 ·
Guidelines for Cultural Heritage Impact Assessment |
·
N/A |
· No mitigation measures
would be required. |
·
N/A |
Operation Impact |
|||||
Cultural heritage
resources |
·
No impact would be anticipated during the operation phase. |
·
Antiquities and Monuments Ordinance
(Cap.53) ·
Environmental Impact Assessment Ordinance (EIAO) (Cap.499) and EIAO-TM
Annexes 10 and 19 ·
Guidance Note on Assessment of Impact on Sites of Cultural Heritage in
Environmental Impact Assessment Studies ·
Hong Kong Planning Standards and Guidelines Chapter 10 ·
Guidelines for Cultural Heritage Impact Assessment |
·
N/A |
·
No mitigation measure would be required. |
·
N/A |
Landscape and Visual |
|||||
Construction Impact |
|||||
Landscape Reources (LRs) |
·
Moderate landscape impact on LR 4.1 (Tsuen Wan Park), LR 4.4 (Kwai
Chung Park), LR 4.5 (Kwai Shun Street Playground). ·
Slight/moderate landscape impact on LR 1 (Vegetation on Slope and
Roadside Planting). ·
Insubstantial landscape impact on LR 2 (Vegetation within G/IC Site),
LR 3 (Waterbody in Rambler Channel), LR 4.2 (Tsuen Wan Promenade and Tsuen
Wan Riviera Park), LR 4.3 (Other Open Spaces in Tsuen Wan), LR 4.6 (Other
Open Spaces in Kwai Tsing), LR 5 (Landscape Areas in Residential Development
in Tsuen Wan). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Preservation of Existing Vegetation ·
Transplanting of Affected Trees ·
Control of Night-time Lighting Glare ·
Erection of Decorative Screen Hoarding ·
Management of Construction Activities and Facilities ·
Reinstatement of Temporarily Disturbed Landscape Areas |
·
Slight/moderate landscape impact on LR 4.1, LR 4.4, LR 4.5. ·
Insubstantial/slight landscape impact on LR 1. ·
Insubstantial landscape impact on LR 2, LR 3, LR 4.2, LR 4.3, LR 4.6,
LR 5. |
Landscape Character
Areas (LCAs) |
·
Moderate landscape impact on LCA 1 (Transportation Corridor Landscape
LCA), LCA 5.1 (Tsuen Wan Park Urban Landscape LCA), LCA 5.2 (Kwai Chung Park
Urban Landscape LCA). ·
Slight/moderate landscape impact on LCA2.2 (Kwai Cung Industrial Urban
Landscape LCA), LCA 4.1 (Tsuen Wan Miscellaneous Urban Fringe Landscape LCA). ·
Insubstantial/slight landscape impact on LCA 4.2 (Kwai Chung
Muscellaneous Urban Fringe Landscape LCA). ·
Insubstantial landscape impact on LCA 2.1 (Tsuen Wan Industrial Urban
Landscape LCA), LCA 3.1 (Tsuen Wan Residential Urban Landscape LCA), LCA 3.2
(Kwai Chung Residential Landscape LCA), LCA 6 (Mixed Modern Comprehensive
Urban Development Landscape LCA), LCA 7 (Cemetery Landscape LCA), LCA 8
(Strait Landscape LCA). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Preservation of Existing Vegetation ·
Transplanting of Affected Trees ·
Control of Night-time Lighting Glare ·
Erection of Decorative Screen Hoarding |
·
Slight/moderate landscape impact on
LCA 1, LCA 5.1, LCA 5.2. ·
Insubstantial/slight landscape impact on LCA 2.2, LCA 4.1. ·
Insubstantial landscape impact on LCA 2.1, LCA 3.1, LCA 3.2, LCA 4.2,
LCA 6, LCA 7, LCA 8. |
Visually Sensitive
Receivers (VSRs) |
·
Substantial visual impact on REC-7. ·
Moderate visual impact on R-4, REC-2, REC-5, GIC-1, GIC-2, GIC-3,
GIC-6, T-1, T-6. ·
Moderate/substantial visual impact on R-7, R-8, O-1, O-2, O-3, O-5,
T-2, T-4, T-5. ·
Slight/moderate visual impact on R-2, R-3, REC-1, O-4. ·
Insubstantial/slight visual impact on R-1, R-5, REC-3, REC-4. ·
Insubstantial visual impact on other VSRs. |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Preservation of Existing Vegetation ·
Transplanting of Affected Trees ·
Control of Night-time Lighting Glare ·
Erection of Decorative Screen Hoarding ·
Management of Construction Activities and Facilities ·
Reinstatement of Temporarily Disturbed Landscape Areas ·
Reinstatement of Affected Slopes |
·
Moderate/substantial residual visual impact on REC-7. ·
Moderate residual visual impact on R-7, R-8, O-1, O-2, O-3, O-5, T-2,
T-4, T-5. ·
Slight/moderate residual visual impact on R-4, REC-2, REC-5, GIC-1,
GIC-2, GIC-3, GIC-6, T-1, T-6. ·
Insubstantial/slight residual visual impact on R-2, R-3, REC-1, O-4. ·
Insubstantial residual visual impact on other VSRs. |
Operation Impact |
|||||
Landscape Reources (LRs) |
·
Moderate landscape impact on LR 4.1 (Tsuen Wan Park), LR 4.4 (Kwai
Chung Park), LR 4.5 (Kwai Shun Street Playground). ·
Slight/moderate landscape impact on LR 1 (Vegetation on Slope and
Roadside Planting). ·
Insubstantial landscape impact on LR 2 (Vegetation within G/IC Site),
LR 3 (Waterbody in Rambler Channel), LR 4.2 (Tsuen Wan Promenade and Tsuen
Wan Riviera Park), LR 4.3 (Other Open Spaces in Tsuen Wan), LR 4.6 (Other
Open Spaces in Kwai Tsing), LR 5 (Landscape Areas in Residential Development
in Tsuen Wan). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory Planting for Loss of Existing Trees ·
Landscape Reinstatement and Treatment of Slopes ·
Maximization of Roadside Planting ·
Re-provision of Affected Open Space ·
Visually Pleasing Aesthetic Treatment on Noise Barriers and Noise Enclosures ·
Aesthetic Pleasing Design for Carriageways and Other Highways
Structures |
·
Slight/moderate residual impact during day 1 of operation and
insubstantial/slight residual impact during year 10 of operation on LR 4.1,
LR 4.4, LR 4.5. ·
Insubstantial/slight residual impact during day 1 of operation and
insubstantial residual impact during year 10 of operation on LR 1. ·
Insubstantial residual impact during day1 and year 10 of operation on
LR 2, LR 3, LR 4.2, LR 4.3, LR 4.6, LR 5. |
Landscape Character Areas (LCAs) |
·
Moderate landscape impact on LCA 1 (Transportation Corridor Landscape
LCA), LCA 5.1 (Tsuen Wan Park Urban Landscape LCA), LCA 5.2 (Kwai Chung Park
Urban Landscape LCA). ·
Slight/moderate landscape impact on LCA2.2 (Kwai Cung Industrial Urban
Landscape LCA), LCA 4.1 (Tsuen Wan Miscellaneous Urban Fringe Landscape LCA). ·
Insubstantial/slight landscape impact on LCA 4.2 (Kwai Chung
Muscellaneous Urban Fringe Landscape LCA). ·
Insubstantial landscape impact on LCA 2.1 (Tsuen Wan Industrial Urban
Landscape LCA), LCA 3.1 (Tsuen Wan Residential Urban Landscape LCA), LCA 3.2
(Kwai Chung Residential Landscape LCA), LCA 6 (Mixed Modern Comprehensive
Urban Development Landscape LCA), LCA 7 (Cemetery Landscape LCA), LCA 8
(Strait Landscape LCA). |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory Planting for Loss of Existing Trees ·
Landscape Reinstatement and Treatment of Slopes ·
Maximization of Roadside Planting ·
Re-provision of Affected Open Space ·
Visually Pleasing Aesthetic Treatment on Noise Barriers and Noise
Enclosures ·
Aesthetic Pleasing Design for Carriageways and Other Highways
Structures |
·
Slight/moderate residual impact during day 1 of operation and
insubstantial/slight residual impact during year 10 of operation on LCA 1, LCA 5.1, LCA 5.2. ·
Insubstantial/slight residual impact during day 1 of operation and
insubstantial residual impact during year 10 of operation on LCA 2.2, LCA
4.1. ·
Insubstantial residual impact during day 1 and year 10 of operation on
LCA 2.1, LCA 3.1, LCA 3.2, LCA 4.2, LCA 6, LCA 7, LCA 8. |
Visually Sensitive
Receivers (VSRs) |
·
Substantial visual impact on REC-7. ·
Moderate visual impact on R-4, REC-2, REC-5, GIC-1, GIC-2, GIC-3,
GIC-6, T-1, T-6. ·
Moderate/substantial visual impact on R-7, R-8, O-1, O-2, O-3, O-5,
T-2, T-4, T-5. ·
Slight/moderate visual impact on R-2, R-3, REC-1, O-4. ·
Insubstantial/slight visual impact on R-1, R-5, REC-3, REC-4. ·
Insubstantial visual impact on other VSRs. |
·
Annexes 10 and 18 of the EIAO-TM ·
Environmental Impact Ordinance Guidance Note 8/2010 |
·
N/A |
·
Compensatory Planting for Loss of Existing Trees ·
Landscape Reinstatement and Treatment of Slopes ·
Maximization of Roadside Planting ·
Re-provision of Affected Open Space ·
Visually Pleasing Aesthetic Treatment on Noise Barriers and Noise
Enclosures ·
Aesthetic Pleasing Design for Carriageways and Other Highways
Structures |
·
Moderate/substantial residual visual impact during day 1 of operation
and moderate residual visual impact during year 10 of operation on REC-7. ·
Moderate residual visual impact during day 1 of operation and
slight/insubstantial residual visual impact during year 10 of operation on
R-7, R-8, O-1, O-2, O-3, O-5, T-2, T-4, T-5. ·
Slight/moderate residual visual impact during day 1 of operation and
insubstantial/slight residual visual impact during year 10 of operation on R-4,
REC-2, REC-5, GIC-1, GIC-2, GIC-3, GIC-6, T-1, T-6. ·
Insubstantial/slight residual visual impact during day 1 of operation
and insubstantial residual visual impact during year 10 of operation on R-2,
R-3, REC-1, O-4. ·
Insubstantial residual visual impact during day 1 and year 10 of
operation on other VSRs. |