1.2 Description
of the Project
1.3 Environmental
Impact Assessment Study Brief
1.5 Objectives
of the EIA Study
1.6 Structure
of this EIA Report
Table 1.1 List of Designated Projects
Table 1.2 Structure of this EIA Report
Figure 1.1 Tuen Mun Bypass General
Layout Plan
o table of contents entries found.
(i)
Construction of a road tunnel of about 7.5 km long
running through Tuen Mun and Tai Lam Country Park, linking the TM-CLKT and the
YLH and KSWH;
(ii)
Construction of tunnel portals and associated
facilities at Tuen Mun Area 40 and Lam Tei Quarry;
(iii)
Construction of viaducts / at-grade roads from the
southern tunnel portal to the roads under planning near Lung Mun Road/Mong Fat
Street, and TM-CLKT at Tuen Mun Area 40;
(iv)
Provision of associated ventilation buildings,
administration building and other tunnel operation area;
(v)
Re-provision of facilities affected by the proposed
works;
(vi)
Provision of possible adits and associated
connection with existing roads;
(vii)
Construction of temporary explosive magazines in
Lam Tei Quarry, Siu Lam and Pillar Point; and
(viii)
Associated geotechnical works, ground investigation
(GI) works, drainage works, natural terrain hazard mitigation works, sewerage
works, traffic aids, directional signs, street lightings, Traffic Control and
Surveillance System, Electrical and Mechanical (E&M) works, environmental
mitigation measures, landscaping works, and services systems for inspection,
maintenance.
Table 1.1 List of Designated Projects
Item No. |
Designated Project |
Designated Project Element under the
Project |
Part I, Schedule 2 of the EIAO |
||
A.1 |
A
carriageway for motor vehicles that is an expressway, trunk road, primary
distributor road or district distributor road |
-
The
Project is a trunk road which comprises the construction and operation of a
dual two-lane carriageway connecting TM-CLKT in the south and YLH and
proposed Lam Tei Interchange (under Route 11) in the north. |
A.7 |
A road tunnel or railway
tunnel more than 800 m in length between portals |
-
The
Project comprises the construction of a road tunnel of about 7.5km long. |
K.10 |
A depot for the storage of,
or a manufacturing plant for the manufacture of, explosives (as defined by
section 2 of the Dangerous Goods Ordinance (Cap. 295)) |
-
There are 3 explosive magazines in
Lam Tei, Siu Lam and Pillar Point to be constructed for storage of explosives
for tunnel construction (NB these explosive magazines are for shared use with
Route 11). |
Q.1 |
All
projects involving earthworks, dredging works and other building works partly
or wholly in an existing or gazetted proposed country park or special area, a
conservation area, an existing or gazetted proposed marine park or marine
reserve, a site of cultural heritage, and a site of special scientific
interest |
-
The
Project comprise the construction of a road tunnel of running through the Tai
Lam Country Park and a temporary under adit underneath the edge of Tai Lam
Country Park. |
(i)
the overall acceptability of any adverse
environmental consequences that are likely to arise as a result of the Project;
(ii)
the conditions and requirements for the detailed
design, construction and operation of the Project to mitigate against adverse
environmental consequences wherever practicable; and
(iii)
the acceptability of residual impacts after the
proposed mitigation measures are implemented.
(i)
to describe the Project and associated works
together with the requirements and environmental benefits for carrying out the
proposed project;
(ii)
to identify and describe the elements of the
community and environment likely to be affected by the Project and/or likely to
cause adverse impacts to the Project, including both the natural and man-made
environment and the associated environmental constraints;
(iii)
to identify and quantify emission sources and determine
the significance of impacts on sensitive receivers and potential affected uses;
(iv)
to identify and quantify potential waste management
issues and impacts arising as a result of construction and operation activities
of the Project;
(v)
to identify and quantify contaminated land within
any project area for development works, and to propose measures to avoid
disposal in the first instance;
(vi)
to identify, evaluate and address any potential
ecological impacts arising from the Project including impacts on recognised
sites of conservation importance, as well as flora, fauna and natural habitats;
(vii)
to identify any potential landscape and visual
impacts and to propose measures to mitigate these impacts;
(viii)
to identify any adverse impacts on sites of
cultural heritage and to propose measures to mitigate these impacts;
(ix)
to identify potential hazard to life impacts, and
to propose mitigation measures to mitigate these impacts;
(x)
to propose the provision of infrastructure or
mitigation measures so as to minimise pollution, environmental disturbance and
nuisance during construction and operation of the Project;
(xi)
to investigate the feasibility, effectiveness and
implications of the proposed mitigation measures;
(xii)
to identify, predict and evaluate the residual
(i.e. after practicable mitigation) environmental impacts and the cumulative
effects expected to arise during the construction and operation phases of the
Project in relation to the sensitive receivers and potential affected uses;
(xiii)
to identify, assesses and specify methods, measures
and standards, to be included in the detailed design, construction and
operation of the Project which are necessary to mitigate these residual
environmental impacts and cumulative effects and reduce them to acceptable
levels;
(xiv)
to investigate the extent of the secondary
environmental impacts that may arise from the proposed mitigation measures and
to identify constraints associated with the mitigation measures recommended in
the EIA study, as well as the provision of any necessary modification;
(xv)
to design and specify the environmental monitoring
and audit requirements; and
(xvi)
to identify any additional studies necessary to
implement the mitigation measures of monitoring and proposals recommended in
the EIA report.
Table 1.2 Structure of this EIA Report
Chapter |
Title |
Aims |
1 |
Introduction |
Introduces the project background and the objectives of
the report |
2 |
Project
Descriptions |
Summarises the various development options and scope for
various environmental aspects Describes relevant main
construction/ engineering aspects of the recommended alignment |
3 |
Air
Quality Impact |
Presents the legislation, methodology, assessment and
recommendations for air quality impacts |
4 |
Noise Impact |
Presents the legislation, methodology, assessment and
recommendations for noise impacts |
5 |
Water Quality Impact |
Presents the legislation, methodology, assessment and
recommendations for water quality impacts |
6 |
Waste Management
Implications |
Presents the legislation, methodology, assessment and
recommendations for waste management |
7 |
Land Contamination |
Presents the legislation, methodology, assessment and
recommendations for land contamination |
8 |
Hazard to Life |
Presents the legislation, methodology, assessment and
recommendations for hazard to life impacts |
9 |
Landfill Gas Hazard |
Presents the legislation, methodology, assessment and
recommendations for landfill gas hazard impacts |
10 |
Ecological Impact
(Terrestrial) |
Presents the legislation, methodology, assessment and
recommendations for terrestrial ecological impacts |
11 |
Landscape and Visual |
Presents the legislation, methodology, assessment and
recommendations for landscape and visual impacts |
12 |
Impact on Cultural
Heritage |
Presents the legislation, methodology, assessment and
recommendations for cultural heritage impacts |
13 |
Environmental Monitoring
& Audit |
Presents the EM&A requirements and a detailed
implementation schedule of the recommended mitigation measures |
14 |
Summary of Environmental
Outcomes |
Presents a summary of the key environmental outcomes
arising from the EIA study |
15 |
Conclusion |
Summarises the findings and concludes the overall
acceptability of the project |