Table 12.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
Design Approach |
Environmental Problems Avoided and |
Adoption of environmentally friendly construction method (Section 2) |
· Adoption of quiet piling method to minimise the construction noise impact on nearby sensitive receivers. · Earthworks are carried out in phases to minimise the construction dust impact to nearby sensitive receivers. |
Avoidance of illegal dumping (Section 6) |
· The recommended preventive measures would avoid/minimise the chance of illegal dumping. |
Bird-friendly design for noise barriers (Section 8) |
· Minimise potential bird collision. |
Implementation of Environmental Monitoring and Auditing System (Section 11) |
· Ensure all the recommended measures are properly in place and their effectiveness. |