Table 1.1 Elements of Designated Project in this Project
Schedule 2 of the EIAO |
Designated Project Element under the Project |
|
Item A.1, Part I |
A carriageway for motor vehicles that is an expressway, trunk road, primary distributor road or district distributor road. |
The proposed roads listed below under the Project comprise primary distributor (PD) roads and district distributor (DD) roads.Proposed roads classified as PD: · A single 2-lane flyover (main ramp) and a single 1-lane flyover (side ramp) across Kai Leng Roundabout; and · A single 2-lane underpass underneath So Kwun Po Road.
Proposed roads classified as DD: · An at-grade road connecting San Wan Road and the proposed flyover; and · An at-grade road connecting the proposed flyover and Pak Wo Road. |
· Section 2 Project Description;
· Section 3 Key Findings of the Environmental Impact Assessment;
· Section 4 Environmental Monitoring and Audit (EM&A); and
· Section 5 Conclusion.
(i) Providing a new direct road link, referred to as So Kwun Po Link (SKPL), which comprises an at-grade road, an underpass, a single 2-lane flyover (main ramp) and a single 1-lane flyover (side ramp) connecting San Wan Road on the north side and Pak Wo Road on the south side of the SKPIC;
(ii) Realigning So Kwun Po Road between So Kwun Po Interchange (SKPIC) and Pak Wo Road;
(iii) Carrying out junction modification works at San Wan Road and Pak Wo Road;
(iv) Re-provisioning of the affected footpaths, cycle tracks and staircases; and
(v) Carrying out the associated roadworks, geotechnical works, landscape works, drainage works, utility works, traffic aids installation, traffic signal modification works, environmental mitigation measures, street lighting, street furniture and other ancillary works.
(a) construction of north-south link road of about 700m connecting Pak Wo Road and San Wan Road;
(b) reconstruction of sections of So Kwun Po Road near North District Park;
(c) widening of the north-western slip road from So Kwun Po Road to San Wan Road;
(d) reconstruction/realignment of So Kwun Po Road between Kai Leng Roundabout and Pak Wo Road;
(e) improvement works at the junction of San Wan Road and the proposed north-south link road;
(f) improvement works at the junction of Pak Wo Road and So Kwun Po Road;
(g) modification of the existing pedestrian subway connecting North District Park underneath So Kwun Po Road;
(h) construction of a lift and a staircase linking San Wan Road and elevated So Kwun Po Road;
(i) construction of a pedestrian subway across So Kwun Po Road near Pak Wo Road;
(j) re-provision of the skating rink within North District Park affected by the road works; and
(k) associated works including geotechnical, landscape, drainage, water, electrical and mechanical, environmental mitigations, street lighting and utilities works, as well as installation of street furniture and traffic aids.
Table 2.1 Tentative Phasing of Major Construction Works
Major Works |
Tentative Schedules |
At-grade Road Construction (Southern Portion) |
Nov 2025 to Jul 2030 |
At-grade Road Construction (Northern Portion) |
May 2026 to Dec 2028 |
So Kwun Po Link (SKPL) (Bridge Portion) |
Jun 2026 to Dec 2029 |
Table 2.2 Summary of Concurrent Projects
Project |
Project |
Construction |
Housing Development in Ching Hiu Road |
Civil Engineering and Development Department (CEDD) / |
2022 to 2030 |
Housing Development in Fanling Area 17 |
CEDD / HD |
2023 to 2031 |
Expansion of North District Hospital |
Architecture Service Department (ArchSD) / |
2021 to 2028 |
Utilities Works and Junction Improvement |
CEDD |
2024 to 2029 |
Reclaimed Water Supply to |
Water Supplies Department (WSD) |
2021 to 2026 |
Air Quality;
Noise;
Water Quality;
Waste Management;
Land Contamination;
Ecology;
Landscape and Visual; and
Cultural Heritage.
3.7.1 Ecological impact assessment for the Project was conducted following the EIA Study Brief and the guidelines in Annexes 8 and 16 of the EIAO-TM. Terrestrial and aquatic habitats identified within the 500m assessment area include agricultural land, channel, developed area, mixed woodland, orchard, plantation, pond and shrubland/grassland. In general, the habitats within the Project site and assessment area are of low ecological value as most of them are within or adjacent to the highly urbanized area that receives human disturbance.
3.7.2 The North District Park Egretry and Day Roost (NDPEDR), where both roosting and breeding activities of Black-crowned Night Heron are found, is located near the Project site boundary. In order to mitigate the disturbance to it during the construction phase, the following specific mitigation measures and monitoring are proposed:
3.7.3 However, the potential impact due to flight-line fragmentation of breeding and roosting ardeids at NDPEDR is considered minor, because only an insignificant number of flight paths will be affected. Besides, a minor potential disturbance impact is also anticipated for the operational disturbance to NDPEDR, as there is an existing disturbance that the ardeids might have already accommodated human disturbance, and there will be insignificant noise level contribution from the Project to the NDPEDR. No specific mitigation is needed for these potential impacts.
3.7.4 Potential bird collision during the operation phase due to the newly constructed noise barriers is another key potential impact arising from the Project. However, it is anticipated that bird collision may mainly occur for small birds rather than ardeids, as small birds usually fly faster, and the NDPEDR is located far away from the new noise barriers. To mitigate this, bird-friendly design should be adopted for these noise barriers when transparent panels are used.
3.7.5 With the implementation of the above mitigation measures, no unacceptable ecological impacts are anticipated to arise from the construction and operation of the Project.
Table 5.1 Summary of Environmental Impacts
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without Mitigation) |
Impact Avoidance Measures/ |
Residual Impacts |
Air Quality |
|||||
Construction Phase |
|||||
Representative ASRs within 500m from the boundary of the Project Site
|
The potential sources of air quality impact associated with the construction works include dust generated from construction sites.
|
· Annexes 4 and 12 of the EIAO-TM
|
Not Applicable |
Appropriate dust control measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices will be incorporated into the Contract Specifications and implemented throughout the construction phase. Regular dust monitoring (also incorporated into the Contract Specifications) will be conducted to ensure the relevant legal requirements and standards are complied with during the construction phase of the Project. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative ASRs (including existing and planned) within 500m from the boundary of the Project Site |
Predicted cumulative air pollutant concentrations (NO2, RSP, FSP) at ASRs with Project operation comply with the prevailing AQOs. |
· Annexes 4 and 12 of the EIAO-TM · Prevailing AQOs |
N/A |
No adverse air quality impact is anticipated during the operation phase of the Project, thus mitigation measure is deemed not necessary. |
No adverse residual impact is anticipated.
|
Noise |
|||||
Construction Phase |
|||||
Representative NSRs within 300m from the boundary of the Project Site |
69dB(A) to 99dB(A) |
· Annexes 5 and 13 of the EIAO-TM · Leq(30-min) 75dB(A) at 1m from the faηade of residential dwellings · Leq(30-min) 70dB(A) at 1m from the faηade of educational institutions (including kindergartens and nurseries) (Leq(30-min) 65dB(A) during examinations). · Leq(30-min) 70dB(A) at 1m from the faηade of places of public worship, courts of law, and hospitals and medical clinics |
Up to 24dB(A) |
Implementation of recommended noise mitigation measures including: · Quality PME prescribed in EPDs Quality Powered Mechanical Equipment (QPME) database. · Temporary movable noise barriers, full enclosure for PME. · Scheduling of construction activities. · Liaise with the schools management for the schedule of construction works to avoid carrying out noisy construction activities during the examination period. · Good site practices. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative NSRs (including existing and planned) within 300m from the boundary of the Project Site |
· Predicted overall noise levels: · Predicted noise levels of the Project roads: · Maximum Contribution from Project roads: |
· Annexes 5 and 13 of the EIAO-TM · L10(1-hour) 70dB(A) at 1m from the faηade of residential dwellings. · 65 dB(A) at 1m from the external faηades of educational institutions (including kindergartens and nurseries), places of public worship and courts of law. · 55dB(A) at 1m from the external faηades of hospitals and clinics. |
· Exceedance of the noise criteria by up to 11dB(A). · Maximum noise contribution by Project Roads at 2.9 dB(A) |
· Low Noise Road Surfacing (LNRS) of - - approximately 330m in length along the new southbound slip road connecting to Pak Wo Road; - approximately 350m in length along the new northbound and southbound slip roads connecting to the new flyover; and - approximately 110m in length along the realigned So Kwun Po Road between the SKPIC and Pak Wo Road; · Cantilever barrier (5m high with 2.5m at ∠45° cantilever) of about 80m in length along the eastern roadside of the new southbound slip road connecting to Pak Wo Road; · Cantilever barrier (5m high with 2.5m at ∠45° cantilever) of about 170m in length along the eastern roadside of the new northbound and southbound slip road connecting to the new flyover; · 3m and 5m high vertical barrier of about 100m and 90m respectively in length along the western roadside of the new northbound slip road connecting to the new flyover; · 3m and 5m high vertical barriers of about 100m and 50m respectively in length along the western roadside of the realigned So Kwun Po Road between the SKPIC and Pak Wo Road; and · 3m high vertical barrier of about 80m in length along the northern roadside of the new So Kwun Po Link connecting to San Wan Road. |
No adverse residual impact is anticipated. |
Water Quality |
|||||
Construction Phase |
|||||
Representative Water Sensitive Receivers (WSRs) within 500m from the boundary of the Project Site. |
The potential sources of water quality impact associated with the construction works include: · Wastewater from general construction activities; · Diversion/ modification of box culvert; · Construction site run-off; · Sewage from the construction workforce; and · Accidental spillage of chemicals |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for Deep Bay Water Control Zone · Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) · Practice Note for Professional Persons (ProPECC) PN1/94 |
Not Applicable |
· Mitigation measures and good site practices in ProPECC PN 1/94 Construction Site Drainage. · Guidelines in DSD Technical Circular No. 1/2017 Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage Systems. · Practices in Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes · Provision of interim treatment facilities, such as chemical toilets, for the construction workforce. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative WSRs within 500m from the boundary of the Project Site. |
Potential water quality impacts associated with the operation phase include surface run-off from new roads |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for Deep Bay Water Control Zone · Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) · Practice Note for Professional Persons (ProPECC) PN5/93 |
Not Applicable |
· Adequate design in silt trap for the new road drainage which takes into account the guidelines in ProPECC PN5/93. · Best Storm Water Management Practices and Storm Water Pollution Control Plan to reduce non-point source pollution. |
No adverse residual impact is anticipated. |
Waste Management Implications |
|||||
Construction Phase |
|||||
C&D
materials, |
· Around 5,690m3 of non-inert C&D materials and 53,688m3 of inert C&D materials will be generated from different construction works of the Project, including site clearance, minor slope and excavation works, as well as piling and superstructure works. · A small quantity of chemical waste in the order of a few hundred litres per month. · Around 227.5kg per day of general refuse will be generated from construction works and on-site staff and workers. |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C); · Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) · Land (Miscellaneous Provisions) Ordinance (Cap. 28) · Public Health and Municipal Services Ordinance Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK)
|
Not Applicable |
· Implementation of good site practices, waste reduction measures, Waste Management Plan (WMP) and proper storage, collection and transport of waste. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Not Applicable |
It is expected that no waste will be generated during the operation phase of the Project. |
Not Applicable |
Not Applicable |
No mitigation measure is provided as the Project would not cause adverse impacts. |
No adverse residual impact is anticipated. |
Land Contamination |
|||||
Onsite construction workers and future occupants |
Adverse land contamination impact arising from the Project is not anticipated. |
· Annex 19 of the EIAO-TM · Guidance Note for Contaminated Land Assessment and Remediation (EPD, 2007) · Practice Guide for Investigation and Remediation of Contaminated Land (EPD, 2011) · Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (EPD, 2007) |
Not Applicable |
As no adverse land contamination impact arising from the Project is anticipated, no mitigation measures were considered necessary. |
No adverse residual impact is anticipated. |
Ecology |
|||||
Construction Phase |
|||||
Representative Ecological Sensitive Receivers within 500m from the boundary of the Project Site |
· Temporary habitat loss of 0.095 ha developed area and 0.056 ha of plantation that is considered of insignificant potential impact. · Potential fragmentation of ardeid flight-lines that are considered as minor potential impact. · Indirect impact due to disturbance generated during construction to the NDPEDR that is considered as minor to moderate for the roosting activity; moderate for the breeding activity. · Indirect impact due to disturbance generated during construction on habitats and wildlife nearby other than the NDPEDR that is considered as insignificant. · Indirect impacts on the channelized section of Shek Sheung River due to surface runoff from works area that is considered as minor to moderate. |
Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) Annexes 8 and 16 |
Not applicable |
· Strictly use of non-percussive piling method within the 100m are of NDPEDR for all year around. Other noisy construction works within 100m area of the NDPEDR should also be avoided in breeding season as far as practicable · Works programme to be scheduled to minimize construction impacts to NDPEDR during peak month(s) of breeding season · A Construction Noise Management Plan shall be prepared before implementation of any construction works within 100m area of the NDPEDR during breeding season · Follow mitigation measures stated in Chapter 4 - Noise · Mitigation for reducing night-time light glare from reaching the NDPEDR · Regular monitoring of the ardeid day roosting and breeding activities at the NDPEDR. · Follow mitigation measures stated in Chapter 5 Water Quality · Good site practice
|
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Representative Ecological Sensitive Receivers within 500m from the boundary of the Project Site |
· Permanent habitat loss of 0.19 ha developed area and 0.46 ha of plantation that is considered of insignificant potential impact. · Indirect impact to habitat that is considered of insignificant potential impact. · Indirect impact due to disturbance generated from the operation to the nearby habitats and wildlife that is considered of minor. · Potential bird collision that is considered of minor to moderate potential impact. · Potential direct mortality of fauna that is considered of insignificant potential impact. · Indirect impacts on the channelized section of Shek Sheung River due to surface runoff during operation that is considered as insignificant. |
Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) Annexes 8 and 16
|
Not applicable |
· Adopting bird-friendly design. · Regular monitoring of the ardeid day roosting and breeding activities at the NDPEDR. |
Permanent loss of 0.46 ha of plantation which is considered of insignificant potential impact, the residual impact is considered acceptable.
|
Landscape and Visual |
|||||
Note: Individual landscape resources/character areas and visual sensitive receivers shall refer to Chapter 9 LVIA of the EIA report. |
|||||
Construction Phase |
|||||
Landscape Resources (LRs) |
· Moderate landscape Impact on LR2.1 & LR3.1 · Slight landscape Impact on LR3.2 · Negligible landscape impact on other LRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Re-provisioned Cycle Track and Footpath · Preservation of Existing Vegetation · Transplanting of Affected Trees · Good Site Practice · Reinstatement of Temporarily Disturbed Landscape Areas |
· Moderate residual landscape impact on LR3.1 · Slight residual landscape Impact on LR2.1 & LR3.2 · Negligible residual landscape impact on other LRs |
Landscape Character Areas (LCAs) |
· Moderate landscape Impact on LCA2 · Slight landscape impact on LCA1 & LCA3 · Negligible landscape impact on other LCAs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Re-provisioned Cycle Track and Footpath · Preservation of Existing Vegetation · Transplanting of Affected Trees · Good Site Practice · Reinstatement of Temporarily Disturbed Landscape Areas |
· Slight residual landscape impact on LCA1, LCA2 & LCA3 · Negligible residual landscape impact on other LCAs |
Visually Sensitive Receivers (VSRs) |
· Substantial Impact on VSR5, VSR15, VSR24 · Moderate Impact on VSR1, VSR2, VSR3, VSR4, VSR6, VSR7, VSR8, VSR9, VSR10, VSR11, VSR12, VSR13, VSR14, VSR16, VSR17, VSR18, VSR19, VSR20, VSR21, VSR23, VSR25, VSR26, VSR27, VSR28, VSR30 · Slight Impact on VSR29 · Negligible visual impact on other VSRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Re-provisioned Cycle Track and Footpath · Preservation of Existing Vegetation · Transplanting of Affected Trees · Control of Night-time Lighting Glare · Good Site Practice · Erection of Decorative Screen Hoarding · Reinstatement of Temporarily Disturbed Landscape Areas |
· Moderate residual visual impact on VSR1, VSR2, VSR3, VSR4, VSR5, VSR6, VSR7, VSR8, VSR9, VSR12, VSR15, VSR21, VSR23, VSR24, VSR25, VSR26, VSR28, · Slight residual visual impact on VSR10, VSR11, VSR13, VSR14, VSR16, VSR17, VSR18, VSR19, VSR20, VSR27, VSR29, VSR30 · Negligible residual visual impact during day 1 and year 10 of operation on other VSRs. |
Operation Phase |
|||||
Landscape Resources (LRs) |
· Moderate landscape Impact on LR2.1 & LR3.1 · Negligible landscape impact on other LRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Compensatory Tree Planting · Roadside Planting · Provision of Aesthetic Pleasing Treatment on Noise Barriers · Aesthetically pleasing design for carriageways and other highways structures |
· Slight residual impact during day 1 of operation and remain slight residual impact during year 10 of operation on LR3.1 · Slight residual impact during day 1 of operation and insubstantial residual impact during year 10 of operation on LR2.1 · Negligible residual impact during day 1 and year 10 of operation on other LRs |
Landscape Character Areas (LCAs) |
· Moderate landscape Impact on LCA2 · Negligible landscape impact on other LRs |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Compensatory Tree Planting · Roadside Planting · Provision of Aesthetic Pleasing Treatment on Noise Barriers · Aesthetically pleasing design for carriageways and other highways structures |
· Slight residual impact during day 1 of operation and remain slight residual impact during year 10 of operation on LCA2 · Negligible residual impact during day 1 and year 10 of operation on other LCAs |
Visually Sensitive Receivers (VSRs) |
· Substantial visual impact on VSR5, VSR15, VSR24 · Moderate visual impact on VSR1, VSR2, VSR3, VSR4, VSR6, VSR7, VSR8, VSR9, VSR10, VSR11, VSR12, VSR13, VSR14, VSR16, VSR17, VSR18, VSR19, VSR20, VSR21, VSR23, VSR25, VSR26, VSR27, VSR28, VSR30 · Slight visual impact on VSR29 |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN 8/2010 (Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
Not Applicable |
· Compensatory Tree Planting · Roadside Planting · Provision of Aesthetic Pleasing Treatment on Noise Barriers · Aesthetically pleasing design for carriageways and other highways structures |
· Moderate residual impact during day 1 of operation and slight residual impact during year 10 of operation on VSR4, VSR5, VSR15, VSR25, VSR26. · Slight residual impact during day 1 of operation and during year 10 of operation on VSR1, VSR2, VSR6, VSR8, VSR9, VSR21, VSR23, VSR24. · Slight residual impact during day 1 of operation and insubstantial residual impact during year 10 of operation on VSR11, VSR12, VSR13, VSR28 · Negligible residual visual impact during day 1 and year 10 of operation on other VSRs. |
Cultural Heritage |
|||||
Construction Phase |
|||||
Cultural heritage resources |
The proposed works areas of the Project are located in an area with no archaeological potential. No archaeological survey is required. The potential impact on archaeological resources is not anticipated.
|
· Annexes 10 and 19 of the EIAO-TM · Antiquities and Monuments Ordinance · Hong Kong Planning Standards and Guidelines (HKPSG) · Guidelines for Cultural Heritage Impact Assessment |
Not Applicable |
· As no declared or proposed monuments and government historic sites identified by the Antiquities and Monuments Office (AMO) have been identified, no impact on these cultural heritage resources is anticipated. Also, there are sufficient separation distances between the Project site and the built heritage items. Therefore, no mitigation measures were considered necessary. · The project proponent and his/her contractor are required to inform AMO immediately when any antiquities or supposed antiquities under the Antiquities and Monuments Ordinance (CAP.53) are discovered during the course of works. |
No adverse residual impact is anticipated. |
Operation Phase |
|||||
Cultural heritage resources |
No impact would be anticipated during the operation phase. |
· Annexes 10 and 19 of the EIAO-TM · Antiquities and Monuments Ordinance · Hong Kong Planning Standards and Guidelines (HKPSG) · Guidelines for Cultural Heritage Impact Assessment |
Not Applicable |
No mitigation measure would be required. |
Not Applicable |
([1]) As Year 2041 would be the peak traffic forecast year within 15 years (Year 2030 to Year 2045) upon the completion year with reference to the population projection data in Hong Kong Population Projections 2020-2069 published by Census and Statistics Department (C&SD), assessment year in 2041 has been adopted for the traffic noise impact assessment to represent the worst-case scenario.