·
Widening
of an approximately 1000-metre-long at-grade road section (with 20m long x 8m
wide bridge deck at Shui Fu Road) of YLH between Lam Tei
Quarry Interchange (LTQI) and Tin Shui Wai West
Interchange (TSWWI) (the road levels at about +24
to +37 mPD) from existing dual-three lane to
dual-four lane (additional 7.3m width carriageway) at
eastbound and one side of the existing YLH supported by slope works, and existing central divider will be adjusted toward south between LTQI and future Ping Shan South
Housing Development (PSS), and toward north between PSS and TSWWI (see Figure 2.3a 2.3c);
·
Widening
of an approximately 600-metre-long at-grade road section of YLH between Tin
Shui Wai West Interchange and Tong Yan San Tsuen Interchange (the road levels
at about +14 to +19 mPD) from existing dual-three
lane to dual-four lane (additional 7.3m width carriageway) at westbound and one
side of the YLH support by retaining structures, and existing central divider
will be adjusted toward south between TSWWI and TYSYI (see
Figure
2.3d 2.3e);
·
Widening
of an approximately 300-metre-long at-grade slip road connecting Hung Tin Road
(southbound) to Yuen Long Highway (eastbound) (the road levels at about +13 to
+14 mPD) from existing one lane to two lanes
(additional 3.65m width carriageway) support by retaining structures (see Figure 2.3d);
·
Associated
works including civil, geotechnical, slope, road drainage, waterworks,
utilities, public lighting, landscaping works, sign gantries modification,
noise barrier upgrading/re-provisioning works due to the widening of Yuen Long
Highway, traffic control and surveillance system, re-provisioning of facilities
affected by the proposed road works and environmental mitigation measures; and
·
The
interfacing works with other projects including.
- Proposed waterworks along YLH eastbound (between Tan Kwai Tsuen Road and Hung
Tin Road) under Agreement No. CE 71/2020 (CE) - Hung Shui Kiu
/ Ha Tsuen New Development Area
- Proposed roadworks along YLH
westbound (between TYSYI and TSWWI) under Agreement Nos. CE 58/2019(CE) &
CE 16/2022(CE) for Yuen Long South Development
- Proposed roadworks at TSWWI and at
slip road connecting Hung Tin Road (northbound) under Agreement No. CE
16/2022(CE) for Yuen Long South Development
- Proposed roadworks along YLH
eastbound (between Tai To Tsuen Road and TSWWI) under
Agreement No. CE 16/2022(CE) for Yuen Long South Development
Without Project Scenario
With Project Scenario
Table 2.1 Summary of Environmental Benefits and Disbenefits With and Without the Project
Scenarios |
Environmental
Benefits |
Environmental
Disbenefits |
With
Project |
·
improving traffic
performance which leading to less traffic congestion and lower vehicular
traffic emissions ·
establishing noise
mitigation measures |
·
C&D materials will be generated ·
The air quality and noise impact imposed on
the existing Air Sensitive Receivers/ Noise Sensitive Receivers during
construction stage. ·
Although there is a vehicular emission
reduction owing to less traffic congestion for "with
project", it is possible that there is a potential to have higher air
quality impacts on the ASRs which are located closer to the widened road of
the project. |
Without
Project |
·
No construction and demolition wastes generated ·
No construction-related environmental impacts
to the area ·
No additional land requirement avoiding
potential disturbance to the nearby environment |
·
Road traffic congestion could not be
relieved, and the associated air and noise pollution to the existing Air
Sensitive Receivers/ Noise Sensitive Receivers will get worse ·
Miss an opportunity to relieve environmental impacts to existing and planned Air
Sensitive Receivers/ Noise Sensitive Receivers |
Table 2.2 Evaluation of Different Widening Schemes
General
Description |
Scheme
1 |
Scheme 2 |
Scheme 3
(Recommended) |
-
Section of YLH between LT and TSWWI |
Widening from
dual 3-lane to dual 4-lane toward west |
Widening
from dual 3-lane to dual 4-lane toward west |
Widening
from dual 3-lane to dual 4-lane toward west |
-
Section of YLH at TSWWI |
No widening
works |
Widening
from dual 3-lane to dual 4-lane toward west with extensive bridgeworks |
No widening
works |
- Section of
YLH between TSWWI and TYSY |
Widening
from dual 3-lane to dual 4-lane both south and north |
Widening
from dual 3-lane to dual 4-lane toward north |
Widening from
dual 3-lane to dual 4-lane toward south |
Land
Matters |
More land
lots required. More slope works required.
|
More land
lots required. More extensive slope works required. Encroachment
to existing Hop Hing Building located at north of YLH near TYSY |
Less land
lots required. Less slope works required. |
Utility
Diversion |
More impact
to existing utility |
Extensive
impact to existing utility |
Less impact
to existing utility |
Interface
with planned projects |
Encroachment to other planned projects
is avoided |
Extensive
bridgeworks is anticipated at TSWWI where there is
planned improvement works of TSWWI under Yuen Long South Development Large-scale
temporary traffic arrangement at TSWWI would be required and induce traffic
congestion |
Encroachment to other planned projects
is avoided |
Engineering
& Constructability |
Less
efficiency due to more slope works involved |
Less
efficiency due to more slope works and extensive bridgeworks involved |
More
efficiency with less slope works involved |
Road
safety |
Design
complies with road safety |
Design
complies with road safety |
Design
complies with road safety |
Construction
Programme |
Longer
construction period. |
Longer
construction period. |
Shorter
construction period. |
Public
disruption |
Longer
duration of public disruption due to longer construction period |
Longer
duration of public disruption due to longer construction period |
Shorter
duration of public disruption due to shorter construction period |
Cost
Implication |
Higher
construction cost |
Higher construction
cost |
Lower
construction cost |
Air Quality
Impact |
More
potential air quality impact during constructional stage due to more slope
works |
More
potential air quality impact during constructional stage due to more slope
works |
Less air
quality impact during construction as less slope works and shorter duration
of construction |
Noise Impact |
More
potential construction noise impact due to longer construction period and
more slope works |
More
potential construction noise impact due to longer construction period and
extensive slope works |
Less
construction noise impact as less slope works and shorter duration of
construction |
Water
Quality Impact |
No natural
steam would be affected |
No natural
steam would be affected |
No natural
steam would be affected |
Waste
Management |
More C&D
material generated from slope works and utility diversion |
More C&D
material generated from extensive slope works and utility diversion |
C&D
material could be minimized as less excavation works |
Ecological
Impact |
More habitat
(such as Agricultural Land at Fui Sha Wai near
north of TSWWI) loss as a result of more land
required. Longer
construction period may cause more disturbance impact. |
More habitat
(such as Agricultural Land at Fui Sha Wai near
north of TSWWI) loss as a result of more land
required. Longer
construction period may cause more disturbance impact. |
Less habitat
loss as a result of less land requirement. Shorter
construction period may cause less disturbance impact. |
Landscape
and Visual Impact |
Less tree
preserved due to more land requirement |
Less tree
preserved due to more land requirement |
More tree
preserved due to less land requirement |
Cultural
Heritage Impact |
No cultural
heritage would be affected |
No cultural heritage
would be affected |
No cultural
heritage would be affected |
Avoidance of encroachment to existing Hop Hing
Building located at north of YLH near TYSY
Minimisation of air quality impact during construction stage
Minimisation of noise impact during construction
stage
Minimisation of C&D Material
1)
Form fill/cut slopes or retaining structures along
the northern side of YLH eastbound as site formation for utilities diversion of
the affected trunk utilities;
2)
Laying the new trunk utilities or watermains by the contractor or
utilities undertakers and then connection to the unaffected section of the
trunk utilities;
3)
Carrying out foundation works, either base slabs for retaining
structures/box structures for subways or piling for the bridge structures;
4)
Construct piers or upper part of retaining structures
5)
Erecting bridge deck by precast segment or cast-situ;
6)
Backfilling retaining structures or embankments and then drainage works and parapet works; shifting the both bounds of YLS to
north after replacing central median by temporary barriers with using TTA;
7)
After shifting the YLH to north, removing the existing noise barriers
and foundation of new noise barriers at YLH westbound would be carried out
while the new noise barriers at eastbound will also be erected; afterward noise
barrier panels would be erected;
8)
Site formation for road and road pavement would be done for new carriageway;
9)
Finally sign faces for sign gantry will be updated and replaced for the
new dual 4-lane system and TCSS if necessary.
Table 2.3 Comparison of Different Formwork Systems
Construction
Methods |
Wooden Formwork |
Steel Formwork |
Merits |
Wood is readily available and
relatively inexpensive Wood formwork is lightweight, easy to
handle |
Steel is a strong and durable material
and recyclable Steel formwork is highly durable and
can withstand harsh weather conditions, moisture, and repeated use Steel is stronger than wood and
provides excellent structural stability |
Demerits |
Wooden formwork is susceptible to
damage from moisture, weather conditions, and repeated use. Less recyclable material compared to steel Wood may deform or warp over time and additional
supports and bracing are often required for concrete pouring |
Steel is more expensive than wood. Steel formwork is heavier. Mechanical
equipment used for handling is required. |
Table 2.4 Comparison of Different Construction Methods for bridge deck at Shui Fu Road
Construction
Methods |
Precast Segment |
Cast-situ |
Merits |
Minimise concrete mixing truck travelling in
site area, thus minimise potential air and noise impact Shorten construction time, minimising on-site potential environmental impacts and
cumulative environmental impacts with concurrent projects. Carry out precasting
works in fabrication yard away from the site Better control of quality and
workmanship for works in fabrication yard. |
Conventional construction method and
require relatively less special skilled labour when
comparing with other construction methods. Durable and less maintenance cost. |
Demerits |
Require another trade of skilled
workers and additional construction equipment for erecting precast segments. |
Longer construction time to carry out
bridge deck construction, i.e. span by span. Required concrete mixing truck and
concrete pump truck travelling in site area, thus induce potential air and
noise impact. Require substantial temporary steel
platform / falsework for construction of the bridge deck section over
existing live traffic. Use of timber formwork, thus more
C&D waste/ materials will be generated. |
Table 2.5 Construction Methods
Construction Activities |
Construction Methodology |
Site
Clearance & Utility Diversion |
The
proposed site clearance and utilities works include site formation, temporary
road, drainage systems and utility diversion by undertakers to be carried out
in advance before road widening works for YLH. |
ELS
Works (Sheet piling and excavation works) |
The
excavation and lateral support (ELS) is used for
slope cutting or excavation in trench or area. ELS is to be carried out layer
by layer together with excavation and installation of lateral supports. The
surplus excavated inert Construction & Demolition material would be
reused within the Project areas as far as practicable. Conventional backhoe
will be used for the proposed earthworks. |
Geotechnical
Works |
Near
the hillside, soil nails or dowl bars will be used to reinforce the cut slope
works. |
Foundation
and Substructure Works (Rebar fixing and concreting works) |
The
L-shape retaining walls will be in form of reinforced concrete (RC) L-shape
walls founded at-grade. For
the substructures for retaining wall on piles and bridges, bored
piles/pre-bored H-piles will be used. Piling plant, crawl cranes will be
deployed for the works. Desilting tanks will be used to recycle benite as agent for temporary support for the bored
piling works. Temporary
drainage arrangement will also be developed during the construction stage to
avoid impact to the watercourse. |
Road
Upgrading Works (Backfill and reinstatement works) |
Road
works will be carried out section by section and the length of each active
section of the construction site is about 100 m subject to approved temporary
traffic arrangement (that the existing three-lane traffic in each direction
of Yuen Long Highway will be maintained throughout the construction period,
and no adverse environmental implications due to temporary traffic
arrangement is anticipated). The
works involve earthworks, utilities laying, backfilling, laying of sub-base
materials and reinstatement of bituminous or concrete pavement with low-noise
road surfacing as applicable on some road sections. |
Construction
of Superstructure Works Bridges and Noise Mitigation Works |
Regarding
the superstructure, given the long total length of noise barriers and limited
working space, prefabricated frames and panels will be usually adopted and
erected on site with appropriate temporary traffic arrangement. The
superstructure will be in form of typical steel structures. For
the bridges at Shui Fu Road to form additional carriageway width for widening
works, precast beams or segments will be used and precast in offsite area in
China or other parts of Hong Kong and transfer them to Hong Kong on site for
erection. Appropriate
temporary traffic arrangement will be used at local road (Fui
Sha Wai South Road between Ping Shan South and TSWWI) as most widening works
will be carried out outside the existing YLH. Heavy
lifting machine will be deployed for the precast beams or segment erection. |
Street
Furniture |
Street
furniture works at roadside and slopes will be provided after road widening
works and site formation works. |
Table 2.6 Key Construction Works of the project
Description |
Tentative Construction Period |
Potential environmental impact |
Mitigation measures |
Utilities
Diversion works at the eastern portion (northern side
of YLH eastbound section between Ping Shan South and TSWWI) |
Q3
2026 Q4 2028 |
potential
dusty work water
quality impact due to construction site drainage |
Mitigation
measures for air quality and water quality impact were proposed in Section 3 and 5 respectively |
Site
Formation at |
Q1
2029 Q1 2030 |
potential
dusty work construction
noise impact water
quality impact due to construction site drainage |
Mitigation
measures for air quality, noise and water quality impact were proposed in Section 3, 4 and 5
respectively |
Road
Widening at YLH eastbound |
Q1
2030 Q2 2031 |
construction
noise impact water
quality impact due to construction site drainage |
Mitigation
measures for noise and water quality impact were proposed in Section 4 and 5
respectively |
Site
Formation at |
Q1
2030 Q3 2030 |
potential
dusty work construction
noise impact water
quality impact due to construction site drainage |
Mitigation
measures for air quality, noise and water quality impact were proposed in Section 3, 4 and 5
respectively |
Road
Widening at YLH westbound |
Q2
2031 Q4 2031 |
construction
noise impact water
quality impact due to construction site drainage |
Mitigation
measures for noise and water quality impact were proposed in Section 4 and 5
respectively |
Noise
Barrier Construction and associated works |
Q1
2023 Q4 2032 |
construction
noise impact |
Mitigation
measures for noise impact was proposed in Section 4 |
Table 2.7 Concurrent Projects
Item |
Agreement no. and Project Title |
Description |
Tentative Implementation |
Potential Cumulative Impacts |
|
Construction phase |
Operation phase |
||||
1 |
CE 42/2016 (CE) |
A new Green transit system in Hung Shui Kiu/Ha
Tsuen New Development Area |
Phase 1:
Year 2027 2030/31 Phase 2:
Year 2032 2036 Phase 3: Year 2034
2038 |
Cumulative
construction dust impact was evaluated in Section 3 Cumulative
construction noise impact was evaluated in Section 4 |
Cumulative
operation noise impact arisen from the concurrent project was considered in
this study |
2 |
CE
13/2021 (HY) |
A new highway linking
Lam Tei and Lantau |
No later than Year
2033 |
Cumulative construction
dust impact was evaluated in Section 3 |
Cumulative
operation noise and air impact arisen from the concurrent project was
considered in this study |
3 |
CE 75/2017(CE) Site Formation and Infrastructure
Works for Public Housing Developments at Long Bin, Yuen Long |
A public housing
development to meet housing needs |
Year 2020 - 2026 |
Not
anticipated in view of no overlapping construction period |
Not
anticipated in view of the nature of the concurrent project. |
4 |
CE 92/2017(CE) Site Formation and
Infrastructure Works for Public Housing Development near Tan Kwai Tsuen, Yuen
Long |
A public housing
development to meet housing needs |
Year 2022 - 2027 |
Not
anticipated in view of no overlapping construction period |
Not
anticipated in view of the nature of the concurrent project. |
5 |
CE 32/2017(CE), CE 58/2019(CE) &
CE 16/2022(CE) Yuen Long South
Development |
A new development
area to meet housing needs |
2022 2038 |
Cumulative
construction dust impact was evaluated in Section 3 Cumulative
construction noise impact was evaluated in Section 4 |
Not
anticipated in view of the nature of the concurrent project. |
6 |
CE 71/2020(CE) Hung Shui Kiu / Ha Tsuen New Development Area |
A new development
area to meet housing needs |
2020 2038 |
Cumulative
construction dust impact was evaluated in Section 3 Cumulative
construction noise impact was evaluated in Section 4 |
Not
anticipated in view of the nature of the concurrent project. |
7 |
CE 36/2018(CE) Preliminary Technical
Review on Potential Sites in Yuen Long Areas 13 and 14 for Housing
Development |
A public housing
development to meet housing needs |
Year 2025 - 2032 |
Cumulative
construction dust impact was evaluated in Section 3 |
Not
anticipated in view of the nature of the concurrent project. |
Table 2.8 Key comments received during public inspection of the project profile
Key Issue |
Public
Comment |
Action /
Response |
Air Quality and Health
Index |
There were concerns
about many concurrent development projects interfacing with the project. A
comprehensive cumulative air pollution impact assessment was then recommended
during the EIA |
The cumulative air
quality impact during operation phase which takes into
account the concurrent projects in the vicinity has also been
included. Continuous monitoring
of dust will be conducted during construction phase. |
Traffic and Transport
Impact |
There were concerns
about traffic jam issue during construction phase. Adverse air quality impact
might be resulted due to the traffic jam during the construction phase. |
Construction Traffic
Impact Assessment has been conducted for the project. No adverse impact to
the traffic is anticipated. |
Waste
Management |
There were concerns
about the waste management of construction and demolition (C&D)
materials, chemical wastes, refuse, etc. Also, illegal disposal of waste
should be monitored and penalized. |
The waste management
implication has been assessed in the EIA, Chapter 6. Trip-ticket system would
be adopted to monitor the disposal of C&D materials at public filling
facilities and landfills and to control fly-tipping. Stockpiling area
should be provided with covers and water spraying system to prevent materials
from wind-blown or being washed away. Proper construction site drainage
should be provided. |
Bird
Collision |
There were concerns
about bird collision to noise barriers/enclosures and screen hoardings |
It is anticipated
that the number of birds passing through is low due to the highly disturbed
nature as recorded in the assessment. Bird friendly design of noise barriers
would be provided to further reduce the bird collision. |
Site
Boundary |
There was concern
about the extend of the environmental impact
assessment, i.e. the project limit mentioned in
drawing no. HMW2003-SK1029. |
The assessment area
for the EIA study, as specified in the EIA Study Brief, has been followed. |
Table 2.9 Relevant EPs
EP no. |
EP Title |
Location |
EP-163/2003/H |
Deep Bay Link and
Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung (Lam Tei to Tan
Kwai Tsuen Section) |
Yuen Long Highway
(section between Lam Tei and Tan Kwai Tsuen) |
EP-141/2002/A |
Widening of Yuen Long
Highway between Lam Tei and Shap
Pat Heung Interchange |
Yuen Long Highway
(section between Lam Tei and Shap
Pat Heung) |