TABLE OF CONTENTS

 

17        Conclusion.. 17-1

17.1       Conclusion of EIA Study. 17-1

 

 

List of tables

Table 17.1         Summary of Key Environmental Outcomes and Benefits. 17-2

 

 

LIST OF Appendices

Appendix 17.1

Key Assessment Assumptions and Limitation of Assessment Methodologies

Appendix 17.2

Summary of Environmental Impacts

 

 


17               Conclusion

17.1           Conclusion of EIA Study

17.1.1       This EIA Report provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available during the course of EIA Study.

17.1.2       The assessment was conducted, in accordance with EIAO-TM, covering the following environmental issues:

         Air Quality;

         Airborne Noise;

         Ground-borne Noise;

         Water Quality;

         Sewerage and Sewage Treatment Implications;

         Waste Management Implications;

         Land Contamination;

         Ecology (Terrestrial and Aquatic);

         Fisheries;

         Landscape and Visual;

         Cultural Heritage; and

         Hazard to life.

17.1.3       The findings of this EIA Study determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operational phases.  The Implementation Schedule listing the recommended mitigation measures is presented in Appendix 15.1.

17.1.4       Overall, the EIA Study predicted that the Project, with the implementation of the recommended mitigation measures, would be environmentally acceptable with no adverse residual impacts on the environmentally sensitive receivers and resources.  The key environmental outcomes and benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project are summarized in Table 17.1 below.  The summary of key assessment assumptions and limitation of methodologies and the summary of environmental impacts are presented in Appendices 17.1 and 17.2 respectively.

17.1.5       The various sections of this EIA Report present the measures to minimise the potential environmental impacts associated with the Project throughout the construction and operational phases. The key measures to minimise the environmental impacts are summarised in Section 16.6.

17.1.6       Environmental monitoring and audit (EM&A) requirements have been recommended, where necessary, to check on project compliance of environmental legislation and standards. These are presented in a separate, stand-alone EM&A manual.

Table 17.1    Summary of Key Environmental Outcomes and Benefits

Environmental / Social Benefits of the Project

     Provide a more efficient and environmental friendly railway services to the existing and future communities in Northwestern New Territories to encourage greater use of the whole railway system, by enhancing coverage, and thereby improving the mobility and transport connections to the existing TML and EAL, alleviating traffic congestion, which in turns reducing the road traffic noise and vehicular emissions; and

     Unleash the development potential of the Northwestern New Territories.

Environmentally Friendly Design and Options

     Avoidance / Minimisation of aboveground encroachment to ecological sensitive areas (e.g. Mai Po Inner Deep Bay Ramsar Site, Sha Po Marsh, WCA, WBA and Country Park);

     Adoption of environmentally friendly construction method (e.g. MiC and DfMA) to minimize the impacts to surrounding receivers;

     Adopt underground scheme and proper design (i.e. decking at NTD and noise canopies at the trough area) to avoid/minimise the operational airborne rail noise impact;

     Adoption of proactive measures to avoid illegal dumping;

     Implementation of environmental monitoring and auditing system; and

     Integration of sustainability initiatives (e.g. green roof and photovoltaic panels for power generation) into architectural design during design stage.

Air Quality Impact

Construction Phase

     Major potential air quality impacts during the construction works of the Project would be construction dust arising from site clearance, site formation, demolition works, excavation, tunnelling works, backfilling, spoil handling, vehicle movement on haul roads, mucking-out activities, and wind erosion of exposed works sites.

     With the implementation of recommended dust suppression measures including regular watering on active works areas, exposed areas, unpaved haul roads and unloading point of spoils generated by TBM excavation; provision of hoarding; installation of blast door; provision of filtration system with watering and dust collector at ventilation exhaust for tunneling works by drill-and-blast; and mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation and EM&A programme, it is anticipated that there would be no significant dust impact on the air sensitive receivers.

Operational Phase

     No adverse air quality impact is expected from the operation of the Project with emission free electric-powered rail system. The Non-Road Mobile Machinery to be used within NTD would also comply with relevant standards and requirements and therefore no significant air quality impact is anticipated.

Airborne Noise Impact

Construction Phase

     Potential construction noise impacts arising from the operation of powered mechanical equipment (PME) are expected.  Mitigation measures including adoption of quieter construction methods, good site practice, quiet PMEs (including Quality Powered Mechanical Equipment (QPME)) and temporary movable noise barriers/noise enclosures/noise insulating fabric/silencer/soundproof hammer bracket, as well as avoidance of noisy construction works during the examination periods where necessary, have been proposed. The assessment results indicated that the mitigated noise levels at all NSRs would comply with the construction noise criterion as set out in EIAO-TM. 

Operational Phase (Fixed Noise)

     Maximum allowable sound power levels (SWLs) emitted from planned fixed plant were predicted.  Proper selection of quiet plant and adoption of acoustic treatment were recommended for compliance at existing and planned NSRs with the respective noise criteria.

Operational Phase (Rail Noise)

     The NOL alignment would be located underground except a short trough section at the tunnel portal connecting to NTD.  The trough section has been minimised and would be covered with noise canopies and vertical louvre walls with natural ventilation feature. Considering the train speed and train frequency are relatively low at the trough section and there would be no direct line of sight from any NSRs to the airborne railway noise sources at the trough section and NTD, adverse airborne railway noise impact due to the operation of the Project is therefore not anticipated.

Ground-borne Noise Impact

Construction Phase

     Potential ground-borne noise impacts would be induced by the use of PME and TBM during tunnelling works. Assessment results demonstrated the compliance of daytime criteria at the representative GBNSRs, while exceedance was predicted at a planned school site during examination period. Close liaison with the representatives of the education institution and avoidance of TBM operation during the examination period is recommended. 

Operational Phase

     With the installation of Type 1a (Alt 1) trackform, compliance of noise criteria at the representative GBNSRs was predicted, and thus no adverse operational ground-borne noise impacts would be anticipated.

     Nevertheless, it is recommended to review the ground-borne noise predictions based on the findings of tunnel impact test to be conducted after the completion of tunnel construction.

Cumulative Operational Ground-borne Noise Impact

     Potential cumulative impacts were evaluated and no adverse impacts would be anticipated.

Water Quality Impact

Construction Phase

     Water quality impacts from the construction activities would be controlled by implementing the recommended mitigation measures and good site practices. Regular site inspections would be carried out to minimise water quality impacts.

Operational Phase

     Proper sewage and wastewater collection and diversion, and best management practices for stormwater discharge will be adopted for the Project to minimise the potential water quality impact during operational phase. 

Sewerage and Sewage Treatment Implications

     Liaison with concurrent projects at the vicinity will be conducted for proper arrangement of sewerage interfaces to reduce potential sewerage impact.  

Waste Management Implications

Construction Phase

     The main waste types to be generated during the construction phase of the Project will include inert and non-inert construction and demolition (C&D) materials, general refuse, chemical waste and excavated land-based sediment. Reduction measures have been recommended to minimise the amount of materials generated by the Project by reusing C&D materials and excavated sediment as far as practicable before offsite disposal, and adopting good site practices. Provided that the waste is properly handled, transported and disposed of in accordance with good waste management practices, relevant legislation and waste management guidelines, no adverse environmental impacts would be expected.

Operational Phase

     The main waste types to be generated during the operational phase of the Project will include municipal solid waste and chemical waste. Provided that the waste is properly handled, transported and disposed of using approved methods, no adverse environmental impacts would be expected.

Land Contamination

     Further site appraisal, associated SI works and any necessary remediation action are recommended to be carried out after site operation has ceased but prior to the commencement of construction works by mean of excavation at the concerned sites.  The recommended further works, including the submission of Supplementary CAP(s), CAR(s) / RAP(s) and RR(s), would need to follow EPD¨s Guidance Manual, Guidance Note and Practice Guide.

     With the implementation of the recommended further works, any soil / groundwater contamination would be identified and properly treated.  Land contamination impacts are therefore considered not insurmountable.

Terrestrial and Aquatic Ecology

Construction Phase

     Habitats identified within the assessment area include developed area/wasteland, grassland, shrubland, mixed woodland, woodland, dry agricultural land, marsh/reed, pond, watercourse, village/orchard.  Egretries and ardeid night roosts with ecological resources such as Little Egrets and Chinese Pond Herons habituating are also identified within assessment area.

     Direct impacts include the loss of marsh/reed with moderate ecological value, loss of a bat day-roost in Pok Wai Public School and potential direct injury/mortality of the roosting bats, if any, terrestrial habitats and impacts on the associated species. Indirect impacts include disturbances to ecological sensitive resources, water quality and hydrology.

     With the implementation of mitigation measures including noise and glare reduction measures,  bat inspection before commencement of demolition of the deserted Pok Wai Public School, installation of bat exclusion devices, provision of bat shelter and compensatory wetland, adoption of site hoarding and barriers, careful arrangement of work programme to avoid noisy construction activities near the Kam Po Road Egretry during breeding season as far as practicable, control of working hours to avoid noisy construction activities within buffer zone from the Kam Po Road night roost with due consideration of peak time return of ardeids to night roost, and good site practices to control construction runoff, no unacceptable ecological impacts are anticipated to arise from the construction of the Project.

Operational Phase

     With the provision of glare reduction measures and careful landscape design to avoid tall landscape plants in the green roof system at Stations, no unacceptable ecological impacts are anticipated from the operation of the Project. 

Fisheries Impact

     With the implementation of water quality and groundwater drawdown control measures, unacceptable residual impacts would not be anticipated during both construction and operational phases. 

Landscape and Visual

     Approximately 6,168 existing trees were estimated within proposed works sites and areas, of which trees will not be affected by the proposed works will be retained, while trees will be directly affected by the proposed works will be proposed to be removed or proposed to be transplanted as appropriate. There are neither OVT, rare species nor endangered species affected by the proposed works, and the surveyed trees mainly are common tree species with some rare species identified and are in fair quality and medium sensitivity.

     Opportunities for tree compensation have been fully explored and incorporated in the proposed mitigation measures as much as practicable. During the course of EIA study, potential sites for on-site and off-site tree compensation were identified/studied in consultation with relevant stakeholders (relevant government departments including DEVB, ArchSD, HA/HD, HyD, LCSD, AFCD, CEDD and LandsD etc.).  The exact number of trees to be retained, transplanted and felled as well as the associated compensation proposal would be further explored with the consideration of available areas for tree planting and operation constraints during the preparation of a detailed Tree Preservation and Removal Proposals (TPRPs) in accordance with LAO Practice Note 6/2023 to be submitted to relevant government departments in later stage of the Project with an aim to achieve a tree compensation ratio of 1:1 in terms of number as far as practicable.

     Although the Project will have certain adverse landscape and visual impacts, they will be mitigated as far as practicable by appropriate mitigation measures with both on-site and off-site compensatory planting. In view of the above, it is considered that, with the implementation of the appropriate mitigation measures such as tree transplanting, aesthetically pleasing design of aboveground structures, compensatory tree planting and landscape treatments on slope of retaining structure, the overall residual landscape impacts are minimised to marginally acceptable level, and the overall residual visual impacts are minimised to acceptable level during the construction and operational phases of the Project.

Cultural Heritage

Built Heritage

     A total of two other identified items (i.e. Pok Wai Public School and Fung Kat Vegetable Marketing Co-operative Society Ltd.) within the project area would be anticipated to be demolished unavoidably and preservation in means of cartographic and photographic record and other documentation means (including 3D scanning) prior to the commencement of construction works at the respective area are recommended. 

     Indirect impact would include disturbance to the other identified item (i.e. San Yau Vegetable Marketing Co-operative Society Ltd.) due to ground-borne vibration, settlement and tilting during construction phase.  Monitoring of ground-borne vibration, tilting and ground settlement under Buildings Ordinance is proposed to be employed for this identified item that may be impacted by ground-borne vibration, tilting and ground settlement.

Archaeology

     Archaeological survey-cum-excavation at Long Ha Archaeologically Sensitive Area (ASA) and Ngau Tam Mei ASA, further archaeological investigation at NTM-TP3, and further archaeological survey at  the south of SAT Station to be undertaken by archaeologist(s) at later stages after land resumption and before commencement of site formation and construction works is recommended. Scope, methodology and programme of the archaeological fieldwork should be agreed with AMO in advance.

     Archaeological watching brief at the northwest of SAT Station to be carried out by archaeologist(s) during the course of excavation works is recommended.  The details of watching brief should be agreed with AMO in advance.

     If antiquities or supposed antiquities under the Antiquities and Monuments Ordinance (Cap. 53) are discovered during the construction phase, the project proponent is required to inform AMO immediately for discussion of appropriate mitigation measures to be agreed by AMO before implementation by the project proponent to the satisfaction of AMO.

Hazard to Life

     According to the latest information available, AT WTW has been delisted and will no longer classified as a Potentially Hazardous Installations, no hazard-to-life concerns are anticipated.

     Given that the proper design and maintenance of the blasting face and provision of blast door or cover, together with the fact that the blasting would be conducted inside the tunnel section and with the blast cover shut, the associated risk for the use of explosives at drill-and-blast tunnel and underground tunnel sections would be well within the acceptable region.

     The risk for the use of explosives is within `acceptable¨ region, while the risks for overnight storage and transportation of explosives slightly entered the ^ALARP ̄ region.

     The individual risk due to the use, overnight storage and transport of explosives complies with the criteria in EIAO-TM and therefore is considered acceptable.

     The cumulative risk from the use, overnight storage and transport of explosives falls within the ALARP region of stipulated criteria under EIAO-TM.  A cost-benefit analysis has been undertaken to consider a range of options of alternatives (e.g. methods of construction, magazine sites, explosive types and quantities, etc.) and mitigation measures to demonstrate that all reasonably practicable measures have been taken to reduce risks.

     Good practices are recommended to further manage and minimize the potential risks during construction phase of the Project.