3
Air Quality impact
3.1.1
This section presents the assessment of
potential air quality impacts on air sensitive receivers (ASRs) arising from
the construction of the Project.
Assessment was conducted in accordance with criteria and guidelines as
stipulated in Annex 4 and Annex 12 of the EIAO-TM as well as the requirements
given in Clause 3.4.3 and Appendix B of the EIA Study Brief (No. ESB-346/2021).
3.1.2
The potential dust impact arising from dusty
construction activities of the Project were assessed and appropriate mitigation
measures were proposed to alleviate any adverse air quality impact.
3.1.3
The rail system to be employed in the Project
will be electric-powered, and air-emission free during the normal
operation. The potential air
quality impact during operation phase was thus considered insignificant and was
not assessed in this section.
Air
Quality Objectives & Technical Memorandum on EIA Process
3.2.1
The criteria and guidelines for air quality
assessment are laid down in Annex 4 and Annex 12 of the Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM).
3.2.2
The Air Pollution Control Ordinance (APCO)
provides the statutory authority for controlling air pollutants from a variety
of sources. The Hong Kong Air
Quality Objectives (AQOs), which stipulate the maximum allowable concentrations
over specific periods for typical pollutants, should be met. The relevant prevailing AQOs are listed
in Table
3.1.
Table 3.1 Hong
Kong Air Quality Objectives
Pollutant
|
Averaging Time
|
Maximum Average Concentration (µg/m3)
(1)
|
No. of Exceedances Allowed (2)
|
Fine
Suspended Particulates (PM2.5)
(4)
|
24-hr
|
50
|
35
|
Annual
(3)
|
25
|
NA
|
Respirable
Suspended Particulates (PM10) (5)
|
24-hr
|
100
|
9
|
Annual (3)
|
50
|
NA
|
Sulphur
Dioxide (SO2)
|
10-min
|
500
|
3
|
24-hr
|
50
|
3
|
Nitrogen
Dioxide (NO2)
|
1-hr
|
200
|
18
|
Annual (3)
|
40
|
NA
|
Carbon
Monoxide (CO)
|
1-hr
|
30,000
|
0
|
8-hr
|
10,000
|
0
|
Ozone
|
8-hr
|
160
|
9
|
Lead
(Pb)
|
Annual (3)
|
0.5
|
NA
|
Notes:
(1)
Gaseous pollutant is measured at 293 K and 101.325
kPa.
(2)
The number of exceedances allowed per year.
(3)
Arithmetic mean.
(4)
Suspended particulates in air with a nominal
aerodynamic diameter of 2.5 mm or smaller.
(5)
Suspended particulates in air with a nominal
aerodynamic diameter of 10 mm or smaller.
Air Pollution Control (Construction Dust)
Regulation
3.2.3
Notifiable and regulatory works are under the
control of Air Pollution Control (Construction Dust) Regulation. Notifiable works include site formation,
reclamation, demolition, foundation and superstructure construction for
buildings and road construction.
Regulatory works include building renovation, road opening and
resurfacing, slope stabilisation, and other activities including stockpiling,
dusty material handling, excavation, concrete production, etc. The Project is expected to include
notifiable works (site formation, demolition, foundation and superstructure
construction for station structure) and regulatory works (dusty material
handling and excavation).
Contractors and site agents are required to inform EPD and adopt dust
reduction measures to minimize dust emissions, while carrying out construction
works, to the acceptable level.
Air
Pollution Control (Non-road Mobile Machinery) (Emission) Regulation
3.2.4
The Air Pollution Control (Non-road Mobile
Machinery) (Emission) Regulation comes into operation on 1 June 2015. Under the Regulation, Non-road mobile
machinery (NRMMs), except those exempted, are required to comply with the
prescribed emission standards. From 1 September 2015, all regulated
machines sold or leased for use in Hong Kong must be approved or exempted with
a proper label in a prescribed format issued by EPD. Starting from 1
December 2015, only approved or exempted NRMMs with a proper label are allowed
to be used in specified activities and locations including construction
sites. The Contractor is required
to ensure the adopted machines or non-road vehicle under the Project could meet
the prescribed emission standards and requirement.
Air
Pollution Control (Fuel Restriction) Regulation
3.2.5
The Air Pollution Control (Fuel Restriction)
Regulation was enacted in 1990 to impose legal control on the types of fuel
allowed for use and their sulphur contents in commercial and industrial
processes to reduce sulphur dioxide (SO2) emissions. Since 1 October
2008, liquid fuel with a sulphur content not exceeding 0.005% by weight such as
Ultra Low Sulphur Diesel (ULSD) shall be used, unless a valid certificate of
compliance with emission limits issued by a competent examiner.
Air
Pollution Control Ordinance ¨C Specified Processes and the Licensing of Premises
3.2.6
Process stipulated in Schedule 1 of Air
Pollution Control Ordinance (APCO) is classified as Specified Process (SP). A
licence is required to conduct the process in a premises under Part IV of the
ordinance. SP relevant to the Project is summarized as follows:
¡¤
Cement
Works (Concrete Batching Plant) ¨C Works in which the total silo capacity
exceeds 50 tonnes and in which cement is handled or in which argillaceous and
calcareous materials are used in the production of cement clinker, and works in
which cement clinker is ground.
3.2.7
Grant of a SP licence by EPD is subject to
whether the applicant can fulfil the environmental standards to avoid causing
air pollution. A Guidance Note on the Technical, Management and Monitoring
Requirements for Specified Process ¨C Cement Works (Concrete Batching Plant) BPM
3/2 (16) sets out the minimum requirements for the provision and
maintenance of the best practical means for an individual plant. Apart from the
suggested control measures in the BPM, particulates emission concentration
limit of 10 mg/m3 (expressed at reference condition, 0¡ãC, 101.325
kPa) shall be satisfied by 1 January 2018 by all plants.
Existing
Environment
3.3.1
The Project Site is located in the northern part
of New Territories. The proposed
NOL alignment runs from the proposed Kam Sheung Road (KSR)(NOL) Station,
passing via three intermediate stations at Au Tau (AUT), Ngau Tam Mei (NTM) and
San Tin (SAT), and ends at Kwu Tung (KTU)(NOL) Station. The existing environment adjacent to the
proposed alignment is rural, with variety of land uses comprising residential
developments, villages, industrial, agricultural, recreational, comprehensive
development area, open storage, government, institution or community (G/IC),
green belt, conservation area and open space.
3.3.2
The dominant existing air pollutants sources
within the 500m assessment area of the NOL alignment are the vehicular emission
from major open roads including Tsing Long Highway, Kam Tin Road, Kam Tin
Bypass, San Tin Highway, Castle Peak Road and Fanling Highway.
3.3.3
The closest EPD¡¯s air quality monitoring station
to the assessment area is the North Air Quality Monitoring Station (AQMS)
situated at the Po Wing Road Sports Centre which is operating since July 2020
and is under the land use type ¡°New Town¡±.
Owing to insufficient data for time before Year 2020 and in Year 2020,
the background observation refers to the next closest station with the same
land use type instead, i.e. Yuen Long AQMS at Yuen Long District Office
Building as published in Air Quality in Hong Kong. The major air
pollutants induced from the construction of the Project would be the
particulates emissions during the construction phase, while there will be no
air pollutant emission arising from the operation of electrically powered
trains during operation of the Project.
Therefore, the Fine Suspended Particulates (FSP) and Respirable
Suspended Particulates (RSP) monitoring data recorded between Year 2018 to 2022
are examined and summarized in Table
3.2.
It is observed that daily and annual averages of RSP and FSP
concentration complied with prevailing AQOs during Year 2018 to 2022.
Table 3.2 The
Air Quality Monitoring Data Recorded at EPD¡¯s Yuen Long in Year 2018 ¨C 2022
Pollutant
|
Averaging Time
|
AQO[1]
|
Data Summary
|
Year [2]
|
2018
|
2019
|
2020
|
2021
|
2022
|
Fine Suspended
Particulates (FSP) [3]
|
24-hr
|
50 (35)
|
Max.
|
80
|
81
|
44
|
75
|
64
|
36th
Max.
|
34
|
34
|
28
|
31
|
30
|
No.
of Exceedance(s)
|
5
|
5
|
0
|
3
|
5
|
Annual
|
25
|
-
|
20
|
20
|
16
|
17
|
16
|
Respirable Suspended
Particulates (RSP) [3]
|
24-hr
|
100 (9)
|
Max.
|
121
|
125
|
97
|
109
|
81
|
10th
Max.
|
75
|
83
|
77
|
73
|
56
|
No.
of Exceedance(s)
|
4
|
2
|
0
|
1
|
0
|
Annual
|
50
|
-
|
37
|
37
|
30
|
30
|
25
|
Notes:
[1] Values in ( ) mean the number of
exceedances allowed per year.
|
[2] Bolded values mean
exceedance of the AQO limit values.
|
[3] All concentration
units are in microgram per cubic metre (µg/m3).
|
Table 3.3 PATHv2.1
Model - Air Pollutant Concentrations in Year 2025
Pollutant
|
Aver-aging Time
|
AQO [1]
|
Data Summary
|
PATH Grid Cell [2]
|
Year 2025
|
Fine Suspended Particulates (PM2.5)
[3]
|
24-hr
|
50 (35)
|
Max.
|
73
- 87
|
36th Max.
|
24 ¨C 29
|
No. of Exceedance(s)
|
9 ¨C 11
|
Annual
|
25
|
-
|
15 ¨C 18
|
Respirable Suspended Particulates (PM10)
[4]
|
24-hr
|
100 (9)
|
Max.
|
91 - 105
|
10th Max.
|
63 ¨C 71
|
No. of Exceedance(s)
|
0 ¨C 1
|
Annual
|
50
|
-
|
26
- 30
|
Notes:
[1] Values in
( ) mean the number of exceedances allowed per year.
[2] Bolded
values mean exceedance of the AQO limit values.
[3] Annual
FSP concentration is adjusted by adding 3.5 µg/m3 with reference to
Guidelines on Choice of Models and Model Parameters.
[4] Daily and
annual RSP concentration is adjusted by adding 11.0 µg/m3 and 10.3 µg/m3 respectively with reference to
Guidelines on Choice of Models and Model Parameters.
[5] All concentration units are in microgram per
cubic metre (µg/m3).
3.4.1
In accordance with Annex 12 of the EIAO-TM, any
domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing
accommodation, school, educational institution, office, factory, shop, shopping
centre, place of public worship, library, court of law, sports stadium or
performing arts centre are considered as air sensitive receivers (ASRs). Any other premises or place with which,
in terms of duration or number of people affected, has a similar sensitivity to
the air pollutants as the aforementioned premises and places is also considered
to be a sensitive receiver. As
stated in the EIA Study Brief (No. ESB-346/2021), the boundary of the
assessment area for air quality assessment should be 500m from the Project
boundaries of all associated areas under the Project.
3.4.2
The representative ASRs (existing / planned)
that may be affected by the Project within the 500m assessment area were
identified based on the latest Outline Zoning Plans, Layout Plan, Outline
Development Plans, Layout Plans and other relevant published land use plans.
3.4.3
Concurrent projects are expected in the vicinity
of the proposed stations and would introduce planned ASRs upon their completion
as well as cumulative impacts from concurrent projects at these planned ASRs,
subject to the completion year of the concurrent projects.
3.4.4
The locations of the representative ASRs along
NOL are shown in Figure Nos. C1603/C/NOL/ACM/M51/303 to 317. The details of the representative ASRs
for assessment are presented in Table 3.4.
Table 3.4 Representative
Air Sensitive Receivers along NOL
ASR
|
Description
|
Land Use(1)
|
Approx. Distance between ASR and closest works
area/works site (m)
|
No. of Storey
|
KSR-A01
|
Taoist
Temple
|
W
|
140
|
1
|
KSR-A02
|
Go
Green Farm
|
A
|
259
|
2
|
KSR-A03
|
Dude
Ranch
|
A
|
160
|
2
|
KSR-A04
|
Chui
Yee Garden
|
R
|
42
|
3
|
KSR-A05
|
Kut
Hing Garden
|
R
|
91
|
3
|
KSR-A06
|
Noble
Park
|
R
|
166
|
3
|
KSR-A07
|
Kam
Fung Garden
|
R
|
314
|
3
|
KSR-A08
|
Kam
Fung Garden
|
R
|
430
|
3
|
KSR-A09
|
Kam Tin Mung Yeung Public School
|
E
|
484
|
3
|
KSR-A10
|
Village
House
|
R
|
30
|
2
|
KSR-A11
|
Shek
Wu Tong
|
R
|
93
|
1
|
KSR-A12
|
Strong
Sing Garden
|
R
|
288
|
2
|
KSR-PA01
|
Planned
Public Housing in Kam Tin South Development (Site 1)
|
R
|
11
|
-(2)
|
KSR-PA02
|
Planned
G/IC site in Kam Tin South Development (Site 1)
|
GIC
|
9(3)
|
-(2)
|
KSP-PA03
|
Planned
G/IC site in Kam Tin South Development (Site 6)
|
GIC
|
25
|
-(2)
|
KSR-PA04
|
Grand
Mayfair (Planned)
|
R
|
32
|
-(2)
|
KSR-PA05
|
Planned
Residential Use under Kam Tai Road Residential Development
|
R
|
344
|
-(2)
|
SMA-A01
|
Park
Vista Tower 9A
|
R
|
22
|
19
|
SMA-A02
|
Park
Yoho Tower 8B
|
R
|
10
|
16
|
SMA-A03
|
Cheung
Chun San Tsuen
|
R
|
150
|
1
|
SMA-A04
|
Au
Tau Fisheries Office, AFCD
|
GIC
|
13
|
1
|
SMA-A05
|
Riva
Helorus Boulevard
|
R
|
398
|
25
|
SMA-A06
|
Crescent
Green Tower 1
|
R
|
316
|
13
|
SMA-A07
|
Cheung
Chun San Tsuen
|
R
|
77
|
3
|
AUT-A01
|
Park
Yoho Genova Tower 12
|
R
|
128
|
19
|
AUT-A02
|
Sha
Po Tsuen
|
R
|
251
|
3
|
AUT-PA03
|
Planned
Public Housing in Sha Po Housing Development
|
R
|
21
|
-(2)
|
AUT-A04
|
Open
Storage at Castle Peak Road ¨C Tam Mei
|
OS
|
140
|
2
|
AUT-A05
|
Shum
Residence
|
R
|
58
|
2
|
AUT-A06
|
Mo
Fan Heung
|
R
|
0
|
1
|
AUT-A07
|
Wing
Kei Tsuen
|
R
|
179
|
3
|
PWA-A01
|
Village
House
|
R
|
1
|
2
|
PWA-A02
|
Pok
Wai
|
R
|
2
|
3
|
PWA-A03
|
Elite
Garden
|
R
|
72
|
3
|
PWA-A04
|
Elite
Garden
|
R
|
113
|
3
|
LHA-A01
|
Village
House
|
R
|
17
|
1
|
LHA-A02
|
Village
House
|
R
|
106
|
1
|
LHA-A03
|
Merry
Garden
|
R
|
166
|
3
|
LHA-A04
|
Village
House
|
R
|
15
|
1
|
NTM-A01
|
Village
House
|
R
|
32
|
2
|
NTM-A02
|
Fuk
Hing Lei
|
R
|
172
|
3
|
NTM-A03
|
Hongtai
Home for the Aged Limited
|
HA
|
9
|
3
|
NTM-A04
|
Village
House
|
R
|
3
|
1
|
NTM-A05
|
Village
House
|
R
|
193
|
3
|
NTM-A06
|
Village
House
|
R
|
10
|
1
|
NTM-A07
|
China
Bible Seminary
|
E
|
182
|
3
|
NTM-A08
|
Village
House
|
R
|
59
|
1
|
NTM-A11
|
Yau
Tam Mei Tsuen
|
R
|
31
|
3
|
NTM-A12
|
Greenacres
Villa House A
|
R
|
96
|
3
|
NTM-A13
|
Yau Tam Mei Tsuen
Village House
|
R
|
0
|
2
|
NTM-A14
|
Yau
Tam Mei Tsuen
|
R
|
0
|
1
|
SAT-A01
|
Christian
New Life Association
|
GIC
|
11
|
1
|
SAT-A02
|
San
Tin Barracks
|
GIC
|
288
|
6
|
SAT-A03
|
Shek
Wu Wai
|
R
|
56
|
1
|
SAT-A04
|
Hung
Yat Farm
|
A
|
51
|
2
|
SAT-A05
|
Shek
Wu Wai
|
R
|
14
|
3
|
SAT-A06
|
Shun
Sum Yuen Farm
|
A
|
7
|
2
|
SAT-A07
|
San
Tin Barracks
|
GIC
|
211
|
6
|
SAT-A08
|
Luk
Mei Tsuen
|
R
|
280
|
1
|
SAT-A09
|
Farmers¡¯
Cooperative
|
A
|
11
|
2
|
SAT-A10
|
Village
House
|
R
|
42
|
1
|
SAT-A11
|
Open
Storage at Kwu Tung Road
|
OS
|
90
|
1
|
SAT-A12
|
Wah
Sang Yuen
|
A
|
60
|
1
|
SAT-A13
|
Village
House
|
V
|
54
|
1
|
SAT-A14
|
Man
Tin Cheung Park
|
O
|
142
|
1
|
SAT-A15
|
Fan
Tin Tsuen
|
R
|
150
|
3
|
SAT-A16
|
Village
House
|
V
|
169
|
2
|
SAT-A17
|
Siu
Hum Tsuen
|
R
|
185
|
3
|
SAT-A18
|
Siu
Hum Tsuen
|
R
|
207
|
3
|
SAT-PA01
|
Potential
Housing Development in STLMC DN
|
R
|
44
|
-(2)
|
KTU-A01
|
Chau
Tau Tsuen
|
R
|
288
|
3
|
KTU-A02
|
Village
Meeting Place
|
O
|
33
|
1
|
KTU-A03
|
Open
Storage at Kwu Tung Road
|
OS
|
14
|
1
|
KTU-A05
|
Village
House
|
GB
|
35
|
2
|
KTU-PA01
|
Planned
Housing Development at Kwu Tung North
|
R
|
10
|
-(2)
|
KTU-PA02
|
Planned
Housing Development at Kwu Tung North
|
R
|
10
|
-(2)
|
KTU-PA03
|
Planned
Housing Development at Kwu Tung North
|
R
|
19
|
-(2)
|
KTU-PA04
|
Planned
Housing Development at Kwu Tung North
|
R
|
43
|
-(2)
|
KTU-PA05
|
Planned
Hospital at Kwu Tung North
|
GIC
|
171
|
-(2)
|
KTU-PA07
|
Purpose-built
Multi-welfare Services Complex in Area 29
|
GIC
|
41
|
40
|
Notes:
(1) A ¨C Agricultural; E ¨C Educational;
GIC - Government, institution and community; I ¨C Industrial; O ¨C Open Space; OS
¨C Open Storage; R ¨C Residential; HA ¨C Home for the Aged; W ¨C Place of Public Worship; GB ¨C
Green Belt.
(2) Information subject to the design of
planned development.
(3) A reserve zone of 8m wide will be provided
at the south-western boundary of Site 1 for provision of CLP cable.
3.4.5
The locations of the representative ASRs
near the temporary explosive magazine site at Tai Shu Ha (Yuen Long) are shown
in Figure No. C1603/C/NOL/ACM/M51/317. The details of the representative ASRs
for assessment are presented in Table
3.5.
Table 3.5 Representative
Air Sensitive Receivers near Temporary Explosive Magazine Site at Tai Shu Ha
(Yuen Long)
ASR
|
Description
|
Land Use
|
Approx. Distance between ASR and closest works
area/works site (m)
|
No. of storey
|
TSH-A01
|
Hong
Kong Model Engineering Club (HKMEC) International Model Aviation Centre
|
Institutional
|
126
|
1
|
TSH-A02
|
Village
House
|
Village
|
307
|
3
|
Construction Phase
Construction
Works Site along NOL
¡¤
Construction
of 5 stations including KSR(NOL), AUT, NTM, SAT and KTU(NOL) by cut-and-cover; Construction of tunnel connecting KSR(NOL), AUT, NTM, SAT
and KTU(NOL) Stations by Tunnel Boring Machine (TBM);
¡¤
Construction
of branching tunnel connecting to Ngau Tam Mei Depot (NTD) by cut-and-cover,
mined and drill-and-blast tunnelling method;
¡¤
Construction
of NTD;
¡¤
Construction
of overrun tunnel section at KSR and crossover box and bifurcation at SAT by
cut-and-cover;
¡¤
Demolition
of EAP aboveground structure under Existing EAL at Kwu Tung;
¡¤
Site
clearance and construction of temporary explosive magazine at Tai Shu Ha (Yuen
Long) and reinstatement; and
¡¤
Construction
of Ancillary Buildings for EAP/EEPs/VBs.
¡¤
For
an EPB, excavated materials will be collected in the excavation chamber and
treated with foams and polymers, transforming into a flowing material (muck) to
achieve pressure balance at the cutterhead. The muck which is wet in nature
will be removed through a screw conveyor to the stockpiling area for
mucking-out. Given the closed system of EPB and the use of conveyor belt system
within the tunnel, the dust emission associated with the tunneling works by EPB
would be expected minimum. Limited
dust emission would only arise from the mucking-out operation.
¡¤
For
a Mixshield Slurry Type TBM, excavated boulders will be crushed inside the TBM,
mixed with the slurry and then hydraulicly removed through a closed slurry
circuit. The excavated material is
wet in nature and conveyed by conveyor system to the stockpiling area for
mucking-out. Given
the closed system of TBM and wet nature of the slurry generated, the dust
emission associated with the tunneling works by slurry type and the subsequent
conveying and handling of excavated material is also expected minimum.
3.5.5
The excavated material from the tunneling works
by TBM and drill-and-blasts would be transported with dump trucks out of the
works sites to receiving sites. The induced traffic would cause vehicle
emission along the routes. Dump trucks would collect spoils from separate
sites, including KSR(NOL) Station, AUT, NTM Station and NTD, SAT Station and
KTU(NOL) Station, eventually via Yuen Long Highway, Tuen Mun Road to Tuen Mun
Area 38 Fill Bank, with the tentative transportation routes discussed in Section
8.4.48. Maximum number of trucks per hour were estimated based on the
current engineering design and are discussed in the following sections.
Comparing with the high traffic flow of Yuen Long Highway and Tuen Mun Road,
the additional dump trucks generated from the isolated works sites along NOL
would not cause significant increment in traffic. Dump truck to be employed
would be equipped with water-tight containers and mechanical cover, and
fugitive dust emission on the road is anticipated to be limited. It is
anticipated that the transportation of excavated spoils would not cause adverse
air quality impact along the routes with the implementation of appropriate
mitigation measures.
3.5.6
A concrete batching plant (CBP) will be provided
at works sites of SAT Station under NOL for supporting the construction of NOL,
in order to meet the concrete demand by the constructions of tunnel and
stations. According to the preliminary engineer design, the maximum production
of each CBP would be 3,000 m3 per day. The CBP uses electricity as
the power supply for operation, thus no gaseous pollutants by fuel combustion
is anticipated. Potential dust impact would arise from the operation of the CBP
and is addressed qualitatively in the assessment. The CBP would have total silo
capacity exceeding 50 tonnes which is classified as Specified Process and
requires a licence to operate pursuant to Air Pollution Control Ordinance
(APCO).
3.5.7
The temporary explosive magazine site is
proposed to be located at Tai Shu Ha (Yuen Long) and the location is presented
in Figure No. C1603/C/NOL/ACM/M51/317. The site was formerly used as temporary
explosive magazine site for the tunnel construction works by MTR Corporation in
the Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail Link under EP-349/2009/N and CEDD¡¯s Liantang/Heung
Yuen Wai Boundary Control Point Project
under EP-502/2015/A and had been reinstated for about 5 years. Minor non-dusty
works would be required to set up the magazine site, such as vegetation
clearance, brick-built magazine, fencing, sandbag mounds and the existing
access road. During the
construction of NOL, there would be maximum of 2 trucks per hour accessing the
site. The temporary explosive magazine site from Tai Shu Ha Road West would be
reinstated as per the requirement from relevant government department upon
completion of tunnelling works.
Based on the preliminary design information, considering no excavation
works and only limited traffic to be involved, its potential dust impact is
considered minor, thus it was addressed qualitatively.
Tentative Construction Programme
3.5.8
The construction of the Project would
tentatively commence in 2025 for target completion in 2034, in which the major
civil works would be between 2025 and 2033. The detailed
construction programme along the alignment is presented in Appendix 2.2.
Identification of Potential Emission
Sources and Key Air Pollutants
3.5.9
The potential dust impact would arise from the
construction activities of the Project. The major construction activities
causing dust emission include site clearance, site formation, demolition works,
excavation, tunnelling works (e.g. TBM, cut-and-cover, drill-and-blast and
mining), backfilling, spoil handling, vehicle movement on haul roads within
works area/works sites and wind erosion of the exposed site area. Watering at
regular time interval will be provided over all the active works sites and exposed
areas. As a proven effective dust suppression measures in the past approved EIA
reports, regular watering would reduce the dust impact due to the major
construction activities to an acceptable level.
3.5.10
Construction vehicles on the haul road within
the works areas/works sites would also cause construction dust impact. Dust suppression measures such as paving
and regular watering will be provided to abate the dust emission from open haul
roads. Underground haul roads, i.e. inside tunnel, would be unpaved but wetted
regularly for dust suppression.
Construction vehicle will be required to pass through the wheel washing
facilities upon site exit. Thus, the construction vehicle movements outside the
works areas/works sites would not cause any significant dust impact.
3.5.11
On-site use of diesel-powered engines is the
potential source for other gaseous pollutants such as NO2, SO2
and smoke. The Air Pollution
Control (Non-road Mobile Machinery) (Emission) Regulation came into effect in
June 2015 to control emissions from diesel-powered engines. Fuel with sulphur
content not exceeding 0.005% by weight will be used to minimize SO2
emission in accordance with the Air Pollution Control (Fuel Restriction)
Regulation. In addition, the use of NRMMs with exempted label under the Air
Pollution Control (NRMM) Regulation will be avoided as far as practicable. The
equipment would also be properly maintained to minimize any emissions. Also,
the use of electrified NRMMs, as well as the TBM, electric excavator, etc. will
be employed as far as practicable, which is unlikely to cause significant smoke
and gaseous emissions. Alternative
power supply such as off-grid power storage, e.g. AMPD Enertainer, will also be
considered where feasible. In view
of the minor impact by NRMMs, particulates from dusty construction activities
would be the major air pollutant during construction phase.
Concurrent
Projects
3.5.13 There
are five planned housing development in vicinity of the proposed KSR(NOL)
Station, with their details discussed below:
¡¤
Kam
Tin South Housing Development ¨C It is now under construction and would be
completed in 2030, thus cumulative construction dust impact is expected.
¡¤
Kam
Sheung Road Package 2 Property Development ¨C It is now under planning, and no
construction programme is available for the assessment.
¡¤
Grand
Mayfair ¨C It is now under construction and would be completed in 2024, before
the commencement of the Project, and thus no concurrent construction works is
expected.
¡¤
Kam
Tai Road Residential Development ¨C It is now under construction and would be
completed in Q3 2025, and thus no concurrent construction works is expected.
3.5.14
A planned project, Park Yoho Phase 2 and 3,
would be adjacent to Shui Mei Road Ancillary Building (SMA). However, Park Yoho
Phase 2 and 3 are under planning and no construction programme is available,
therefore it was not addressed in this assessment.
3.5.15 There
is also a planned project in vicinity of the AUT Station, namely Sha Po Public
Housing Development. The construction works of Sha Po Public Housing
Development would be commence in 2025 and its foundation works would be
completed in 2027. Its cumulative construction dust impact was addressed in
this assessment.
3.5.16
Two projects are in the vicinity of NTM, namely
Land Use Review Study for Ngai Tam Mei Area ¨C Feasibility Study (NTM
LUR) and Proposed Fresh Water Trunk Main under Ngau Tam Mei Water
Treatment Works Extension. However,
both projects are under planning and no detailed construction programme is
available for the assessment, thus they were not considered in the
assessment.
3.5.17
There would be new developments in San Tin under
First Phase Development of the New Territories North ¨C San Tin / Lok Ma Chau
Development Node ¨C Investigation (STLMC DN) respectively. The study areas would be located in the
vicinity of SAT Station. The
construction works would commence in 2024 and target for completion in
2034. The cumulative construction
dust impact was addressed in this assessment.
3.5.18
The KTU(NOL) Station situates in the Kwu Tung
North New Development Area (KTN NDA) and adjoins with the Kwu Tung Station on
Lok Ma Chau Spur Line of East Rail Line (KTU(EAL) Station). The construction
periods of first and remaining phases in KTN NDA is 2019 ¨C 2026, and 2024 ¨C
2031 respectively. Construction
works for KTU(EAL) Station would commence in 2023 and the major construction
works to be completed in 2026 for completion in 2027. Concurrent construction works
of KTN NDA and KTU(EAL) Station would be expected and were considered in the
cumulative construction dust impact assessment based on best available
information.
Review of
Dust Monitoring Data of Past Projects
3.5.19
Based on the nature and scale of the Project, it
is considered that the Project is similar to a railway project, i.e. High Speed
Rail (Hong Kong Section) (HSR) (formerly named as ¡°the Hong Kong Section of
Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL)¡±), which comprises 26-km
long high-speed rail railway running underground from West Kowloon to boundary
at Huanggang, a terminus in West Kowloon, nine tunnel ventilation
buildings/emergency access point, stabling siding and maintenance facilities,
on-site concrete batching plant, etc. The underground tunnels of HSR were built
by various methods, namely drill-and-blast, cut-and-cover and TBM, while the
ventilation buildings/emergency access point were constructed by cut-and-cover,
and Shek Kong Stabling Sidings by cut-and-fill method. The construction of HSR
commenced in Year 2011 and its operation commenced on 23 September 2018.
3.5.20
Based on the approved HSR EIA Report (Register
No.: AEIAR-143/2009), it was estimated that the total approximate quantities of
excavated rock and soft inert materials would be 2,776,500 m3 and
5,378,800 m3 respectively, while the NOL Project would generate
about 431,840 m3 and 3,675,300 m3 of rock and soft inert
materials respectively. It is
therefore anticipated that the Project would generate lesser dust impact than
that from HSR due to excavation works and associated activities (e.g. spoil handling).
3.5.21
Given the similarities in nature of HSR and NOL,
components and construction methods, the actual dust impact by HSR has been
reviewed. Various construction
activities were carried out near the dust monitoring stations and their actual
dust impact was recorded, according to the EM&A manual of the approved HSR
EIA Report. Dust monitoring stations were generally placed near the surface
works sites of station, stabling sidings and shafts/ventilation buildings/emergency
access point. The actual dust
impact was recorded during the abovementioned construction activities and the
detailed dust monitoring results refer to its EM&A data website.
During the construction period of HSR, the measured 24-hr TSP levels at
all monitoring stations located at about 6m to 153m from the works site
boundary complied with limit level of 260 µg/m3, except two
measurement events of exceedance recorded which was not related to the
construction of the HSR project. In
addition, over 99% of the measured 24-hr TSP levels at all monitoring stations
were below the Action Level (i.e. 146 - 217 µg/m3) throughout the
construction period, indicating that no significant dust impact arising from
the construction of HSR. Therefore,
it is anticipated that no significant dust impact would arise from the
construction of the NOL which has similar nature and scope of HSR.
3.5.22
In view of insignificant dust impact caused by
past railway project of similar nature and scope, the potential construction
dust impact by the Project is evaluated by qualitative approach. A
comprehensive EM&A programme with RSP and FSP real-time monitoring would be
conducted to ensure the proper implementation of dust suppression measures and
the compliance of AQOs during the construction of NOL.
Operational
Phase
3.5.23
As electrically powered trains will be operated for
the Project, no air pollutants emissions will arise from the train operations.
The seven ancillary buildings will serve as Emergency Egress Point, Emergency
Access Point and/or Ventilation Building, which have no emissions. Exhaust for general ventilation and
smoke extraction facilities will be carefully positioned to avoid causing any
nuisance to the ambient. Train inspection/maintenance/repairing services will
be provided at Ngau Tam Mei Depot, which would not cause any emission. Electrified equipment for maintenance
will be deployed as far as practicable, and NRMM (Non-Road Mobile Machinery),
if any, to be used in the depot would comply with the prescribed emission
standard (i.e. approved NRMM) with relevant labels under the requirements of
the Air Pollution Control (NRMM) (Emission) Regulation, such that
limited air emission is anticipated, while exempted NRMM will also be avoided
as far as practicable. Therefore, no air quality issue is envisaged from
operation of the Project.
3.6
Prediction and Evaluation of Environmental Impacts
Construction Works Sites along
NOL
3.6.1
NOL comprises five stations, connecting
underground railway tunnels and seven ancillary buildings along NOL alignment.
As referred to Figure No. C1603/C/NOL/ACM/M50/305,
the station boxes, ancillary buildings, KSR(NOL) overrun tunnels and
crossover box and bifurcation at SAT
are to be constructed by cut-and-cover (Table 3.6 refers) while the
underground railway tunnel is to be constructed by TBM, cut-and-cover and
drill-and-blast methods (Table 3.7 refers). Construction works to be
conducted in different locations are also summarized in Table 3.6. These
major construction works would be carried out in open-air or completely
underground subject to their construction methods. Based on the latest design,
the works sites would scatter along the alignment and separate from each other
more than 500 meters apart.
The evaluation of potential construction dust impact for these distinct
locations are discussed separately in the following sections, together with the
identified concurrent works within 500 metres where applicable.
Table 3.6 Summary
of Major Aboveground Construction Works of NOL
Location
|
Aboveground Construction Works
|
Concurrent Project(s) Considered in the
Assessment
|
Kam Sheung Road
|
Construction of KSR(NOL) Station and
overrun tunnels (Cut-and-Cover)
|
Kam Tin South Housing Development
|
Shui Mei Road
|
Construction of Shui Mei Road Ancillary
Building (SMA) (Cut-and-Cover)
|
Nil
|
TBM Launching & Mucking-out
(Tunnels towards KSR and Tunnels towards AUT / NTM)
|
Au Tau
|
Construction of AUT Station
(Cut-and-Cover)
|
Sha Po Housing Development
|
Pok Wai and Long Ha
|
Construction of Pok Wai Ancillary Building
(PWA) (Cut-and-Cover)
|
Nil
|
Construction of Long Ha Ancillary Building
(LHA) (Cut-and-Cover)
|
Ngau Tam Mei
|
Construction of NTM Station
(Cut-and-Cover)
|
Nil
|
Construction of Ngau Tam Mei Depot (NTD)
(Cut and Fill)
|
San Tin
|
Construction of SAT Station, crossover
box, bifurcation, San Tin Ancillary Building (SNA) (Cut-and-Cover)
|
STLMC DN
|
TBM Launching & Mucking-out (Tunnel
towards NTM)
|
Construction of Ka Lung Road Ancillary
Building (KLA) (Cut-and-Cover)
|
Construction of Kwu Tung Ancillary
Building (KTA) (Cut-and-Cover)
|
Pak Shek Au
|
Construction of Pak Shek Au Ancillary
Building (PAA) (Cut-and-Cover)
|
STLMC DN
|
Kwu Tung
|
Construction of KTU(NOL) Station
(Cut-and-Cover)
|
KTN NDA &
KTU(EAL) Station
|
TBM Launching & Mucking-out (Tunnel
towards SAT)
|
Table 3.7 Summary
of Tunnelling Works of NOL
Tunnel
Section
|
Construction
Methods
|
Tunnels between KSR Station and AUT
Station
|
TBM
|
Tunnels between AUT Station and NTM
Station
|
TBM
|
Tunnels for crossover and tunnels between
PWA and LHA, and tunnels between LHA and NTD
|
Drill-and-Blast, Mined and Cut-and-Cover
|
Tunnels between NTM Station and SAT
Station
|
TBM
|
Tunnels between SAT Station and KTU(NOL)
Station
|
TBM
|
Kam Sheung Road (KSR) (NOL)
Station / Kam Sheung Road Area
3.6.2
KSR(NOL) Station adjacent to the existing
KSR(TML) and KSR(NOL) overrun tunnel would be built in the area by
cut-and-cover method. Also, the
works sites of KSR(NOL) Station would be utilized for the retrieval of TBMs
from SMA for the construction of underground tunnel north of the station.
Potential dust impact would arise from the associated construction activities
at these works sites, including site formation, excavation, backfilling, spoil
handling, vehicle movement on haul roads, wind erosion of the exposed site
area. The locations of works sites are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/303
to 304. Major excavation
works would be confined to station box. The construction of KSR(NOL) would also
adopt top-down construction method in certain section where some of works sites
would be covered up by the casted slab after the uppermost floor level is excavated.
The exposed area in the works site would therefore be reduced and only limited
openings would be left for transport of spoil out of the works sites. At the peak construction year of 2028 at
KSR, an averaged hourly traffic of about 26 trucks would be required for these
construction works based on the maximum daily spoiling rate estimated under the
current engineering design.
3.6.3
Village and planned residential uses are found
in the vicinity of KSR(NOL) works sites. ASRs within 500 metres from NOL works
sites have been identified and are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/303
to 304. The nearest ASRs to the
works sites would be the planned Kam Tin South GIC sites (KSR-PA02) where the
site boundary is 9 metres away from the works site, as the building layout is
yet to be finalized or available. The construction works of this planned public
housing site would be completed by phases, i.e. in 2027, 2028 and 2030 (Table
2.11 refers).
3.6.5
Construction works under Kam Tin South Housing
Development would be carried out concurrently with the Project. The location of
the concurrent project is illustrated in Figure Nos. C1603/C/NOL/ACM/M51/303
to 304. According to its
construction programme, most of the site formation and foundation works would
be completed by the time NOL works fully commencing in the area. Also, it is anticipated that appropriate
dust suppression measures stipulated in Air Pollution Control (Construction
Dust) Regulation, such as regularly watering and paved haul road, would be
implemented by the contractor of concurrent works and it would result in
minimum fugitive dust emission from the construction activities.
3.6.6
Should there be any intensive construction works
conducted in close vicinity of an ASR, the ASR would suffer from significant
dust impact. In order to avoid intensive works at a location in works sites,
KSR(NOL) Station and KSR(NOL) overrun tunnels would be constructed in several
workfronts by design of construction works. Construction activities would
scatter among these workfronts, as well as the associated fugitive dust
emission. Furthermore, coordination
or collaboration with the contractor(s)/project proponent of other concurrent
projects would be conducted such that any concurrent construction works in
close vicinity of ASRs could be adjusted / well-planned as far as practicable
for minimisation of potential dust impact.
3.6.7
The works sites of KSR(NOL) would be located at
about 9 metres away from boundary of planned GIC sites (KSR-PA02) of Kam Tin
South, and 11 metres away from planned public housing (KSR-PA01) under Kam Tin
South Public Housing Development. Dusty activities would be taken place
progressively across each work front with moving construction plant according
to work requirements to be determined at the time of construction. Hence,
construction dust emission is expected to be transient in nature. Dust impact
to these concerned ASRs should be limited with the adoption of dust suppression
measures such as regular watering and erection of hoarding with a combined
height of up to 3m (i.e. 2.4m hoarding with 0.6m dust screen on top) (subject
to site constraints and the required setback from CLP cable reserve zone) in
front of the air sensitive façade facing to the work site to shield off the
concerned ASRs from nearby dust emission sources. Dust monitoring is
recommended to ensure the potential dust impact complying with AQOs during the
construction phase. Detailed requirements of the dust monitoring are specified
in the EM&A Manual.
3.6.8
With the implementation of the abovementioned
effective dust suppression measures and good site practices, no adverse dust
impact on nearby ASRs in the area due to the construction of KSR(NOL) Station,
its overrun tunnel and other concurrent projects is anticipated. A
comprehensive EM&A programme would be conducted to ensure the proper
implementation of measures and the compliance of AQOs during the construction
of NOL in the area.
Shui Mei Road Ancillary Building (SMA)
3.6.9
Shui Mei Road Ancillary Building (SMA) locates
at the immediate south of Park Yoho and would be built by cut-and-cover
method. As
discussed in Section 2, the potential disturbance and impact to the
public and environment has been minimised through utilization of works site for
stations/ABs as TBM launching/retrieval shafts. The works sites of SMA would be used to
launch TBM towards KSR(NOL) Station and NTM Station. The location of works
sites are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/305 to 306. Potential construction dust
impact would arise from the associated construction activities in the works
sites, including site formation, excavation, backfilling, mucking out for TBM
tunneling, spoil handling, vehicle movement on haul roads, wind erosion of the
exposed site area. Major excavation
works is confined within the shaft area.
Upon completion of shaft construction, the dust emission associated with
the TBM tunneling works is expected minimum due to its adoption of a closed
system (Section 3.5.3
refers). At the peak construction year of 2028 at SMA, an averaged hourly
traffic of about 15 trucks would be required for these construction works based
on the maximum daily spoiling rate estimated under the current engineering
design.
3.6.10 Villages
and existing residential use are found in the vicinity of SMA. ASRs within 500
metres from SMA works sites have been identified and are illustrated in Figure
Nos. C1603/C/NOL/ACM/M51/305 to 306. Park Yoho (SMA-A02) would be
the nearest ASR to the works sites, which is around 10 metres away.
3.6.11 Similarly,
dust suppression measures for the construction works of other stations as
discussed in Section 3.6.4
is also applicable to the works sites of SMA. With the implementation of
appropriate dust suppression measures, for example regular watering at
excavation works, exposed areas and sites of spoil handling, paved and
regularly wetted haul roads, wheel washing facilities upon exit of works
sites/works areas, and good site practices, the fugitive dust emission from the
construction works would be reduced to minimum.
3.6.12 With
the implementation of the abovementioned effective dust suppression measures at
the works site and dust control measures at TBM tunnel works as stated in Section
3.5.3,
no adverse dust impact on nearby ASRs in the area due to the construction of
SMA and mucking out for TBM tunneling is anticipated. A comprehensive EM&A
programme would be conducted to ensure the proper implementation of measures
and the compliance of AQOs during the construction of NOL in the area.
Au Tau
(AUT) Station / Au Tau Area
3.6.13 AUT
Station locates adjacent to the planned Sha Po Public House Development, north
of Sha Po Tsuen, and it would be constructed by cut-and cover method. Potential
construction dust impact would arise from the associated construction
activities in the works sites, including site formation, excavation,
backfilling, spoil handling, vehicle movement on haul roads, wind erosion of
the exposed site area. The locations of works sites are illustrated in Figure
Nos. C1603/C/NOL/ACM/M51/306.
At the peak construction year of 2028
at AUT, an averaged hourly traffic of about 24 trucks would be required
for these construction works based on the maximum daily spoiling rate estimated
under the current engineering design.
3.6.14 There
are a few existing villages and planned public housing in the vicinity of the
NOL works, namely Sha Po Tsuen in the south and Mo Fan Heung in the north and
adjacent Sha Po Housing Development. ASRs within 500 metres from AUT
works sties have been identified and are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/306. Mo
Fan Heung (AUT-A06) would be the nearest ASR to the works site, which is
adjacent to the site hoarding of the works site. Planned public housing under
Sha Po Housing Development adjacent to AUT Station is to be completed in Year
2031. Referring the construction programme, major dusty construction works of
AUT Station, e.g. excavation works, is to be completed by mid of 2029, thus
only minor dust impact on the adjacent planned public house is expected due to
the remaining works of AUT Station.
3.6.15 Similarly,
dust suppression measures for the construction works of other stations as
discussed in Section 3.6.4
is also applicable to the works sites of AUT Station. With the implementation
of appropriate dust suppression measures, for example regular watering at
excavation works, exposed areas and sites of spoil handling, paved and
regularly wetted haul roads, wheel washing facilities upon exit of works
sites/works areas, and good site practices, the fugitive dust emission from the
construction works would be reduced to minimum.
3.6.16 Construction
works under Sha Po Housing Development would be the concurrent works
near the Project. According to its construction programme, its foundation works
would be completed by end of 2027 while the excavation works of AUT Station
commences in early 2027. Dusty construction activities of Sha Po Housing
Development would overlap with those of AUT Station in Year 2027. It is also
anticipated that appropriate dust suppression measures stipulated in Air
Pollution Control (Construction Dust) Regulation, such as regularly watering
and paved haul road, would also be implemented by the contractors of concurrent
works and it would result in minimum fugitive dust emission from the
construction activities.
3.6.17 Should
there be any intensive construction works conducted in close vicinity of an
ASR, the ASR would suffer from significant dust impact. In order to avoid
intensive works at a location in works sites, AUT Station is to be constructed
in several workfronts by design. Construction activities scatter among these
smaller workfronts and thereby minimising the associated fugitive dust
emission. Furthermore, coordination
or collaboration with the contractor(s)/project proponent of other concurrent
projects would be conducted such that any concurrent construction works in
close vicinity of ASRs could be adjusted / well-planned as far as practicable
for minimisation of potential dust impact.
3.6.18 The
works sites of AUT would exist in immediate proximity to the village house of
Mo Fan Heung (AUT-A06) which is adjacent to site hoarding of the works site.
Dusty activities would be taken place progressively across each work front with
moving construction plant according to work requirements to be determined at
the time of construction. Hence, construction dust emission is expected to be
transient in nature. Dust impact to these concerned ASRs should be limited with
the adoption of dust suppression measures such as regular watering and erection
of hoarding with a combined height of up to 3m (i.e. 2.4m hoarding with 0.6m
dust screen on top) in front of the air sensitive façade facing to the work
site to shield off the concerned ASRs from any dust emission sources. Dust
monitoring at these locations is recommended to ensure the potential dust
impact complying with AQOs during the construction phase.
3.6.19 With
the implementation of the abovementioned effective dust suppression measures
and good site practices, no adverse dust impact on nearby ASRs in the area due
to the construction of AUT Station and other concurrent projects is
anticipated. A comprehensive EM&A programme would be conducted to ensure
the proper implementation of measures and the compliance of AQOs during the
construction of NOL in the area.
Pok Wai Ancillary Building (PWA) and Long Ha Tsuen Ancillary Building (LHA)
3.6.20 Pok Wai Ancillary
Building (PWA) and Long Ha Tsuen Ancillary Building (LHA) locate east of
Kai Kung Shan, between AUT and NTM Stations along the NOL alignment. These two
ABs would be built by cut-and-cover method and the works sites would also be
utilized for export of spoil from the drill-and-blast underground tunnel
towards the NTD Portal, and exhaust vent for the underground works. The locations of works sites are
illustrated in Figure Nos. C1603/C/NOL/ACM/M51/307.
Potential construction dust impact would arise from the associated
construction activities in the works sites, including site formation,
excavation, backfilling, spoil handling, vehicle movement on haul roads, wind
erosion of the exposed site area.
Major excavation works would be confined to small shaft areas. Upon completion of shaft construction,
the dust emission associated with the drill-and-blast works is expected minimum
with adoption of regular watering, filtration system and blast door for confining
the dust within the shaft (Section 3.5.4
refers). At the peak construction year of 2029 at PWA and LHA, an averaged
hourly traffic of about 11 ad 19 trucks respectively would be required for
these construction works based on the maximum daily spoiling rate estimated
under the current engineering design.
3.6.21 Villages
and existing residential use are found in the vicinity of PWA and LHA. ASRs
within 500 metres from the works sites have been identified and are illustrated
in Figure Nos. C1603/C/NOL/ACM/M51/307.
The nearest ASRs to the works sites of PWA would be the village houses (PWA-A01
& PWA-A02) adjacent to the site hoarding of works sites, while the village
house (LHA-A01) is 17 metres away from the works site of LHA. With careful planning of work sequence
and design optimization of workfronts, the fugitive dust emission from the
works sites could be reduced.
3.6.22 In
addition, dust suppression measures for the construction works of other
stations as discussed in Section 3.6.4
is applicable to the works sites of PWA and LHA. A
filtration system comprising watering and dust collector, etc. with overall
dust removal efficiency of at least 80% should be provided at the ventilation
exhaust. Together with the implementation of appropriate dust suppression
measures, for example regular watering at excavation works, exposed areas and
sites of spoil handling, paved and regularly wetted haul roads, wheel washing
facilities upon exit of works sites/works areas, and good site practices, the
fugitive dust emission from the construction works would be reduced to minimum.
3.6.23 The
works sites of PWA would exist in immediate proximity to nearby village houses
(PWA-A01 & PWA-A02) which are adjacent to the site hoarding of the works
site. Dusty activities would be taken place progressively across each work
front with moving construction plant according to work requirements to be
determined at the time of construction. Hence, construction dust emission is
expected to be transient in nature. Dust impact to these concerned ASRs should
be limited with the adoption of dust suppression measures such as regular
watering and erection of hoarding with a combined height of up to 3m (i.e. 2.4m
hoarding with 0.6m dust screen on top) in front of the air sensitive façade
facing to the works site to shield off the concerned ASRs from any dust emission
sources. Dust monitoring at these locations is recommended to ensure the
potential dust impact complying with AQOs during the construction phase.
3.6.24 With
the implementation of the abovementioned effective dust suppression measures,
no adverse dust impact on nearby ASRs in the area due to the construction of
PWA and LHA, and export of spoil from drill-and-blast tunneling works is
anticipated. A comprehensive EM&A programme would be conducted to ensure
the proper implementation of measures and the compliance of AQOs during the
construction of NOL in the area.
Ngau Tam
Mei (NTM) Station and Ngau Tam Mei Depot (NTD)
3.6.25 Several
components of NOL are to be constructed in Ngau Tam Mei, namely Ngau Tam Mei
(NTM) Station, Ngau Tam Mei Depot (NTD), and NTD Portal. NTM Station and NTD
Portal would be constructed by cut-and-cover, while NTD would involve mostly
cut slope and backfilling. NTD
Portal would also be utilized for export of spoil from the drill-and-blast
underground tunnel in the south, and exhaust vent for the underground
works. The locations of works sites
are illustrated in Figure No. C1603/C/NOL/ACM/M51/309.
Potential dust impact would arise from the associated construction
activities at the works sites, including site formation, excavation,
backfilling, spoil handling, vehicle movement on haul roads, wind erosion of
the exposed site area. Major excavation works would be confined to station box
and portal area for initial tunneling works. Also, the works sites of NTM Station
would be utilized for the retrieval of TBMs from KTU(NOL) Station and from SMA
for the construction of northbound and southbound underground tunnel
respectively. Upon completion of shaft construction, the dust emission
associated with the drill-and-blast works is expected minimum with adoption of
regular watering, filtration system and blast door for confining the dust
within the shaft (Section 3.5.4
refers). At the peak construction year of 2027 at NTM and NTD, an averaged
hourly traffic of about 58 trucks would be required for these construction
works based on the maximum daily spoiling rate estimated under the current
engineering design.
3.6.26 Existing
village house and low-rise residential uses are found in the vicinity of NOL
works in the area. ASRs within 500 metres from works sites have been identified
and are illustrated in Figure No. C1603/C/NOL/ACM/M51/309. The
land uses in the area are being reviewed under NTM LUR of which the proposed
land uses and their implementation programme are not available during the
course of this EIA study. The
nearest ASRs to the works sites would be the village house (NTM-A13 & NTM-A14) which are adjacent to the
site hoarding of works sites. With
careful planning of work sequence and design optimization of workfronts in Ngau
Tam Mei area, dispersion of construction dust out of works sites to the nearby
ASRs could be reduced.
3.6.27 In
addition, dust suppression measures for the construction works of other
stations as discussed in Section 3.6.4
is also applicable to the works sites of NTM Station and NTD. A filtration
system comprising watering and dust collector, etc. with overall dust removal
efficiency of at least 80% should be provided at the ventilation exhaust.
Together with the implementation of appropriate dust suppression measures, for
example regular watering at excavation works, exposed areas and sites of spoil
handling, paved and regularly wetted haul roads, wheel washing facilities upon
exit of works sites/works areas, and good site practices, the fugitive dust
emission from the construction works is reduced to minimum.
3.6.28 It
is assumed that appropriate dust suppression measures stipulated in Air
Pollution Control (Construction Dust) Regulation, such as regularly watering
and paved haul road, would be implemented properly by the contractors of
concurrent works and it results in minimum fugitive dust emission from their
construction activities.
3.6.29 In
order to avoid intensive works at a location near ASR, NTM Station is to be
constructed by several workfronts in design. The cut and fill works of NTD
would be conducted by stages, from north to south. With the implementation of
workfronts in design, construction activities scatter among these smaller
workfronts and thereby minimising the associated fugitive dust emission.
3.6.30 The
works sites of NTM station would exist in close proximity to two ASRs, e.g. at
9 metres away from Hongtai Home for the Aged Limited (NTM-A03) and at 3 metres
away from the village house (NTM-A04). The village houses (NTM-A13 &
NTM-A14) are adjacent to the site hoarding of the NTD works site. Dusty
activities would be taken place progressively across each work front with
moving construction plant according to work requirements to be determined at
the time of construction. Hence, construction dust emission is expected to be
transient in nature. Dust impact to these concerned ASRs should be limited with
the adoption of dust suppression measures such as regular watering and erection
of hoarding with a combined height of up to 3m (i.e. 2.4m hoarding with 0.6m
dust screen on top) in front of the air sensitive façade facing to the works
site to shield off the concerned ASRs from nearby dust emission sources. Dust
monitoring at these locations is recommended to ensure the potential dust
impact complying with AQOs during the construction phase.
3.6.31 With
the implementation of the abovementioned effective dust suppression measures
and good site practices, no adverse dust impact on nearby ASRs in the area due
to the construction of NTM Station, NTD and NTD Portal is anticipated. A
comprehensive EM&A programme would be required to ensure the proper
implementation of measures and the compliance of AQOs during the construction
of NOL in the area.
San
Tin (SAT) Station / SNA / KLA / KTA / San Tin Area
3.6.32 San Tin (SAT) Station locates within the
planned San Tin / Lok Ma Chau Development Nodes (STLMC DN). The works
sites would be used for the launch of TBMs, tunneling towards NTM Station.
There are also three ancillary buildings (i.e. SNA, KLA, KTA) within STLMC DN.
SAT Station and the three ancillary buildings would be built by cut-and-cover method.
A CBP is also proposed at the works site of SAT Station, adjacent SNA, to meet
the concrete demand by the constructions of tunnel and stations. Potential
construction dust impact would arise from the associated construction
activities in the works sites, including site formation, excavation,
backfilling, mucking out for TBM tunneling, spoil handling, vehicle movement on
haul roads, wind erosion of the exposed site area and concrete batching. The
location of works sites are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/310,
312 to 315. Major excavation works would be confined to station box and
shaft areas. Upon completion of
launching shaft, the dust emission associated with the TBM tunneling works is
expected minimum due to its adoption of a closed system (Section 3.5.3
refers). At the peak construction year of 2030 at SAT and SNA, an averaged
hourly traffic of about 54 trucks would be required for these construction
works based on the maximum daily spoiling rate estimated under the current
engineering design. Similarly, an averaged hourly traffic of about 3 and 2
trucks would be required during the peak construction year of 2028 at KLA and
2029 at KTA respectively.
3.6.33 Existing
village house and low-rise structures for brownfield operations are found in
the vicinity of NOL works in the area. Under STLMC DN, most of the San Tin area
are to be redeveloped except the existing villages to be retained, namely Shek
Wu Wai, Fan Tin Tsuen, Wing Ping Tsuen and Siu Hum Tsuen, etc. The
redevelopment in STLMC DN would be completed in three phases: Initial Phase for
northeastern and southwestern areas of STLMC DN, Main Phase for the
southeastern and northwestern parts, and Remaining Phase for sites with the
completed NOL works. The first population intake in STLMC DN Initial Phase
would be expected in Year 2031, while the population intake in STLMC DN Main
Phase would appear in Year 2034. SAT Station of NOL is designed to support the
population in STLMC DN, thus major construction works of SAT Station and ABs in
this area should be completed by the first population intake in STLMC DN Main
Phase. Planned uses under STLMC DN Main Phase and Remaining Phase should
therefore not be affected by the dust impact due to remaining works of SAT
Station and ABs. ASRs within 500 metres from works sites have been identified
and are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/310,
312 to 314. The nearest ASR to works site of SAT
Station and ABs during the construction phase would include Christian New Life
Association (SAT-A01) which is 11 metres away from the works sites of SAT, the
retained village Shek Wu Wai (SAT-A03 & SAT-A05) which is 56 and 14 metres
away from the works site of SAT respectively. Shun Sum Yuen Farm (SAT-A06) is 7
metres away from the works site of SAT and SNA. The planned residential uses
(SAT-PA01) will commission under STLMC Initial Phase, which is 44 metres away
from the south portal of SAT station. With careful planning of work sequence
and design optimization of workfronts, the fugitive dust emission from the
works sites could be reduced.
3.6.34 In
addition, dust suppression measures for the construction works of other
stations as discussed in Section 3.6.4
is applicable to the works sites of SAT Station, SNA KLA and KTA. With the
implementation of appropriate dust suppression measures, for example regular
watering at excavation works, exposed areas and sites of spoil handling, paved
and regularly wetted haul roads, wheel washing facilities upon exit of works
sites/works areas, and good site practices, the fugitive dust emission from the
construction works would be reduced to minimum.
3.6.35 For
the potential cumulative impact, the construction programme of STLMC DN has
also been reviewed. Site formation
works of STLMC DN Initial Phase would commence in late 2024 and target for
first population intake by Year 2031. Site formation works of STLMC DN Main
Phase would commence in Year 2026 and target for population intake by Year
2034. Major construction works of SAT Station and ABs including excavation and
backfilling works would be carried out concurrently with STLMC DN Main Phase,
and would be completed by the first population intake in STLMC DN Main Phase.
It is anticipated that appropriate dust suppression measures stipulated in Air
Pollution Control (Construction Dust) Regulation, such as regularly
watering and paved haul road, would also be implemented by the contractors of
STLMC DN and it would result in minimum fugitive dust emission from their
construction activities.
3.6.36 The
operation of the proposed CBP would last longer, until Year 2034 to support the
overall construction of NOL. Dust control measures should be implemented in the
CBP as required in A Guidance Note on the Technical, Management and
Monitoring Requirements for Specified Process ¨C Cement Works (Concrete Batching
Plant) (BPM 3/2 (16)). Best practicable means such as dust collectors at
silos / mixers, 3-side and top enclosure at aggregate receiving hopper,
regularly wetting on paved haul roads, etc. are proven effective measures in
suppressing fugitive dust emission arising from concrete batching. The proposed
CBP is classified as a Specified Process, thus its operation, dust control
measures and resulting dust impact are regulated under APCO and a licence under
the regulations should be applied by the responsible contractor as appropriate.
With the implementation of effective dust control measures and good site
practice, it is expected that the significant dust impact due to the operation
of CBP would be confined within the boundary of the plant.
3.6.37 In
order to avoid intensive works at a location near ASR, SAT Station, crossover
box and bifurcation would be constructed in several workfronts by design. Owing to the large extent of STLMC DN,
the construction works under Initial and Main Phases are also expected to be
conducted in numerous workfronts, subject to the land resumption schedule. With
the implementation of workfronts in the works sites, construction activities
scatter among these smaller workfronts and thereby minimising the associated
fugitive dust emission.
Furthermore, coordination or collaboration with the
contractor(s)/project proponent of other concurrent projects would be conducted
such that any concurrent construction works in close vicinity of ASRs could be
adjusted / well-planned as far as practicable for minimisation of potential
dust impact.
3.6.38 The
works sites in San Tin area would exist in close proximity to one ASR, i.e.
Shun Sum Yuen Farm (SAT-A06) at 7 metres away from works sites of SAT station
and SNA. The concerned ASR is subject to development under the STLMC DN. Dusty
activities would be taken place progressively across each work front with
moving construction plant according to work requirements to be determined at
the time of construction. Hence, construction dust emission is expected to be
transient in nature. Dust impact to the concerned ASR should be limited with
the adoption of dust suppression measures such as regular watering and erection
of hoarding with a combined height of up to 3m (i.e. 2.4m hoarding with 0.6m
dust screen on top) in front of the air sensitive façade facing to the works
site to shield off the concerned ASR from nearby dust emission sources. Dust
monitoring at the concerned ASR is recommended to ensure the potential dust
impact complying with AQOs during the construction phase.
3.6.39 With
the implementation of the abovementioned effective dust suppression measures
and good site practices, no adverse dust impact on nearby ASRs in the area due
to the construction of SAT Station, ABs, and other concurrent projects is
anticipated. A comprehensive EM&A programme would be conducted to ensure
the proper implementation of measures and the compliance of AQOs during the
construction of NOL in the area.
Pak Shek Au Ancillary Building (PAA)
3.6.40 Pak Shek Au
Ancillary Building (PAA) locates between STLMC DN and KTU
NDA and would be built by cut-and-cover method. The locations of works sites
are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/315
to 316. Potential
construction dust impact would arise from the associated construction
activities in the works sites, including site formation, excavation,
backfilling, spoil handling, vehicle movement on haul roads, wind erosion of
the exposed site area. Major
excavation works will be limited to relatively small shaft area. At the peak
construction year of 2026 at PAA, an averaged hourly traffic of about 2 trucks
would be required for these construction works based on the maximum daily
spoiling rate estimated under the current engineering design.
3.6.41 Existing
villages and planned uses under STNLMC DN and KTU NDA are found in the vicinity
of PAA. ASRs within 500 metres from the works sites have been identified and
are illustrated in Figure Nos. C1603/C/NOL/ACM/M51/315
to 316. The nearest ASR to the
works site would be a village house (i.e. KTU-A05) which is approximately 35
metres away from the works site.
With careful planning of work sequence and design optimization of
workfronts, the fugitive dust emission from the works sites could be reduced.
3.6.42 In
addition, dust suppression measures for the construction works of other
stations as discussed in Section 3.6.4
is applicable to the works sites of PAA. With the implementation of
appropriate dust suppression measures, for example regular watering at
excavation works, exposed areas and sites of spoil handling, paved and
regularly wetted haul roads, wheel washing facilities upon exit of works
sites/works areas, and good site practices, the fugitive dust emission from the
construction works would be reduced to minimum.
3.6.43 For
the potential cumulative impact, the construction programme of KTN NDA has also
been reviewed. Site formation works
of KTN NDA Advance Works would be completed in 2025/2026 and target for first
population intake by Year 2026. Site formation works of Remaining Phase would
commence in Year 2024 and target for population intake by Year 2034. The
construction works of PAA including site formation and excavation works would
start in Year 2025 and to be completed by Year 2027, which are to be carried
out concurrently with KTN NDA. It is assumed that appropriate dust suppression
measures stipulated in Air Pollution Control (Construction Dust) Regulation,
such as regularly watering and paved haul road, would be implemented properly
by the contractors of KTN NDA and it would result in minimum fugitive dust
emission from their construction activities.
3.6.44 With
the implementation of the abovementioned effective dust suppression measures,
no adverse dust impact on nearby ASRs in the area due to the construction of
PAA is anticipated. A comprehensive EM&A programme would be conducted to
ensure the proper implementation of measures and the compliance of AQOs during
the construction of NOL in the area.
Kwu Tung (KTU) Station (NOL) / Kwu Tung Area
3.6.45 Kwu
Tung (KTU) Station (NOL) is to be constructed by cut-and-cover method, which
locates next to KTU(EAL) station and within the planned Kwu Tung North New
Development Area (KTN NDA). The works sites of KTU(NOL) Station would also
be used to launch TBMs, tunnelling towards SAT Station. The location of works sites are
illustrated in Figure Nos. C1603/C/NOL/ACM/M51/316.
Potential construction dust impact would arise from the associated construction
activities in the works sites, including site formation, excavation,
backfilling, mucking out for TBM tunneling, spoil handling, vehicle movement on
haul roads, wind erosion of the exposed site area. Major excavation works would
be confined to station box. Top-down construction method is adopted for part of
the station in which the uppermost floor level is excavated first, followed by
casting a slab above, and repeat this process until the bottom level is
reached. With such method, the exposed area of the works sites would be covered
up by the slab with the subsequent construction activities to be conducted
underneath. It would result in less fugitive dust emitted from the works sites
and only confined at the openings of the slab. Upon completion of launching
area of TBM, the dust emission associated with the TBM tunneling works is
expected minimum due to its adoption of a closed system (Section 3.5.3
refers). At the peak construction year of 2030 at KTU(NOL), an averaged
hourly traffic of about 34 trucks would be required for these construction
works based on the maximum daily spoiling rate estimated under the current
engineering design.
3.6.46 KTN
NDA would be constructed by two phases, namely Advance Works and Remaining
Phase. The site formation works and infrastructure works under Advance Works
already commenced in Year 2019 and the ones of Remaining Phase will commence in
coming 2024. The area of KTU NDA is expected to be under construction by the
time KTU(NOL) Station construction works commence. Existing land use in
vicinity of KTU(NOL) Station would no longer exist. The existing residential
uses would be south of KTU NDA across Fanling Highway. Planned public housing
under KTN NDA would appear in around Year 2027 and Year 2030 under the two
phases respectively. ASRs within 500 metres from works sites have been
identified and are illustrated in Figure No. C1603/C/NOL/ACM/M51/316. The nearest ASR to works site of
KTU(NOL) Station would be the planned public and private housing under KTN NDA
(KTU-PA02) which is 10 metres away from the works site of KTU(NOL) Station. As mentioned in Section 3.6.39,
the proposed top-down construction method for the construction of KTU(NOL)
Station would limit the exposed area of the works sites and cover the
subsequent construction activities to be conducted underneath.
3.6.47 In
addition, dust suppression measures for the construction works of other
stations as discussed in Section 3.6.4
is applicable to the works sites of KTU(NOL) Station. With the
implementation of appropriate dust suppression measures, for example regular
watering at excavation works, exposed areas and sites of spoil handling, paved
and regularly wetted haul roads, wheel washing facilities upon exit of works
sites/works areas, and good site practices, the fugitive dust emission from the
construction works would be reduced to minimum.
3.6.48 For
the potential cumulative impact, the construction programme of KTN NDA has also
been reviewed. Site formation works
of KTN NDA Advance Works would be completed in 2025/2026 and target for first
population intake by Year 2026. Site formation works of Remaining Phase would
commence in Year 2024 and target for population intake by Year 2034.
Construction works of KTU(EAL) would commence in Year 2023 and with major works
to be completed before Year 2026. Meanwhile, major construction works of
KTU(NOL) Station including excavation and backfilling works would be concurrent
with KTN NDA and KTU(EAL), and to be completed by Year 2031. It is assumed that
appropriate dust suppression measures stipulated in Air Pollution Control
(Construction Dust) Regulation, such as regularly watering and paved haul
road, would be implemented properly by the contractors of KTN NDA and it would
result in minimum fugitive dust emission from their construction
activities. Furthermore,
coordination or collaboration with the contractor(s)/project proponent of other
concurrent projects would be conducted such that concurrent construction works,
if any, in close vicinity of ASRs could be adjusted / well-planned as far as
practicable for minimisation of potential dust impact.
3.6.49 The
works sites KTU(NOL) would be located at about 10 metres away from planned
housing development (KTU-PA01 & KTU-PA02). These concerned ASRs are under
the development of KTN NDA. These ASRs would adopt podium design which causes
their first level of air sensitive use further away from the ground. Dusty
activities would be taken place progressively across each work front with
moving construction plant according to work requirements to be determined at
the time of construction. Hence, construction dust emission is expected to be
transient in nature. Dust impact to these concerned ASRs should be limited with
the adoption of dust suppression measures such as regular watering. Dust
monitoring at these locations is recommended to ensure the potential dust impact
complying with AQOs during the construction phase.
3.6.50 With
the implementation of the abovementioned effective dust suppression measures,
no adverse dust impact on nearby ASRs in the area due to the construction of
KTU(NOL) is anticipated. A comprehensive EM&A programme would be conducted
to ensure the proper implementation of measures and the compliance of AQOs
during the construction of NOL in the area.
Offsite Explosive
Magazine Site
3.6.51 The
offsite works area at Tai Shu Ha, Yuen Long is proposed to be used as temporary
explosive magazine site. The site was formerly used as temporary explosive
magazine site by HSR and Liantang/Heung Yuen Wai Boundary Control Point
Project and had been reinstated for about 5 years. The closest ASR, TSA01, is located at
more than 125 metres away from the boundary of the magazine site. Minor non-dusty
works would be required to prepare the magazine site, such as vegetation
clearance, brick-built magazine, fencing, sandbag mounds and access road, where
no excavation works would be anticipated for these preparation works. Vehicle access to the site is expected to be
a maximum of about 2 trucks per hour during the construction of NOL. Given
no excavation works and minor traffic induced, the associated potential air
quality impact on the ambient is considered negligible.
3.6.52 The
temporary magazine site will be decommissioned and reinstated after the
construction of the Project. The decommissioning works would include minor
dismantling, demolition and removal of temporary structures. Owing to the
nature and the small scale of decommissioning works, the potential dust impact
is expected to be minimum. With the implementation of dust suppression measures
stipulated in the Air Pollution Control (Construction Dust) Regulation, no
adverse dust impact due to the decommissioning works is expected.
3.7
Summary of Dust Suppression Measures
3.7.1
Based on the above discussion, a summary of key
dust suppression measures to be implemented during the construction phase is
provided below:
¡¤
Regular watering on construction works sites and exposed site surface should be
conducted.
¡¤
Paving should be provided to open haul road within works sites / works
areas.
¡¤
For the works sites close to the ASRs
with the air sensitive facades at a separation distance of less than 10 m,
provide hoarding with a combined height of up to 3m
(i.e. 2.4m hoarding with 0.6m dust screen on top) from ground level along the site
boundary, subject to site constraints and status of ASRs; for the other work
sites in general, provide
hoarding of not less than 2.4m high from ground level along site boundary
except for site entrance or exit.
¡¤
Dust control measures will be
implemented in the CBP as required in A Guidance Note on the Technical,
Management and Monitoring Requirements for Specified Process ¨C Cement Works
(Concrete Batching Plant) (BPM 3/2 (16)).
¡¤
For the mucking-out operation at TBM launching shafts, regular watering
should be provided at the unloading point of spoils generated by the TBM
excavation.
¡¤
For the tunnelling works by drill-and-blast, in addition to the regular
watering at spoiling handing and unpaved / paved haul roads, a blast door
should be installed at the opening to avoid the escape of fugitive dust from
the blasting. The blast door should remain closed and ventilation stopped
during blasting. Water spaying should be applied to facilitate dust settlement.
A filtration system comprising watering and dust collector, etc. with overall
dust removal efficiency of at least 80% should be provided at the ventilation
exhaust to treat dust-laden exhaust before release to the ambient. The exhaust
vents will locate at the tunnel portals at the sites of NTD, LHA and PWA.
3.8
Evaluation of Residual Impacts
3.8.1
Apart from dust suppression measures mentioned
in Section 3.7, the dust suppression measures stipulated in the Air
Pollution Control (Construction Dust) Regulation and good site practices listed
below should also be carried out to further minimize construction dust impact.
¡¤
Use of regular watering to reduce dust emissions from exposed site
surfaces and unpaved roads, particularly during dry weather.
¡¤
Side enclosure and covering of any aggregate or dusty material storage
piles to reduce emissions. Where
this is not practicable owing to frequent usage, watering should be applied to
aggregate fines.
¡¤
Open stockpiles should be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs.
¡¤
Tarpaulin covering of all dusty vehicle loads transported to, from and
between site locations.
¡¤
Establishment and use of vehicle wheel and body washing facilities at
the exit points of the site.
¡¤
Imposition of speed controls for vehicles on site haul roads.
¡¤
Where possible, routing of vehicles and positioning of construction
plant should be at the maximum possible distance from ASRs.
¡¤
Instigation of an environmental monitoring and auditing program to
monitor the construction process in order to enforce controls and modify method
of work if dusty conditions arise.
3.8.2
With the implementation measures specified in
Air Pollution Control (Construction Dust) Regulation together with the
control measures such as regular watering on the works sites and exposed
surface, no adverse residual impact would be expected from the construction of
the Project.
3.8.3
To minimise the exhaust emission from NRMMs
during the construction phase, the following measures should be applied as far
as practicable:
¡¤
Connect construction plant and equipment to main electricity supply and
avoid use of diesel generators and diesel-powered equipment;
¡¤
Avoid the use of exempted NRMMs as far as practicable; and
¡¤
Deploy electrified NRMMs as far as practicable.
3.9
Environmental Monitoring and Audit
3.9.1
EM&A for potential dust impacts are
recommended during the construction phase of the Project so as to check
compliance with legislative requirements. Real-time RSP and FSP monitoring will
also be conducted. Details of the monitoring and audit programme are presented
in a stand-alone EM&A Manual.
3.10.1
Potential construction dust impact would arise
from the construction of the Project.
Cumulative dust impact from construction activities of the Project and
concurrent projects were evaluated.
Based on former dust monitoring data of HSR which has similar nature and
scale of the Project, it would be anticipated that no significant dust impact
would arise from the construction of the Project. Design control measures and dust suppression measures such as regular watering
during the dusty construction activities, blasting door and regular
watering during blasting operation will be implemented during the construction
of the Project, no adverse construction dust impact is anticipated. A comprehensive EM&A programme would
be conducted to ensure the proper implementation of measures and the compliance
of AQOs during the construction of NOL.