TABLE OF CONTENTS
5.2 Environmental
Legislation, Plans, Standards, and Guidelines
5.3 Description of the Environment
5.5 Ground-borne
Noise Sensitive Receivers
5.7 Evaluation
of Environmental Impacts
5.8 Recommended Mitigation Measures
5.9 Cumulative
Impacts from Existing Railway
Projects
5.10 Evaluation
of Residual Impacts
List
of Tables
Table 5.1 Construction
Ground-borne Noise Criteria
Table 5.2 Operational
Ground-borne Noise Criteria
Table 5.5 Reference Source Levels
Table 5.6 Train Operation Parameters
Adopted in Operational Ground-borne Noise Assessment
Table 5.7 Predicted Construction
Ground-borne Noise Impact from PME Operation
Table 5.8 Predicted Construction
Ground-borne Noise Impact from TBM Operation
Table 5.9 Predicted Cumulative
Construction Ground-borne Noise Impact
Table 5.10 Predicted Ground-borne
Railway Noise Impact under Base Case Scenario
Table 5.11 Cumulative Ground-borne
Railway Noise Impact
List
of Figures
|
Locations
of Noise Sensitive Receivers (Ground-borne Noise) (Key Plan) Locations
of Noise Sensitive Receivers (Ground-bone Noise) (Sheet 1 to 11) |
Appendix
5.1 |
Not
Used |
|
Force
Density Level of Train Type SP1900 |
|
|
Tunnel
Coupling Factor for Bored Tunnel in Soil |
|
|
Noise
Measurement Report for Line Source Response (LSR) for Different Ground Types |
|
|
Adopted
LSR Values for Ground-borne Noise Assessment |
|
|
Building
Coupling Factor ¨C Type 0 to Type 3 Structures |
|
|
Building
Vibration Response |
|
|
Train
Speed Profile |
||
GBN
Calculation for PME Operation |
|
|
GBN
Calculation for TBM Operation |
|
|
Trackform
Insertion Loss |
|
|
Sample
Calculation for Operational Ground-borne Railway Noise (Base Case Scenario) |
|
|
Predicted
Ground-borne Railway Noise Levels at the NSRs at Representative Floor Levels |
|
Table 5.1 Construction Ground-borne Noise Criteria
Type of
GBNSR / Assessment Point (1) |
Construction
Ground-borne Noise Criteria |
||
Daytime (0700-1900 hrs) (Leq, 30min, dB(A)) |
Daytime during
general holidays and Sundays and all days during Evening(2) (Leq, 5min, dB(A)) |
Night(2) (Leq, 5min, dB(A)) |
|
Domestic premises,
hotels and hostels |
65 |
60 for ASR
¡°C¡± / 55 for ASR
¡°B¡± / 50 for ASR ¡°A¡± |
45 for ASR
¡°C¡± / 40 for ASR
¡°B¡± / 35 for ASR
¡°A¡± |
Churches,
Educational Institutions and Clinics |
60 / 55 (3) |
60 for ASR
¡°C¡± / 55 for ASR
¡°B¡± / 50 for ASR ¡°A¡± |
- (4) |
Notes:
(1)
Assessment point locates at an internal
location of a building in which the GBNSR is located.
(2)
Ground-borne noise is deemed not to be
affected by Influencing Factors (IF), therefore, the effect of IF should not be
considered to determine the appropriate noise criteria during restricted hours.
(3)
A 5dB(A) reduction to the ground-borne
noise criteria is recommended for school during examination period.
(4)
No sensitive use/activity during this
period.
Table 5.2 Operational Ground-borne Noise Criteria
Type of
GBNSR / Assessment Point (1) |
Ground-borne
Noise Criteria, (Leq,
30min, dB(A)) |
|
Day and Evening(2) (0700-2300 hrs) |
Night(2) |
|
Domestic premises, hotels and hostels |
60 for ASR
¡°C¡±/ 55 for ASR
¡°B¡± / 50 for ASR ¡°A¡± |
50 for ASR
¡°C¡± / 45 for ASR
¡°B¡± / 40 for ASR ¡°A¡± |
Churches, Educational
Institutions and Clinics |
- (3) |
Notes:
(1)
Assessment point locates at an internal
location of a building in which the GBNSR is located.
(2)
Ground-borne noise is deemed not to be affected
by IF, therefore, the effect of IF should not be considered to determine the
appropriate noise criteria.
(3)
No sensitive use/activity during this
period.
Table 5.3 Representative
Existing Ground-borne Noise Sensitive Receivers during
Construction and Operational Phases
GBNSR ID |
Description |
Land Use(1) |
No. of Storey |
Type of Area |
Influencing Factor |
Degree to which GBNSR is
affected (2) |
ASR(2) |
Construction GBN Impact |
Operation GBN Impact |
|
TBM(10) |
PME |
|||||||||
KSR-G01 |
No.110 Cheung Chun San Tsuen |
R |
2 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
KSR-G02 |
Blk 77, Sam Yuen |
R |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
KSR-G03 |
Kam Tin Mung Yeung Public School |
E |
2 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
KSR-G04 |
No.297-298 Kut Hing Wai |
R |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
KSR-G05 |
Kat Hing Garden |
R |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
AUT-G01 |
No. 173, Mo Fan Heung |
R |
1 |
Area other than those
above(3) |
Industrial Zone |
Within 100m of Industrial Zone(9) |
B |
¡Ì |
|
¡Ì |
AUT-G02 |
No. 137, Mo Fan Heung |
R |
1 |
Area other than those
above(3) |
Industrial Zone |
Within 100m of Industrial Zone(9) |
B |
¡Ì |
|
¡Ì |
AUT-G03 |
No. 80, Mo Fan Heung |
R |
1 |
Area other than those
above(3) |
Industrial Zone |
Within 100m of Industrial Zone(9) |
B |
¡Ì |
|
¡Ì |
AUT-G06 |
Tower 2B, Park Yoho Silica |
R |
14 |
Area other than those
above (4) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-G07 |
Tower 9B, Park Vista |
R |
16 |
Area other than those
above (4) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-G08 |
Tower 8B, Park Yoho |
R |
14 |
Area other than those
above (4) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-G09 |
In Keen Garden Phase 1 |
R |
3 |
Area other than those
above (4) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-G10 |
York International Kindergarten (8) |
E |
1 |
Area other than those
above (4) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-G11 |
169 Pok Wai |
R |
2 |
Low density residential area |
San Tin Highway |
Indirectly Affected |
B |
(11) |
¡Ì |
|
NTM-G01 |
The Vineyard |
R |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
NTM-G02 |
China Bible Seminary |
E |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
NTM-G03 |
House A, Greenacres Villa |
R |
3 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
NTM-G04 |
Hongtai Home for the Aged Limited |
EC |
3 |
Area other than those
above (5) |
- |
- |
B |
¡Ì |
|
¡Ì |
NTM-G04a |
Temporary Structure near Ching
Yau Road |
R |
1 |
Area other than those
above (5) |
- |
- |
B |
¡Ì |
|
¡Ì |
NTM-G06 |
Village House near Fuk Hing Lei |
R |
2 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
¡Ì |
NTM-G07 |
Village House near Wang Ping Shan
South Road |
R |
3 |
Area other than those
above (6) |
- |
- |
B |
¡Ì |
¡Ì |
¡Ì |
NTM-G08 |
Village House near Wang Ping Shan
South Road |
R |
1 |
Area other than those
above (6) |
- |
- |
B |
¡Ì |
¡Ì |
¡Ì |
NTM-G09 |
Village House in Long Ha |
R |
1 |
Low density residential area |
- |
- |
A |
(11) |
¡Ì |
|
SAT-G03 |
Temporary Structure near Shek Wu
Wai |
R |
2 |
Low density
residential area |
- |
- |
A |
¡Ì |
|
|
KTU-G01 |
Village House in Chau Tau Tsuen |
R |
2 |
Low density
residential area |
Fanling Highway |
Not Affected |
A |
¡Ì |
|
¡Ì |
KTU-G02 |
Village House in Chau Tau Tsuen |
R |
1 |
Area other than those
above (7) |
Fanling Highway |
Not Affected |
B |
¡Ì |
|
¡Ì |
Notes:
(1) R ¨C Residential; EC ¨C Elderly Centre; E ¨C Educational institutions.
(2)
Ground-borne noise is deemed not to be
affected by IF, therefore, the effect of IF should not be considered to
determine the appropriate noise criteria.
(3)
GBNSR AUT G01 to G03 are located in low density
development with industrial zone which numerous open storages/industrial uses
are located in the vicinity of the GBNSRs, therefore, type of area was
considered to be ¡°Area other than those above¡±.
(4)
GBNSR AUT G06 to G10 are located in a
medium to high-density residential area with some scattered industrial
activities (e.g. garage), therefore, type of area was considered to be ¡°Area
other than those above¡±.
(5)
According to Section 16 of LC Paper No.
CB(1)756/20-21(01) - Using Brownfield Clusters for Public Housing Development
(Second Phase Review) and Other Developments, Ngau Tam Mei Area would be
developed to provide a mix of over 6,000 public and private housing units.
Based on this information, type of area was considered to be ¡°Area other than
those above¡±.
(6)
In view of open storages/industrial uses (e.g.
Jaguar Cool Chain Co Ltd. And Wing Ming Farm) located in the vicinity of the
GBNSRs, type of area was considered to be ¡°Area other than those above¡±.
(7)
In view of open storages/industrial uses located in
the vicinity of the GBNSRs, type of area was considered to be ¡°Area other than
those above¡±.
(8)
No examination would be anticipated at kindergarten.
(9)
Considering the existing industrial
zone would be changed to other land uses for Sha Po Public Housing Development,
for conservative approach, the effect of industrial zone was not considered to
determine the appropriate noise criteria.
(10) The locations of
TBM operation are indicated in Figure No. C1603/C/NOL/ACM/M50/305.
(11) This NAP is located at more than 100m from TBM tunnels. Other
representative GBNSRs, which are located closer to the TBM Tunnel, were
considered, and thus this NAP was not selected for prediction.
Table 5.4 Representative
Planned Ground-borne Noise Sensitive Receivers during Construction and
Operational Phases
GBNSR ID |
Description |
Land Use(1) |
No. of Storey |
Type of Area |
Influencing Factor |
Degree to which GBNSR is
affected (2) |
ASR(2) |
Construction GBN Impact |
Operation GBN Impact |
|
TBM(14) |
PME |
|||||||||
KSR-PG01a |
Planned School in Park Yoho Phase
3 |
E |
-(3) |
Area other than those
above(4) |
- |
- |
B |
¡Ì |
|
¡Ì |
KSR-PG01b |
Proposed Residential Development
in Park Yoho Phase 3 |
R |
-(3) |
Area other than those
above(4) |
- |
- |
B |
¡Ì |
|
¡Ì |
KSR-PG01c |
Proposed Residential Development
Park Yoho Phase 2 |
R |
-(3) |
Area other than those
above(4) |
- |
- |
B |
¡Ì |
|
¡Ì |
KSR-PG01d |
Planned School in Park Yoho Phase
3 |
E |
-(3) |
Area other than those
above(4) |
- |
- |
B |
¡Ì |
|
¡Ì |
KSR-PG02 |
Kam Tai
Road Residential Development |
R |
-(3) |
Low density
residential area (5) |
- |
- |
A |
¡Ì |
|
¡Ì |
KSR-PG03 |
Grand Mayfair (under
Construction) |
R |
16 |
Area other than those
above(6) |
- |
- |
B |
|
|
¡Ì |
KSR-PG04 |
Future Kam Sheung Road Package 2
Property Development |
R |
-(3) |
Area other than those
above(7) |
- |
- |
B |
|
|
¡Ì |
KSR-PG05a |
Planned G/IC Site at Kam Tin
South Housing Development |
G/IC |
-(3) |
Area other than those
above(8) |
- |
- |
B |
|
|
¡Ì |
KSR-PG05b |
Planned Residential Block at Kam
Tin South Housing Development |
R |
-(3) |
Area other than those
above(8) |
- |
- |
B |
|
|
¡Ì |
KSR-PG06a |
Planned G/IC Site at Kam Tin
South Housing Development |
G/IC |
-(3) |
Area other than those
above(8) |
- |
- |
B |
|
|
¡Ì |
KSR-PG06b |
Planned School Site at Kam Tin
South Housing Development |
E |
-(3) |
Area other than those
above(8) |
- |
- |
B |
|
|
¡Ì |
KSR-PG06c |
Planned Residential Block at Kam Tin
South Housing Development |
R |
-(3) |
Area other than those
above(8) |
- |
- |
B |
|
|
¡Ì |
AUT-PG01 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
-(3) |
Area other than those
above(9) |
- |
- |
B |
¡Ì |
|
¡Ì |
AUT-PG03 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
-(3) |
Area other than those
above(9) |
- |
- |
B |
¡Ì |
|
¡Ì |
NTM-PG01 |
Potential Development at Land Use
Review Study for Ngau Tam Mei Area (NTM LUR) |
-(3) |
-(3) |
Area other than those
above(10) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01a |
Potential Housing Development in
San Tin / Lok Ma Chau Development Node (STLMC DN) |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01b |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01c |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01d |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01e |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01f |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01g |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01h |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01i |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01j |
Potential Housing Development in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG01k |
Potential Cultural &
Recreational Complex in STLMC DN |
G/IC |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG02 |
Potential Cultural &
Recreational Complex in STLMC DN |
G/IC |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG02a |
Potential GIC Facility in STLMC
DN |
G/IC |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG03a |
Potential School in STLMC DN |
E |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG03b |
Potential School in STLMC DN |
E |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG03c |
Potential GIC Facility in STLMC
DN |
G/IC |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
SAT-PG03d |
Potential FSD Staff Quarter in
STLMC DN |
R |
-(3) |
Area other than those
above(11) |
- |
- |
B |
|
|
¡Ì |
KTU-PG01 |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
¡Ì |
|
¡Ì |
KTU-PG01a |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
¡Ì |
|
¡Ì |
KTU-PG02 |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
|
|
¡Ì |
KTU-PG02a |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
|
|
¡Ì |
KTU-PG03 |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
|
|
¡Ì |
KTU-PG03a |
Planned Housing Development at
Kwu Tung North NDA |
R |
-(3) |
Area other than those
above(12) |
- |
- |
B |
|
|
¡Ì |
Notes:
(1) R ¨C Residential; EC ¨C Elderly Centre; E ¨C Educational institutions; G/IC
¨C Government, Institution or Community.
(2)
Ground-borne
noise is deemed not to be affected by IF, therefore, the effect of IF should
not be considered to determine the appropriate noise criteria.
(3) Information subject to the design of
planned development.
(4)
According to planning application
A/YL-KTN/604 and A/YL-KTN/663, Park Yoho Phase 2 and 3 will be developed to a
medium to high-density residential area, therefore, type of area was considered
to be ¡°Area other than those above¡±.
(5)
According to planning application No.
A/YL-KTN/791, the Kam Tai Road
Residential Development will be developed to residential area
with low-rise and isolated high-rise development, therefore, type of area was considered to be ¡°Low density
residential area¡±.
(6)
According to the information in Sales
Brochure of the development, Grand Mayfair I will
be developed to a medium to high-density residential area, therefore, type of area
was considered to be ¡°Area other than those above¡±.
(7)
As the areas in the vicinity of the
Future Kam Sheung Road Package 2 Property Development (i.e. Grand Mayfair and
Kam Tin South Public Housing Development) will be developed to medium to
high-density residential area, type of area
was considered to be ¡°Area other than those above¡±.
(8)
According to the building layout plans
provided by Housing Department, the Planned Kam Tin South Development (Site 1
& 6) would be developed to medium to high-density residential area,
therefore, type of area was
considered to be ¡°Area other than those above¡±. For KSR-PG06a, the proposed facilities
inside the GIC site would refer to the District Council Discussion Papers (No.
15/2023) on 25 April 2023 for Yuen Long District Council.
(https://www.districtcouncils.gov.hk/yl/doc/2020_2023/en/dc_meetings_doc/23824/dc_paper_no_2023_15.pdf)
(9)
According to the block layout provided
by Housing Department, the Proposed Public Housing Development Near Sha Po
Tsuen would be developed to medium to high-density residential area, type of area was therefore
considered to be ¡°Area other than those above¡±.
(10) According
to Section 16 of LC Paper No. CB(1)756/20-21(01) - Using Brownfield Clusters
for Public Housing Development (Second Phase Review) and Other Developments,
Ngau Tam Mei Area would be developed to provide a mix of over 6,000 public and
private housing units. Based on this information, type of area was considered to be ¡°Area other
than those above¡±.
(11)
According to Section 14 of LC Paper No.
CB(1)756/20-21(01) - Using Brownfield Clusters for Public Housing Development
(Second Phase Review) and Other Developments, the San Tin Lok Ma Chau
Development Node (STLMC DN) would be developed as a new development area
supporting an estimated housing yield of 31 000 units together with economic
and community facilities. Based on this information, type of area was considered to be ¡°Area other than
those above¡±.
(12)
Based on the information provided in
the approved NENT NDA EIA report (Register No.: AEIAR-175/2013), the area near
KTU Station will be developed to a medium to high-density residential area,
type of area was therefore considered to be ¡°Area other than those above¡±.
(13)
The identification of GBNSRs was based
on the following sources of best available information:
¡ì KSR-PG01a,
1b, 1c & 1d - Reference was
made to planning application A/YL-KTN/604 and A/YL-KTN/663, and the GBNSRs were
identified based on the Indicative Master Layout Plan shown in these planning
applications.
¡ì KSR-PG02
- According to the master layout
plan shown in the Planning application No. A/YL-KTN/791, a setback distance of
50m from the existing TML was adopted for all GBNSRs. Therefore, the identified
GBNSR was assumed to be located at 50m from the existing TML.
¡ì KSR-PG03
¨C Reference was made to the building layout provided in Sales Brochure of the
development (See Note 6).
¡ì KSR-PG04
¨C No indicative layout plan was available during the course of EIA study and
therefore the indicative location of GBNSR was set at the boundary of the
Future Kam Sheung Road Package 2 Property Development.
¡ì KSR-PG
05b & 06c - Reference was made to the tentative building layout plans
provided by Housing Department.
¡ì KSR-PG05a
& 06b ¨C No indicative layout plan was available during the course of EIA
study and therefore the indicative location of GBNSR was set at the boundary of
the G/IC site.
¡ì KSR-PG06a
- Based on the best available information provided by CLP Power Hong Kong
Limited, there will be a cable reserve zone along the southwest boundary of the
G/IC site and a planned substation to be located at southern part of the GI/C
site. The NAP was assumed at a location outside the cable reserve zone and the
planned substation.
¡ì AUT-PG01
& 03 - Reference was made to the building layout plans in Final Report (Sha
Po) of Agreement No. CE 10/2020 (CE) Site Formation and Infrastructure Works
for Proposed Public Housing Developments at Sha Po, Shap Pat Heung and Tai Kei
Leng, Yuen Long ¨C Feasibility Study, as provided by Housing Department.
¡ì SAT-PG01a
to 1k, 02, 02a, 03a to 03d - Reference was made to the Recommended Outline
Development Plan (RODP) provided by the project proponent of STLMC DN.
¡ì KTU-PG01,
01a, 02, 02a, 03 & 03a - Reference was made to the information provided by
CEDD.
(14)
The locations of TBM operation are
indicated in Figure No. C1603/C/NOL/ACM/M50/305.
¡¤
Vibration
source levels from the operation of TBM and concerned PMEs (e.g. hydraulic
breaker and rock
drill);
¡¤
Vibration
propagation through the ground to the structure foundation;
¡¤
Vibration
reduction due to the soil/structure interface;
¡¤
Vibration
propagation through the building and into occupied areas; and
¡¤
Conversion
from floor and wall vibration to noise.
Cdist: Distance
attenuation
Cdamping: Soil
damping loss across the geological media
Cbuilding: Coupling
loss into building foundation
Cfloor: Coupling
loss per floor
Cnoise: Conversion
factor from floor vibration levels to noise levels
Cmulti: Noise
level increase due to multiple sources
Ccum: Cumulative
effect due to neighbouring sites
Lp
= Lv,rms + Cdist + Cdamping + Cbuilding
+ Cfloor + Cnoise + Cmulti + Ccum
Table 5.5 Reference
Source Levels
Plant |
Reference Vibration Level, mm/s |
Remarks |
Hydraulic Breaker |
0.298
|
rms
Vibration velocity level at reference distance of 5.5m |
Rock Drill |
0.536
|
rms
Vibration velocity level at reference distance of 5.5m |
TBM |
2.5
(1) |
PPV
Vibration velocity level at reference distance of 5.5m |
Note:
(1) The vibration in-situ measurements for the TBM operation were conducted during the bored tunnelling of Kwai Tsing Tunnel under West Rail project, and the measurement data was adopted in the approved KSL EIA report (Register No.: AEIAR-083/2005) for ground-borne noise assessment. Same TBM had subsequently been used for the construction of LMCSL. In addition, the vibration measurements taken for Kwai Tsing tunnelling works were conducted at a geology which consists of mainly granite, which would be expected to generate higher vibration. As presented in Appendix 2.1, the geology along the NOL alignment comprises mainly softer material (e.g. decomposed tuff), except a section near KSR Station (chainage approx. 1+350 to 2+230) which consists of granite. As confirmed by the MTR, the TBMs to be adopted for the construction of NOL tunnels would be similar to that was used for LMCSL. As such, the vibration measurement data was therefore considered to be applicable for the purpose of assessing TBM ground-borne noise, and no adjustment to the source term would be required.
Cdist = 20 x log (R/R0), where
Table 5.6 Train Operation
Parameters Adopted in Operational Ground-borne Noise Assessment
Item |
Parameters |
|
Train Type and No.
of Car (1) |
¡¤
Electric Multiple
Unit Train, train length 200m for maximum 8-car train
operation |
|
Train Frequency/Movement
|
NOL Mainline: ¡¤
29 number per hour
per direction during peak daytime and evening time periods. ¡¤
20 number per hour
per direction during night-time period. |
|
Speed Profile |
Speed Profile of
NOL is provided in Appendix 5.8. |
Note:
(1)
The
train type, number of car and peak train frequencies were provided and
confirmed by MTRCL.
Table
5.7 Predicted
Construction Ground-borne Noise Impact from PME Operation
GBNSR ID |
Description |
Land Use(1) |
Predicted Ground-borne Noise Levels Leq(30min), dB(A) |
Daytime
Criterion, Leq(30min) dB(A) |
Compliance |
AUT-G11 |
169 Pok Wai |
R |
63 |
65 |
Yes |
NTM-G07 |
Village House near Wang Ping Shan South Road |
R |
51 |
65 |
Yes |
NTM-G08 |
Village House near Wang Ping Shan South Road |
R |
55 |
65 |
Yes |
NTM-G09 |
Village House in Long Ha |
R |
50 |
65 |
Yes |
Note:
(1) R ¨C Residential.
Table
5.8 Predicted
Construction Ground-borne Noise Impact from TBM Operation
GBNSR ID |
Description |
Land Use(1) |
Predicted
Ground-borne Noise Levels Leq(30min), dB(A) |
Daytime
Noise Criterion, Leq(30min), dB(A) |
Compliance |
Existing GBNSRs |
|||||
KSR-G01 |
No.110 Cheung Chun San Tsuen |
R |
58 |
65 |
Yes |
KSR-G02 |
Blk 77, Sam Yuen |
R |
46 |
65 |
Yes |
KSR-G03 |
Kam Tin Mung Yeung Public School |
E |
49 |
60 (55 during Exams) |
Yes |
KSR-G04 |
No.297-298 Kut Hing Wai |
R |
55 |
65 |
Yes |
KSR-G05 |
Kat Hing Garden |
R |
62 |
65 |
Yes |
AUT-G01 |
No. 173, Mo Fan Heung |
R |
59 |
65 |
Yes |
AUT-G02 |
No. 137, Mo Fan Heung |
R |
63 |
65 |
Yes |
AUT-G03 |
No. 80, Mo Fan Heung |
R |
62 |
65 |
Yes |
AUT-G06 |
Tower 2B, Park Yoho Silica |
R |
55 |
65 |
Yes |
AUT-G07 |
Tower 9B, Park Vista |
R |
56 |
65 |
Yes |
AUT-G08 |
Tower 8B, Park Yoho |
R |
55 |
65 |
Yes |
AUT-G09 |
In Keen Garden Phase 1 |
R |
50 |
65 |
Yes |
AUT-G10 |
York International Kindergarten (2) |
E |
59 |
60 |
Yes |
NTM-G01 |
The Vineyard |
R |
54 |
65 |
Yes |
NTM-G02 |
China Bible Seminary |
E |
55 |
60 (55 during Exams) |
Yes |
NTM-G03 |
House A, Greenacres Villa |
R |
58 |
65 |
Yes |
NTM-G04 |
Hongtai Home for the Aged Limited |
EC |
57 |
65 |
Yes |
NTM-G04a |
Temporary Structure near Ching
Yau Road |
R |
60 |
65 |
Yes |
NTM-G06 |
Village House near Fuk Hing Lei |
R |
58 |
65 |
Yes |
NTM-G07 |
Village House near Wang Ping Shan
South Road |
R |
60 |
65 |
Yes |
NTM-G08 |
Village House near Wang Ping Shan
South Road |
R |
48 |
65 |
Yes |
SAT-G03 |
Temporary Structure near Shek Wu
Wai |
R |
59 |
65 |
Yes |
KTU-G01 |
Village House in Chau Tau Tsuen |
R |
48 |
65 |
Yes |
KTU-G02 |
Village House in Chau Tau Tsuen |
R |
60 |
65 |
Yes |
Planned GBNSRs |
|||||
KSR-PG01a |
Planned School in Park Yoho Phase
3 |
E |
57 |
60 (55 during Exams) |
No (2 dB(A) exceedance during
Exams) |
KSR-PG01b |
Proposed Residential Development
in Park Yoho Phase 3 |
R |
56 |
65 |
Yes |
KSR-PG01c |
Proposed Residential Development
Park Yoho Phase 2 |
R |
57 |
65 |
Yes |
KSR-PG01d |
Planned School in Park Yoho Phase
3 |
E |
60 |
60 (55 during Exams) |
No (5 dB(A) exceedance during
Exams) |
KSR-PG02 |
Proposed Residential Development
at Kam Tin North |
R |
64 |
65 |
Yes |
AUT-PG01 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
59 |
65 |
Yes |
AUT-PG03 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
57 |
65 |
Yes |
KTU-PG01 |
Planned Housing Development at
Kwu Tung North NDA |
R |
46 |
65 |
Yes |
KTU-PG01a |
Planned Housing Development at
Kwu Tung North NDA |
R |
55 |
65 |
Yes |
Notes:
(1) R ¨C Residential; EC ¨C Elderly Centre; E ¨C Educational institutions.
(2) No examination period would be anticipated at kindergarten.
(3) Numbers in bold and underlined indicate exceedances of the noise
criterion.
Table
5.9 Predicted
Cumulative Construction Ground-borne Noise Impact
GBNSR ID |
Predicted
Ground-borne Noise Levels Leq(30min),
dB(A) |
Total |
Daytime
Criterion, Leq(30min) dB(A) |
Compliance |
|
TBM |
PME |
||||
NTM- G07 |
60 |
51 |
60 |
65 |
Yes |
NTM-G08 |
48 |
55 |
56 |
65 |
Yes |
Table
5.10 Predicted Ground-borne
Railway Noise Impact under Base Case Scenario
GBNSR ID |
Description |
Land Use(1) |
ASR |
Predicted Ground-borne Railway Noise Levels, Leq(30min, dB(A) |
Criteria,
Leq(30min), dB(A) |
Compliance (Yes/No) |
|||
Day/Evening (0700-2300
hrs) |
Night (2300-0700 hrs) |
Day/Evening (0700-2300
hrs) |
Night (2300-0700 hrs) |
Day/Evening (0700-2300
hrs) |
Night (2300-0700 hrs) |
||||
Existing GBNSRs |
|||||||||
KSR-G01 |
No.110 Cheung Chun San Tsuen |
R |
A |
22 |
20 |
50 |
40 |
Yes |
Yes |
KSR-G02 |
Blk 77, Sam Yuen |
R |
A |
<20 |
<20 |
50 |
40 |
Yes |
Yes |
KSR-G03 |
Kam Tin Mung Yeung Public School |
E |
A |
20 |
- (3) |
50 |
- (3) |
Yes |
- (3) |
KSR-G04 |
No.297-298 Kut Hing Wai |
R |
A |
22 |
21 |
50 |
40 |
Yes |
Yes |
KSR-G05 |
Kat Hing Garden |
R |
A |
24 |
23 |
50 |
40 |
Yes |
Yes |
AUT-G01 |
No. 173, Mo Fan Heung |
R |
B |
26 |
24 |
55 |
45 |
Yes |
Yes |
AUT-G02 |
No. 137, Mo Fan Heung |
R |
B |
29 |
27 |
55 |
45 |
Yes |
Yes |
AUT-G03 |
No. 80, Mo Fan Heung |
R |
B |
26 |
24 |
55 |
45 |
Yes |
Yes |
AUT-G06 |
Tower 2B, Park Yoho Silica |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
AUT-G07 |
Tower 9B, Park Vista |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
AUT-G08 |
Tower 8B, Park Yoho |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
AUT-G09 |
In Keen Garden Phase 1 |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
AUT-G10 |
York International Kindergarten (2) |
E |
B |
23 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
NTM-G01 |
The Vineyard |
R |
A |
<20 |
<20 |
50 |
40 |
Yes |
Yes |
NTM-G02 |
China Bible Seminary |
E |
A |
<20 |
- (3) |
50 |
- (3) |
Yes |
- (3) |
NTM-G03 |
House A, Greenacres Villa |
R |
A |
<20 |
<20 |
50 |
40 |
Yes |
Yes |
NTM-G04 |
Hongtai Home for the Aged Limited |
EC |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
NTM-G04a |
Temporary Structure near Ching
Yau Road |
R |
B |
24 |
22 |
55 |
45 |
Yes |
Yes |
NTM-G06 |
Village House near Fuk Hing Lei |
R |
A |
21 |
<20 |
50 |
40 |
Yes |
Yes |
NTM-G07 |
Village House near Wang Ping Shan
South Road |
R |
B |
20 |
<20 |
55 |
45 |
Yes |
Yes |
NTM-G08 |
Village House near Wang Ping Shan
South Road |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KTU-G01 |
Village House in Chau Tau Tsuen |
R |
A |
<20 |
<20 |
50 |
40 |
Yes |
Yes |
KTU-G02 |
Village House in Chau Tau Tsuen |
R |
B |
27 |
25 |
55 |
45 |
Yes |
Yes |
Planned GBNSRs |
|||||||||
KSR-PG01a |
Planned School in Park Yoho Phase
3 |
E |
B |
<20 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
KSR-PG01b |
Proposed Residential Development
in Park Yoho Phase 3 |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KSR-PG01c |
Proposed Residential Development
Park Yoho Phase 2 |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KSR-PG01d |
Planned School in Park Yoho Phase
3 |
E |
B |
25 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
KSR-PG02 |
Kam Tai
Road Residential Development |
R |
A |
34 |
33 |
50 |
40 |
Yes |
Yes |
KSR-PG03 |
Grand Mayfair (under
Construction) |
R |
B |
25 |
24 |
55 |
45 |
Yes |
Yes |
KSR-PG04 |
Future Kam Sheung Road Package 2
Property Development |
R |
B |
35 |
33 |
55 |
45 |
Yes |
Yes |
KSR-PG05a |
Planned G/IC Site at Kam Tin
South Housing Development |
G/IC |
B |
32 |
30 |
55 |
45 |
Yes |
Yes |
KSR-PG05b |
Planned Residential Block at Kam
Tin South Housing |
R |
B |
25 |
23 |
55 |
45 |
Yes |
Yes |
KSR-PG06a |
Planned G/IC Site at Kam Tin
South Housing Development |
G/IC |
B |
28 |
26 |
55 |
45 |
Yes |
Yes |
KSR-PG06b |
Planned School Site at Kam Tin
South Housing Development |
E |
B |
47 |
-
(3) |
55 |
- (3) |
Yes |
- (3) |
KSR-PG06c |
Planned Residential Block at Kam
Tin South Housing Development |
R |
B |
32 |
30 |
55 |
45 |
Yes |
Yes |
AUT-PG01 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
B |
20 |
<20 |
55 |
45 |
Yes |
Yes |
AUT-PG03 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
NTM-PG01 |
Potential Development at Land Use Review
Study for Ngau Tam Mei Area |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
SAT-PG01a |
Potential Housing Development in
San Tin / Lok Ma Chau Development Node (STLMC DN) |
R |
B |
25 |
23 |
55 |
45 |
Yes |
Yes |
SAT-PG01b |
Potential Housing Development in
STLMC DN Node |
R |
B |
20 |
<20 |
55 |
45 |
Yes |
Yes |
SAT-PG01c |
Potential Housing Development in
STLMC DN |
R |
B |
27 |
25 |
55 |
45 |
Yes |
Yes |
SAT-PG01d |
Potential Housing Development in
STLMC DN |
R |
B |
35 |
33 |
55 |
45 |
Yes |
Yes |
SAT-PG01e |
Potential Housing Development in
STLMC DN |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
SAT-PG01f |
Potential Housing Development in
STLMC DN |
R |
B |
24 |
22 |
55 |
45 |
Yes |
Yes |
SAT-PG01g |
Potential Housing Development in
STLMC DN |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
SAT-PG01h |
Potential Housing Development in
STLMC DN |
R |
B |
28 |
26 |
55 |
45 |
Yes |
Yes |
SAT-PG01i |
Potential Housing Development in
STLMC DN |
R |
B |
25 |
23 |
55 |
45 |
Yes |
Yes |
SAT-PG01j |
Potential Housing Development in
STLMC DN |
R |
B |
30 |
28 |
55 |
45 |
Yes |
Yes |
SAT-PG01k |
Potential Cultural &
Recreational Complex in STLMC DN |
G/IC |
B |
<20 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
SAT-PG02 |
Potential Cultural &
Recreational Complex in STLMC DN |
G/IC |
B |
<20 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
SAT-PG02a |
Potential GIC Facility in STLMC
DN |
G/IC |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
SAT-PG03a |
Potential School in STLMC DN |
E |
B |
<20 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
SAT-PG03b |
Potential School in STLMC DN |
E |
B |
<20 |
- (3) |
55 |
- (3) |
Yes |
- (3) |
SAT-PG03c |
Potential GIC Facility in STLMC
DN |
G/IC |
B |
25 |
23 |
55 |
45 |
Yes |
Yes |
SAT-PG03d |
Potential FSD Staff Quarter in
STLMC DN |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KTU-PG01 |
Planned Housing Development at
Kwu Tung North |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KTU-PG01a |
Planned Housing Development at
Kwu Tung North |
R |
B |
22 |
20 |
55 |
45 |
Yes |
Yes |
KTU-PG02 |
Planned Housing Development at
Kwu Tung North |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KTU-PG02a |
Planned Housing Development at
Kwu Tung North |
R |
B |
24 |
23 |
55 |
45 |
Yes |
Yes |
KTU-PG03 |
Planned Housing Development at
Kwu Tung North |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
KTU-PG03a |
Planned Housing Development at
Kwu Tung North |
R |
B |
<20 |
<20 |
55 |
45 |
Yes |
Yes |
Notes:
(1)
R ¨C Residential; EC ¨C Elderly
Centre; E ¨C Educational institutions; G/IC ¨C Government, Institution or
Community.
(2)
Information
subject to the design of planned development.
(3)
No sensitive use is anticipated during night-time
period.
Table
5.11 Cumulative Ground-borne
Railway Noise Impact
GBNSR ID |
Predicted Ground-borne
Noise Levels Leq(30min),
dB(A) |
Cumulative GBN Levels, dB(A) |
Nose
Criterion, Leq(30min) dB(A) |
Compliance |
|
NOL |
Existing Railway |
||||
Daytime and Evening Period (0700-2300 hours) |
|||||
NTM-
G02 |
<20 |
<30
(1) |
<30
(2) |
50 |
Yes |
NTM-
G03 |
<20 |
<30
(1) |
<30
(2) |
50 |
Yes |
NTM-
PG01 |
<20 |
<30
(1) |
<30
(2) |
55 |
Yes |
KTU-G01 |
<20 |
(3) |
At least 10dB(A) below noise criterion (2) |
50 |
Yes |
KTU-G02 |
27 |
55 |
Yes |
||
KTU-PG01 |
<20 |
55 |
Yes |
||
KTU-PG01a |
22 |
55 |
Yes |
||
KTU-PG02 |
<20 |
55 |
Yes |
||
KTU-PG02a |
24 |
55 |
Yes |
||
KTU-PG03 |
<20 |
55 |
Yes |
||
KTU-PG03a |
<20 |
55 |
Yes |
||
Night-time
Period (2300-0700 hours) |
|||||
NTM-
G02 |
- (4) |
- (4) |
- (4) |
- (4) |
- (4) |
NTM-
G03 |
<20 |
<20(1) |
<23
(2) |
40 |
Yes |
NTM-
PG01 |
<20 |
<20(1) |
<23
(2) |
45 |
Yes |
KTU-G01 |
<20 |
(3) |
At least 10dB(A) below noise criterion (2) |
40 |
Yes |
KTU-G02 |
25 |
45 |
Yes |
||
KTU-PG01 |
<20 |
45 |
Yes |
||
KTU-PG01a |
20 |
45 |
Yes |
||
KTU-PG02 |
<20 |
45 |
Yes |
||
KTU-PG02a |
23 |
45 |
Yes |
||
KTU-PG03 |
<20 |
45 |
Yes |
||
KTU-PG03a |
<20 |
45 |
Yes |
Notes:
(1) According to Table
6.15 of the approved EIA report for XRL, the unmitigated GBN railway impacts at
Ngau Tam Mei area (e.g. GBNSR No. GN36, 37, 37a (See Table 6.15 of approved EIA
report for XRL)) were predicted less than 21 dB(A) and 16 dB(A) during day/evening
and night-time respectively.
(2) As the predicted railway ground-borne noise impact arising from the Project is at least 10 dB(A)
below ANL, no adverse cumulative GBN impact is anticipated.
(3) No quantitative
ground-borne noise assessment was performed in the approved EIA report of LMCSL.
Nevertheless, as the predicted railway ground-borne
noise impact arising from
the Project is at least 10 dB(A) below ANL, no adverse cumulative GBN impact is
anticipated.
(4)
No sensitive use is anticipated during night-time
period.
[2] Type 1a: A medium attenuation baseplate or booted
dual sleepers based on a bonded or non-bonded compression style baseplate with
a resilient elastomeric element having static stiffness of about 25 kN/mm, to
be fitted atop the concrete sleepers or atop the invert.