13.1.1.1
This section presents the analysis and findings of the
Hazard to Life Assessment undertaken for the Project in accordance with Section 3.4.14 of the EIA Study Brief
(ESB-340/2021).
13.1.1.2
According to Section 3.4.14 and Appendix M of
the EIA Study Brief, a hazard to life assessment shall be conducted to evaluate
the risks associated with (i) manufacture, storage, use and on-site transport
of chlorine at Ngau Tam Mei Water Treatment Works (NTM WTW); (ii) use,
transport and overnight storage of explosives; (iii) generation, storage, use
and on-site transport of biogas at the proposed sewage treatment works.
13.1.1.3
According to the latest study findings, the
development of rock cavern is not recommended under the STLMC DN Project. Since
the potential underground rock cavern will no longer be proposed for the
development under the STLMC DN Project, the Project site will be located
outside the 1km radius consultation zone (CZ) of NTM WTW. As such, hazard
assessments for explosives and NTM WTW are not required.
13.1.1.4
In addition to the hazardous facilities
mentioned in the EIA Study Brief, a high pressure underground town gas
transmission pipeline (HP Gas Pipeline) running along San Tin Highway located
in close vicinity to the proposed development site is identified, and a hazard
assessment to address the risk associated with the HP Gas Pipeline was
conducted.
13.1.1.5
Two Green Fuel Stations (GFSs) are also proposed
within the Project site, and they are proposed to provide LPG filling services for
the purpose of this EIA Study. A hazard assessment to address the risk
associated with LPG operation of the two proposed GFSs was also carried out.
13.1.1.6
Plate 13‑1 shows the locations of
hazardous facilities that were assessed in this section, with respect to the
Project site.
Plate 13‑1 Locations of the Hazardous Facilities
13.1.1.7
Details of the Quantitative Risk Assessment
(QRA) for the Project are presented in the following appendices:
(a)
Appendix 13.1: Hazard to Life
Assessment in association with the proposed Effluent Polishing Plant (EPP);
(b)
Appendix 13.2: Hazard to
Life Assessment in association with the HP Gas Pipeline; and
(c)
Appendix 13.3: Hazard to
Life Assessment in associated with the proposed GFSs.
13.2.1.1
The requirements and criteria for assessing hazard to life are outlined
in Section 3.4.14 of the EIA Study Brief (ESB-340/2021) and Annex 4 of the
Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM),
respectively. The estimated risk levels due to operations of biogas-related facilities,
the HP Gas Pipeline and the GFSs were compared with the individual and societal
risk criteria set out in the Hong Kong Risk Guidelines (HKRG) to determine the
acceptability of the risk levels.
13.2.2
Hong Kong Risk Guidelines (HKRG), EIAO-TM
Annex 4
13.2.2.1
Individual risk is the predicted increase in the chance of fatality per
year to an individual due to a potential hazard. The individual risk guidelines
require that the maximum level of individual risk should not exceed 1 in
100,000 per year i.e. 1×10-5 per year.
13.2.2.2
Societal risk refers to the risks to the whole population. It is
expressed graphically by plotting the cumulative frequency (F) of N or more
deaths in the population from incidents at a certain installation against the
number of fatalities (N) (Plate 13-2 refers). Two F-N risk lines are
used in the HKRG to denote “Acceptable” or “Unacceptable” societal risks. To
avoid major disasters, there is a vertical cut-off line at the 1,000 fatality
level extending down to a frequency of 1 in a billion (1x10-9) per
year. The intermediate region indicates that the acceptability of societal risk
is borderline and that it should be reduced to a level which is “as low as
reasonably practicable” (ALARP). It seeks to ensure that all practicable and
cost-effective measures that can reduce risk are considered.
Plate 13‑2 Societal Risk Guidelines
13.3.1.1
The main objective of this QRA is to assess the hazard to life of the
general public from the hazards that arise from the proposed EPP and GFSs, and
the existing HP Gas Pipeline that are required to facilitate the construction
and operation of the Project. The results of the QRA should then be compared
with the HKRG.
13.3.1.2
The detailed requirements of the study are given in Section 3.4.14 of
the EIA Study Brief. The main requirements are:
(a) Identify
hazardous scenarios associated with the operation of the proposed EPP and GFSs
and the existing HP Gas Pipeline, and subsequently determine a set of relevant
scenarios to be included in a QRA;
(b)
Execute
a QRA of the set of hazardous scenarios determined in sub-section (a) above,
expressing population risks in both individual and societal terms;
(c)
Compare
individual and societal risks with the criteria for evaluating hazard to life
stipulated in Annex 4 of the EIAO-TM; and
(d)
Identify
and assess practicable and cost-effective risk mitigation measures.
13.3.1.3
This assessment consisted of the following six main tasks:
(a) Data
Collection:
Collect relevant data / information including the operational details of the
hazardous facilities, population, road traffic and weather data;
(b) Hazard
Identification: Identify a set of hazardous scenarios associated with the
hazardous sources, project specific hazards due to the blasting operation,
dangerous goods storage and handling in the hazardous facilities will be
reviewed and considered in the assessment;
(c) Frequency
Analysis:
Estimate the frequencies of the identified hazardous scenarios by using Fault
Tree and Event Tree Analyses;
(d) Consequence
Analysis:
Evaluate the potential hazard zones for each risk outcomes by using the
well-established and widely accepted model, e.g. SAFETI;
(e) Risk
Evaluation:
Evaluate the risks associated with the identified hazardous scenarios.
The evaluated risks will be compared with the above-mentioned risk criteria to
determine their acceptability. The estimation of fatality will be
reviewed with consideration of site-specific conditions and properties of the
hazardous materials in consideration.
(f) Mitigation
Measures:
Where necessary, risk mitigation measures will be identified and assessed to
comply with the “as low as reasonably practicable (ALARP) principle used in the
above-mentioned risk criteria. Possible mitigation measures would include but
not limited to staging of construction activities to manage the population
increase during construction phase, provision of additional safety measures for
the identified hazardous facilities to lower the failure probabilities, etc.
13.3.1.4
This hazard assessment covered the following two scenarios:
·
Year
2032 (Construction phase) – The risk imposed by the operation of the biogas
facilities in the proposed EPP and two GFS, and the HP Gas Pipeline to the
existing, committed and planned population in 2032. This scenario accounted
for the commencement of the EPP and the two GFSs, and also the presence of the
construction workers for areas of the proposed development located along the
San Tam Road.
·
Year
2039 (Operation phase) – The risk imposed by the operation of the biogas
facilities in the proposed EPP and two GFSs, and the HP Gas Pipeline to the
existing, committed and planned population in 2039. This scenario accounted
for the ultimate situation with all the planned land users of the proposed
development being considered.
13.4.1.1
The land/ building population as well as road population were estimated
based on the information collected from the following sources:
(a)
Desktop
study and site survey;
(b)
2030+
TPEDM data;
(c)
Latest
Annual Traffic Census (ATC) from Transport Department;
(d)
Traffic
Impact Assessment (TIA) report of this Assignment; and
(e)
Previous
reports of similar studies.
13.4.1.2
The population data adopted in the hazard assessments are detailed in Appendices 13.1 to 13.3.
13.5.1.1
The hazards associated with the hazardous installations
were identified by reviewing the past incidents (e.g. Major Hazard Incident
Data Services (MHIDAS)), existing conditions of the hazardous installations and
previous studies. The hazard scenarios include the loss of containment from
the proposed EPP leading to fire and explosion, loss of
containment from the HP Gas Pipeline leading to gas
leak, fire, explosion and toxic release, and loss of containment from the
proposed GFSs leading to fire and explosion, as detailed in Appendices 13.1 to 13.3 respectively.
13.6.1.2
Appendices 13.1 to 13.3 provide the details of the
frequency assessment in each hazard assessment.
13.7.1.1
The consequence assessment estimates the impact of each
outcome in the area of concern. It includes discharge rate modelling,
dispersion modelling and fire and explosion modelling. The details of the
consequence assessment are presented in Appendices 13.1 to 13.3.
13.8.1
Introduction
13.8.1.1
By combining the results of frequency estimation and
consequence analysis, risk levels of the assessment scenarios were
characterised in terms of individual risk (presented in individual risk
contours plot) and societal risk (presented in FN curves and Potential Loss of
Life).
13.8.2
Individual Risk
13.8.2.1
The predicted individual risk contours for the proposed
EPP are detailed in Appendix 13.1, while the predicted individual risk contours for the HP Gas
Pipeline are detailed in Appendix 13.2 and the predicted individual risk contours for the two proposed GFSs
are detailed in Appendix 13.3. The associated risk levels were based on 100% occupancy with no
allowance made for shelter or escape, as specified in the user manual of Phast
Risk.
13.8.2.2
Based on the operation details assumed for the proposed
EPP, GFSs and the HP Gas Pipeline, the maximum off-site individual risks
associated with their operations are less than 1×10-5 per year. The
individual risk of 1×10-5 per year contour was observed due to
operation of the proposed EPP but the contour would be confined entirely within
the boundary of EPP. Given that there is no off-site risk with frequency
greater than 1×10-5 per year, no off-site individual would be
exposed to risk level greater than 1×10-5 per year. The level of
individual risk associated with the operation of the proposed EPP, GFSs and the
HP Gas Pipeline, as well as the individual risk imposed on the Project is
considered acceptable and in compliance with the HKRG.
13.8.3
Societal Risk
13.8.3.1
The societal risks of the proposed EPP, the HP Gas
Pipeline and the two GFSs during both construction and operation phases of the
Project, are presented in Appendices 13.1 to 13.3 respectively. As shown in the FN plots, the societal
risks for these facilities fall within the “Acceptable” region in both
assessment years. The total Potential Loss of Life (PLL) associated with
operation of the proposed EPP was found to be 3.09×10-6 per year and
3.57×10-6 per year for construction and operation phases; the total
PLL associated with operation of the HP Gas Pipeline was found to be 5.57×10-6
per year and 1.22×10-5 per year for construction and operation
phases; while the total PLL
associated with operation of the two proposed GFSs was found to be 3.83×10-6
to 5.16×10-6 per year and 3.89×10-6
to 5.62×10-6 per year for construction and
operation phases.
13.9.1.1
Apart from the proposed EPP and two
GFSs, no other concurrent, planned or committed projects leading to any other
hazardous events have been identified at the present stage, it is then
reasonable to conclude there will be no potential cumulative impacts expected
to arise due to other projects during the Project cycle.
13.9.1.2
This section addresses cumulative
impacts of the Project related to the proposed EPP and two GFSs, with the
existing HP underground town gas transmission pipelines. These are presented as
combined Individual Risk Contours and F-N curve following the same approach as
the approved EIAs for the Sha Tin Cavern project
and the In-situ Reprovisioning of Sha Tin Water Treatment Works project.
13.9.1.3
The Individual Risk contours presented
in Plate 13‑3 show
that cumulative risks are generally lower than 10-5 per year for
off-site areas of the proposed hazardous facilities. The F-N curves for the
construction and operation phases of the Project are shown in Plate
13‑4 and Plate
13‑5 respectively. The cumulative societal
risks from these facilities fall within the “Acceptable” region in both
assessment years.
Plate 13‑3 Cumulative Individual Risk Contours
Plate 13‑4 FN Curves of Cumulative Risks (Year 2032)
Plate 13‑5 FN Curves of Cumulative Risks (Year 2039)
13.10.1.1
Hazard assessments were conducted to assess the
risks associated with operation of the proposed EPP, the HP Gas Pipeline, and
the proposed GFSs during the construction and operation phases of the Project.
The results showed that both the individual risks and societal risks, taking
into account the population induced by the Project, would be in compliance with
the risk criteria stipulated in Annex 4 of the TM-EIAO, risk mitigation
measures are therefore not required.