Table of Content
17 Implementation Schedule of Recommended Mitigation Measures
17.1 Implementation
Schedule of Recommended Mitigation Measures
Table
17.1 Implementation Schedule of Recommended Mitigation
Measures
Table 17.1 Implementation Schedule of Recommended Mitigation Measures
Relevance to Designated Project (DP) |
Environmental Protection Measures |
Location / Duration of Measures /
Timing of Completion of Measures |
Implementation Agent |
Implementation Stage* |
Relevant Legislation & Guidelines |
|||
Des |
C |
O |
||||||
Air Quality Impact |
||||||||
Construction Phase |
||||||||
3.8.1.1 |
All
DPs and Non-DPs |
Dust suppression
measures stipulated in Air Pollution Control (Construction Dust) Regulation
and good site practices listed below should be carried out to further
minimize construction dust impact.
Use
of regular watering to reduce dust emissions from exposed site surfaces and
unpaved roads, particularly during dry weather.
Use
of frequent watering for particularly dusty construction areas and areas
close to ASRs.
Side
enclosure and covering of any aggregate or dusty material storage piles to
reduce emissions. Where this is not
practicable owing to frequent usage, watering shall be applied to aggregate
fines.
For
the work sites close to the ASRs with a separation distance less than 10 m,
provide hoardings of not less than 3 m high from ground level along the site
boundary; for the other work sites in general, provide hoarding not less than
2.4m high from ground level along site boundary except for site entrance or
exit.
Avoid
position of material stockpiling areas, major haul roads and dusty works
within the construction site close to concerned ASRs.
Avoid
unnecessary exposed earth.
Locate
all the dusty activities away from any nearby ASRs as far as practicable.
Open
stockpiles shall be avoided or covered.
Where possible, prevent placing dusty material storage piles near
ASRs.
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations.
Establishment
and use of vehicle wheel and body washing facilities at the exit points of
the site.
Where
possible, routing of vehicles and positioning of construction plant should be
at the maximum possible distance from ASRs.
Imposition
of speed controls for vehicles on site haul roads.
Instigation
of an environmental monitoring and auditing program to monitor the
construction process in order to enforce controls
and modify method of work if dusty conditions arise. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
Air Pollution
Control Ordinance (APCO) Air Quality
Objectives (AQO) Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM) |
3.8.1.2 |
All
DPs and Non-DPs |
Guidelines
stipulated in EPDs Recommended Pollution Control Clauses for Construction
Contracts should be incorporated in the contract document to abate dust
impacts. These clauses include:
The
Contractor shall observe and comply with APCO and its subsidiary regulation, particularly
the Air Pollution Control (Construction Dust) Regulation.
The
Contractor shall undertake at all times to prevent
dust nuisance as a result of the construction activities.
The
Contractor shall ensure that there will be adequate water supply /storage for
dust suppression.
The
Contractor shall devise and arrange methods of working and carrying out the
works in such a manner so as to minimize dust impact on the surrounding environment, and shall provide experienced personnel with
suitable training to ensure that these methods are implemented properly.
Before
the commencement of any work, the Contractor may be required to submit the
methods of working, plant, equipment and air
pollution control system to be used on the site for the Engineer inspection
and approval. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
APCO Air Pollution
Control (Construction Dust) Regulation AQO EIAO-TM |
3.8.1.3 |
All
DPs and Non-DPs |
In order to help
reduce carbon emission and pollution, timely application of temporary
electricity and water supply would be made and
electric vehicles would be adopted in accordance with DEVB TC(W) No. 13/2020
Timely Application of Temporary Electricity and Water Supply for Public
Works Contracts and Wider Use of Electric Vehicles in Public Works Contracts
in the Project. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
DEVB TC(W) No.
13/2020 |
3.8.1.4 |
All
DPs and Non-DPs |
To
minimise the exhaust emission from non-road mobile machinery (NRMMs) during
the construction phase, the following measures should be applied as far as
practicable:
Connect
construction plant and equipment to main electricity supply and avoid use of
diesel generators and diesel-powered equipment;
Avoid
exempted NRMMs as far as practicable; and
Deploy
electrified NRMMS as far as practicable. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
Air
Pollution Control (Non-road Mobile Machinery)
(Emission) Regulation |
Operation Phase |
||||||||
3.5.3.1 |
DP2 |
The generated biogas
will undergo treatment in sulphur absorption vessels to remove H2S
by the filter before passing to the CHP generator,.
In addition, the Anammox process will also be adopted for sewage treatment so as to convert ammonia (NH3) in the sewage to
nitrogen gas to reduce the overall NH3 emission from the plant. |
EPP
/ Operation
Phase |
DSD |
√ |
|
√ |
EIAO-TM |
3.7.3.2
& 3.7.3.3 |
Non-DP |
Design of central
air-conditionings for the buildings at Site G.5.8, G.5.9, G.5.19, G.5.10,
G.5.11, G.5.12 and OU(I&T)3.1.8 and the fresh air intake of these
buildings being positioned 20mAG or above. |
Site
G.5.8, G.5.9, G.5.19, G.5.10, G.5.11, G.5.12 and OU(I&T)3.1.8 / Operation
Phase |
Site
Developers / Operators |
√ |
|
√ |
EIAO-TM |
3.8.3.2 |
DP2 |
Proposed Effluent
Polishing Plant (EPP) to be equipped with 2-stage deodourisation
system with overall 95% odour removal efficiencies |
EPP
/ Operation
Phase |
DSD |
√ |
|
√ |
EIAO-TM |
3.8.3.2 |
Non-DP |
Proposed Food Waste
Pre-Treatment Facilities (FWPF) to be equipped with activated carbon filter |
FWPF
/ Operation
Phase |
EPD |
√ |
|
√ |
EIAO-TM |
3.8.3.2 |
Non-DP |
The three proposed
SPSs to be equipped with odour removal system with odour removal efficiency
of at least 95% |
Three
proposed SPSs / Operation
Phase |
DSD |
√ |
|
√ |
EIAO-TM |
Noise
Impact |
||||||||
Construction Phase |
||||||||
4.8.1.1
4.8.1.2 |
All
DPs and Non-DPs |
Adopting Quality
Powered Mechanical Equipment (QPME) is recommended. The use of QPME
associated with the construction works is prescribed in EPDs QPME database,
which contains the sound power levels (SWLs) for quality/quiet
PME of various types, brands and models. |
Construction
sites |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.3 |
All
DPs and Non-DPs |
Movable noise
barriers have been proposed for excavator, mobile crane, loader, backhoe,
dump truck, dump truck with grab, piling (large diameter bored, RCD), piling
(large diameter bored, oscillator), crawler crane (mobile, diesel), roller
(vibratory), paint line marker, cherry picker, crane lorry, crane, welding
set, lorry, breaker (hand-held, mass >10kg and <20kg), poker
(vibratory, hand-held), concrete lorry mixer, concrete mixer, bar bender and
cutter (electric), saw (circular, wood), water pump (submersible, electric),
breaker (hand-held, mass <= 10kg), piling (vibrating hammer), chisel,
drill rig (rotary type (diesel)), asphalt paver, cutter (circular, steel),
drilling rig, etc. Movable temporary noise barriers that can be located close
to noisy plant and be moved iteratively with the plant along a worksite can
be very effective for screening noise from noise sensitive receivers
(NSRs). A cantilevered top cover would
be required to achieve screening benefits at upper floors of noise sensitive
receivers (NSRs). |
Construction
sites |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.4 |
All
DPs and Non-DPs |
Use of full enclosure for generator (silenced), Generator for HAC, and
generator for DCM. |
Construction
sites |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.5 |
All
DPs and Non-DPs |
Use of non-percussive equipment and method, such as silent piling by
Press-in Method, to carry out sheet piling works |
Construction
sites |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.6 |
All
DPs and Non-DPs |
Use of non-percussive equipment and method, such as hydraulic crusher,
chemical expansion agent, quieter type blade saw and bursting system to carry
out demolition/concrete breaking/removal activities as far as practicable |
Construction
sites |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.7 |
All
DPs and Non-DPs |
For Ground Treatment High Arsenic Containing Soil, the construction
equipment i.e. roller and excavator should not be used simultaneously with
backhoe and bulldozer. |
Construction
sites of A.2.1-1-1, A.2.1-2-1 and A.5.3-0-1 |
Contractor |
|
√ |
|
EIAO-TM |
4.8.1.11 |
All
DPs and Non-DPs |
Construction Noise Management Plan would be prepared before tender
stage and before commencement of construction works to verify the inventory
of noise sources, and to assess the effectiveness and practicality of all
identified measures for mitigating the construction noise impact of the
project. |
Construction
sites |
CEDD/
Contractor |
|
√ |
|
EIAO-TM |
Operation Phase |
||||||||
4.8.2.2 |
DP1
and Non-DPs |
Provide low noise
road surfacing on the Project Road |
Roads D1, D2, D4,
D5, P1, L1,
L3, L4, L5, L6, L7, L8, L9, L10, L13, L14, L19& L20 Prior to road
opening. |
CEDD (construction
phase) /HyD (operation phase) |
√ |
√ |
√ |
EIAO-TM |
4.8.2.2
|
Non-DPs |
Provide acoustics
windows / balcony at private / public housing site |
RSc.2.1,
RSc.2.2, RSc.3.2, R.1.2.1, R.1.2.2,
R.1.2.3.2, R.1.3.2, OU(MU)1.2.1, OU(MU)2.1.1, G.3.1 Prior to population
intake of the residential sites. |
Housing Department/ Private Developers |
√ |
√ |
√ |
EIAO-TM |
4.8.2.4 |
Non-DPs |
A traffic noise
management plan, which to review and confirm the direct mitigation measure
(i.e., Noise barrier) for the operation phase traffic noise impacts arising
from the Project, would be prepared for EPDs approval before road opening. |
Design and Operation
Phases |
CEDD |
√ |
√ |
√ |
EIAO-TM |
4.8.2.5 |
Non-DPs |
Noise Impact
Assessment for the planned private residential developments shall be
conducted by private developers and Environmental Assessment Study (EAS) for
the planned public housings shall be conducted by Housing Department in the
detailed design stage to comply with relevant noise criteria stipulated in
EIAO-TM and HKPSG. |
Design and Operation
Phases |
Housing Department/ Private Developers |
√ |
√ |
√ |
EIAO-TM Ch.9 of the HKPSG |
4.8.2.2 |
Non-DPs |
Provide vertical
noise barrier and cantilevered noise barrier |
Roads L6, L7, L8, L9, L13, L14, San
Tin Highway and near the existing San Tin Tsuen Road Prior to road
opening for existing NSRs or population intake of planned NSRs |
CEDD |
√ |
√ |
√ |
EIAO-TM Guidelines
on Design of Noise Barriers |
4.7.2.7
and 4.7.2.9 |
Non-DPs
|
All maximum
allowable Sound Power Levels presented in this EIA Report should be included
in the tender specification. The relevant government department/future
operator shall also take into account the latest
available information at the time of detailed design to review and update the
maximum allowable SWL as appropriate. |
Design and Operation
Phases |
Relevant government
departments/ future operators |
√ |
√ |
√ |
EIAO-TM NCO |
4.7.2.9 |
Non-DPs |
Noise commissioning
test for fixed noise sources will be carried out by relevant government departments/
future operators before operation of fixed noise sources and incorporate the
requirement in the implementation schedule. |
Design and Operation
Phases |
Relevant government
departments/ future operators |
√ |
√ |
√ |
EIAO-TM NCO Technical Memorandum on Noise from Places other than Domestic
Premises, Public Places or Construction Sites (IND-TM) |
Water
Quality Impact |
||||||||
Construction Phase |
||||||||
5.7.1.3 |
All
DPs and Non-DPs |
Surface run-off from
construction site should be discharged into storm drains via adequately
designed sand / silt removal facilities such as sand traps, silt traps and
sedimentation basins. Channels, earth
bunds or sand bag barriers should be provided on
site to properly direct stormwater to such silt removal facilities. Perimeter channels at site boundaries
should be provided as necessary to intercept storm run-off from outside the site
so that it will not wash across the site.
Catchpits and perimeter channels should be constructed in advance of
site formation works and earthworks. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
Water Pollution
Control Ordinance (WPCO) EIAO-TM Professional Persons
Environmental Consultative Committee Practice Notes (ProPECC
PN) 2/23 |
5.7.1.4 |
All
DPs and Non-DPs |
Silt removal facilities,
channels and manholes should be maintained and the
deposited silt and grit should be removed regularly (as well as at the onset
of and after each rainstorm) to prevent overflows and localised
flooding. Before disposal at the
public fill reception facilities, the deposited silt and grit should be
solicited in such a way that it can be contained and delivered by dump truck
instead of tanker truck. Any practical
options for the diversion and realignment of drainage should comply with both
engineering and environmental requirements in order to
provide adequate hydraulic capacity of all drains. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.5 |
All
DPs and Non-DPs |
Construction works
should be programmed to minimise soil excavation in the wet season (i.e.
April to September). If soil
excavation cannot be avoided in these months or at any time of year when
rainstorms are likely, temporarily exposed slope surfaces should be covered
e.g. by tarpaulin, and temporary access roads should be protected by crushed
stone or gravel, as excavation proceeds.
Intercepting channels should be provided (e.g. along the crest / edge
of excavation) to prevent storm run-off from washing across exposed soil
surfaces. Arrangements should always
be in place in such a way that adequate surface protection measures can be
safely carried out well before the arrival of rainstorm. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.6 |
All
DPs and Non-DPs |
Earthworks final
surfaces should be well compacted and the subsequent
permanent work or surface protection should be carried out immediately after
the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting
channels should be provided where necessary. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.7 |
All
DPs and Non-DPs |
Measures should be
taken to minimise the ingress of rainwater into trenches. If excavation of trenches in the wet season
is necessary, they should be dug and backfilled in short sections. Rainwater pumped out from trenches or
foundation excavations should be discharged into storm drains via silt
removal facilities. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.8 |
All
DPs and Non-DPs |
Open stockpiles of
construction materials (e.g. aggregates, sand and
fill material) on sites should be covered with tarpaulin or similar fabric
during rainstorms. Measures should be
taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.9 |
All
DPs and Non-DPs |
Manholes (including
newly constructed ones) should always be adequately covered and temporarily
sealed so as to prevent silt, construction materials
or debris from getting into the drainage system, and to prevent storm run-off
from getting into foul sewers.
Discharge of surface run-off into foul sewers must always be prevented
in order not to unduly overload the foul sewerage system. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.10 |
All
DPs and Non-DPs |
Water used in ground
boring and drilling for site investigation or rock / soil anchoring should as
far as practicable be re-circulated after sedimentation. When there is a need for final disposal,
the wastewater should be discharged into storm drains via silt removal
facilities. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.11 |
All
DPs and Non-DPs |
All vehicles and
plants should be cleaned before they leave a construction site to minimise
the deposition of earth, mud and debris on
roads. A wheel washing bay should be
provided at every site exit if practicable and washwater
should have sand and silt settled out or removed before discharging into
storm drains. The section of
construction road between the wheel washing bay and the public road should be
paved to reduce vehicle tracking of soil and to prevent site run-off from
entering public road drains. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM WPCO Waste Disposal
Ordinance (WDO) ProPECC
PN 2/23 |
5.7.1.12 |
All
DPs and Non-DPs |
Acidic wastewater
generated from acid cleaning, etching, pickling and similar activities should
be neutralised to within the pH range of 6 to 10 before discharging into foul
sewers. If there is no public foul
sewer in the vicinity, the neutralised wastewater should be tankered off site for disposal into foul sewers or
treated to a standard acceptable to storm drains and the receiving waters. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 Technical Memorandum
on Standards for Effluents Discharged into Drainage and Sewerage Systems,
Inland and Coastal Waters (TM-DSS) |
5.7.1.13 |
All
DPs and Non-DPs |
Good site practices
should be adopted to remove rubbish and litter from construction site so as to prevent the rubbish and litter from spreading
from the site area. It is recommended
to clean the construction site on a regular basis. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM WDO ProPECC
PN 2/23 |
5.7.1.14 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
|
5.7.1.15
5.7.1.16 |
All
DPs and Non-DPs |
The practices
outlined in Environment, Transport and Works Bureau (ETWB) TC (Works) No.
5/2005 Protection of natural streams/rivers from adverse impacts arising
from construction works should also be adopted where applicable to
minimise the water quality impacts upon any natural streams or surface water
systems. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 ETWB TC (Works) No.
5/2005 |
5.7.1.17
|
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
|
5.7.1.18 |
All
DPs and Non-DPs |
Construction works
at watercourse should be undertaken only after flow diversion or dewatering
operation is fully completed to avoid water flow in the works area. Dewatering of watercourse should be
performed by diverting the water flow to new or temporary drainage. Where necessary, cofferdams or similar
impermeable sheet pile walls should be used to isolate the works areas from
neighbouring waters. The permanent or
temporary drainage for carrying the diverted flow from existing watercourse
to be removed should be constructed and completed before dewatering of that
existing watercourse. Construction of
all the proposed permanent and temporary drainage should be undertaken in a
dry zone prior to receiving any water flow. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
5.7.1.19 |
All
DPs and Non-DPs |
The Contractor
should provide a dry zone for all the construction works to be undertaken in
watercourses and stormwater drainage following the tentative works sequence
as described above or using other approved methods as appropriate to suit the
works condition. The flow diversion
works should be conducted in dry season, where possible, when the flow in the
watercourse is low. The wastewater and
ingress water from the site should be properly treated to comply with the
WPCO and the TM-DSS before discharge. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
5.7.1.20 |
All
DPs and Non-DPs |
The
site practices outlined in the ProPECC PN 2/23 Construction
Site Drainage and ETWB TC (Works) No. 5/2005 Protection of natural
streams/rivers from adverse impacts arising from construction works
should be adopted for the proposed demolition or diversion of watercourses
where applicable. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 ETWB TC (Works) No.
5/2005 |
5.7.1.21 |
DP1,
DP6, DP7, Non-DPs |
Construction
works at the existing ponds / wet areas should be conducted only after
dewatering of these ponds / wet areas is fully completed. The drained water generated from the
dewatering of these ponds / wet areas to be removed should be temporarily
stored in appropriate storage tanks or containers for reuse on-site as far as
possible. Any surplus drained water
should be tankered away for disposal
at the sewage treatment works (STW) in a controlled manner.
No direct discharge of drained water to the stormwater drainage system or
marine water should be allowed. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
5.7.1.22 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WDO ProPECC
PN 2/23 ETWB TCW No. 34/2002 |
|
5.7.1.23 |
All
DPs and Non-DPs |
Contractor must
register as a chemical waste producer if chemical wastes would be produced
from the construction activities. The
WDO (Cap 354) and its subsidiary regulations in particular
the Waste Disposal (Chemical Waste) (General) Regulation, should be observed
and complied with for control of chemical wastes. The Contractor is also recommended to
develop management procedures for chemicals used and prepare an emergency
spillage handling procedure to deal with chemical spillage in case of
accident occurs. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO WDO ProPECC
PN 2/23 Waste Disposal
(Chemical Waste) (General) Regulation EIAO-TM |
5.7.1.24 |
All
DPs and Non-DPs |
Any service shop and
maintenance facilities should be located on hard standings within a bunded
area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these
discharges. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO WDO ProPECC
PN 2/23 Waste Disposal (Chemical
Waste) (General) Regulation EIAO-TM |
5.7.1.25 |
All
DPs and Non-DPs |
Disposal of chemical
wastes should be carried out in compliance with the WDO. The Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes published under the WDO should be
followed to avoid leakage or spillage of chemicals. General requirements are given as follows:
Suitable
containers should be used to hold the chemical wastes to avoid leakage or
spillage during storage, handling and transport;
Chemical
waste containers should be suitably labelled, to notify and warn the
personnel who are handling the wastes, to avoid accidents; and
Storage
area should be selected at a safe location on site and adequate space should
be allocated to the storage area. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO WDO ProPECC
PN 2/23 Waste Disposal
(Chemical Waste) (General) Regulation EIAO-TM |
5.7.1.26 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
|
5.7.1.27 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 |
|
5.7.1.28 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
|
5.7.1.29 |
All
DPs and Non-DPs |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO TM-DSS ProPECC
PN 2/23 Guidance Note for Contaminated
Land Assessment and Remediation |
|
5.7.1.30 |
All
DPs and Non-DPs |
If
deployment of wastewater treatment is not feasible for handling the
contaminated groundwater, groundwater recharging wells should be installed as
appropriate for recharging the contaminated groundwater back into the ground. The recharging wells should be selected at
places where the groundwater quality will not be affected by the recharge
operation as indicated in Section 2.3 of TM-DSS. The baseline groundwater quality should be
determined prior to the selection of the recharge wells, and submit a working
plan to EPD for agreement. Pollution
levels of groundwater to be recharged shall not be higher than pollutant
levels of ambient groundwater at the recharge well. Groundwater monitoring wells should be
installed near the recharge points to monitor the effectiveness of the
recharge wells and to ensure that no likelihood of increase of groundwater
level and transfer of pollutants beyond the site boundary. Prior to recharge, free products should be
removed as necessary by installing the petrol interceptor. The Contractor should apply for a discharge
licence under the WPCO through the Regional Office of EPD for groundwater
recharge operation or discharge of treated groundwater. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
5.7.1.31 |
All
DPs and Non-DPs |
Provide
spare or standby treatment facilities of suitable capacities for emergency
replacement in case damage or defect or malfunctioning of the duty treatment
facilities is observed;
Conduct
daily integrity checking of the construction site drainage and treatment
facilities to inspect malfunctions, in particular before,
during and after a storm event; and
Carry
out regular maintenance or desilting works to maintain effectiveness of the
construction site drainage and treatment facilities in
particular before, during and after a storm event. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
5.7.1.32 |
All
DPs and Non-DPs |
An
Emergency Response Plan (ERP) should be developed
to minimise the potential impact from construction site discharges under
failure of treatment facilities during emergency situations or inclement
weather. The ERP should give the
emergency contacts to mobilise flood retention facilities and stakeholders to
be notified as well as the details of the proposed construction site drainage
system and the design and operation of duty and standby treatment facilities. The ERP should also provide the procedures
and guidelines for routine integrity checking and maintenance of the drainage
system and treatment facilities as well as the emergency response and
rectification procedures to restore normal operation of the treatment facilities
in case of treatment failure during emergency situation
or inclement weather. The Best
Management Practices (BMPs) in controlling water pollution arising from the
construction activities and an event and action plan with action and limit
levels for water quality monitoring should be included in the ERP. The ERP should be submitted to the EPD for
approval before commencement of the construction works. |
Construction
Sites / Construction Phase |
Contractor |
|
√ |
|
WPCO EIAO-TM ProPECC
PN 2/23 TM-DSS |
Design and Operation Phases |
||||||||
5.7.2.1 |
DP2 |
Given the
sensitivity of inner Deep Bay in term of water quality and ecology, extensive
effort will be expedited to avoid the occurrence for emergency
discharge. In order
to achieve this, the design of STLMC Effluent Polishing Plant (EPP)
will be cautiously reviewed to include additional provisions including as
follows:
Applied
peaking factors for all major treatment units and electrical and mechanical
equipment to avoid equipment failure;
By-pass
mechanism would be provided for both coarse screens and fine screens in the
inlet to avoid/minimise failure in coarse/fine screens; Interim by-pass would
be provided after the primary sedimentation tank to avoid raw sewage by-pass
as much as possible;
Standby
unit for all major equipment would be provided in case of unexpected
breakdown of pumping and treatment facilities such that the standby pumps and
treatment facilities could take over and function to replace the broken
pumps; and
Back-up
power for dual power supply would be provided in case of power failure to
sustain the function of pumping and treatment facilities. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO EIAO-TM ProPECC
PN 1/23 |
5.7.2.2 |
DP2 |
To provide a
mechanism to minimise the impact of emergency discharges and facilitate
subsequent management of any emergency, an Emergency Response Plan will be
formulated prior to commissioning of STLMC EPP to set out the emergency
response procedures and actions to be followed in case of equipment or sewage
treatment failure. The plant operators
of STLMC EPP should carry out necessary follow-up actions according to the
procedures of the contingency plan to minimise any impacts on the identified
water sensitive receivers (WSRs) due to emergency bypass. Regular maintenances and inspections to all
treatment units, penstocks and plant facilities are necessary to maintain a
good operation condition. A follow-up
water quality monitoring exercise shall be conducted after each emergency
discharge event to monitor the recovery of water quality in the vicinity. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO EIAO-TM ProPECC
PN 1/23 |
5.7.2.3 |
Non-DPs |
·
Regular inspection,
checking and maintenance of the sewerage system; ·
Provisions of twin rising
mains as backup and to facilitate maintenance and repairing purposes; ·
Provisions of leakage
collection systems linking to the nearest chamber at its downstream to the
rising main for collection of sewage leakage from the damaged rising main; ·
Use tankers to store
emergency discharge and transport to the EPP by registered tankers companies
for disposal in case of both twin rising mains failure; and ·
Provisions of spare /
standby parts of sewage pipeworks to facilitate
maintenance and repairing of equipment. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO EIAO-TM ProPECC
PN 1/23 Sewerage Manual_Part 2 (DSD) |
5.7.2.4 |
Non-DPs |
In order to minimise the chance
of emergency sewage discharge, the following precautionary measures are
proposed to be incorporated in the design of the Sewage Pumping Stations
(SPS): · A standby pump and
screen should be provided to cater for breakdown and maintenance of the duty
pump in order to avoid emergency discharge; · Backup power supply
in the form of dual / ring circuit power supply or generator should be
provided to secure electricity supply; · An alarm should be
installed to signal emergency high water level in the wet well; · An emergency storage
tank should be provided for the proposed SPS to cater for breakdown and
maintenance of duty pump; · Regular maintenance
and checking of plant equipment should be undertaken to prevent equipment failure; · Twin rising mains
system should be provided to facilitate maintenance works and to avoid
emergency discharge of sewage; · A telemetry system
to the nearest manned station / plant should be provided so that swift action
can be undertaken in case of malfunction of the unmanned facilities; and · A bar screen (with
clear spacing of approximately 25 mm) should be provided to cover the lower
half of the opening of any emergency sewage bypass which can prevent the
discharge of floating solids into receiving waters as far as practicable
while ensuring flooding at the facilities would not occur event if the screen
is blocked. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO EIAO-TM ProPECC
PN 1/23 Sewerage Manual_Part 2 (DSD) |
5.7.2.5 |
Non-DPs |
· Locations of water
bodies or WSRs in the vicinity of the emergency discharges; · A list of relevant
government departments to be informed and to provide assistance in the event
of emergency discharge, including key contact persons and telephone numbers; · Reporting procedures
required in the event of emergency discharges; and · Procedures listing
the most effective means in rectifying the breakdown of the SPS in order to minimise the discharge duration. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO EIAO-TM ProPECC
PN 1/23 |
5.7.2.6 5.7.2.14 |
All DPs and Non-DPs |
Best Management
Practices (BMPs) to reduce storm water and non-point source pollution are
also proposed as follows: Design Measures
·
Exposed
surface shall be avoided within the development sites to minimise soil
erosion. The development site shall be
either hard paved or covered by landscaping area and plantation where
appropriate. ·
The major
water channels and nullahs within the development sites should be retained as
far as practicable to maintain the original flow path. The drainage system should be designed to
avoid flooding. ·
Green areas /
tree / shrub planting etc. should be introduced within the development site
as far as possible including open space and along roadside amenity strips and
central dividers, which can help to reduce soil erosion. Devices/
Facilities to Control Pollution
·
Screening
facilities such as standard gully grating and trash grille, with spacing
which is capable of screening large substances such as fallen leaves and
rubbish should be provided at the inlet of drainage system. ·
Road gullies
with standard design and silt traps and oil interceptors should be
incorporated during the detailed design to remove particles present in
stormwater run-off, where appropriate. ·
Evergreen tree
species, which in general generate relatively smaller amount of fallen
leaves, should be selected where possible.
Administrative Measures ·
Good
management measures such as regular cleaning and sweeping of road surface /
open areas is suggested. The road
surface / open area cleaning should also be carried out prior to occurrence
of rainstorm. · Manholes, as well as storm water gullies, ditches
provided among the development areas should be regularly inspected and
cleaned (e.g. monthly). Additional
inspection and cleansing should be carried out before forecast heavy
rainfall. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO ProPECC
PN 1/23 |
5.7.2.15 |
All
DPs and Non-DPs |
For maintenance of
stormwater drainage system, reference should be made to ETWB TC (Works) No.
14/2004 Maintenance of Stormwater Drainage Systems and Natural
Watercourses where applicable.
The circular sets out the departmental responsibilities for the
maintenance of stormwater drainage systems and natural watercourses in
government and private lands. Any
required maintenance or desilting work (e.g. to remove any silt, grit or
rubbish deposited in the inland water system) should be carried out during
periods of low flow in the dry season to minimise impacts on downstream water
quality and sediment suspension. |
Project
site / Design and Operation Phase |
Project
Proponent |
√ |
|
√ |
WPCO ProPECC
PN 1/23 ETWB TC (Works) No.
14/2004 |
5.7.2.16 |
DP3 |
A new water
reclamation plant is proposed under this Project which will receive the
tertiary treated effluent from the STLMC EPP during operation phase. Ultrafiltration treatment process is
recommended to employed for water reclamation. Once the water reclamation
plant has commenced operation, the tertiary treated effluent from the STLMC
EPP will be further polished into reclaimed water which will cut down the
freshwater demand in the area, saving precious freshwater resources and
reducing the pollution loading discharge to the Deep Bay waters. The potential water quality impact from the
STLMC EPP effluent would decrease as compared with the worst-case scenario of
STLMC EPP with full discharge of 125,000 m3/day to Deep Bay. |
Design
and Operation Phase |
Project
Proponent |
√ |
|
√ |
Reclaimed water
quality standards endorsed by the Working Group on the Implementation of
Reclaimed Water Supply in Sheung Shui and Fanling |
Sewerage and Sewage Treatment |
||||||||
Operation
Phase |
||||||||
6.13.1
6.13.2 |
Non-DPs |
Non-dosing solutions
should be considered in prior to dosing solutions. Direct injection of oxygen into the rising
mains and pre-aeration in the wet well of the pumping stations are adopted as
the sewage septicity control measures. |
Project
site / Operation Phase |
Project
Proponent |
|
|
√ |
EIAO-TM WPCO |
6.13.3 |
Non-DPs |
Enclosed the pumping
station inside building structure is considered as an odour mitigation
measures. The structure is equipped
with adequate odour control measures such as scrubber and activated charcoal
filter at the exhaust of the ventilation system. The vent will be located away from air
sensitive uses including the proposed development itself. |
Project
site / Operation Phase |
Project
Proponent |
|
|
√ |
EIAO-TM WPCO |
6.13.4 |
DP2 |
The effluent from STLMC
EPP should follow a stringent standard and fulfil discharge limits of
pollutants in Standards for Effluents Discharged into Drainage and Sewage
System, Inland and Coastal Waters, the Water Pollution Control Ordinance (CAP
358) which wont deteriorate the Deep Bay water quality. |
Project
site / Operation Phase |
Project
Proponent |
|
|
√ |
EIAO-TM WPCO |
6.13.5 |
DP2 |
To avoid the
occurrence for emergency discharge, the design of STLMC EPP will be
cautiously reviewed to include additional provisions including as follows: ·
Applied
peaking factors for all major treatment units and electrical and mechanical
equipment to avoid equipment failure; ·
Standby unit
for all major equipment would be provided in case of unexpected breakdown of
pumping and treatment facilities such that the standby pumps and treatment
facilities could take over and function to replace the broken pumps; and ·
Back-up power
for dual power supply would be provided in case of power failure to sustain
the function of pumping and treatment facilities. |
Project
site / Operation Phase |
Project
Proponent |
|
|
√ |
EIAO-TM WPCO |
Waste Management Implication |
||||||||
Construction
Phase |
||||||||
7.6.1.17.6.1.2 |
All
DPs and Non-DPs |
Waste
Management Hierarchy The waste management hierarchy should be applied including
the following in descending preference:
Avoidance
and minimisation of waste generation;
Reuse
of materials as far as practicable;
Recovery
and recycling of residual materials where possible; and
Treatment
and disposal of waste according to relevant laws, guidelines
and good practices. To
minimize C&D materials generation and encourage proper management of such
materials, a C&DMMP should be prepared.
An EMP and trip-ticket system are recommended for monitoring
management of waste. Specific measures
targeting the mitigation of impacts in works areas and the transportation of
waste off-site should be provided to minimise the potential impacts to the
surrounding environment. |
Construction
Sites |
Contractor |
|
√ |
|
WDO ETWB TCW No. 19/2005 DEVB TCW No. 06/2010 Project
Administration Handbook (PAH) got Civil Engineering Works |
7.6.1.3 |
All
DPs and Non-DPs |
Good Site Practices The following good site practices are recommended during
the construction phase:
Nomination
of an approved personnel, such as a site manager, to be responsible for the
implementation of good site practices;
Training
of site personnel in site cleanliness, proper waste management and chemical
handling procedures;
Provision
of sufficient waste disposal points and regular collection of waste for disposal;
Adoption
of appropriate measures to minimise windblown litter and dust during
handling, transportation and disposal of waste; and Preparation of a WMP in accordance with the ETWB TCW No. 19/2005 Environmental Management on Construction
Sites and submitted it to the Engineer for approval. |
Construction
Sites |
Contractor |
|
√ |
|
WDO Public Cleansing and
Prevention of Nuisances Regulation (Cap. 132BK) |
7.6.1.4 |
All
DPs and Non-DPs |
Waste
Reduction Measures Recommendations to
achieve waste reduction include:
Segregate and store different types of waste in different containers, skips or stockpiles to enhance
reuse or recycling of
materials and their
proper disposal;
Adopt proper storage and site practices to
minimise the potential for damage to, and contamination of, construction materials;
Plan
the delivery and stock of construction materials carefully to minimise the
amount of waste generated;
Sort
out demolition debris and excavated materials from demolition works to
recover reusable / recyclable portions (i.e. soil, rock, broken concrete,
etc.);
Maximise
the use of reusable steel formwork to reduce the amount of C&D materials;
Minimise
over ordering of concrete, mortars and cement grout
by doing careful check before ordering; and
Adopt
pre-cast construction method instead
of cast-in-situ method for construction of concrete structures as far as possible. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.1.5 |
All
DPs and Non-DPs |
Storage
of Waste Recommendations to
minimise the impacts include: Waste, such as soil, should be handled and
stored well to ensure secure containment, thus minimising the potential of pollution; Maintain and clean
storage areas routinely; Stockpiling area
should be provided with covers and water spraying system to prevent materials
from being wind-blown or washed away; and Different locations should be designated to stockpile each material to enhance reuse. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.1.6 |
All
DPs and Non-DPs |
Collection of Waste Waste
hauler with appropriate permits should be employed by the Contractor for the collection and transportation of waste
from works areas to respective disposal outlets. The following recommendation should be
implemented to minimise the impacts: Remove waste in
timely manner; Employ the trucks
with cover or enclosed containers for waste transportation;
Obtain relevant
waste disposal permits from the appropriate authorities; and Dispose of waste at licensed
waste disposal facilities. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.2.1 |
All
DPs and Non-DPs |
Construction and
Demolition Materials Careful design,
planning together with good site management can reduce over-ordering and
generation of Construction and Demolition (C&D) materials such as
concrete, mortar and cement grouts.
Formwork should be designed to minimise the use of standard wooden
panels, so that high reuse levels can be achieved. Alternatives such as steel formwork or
plastic facing should be considered to increase the potential for reuse. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.2.2 |
All
DPs and Non-DPs |
The inert C&D
materials with suitable characteristics / size should be reused on-site as
fill or recycled as aggregate for other projects as far as practicable. When disposing C&D material at a public
filling reception facility for beneficial reuse, the material should only
consist of soil, rock, concrete, brick, cement plaster / mortar, inert
building debris, aggregates and asphalt. The material should be free from household
refuse, plastic, metals, industrial and chemical waste, animal and vegetable
matter, and other material considered to be unsuitable by the Filling
Supervisor. Prior to disposal of
non-inert C&D materials, wood, steel and other
metals should also be separated for reuse and / or recycling where
practicable so as to minimise the quantity of waste to be disposed of at
landfill. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.2.3 |
All
DPs and Non-DPs |
Suitable areas
should be designated within the site boundaries for sorting and providing
temporary stockpiling of C&D materials.
Within stockpile areas, the following measures should be taken to
control potential environmental impacts or nuisance:
Surface
of stockpiled soil should be regularly wetted with water especially during
dry season;
Disturbance
of stockpile soil should be minimised;
Stockpiled
soil should be properly covered with tarpaulin especially when heavy storms
are predicted; and
Stockpiling
areas should be enclosed where space is available. |
Construction
Sites |
Contractor |
|
√ |
|
WDO ETWB TCW No.19/2005 |
7.6.2.4 |
All
DPs and Non-DPs |
In
order to monitor the delivery
of C&D materials at the designated public fill reception facility and
landfill and to control fly-tipping, a trip-ticket system should be
included. A recording system for the amount of waste generated, recycled and disposed,
including the disposal sites, should also be set up. Warning signs should be put up to remind
the designated disposal sites. CCTV
should also be installed at the vehicular entrance and exit of the site to
monitor handling of C&D materials disposal. To prohibit illegal dumping and landfilling
of C&D materials, as well as proper delivery to concurrent project sites
for re-use, the dump trucks engaged on site should be equipped with GPS or
equivalent automatic system for real time tracking and monitoring of their
travel routings, parking locations and disposal activities. |
Construction
Sites |
Contractor |
|
√ |
|
WDO DEVB TC(W)
No.06/2010 Land (Miscellaneous
Provisions) Ordinance (Cap. 28) |
7.6.2.5
7.6.2.7 |
All
DPs and Non-DPs |
Due to the potential
large amount of asbestos containing materials (ACM) during the site clearance
stage, asbestos investigation is
required. However, as asbestos
investigation will involve a large number of buildings and most premises
will involve private access, which cannot be obtained at this stage, it is considered that an asbestos specialist shall be employed by the responsible parties during
the construction stage
to investigate this issue. Sufficient and reasonable lead time shall
be allowed for preparation, vetting
and implementation of Asbestos Investigation Report and Asbestos Abatement Plan in accordance with Air Pollution Control Ordinance before
commencement of any demolition or site clearance work. Some key
precautionary measures related to the handling and disposal of asbestos are listed
as following:
Adoption
of protection, such as full containment, mini containment, or segregation of
work area;
Provision
of decontamination facilities for cleaning of workings, equipment and bagged
waste before leaving the work area;
Adoption
of engineering control techniques to prevent fibre release from work area,
such as use of negative pressure equipment with high efficiency particulate
air (HEPA) filters to control air flow between the work area and the outside environment;
Wetting
of asbestos containing materials before and during disturbance, minimising
the breakage and dropping of asbestos containing materials, and packing of
debris and waste immediately after it is produced;
Cleaning
of work area by wet wiping and vacuuming with HEPA-filtered vacuum cleaner;
Coating
on any surfaces previously in contact with or contained by asbestos with a sealant;
Proper
bagging, safe storage and disposal of asbestos and asbestos-contaminated waste;
Pre-treatment
of all effluent from the work area before discharged; and
Air
monitoring strategy to check the leakage and clearance of the work area
during and after the asbestos work. |
Construction
Sites |
Contractor |
|
√ |
|
APCO Code of Practice on
Handling, Transportation and Disposal of Asbestos Waste ProPECC
PN 2/97 Handling of Asbestos Containing Materials in Buildings |
7.6.2.9
7.6.2.10 |
All
DPs and Non-DPs |
Chemical Waste For those
processes which generated chemical waste, it may be possible to find alternatives to eliminate the use of
chemicals, to reduce the generation quantities or to select a chemical type of less
impact on environment, health and safety as far as possible. If chemical waste is
produced at the construction site, the Contractor will be required to register with the EPD as a chemical
waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste. Chemical waste should be stored in
appropriate containers and collected by a licensed chemical waste contractor.
Chemical waste (e.g. spent
lubricant oil) should be recycled at
an appropriate facility as far as possible, while chemical waste that cannot
be recycled should be disposed of
at either the Chemical Waste
Treatment Centre (CWTC), or another licensed facility, in accordance with the Waste
Disposal (Chemical Waste)
(General) Regulation. |
Construction
Sites |
Contractor |
|
√ |
|
Waste Disposal
(Chemical Waste) General) Regulation Code of Practice on
the Packaging, Labelling and Storage of Chemical Waste |
7.6.2.11
7.6.2.12 |
All
DPs and Non-DPs |
General
refuse should be stored in enclosed bins or compaction units separate from
C&D materials and chemical wastes.
A reputable waste collector should be employed by the contractor to
remove general from the site, separately from C&D materials and chemical
wastes, on a daily basis to minimise odour, pest and
litter impacts. The collected general refuse would be
disposed of at designated landfill.
Clearly labelled recycling bins should be provided on site in order to encourage segregation and recycling of
aluminium and plastic wastes, and wastepaper in order to reduce general
refuse production. The contractor
should carry out an education programme for workers in avoiding, reducing, reusing and recycling of materials generation. Posters and leaflets advising on the use of
the bins should also be provided onsite as reminders. The recyclable waste materials should then
be collected by reliable waste recycling agents on a daily
basis. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.2.13 |
All
DPs and Non-DPs |
Excavated Sediment Since the amount of
excavated sediment generated from the pond excavation works is expected to be
small, all excavated sediment will be treated and reused on-site as backfilling materials for the Project. This approach avoids the need for off-site disposal that may result in
impacts on the marine environment. In
addition, all construction works
near the watercourses should be undertaken within a dry zone and during
dry season to avoid adverse
impacts to the environment. The excavated sediment, if stockpiled on site, should
be stored in enclosed containers and transported
to
the on-site treatment facilities as soon as practicable to minimise any
potential odour impacts. |
Construction
Sites |
Contractor |
|
√ |
|
WDO |
7.6.2.14 |
All
DPs and Non-DPs |
Floating Refuse In case of floating
refuse is identified, the floating materials should be removed and eventually
stored and disposed of together with the general refuse, after separating the
recyclables for recycling. Any floating refuse trapped within the Project
area will be collected by the Contractor and disposed together with other
general refuse. Apart from collecting
and storing waste with good waste management practice on site to avoid having
waste transported to river channels or water bodies under extreme weather
conditions, the contractor should be responsible for the collection of
refuse, if any, within the works area.
Contractor shall collect and remove floating refuse at regular
intervals on a daily basis to keep river channels or
water bodies within the Project area and the neighbouring water free from
rubbish during the construction phase.
|
Construction
Sites |
Contractor |
|
√ |
|
WDO |
Operation Phase |
||||||||
7.6.3.1 7.6.3.2 |
All
DPs and Non-DPs |
Municipal Solid
Waste Implementation of a
waste prevention programme as well as materials recovery and recycling programme are recommended in order to minimise
the production of waste. The programmes should consist of the following components:
Recycling
bins such as paper, aluminium cans, plastic bottles, glass bottles, etc.
should be placed at prominent locations to encourage recycling;
Banner
should be erected at the recycling bins area;
Operator
should make arrangements with the recycler to collect and recycle used
fluorescent lamps, toner cartridges as well as the scrap electronic
equipment, such as computers to avoid disposal at landfills as far as practicable;
Staff
awareness training should be provided on waste management procedures,
including waste reduction and recycling;
Operator
should set up waste reduction and recycled targets; and
Operator
should participate in the Wastewi$e Label scheme to
facilitate waste reduction. MSW generated from
residential, commercial and industrial buildings
should be collected with lidded
bins, delivered to the refuse
collection room and stored in enclosed containers installed in each building at
the ground floor to prevent windblown, vermin, water pollution and visual impact. At least daily collection should be
arranged by the waste collector to
transport the waste to the refuse collection points (RCPs) or refuse transfer
station (RTS) within the STLMDC DN.
Odour removal installations
are recommended to be installed at the RCPs and RTS to treat the exhaust
air. Such arrangements will minimise potential environmental impacts.
The above recommendations are proposed as technical guidelines for the operators consideration and will be subject to detailed design. |
Operation Phase |
FEHD/ relevant operators |
|
|
√ |
WDO |
7.6.3.3 |
All
DPs and Non-DPs |
Chemical Waste The proposed
mitigation measures for operation phase are the same as that proposed for the construction phase.
The operator should register with EPD as a chemical waste producer and follow the guidelines
stated in the Code of Practice on the Packaging, Labelling and Storage
of Chemical Wastes. Chemical waste should be stored in appropriate
containers and collected by a licensed chemical waste contractor. Chemical
waste (e.g. spent lubricant oil) should be recycled at an appropriate
facility as far as possible, while
chemical waste that cannot be recycled should be disposed of at either the CWTC, or another licensed facility,
in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. |
Operation Phase |
Relevant operators |
|
|
√ |
Waste Disposal
(Chemical Waste) (General) Regulation Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes |
7.6.3.4 |
DP2 |
Screenings, Grits and Sewage Sludge Screenings and grits
generated from the EPP is suggested to be disposed of at the NENT Landfill whereas the dewatered sludge generated from the EPP
is suggested to be treated at the STF.
The screenings, grits and
dewatered sludge will be delivered by road transport in water
tight containers or skips to
avoid odour emission during transportation.
Unloading process will be
operated in the designated room inside STF
which should be enclosed and served
by negative pressure by extracting odorous
gas to deodorising unit. |
Operation Phase |
DSD / relevant operators |
|
|
√ |
WDO |
Hazard to Life |
||||||||
13.9.1.1 |
N/A |
Since hazard to life issue would not be anticipated, no mitigation measure
is considered necessary for the Project.
|
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Land Contamination |
||||||||
Construction Phase |
||||||||
8.8.3.2
- 8.8.3.8 |
All
DPs and Non-DPs |
Potentially Contaminated Sites
Prior
to development of these sites, the Project Proponent should appoint a
consultant to re-appraise these sites to update the corresponding findings
and sampling and testing requirements presented in the Contamination
Assessment Plan (CAP). Supplementary CAP(s), incorporating the findings of
the site re-appraisal and the updated sampling and testing strategy, should
be prepared and submitted to EPD for approval prior
to conducting any site investigation (SI) works. SI works should then be
carried out according to the supplementary CAP(s). Contamination Assessment
Report (CAR(s)) and, if contaminated soil and/or groundwater identified,
Remediation Action Plan (RAP(s)) should be prepared and submitted to EPD for
approval.
For the nine (9) sites (namely S201, S202, S301,
S302, W101, W102, W103, W104 and W105), the Project Proponent shall carry out
site investigation and sampling works in accordance with the CAP in Appendix 8.1 of the EIA Report at a later stage. |
All
Potentially Contaminated Sites as listed in CAP
/
After
the land is resumed and handed over to the Project Proponent and prior to
commencement of any remediation / construction works.
|
Project
Proponent / Contractor
|
|
√ |
|
Annex 19 of the
EIAO-TM Guidance Note for
Contaminated Land Assessment and Remediation (EPD, Revised in April 2023) Practice Guide for
Investigation and Remediation of Contaminated Land (EPD, Revised in April
2023)
Guidance
Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management (EPD, Revised in April 2023) |
8.8.3.9
- 8.8.3.12 |
All
DPs and Non-DPs |
Sites Requiring Further Appraisal &
Non-Contaminated Sites
After
the sites are handed over to the Project Proponent for development, the
Project Proponent should appoint a consultant for site re-appraisal to assess
the latest land uses and site conditions. If any of these sites are found to
have potential land contamination issues, the Project Proponents appointed
consultant should prepare and submit supplementary CAP(s) to EPD for approval
prior to conducting any SI works. SI works should then be carried out
according to the supplementary CAP(s). CAR(s) and, if contaminated soil
and/or groundwater identified, RAP(s) should be prepared and submitted to EPD
for approval.
|
All
Sites Requiring Further Appraisal & Non-Contaminated Sites as listed in CAP
/
After
the land is resumed and handed over to the Project Proponent and prior to
commencement of any remediation / construction works.
|
Project
Proponent / Contractor
|
|
√ |
|
Annex 19 of the
EIAO-TM Guidance Note for
Contaminated Land Assessment and Remediation (EPD, Revised in April 2023) Practice Guide for
Investigation and Remediation of Contaminated Land (EPD, Revised in April
2023)
Guidance
Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management (EPD, Revised in April 2023) |
8.8.3.13
- 8.8.3.15 |
All
DPs and Non-DPs |
Sites not to be Developed
In
the event of a change to the Project plan wherein these sites will be developed,
re-appraisal will be required to assess the potential land contamination
status at such time that the site become accessible
|
All
Sites not to be Developed as listed in CAP
/
After the land is
resumed and handed over to the Project Proponent and prior to commencement of
any remediation / construction works. |
Project
Proponent / Contractor |
|
√ |
|
Annex 19 of the
EIAO-TM Guidance Note for
Contaminated Land Assessment and Remediation (EPD, 2 Revised in April 2023) Practice Guide for
Investigation and Remediation of Contaminated Land (EPD, Revised in April
2023)
Guidance
Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management (EPD, Revised in April 2023) |
8.12.5.2 |
All
DPs and Non-DPs |
Further
arsenic assessment should be carried out during site formation and during
construction of foundation. The Government will treat the HAC soil in the
shallow region before land allocation or land lease. The treatment depth will
depend on the future land use in RODP.
Subsequent Developer/Works Departments will treat HAC soil in deep
regions for excavations required for basements, piles
and utilities.
|
After the land is
resumed and handed over to the Project Proponent and prior to commencement of
any remediation / construction works. |
Project
Proponent / Contractor |
|
√ |
|
EIAO-TM |
Landfill Gas
Hazard |
||||||||
Construction Phase |
||||||||
9.7.2.1
|
Non-DPs |
During construction
phase, the risk was classified as very low (insignificant) that no
precautionary measures are required.
|
Not required |
Not Required |
|
|
|
Landfill Gas Hazard Assessment Guidance Note |
Operation Phase |
||||||||
9.7.3.1
9.7.3.9 |
Non-DPs |
Generic Passive
Precautionary Measures
Utility protection measures for services passing
through the consultation zone.
Creation of a subsurface preferential gas venting
pathway or construction of a subsurface gas barrier.
Venting of manholes and above ground
terminations.
In ground venting or gas barrier protection
measures may be located on the boundary of the development closest to the
landfill. Dependent upon the orientation of the development and detailed design, utilities penetrating a ground floor slab on grade may require sealing. Utility Protection Design Measures The void around any service ducts, pipes or cables within conduits at the point where the trench passes through the perimeter of the consultation zone should be filled with gas resistant mastic. All ducts, manholes and chambers to utility services should be sealed from the surrounding ground to prevent gas entry and provided with vented covers to allow any gas that enters to dissipate to atmosphere. The service run should be designated as a special route and utility companies should be informed to that effect so that they may implement precautionary measures. Precautionary measures should include ensuring that staff members are aware of the potential hazards of working in confined spaces such as manholes and service chambers, and that appropriate monitoring procedures are in place to prevent hazards due to asphyxiating atmospheres in confined spaces. Structure Protection Design Measures
For
sub-surface building services/utilities, generic protection measures should
include U-bends fitted to water pipes and sewers which are not always fully
filled to effectively seal off the conduit and prevent gas-phase transport.
For
building services penetrating the ground floor slab, collar seals should be
installed to prevent gas ingress via the penetration. Vent pipes or gridded manhole covers may be used to avoid build-up of gas in underground utility manholes. |
Development within 250m Landfill Consultation Zone |
Project
Proponent / Contractor |
|
|
√ |
Landfill Gas Hazard Assessment Guidance Note |
9.7.4.1
9.7.4.2 |
Non-DPs |
Any
service voids, manholes or chambers which are large enough to permit access
to personnel should be subject to entry safety procedures. Works in confined spaces are controlled by
the Factories and Industrial Undertakings (Confined Spaces) Regulation of the
Factories and Industrial Undertakings Ordinance and the Safety Guide to
Working in Confined Spaces should be followed to ensure compliance with the
Regulation.
In general, when work is being undertaken in confined spaces, sufficient approved resuscitation equipment, breathing apparatus and safety torches should be made available. Persons involved in or supervising such work should be trained and practiced in the use of such equipment. A permit-to-work system for entry into confined spaces should be developed by an appropriately qualified person and the system should be consistently employed. The safety measures recommended in Chapter 8 of the Landfill Gas Hazard Assessment Guidance Note should also be strictly followed. |
|
|
|
|
√ |
Factories and
Industrial Undertakings (Confined Spaces) Regulation of the Factories and
Industrial Undertakings Ordinance Safety Guide to
Working in Confined Spaces Landfill Gas Hazard
Assessment Guidance Note |
Ecological Impact (Terrestrial
and Aquatic) |
||||||||
Construction Phase |
||||||||
10.11.1.4 |
Non-DPs |
Enhanced Wetland
within the proposed SPS WCP The Government will develop the Sam Po Shue Wetland
Conservation Park (SPS WCP) with a proposed area of approximately 338 ha to
create environmental capacity for the development of San Tin Technopole. Among
the 338 ha, while 10 ha is reserved for supporting facilities such as visitor
center and other basic infrastructure, the Government will enhance the
ecological function and capacity of 288 ha of wetlands and fisheries resources of 40 ha of fishponds by
establishing the SPS WCP with active conservation management and modernised aquaculture to compensate for the loss in
wetland habitats and fisheries resources arising from the
development of San Tin Technopole and to
achieve no-net-loss in ecological function and capacity of the wetlands
concerned. Among the 288 ha, there
will be 253 ha of ecologically
enhanced fishponds
compensating for pond habitat loss, and 35 ha of enhanced freshwater wetland habitat compensating for other freshwater wetland habitat loss. The Government aims to start the development of SPS WCP in around 2026/2027 for completion by 2039
or earlier to tie in with the full operation of San Tin Technopole. For
the site formation works of the first batch of land at San Tin Technopole
targeted for commencement in late 2024, no pond filling will be
involved. On current planning, pond
filling works will not start until 2026/27, and the pace of pond filling will
tie in with the development progress of the SPS WCP. To this end, a working group will be formed
between CEDD (as San Tin Technopoles works agent) and AFCD (as SPS WCPs
sponsoring department) to coordinate the progress of pond filling and SPS WCP
implementation. Enhancement measures in the form of
improvement of tidal channel near Mai Po Nature Reserve and removal of
exotic mangrove species in the Deep Bay area will also be implemented. Furthermore, interim wetland
enhancement works would also be conducted at suitable ponds in the Inner Deep
Bay area prior to the commencement of pond filling works. Both of these
measures are further described below. |
Enhanced
Wetland within the proposed SPS WCP / Construction
and Operation Phase |
Construction
phase: AFCD as project proponent of SPS WCP; CEDD as works agent Operation
phase: AFCD (within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
EIAO-TM TPB PG-NO. 12C
(Revised May 2014) |
10.11.3.3
10.11.3.4 |
Non-DPs |
Enhanced Wetland for
Pond Habitat
Under the current wetland enhancement strategy,
about 253 ha of enhanced wetland in the form of ecologically enhanced
fishponds shall be established within the proposed SPS WCP. These ecologically enhanced fishponds would
comprise existing pond habitats, and ponds that would be converted from
existing brownfield or wasteland areas.
These ponds shall be further enhanced with various features to
increase the functional value and the carrying capacity to accommodate for
higher abundance of wildlife. Enhancement
measures could include:
Increase
in pond area and enhance connectivity;
Physical
modification of pond habitats to increase environmental carrying capacity;
Managing
and sequencing pond drain down across multiple ponds in the dry season to maximize
feeding opportunities for avifauna and other wildlife;
Providing
fencing/controlling access to reduce disturbance from human activities and
also prevent disturbance and predation of wildlife by feral dogs;
Removal
of existing bird scaring devices at actively managed ponds, where appropriate
Stocking
ponds with suitable prey items (i.e., trash fish) for target wildlife species
(may be considered as an enhancement measure to achieve higher enhancement
value). |
Enhanced
Wetland within the proposed SPS WCP / Construction
and Operation Phase |
Construction
phase: AFCD as project proponent of SPS WCP; CEDD as works agent Operation
phase: AFCD (within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
EIAO-TM |
10.11.3.6 |
Physical Modification of Pond Habitats
Across the entire
ecologically enhanced fishpond areas, ponds could be physically modified to
enhance ecological function and capacity.
Typical measures to be implemented could be based on successful
examples in Hong Kong such as the LMC EEA, including:
Consolidating
smaller, fragmented ponds into larger waterbodies that support higher
densities of avifauna and attract larger, more disturbance sensitive species;
Reprofiling
pond banks to make the edges more gently sloping and shallower, increasing
the available foraging area for avifauna;
Creating
habitat islands that provide refuge for avifauna and other wildlife; and
Floating
platforms / wetlands will be placed in each pond to provide additional
foraging areas for wetland avifauna and potential breeding sites for other
species. |
Enhanced Wetland within the
proposed SPS WCP / Construction and Operation
Phase |
Construction phase: AFCD as
project proponent of SPS WCP; CEDD as works agent Operation phase: AFCD (within
completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
- |
|
10.11.3.7
10.11.3.9 |
Non-DPs |
Pond Drain-down and
Water Management
To
help enhance the functional value of fishpond habitats, the total number of
ponds drained down at any one time can be increased over and above levels
currently implemented under the current Management Agreement (MA) practice. Under current MA practice, a relatively small number
of ponds across the SPS WCP are drained down at any one time. Furthermore,
most ponds participating in the programme are
only partially drained for a period of 7 days. Feeding
opportunities for avifauna could be enhanced by making the following changes
to drain-down practices:
The
total area of fishponds drain-down at any one time could be increased;
Full
drain-down will be implemented rather than partial draining; and
Similar to
recommendations in the approved EIA report for Proposed Development at Fung
Lok Wai, Yuen Long (Mutual Luck Investment Limited, 2008), drain-down periods
will be extended to longer than typical commercial practices or drain-downs
under current practices.
Extending
the length of drain down would allow for water levels to be lowered more
gradually. Where ponds have been
reprofiled to have a shallower gradient, this would result in progressively
larger areas of shallow water/mud being exposed. Overall, this would provide a more stable, high-value feeding habitat for avifauna compared to ponds
which are drained down more quickly. Fishpond water will
primarily be supplied by direct rainfall that will be retained and
re-circulated during drain-down periods.
As with current practice in the area, supplemental water can be
sourced from drainage channels that traverse the site as required. For controlling water levels in the ponds, adjustable sluices or similar water control devices can be provided to connect adjacent ponds, with ponds adjacent to retained drainage channels also having similar devices connecting the ponds to the drainage channels. The water control device levels can be adjusted to allow excess water to flow from pond to pond towards the drainage channels gravity during storm events to prevent overtopping. |
Enhanced
Wetland within the proposed SPS WCP / Construction
and Operation Phase |
AFCD
(within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
- |
10.11.3.10
10.11.3.11 |
Non-DPs |
Controlled Access and
Feral Dog Control
Public access to ecologically enhanced fishponds
habitat area could be controlled to reduce disturbance from human
activities. This could be achieved by potentially gating key access points along the Border Road,
Tun Yu Road and San Tin Tsuen Road (where appropriate,
subject to detailed design). Smaller gates can be
provided to control vehicular access along fishpond bunds. Site access would be maintained and
controlled during the construction and operation phases of the SPS WCP.
Measures
(such as trapping and neutering) would be adopted to minimize disturbance and
predation of wildlife by feral dogs. |
Enhanced
Compensatory Wetland within the proposed SPS WCP / Construction
and Operation Phase |
AFCD
(within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
- |
10.11.3.12 |
Non-DPs |
Removing Bird-scaring
Devices
The use of wire strung across ponds or other
devices to discourage birds predating on fish stocks is still relatively
common across the proposed SPS WCP area, particularly in the west close to
MPNR. Removing these devices will add value to the ponds for wetland
avifauna.
|
Enhanced
Compensatory Wetland within the proposed SPS WCP / Construction
and Operation Phase |
AFCD
(within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
- |
10.11.3.13
& 10.11.3.26 |
Non-DPs |
Trash Fish Stocking
Stocking shallow ponds with small fish provides a
high-quality feeding resource for many species of bird and other fish-eating
species and may be considered as an additional measure to achieve higher
enhancement value).
This measure will be derived as needed to further enhance the functional value of the ponds. |
Enhanced
Compensatory Wetland within the proposed SPS WCP / Construction
and Operation Phase |
AFCD
(within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
- |
10.11.3.28
10.11.3.34 |
Non-DPs |
Enhanced Wetland for Other Freshwater Wetland Habitats
Under the current wetland enhancement strategy,
about 35 ha of enhanced freshwater wetland habitats shall also be
established within the proposed SPS WCP, alongside the
compensation of ecologically enhanced fishponds.
The
enhanced freshwater wetland habitats would be designed to compensate for
impacts on a like-for-like basis as far as practicable, and could include various habitat types that would support
communities currently utilising impacted freshwater habitats:
Ducks
and Grebes;
Freshwater
Wetland Avifauna;
Other
Wetland-associated Avifauna Species;
Eurasian
Otters; and
Other
Non-Avifaunal Species of Conservation Interest Disturbance impact
from the Project is anticipated to result in EZ and RDZ along the Project
boundary, which is expected to support lower densities of disturbance
sensitive of wildlife, in particular avifauna species. As the species recorded in marsh / reed
habitats tend to be less disturbance-sensitive than species utilizing more
open wetland habitats, the proposed enhanced freshwater wetland habitats
could be considered along these EZ and RDZ, where the remaining areas of the
proposed SPS WCP (outside the EZ and RDZ) can be maximised for ecologically
enhanced fishponds. Upon the establishment of the proposed SPS WCP, it could be able to
accommodate the aforementioned enhanced wetland of
about 288 ha (253 ha of ecologically enhanced fishponds and 35 ha of
enhanced freshwater wetland habitats).
The Government will enhance the ecological function and capacity of
288 ha of wetlands in the proposed SPS WCP with active conservation
management to compensate for the loss in wetland arising from the development of San Tin Technopole, which
would create sufficient environmental capacity to support the compensation
requirement of the Project. |
Enhanced
Wetland within the proposed SPS WCP / Construction
and Operation Phase |
Construction
phase: AFCD as project proponent of SPS WCP; CEDD as works agent Operation
phase: AFCD (within completed phases of SPS WCP handed over to AFCD only) |
|
√ |
√ |
EIAO-TM
|
10.11.3.35 |
Non-DPs |
Habitat Creation and Management Plan
(HCMP)
Details
of the ecologically enhanced fishponds and enhanced freshwater wetland
habitat, including detailed design of habitats, habitat requirement for the aforementioned
target species, details of management practices,
implementation details, as well as the monitoring requirements (e.g., monitoring period, location, frequency, parameters, and
target levels), will be provided in the subsequent HCMP. The
HCMP should be submitted for approval from relevant Government
departments (including AFCD and EPD), at
least three months before the commencement of pond filling works.
|
Enhanced
Wetland within the proposed SPS WCP / Design
Phase |
Design
phase: Project Proponent, in consultation with AFCD (as project proponent)
and CEDD (as works agent) of SPS WCP |
√ |
|
|
- |
10.11.3.36 |
Non-DPs |
Minimising Construction Phase Indirect Impacts on Sites of
Conservation Importance and Associated Habitats
Phasing of pond filling works in San Tin Sam Po Shue area should be adopted. The pond filling works will be phased to tie in with the phased development of the SPS WCP, with a working group formed to coordinate the progress of pond filling and SPS WCP implementation. The pond filling works should also be started from urbanised area towards the wider wetland area (i.e. from the southeast near STEMDC or San Tin Highway towards the northwest) and construction activities should be minimised at any one time, so as to allows gradual migration of wildlife to the wetland habitats northwest to the Project area. Pond filling works should also be conducted in wet season as far as possible when there is a lower abundance of avifauna. In order to reduce the scale of disturbance and the total area of pond filling at the same time, filling of ponds in San Tin / Sam Po Shue should be conducted in multiple wet seasons (at least 2 years or more). |
Project
site / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
- |
10.11.3.37 |
Non-DPs |
Minimising Construction Phase Indirect Impacts on Sites of Conservation
Importance and Associated Habitats
Site
hoarding of about 3 m high should be erected along the works site and works
area before commencement of construction activities, to shield the avifauna
in the nearby wetlands from the disturbance of human activities during
construction phase. Such hoarding
would be non-transparent and superimposing dark patterns or stripes to avoid
the risk of potential bird collision.
|
Project
site / Construction
Phase |
Contractor |
|
√ |
|
- |
10.11.3.38 |
Non-DPs |
Minimising Construction Phase Indirect Impacts via the establishment
of an Eco-Interface
Under the Revised
RODP, an eco-interface area with width of about 35 m was proposed along the
northwest of the Project boundary, between the proposed Project area in San
Tin and the wider pond habitats in San Tin and Sam Po Shue; while another
eco-interface area with width of about 20 m was also proposed along the
east of STEMDC, creating a buffer between the OU(I&T) land use and the
watercourse STEMDC. The
eco-interface would be established in the form of a landscape buffer via
landscape planting, comprising native tree species, shrub mix and riparian
vegetation, and incorporating a gentle slope interface, with an aim to
minimise disturbance from Project area by providing a buffer between the
development and the adjacent wetland habitats and associated fauna.
|
Project
site / Design
and Construction Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
10.11.3.39
10.11.3.41 |
Non-DPs |
Wetland
Enhancement Measure Together with the development of the Project,
enhancement measures would also be implemented to enhance the ecological value
of wetland habitats in the Deep Bay area. Two
management issues at Mai Po Inner Deep Bay Ramsar Site could be addressed to
enhance environmental capacity across the broader North
West New Territories (NWNT) wetland system:
Firstly,
tidal channels that link gei wai in the Mai Po Nature Reserve to the Inner Deep
Bay have become silted up over time, limiting tidal exchange and degrading
the function of habitats within the gei wai.
Improvement of these channels via de-silting can promote tidal
exchange and enhance habitat condition within the gei
wai.
Secondly,
the invasive exotic mangrove Sonneratia sp.
has spread rapidly across mudflat habitats and drainage channels across the
NWNT. Selective clearance of larger Sonneratia stands can help restore wetland
habitats in affected areas. Realising the beneficial effects brought by the
enhancement measures, they are targeted to be commenced as early as
possible. Both enhancement measures
shall be undertaken in the wet season (April September) to minimise
disturbance impacts to overwintering avifauna and hence they are proposed to
be commenced earliest at the start of the 2025 wet season. Details of the enhancement measures (e.g.
details, timeframe and
requirement/frequency of repetition for the enhancement works)
shall be provided in a separate work plan prepared
by the project proponent, and submitted to AFCD for agreement at
least three months prior to the commencement of these works. |
Off-site
enhancement area / Construction
and Operation Phase |
Project
Proponent / Contractor |
√ |
√ |
√ |
- |
10.11.3.42
10.11.3.44 |
Non-DPs |
Improvement of Tidal Channel
Selected tidal
channels could be de-silted. These
channels connect to the sluice-gates of several existing gei
wai, where proposed de-silting works could
potentially enhance the functioning of gei
wai.
De-silting works would be undertaken in the wet season (April
September) by phases to minimise disturbance impacts to overwintering
avifauna. |
Off-site
enhancement area / Construction
and Operation Phase |
Project
Proponent / Contractor |
√ |
√ |
√ |
- |
10.11.3.45
10.11.3.46 |
Non-DPs |
Sonneratia Clearance
Additional
enhancement of the Deep Bay area will be provided by the removal of exotic
mangrove species on mudflat (Sonneratia spp.).
The removal of exotic mangrove species would be undertaken in the wet
season (April September) selectively to minimise disturbance impacts to
overwintering avifauna. |
Off-site
enhancement area / Construction
and Operation Phase |
Project
Proponent / Contractor |
√ |
√ |
√ |
- |
10.11.3.47 |
Non-DP |
Interim Wetland
Enhancement
Interim wetland enhancement measures prior to the
commencement of pond filling works would also be implemented. Suitable ponds in the Inner Deep Bay area
will be identified for implementing interim enhancement works, which may
comprise restoration of abandoned ponds and arrangement of active management
including fish stocking for suitable ponds.
Details of the suitable ponds and interim enhancement works shall be
provided in a separate Interim Wetland Enhancement Plan and submitted for
approval from relevant Government departments (including AFCD and EPD) at
least three months before the commencement of these interim enhancement works.
|
Off-site
interim wetland enhancement area / Construction
Phase |
Project
Proponent / Contractor |
√ |
√ |
|
- |
10.11.2.2,
and 10.11.4.3
10.11.4.4 |
DP7,
Non-DPs |
Impact on Egretries: Mai Po Lung Village (MPLV) Egretry The Revised RODP of
the Project was carefully designed with the aim to preserve the MPLV Egretry, and the vegetation currently used by the
breeding ardeids. An Open Space is
currently proposed to preserve the core
area of the egretry and the vegetation. Detailed design of this Open Space shall
incorporate enhancement features, which may include:
Preservation
of trees currently within the core area of the MPLV Egretry;
Incorporation
of water features within the Open Space area, adjacent to the existing of
MPLV Egretry;
Planting
of mature trees adjacent to the water features, with native species that are
currently used as egretry substratum; and
Maintaining a buffer area between the water features
and the established mature trees from the adjacent proposed land-uses (e.g. logistics storage
and workshop, district cooling system, and traffic roads). The enhancement
measures would be established during the construction phase. Buffer planting along the Open Space could
also minimise potential
indirect disturbance impacts on the egretry from
adjacent proposed land-use and traffic network during operation phase. Under the proposed
Open Space, only low intensity activities would be allowed (e.g. plant
nursery), while other recreational activities (e.g. sports and recreation)
would not be included in the Open Space in order to
minimise the disturbance to the MPLV Egretry. A pre-construction
surveys are necessary to confirm the latest boundary and condition MPLV Egretry before commencement of the construction works.
Any construction activities within the 100 m distance of the egretry (subject to findings of pre-construction survey)
should be subject to seasonal control.
An Egretry Habitat Enhancement and Management Plan including
the details of design plan, site preparation works, works schedule and
management plan should be prepared for approval from
relevant Government departments (including EPD and AFCD) before the
commencement of construction works. Maintenance of
enhancement features suggested above (e.g. preservation and planting of egretry substratum, incorporation of water features, and
maintaining buffer area) shall be implemented during the period of egretry
monitoring. |
Construction
sites in the vicinity of the egretries / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
Guidelines
for Planning and Carrying out Construction Works at Egretries |
10.11.4.10
10.11.4.12 |
DP1,
DP7, Non-DPs |
Minimising Construction Phase Impacts on Egretries Considering the close proximity between the proposed development and both
MPLV Egretry and MPV Egretry,
encroachment into the trees at both egretries shall
be strictly avoided during construction phase (except for the minor
encroachment of the MPLV egretry). The latest
boundary, condition, flight paths of both MPLV Egretry
and MPV Egretry and the associated mitigation
measures should be confirmed by pre-construction surveys before commencement
of the construction works. Potential
disturbance impact on the breeding ardeids shall be further minimised by
establishing a buffer area of 100 m from the footprint of both egretries. In
addition, the boundary of the 100 m buffer area should be updated subject to
the findings of pre-construction survey.
Stringent seasonal control would be implemented within the buffer
area, where construction activities shall be avoided during the ardeid
breeding period (i.e. from March to early September). Construction activities shall be conducted
from late September to February in the following year, unless AFCDs prior
approval on construction method has been obtained and appropriate mitigation
measures have been proposed and adopted.
Tree crown pruning works at the egretries
shall be avoided as best as possible, and where necessary, shall also be conducted and completed outside the ardeid breeding season
to minimise disturbance to any breeding ardeids that may be present. Method Statement on construction activities
near the egretries and necessary tree crown pruning
works shall be submitted to AFCD in advance of the works. Other stringent
control measures shall also be implemented (e.g. establishment of hoarding
and regular auditing). Aside from the
construction activities, any associated temporary works areas (e.g. site
office, stockpiling / material storage area, etc.) shall be strictly
restricted outside the egretries as well. Potential pruning works shall only be
conducted where necessary, limited at overgrown tree branches that may affect
construction activities. |
Construction
sites in the vicinity of the egretries / Design
and Construction Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
Guidelines
for Planning and Carrying out Construction Works at Egretries |
10.11.5.3
10.11.5.5 |
Non-DPs |
Re-provision of
Roosting Substratum for Ha Wan Tsuen Night Roost A re-provision of
roosting area which comprises water features and riparian vegetation shall be
provided before the removal of Ha Wa Tsuen Night
Roost, adjacent to the proposed fisheries research centre under the Revised
RODP. The re-provided roosting
area would comprise mature individuals of native tree species that are
currently used as a roosting substratum.
The incorporation of these features (water features and associated
roosting trees) shall be completed before dry season (October to March),
prior to the arrival of the overwintering birds, in order
to provide suitable roosting opportunities. A pre-construction survey is necessary to
confirm the latest boundary and condition of the night roosts before
commencement of the construction works. Prior to the tree
removal at the existing Ha Wan Tsuen Night Roost, noisy construction
activities within 100 m of the existing Ha Wan Tsuen Night Roost would be
subject to timing control during dry season (October to March) to minimise
indirect disturbance impacts; while upon the tree removal at Ha Wan Tsuen
Night Roost (and the re-provision of roosting substratum at the Fisheries
Research Centre), the same timing control would be implemented within 100 m
of the re-provided night roost. During
dry season (October to March), noisy construction activities (with the use of
PME) within the 100 m buffer area should cease at least an hour before
sunset, and shall commence at least an hour after sunrise on the following
day, making reference to the time of sunrise and
sunset from the Hong Kong Observatory |
Construction
sites, existing night roosts, and re-provision roosting area / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
- |
10.11.5.6
10.11.5.7 |
DP6,
DP7 |
Re-provision of
Roosting Substratum for San Tin Open Storage Area Night Roost Roosting opportunity
shall be provided at the Open Space along
the bank of the diverted and revitalised WC-N8 (STWMDC), approximately 110 m
east of the original night roost. The
reinstated roosting area should instead include mature native tree species
recorded in other night roost, including but not limited to mature Ficus
spp. The re-provision of
roosting area should be completed before dry season (October to March), prior
to the arrival of the overwintering birds, in order to
provide suitable roosting opportunities. A pre-construction survey is
necessary to confirm the latest boundary and condition of the night roosts
before commencement of the construction works. Furthermore,
construction activities within 100 m of the re-provided night roosts of San
Tin Open Storage Area Night Roost shall be subject to timing control during
dry season (October to March) to minimise indirect impacts. Prior to the tree removal at the existing roosting site,
noisy construction activities within 100 m of the existing San Tin Open
Storage Area Night Roost would be subject to timing control during dry season
(October to March) to minimise indirect disturbance impacts; while upon the
tree removal (and the re-provision of roosting substratum along the
revitalised STWMDC), the same timing control would be implemented within 100
m of the re-provided night roost.
During dry season (October to March), noisy
construction activities (with the use of PME) within the 100 m Buffer Area should cease at least an hour before sunset,
and shall commence at least an hour after sunrise on the following day,
making reference to the time of sunrise and sunset from the Hong Kong
Observatory. Monitoring of the re-provided roosting sites (e.g. conditions of the
re-provided tree individuals) shall also be conducted, with maintenance
conducted by the Project Proponent and Contractor during the period of night
roost monitoring. |
Construction
sites, existing night roosts, and re-provision roosting area / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
- |
10.11.5.1
10.11.5.8 |
Non-DPs |
Minimising
Construction Phase Direct / Indirect Impacts on Night Roost The construction
activities and tree felling in Ha Wan Tsuen Night Roost and San Tin Open
Storage Area Night Roost should be allowed only in wet season (April
September) which no roosting individual was recorded in current survey. Re-provision planting of the roosting
substratum both night roosts should also be commenced as early as possible
before the commencement of construction activities that may result in the
loss of both night roosts. In the case where
construction activities or temporary works cannot be avoided during the
overwintering season, As discussed above, in the case where construction
activities or temporary works near the re-provided night roosts cannot be
avoided during the overwintering season (October to March), noisy
construction works within 100 m of the existing night roosts (prior to tree
felling) and re-provided night roosts (upon re-provision) (exact area would
be subject to the pre-construction survey finding and detailed design in the
future) should cease before the peak returning time (an hour before sunset)
of the ardeids and Great Cormorants, and shall commence at least an hour
after sunrise on the following day, making reference to the time of sunrise
and sunset from the Hong Kong Observatory. Monitoring of the re-provided roosting sites (e.g. conditions of the
re-provided tree individuals) shall also be conducted, with maintenance
conducted by the Project Proponent and Contractor during the period of night
roost monitoring. |
Construction
sites, existing night roosts, and re-provision roosting area / Construction
Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
10.11.6.1
10.11.6.3 |
Non-DPs |
Impact on Flight
Paths: MPLV Egretry A Non-Building Area
(NBA) of about 70 m wide is proposed to the northwest from the existing MPLV Egretry. Under the
Project, obstruction of flight paths will also be further minimised by
maintaining flight corridors along the proposed Road D3, allowing connection of flights between the MPLV
and the diverted WC-N8 located towards the northeast, and along the proposed Road L11 towards the west. No tall structures are anticipated above
the proposed Road D3 and Road L11, thus expected to allow flight to and from
the MPLV Egretry, partially coinciding with the
observed Flight Paths. Heights of
associated structures on these corridors shall be limited in
order to allow flight movement. In
order to minimize the disturbance on the flight path along the NBA during
breeding period of the egretry (i.e. from March to
early September) and encourage ardeid usage, the noisy construction works
(with the use of PME) within the 70 m wide NBA should cease at least an hour
before sunset, and shall commence at least two hours after sunrise on the
following day, making reference
to the time of sunrise and sunset from HKO), to
avoid the period of highest utilisation of flight
path. Further disturbances
shall be minimised along the proposed flight paths, by incorporation of
greening features of suitable heights, where appropriate, to minimise visual disturbance
on the ardeids from human activities and further encourage flight usage. |
Construction
sites / Design
and Construction Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
10.11.6.4
10.11.6.5 |
Non-DPs |
Impact on Flight
Paths: MPV Egretry The proposed
eco-interface with provision of greening and wetland habitats is overlapped
with certain flight paths from MPV Egretry, thus
promoting the connectivity and movement corridor of the MPV Egretry and the wider wetland habitats. |
Construction
sites / Design
and Construction Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
10.11.6.6
10.11.6.9 |
Non-DPs |
Maintaining Flight
Corridor Across LMC BCP The Project would
incorporate a flight corridor with width of about 300m. This flight corridor would comprise the
proposed AFCD Fisheries Research Centre (near the
Loop), a few GIC sites (reserved for a pumping
station, HKPF Weigh Station and Customs dog base) and a proposed NBA within I&T sites near STEMDC to
preserve a corridor for flight movement between the east and the west. Minimal building structures with small area
are anticipated at the AFCD Fisheries Research Centre
and the GIC sites, with building height of not more than 15 mPD. No
aboveground building structures would be established above the STEMDC and the
NBA. Noisy construction works (with the use of PME) within the 300 m wide
flight corridor should
cease at least an hour before sunset, and shall
commence at least two hours after sunrise on the following day
(making reference to the time of sunrise and sunset from HKO) during dry season (October to March) to avoid
the period of highest utilisation of the flight corridor. To further promote
flight movement, stepping height of the building structures adjacent to the flight
corridor would also be implemented, with building height of not more than
+35mPD proposed on both north and
south sides of the flight corridor to encourage usage of this corridor and minimise
potential obstruction impact. |
Construction
sites / Design
and Construction Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
10.11.8.2
10.11.8.4 |
Non-DPs |
Woodland Compensation Compensatory
planting would be performed for the loss of the 1.64 ha woodland of moderate
value at an off-site woodland compensation site. A suitable area was identified near the
compensatory woodland for the Lok Ma Chau Loop Project. Native species of different growth form
with high market availability are preferred for compensatory planting. Compensatory planting would be provided sequentially
upon the completion of works within the Project area. To facilitate successful establishment of
the compensatory woodland, a detailed Woodland Compensation Plan should be
prepared by local ecologists / botanist with
at least 5 years of relevant experience.
The plan should include implementation details, management requirement and monitoring
requirements (e.g., methodology,
schedule, frequency of
monitoring, and monitoring parameters), and should
be submitted to relevant Government departments (including AFCD and EPD) for
approval at least two months before commencement of the planting. |
Off-site
woodland compensation area / Design,
Construction and Operation Phase |
Project
Proponent / Design stage consultant / Contractor & Qualified Botanist /
Ecologist |
√ |
√ |
|
EIAO-TM |
10.11.8.2
10.11.8.4; EM&A
Manual 9.3.6 |
Non-DPs |
Upon the completion
of planting, monitoring and maintenance works (e.g.,
irrigation, weeding, pruning, control of pests and diseases, replacement
planting and repair of damage) of the compensatory woodland should be
implemented. Upon the completion of compensatory planting,
a three-year monitoring by local ecologist / botanist
with at least 5 years relevant experience is recommended to ensure proper
establishment of this compensatory woodland.
The monitoring frequency should be monthly within the first year
upon the establishment of the compensatory planting, and bi-monthly in the
next two years of the monitoring. |
Off-site
woodland compensation area / Construction
and Operation Phase |
Project
Proponent / Contractor & Qualified Botanist / Ecologist |
|
√ |
√ |
- |
10.11.9.1
10.11.9.3 |
Non-DPs |
Avoiding Direct Loss
of Species of Conservation Importance A few individuals of
the flora species of conservation importance were recorded at areas which
would be zoned as Green Belt (GB) land use under the Revised RODP. As habitat and vegetation would be
preserved at these GB zones, direct impact to the Incense Trees would be
avoided. Direct impact on other flora
and fauna species of conservation importance shall be further avoided /
minimised by mitigation measures such as pre-construction surveys and
transplantation / translocation / nest control measure of the species. |
Construction
sites / Design
and Construction Phase |
Design
stage consultant / Contractor & Qualified Ecologist |
√ |
√ |
|
EIAO-TM |
10.11.9.4
10.11.9.5 |
Non-DPs |
Flora Species of Conservation Importance Transplantation is
recommended as far as possible for Cycad-fern and Incense Tree to minimise
the direct impact to this species.
Prior to the commencement of the construction phase, a detailed
vegetation survey would be conducted by a qualified botanist / ecologist to
confirm the locations and health condition of Cycad-fern and Incense
Tree. All the healthy individuals
suitable for transplantation would be identified and rescued. They would be transplanted to suitable
receptor site outside Project area, ideally at wooded habitats such as mixed
woodland, plantation, shrubland or woodland outside the Project area. Pre-construction survey, screening /
selection of receptor site(s) and preparation of a Protection and Transplantation Proposal describing details
of the transplantation methodologies would be prepared by qualified botanist
/ ecologist and submitted for approval prior to transplantation. Mitigation for Luofushan Joint-fir is
recommended in compensation manner.
Seedling planting of Luofushan Joint-fir is recommended in receptor site(s). However, it should be planted in low
density to reduce its shading stress to the receptor site(s) in future. Pre-construction survey, collection of
seeds, screening / selection of receptor site(s) and preparation of a Protection and Seedling Planting Proposal should
be prepared by qualified botanist / ecologist for approval. |
Construction
sites / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor & Qualified Botanist /
Ecologist |
√ |
√ |
|
EIAO-TM |
10.11.9.4
10.11.9.5; EM&A
Manual 9.3.7 |
Non-DPs |
Upon the
transplantation / seedling planting of the identified individuals, a
three-year post-transplantation / post-seedling planting monitoring should be
implemented to monitor the health conditions and survival of the transplanted
individuals. The suggested monitoring
frequency should be monthly within the first year upon the establishment of
the transplantation, and bi-monthly in the next two years of the monitoring. |
Receptor
site of flora species of conservation importance (e.g., off-site woodland
compensation area) / Construction
and Operation Phase |
Project
Proponent / Contractor & Qualified Botanist / Ecologist |
|
√ |
√ |
- |
10.11.9.6
10.11.9.12 |
Non-DPs |
Fauna Species of Conservation Importance Breeding
Ground of Avifauna Species of Conservation Importance In
order to avoid direct injury
to the breeding pairs, chicks and eggs, nest control measures should be
implemented in non-breeding season (late August to early February) to
discourage breeding behaviour within Project area prior to construction
works. To avoid nesting of
Little Ringed Plover in drained ponds, drained ponds should be covered by
black pond liner immediately to discourage Little Ringed Plover from nesting
on the drained ponds. To discourage
nesting of White-shouldered Starling, box attached to electric pole should be
sealed / removed in non-breeding season.
To discourage nesting of White-throated Kingfisher, the mud wall and
mud wall tunnels within Project area on Ngau Tam Shan should be sealed in
non-breeding season. Prior to nest
control measures, the drained pond, box and mud wall
tunnel should be checked carefully by qualified ecologists to ensure no
avifauna / eggs are present. Preparation
of Nest Control Proposal,
pre-construction survey and the nest control measures mentioned should be
conducted by qualified ecologist with at least 10 years relevant experience
to ensure the control measures and the subsequent works would not injure any
breeding pairs, chicks or eggs. Freshwater
Fauna Species of Conservation Importance Pre-construction
survey would be conducted for Rose Bitterling, followed with measures to capture and translocate them to suitable habitat(s)
nearby, which are free from development pressure. Qualified ecologist with freshwater fauna
experience with at least 5 years relevant experience should prepare a
detailed Translocation Proposal for approval.
For example, considering the Rose Bitterling has a spawning symbiosis
relationship with Chinese Pond Mussel, translocation of Chinese Pond Mussel
should also be included in the scope of translocation; while mud should also
be deposited to support the mussel, etc.
The potential receptor sites should be in similar size compared to the
original fishponds (approximately 0.42 ha / pond). The abiotic (temperature, pH, salinity,
level of dissolved oxygen, turbidity and pollution)
and ecological (vegetation, presence of invasive fish / predators) parameters
of receptor site(s) should be examined prior to translocation. Screening and selection of potential
receptor sites would be included in the Translocation Proposal, conducted by
qualified ecologist before the commencement of construction phase. Capture and
translocation are recommended two freshwater crab species of conservation
importance (Cryptopotamon anacoluthon
and Somanniathelphusa zanklon). Pre-construction survey focusing the
locations where they were previously recorded in Project area should be
conducted, identified individuals should be captured and translocate to
suitable receptor sites. Preparation
of Translocation Proposal, screening / selection of receptor sites and
capture release process should be conducted by qualified ecologist with
relevant experience. Herpetofauna
Fauna Species of Conservation Importance Translocation is
suggested for amphibian species of conservation importance. Similar capture release approach would
also be adopted for amphibians. Both
adults and tadpole shall be included in the scope of translocation. The pre-construction survey, capture and
release should be conducted during night-time in wet season when amphibian is
relatively active to maximise capture rate.
Preparation of Translocation Proposal, screening / selection of
receptor sites and capture release process should be conducted by qualified
ecologist with relevant experience. |
Construction
sites / Design
and Construction Phase |
Project
Proponent / Design stage consultant / Contractor & Qualified Ecologist |
√ |
√ |
|
EIAO-TM |
10.11.9.9
10.11.9.13; EM&A
Manual 9.3.8 |
Non-DPs |
Upon
the translocation of the identified individuals, a three-year
post-translocation monitoring should be implemented to investigate the
survival of translocated individuals as best as possible. The
suggested monitoring frequency should be monthly within the first year upon
translocation, and bi-monthly in the next two years of the monitoring. |
Receptor
site of fauna species of conservation importance / Construction
and Operation Phase |
Project
Proponent / Contractor & Qualified Ecologist |
|
√ |
√ |
- |
10.11.9.4
10.11.9.12 |
Non-DPs |
Post-transplantation,
post-plantation and post-translocation monitoring programs for the mentioned
flora / fauna species are required for determining the success of
mitigation. Direct observation and
counting, mark-recapture and active search would be potential methodology for
the monitoring programs depend on the target species. Detailed methodology, schedule and
frequency of monitoring program would be provided in the corresponding
Transplantation / Translocation Proposal(s). |
Construction
sites / Construction
and Operation Phase |
Project
Proponent / Design stage consultant / Contractor & Qualified Ecologist |
|
√ |
√ |
EIAO-TM |
10.11.9.15 |
Non-DPs |
Eurasian Otter While no significant ecological impacts are anticipated on the low
occurrence of Eurasian Otters, a conservative approach has been adopted, and
their potential movement corridor across the Project area was considered
under the Revised RODP with the inclusion of a wildlife corridor (detailed in
Section 10). Further
pre-construction site check will be included under a conservative approach on
this highly elusive species. |
Construction
sites / Construction
Phase |
Contractor
& Qualified Ecologist |
√ |
√ |
|
EIAO-TM |
10.11.10.1 |
All
DPs and Non-DPs |
Minimising Direct
Injury / Mortality of Wildlife Proper
screening (e.g. hoarding or barrier) would be provided to restrict
construction activities within the Project sites, to minimise
potential direct injury to nearby wildlife by confining the construction
activities, and to avoid the wildlife from accidentally entering the Project
sites. |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
- |
10.11.12.1
10.11.12.2 |
All
DPs and Non-DPs |
Minimising
Construction Disturbance to Habitats, Sites of Conservation Importance and
Wildlife Mitigation measures
should be implemented to minimise the disturbance impacts (e.g. noise, glare and dust) to the adjacent habitats and their
associated wildlife arising from the construction activities, including but
not limited to the following:
Noise
mitigation measures by effective placing of site hoarding, temporary noise
barriers and material stockpiles where practicable as screening, shut down of
machines and plants that are in intermittent use, and the use of quality
power mechanical equipment (PME) to limit noise emissions at source. Machines and plant known to emit strong
directional noise should, wherever practicable, be orientated so that the
noise is directed away from the nearby habitats. QMP and other machines and plants should be
covered by noise enclosure to further reduce noise impact;
A
balance between lighting for safety, and avoiding excessive lighting can be
achieved through the use of directional lighting to avoid light spill into
sensitive areas (e.g. construction activities near the egretries
and ardeid night roosts), hoarding provision, and control night-time lighting
periods, particularly for the works site(s) located in proximity, and during
peak season of activities (e.g. breeding season of the egretries,
peak roosting season of ardeids at night roosts during dry season), hence
minimising the potential indirect impact on the community of the breeding and
night-roosting ardeids;
Dust
suppression measures (such as regular spraying of haul roads, proper storage
of construction materials, covering trucks or transporting waste in enclosed
containers, and environmental control measures as stipulated in the Air
Pollution Ordinance (Construction Dust) Regulation) to avoid and minimise
emission and dispersal dust, which would cover vegetation and potentially
discourage usage of nearby wildlife; and For construction
activities at pond habitats within the Wetland Conservation Area, percussive
piling works and demolition using excavator mounted breakers should be
avoided from November to March. Where
such construction activities are unavoidable, additional agreement with
relevant Government departments (including EPD and AFCD) should be sought
prior to the commencement of works. |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
Noise Control Ordinance (NCO) Air Pollution
Ordinance (Construction Dust) Regulation) |
10.11.12.2 |
All
DPs and Non-DPs |
Good site practices
should be strictly followed to avoid / minimise adverse impacts arising from
the construction activities.
Recommendations for good site practices during the construction phase
include:
Nomination
of approved personnel, such as a site manager, to be responsible for
implementation of good site practices, arrangements for waste collection and
effective disposal to an appropriate facility;
Training
of site personnel in site cleanliness, concepts of waste reduction, reuse and
recycling, proper waste management and chemical waste handling procedures;
Provision
of sufficient waste reception/ disposal points, and regular collection of waste;
Adoption
of appropriate measures to minimise windblown litter and dust during
transportation of waste by either covering trucks or by transporting wastes
in enclosed containers;
Provision
of regular cleaning and maintenance programme for drainage systems, sumps and
oil interceptors;
Adoption
of a recording system for the amount of wastes
generated, recycled and disposed (including the disposal sites); and Preparation of Waste
Management Plan (WMP), as part of the Environmental Management Plan (EMP). |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
WDO Public Cleansing and
Prevention of Nuisances Regulation (Cap. 132BK) |
10.11.12.3 |
All
DPs and Non-DPs |
Minimising Water
Quality Impacts Good site practices
during the construction phase should be adopted to avoid any pollution
entering any nearby watercourses.
Practices to minimise surface run-off and to reduce suspended solid
levels should be undertaken during construction:
Surface
run-off from construction sites should be discharged into storm drains via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sedimentation basins;
Open
stockpiles of construction materials (e.g. aggregates, sand and fill
material) on sites should be covered with tarpaulin or similar fabric during rainstorms;
General refuse
and construction waste should be collected and disposed of in a timely and
appropriate manner;
Drainage
arrangements should include sediment traps to collect and control
construction run-off;
Silt removal
facilities, channels and manholes should be maintained, and the deposited
silt and grit should be removed regularly, at the onset of and after each
rainstorm to prevent local flooding;
All works and
storage areas should be restricted to the site boundary;
All vehicles
and plant should be cleaned before they leave a construction site to minimise
the deposition of earth, mud, debris on roads; and Regular check of the construction boundary to avoid
unmitigated impacts imposed on nearby watercourse. |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
WPCO ProPECC
PN 2/23 EIAO-TM |
Construction and Operation Phase |
||||||||
10.11.10.2 |
All
DPs and Non-DPs |
Minimising Bird
Collision The potential bird
collision should be avoided by using low reflective materials (e.g. tinted
glass, low reflective window film) and appropriate architectural features on
building structures c-transparent panels should also be used as noise
enclosure, as well as adopting non-glaring tinted materials, or superimposing
dark patterns at the majority of glazing along
barriers to avoid and minimise bird mortality from collision. |
Construction
sites / Design,
Construction and Operation Phase |
Design
stage consultant / Contractor / Operator |
√ |
√ |
√ |
Guidelines on Design of Noise Barriers Practice Notes No. BSTR/PN/003 (Revision E) Noise Barriers with
Transparent Panels |
10.11.12.1
10.11.12.2 |
Non-DPs |
Wildlife Corridor Under the Revised RODP, wildlife corridors have been
incorporated to provide opportunity for ecological linkage between STEMDC, Ha
Wan Tsuen and Lok Ma Chau. This
wildlife corridor should comprise underground sections (concrete underpasses
across proposed roads) and aboveground sections which
would be provided within the AFCD Fisheries Research Centre, to provide
connection between the AFCD Fisheries Research Centre and the STEMDC. Indicative locations of these proposed wildlife corridors are presented in Figure 10.10A, which would
provide opportunity for wildlife movement across the area, in
particular the mammal species currently recorded, as well as potential
usage of Eurasian Otters. Revitalisation works
would be conducted along the STEMDC to provide eco-friendly habitats for
wildlife including target mammal species.
Continuous fencing of suitable height for mammal barrier
should be erected along the wildlife corridor in order to
prevent roadkill and guiding wildlife into the underpasses. Wildlife corridors
shall be considered to provide ecological linkage between the various GB
under the Revised RODP, targeting mammal species of conservation importance
recorded including East Asian Porcupine, Leopard Cat and Red Muntjac. Details of the proposed wildlife corridor
shall be formulated in detailed design in later stages, and
shall be agreed with relevant Government departments (including AFCD
and EPD) prior to commencement of construction works. It is expected that, provision of wildlife
corridor can maximise the ecological function of preserved GB and mitigate
the habitat fragmentation impact.
Potential usage of the wildlife corridor should also be recorded (e.g.
with the use of camera traps). Maintenance work
such as weeding, screening, and repairing broken fencing / structure should
be conducted, where necessary, during the period of monitoring of the
wildlife corridor conditions |
Construction
sites / Design,
Construction and Operation Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
- |
10.11.13.1 |
Non-DPs |
Eco-Interface The eco-interface
could provide opportunities for further enhancement measure to promote
wildlife usage. Installation of
artificial nest boxes and bat boxes are recommended in eco-interface areas
to attract avifauna and bat species including species of conservation
importance such as White-shouldered Starling and Japanese Pipistrelle. Location and selection of nest box and bat
box would be subject to detailed design. |
Construction
sites / Design,
Construction and Operation Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
|
10.11.13.2 |
DP6
and DP7 |
River Revitalisation Major watercourse
including WC-N3 and WC-3 (i.e. STEMDC) and WC-N8 (i.e. STWMDC) would be
reinstated and revitalised, while details of the revitalisation would be
available after detailed design.
Opportunities for ecological enhancement (e.g. bioengineering,
creating meanders) would be explored to improve its ecological value. Provision of natural substrate that would
encourage colonisation of flora and freshwater fauna in the bottom and banks
of the revitalised watercourses would be considered, subject to detailed
design of the proposed revitalisation measures. Vegetation species to be planted along the
riparian zone would be selected on the basis that it would benefit the
wildlife recorded in the vicinity.
Fauna species recorded from recent surveys and previous studies (e.g.
foraging ground for avifauna species, drinking site for bat species) would be
potentially benefit from the revitalised watercourse.
Maintenance works (e.g.
weeding, de-silting, replacement planting, repair of damage, etc.) should
also be conducted as necessary. |
Construction
sites / Design,
Construction and Operation Phase |
Project
Proponent / Design stage consultant / Contractor / DSD |
√ |
√ |
√ |
- |
10.11.13.3 |
Non-DPs |
Enhanced
Connectivity at Green Belts With the inclusion
of the proposed wildlife corridors, enhanced connectivity is anticipated
between Green Belts to benefit wildlife usage. Other Green Belts were also retained under
the Revised RODP. While some Green
Belts on the southern portion of the Project area was not recorded with particular mammal species of conservation importance (e.g.
GB.3.1 and GB.5.5), similar underpass structures are proposed to connect
these Green Belts in order to provide enhanced connectivity for general
wildlife (e.g. future urban wildlife within the Revised RODP). No specific ecological monitoring would be
required for this enhancement feature. |
Construction
sites / Design,
Construction and Operation Phase |
Project
Proponent / Design stage consultant / Contractor |
√ |
√ |
|
- |
10.11.13.4 |
All
DPs and Non-DPs |
Greening Opportunity
Greening
opportunities should be explored to promote the overall habitat quality and
ecological connection. Native tree,
shrub and herb species should be considered as far as possible, with
consideration of market availability, for landscape planting and buffer
planting in the Project area and Project boundary. Furthermore, native host plants and nectar
plants should preferentially be considered in the planting plan to provide a
butterfly-friendly environment. Beside
planting host and nectar plant for attracting butterfly, Livistona chinensis could also be planted to create favourable roosting
habitat for Short-nosed Fruit Bats recorded in the present study, and native
fruits trees with food sources (e.g. Ficus
microcarpa, F.
subpisocarpa, F. variegata, Dimocarpus longan, Clausena lansium) be
planted to attract birds. Buffer
planting together with nectar plants and host plants is highly recommended
especially in the south of Pang Loon Tei, close to CA in the hillside, where
a high diversity of butterfly species was recorded. |
Construction
sites / Design,
Construction and Operation Phase |
Design
stage consultant / Contractor |
√ |
√ |
|
- |
Fisheries Impact |
||||||||
11.7.1.1 |
DP1, DP6, DP7, Non-DPs |
Maintaining Bund
Stability During the
construction stage, all ponds to be removed (including ponds partially
encroached by the Project boundary) shall be isolated and not connected to
any existing watercourse. The pond
would then be drained before filling up these areas or before commencement of
any excavation and construction works.
To maintain bund stability of remaining adjacent ponds, a layer of
shoring or sheet pile wall should be erected along the site boundary adjacent
to fishponds. In addition, the shoring
/ sheet pile wall should have grouting or a grout curtain to avoid water
seepage from the fishpond to the excavation area. |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
- |
11.7.1.2 11.7.1.3 |
DP1, DP6, DP7, Non-DPs |
Minimisation of
Potential Water Quality Impacts Mitigation measures
and good site practices should be implemented during the construction phase,
as proposed in Section 5 (e.g.
proper covering of construction debris and stockpiling of material to avoid
runoff into the ponds), to further minimise potential water quality impact on
the ponds adjacent to the Project boundary.
Surface drainage system shall also be provided to collect road run-off
during the operation phase of the Project.
Examples of mitigation measures for potential water quality impact include: Control of Site
Run-off
Implementation
of Best Management Practices (BMPs), following the guidelines for handling
and disposal of construction site discharges detailed in ProPECC
PN 2/23 "Construction Site Drainage";
Controlling
surface run-off from construction site into storm drains via adequately
designed channels, earth bunds or sand bag barriers,
directing the runoff to sand / silt removal facilities such as sand traps,
silt traps and sedimentation basins;
Minimising
soil excavation in wet season (April to September), or where impracticable,
proper covering of temporarily exposed slope surfaces, while intercepting
channels should be provided along the crest / edge of excavation;
Proper
covering of open stockpiles of construction materials during rainstorms (e.g.
with tarpaulin or similar fabric). Control of Other
Construction-Related Activities
All
vehicles and plants should be cleaned before they leave the construction site
to minimise the deposition of earth, mud and debris in surrounding areas;
Acidic
wastewater generated from acid cleaning, etching, pickling and similar
activities should be neutralised to within the pH range of 6 to 10 before
discharging into foul sewers. If there
is no public foul sewer in the vicinity, the neutralised wastewater should be
tankered off site for disposal into foul sewers or
treated to a standard acceptable to storm drains and the receiving waters;
The
Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste)
(General) Regulation, should be observed and complied with for control of
chemical wastes. The Contractor is
also recommended to develop management procedures for chemicals used and
prepare an emergency spillage handling procedure to deal with chemical
spillage in case of accidents. |
Construction
sites / Construction
Phase |
Contractor |
|
√ |
|
ProPECC
PN 2/23 WDO Waste Disposal
(Chemical Waste) (General) Regulation EIAO-TM |
11.7.2.3 11.7.2.4 |
Non-DPs |
Fisheries Compensation
Requirement and Location The requirement of
fisheries compensation mainly arises from the direct permanent loss of active
fishponds (which support existing aquaculture activities and production), and
the permanent loss of inactive fishponds (with potential value to support
future aquaculture activities upon conversion). The Government will introduce a suite of mitigation
measures to enhance the fisheries resources (e.g. fisheries activities and production, culture
area and aquaculture potential etc.) of the proposed SPS WCP with a view to compensate
for the loss of fishponds arising from the development of the San Tin
Technopole as well as making an overall improvement to the utilisation of
fisheries resources for aquaculture and promoting sustainable development of
the industry in the long run. The Government will enhance the fisheries resources
of 40 ha of land in the SPS WCP, including incorporation of modernised
aquaculture, to compensate for the loss in fisheries resources arising from
the development of San Tin Technopole. The Government will
reserve 40 ha of land in the proposed SPS WCP as a fisheries enhancement
area, in which the fisheries resources will be enhanced by
incorporation of modernised aquaculture and
proper planning and management of aquaculture activities therein. The fisheries enhancement area shall be
delineated separately from the ecologically enhanced fishponds, of which
the purpose would conflict with aquaculture activities for food fish
production since the ecologically enhanced fishponds mainly serve to
provide ecological enhancement and attract foraging birds and other
wildlife. |
Fisheries
compensation area within the proposed SPS WCP / Construction
and Operation Phase |
Construction
phase: AFCD as project proponent of SPS WCP; CEDD as works agent Operation
phase: AFCD |
|
√ |
√ |
EIAO-TM |
11.7.2.5 11.7.2.6 |
Non-DPs |
Development of
Modernised Aquaculture The proposed
fisheries enhancement area shall utilise existing fishponds, abandoned
fishponds, and brownfield areas within the proposed SPS WCP as far as
possible, and shall be actively managed for modernised aquaculture,
comprising both indoor and outdoor facilities, where aquaculture activities
and fisheries production are generally anticipated to be multiplied upon
establishment. The aforementioned measures
would improve both the yield and the quality of aquaculture production,
promoting the sustainable development and modernization of the fisheries
industry. Modernised
aquaculture generally refers to intensive high-density aquaculture
activities, indoor or outdoor, with the adoption of innovative green
technologies, such as recirculating aquaculture system (RAS),
compartmentalisation, remote real-time environmental monitoring, species
selection, ecological polyculture, nutrition management, disease prevention
and health management, etc., that create water bodies and environmental
conditions suitable for fish growth under high-density stocking conditions. |
Fisheries
compensation area within the proposed SPS WCP / Operation
Phase |
AFCD
as project proponent of SPS WCP |
|
|
√ |
|
11.7.2.10 11.7.2.11 |
Non-DPs |
Establishing the
AFCD Fisheries Research Centre Proper technical
support would ensure the proper implementation of these practices to enhance
actual fisheries aquaculture production. As such, under the Project, an AFCD
Fisheries Research Centre shall be established at a location near the Loop to
bridge the technical gap by providing support to the modernised aquaculture
that is currently practised only in a limit extent in Hong Kong. Details of layout and design are subject to
AFCDs approval on the site requirement in the design and construction stage. The proposed AFCD
Fisheries Research Centre shall be implemented with accorded priority under
the initial phase of the Project, for it is indispensable in serving a vital
role in the provision of mitigation measures by promoting modernised
aquaculture, conducting aquaculture research, and transferring modernised
aquaculture techniques to local fish farms, thus facilitating the
transformation and upgrading of the industry through technological
advancement and improving aquaculture activities in the area. Furthermore, the
proposed AFCD Fisheries Research Centre would be implemented under the
initial phase of the Project, while the majority of the fishpond loss in San
Tin and Sam Po Shue would occur during the main phase of the Project (refer
to Appendix 2.1 for development
phasing plan). With the early
establishment of the Fisheries Research Centre, early enhancement of
aquaculture production and activities would be possible, thus minimising
fisheries impact before the establishment of fisheries enhancement area in
the proposed SPS WCP. |
OU(I&T)6
site in the northern portion of the Project area, southwest to the Loop / Construction
and Operation Phase |
Construction
phase: AFCD as project proponent of Fisheries Research Centre; CEDD as works agent Operation
phase: AFCD |
|
√ |
√ |
|
11.7.2.13 |
Non-DPs |
Proper Planning of
Aquaculture Activities in the proposed SPS WCP The compensation
strategy within the proposed SPS WCP shall include proper replanning of
fishpond areas and wetland habitats within the SPS WCP, incorporating
suitable modernised aquaculture technology and management practice in
accordance with the environmental constraints and the purpose of aquaculture
operation, and centralising the same types of aquaculture activities in the
same area, etc. Details of the
compensation strategy would be further formulated in later detailed studies
of the proposed SPS WCP project. |
Fisheries
compensation area within the proposed SPS WCP / Operation
Phase |
AFCD
as project proponent of SPS WCP |
|
|
√ |
|
Impact on Cultural Heritage |
||||||||
12.5.4.1 |
DP2, Non-DPs |
Cartographic
and Photographic Record Preservation by record must be carried out before
the demolition of Tin Tak Heroes Temple, Mai Po Lung Vegetable Marketing
Co-operative Society Ltd. and Sun Tin Vegetable Marketing Co-operative
Society Ltd..
A
comprehensive record through 3D scanning, video recording and cartographic
and photographic recording should be conducted by the project proponent of
subsequent developer(s) prior to any construction works. A copy of these records should be provided
to Antiquities and Monuments Office (AMO) for record purpose and future use,
such as research, exhibition and educational programmes. |
Construction sites / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM
Guidance Note on
Assessment of Impact on Sites of Cultural Heritage in Environmental Impact
Assessment Studies
(GCH-EIA)
Hong Kong Planning Standards and Guidelines (HKPSG) Guidelines
for Cultural Heritage Impact Assessment (GCHIA) |
12.5.4.2-12.5.4.7 |
DP1,
Non-DPs |
Monitoring
of ground-borne vibration, tilting and ground settlement Monitoring of ground-borne vibration, tilting and
ground settlement, shall be employed for Entrance Gate, Enclosing Walls and
Shrine, Yan Shau Wai (HBN186) during the site formation and construction
phases. The monitoring should be incorporated with a set of Alert, Alarm and
Action (3As) system strictly following AMOs monitoring requirements for
grade 3 historic building. The actual 3As criteria should be agreed with the
AMO prior to the commencement of construction works. A monitoring proposal, including checkpoint
locations, installation details, response actions to be taken when reaching
each of the Alert/ Alarm/ Action (3As) levels and frequency of monitoring
should be submitted to AMO and relevant stakeholder(s) for consideration
before commencement of the works.
Prior agreement and consent should be sought from the owner(s),
stakeholder(s) and relevant Government department(s)
for the installation of monitoring points before commencement of the
works. Record of monitoring should be
submitted regularly to AMO during the construction. AMO should be alerted in case any
irregularities are observed. Monitoring of ground-borne vibration, tilting and
ground settlement is also proposed to be employed for Yeung Hau Temple (San
Tin) (MPT01) and Structure between No. 5 and No. 7, Shek Wu Wai (SWW01)
during the site formation and construction phases. The monitoring should be
incorporated with a set of Alert, Alarm and Action (3As) system strictly
following the requirements set out in Practice Note for Authorized Persons,
Registered Structural Engineers and Registered
Geotechnical Engineers - Ground-borne Vibrations and Ground Settlements
Arising from Pile Driving and Similar Operations (PNAP APP-137) on
vibration-sensitive and dilapidated buildings. If the alert level is exceeded, the
monitoring frequency should be increased. If the alarm level is exceeded, the
design of the construction may have to be amended. If the action level is
exceeded, all works should be stopped. The actual 3As criteria shall be
further confirmed via an assessment on the effects of ground-borne
vibrations, settlements and tilting on MPT01 and SWW01. Prior agreement and consent should be sought from
the owner(s), stakeholder(s) and relevant Government
department(s) for the installation of monitoring points on the building
before commencement of the works.
Record of monitoring should be submitted regularly to the Buildings
Department during the construction under Buildings Ordinance. Buildings
Department should be alerted in case any irregularities are observed. Seven other identified items may experience impacts
of ground borne vibration, tilting and settlement, namely Gurkha Cemetery
(BH03), Mans Boundary Stone
(BH06), Grave of Man Lun Fung ("麒麟吐玉書) (BH07), Grave of
Man Chung Luen (BH08), Grave of Man Chu Shui (BH10), Grave of Mrs Man Leung (BH11) and Grave of Chong Yin Kei
(BH12). With an aim to define the
vibration limit and to evaluate if ground-borne vibration, tilting and ground
settlement monitoring and structural strengthening measures are required during
construction phase, a baseline condition survey and baseline vibration impact
assessment should be conducted for these non-building structures by a
qualified building surveyor or qualified structural engineer during
pre-construction stage of the proposed developments. This is to ensure the construction
performance meets with the vibration standard stated in the EIA report. |
Construction sites / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM
Buildings Ordinance |
12.5.4.8-12.5.4.9 |
DP1,
Non-DPs |
Safe Access The entrance door of Yeung Hau Temple (San Tin)
leads directly to the Project boundary.
A safe access route shall be maintained for visitors during the
construction stage. There would be a temporary change of access to
Gurkha Cemetery, Grave of Man Lun Fung ("麒麟吐玉書), Grave of Man
Chung Luen, Grave of Man Chu Shui and Grave of Mrs
Man Leung during the construction phase.
A safe access route to these burial grounds should be maintained for
conducting any mitigation measures, in particular during
Ching Ming Festival, Chung Yeung Festival and Purkha Divas. |
Construction sites / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
12.5.4.10 |
Non-DPs |
Protective Barrier The contractors
should enforce protocol to forbid any light machinery, such as handheld
jackhammer, or heavy machinery to come into direct contact with Yeung Hau
Temple (San Tin),
which is located right next to the Project boundary. Physical protective barriers/ covers or
intervention/cushioning materials, including but not limited to covering or
sheltering, shall be provided during the proposed construction works to
separate the works areas from the structure.
No piling works shall be allowed within the protective zone. No worker or any construction related
equipment(s) and material(s) should trespass the protective zone. The
contractor should propose the actual extent of the protective zone and
suitable protective covering materials to the satisfaction of AMO prior to
the commencement of the proposed construction works. |
Construction
sites / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
12.5.4.11 |
Non-DPs |
Dust Suppression Implementation of mitigation measures in the Air
Pollution Control (Construction Dust) Regulation, dust suppression
measures and good site practice should be observed by the project proponent
on Yeung Hau Temple (San Tin) and Grave of Chong Yin Kei during the
construction phase. |
Construction sites / Construction Phase |
Project Proponent |
|
√ |
|
EIAO-TM Air Pollution Control (Construction Dust) Regulation |
12.6.7.1 |
DP1, DP2, Non-DPs |
Archaeological Watching Brief is recommended to be
carried out in Shek Wu Wai Archaeologically Sensitive Area (ASA) and Mai Po
Lung (South) ASA should works involve soil disturbance occurred (such as site
formation) during the construction phase.
The project proponent or future subsequent developer(s) should employ
an archaeologist who must obtain a Licence
to Excavate and Search for Antiquities from the Antiquities Authority
prior the commencement of the fieldworks.
The scope, methodology and programme of the
archaeological survey shall be agreed with AMO. |
Construction sites / Construction Phase |
Project
Proponent |
|
√ |
|
EIAO-TM |
12.6.7.2-12.6.7.4 |
DP1, DP2, DP5, Non-DPs |
Further archaeological survey at later stages after
land resumption but before site formation works is recommended for Hop Shing
Wai ASA, Mai Po ASA, Siu Hum Tsuen (West) ASA, Siu Hum Tsuen (East) ASA and
Pang Loon Tei ASA. The survey shall be
conducted by an archaeologist who must obtain a Licence
to Excavate and Search for Antiquities from the Antiquities Authority
prior the commencement of the fieldworks.
The scope, methodology and programme of the
archaeological survey shall be agreed with AMO. |
Construction sites / Construction Phase |
Project
Proponent |
|
√ |
|
EIAO-TM |
12.6.7.8 |
All DPs and Non-DPs |
If antiquities or supposed antiquities under the
Antiquities and Monuments Ordinance (Cap. 53) are discovered, the project
proponent is required to inform AMO immediately for discussion of appropriate
mitigation measures to be agreed by AMO before implementation by the project
proponent to the satisfaction of AMO. |
Construction sites / Construction Phase |
Project
Proponent |
|
√ |
|
EIAO-TM
Antiquities and
Monuments Ordinance |
Hazard to Life |
||||||||
13.9.1.1 |
N/A |
Since hazard to life issue would not be anticipated, no mitigation measure
is considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Landscape and Visual Impact |
||||||||
Table
14.9 |
Non-DPs |
Provision
of Wildlife corridor where appropriate and applicable (DM1) -
Opportunity
for ecological linkage is proposed at below location
-
1)
Between STEMDC, Ha Wan Tsuen and Lok Ma Chau should be provided for target
mammal species via culvert / constructed wetland in order
to prevent roadkill and guiding wildlife into the underpasses. -
2)
Provide ecological linkage between the various GB under the Revised RODP,
targeting mammal species of conservation importance -
Details
of the proposed wildlife corridor shall be formulated in detailed design in
later stages, and shall be agreed with relevant
authorities (e.g. AFCD and EPD) prior to commencement of construction
works. It is expected that, provision
of wildlife corridor can maximise the ecological function of preserved GB and
mitigate the habitat fragmentation impact. -
To
enhance visual and air permeability For further details,
refer to Section 10.11 of the Ecological Impact Assessment |
Design
Construction and Operation Phase |
Design
stage consultant / Contractor / Operator |
√ |
√ |
√ |
|
Construction
Phase |
||||||||
Table
14.10 |
All
DPs and Non-DPs |
Preservation of
Existing Vegetation (CM1)
All
the existing vegetation and trees to be retained and not to be affected by
the Projects shall be carefully protected during construction by means of
fencing during construction stage to prevent damage to tree canopies and root
zones from vehicles and storage of materials.
The
tree preservation and tree treatment shall be subject to the detailed design
stage and in accordance with DEVB TC(W) No. 4/2020 - Tree Preservation and
the latest guidelines on Tree Preservation during Development issued by GLTMS
of DEVB.
A
detailed tree survey will be carried out for the Tree Preservation and
Removal proposal (TPRP) process which will be carried out at the later
detailed design stage of the Project. The detailed tree survey will propose
which trees should be retained, transplanted, or removed and will include
details of tree protection measures for those trees to be retained. |
Project
site / Construction Phase |
Contractor |
√ |
√ |
|
DEVB
TC(W) No. 4/2020 - Tree Preservation |
Table
14.10 |
All
DPs and Non-DPs |
Transplanting of
Existing Trees (CM2)
Trees
unavoidably affected by the works should be transplanted as far as possible
in accordance with DEVB TC(W) No. 4/2020- Tree preservation and the latest
Guidelines on Tree Preservation during Development issued by GLTMS of DEVB.
Sufficient
time should be reserved for the advanced tree transplanting preparation works
to enhance the survival rate of the transplanted trees. The transplanting
proposals are subject to review at the detailed design stage and to
agreement-in-principle with the relevant management and maintenance agents
and/or government departments. |
Project site / Construction Phase |
Design
stage consultant / Contractor |
|
√ |
|
DEVB
TC(W) No. 4/2020 - Tree Preservation |
Table
14.10 |
All
DPs and Non-DPs |
Reinstatement of
Temporarily Disturbed Landscape Areas (CM3) All hard and soft
landscape areas disturbed. All hard
and soft landscape areas disturbed temporarily during construction should be
reinstated on like-to-like basis, to the satisfaction of the relevant
Government Departments. |
Project site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Table
14.10 |
All
DPs and Non-DPs |
Minimise Disturbance
on Watercourses (CM4) The design shall
minimise disturbance on watercourses, particularly for natural watercourse. Good site practices as described in ETWB
TCW No. 5/2005 Protection of natural streams/rivers from adverse impacts
arising from construction works shall also be adopted to avoid any pollution
entering the watercourses nearby where applicable. Should temporarily or indirect disturbance
on watercourse is unavoidable, it shall be reinstated to the satisfaction of
relevant Government Departments. |
Project site / Construction Phase |
Contractor |
|
√ |
|
ETWB TCW No. 5/2005 |
Table
14.10 |
All
DPs and Non-DPs |
Minimise
topographical changes (CM5) The proposed site
formation works should be optimised to reduce topographical/ landform
changes, as well as reduce land take and interference with natural terrain.
Where there is a need to significantly cut
into the existing landform, retaining walls should be considered and cut
slopes should be considered to minimise landform changes and land resumption.
Earthworks
and engineered slopes should be designed to be a visually interesting
landform, compatible with the surrounding landscape and maximise greening
opportunities. |
Project site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Table
14.10 |
All
DPs and Non-DPs |
Management of
Construction Activities and Facilities (CM6) Management of
facilities on work sites which give control on the height and
disposition/arrangement of all facilities on the works site to minimise
visual impact to adjacent VSRs. |
Project site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Table
14.10 |
All
DPs and Non-DPs |
Control of
Night-time Lighting (CM7) Control of
night-time lighting glare to prevent light overspill to the nearby VSRs and
into the sky. Relevant best practices
as suggested in the "Charter on External Lighting" and Guidelines
on Industry Best Practices for External Lighting Installations promulgated
by The Environment Bureau (ENB) shall be adopted. |
Project site / Construction Phase |
Contractor |
|
√ |
|
Charter of External Lighting issued Guidelines on Industry Best
Practices for External Lighting Installations |
Table
14.10 |
All
DPs and Non-DPs |
Construction of
Decorative Hoarding around Construction Works (CM8) Erection of
decorative screen hoarding or hoarding compatible with the surrounding
setting. |
Project site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Table
14.10 |
All
DPs and Non-DPs |
Advance Planting of
Screen Planting (CM9) Advance
screen planting of fast-growing tree and shrub species to proposed
development |
Project
site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Table
14.10 |
DP
6,7 and Non-DPs |
Creating interface
between Ponds, Wetland and the proposed Project (CM10)
The
20m "landscape buffer between STEMDC and OU(I&T) and the 35m
"landscape buffer are being proposed to create buffer between the
existing and/or the development and wetland.
Native
tree species, shrub mix, and riparian vegetation should be incorporated in
the "landscape buffer.
Phasing
of pond filling works in San Tin Sam Po Shue area should be adopted. The pond filling works should be started
from urbanised area towards the wetland area (i.e. from the southeast near
STEMDC or San Tin Highway towards the northwest) and construction activities
should be minimised at any one time, so as to allow
gradual displacement of wildlife. It shall be conducted during wet season as
far as practicable. For
details of the wetland enhancement areas, please refer to Section 2 - Project
description and Section 10 -Ecological Impact Assessment |
Project
site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
14.9.4 |
All
DPs and Non-DPs |
The
following good site practice measures will also be incorporated in the
construction phase of the Project:
Topsoil,
where identified, shall be stripped, and stored for re-use in the
construction of the soft landscape works. Existing trees to be
retained on site shall be carefully protected during construction. |
Project
site / Construction Phase |
Contractor |
|
√ |
|
EIAO-TM |
Operation Phase |
||||||||
Table
14.10b |
All
DPs and Non-DPs |
Sensitive and
aesthetically pleasing Design of Aboveground structures (OM1)
Aesthetically
pleasing design as regard to the form, material and faηade finishes should be
incorporated to the proposed above ground structures for both Schedule 2 and
Schedule 3 DPs above ground structures. Implementation of lighter colour
tone, natural materials on faηade design should be implemented where
appropriate. The planning of the
Revised RODP has considered reducing potential visual impacts, enhancing
visual amenity, and keeping visual corridors. The proposed development will
ensure the building massing is compatible with its surroundings. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM DSD TC No.
2/2022-Vetting Committee on Aesthetic Design of Drainage Services Buildings APP-152: Sustainable
Building Design Guidelines |
Table
14.10b |
All
DPs and Non-DPs |
Landscape
integration of Built Development (OM2)
Buffer
tree planting and vertical greening shall also be maximised for ventilation
building, engineering structures and associated facilities as far as
appropriate to provide a source of green visual relief, minimise any
potential adverse landscape and visual impacts through greening effect (e.g.,
provision of tree / shrub / climber planting), and to blend in the structures
to the adjacent landscape and visual context. Integration of
biophilic/ resilient/sustainable landscape design, smart landscape
infrastructure and edible planting are encouraged where
practicable subject to detail design stage.
|
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.10b |
All
DPs and Non-DPs |
Provision of
roadside planting/ amenity planting/ peripheral screening or planting (OM3) Roadside soft
landscape should be incorporated to the proposed vehicular roads, station and associated engineering facilities. Ornamental and native species suited for
roadside planting should be proposed to soften the road corridors. Shade tolerant plants with tall to medium
height should be planted to under the viaduct to soften the hard edges and
provide screening. When technically
feasible, application of blue-green infrastructure and sustainable drainage
system shall be incorporated in roadside planters. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.10b |
All
DPs and Non-DPs |
Provision of new
tree planting (OM4)
Compensatory
tree planting should be provided in accordance with DEVB TC(W) 4/2020 Tree
Preservation to compensate for felled trees and maintained until end of the
establishment period. Compensatory
shrub planting should be provided to compensate for the loss of shrub
planting in amenity areas.
As
far as practicable, tree compensation within the proposed Project will be
provided at a 1:1 ratio when appropriate and applicable. Trees affected by
DPs will be compensated within their respective DP areas. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
DEVB TC(W) 4/2020 |
Table
14.10b |
All
DPs and Non-DPs |
Incorporation of
green roof (OM5) Roof Greening should
be proposed to the roof area of the proposed structures as far as practical
to enhance the landscape quality of the structures and mitigate any potential
visual impact on adjacent VSRs. Roof
greening which compliance with the site coverage of greenery requirements
shall be in accordance with DEVB TC(W) No. 3/2012 Site Coverage of Greenery
for Government Building Projects. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
DEVB TC(W) No.
3/2012 |
Table
14.10b |
All
DPs and Non-DPs |
Sensitive design of
noise barriers (OM6) The proposed noise
barriers & enclosures shall be design in an elegant manner that includes
suitable combination of transparent and sound absorbent materials,
appropriate colour selection of panels and supporting structures, or
provision of at-grade planting of trees, shrubs and/or climbers. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.10b |
All
DPs and Non-DPs |
Control of
night-time lighting glare (OM7) All
the night-time lighting shall be avoided except for safety purpose. No light glare shall illuminate directly
outside the Project. Relevant best
practices as suggested in the Guidelines on Industry Best Practices for
External Lighting Installations promulgated by ENB shall be adopted. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
Guidelines on
Industry Best Practices for External Lighting Installations |
Table
14.10b |
All
DPs and Non-DPs |
Revitalisation and naturalisation of river to create
a blue-green network (OM8)
The
major drainage channel/ man-made watercourse channels within the Project area
will be affected by the works.
It
presents an opportunity to better integrate integrated blue-green
infrastructure into the urban and landscape design. As such, forming a more
resilient blue-green feature facilitating drainage function and a more scenic
recreation destination.
Where
technically feasible, soft banks allowing reed planting, tree planting shall
be encouraged. Ponds
and water features should be incorporated where appropriate |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM DEVB
TC(W) No. 09/2020: Blue-Green Drainage Infrastructure DSD
PN No. 2/2022 - Guidelines on Application of
Floodable Area and Drainage Facility Co-Use in Drainage Management |
Table
14.10b |
All
DPs and Non-DPs |
Maximise greening on engineering structures and
surfaces (OM9)
Where
technically feasible and appropriate (i.e. where suitable depth of planting
medium, maintenance access and enough light penetration to ground level
available) climber should be proposed at vertical surfaces such as greening
facade of building blocks, viaduct piers or noise barriers to break up the
appearance of uniform engineered structures and surfaces.
Tree
planting integrate with wider streetscape elements such as hardscape paving,
outdoor furniture and lighting poles should be considered to create a
pedestrian-friendly network.
At-grade
road planting should be considered along central median planters and on the
road island with reference to DEVB TC(W) No. 2/2012, DEVB TC(W) No. 1/2018,
DEVB TC(W) No. 6/2015. For
greening of highways specifically, refer to HQ/GN/15 Guidelines for
Greening Works along Highways. The above mitigation measures would only be
implemented for public developments/projects. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
HQ/GN/15 Guidelines for Greening Works
along Highways. DEVB TC(W) No. 2/2012 DEVB TC(W) No. 1/2018 DEVB TC(W) No.
6/2015 |
Table
14.10b |
All
DPs and Non-DPs |
Landscape treatment on slope (OM10)
To
minimise adverse impacts in relation to LRs, LCAs and VSRs site formation
should be reduced as far as possible to avoid substantial slope cutting. When
condition does not allow, slope landscaping shall be explored wherever
possible.
Hydroseeding
of modified slopes should be done as soon as grading works are completed to
prevent erosion and subsequent loss of landscape resources and character. -
Tree seedlings and/ or shrubs should be planted where the slope gradient and
site conditions allow. Greening shall be planted on retaining structures
associated with modified slopes, where technically feasible.
All
slope landscaping works should comply with GEO Publication No. 1/2011-
Technical Guidelines on landscape Treatment for Slopes. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
GEO Publication No.
1/2011 - Technical Guidelines on landscape Treatment for Slopes. |
Table
14.10b |
All
DPs and Non-DPs |
Sensitive design of landscape areas / provision of
Open Space (OM11)
The
principles adopted in the RODP ensure that Urban design and Landscape
Framework are incorporated which will also improve the landscape visual
amenity.
Elegant,
sensitive design and generous planting of the associated landscape
areas.
Provision
of wetland/freshwater habitat/water pond at appropriate location for habitat
creation.
All
requirements for Open Space areas stated in the EIA Report should be adhered
to. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.10b |
All
DPs and Non-DPs |
Off-site woodland compensation (OM12)
Woodland
compensatory is proposed for woodland that are unavoidably affected. The
proposed location and detailed design is subject to
further agreement.
Woodland
compensation would be provided based on no net loss and like for like
basis or by providing a compensation area with equivalent or higher
ecological function. However, in light of a paucity
of suitable area for on-site compensation within the Project area, off-site
woodland compensation is considered instead.
Plant
species should be selected to include a mix of species with pioneering
characteristics (fast-growing/ light-tolerant/ drought-tolerant/
wind-tolerant, etc.) and native species and complementary species to the
local area. For
further detailed for the proposed location and list of recommended species,
refer to S10.13 of the EIA Report. |
Design
and Operation Phase |
AFCD |
√ |
|
√ |
EIAO-TM |
Table
14.11 |
All
DPs and Non-DPs |
Creation of
landscape buffer (OM13)
An
NBA namely landscape buffer area was proposed along the north-western
boundary of the Revised ROPD, between the proposed Project area in San Tin
and Sam Po Shue Wetland, and also at the existing
LMC BCP, between the land use OU(I&T).1.1.1 and STEMDC.
The
landscape buffer would minimise disturbance from Project Area by providing
a buffer area between the development and the adjacent wetland and by
incorporating gentle slope interface with the ponds and planting of trees and
native/ suitable vegetation. For
further details, refer to Section 10.11.12. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.11 |
All
DPs and Non-DPs |
Stepped building height profile (OM14)
The building height profile shall make reference to
the recommended Building Height Concept ( Appendix 14.2.4) down from
the south to the north to respond to the SPS WCP and the important bird
flight paths adjacent to the LMC station in order to minimise negative
impacts on the sensitive area. The pinnacles and building profiles of each
character zone shall also respect the peak and ridge line in the backdrop.
As
a broad general principle, the maximum development height permitted will be
reduced as they approach villages, low rise developments and open space.
While high-rise development shall be considered at mixed use development and
critical pedestrian and vehicular entry.
Low rise
profiles shall be adopted along ecologically sensitive areas. A stepdown
approach shall be used along important bird flight paths. For further detail, refer to S14.5.17-14.5.19 and Appendix 14.2.4 of the EIA Report. |
Design
Construction and Operation Phase |
Contractor |
√ |
√ |
√ |
HKPSG Ch11- Urban Design Guidelines. |
Table
14.11 |
All
DPs and Non-DPs |
Provision
of Breezeway/ Airpaths (OM15)
Provision
of Breezeway/ Airpaths to ensure effective air ventilation going through the
Area and to improve the micro-climate of its proposed urban environments in
accordance to the HKPSG Ch11- Urban Design
Guidelines.
Major
ones include 1) along San Tin Highway and Fanling
Highway towards Kwu Tung North New Development Area
to the east; 2) along proposed open space to the southeast of the proposed
San Tin Station, namely Town Park. 3) along the proposed major road of Road
D1 parallel to Town Park across the San Tin Town Centre (East) through the
proposed open space along STEMDC, namely Riverside Park towards the low-rise
education uses and Ki Lun Shan.
Other
breezeways are generally following the revitalised river channels STEMDC
and STWMDC, major walkways and public open space.
To
enhance visual and air permeability
For
further details, refer S14.5.23-25 of the EIA Report. |
Design
Construction and Operation Phase |
Contractor |
√ |
√ |
√ |
HKPSG Ch11- Urban Design Guidelines. |
Table
14.11 |
All
DPs and Non-DPs |
Provision of view corridor (OM16) View
Corridor are proposed to maximise and aligned principally along major
breezeways and visual connection to local landmarks and visual resources. |
Design
Construction and Operation Phase |
Contractor |
√ |
√ |
√ |
HKPSG Ch11- Urban Design Guidelines. |
Table
14.11 |
DP2,
DP3 and Non-DPs |
Sensitive
layout design of drainage related above-ground structures (OM17)
All
above-ground structures, including STLMC Effluent Polishing Plant (DP2) and
STLMC Water Reclamation Plant (DP3), etc. shall be sensitively designed in a
manner that responds to the existing and planned urban context. The height,
form and layout shall be optimised to minimise potential visual impact.
The
footprint layout and massing of development components and the works area
should also be kept to a practical minimum and the detailed design of
development components for construction phase should follow the Sustainable
Building Design Guidelines. The
form, textures, finishes and colours of the proposed development components
should aim to be compatible with the existing surroundings. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
EIAO-TM |
Table
14.11 |
DP6,
DP7, Non-DPs |
Watercourse impact
mitigation within Wetland conservation Area (OM18) For
channelised watercourses, if these are modified, the DSD PN No. 3/2021-
Guidelines on Design for Revitalisation of River Channel, should be
considered and appropriate mitigation measures included ensuring the new
watercourses match the existing as far as possible. Measures can include enhancement planting
to upgrade the channels as appropriate, including consideration of wetland
planting along embankments where appropriate; as well as consideration of the
best materials for the channel lining (e.g. gabion). All measures must also ensure any necessary
maintenance work can be carried out and that the channel meets all its
requirements for water flow. |
Design
and Operation Phase |
Contractor |
√ |
|
√ |
DSD
PN No. 3/2021- Guidelines on Design for Revitalisation of River Channel DSD
PN No. 2/2022 - Guidelines on Application of
Floodable Area and Drainage Facility Co-Use in Drainage Management |
Impacts from Electric and
Magnetic Fields |
||||||||
15.6.1.1 |
N/A |
Since electric and magnetic fields issue would not be anticipated, no mitigation measure is
considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
*Des
= Design; C = Construction; O = Operation